JPS5847823A - Construction of in-place concrete pile - Google Patents

Construction of in-place concrete pile

Info

Publication number
JPS5847823A
JPS5847823A JP14801181A JP14801181A JPS5847823A JP S5847823 A JPS5847823 A JP S5847823A JP 14801181 A JP14801181 A JP 14801181A JP 14801181 A JP14801181 A JP 14801181A JP S5847823 A JPS5847823 A JP S5847823A
Authority
JP
Japan
Prior art keywords
piles
soil
excavated
retaining wall
pillar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP14801181A
Other languages
Japanese (ja)
Other versions
JPS6119771B2 (en
Inventor
Toshio Enoki
榎 敏男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP14801181A priority Critical patent/JPS5847823A/en
Publication of JPS5847823A publication Critical patent/JPS5847823A/en
Publication of JPS6119771B2 publication Critical patent/JPS6119771B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/36Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

PURPOSE:To prevent the lowering of the bonding strength of reinforcing bars caused by mud water films by a method in which soil-cement piles are driven along the periphery side of a pile to be constructed to form a pillar-row sheathing wall, the inside area is excavated, and then fresh water is filled therein. CONSTITUTION:Excavation is made to a given depth while injecting a cement milk mixed with bentonite, etc., from the tip of an earth auger, and then soil- cement piles B are placed orderly in such a way as to overlap them on the periphery of the soil-cement piles B already placed, whereby forming a pillar-row sheathing wall B'. The inside area of the wall B' is excavated by the bucket of an excavator and fresh water D is filled up in the excavated pit C to balance it with earth pressure. Then, an iron bar cage E is inserted, and fresh concrete is gradually poured through a tremie tube F to the bottom of the pit to construct in-place concrete piles.

Description

【発明の詳細な説明】 この発明は、場所打コンクリート杭の築造方法に関する
ものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for constructing cast-in-place concrete piles.

最近建築物の高層化にともない、その基礎杭の支持力も
極めて大きいものが要求されるので、一般には場所打コ
ンクリート杭方式が多く採用されている。
Recently, as buildings become taller, foundation piles are required to have an extremely large bearing capacity, so cast-in-place concrete piles are generally used.

この方式のパケットアース工法或はリパースサーキュレ
ーション工法には、泥水安定液(ヘントナイト溶液や0
.M、Oを使用する)を使用しているので、上記泥水安
定液の配合、混線の管理が困難になると共に、溢れ出る
泥水により各種公害問題が発生する欠点があった。
This type of packet earth construction method or reparse circulation construction method uses a muddy water stabilizing solution (hentonite solution or zero
.. M, O) is used, which makes it difficult to mix the muddy water stabilizer and control crosstalk, and the overflowing muddy water causes various pollution problems.

また、大なり、小なり孔壁が崩壊し、かつ、鉄筋能の挿
入時にも孔壁が崩壊して生コンクリートに崩壊上が混入
するので、出来上った杭が脆くなると共に、特に鉄筋に
泥水膜ができてコンクリートの付着力(結合)が弱くな
るという欠点もあった。
In addition, the hole wall collapses to a greater or lesser degree, and when reinforcing steel is inserted, the hole wall also collapses and the collapsed material mixes into the ready-mixed concrete, making the finished pile brittle. Another drawback was that a muddy water film formed, weakening the adhesion (bond) of the concrete.

この発明は、掘削時に泥水安定液の代りに清水を用いて
、上述の欠点を解消することを目的としている。
This invention aims to eliminate the above-mentioned drawbacks by using fresh water instead of mud stabilizer during excavation.

この発明は、築造せんとする杭の外周に沿いソイルセメ
ント杭を連続に打設して柱列土留壁を施工したのち、こ
の土留壁の内側を掘削排土すると共に、掘削孔中に清水
を充満させて、土留壁に受ける土圧や地下水圧の外力と
パヲンスをとり、上記の掘削が所定の深さに到達すると
その孔中に鉄筋籠を挿入し、次にトレミ管方式により孔
底から徐々に生コンクリートを打設する場所打コンクリ
ート杭の築造方法を提供する。
In this invention, soil cement piles are continuously driven along the outer periphery of the piles to be constructed to construct a column-row earth retaining wall, and then the inside of this earth retaining wall is excavated and removed, and fresh water is poured into the excavated hole. Fill the hole and balance it with the external forces of earth pressure and groundwater pressure applied to the earth retaining wall. When the above excavation reaches a predetermined depth, a reinforcing bar cage is inserted into the hole. Provided is a method for constructing cast-in-place concrete piles in which fresh concrete is gradually poured.

以下、この発明の実施例を添付図面に基づいて説明する
Embodiments of the present invention will be described below with reference to the accompanying drawings.

まず、築造せんとする杭の外周に沿いソイルセメント杭
Bを連続に打設して柱列土留壁Btを施工する。
First, soil cement piles B are continuously driven along the outer periphery of the piles to be constructed to construct the column retaining wall Bt.

上記柱列土留壁B9の施工は、図示の場合掘削機1のア
ースオーガー2により、地面から地中に向けて一上記ア
ースオーガー2の先端からベントナイト等の硬化遅延材
を配合したセメントミVりを注入(オーガーの軸芯とな
る管軸を用いて)しながら掘削し、その掘削が所定の深
度に到達したのち、上記アースオーガー2を引き抜くこ
とによりソイルセメント杭Bが打設される。
In the case shown in the figure, the construction of the pillar-row earth retaining wall B9 is carried out by using the earth auger 2 of the excavator 1 to drill a cement mixture containing hardening retardant such as bentonite from the ground to the ground from the tip of the earth auger 2. Excavation is carried out while pouring (using the tube axis which is the axis of the auger), and after the excavation reaches a predetermined depth, the soil cement pile B is driven by pulling out the earth auger 2.

次に、上記ソイルセメント杭Bの柱列進行方向側にアー
スオーガー2を位置させると共に、打設されたソイ〃セ
メンF杭Bの周面にアースオーガー2の周縁部をオーバ
ー′フツデさせて、順次ソイルセブント杭Bを打設する
ことにより、柱列土留壁B1が形成される。
Next, the earth auger 2 is positioned on the column advancing direction side of the soil cement pile B, and the peripheral edge of the earth auger 2 is placed over the circumferential surface of the driven soy cement pile B. By sequentially driving the soil seven piles B, a columnar earth retaining wall B1 is formed.

しかして、柱列土留壁Blの内側を掘削機3のパケット
4により掘削排土すると共に、削孔C内に清水りを充満
させて、柱列土留壁B1に受ける土庄や、地下水圧の外
力とバランスをとると共に、上記柱列土留壁B+の孔壁
の崩壊を防止する。
Then, the inside of the columnar earth retaining wall Bl is excavated and removed by the packet 4 of the excavator 3, and the drilled hole C is filled with fresh water to reduce the external force of the soil and groundwater pressure that is received by the columnar earth retaining wall B1. In addition to maintaining a balance with this, collapse of the hole wall of the columnar earth retaining wall B+ is prevented.

そして、上記の掘削が支持層に到達すると、水中ポンプ
を用いて削孔Cの底のスライムを(先端支持力を最大限
に発揮できるよう)吸い上げる。
When the above-mentioned excavation reaches the supporting layer, a submersible pump is used to suck up the slime at the bottom of the drilled hole C (so that the tip supporting force can be maximized).

その後に、削孔C内に鉄筋籠Eを挿入したのち、トVミ
管Fにより孔底から徐々に生コンクリートGを打設して
、場所打コンクリート杭Aを造成する。
After that, a reinforcing bar cage E is inserted into the drilled hole C, and then fresh concrete G is gradually poured from the bottom of the hole using a V-shaped pipe F to create a cast-in-place concrete pile A.

なお、トレミ管Fにより生コンクリートを打設する前に
柱列土留壁B1の孔壁にビニールシート(図示省略)を
張〉付けておくことにより、フリクション効果を減少し
て、ネガチプの作用する地盤に効果的である。
In addition, by pasting a vinyl sheet (not shown) on the hole wall of the column retaining wall B1 before pouring the fresh concrete using the tremor pipe F, the friction effect can be reduced and the ground where the negative chip acts can be reduced. effective.

以上のように、この発明に係る場所打コンクリート杭の
築造方法によれば、築造せんとする杭の外周に沿い地面
から地中の所定深さにソイルセメント杭を連続に打設し
て柱列土留壁を施再したのち、この柱列土留壁の内側を
掘削排土すると共に、削孔に清水を充満し、上記の削孔
が所定の深さに到達したのち、削孔内に鉄筋龍を挿入し
、そしてトVミ管により孔底から徐々に生コンクリート
を打設して場所打コンクリート杭を築造するので、従来
の泥水安定工法のように鉄筋籠の鋼棒表面に泥水の被膜
ができてコンクリートの付着力が弱くなり、かつ泥水の
配合、混線の管理が困難になったり、溢れ出る泥水によ
り各種公害問題が発生する欠点をなくすることができる
As described above, according to the method for constructing cast-in-place concrete piles according to the present invention, soil cement piles are continuously driven from the ground to a predetermined depth underground along the outer periphery of the pile to be constructed. After the earth retaining wall has been redone, the inside of this pillar-row earth retaining wall is excavated and removed, and the hole is filled with fresh water. After the hole reaches the specified depth, a reinforcing bar is installed inside the hole. The cast-in-place concrete piles are constructed by inserting the concrete and pouring fresh concrete gradually from the bottom of the hole using a V-shaped pipe, so unlike the conventional muddy water stabilization method, there is no muddy water coating on the surface of the steel rods of the reinforcing bar cage. This eliminates the disadvantages of weakening the adhesion of concrete, making it difficult to mix muddy water and managing crosstalk, and causing various pollution problems due to overflowing muddy water.

また、杭の外周に柱列土留壁が密着するので、柱列土留
壁が杭のフリクン3フ面とな9、フリクション効果が増
大する。
In addition, since the column retaining wall is in close contact with the outer periphery of the pile, the column retaining wall becomes the friction surface of the pile9, increasing the friction effect.

さらに、杭の外側地中に柱列土留壁が存在するので、砂
質上の流砂現象を起しやすい地盤でも極めて安全でちる
Furthermore, since there is a column retaining wall in the ground outside the pile, it is extremely safe even in sandy ground that is prone to quicksand phenomena.

また、ソイルセメン)杭の連続打設により柱列土留壁を
築造するので、掘削にともなう孔壁の崩壊或は鉄筋籠の
挿入時孔壁の崩壊をなくする。
In addition, since the column retaining wall is constructed by continuous driving of soil cement (soil cement) piles, the collapse of the hole wall due to excavation or the collapse of the hole wall when reinforcing bar cages are inserted is avoided.

【図面の簡単な説明】[Brief explanation of the drawing]

図面はこの発明の実施例を示すもので、第1図はソイル
セメント杭の造成掘削機を示す側面図、第2図は柱列土
留壁の横断平面図、第3図は削孔掘削機の側面図、第4
図は柱列土留壁に削孔した縦断拡大正面図、第5図は同
上に鉄筋籠を挿入した縦断正面図、第6図は同上の横断
平面図、第7図、第8図はトレミ管により生コンクリー
トを注入した縦断正面図、第9図は杭の縦断正面図であ
る。
The drawings show an embodiment of the present invention; Fig. 1 is a side view showing an excavator for making soil-cement piles, Fig. 2 is a cross-sectional plan view of a column retaining wall, and Fig. 3 is a diagram showing an excavator for drilling a hole. Side view, 4th
The figure is an enlarged vertical front view of the columnar retaining wall with holes drilled, Figure 5 is a vertical front view of the same as above with reinforcing bar cages inserted, Figure 6 is a cross-sectional plan view of the same as above, Figures 7 and 8 are tremor pipes. Fig. 9 is a longitudinal sectional front view of the pile with fresh concrete poured into it.

Claims (1)

【特許請求の範囲】[Claims] 築造せんとする杭の外周に沿い地面から地中の所定深さ
にソイA/−にメント杭を連続に打設して柱列土留壁を
施工したのち、この柱列土留壁の内側を掘削排土すると
共に、削孔に清水を充満し、上記の削孔が所定の深さに
到達したのち、削孔内に鉄筋能を挿入し、そしてトレミ
管にょ9孔底がら徐々に生コンクリートを打設すること
を特徴とする場所打コンクリート杭の築造方法。
After constructing a pillar-row earth retaining wall by continuously driving mento piles in soi A/- from the ground to a specified depth along the outer periphery of the piles to be constructed, excavate the inside of this pillar-row earth retaining wall. At the same time as removing the soil, the drilled hole is filled with clean water, and after the drilled hole has reached the specified depth, reinforcing bars are inserted into the drilled hole, and ready-mixed concrete is gradually poured into the bottom of the nine holes of the tremor pipe. A method for constructing cast-in-place concrete piles, which is characterized by casting.
JP14801181A 1981-09-16 1981-09-16 Construction of in-place concrete pile Granted JPS5847823A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14801181A JPS5847823A (en) 1981-09-16 1981-09-16 Construction of in-place concrete pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14801181A JPS5847823A (en) 1981-09-16 1981-09-16 Construction of in-place concrete pile

Publications (2)

Publication Number Publication Date
JPS5847823A true JPS5847823A (en) 1983-03-19
JPS6119771B2 JPS6119771B2 (en) 1986-05-19

Family

ID=15443103

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14801181A Granted JPS5847823A (en) 1981-09-16 1981-09-16 Construction of in-place concrete pile

Country Status (1)

Country Link
JP (1) JPS5847823A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59195925A (en) * 1983-04-20 1984-11-07 Toshio Enoki Construction of on-site concrete pile
JP2010281084A (en) * 2009-06-03 2010-12-16 Ohbayashi Corp Constructive method of bracing wall, constructive method of pile, bracing wall, pile
JP2011038379A (en) * 2009-08-18 2011-02-24 Takenaka Komuten Co Ltd Method of installing cast-in-place pile
JP2013147933A (en) * 2013-05-08 2013-08-01 Ohbayashi Corp Earth retaining wall construction method, cast-in-place pile construction method, earth retaining wall, and cast-in-place pile
JP2013177808A (en) * 2013-05-23 2013-09-09 Ohbayashi Corp Construction method for earth retaining wall, construction method for pile, pile, and boring machine
CN104294823A (en) * 2014-10-13 2015-01-21 安徽天筑建设(集团)有限公司 Anti-floating pile structure of pre-stressed pipe pile and construction method
CN107190736A (en) * 2017-04-18 2017-09-22 中交第二航务工程局有限公司 Suitable for the flexible shroud and its construction method of steel reinforcement cage under coral reef geology
CN113356283A (en) * 2021-06-11 2021-09-07 天津新路广建筑工程有限公司 Outward-expanding pile foundation reinforcement cage anti-floating device and anti-floating method

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59195925A (en) * 1983-04-20 1984-11-07 Toshio Enoki Construction of on-site concrete pile
JP2010281084A (en) * 2009-06-03 2010-12-16 Ohbayashi Corp Constructive method of bracing wall, constructive method of pile, bracing wall, pile
JP2011038379A (en) * 2009-08-18 2011-02-24 Takenaka Komuten Co Ltd Method of installing cast-in-place pile
JP2013147933A (en) * 2013-05-08 2013-08-01 Ohbayashi Corp Earth retaining wall construction method, cast-in-place pile construction method, earth retaining wall, and cast-in-place pile
JP2013177808A (en) * 2013-05-23 2013-09-09 Ohbayashi Corp Construction method for earth retaining wall, construction method for pile, pile, and boring machine
CN104294823A (en) * 2014-10-13 2015-01-21 安徽天筑建设(集团)有限公司 Anti-floating pile structure of pre-stressed pipe pile and construction method
CN104294823B (en) * 2014-10-13 2016-08-24 杭州江润科技有限公司 A kind of construction method of pile for prestressed pipe anti-floating pile raft structure
CN107190736A (en) * 2017-04-18 2017-09-22 中交第二航务工程局有限公司 Suitable for the flexible shroud and its construction method of steel reinforcement cage under coral reef geology
CN113356283A (en) * 2021-06-11 2021-09-07 天津新路广建筑工程有限公司 Outward-expanding pile foundation reinforcement cage anti-floating device and anti-floating method

Also Published As

Publication number Publication date
JPS6119771B2 (en) 1986-05-19

Similar Documents

Publication Publication Date Title
US4797031A (en) Caisson sinking method
EP0136355A1 (en) Method and apparatus for constructing reinforced concrete walls in the earth
JPS5847823A (en) Construction of in-place concrete pile
CN110700270B (en) Construction method for non-drainage earthwork excavation of ultra-deep foundation pit
JPH0960028A (en) Method for increasing strength of existing steel pipe pile
JPS59195925A (en) Construction of on-site concrete pile
JPS59126821A (en) Erection work of foundation pile
JPS582294B2 (en) Continuous basement wall construction method
JPH07268878A (en) Method for immersing caisson and structure of cutting face of caisson
JPH0776845A (en) Method of settling open caisson
JPS5936058B2 (en) How to construct a structure using underground continuous walls
JPS58189414A (en) Construction of sheathing wall
JPS58120918A (en) Burying method for pile
JPH03122317A (en) Concrete pile for hollow place and driving method thereof
JPH0464618A (en) Pit excavation work method
JPH0776844A (en) Method of settling open caisson
JPS601451B2 (en) Water stop mountain stop wall construction method using Benoto pile excavator
JPH059945A (en) Underground skeleton constructing method
JPH0510084A (en) Execution method of deeper depth man hole
JPH06240656A (en) Restoration of underground water
JPH10140557A (en) Construction method of cast-in-place diaphragm wall with hollow
JPS5869924A (en) Construction of sheathing wall having upper part consisting of underground continuous wall and lower part of pillar-row pile
JPH0122410B2 (en)
JPH0434116A (en) Constructing method of underground structure body
JPH0610339A (en) Landslide protection wall made of reinforced concrete and construction thereof