JPS601451B2 - Water stop mountain stop wall construction method using Benoto pile excavator - Google Patents

Water stop mountain stop wall construction method using Benoto pile excavator

Info

Publication number
JPS601451B2
JPS601451B2 JP6960479A JP6960479A JPS601451B2 JP S601451 B2 JPS601451 B2 JP S601451B2 JP 6960479 A JP6960479 A JP 6960479A JP 6960479 A JP6960479 A JP 6960479A JP S601451 B2 JPS601451 B2 JP S601451B2
Authority
JP
Japan
Prior art keywords
benoto
construction method
wall construction
stop
mountain
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP6960479A
Other languages
Japanese (ja)
Other versions
JPS55161116A (en
Inventor
正光 菊池
光寿 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP6960479A priority Critical patent/JPS601451B2/en
Publication of JPS55161116A publication Critical patent/JPS55161116A/en
Publication of JPS601451B2 publication Critical patent/JPS601451B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 この発明は新規なべノト杭掘削機による止水山止壁工法
、いわゆるシーカント・パイル工法の提供に係わる。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to the provision of a water stop pile construction method, a so-called sea cant pile construction method, using a novel pot pile excavator.

シーカントは、割線または切断の意味で、シーカント・
パイル工法とは、ベノト式ピャを連続して築造し、場所
打鉄筋コンクリート土留め壁を構造する方法である。
Seacant means secant or cut.
The pile construction method is a method of constructing cast-in-place reinforced concrete earth retaining walls by constructing Benoto-style piles in succession.

この土留め壁は、隣接構造物に対する影響がなく、しか
も所要強度も自由に設定でき、信頼性が非常に高いとい
え、また、他の土留め壁工法に比べて、深R(最大30
肌位)のものや、一部または全部のピャを支持層に定着
させて、支持ぐし、を兼ねさすことも容易であるという
長所を有しているので止水山止壁工法に採用されている
This earth retaining wall has no effect on adjacent structures, and the required strength can be freely set, making it extremely reliable.
It has the advantage that it is easy to fix some or all of the pyas on the support layer and also serve as a support pile, so it has been adopted in the water-stopping mountain wall construction method. There is.

このピャの施工要領は (1)〔柾列並び〕を絶えずチェックできる基点を設け
る。
The construction procedure for this pia is (1) Provide a base point that can constantly check [square row arrangement].

(0)べノト機の揺動ペットにスライド式チュ−ブ・ガ
イドを装備する。
(0) Equip the swinging pet of the Benoto machine with a sliding tube guide.

このチューブ・ガイドはケーシング・チューブの末端付
近を支えることができて、鉛直度を確保しながら圧入で
きる構造になっている。(m)べノト機を所定位置に水
平に据え、ケーシング・チューブを〔柱列並びに〕正確
にそわせて建て込む。
This tube guide is capable of supporting the vicinity of the end of the casing tube, and has a structure that allows it to be press-fitted while ensuring verticality. (m) Place the Benoto machine horizontally in the specified position and erect the casing tube, aligning it accurately [with the columns].

(W)ケーシング・チューブの鉛直度の矯正は、それを
2〜3仇圧入するまでに慎重にチェックして行なう。
(W) Correct the verticality of the casing tube by carefully checking it 2 to 3 times before press-fitting it.

それ以上圧入してからは、修正が困難となる。(V)そ
れ以降の施工要領は、ベノト工法に準じ、ケーシング・
チューブの揺動、氏入とハンマー・グラブによる掘進を
繰り返し所定深さまで堀さくする。
If it is pressed in any further, it will be difficult to correct it. (V) Subsequent construction procedures will be based on the Benoto method, including casing and
Repeat the rocking of the tube, insertion, and digging with a hammer/grab to excavate to a specified depth.

鉄筋かごを建て込み、トレミー工法によって速やかに、
コンクリートを打設してピャの築造を終る。以上の工程
よりなり、ピャの並べ方は第1図A、B、C図に示され
る如く、千鳥型、直線オーバー・ラップ型、接線型等の
種類があるが、いずれも施工順序は、図に番号で示すと
おり教本で構成される1ブロックを、連続して継ぎ合わ
せて築造してから、つぎのブロツ外こ移る。
A reinforcing cage was erected and the construction was quickly carried out using the tremie method.
Concrete was poured and the construction of Pya was completed. As shown in Figure 1 A, B, and C, there are various ways to arrange the piers, including staggered, linear overlap, and tangential types. Build one block consisting of textbooks as indicated by the numbers, connecting them in succession, and then move on to the next block.

このうち、とくに、直線オーバー・ラップ型にあっては
、■,■などの中間ピャを掘さくするときに、既設の隣
接ピャをけずることになるので、■,■,■などのピャ
の材令が若いうちに施工しないと、堀さくが困難となる
という難点があるも、ラップしているので、この方法は
完全な止水壁が期待できる点で最もすぐれる。総じて、
ピャ柱列の施工要領については、シーカント・パイル工
法の種類形成のところで述べたとおり、■,■,■など
のピャ築造後に、速やかに■,■などの中間ピャを築造
し1ブロックを終るものであるので、この場合■,■な
どの中間堀さくの際、隣接する既設の■,■,■などの
ピャを切りけずることがあるので、それらのコンクリー
トが、完全に硬化しないうちに施工しなければならない
Among these, especially for the straight-line overlap type, when excavating the intermediate pits such as ■, ■, the existing adjacent piers must be scraped, so Although there is the disadvantage that it will be difficult to dig the trench if it is not done while the water is still young, since it is wrapped, this method is the best in that it can be expected to create a completely watertight wall. Overall,
Regarding the construction procedure for the row of pya columns, as mentioned in the section on the formation of the types of secant pile construction methods, after the construction of pyas such as ■, ■, ■, intermediate pyas such as ■, ■ are immediately constructed to complete one block. Therefore, in this case, when excavating intermediate trenches such as ■ and ■, the adjacent existing pits such as ■, ■, and ■ may be cut, so construction should be done before the concrete has completely hardened. There must be.

したがって、コンクリートには硬化遅延剤を添加し、硬
化時間を調整する必要があると同時に、できる限り短時
間のうちに連続施工をするよう、とくに留意せね‘まな
らないので、この点が難点である。
Therefore, it is necessary to add a curing retarder to the concrete and adjust the curing time, and at the same time, special attention must be paid to continuous construction in the shortest possible time, which is a difficult point. be.

この工法は、地中深くに松杭等の地中障害の大量にある
場合、特に好適である。
This construction method is particularly suitable when there are a large number of underground obstructions such as pine piles deep underground.

すなわち、比較的浅い部分なある障害は、仮山止を施し
ておいて、地中障害の露呈した頭部を把持して引き抜く
ことにより、比較的簡単に除去でき、どの様な工法によ
ってでき山止壁の施工は可能であるが、地中深く(GL
−low程度)にある障害に対しては、上記の如き施工
で処理することは現実的には不可能である。
In other words, some obstacles in relatively shallow areas can be relatively easily removed by temporarily installing a mountain stop, grasping the exposed head of the underground obstacle, and pulling it out. Although it is possible to construct a retaining wall, it is necessary to construct it deep underground (GL
-low degree), it is practically impossible to treat them with the construction described above.

それは、地中障害を把持する作業を行うために作業員が
、掘さく孔底に降りていくためには、堀さく孔壁崩壊を
無くす処理をしておかねばならず、そのためには掘さく
作業がどうしても大袈裟となって地層を乱すこととなる
のに対し、シーカント・パイル工法にあっては、ケーシ
ング・チューブが燭さく孔壁の崩壊を皆無としているの
で、何の付加処理を必要とすることなく作業員はケーシ
ング・チューブ内を降りて把持作業をとり行うことがで
きるという事情による。
In order for workers to descend to the bottom of the borehole to grasp underground obstacles, treatment must be taken to prevent the walls of the borehole from collapsing. Whereas the work is necessarily exaggerated and disturbs the strata, in the seacant pile method, the casing tube prevents the wall of the candle hole from collapsing, so no additional treatment is required. This is due to the fact that the operator can descend into the casing tube and carry out the gripping operation without any trouble.

しかし、地中障害を除去した後に問題が発生する。However, problems arise after removing the underground obstruction.

すなわち、地中障害を除去した跡の空隙部にもコンクリ
ート打設が行われると、それよって形成されるピャは予
定した直耳同のものではなくして、怪外にはみ出し突起
を有する異形ピヤとなり、この突起部が、後の隣接ピャ
築造に際して堀さく障害となることである。本発明は叙
上の点に鑑みなされたもので、その要旨とするところは
べノト機で凝さくした孔のケ−シング・チューブの中に
内ケ−シングを挿入するものとし、その中にはコンクリ
ートを打設し、他方、外周部は止水性のある軟性硬化材
(K・ソィル、ソィルコンクリート等)を埋戻しして、
ピャを外周を軟性材で包んだ2重層に構成し、この外層
部分を、オーバー・ラップして隣接ピャ築造のべノト機
が削孔するとしたところにある。
In other words, if concrete is placed in the void left by removing underground obstructions, the resulting piers will not be the same as planned, but instead will be irregularly shaped piers with protrusions protruding beyond the surface. However, this protrusion becomes an obstacle to excavation when constructing an adjacent pit later. The present invention has been made in view of the above points, and its gist is that an inner casing is inserted into a casing tube with a hole made by a Benoto machine, and the inner casing is inserted into the casing tube. concrete is poured, and the outer periphery is backfilled with waterproof soft hardening material (K-soil, soil concrete, etc.).
The pit is constructed of a double layer with the outer periphery wrapped in a soft material, and this outer layer is overlapped so that the hole is drilled by a Benoto machine for constructing the adjacent pit.

以下、本発明の詳細を図にもとづいて説明する。本発明
工法の施工手順は第2図の平面、縦断正面図に示されて
あり、図において工程(1)はべノト機による堀さくが
完了した態様で、図中1はケーシング・チューブである
。工程(ロ)は該ケーシング・チューブーの中に内ケー
シング2を挿入した態様で、図中3は内ケーシング2下
端開ロに装着するを良しとするコンクリート漏出防止用
袋である。
Hereinafter, details of the present invention will be explained based on the drawings. The construction procedure of the construction method of the present invention is shown in the plan and longitudinal front views of Figure 2, in which step (1) is the state in which the digging by the Benoto machine has been completed, and 1 in the figure is the casing tube. . In step (B), the inner casing 2 is inserted into the casing tube, and 3 in the figure is a bag for preventing concrete leakage that is preferably attached to the lower end of the inner casing 2.

工程(m)は内ケーシング2外周部に安定液+水ガラス
若しくはソィルコンクリート等の止水性で、かつ、べ/
ト村で切削可能な強度の軟性の硬化材料4を埋戻しし、
ケーシング・チューブ1を引き抜いている態様である。
In step (m), the outer periphery of the inner casing 2 is coated with a water-stopping material such as stabilizing liquid + water glass or soil concrete, and base/
backfilling with a soft hardened material 4 strong enough to be cut in a machine;
This is a mode in which the casing tube 1 is being pulled out.

工程(N)は内ケーシング2の中にトレミ−工程でコン
クリート5打設を行ない、内ケーシング2を引き抜いて
いる態様で、図中6はトレミー管である。尚、内ケーシ
ング2は引き抜くことなく埋設しして残してもよい。工
程(V)は以上に述べたピャ築造工程を外層部でラップ
なせながら繰返し施行していきピャを連続させた態様を
示す。
Step (N) is a mode in which concrete 5 is poured into the inner casing 2 in a tremie step and the inner casing 2 is pulled out, and 6 in the figure is a tremie pipe. Note that the inner casing 2 may be buried and left without being pulled out. Step (V) shows a mode in which the above-mentioned pia construction process is repeatedly carried out while wrapping the outer layer part, and the pia is made continuous.

本発明工法は叙上の如き構成よりなるから、従来法にお
けるが如く既設ピャとのラプの際の未硬化中の迅速連続
施工や硬化遅延剤の配慮は一切不要となし得るのみでは
なく、地中障害の場合にあっては、隣接ピャ築造に際し
て切りけずられるのは軟質の外層部分のみで、芯部のコ
ンクIJート部分は内ケーシング2で定形に成形されて
突起することは絶対になく堀さく障害は全く無い。
Since the construction method of the present invention has the above-mentioned configuration, it not only eliminates the need for rapid continuous construction during uncured work and consideration of curing retarders when rapping with existing piers, as in the conventional method, but also eliminates the need for consideration of curing retarders. In the case of moderate failure, only the soft outer layer is cut away when constructing the adjacent piers, and the concrete IJ core part is molded into a regular shape by the inner casing 2 and will never protrude. There are no problems with drilling.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はシーカント・パイル工法に於ける各種形成のピ
ヤ柱列を示し、第2図は本発明工法の施工手順図である
。 符号の簡単な説明、1・・・ケーシング・チューブ、2
・・・内ケーシング、3・・・コンクリート漏出防止用
袋、4・・・軟性の硬化材料、5・・・コンクリ−ト、
6・・・トレミー管。 プタ/鰯 がZ鰯
Fig. 1 shows rows of pillar columns of various formations in the sea cant pile construction method, and Fig. 2 is a construction procedure diagram of the construction method of the present invention. Brief explanation of symbols, 1...Casing tube, 2
... Inner casing, 3... Concrete leakage prevention bag, 4... Soft hardening material, 5... Concrete,
6...tremie tube. Puta/Sardine is Z Sardine

Claims (1)

【特許請求の範囲】[Claims] 1 ベノト機で掘さくした孔のケーシング・チユーブの
中に内ケーシングを挿入するものとし、その中にはコン
クリートを打設し、他方、その外周部には止水性のある
軟性硬化材を埋戻しして、ピヤを外周を軟性材で包んだ
2重層に構成し、この外層部分でオーバー・ラツプして
隣接ピヤを築造するとしたことを特徴とするベノト杭掘
削機による止水山止壁工法。
1. The inner casing shall be inserted into the casing tube of the hole drilled with a Benoto machine, and concrete will be placed inside it, while the outer periphery will be backfilled with water-stopping soft hardened material. A water stop mountain stop wall construction method using a Benoto pile excavator, characterized in that the pier is constructed in a double layer with the outer periphery wrapped in a soft material, and the adjacent pier is constructed by overlapping with this outer layer part.
JP6960479A 1979-06-04 1979-06-04 Water stop mountain stop wall construction method using Benoto pile excavator Expired JPS601451B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6960479A JPS601451B2 (en) 1979-06-04 1979-06-04 Water stop mountain stop wall construction method using Benoto pile excavator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6960479A JPS601451B2 (en) 1979-06-04 1979-06-04 Water stop mountain stop wall construction method using Benoto pile excavator

Publications (2)

Publication Number Publication Date
JPS55161116A JPS55161116A (en) 1980-12-15
JPS601451B2 true JPS601451B2 (en) 1985-01-14

Family

ID=13407601

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6960479A Expired JPS601451B2 (en) 1979-06-04 1979-06-04 Water stop mountain stop wall construction method using Benoto pile excavator

Country Status (1)

Country Link
JP (1) JPS601451B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2019019633A (en) * 2017-07-20 2019-02-07 株式会社技研製作所 Construction method of continuous underground wall and steel pipe pile

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5252157A (en) * 1989-05-01 1993-10-12 Central Plastics Company Electrothermal fusion of large diameter pipes by electric heating wire wrapping and sleeve connector
JP2013127189A (en) * 2011-12-19 2013-06-27 Takenaka Komuten Co Ltd Lattice ground improvement body, impervious wall, and construction method for the same
CN105970972A (en) * 2016-06-21 2016-09-28 中铁第四勘察设计院集团有限公司 Novel secant pile supporting structure and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2019019633A (en) * 2017-07-20 2019-02-07 株式会社技研製作所 Construction method of continuous underground wall and steel pipe pile

Also Published As

Publication number Publication date
JPS55161116A (en) 1980-12-15

Similar Documents

Publication Publication Date Title
JP5282541B2 (en) How to prevent lifting of the lining body
US4496268A (en) Method and apparatus for constructing reinforced concrete walls in the earth
KR100618597B1 (en) Cast in place concrete pile using vibro magnetic shovel hammer, and the construction method of this
KR20100035349A (en) Construction method of retaining wall using cast-in-place pile
KR20070111440A (en) Pit working method forr undergrund floor railroad operation of elevator
US4367057A (en) Method of forming a foundation with liquid tight joints
JPS601451B2 (en) Water stop mountain stop wall construction method using Benoto pile excavator
JPS59126821A (en) Erection work of foundation pile
JPS6158640B2 (en)
JPS5847823A (en) Construction of in-place concrete pile
US4430027A (en) Method of forming a foundation with liquid tight joints
RU2209268C1 (en) Process of development of foundation pit
JP5282542B2 (en) Ground deformation prevention method and ground deformation prevention structure
JPS5936058B2 (en) How to construct a structure using underground continuous walls
JP2874906B2 (en) Shaft construction method
JPH10219680A (en) Work execution method of cast-in-place concrete pile
JPH02266015A (en) Constructing underground continuous wall
JPS5869924A (en) Construction of sheathing wall having upper part consisting of underground continuous wall and lower part of pillar-row pile
KR200375610Y1 (en) Cast in place concrete pile using vibro magnetic shovel hammer
JP2004238981A (en) Method for constructing tunnel
JPH11172708A (en) Method for forming pile penetrating existing underground structure
JPH0366452B2 (en)
JPS6128774B2 (en)
JPS6192235A (en) Fixing of embedded pipe
JPH0510084A (en) Execution method of deeper depth man hole