JPS5985028A - Steel pipe pile and laying work thereof - Google Patents
Steel pipe pile and laying work thereofInfo
- Publication number
- JPS5985028A JPS5985028A JP19342282A JP19342282A JPS5985028A JP S5985028 A JPS5985028 A JP S5985028A JP 19342282 A JP19342282 A JP 19342282A JP 19342282 A JP19342282 A JP 19342282A JP S5985028 A JPS5985028 A JP S5985028A
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- pile
- pipe pile
- ground
- spiral
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
- E02D5/44—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with enlarged footing or enlargements at the bottom of the pile
Abstract
Description
【発明の詳細な説明】
本発明は、特に軟弱地盤における基礎杭として好適注鋼
管杭及びその埋設工法に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a poured steel pipe pile suitable as a foundation pile particularly in soft ground and a method for burying the same.
一般に住宅の基礎は、独立基礎、布基礎あるいはベタ基
礎などで施工しており、良質地盤でぼ問題がないが、最
近大都市周辺の良質地盤の住宅地は、開発がしつくされ
、近時は建築をひかえていた軟弱な地盤に住宅を建築す
ることが多くなっており、前記の一般的な基礎構造では
、年月の経過とともK、地盤の不等沈下などにより、住
宅が沈下、変形し、トラブルを起す事故が頻発している
。In general, the foundations of houses are constructed using independent foundations, cloth foundations, or solid foundations, and there is no problem with good quality ground. Increasingly, houses are being built on soft ground, which has not yet been built, and with the above-mentioned general foundation structure, houses tend to sink over time due to uneven ground subsidence, etc. Accidents resulting in deformation and trouble are occurring frequently.
このような軟弱地盤の改良工法としては、サンドパイル
工法、プラスチックボードトレーン工法、プレローデイ
ング工法、セメント石灰工法などがあり、また、不等沈
下の防止や上部荷重を地盤に伝達する方法としては、摩
擦くい工法及び支持くい工法がある。Improvement methods for such soft ground include the sand pile method, plastic board train method, preloading method, and cement-lime method. , friction pile method and support pile method.
しかし、これらの工法はいずれも敷地の広い大規模な建
設工事に用いられ、さら忙、大きな荷重を支持できるよ
う設計された工法であって、上部荷重の小さい一般住宅
の基礎としては、敷地面積、施工規模、荷重条件、経済
性その他から使用は難かしい。However, all of these construction methods are used for large-scale construction works on large sites, and are designed to support large loads. , its use is difficult due to construction scale, load conditions, economic efficiency, etc.
現在とられている工法としては、木ぐい、小径コンクリ
ートくいあるいは小径鋼管を打込んで、上部荷重を支持
させているが住宅密集地での施工法としては、騒音、振
動に問題があり、また支持地盤が深い場合はくいが長く
なり 経済的でない。The current construction method is to support the upper load by driving wooden piles, small-diameter concrete piles, or small-diameter steel pipes, but this method has problems with noise and vibration when used in densely populated residential areas. If the supporting ground is deep, the piles will be long, making it uneconomical.
本発明は、前述のような住宅密集地に搬入し軟弱地盤中
に施工して地盤を改良すると共に、基礎として十分な強
度と支持力を有する鋼管杭を提供することおよびその埋
設に適した施工法を提供することKより、前記従来工法
の改善を図らんとするものである。The present invention aims to improve the ground by transporting it into a densely populated residential area and constructing it in soft ground, as well as providing a steel pipe pile that has sufficient strength and supporting capacity as a foundation, and a construction method suitable for burying the pile. Rather than providing a method, the present invention aims to improve the conventional method.
以下、本発明の鋼管杭およびその施工法について図面を
参照して説明する。Hereinafter, the steel pipe pile of the present invention and its construction method will be explained with reference to the drawings.
第1図は本発明鋼管杭の一実施例を示した側面図、第2
図は同底面図で、これらの図において1は鋼管製の杭本
体で、その下端には底板2が固設されており、底板2に
は下方に向けて掘削刃4,4が突設されている。また、
杭本体1の下端部にはその外周面に沿って螺旋翼5が突
設されている。この螺旋翼5は実施例においては連続し
て−巻き強にわたり形成されているが、その巻き数は適
宜増減することができ、また、螺旋翼5は不連続状態に
分断し、全体として螺旋状に形成したものであってもよ
い。Figure 1 is a side view showing one embodiment of the steel pipe pile of the present invention, Figure 2
The figures are bottom views of the same, and in these figures, 1 is the main body of the pile made of steel pipe, and a bottom plate 2 is fixed to the lower end of the pile body. ing. Also,
A spiral wing 5 is provided protruding from the lower end of the pile body 1 along its outer peripheral surface. In the embodiment, the spiral blade 5 is formed with a continuous number of turns, but the number of turns can be increased or decreased as appropriate, and the spiral blade 5 can be divided into discontinuous sections to form a spiral shape as a whole. It may be formed as follows.
第3図は本発明鋼管杭の他の実施例を示したもので、前
実施例と異る点は、底板2にグラウト噴出孔3,3を設
けたことにある。FIG. 3 shows another embodiment of the steel pipe pile of the present invention, which differs from the previous embodiment in that grout injection holes 3, 3 are provided in the bottom plate 2.
本発明の鋼管杭は前述のように構成されており、施工に
あたっては杭本体1の上端部に図示を省略した回動押込
み駆動装置を取付け、その駆動によって杭本体1を回動
しながら押込んで地中に埋設するのである。また、第3
図のような鋼管杭の場合は、必要に応じて杭本体1中に
セメントミルクを入れることにより、グラウト噴出孔3
,3からセメントミルクマ・掘削孔内に注入することが
できる。The steel pipe pile of the present invention is constructed as described above, and during construction, a rotary pushing drive device (not shown) is attached to the upper end of the pile body 1, and the pile body 1 is pushed in while being driven by the drive device. It is buried underground. Also, the third
In the case of steel pipe piles as shown in the figure, by pouring cement milk into the pile body 1 as necessary, the grouting hole 3 can be
, 3, the cement milk can be injected into the borehole.
次に1本発明の第3図に示した鋼管杭による最も効果的
な埋設工法について説明すると、地盤上に鋼管杭を立設
し、駆動装置によって鋼管杭を回動させながら地中に押
圧すれば、下端の掘削刃により掘削が進行して、鋼管杭
は地盤中に貫入して行くことになる。鋼管杭の貫入につ
れ、地盤中には螺旋翼5による回転軌跡6が形成される
ことになるが、掘削、貫入にあたってグラウト噴出孔3
からセメントミルクを掘削孔7内圧注入してやることに
より、第3図のように杭本体1の周辺および回転軌跡に
は、セメントミルクが掘削土と混合されて充填し、螺旋
状の周辺支持層8が形成される。そして、所定の深さま
で貫入させてから、鋼管杭を回動させながら上下動を繰
返し行なう。それによって、鋼管杭の螺旋翼5を含む下
端部には、セメントミルクの注入による根固め団塊9が
形成されることKなり、本発明の施工が完了する。その
結果、地盤中には、下端部に螺旋翼5のある鋼管杭と、
これに根固め団塊9および螺旋状の周辺支持層8とが一
体的に結合された状態となって基礎杭としての働きをす
ることになるのである。なお、セメントミルクの注入は
、杭本体1中にセメントミルクを入れてやり噴出孔3か
らの自然噴出にまかせればよいが、必要に応じては噴出
孔、3に注入パイプ等を連結して強制的に噴出させるよ
うにしてもよい。また、貫入後の鋼管杭の管中ば空洞の
ままにしておいても、或はコンクリート等を充填しても
よい。Next, to explain the most effective method of burying steel pipe piles as shown in Fig. 3 of the present invention, the steel pipe piles are erected on the ground and pushed into the ground while being rotated by a drive device. For example, the excavation progresses with the digging blade at the lower end, and the steel pipe pile penetrates into the ground. As the steel pipe pile penetrates, a rotation locus 6 due to the spiral blades 5 will be formed in the ground.
By injecting cement milk into the excavated hole 7 under pressure, the cement milk mixes with the excavated soil and fills the area around the pile body 1 and the rotation locus as shown in FIG. 3, creating a spiral peripheral support layer 8. It is formed. After penetrating to a predetermined depth, the steel pipe pile is repeatedly moved up and down while being rotated. As a result, a hardening block 9 is formed at the lower end of the steel pipe pile including the spiral wings 5 by pouring the cement milk, and the construction of the present invention is completed. As a result, in the ground there is a steel pipe pile with spiral wings 5 at the lower end,
The foot protection nodules 9 and the spiral peripheral support layer 8 are integrally connected to this, and function as a foundation pile. In addition, the injection of cement milk can be done by putting the cement milk into the pile body 1 and letting it flow naturally from the spout hole 3, but if necessary, connect an injection pipe etc. to the spout hole 3. It may be forcibly ejected. Further, the inside of the steel pipe pile after penetration may be left hollow, or it may be filled with concrete or the like.
以上説明したよ5K、本発明は、鋼管製杭本体の下端に
底板を固設し、これに掘削刃或はこれに加えてグラウト
噴出孔を設けると共に、杭本体の下端部外周面に螺旋翼
を突設して鋼管杭を構成したので、杭埋設のための特別
な装置を要することなく、杭自体を回転圧入するだけで
埋設施工が行なえると共に構造が簡単で安価に製作する
ことができ、支持力が大で特に軟弱地盤における住宅等
の基礎杭として好適であり、また、この鋼管杭はこれを
回転、圧入すると共に、グラウト噴出孔よりセメントミ
ルクを注入しながら埋設するようにしたので、鋼管杭の
下端部には螺旋翼と一体結合された大径の根固め団塊が
形成されると共に、鋼管杭の周辺にも螺旋翼の回転軌跡
に溢う周辺支持層が鋼管杭と一体化して形成され、埋設
した鋼管杭の支持力を著しく増大させることができ、し
たがって、小径、短尺な鋼管杭を用いしかもその使用本
数も少なくてすみ、施工の手間および経費が大巾に軽減
され、特に軟弱地盤上に建設する一般住宅用の基礎とし
て優れた効果を発揮するものである。As explained above, the present invention fixes a bottom plate to the lower end of a steel pipe pile body, provides a digging blade or a grout spout hole in addition to this, and has a spiral blade on the outer peripheral surface of the lower end of the pile body. Since the steel pipe pile is constructed by protruding from the pile, there is no need for any special equipment for burying the pile, and the burying can be done by simply rotating and press-fitting the pile itself, and the structure is simple and can be manufactured at low cost. It has a large bearing capacity and is suitable as a foundation pile for houses, etc., especially on soft ground.In addition, this steel pipe pile is rotated and press-fitted, and is buried while pouring cement milk through the grout spout hole. At the lower end of the steel pipe pile, a large-diameter foot-reinforcing mass is formed that is integrally connected with the spiral blade, and around the steel pipe pile, the surrounding support layer overflowing with the rotation trajectory of the spiral blade is integrated with the steel pipe pile. It is possible to significantly increase the bearing capacity of buried steel pipe piles. Therefore, it is possible to use small diameter and short steel pipe piles, and also to reduce the number of them, which greatly reduces the labor and cost of construction. It is particularly effective as a foundation for general housing built on soft ground.
第1図は本発明鋼管杭の一実施例を示す側面図、第2図
は同底面図、第3図は本発明鋼管杭の他の実施例を示す
側面図、第4図は本発明鋼管杭の施工の状態を示す側断
面図である。
1・・・杭本体 2・・・底板
3・・・グラウト噴出孔 4・・・掘削刃5・・・螺旋
翼 6・・・螺旋翼の回転軌跡7・・・掘削孔
8・・・周辺支持層9・・・根固め団塊
特許出願人 吉 1) 耕 之Fig. 1 is a side view showing one embodiment of the steel pipe pile of the present invention, Fig. 2 is a bottom view of the same, Fig. 3 is a side view showing another embodiment of the steel pipe pile of the invention, and Fig. 4 is a steel pipe of the invention. It is a side sectional view showing the state of construction of a pile. 1... Pile body 2... Bottom plate 3... Grout injection hole 4... Drilling blade 5... Spiral blade 6... Rotation locus of spiral blade 7... Drilling hole
8... Peripheral support layer 9... Patent applicant for root solidifying baby boomers Yoshi 1) Koyoshi
Claims (3)
掘削刃を設けると共に、杭本体の下端部外周面に螺旋翼
を突設したことを特徴とする、鋼管杭。(1) A steel pipe pile, characterized in that a bottom plate is fixed to the lower end of a steel pipe pile body, a digging blade is provided on the bottom plate, and spiral wings are protruded from the outer peripheral surface of the lower end of the pile body.
特許請求の範囲第1項記載の鋼管杭。(2) The steel pipe pile according to claim 1, characterized in that the bottom plate is provided with grout injection holes.
設けた底板を固設すると共K、下端部に螺旋翼を突設し
た鋼管杭を地盤中に回転、田入させながらグラウト噴出
孔よりセメントミルクを注入して、鋼管杭の周辺に螺旋
状の周辺支持層を形成し、鋼管杭の所定深さへの貫入後
は、鋼管杭を回動させながら上下動を行ない、鋼管杭の
下端部に根固め団塊を形成させることを特徴とする、鋼
管杭の埋設工法。(3) The lower end of the pile body K, the grouting hole, and the bottom plate with the excavation blade are fixed, and the steel pipe pile with spiral blades protruding from the lower end is rotated and inserted into the ground while grouting the hole. More cement milk is injected to form a spiral peripheral support layer around the steel pipe pile, and after the steel pipe pile has penetrated to a predetermined depth, the steel pipe pile is moved up and down while rotating. A method for burying steel pipe piles, which is characterized by forming a foot protection nodule at the bottom end.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP19342282A JPS5985028A (en) | 1982-11-05 | 1982-11-05 | Steel pipe pile and laying work thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP19342282A JPS5985028A (en) | 1982-11-05 | 1982-11-05 | Steel pipe pile and laying work thereof |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP30104386A Division JPS6347416A (en) | 1986-12-17 | 1986-12-17 | Steel tubular pile and its embedding work |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS5985028A true JPS5985028A (en) | 1984-05-16 |
JPH0262648B2 JPH0262648B2 (en) | 1990-12-26 |
Family
ID=16307700
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP19342282A Granted JPS5985028A (en) | 1982-11-05 | 1982-11-05 | Steel pipe pile and laying work thereof |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5985028A (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6198818A (en) * | 1984-10-19 | 1986-05-17 | Shiraishi:Kk | Rotary pressing-in type steel pipe pile |
JPS6225612A (en) * | 1985-07-26 | 1987-02-03 | Eijiro Kurahashi | Pile |
JPS62228518A (en) * | 1986-03-28 | 1987-10-07 | Eijiro Kurahashi | Steel tubular pile |
JPH02115409A (en) * | 1988-10-25 | 1990-04-27 | Fukuei Juki:Kk | Spiral pile and method of embedding thereof |
JPH05311649A (en) * | 1992-07-27 | 1993-11-22 | Yoshida Yasuyuki | Conical multi-blade steel tube friction pile and its burying method |
JPH08199959A (en) * | 1995-01-21 | 1996-08-06 | Kumho Construction Engineering Co Ltd | Spiral grooving auger drill,executing method of spiral groove to peripheral wall of underground hole by said auger drill and underground pit,in which bearing force is reinforced by spiral groove |
US5575593A (en) * | 1994-07-11 | 1996-11-19 | Atlas Systems, Inc. | Method and apparatus for installing a helical pier with pressurized grouting |
JP2002097886A (en) * | 2000-09-26 | 2002-04-05 | Daido Concrete Co Ltd | Method and device for disposing discharged earth |
JP2007113270A (en) * | 2005-10-20 | 2007-05-10 | Nippon Steel Corp | Foundation structure and construction method of the foundation structure |
JP2014152576A (en) * | 2013-02-13 | 2014-08-25 | Chiyoda Geotech Co Ltd | Foundation pile and foot protection method of foundation pile |
CN105970921A (en) * | 2016-07-08 | 2016-09-28 | 上海长凯岩土工程有限公司 | Integrated construction method for oblique steel pipe and cemented soil stress body |
CN106917404A (en) * | 2017-04-26 | 2017-07-04 | 王景军 | A kind of prefabricated screw stake |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4645091B2 (en) * | 2004-07-27 | 2011-03-09 | Jfeスチール株式会社 | Expanded pile and construction method of the expanded pile |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5194615A (en) * | 1975-02-17 | 1976-08-19 |
-
1982
- 1982-11-05 JP JP19342282A patent/JPS5985028A/en active Granted
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5194615A (en) * | 1975-02-17 | 1976-08-19 |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6198818A (en) * | 1984-10-19 | 1986-05-17 | Shiraishi:Kk | Rotary pressing-in type steel pipe pile |
JPS6225612A (en) * | 1985-07-26 | 1987-02-03 | Eijiro Kurahashi | Pile |
JPH0542524B2 (en) * | 1985-07-26 | 1993-06-28 | Eijiro Kurahashi | |
JPS62228518A (en) * | 1986-03-28 | 1987-10-07 | Eijiro Kurahashi | Steel tubular pile |
JPH02115409A (en) * | 1988-10-25 | 1990-04-27 | Fukuei Juki:Kk | Spiral pile and method of embedding thereof |
JPH05311649A (en) * | 1992-07-27 | 1993-11-22 | Yoshida Yasuyuki | Conical multi-blade steel tube friction pile and its burying method |
US5575593A (en) * | 1994-07-11 | 1996-11-19 | Atlas Systems, Inc. | Method and apparatus for installing a helical pier with pressurized grouting |
JP2709382B2 (en) * | 1995-01-21 | 1998-02-04 | 株式會社錦湖建設 | An auger drill for drilling a spiral groove and a method of constructing a spiral groove on the peripheral wall of an underground hole with this auger drill. |
JPH08199959A (en) * | 1995-01-21 | 1996-08-06 | Kumho Construction Engineering Co Ltd | Spiral grooving auger drill,executing method of spiral groove to peripheral wall of underground hole by said auger drill and underground pit,in which bearing force is reinforced by spiral groove |
JP2002097886A (en) * | 2000-09-26 | 2002-04-05 | Daido Concrete Co Ltd | Method and device for disposing discharged earth |
JP2007113270A (en) * | 2005-10-20 | 2007-05-10 | Nippon Steel Corp | Foundation structure and construction method of the foundation structure |
JP4713297B2 (en) * | 2005-10-20 | 2011-06-29 | 新日本製鐵株式会社 | Foundation structure and construction method of foundation structure |
JP2014152576A (en) * | 2013-02-13 | 2014-08-25 | Chiyoda Geotech Co Ltd | Foundation pile and foot protection method of foundation pile |
CN105970921A (en) * | 2016-07-08 | 2016-09-28 | 上海长凯岩土工程有限公司 | Integrated construction method for oblique steel pipe and cemented soil stress body |
CN105970921B (en) * | 2016-07-08 | 2018-05-11 | 上海长凯岩土工程有限公司 | A kind of integral construction method of oblique steel pipe soil cement beaer |
CN106917404A (en) * | 2017-04-26 | 2017-07-04 | 王景军 | A kind of prefabricated screw stake |
Also Published As
Publication number | Publication date |
---|---|
JPH0262648B2 (en) | 1990-12-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS5985028A (en) | Steel pipe pile and laying work thereof | |
JP2002155530A (en) | Embedding method and tip metal fitting of existing pile | |
JP3752560B2 (en) | Basic structure for constructing a new building in an existing basement and its construction method | |
JPS6347416A (en) | Steel tubular pile and its embedding work | |
CN107288147A (en) | Rock foundation pole and tower foundation construction method | |
JPH0536565B2 (en) | ||
JPS6342046B2 (en) | ||
JPS5827366B2 (en) | Head reinforcement pile construction equipment | |
JP2690361B2 (en) | Pile construction method | |
JPS6013118A (en) | Pile erection work and excavation head for forming consolidated perforated wall therefor | |
JPH0464618A (en) | Pit excavation work method | |
JP2004027610A (en) | Burying method for prefabricated pile | |
KR900005913B1 (en) | Base stake inflated in bump state at lower end there of and its construction | |
JP2732138B2 (en) | Piling method | |
JPH0627405B2 (en) | Ready-made pile burying method | |
JPS6124491B2 (en) | ||
JPH025845B2 (en) | ||
JP4481662B2 (en) | Pile setting method and blade plate | |
JPH11158871A (en) | Method for embedding hollow existing pile | |
JPS6350484B2 (en) | ||
JPH0559726A (en) | Method of driving precast pile into ground | |
JP2003096771A (en) | Precast soil-cement pile having composite blades | |
JPS6140817B2 (en) | ||
JPS62202118A (en) | Burying work of pile | |
JPS62170614A (en) | Construction work of steel pipe pile |