JPS59126821A - Erection work of foundation pile - Google Patents

Erection work of foundation pile

Info

Publication number
JPS59126821A
JPS59126821A JP118783A JP118783A JPS59126821A JP S59126821 A JPS59126821 A JP S59126821A JP 118783 A JP118783 A JP 118783A JP 118783 A JP118783 A JP 118783A JP S59126821 A JPS59126821 A JP S59126821A
Authority
JP
Japan
Prior art keywords
pile
hollow
cavity
mortar
cement milk
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP118783A
Other languages
Japanese (ja)
Other versions
JPS6146610B2 (en
Inventor
Hideo Tayama
田山 秀雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daiwa Kogyo Co Ltd
Aoki Construction Co Ltd
Original Assignee
Daiwa Kogyo Co Ltd
Aoki Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daiwa Kogyo Co Ltd, Aoki Construction Co Ltd filed Critical Daiwa Kogyo Co Ltd
Priority to JP118783A priority Critical patent/JPS59126821A/en
Publication of JPS59126821A publication Critical patent/JPS59126821A/en
Publication of JPS6146610B2 publication Critical patent/JPS6146610B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

PURPOSE:To construct a foundation pile to exactly support a structure by preventing the subsidence and cave-in of the ground above a cave by a method in which a hollow tube pile is inserted into an outer steel tubular pile provided with a slit and a packer, and cement milk is injected into the upper and lower part of the cave. CONSTITUTION:An outer steel tubular pile 3 is erected in a pit 5, and cement milk is injected into an inner hollow pile 1 set on the bottom of the pit 5. When the pile 1 alone is slightly pulled up from the bottom of the pit 5, the cement milk 6b flows out of the lower end of the pile 1 to pack the aperture between the pile 1 and the pile 3, and fills up between the pit 5b and the pile 3 through the slit 9 of the pile 3. After the pile is struck to the supporting ground, sand 7 is packed into the space between the piles 1 and 3, and cement milk 6a is packed onto the packer 8 between the pile 3 and the pit 5a. The subsidence and cave-in of the ground above a cave 4 can thus be prevented, and a foundation pile to exactly support a structure can be constructed.

Description

【発明の詳細な説明】 ある。[Detailed description of the invention] be.

一般に地盤直下に空洞のある場所に直接、構築物を築造
した場合、地盤の陥没や沈下が発生し、その構築物は破
壊される恐れがある。
Generally, when a structure is constructed directly in a place where there is a cavity directly under the ground, the ground may cave in or subside, and the structure may be destroyed.

そこで、従来はその空洞に、セメントモルタル、生コン
クリートやセメントバチルス等による充填施工が実施さ
れて来たが、次の様な問題があった。 即ち、イ)充填
が、その対象とする範囲に完全に施工されたかどうかの
at認が殆んど不可能か又は非常に困難である。
Conventionally, the cavities have been filled with cement mortar, ready-mixed concrete, cement bacilli, etc., but these have had the following problems. That is, (a) it is almost impossible or very difficult to confirm whether the filling has been completely applied to the target area.

口)設計計画時に於いて、空洞の内容積が正確に算定出
来ない為充填数量の正確な把握等が殆んど推定の域を出
ず不確実である。 ハ)目的充填範囲外への填充吻の流
出による地下水汚染の恐れがある。
口) At the time of design planning, the internal volume of the cavity cannot be accurately calculated, so accurate grasping of the filling quantity, etc. is almost beyond estimation and is uncertain. c) There is a risk of groundwater contamination due to the filling nozzle flowing out of the intended filling area.

そこで、かかる場合、確実な工法として、空洞以深の地
盤に支持層を求め、基礎杭により構築物を支持する工法
を採用するのがよいことになる。地盤直下に極めて透水
性の高い層のある場合も同様である。
Therefore, in such a case, as a reliable construction method, it is better to find a support layer in the ground deeper than the cavity and adopt a construction method in which the structure is supported by foundation piles. The same applies if there is an extremely permeable layer directly beneath the ground.

本発明は以上の工法を行なうために創案されたもので、
二重構造の杭、即ち外側に中空外管杭を、内側に既製コ
ンクリート杭又は鋼管杭、又は場所打ち杭等からなる中
空内管杭を使用する事により、この様な地盤条件下での
施工を可能にすると共に、構築物の荷重は内側の杭で負
担し、自然発生的な、又は突発的な陥没等によって発生
する摩靴力は外側の外管杭に作用させる様にした。
The present invention was created to carry out the above construction method,
Construction under such ground conditions can be achieved by using double-structured piles, i.e., hollow outer tube piles on the outside and hollow inner tube piles made of ready-made concrete piles, steel pipe piles, or cast-in-place piles on the inside. At the same time, the load of the structure is borne by the inner pile, and the abrasive force generated by natural or sudden collapse is applied to the outer pipe pile.

中空外管杭の建込み工法は、プレポーリング工法である
が、その削孔の方法として泥水等の安定液を使用する工
法は、空洞の存在の為、泥水が完全に流失して、削孔が
出来なくなるばかりでなく、地下水汚染をも招き適当で
ない。
The construction method for hollow outer pipe piles is the pre-poling method, but the method that uses a stabilizing liquid such as muddy water as a drilling method does not allow the muddy water to completely wash away due to the existence of cavities, making it difficult to drill the holes. Not only will this not be possible, but it will also lead to groundwater contamination, which is inappropriate.

そこで本発明にあっては、削孔の方法を、ダウンザホー
ルハンマー、又は、アースオーガ(ロックオーガー)等
のトライドリリングにより行なう。
Therefore, in the present invention, the hole drilling method is performed by a down-the-hole hammer or tri-drilling using an earth auger (rock auger) or the like.

この方法で所定の深度まで削孔した後、外側杭である中
空外管を建て込むが、空洞部及びその下部の削孔が困難
なときは、外側杭の外管を中堀り工法で所定の深度まで
設置する。
After drilling the hole to a specified depth using this method, the hollow outer pipe that is the outer pile is erected. However, if it is difficult to drill the hollow part and its lower part, the outer pipe of the outer pile can be erected using the hollow drilling method. Install to depth.

外管建込み後その孔底に沈積しているスライムをエアリ
フト等の方法により、充分排除する。
After constructing the outer pipe, thoroughly remove the slime deposited at the bottom of the hole using methods such as air lift.

孔底の洗滌後、内側杭の既製コンクリート杭、又は鋼管
杭の建込み又は場所打ち杭の造成を行なうが内側杭が創
製コンクリート杭又は鋼管杭の場合は、これらの杭の中
空部に孔底まで達するパイプを降し、これより所定量の
セメントミルクを注入し、注入完了後その注入パイプを
揚管して、セメントミルクが硬化しない内に、前に建込
んだ既製コンクリート杭、又は鋼管杭を数十センチメー
トル引揚げて、中空部に貯溜していたセメントミルクを
その先端より流出させ中空外管と中空内管との間隙に、
充填する。
After cleaning the bottom of the hole, install ready-made concrete piles, steel pipe piles, or cast-in-place piles as the inner piles, but if the inner piles are engineered concrete piles or steel pipe piles, the hole bottom is installed in the hollow part of these piles. After the injection is completed, the injection pipe is lifted up and the pre-built concrete pile or steel pipe pile that was erected before is removed before the cement milk has hardened. is pulled up several tens of centimeters, and the cement milk that had been stored in the hollow part flows out from its tip into the gap between the hollow outer tube and the hollow inner tube.
Fill.

又中空外管の外周へは、この外管の先端部分に予め設け
た数箇の開孔部より流出させる。
Further, the water flows out to the outer periphery of the hollow outer tube through several openings provided in advance at the tip of the outer tube.

その後、引揚げていた内側杭である既製コンクリート杭
又は鋼管杭を孔底まで降下し、セメントミルクが硬化し
ないうちに、内側杭をモンケン等により打撃し、その先
端が支持地盤に確実に若者する様にする。
After that, lower the ready-made concrete pile or steel pipe pile, which was the inner pile that was being pulled up, to the bottom of the hole, and before the cement milk has hardened, hit the inner pile with a hammer or similar tool to ensure that its tip is firmly attached to the supporting ground. I'll make it like that.

その後、中空外管と中空内管との間隙を、砂等により充
填し、最後に、中空外管の外周の空洞より上の部分をセ
メントミルク又はモルタル等により充填するがこのとき
、中空外管の所定の位置にパッカーを設けてセメントミ
ルクが空洞へ流失するのを防止する様にし、セメントミ
ルりは外管口元まで充填し空洞上部の地盤と鋼管を一体
化させる。
After that, the gap between the hollow outer tube and the hollow inner tube is filled with sand, etc., and finally, the part of the outer periphery of the hollow outer tube above the cavity is filled with cement milk, mortar, etc. A packer is installed at a predetermined position to prevent cement milk from flowing into the cavity, and the cement mill is filled up to the mouth of the outer pipe to integrate the steel pipe with the ground above the cavity.

本発明のものによれは外杭すなわち中空外管杭を建て込
む前にパッカーが外周に装着され、かつ先端にスリット
を有する中空外管杭を打込むため、この杭を利用してモ
ルタルを充填することができて空洞に向ってモルタルが
流失することがない。
In the case of the present invention, a packer is attached to the outer periphery before building the outer pile, that is, a hollow outer pipe pile, and since the hollow outer pipe pile with a slit at the tip is driven, this pile is used to fill with mortar. This prevents mortar from being washed away into the cavity.

したがって、根固めモルタル注入施工時及び中空外管外
周モルタル填充施工時において空洞内ヘモルタルが流亡
し、地下水層の水質に影響を及はすことがなく、堅固な
基礎杭かえられるという特徴がある。
Therefore, the hemmortal inside the cavity will not be washed away during the pouring of cementing mortar and the filling of mortar around the outer circumference of the hollow outer pipe, which will not affect the water quality of the groundwater aquifer, and the foundation pile will be strong.

以下図面に示す実施例について説明する。The embodiments shown in the drawings will be described below.

第1図は、本発明の施工法によって完成された基礎杭を
示すもので111は中空内管杭となる既製コンクリート
杭等であって、これにより構築物(2)( を支持する。(31&j中空外管杭の鋼管杭であり、(
4)は地盤中に形成された空洞を示すものである。(5
)はプレボーリングされた孔であって、これに前記内側
杭と外側の砕・管杭とからなる二重構造の杭が建込まれ
、孔(5)と杭(11及び杭(3)の空洞下部分、孔(
5)と杭(3)の空洞上部分には、セメントミルク又は
モルタル(6)が填充され、更に杭+11と杭(3)の
間隙には砂(7)が填充される。このとき、セメントミ
ルク又はモルタル(6a)が空洞(4)へ流失するのを
パッカー(8)で防止し、セメントミルク又はモルタル
(6b)が、鋼管(3)の外周へ填充される為に開孔部
(9)を設けておく。パッカー(8)はスポンジ、軟型
プラスチック又は木材製である。
Fig. 1 shows the foundation pile completed by the construction method of the present invention, and 111 is a prefabricated concrete pile or the like that becomes a hollow inner pipe pile, which supports the structure (2). It is a steel pipe pile with an outer pipe pile (
4) shows a cavity formed in the ground. (5
) is a pre-bored hole, into which a double structure pile consisting of the inner pile and the outer crushed/pipe pile is built, and the hole (5), the pile (11) and the pile (3) are erected. Lower part of cavity, hole (
The upper parts of the cavities between the piles 5) and the piles (3) are filled with cement milk or mortar (6), and the gaps between the piles +11 and the piles (3) are filled with sand (7). At this time, the packer (8) prevents the cement milk or mortar (6a) from flowing into the cavity (4), and the cement milk or mortar (6b) is opened to fill the outer periphery of the steel pipe (3). A hole (9) is provided. The packer (8) is made of sponge, soft plastic or wood.

次に施工の順序について説明する。Next, the order of construction will be explained.

先ず、第2図(イ)の様に、ダウンザホールハンマー又
はアースオーガー(ロックオーガー)等の循環泥水を使
わない方法でプレボーリングをし所定深度(支持地盤)
まで達する孔(5)を設ける。
First, as shown in Figure 2 (a), pre-boring is carried out using a method that does not use circulating mud, such as a down-the-hole hammer or an earth auger (rock auger), and the pre-boring is carried out to a specified depth (supporting ground).
Provide a hole (5) that reaches up to.

次に外側の鋼管杭(3)を第2図(ロ)に示したように
建込むが、このとき鋼管杭(3)には予めバッカー(8
)と開孔部(9)を設けて置く。 建込み完了後、孔(
5b) の底部のスライムは、エアリフト等の方法によ
り完全に排除する。
Next, the outer steel pipe pile (3) is erected as shown in Figure 2 (b), but at this time, the steel pipe pile (3) has a backer (8
) and an opening (9). After the erection is completed, the hole (
5b) Completely remove the slime at the bottom using a method such as air lift.

そして第2図(ハ)に示した様に中空的管杭(1)を建
込んだ後この中空的管杭(1+の中空部に孔底まで達ス
ルバイブ0〔によりセメントミルク(6)全注入する。
After erecting the hollow pipe pile (1) as shown in Figure 2 (c), the cement milk (6) was completely injected into the hollow part of the hollow pipe pile (1+) using a vibrator 0 that reached the bottom of the hole. do.

 セメントミルクは第2図に)に示した様に空洞(4)
−1流失しない量だけ注入する。
The cement milk has a cavity (4) as shown in Figure 2).
-1 Inject only the amount that will not be lost.

注入完了後はパイプ0〔を撤去し、セメントミルクが硬
化しないうちに第2図に)の様に内側杭(1)のみを孔
底より数十センチン1トル引き揚げる。
After the injection is completed, remove the pipe 0, and before the cement milk hardens, pull up only the inner pile (1) several tens of centimeters to 1 Torr from the hole bottom as shown in Figure 2).

こうすることによってセメントミルク(6b)は杭(1
)の下端より流出し杭(1)と鋼管杭(3)の間隙を埋
め、更にスリット(9)を通って孔(5b)と鋼管(3
)の間隙をも充填することになる。 そしてセメントミ
ルク(6b)が硬化しないうちに第2図(ホ)に示した
様に中空的管杭(1)を元の状態に戻し、モンケンaυ
により適度な打撃をし、杭tl)の先端が支持地盤に完
全に密着する様にした後、セメントミルク(6b)の硬
化を待って第2図(へ)の様に中空的管杭+11と中空
性管杭(3)との間隙を砂(7)で充填し、最後に杭(
3)の外周と削孔壁(5a)の間隙にセメントミルク又
はモルタル(6a)を充填スるがこのとき、充填物(6
a)が空洞(4)に流失するのを防止する為、杭(3)
の所定の位置にバッカー(8)をセットしておく。
By doing this, the cement milk (6b) is attached to the pile (1
) flows out from the bottom of the pile (1) and the steel pipe pile (3), fills the gap between the pile (1) and the steel pipe pile (3), and then flows through the slit (9) to the hole (5b) and the steel pipe (3).
) will also fill in the gaps. Then, before the cement milk (6b) hardens, the hollow pipe pile (1) is returned to its original state as shown in Figure 2 (e), and the Monken aυ
After applying a moderate blow to ensure that the tip of the pile (tl) is completely in contact with the supporting ground, wait for the cement milk (6b) to harden and attach it to the hollow pipe pile +11 as shown in Figure 2 (f). The gap between the hollow pipe pile (3) is filled with sand (7), and finally the pile (
Cement milk or mortar (6a) is filled into the gap between the outer periphery of the hole (3) and the drilled wall (5a).
In order to prevent a) from being washed away into the cavity (4), the stake (3)
Set the backer (8) in the specified position.

以上の様に、本発明の方法によれば空洞のある地盤中に
公害を発生させる事なく、空洞上の地盤の沈下、陥没を
防止出来、構築物を確実に支持する基礎杭を築造する事
が出来るのである。
As described above, according to the method of the present invention, it is possible to prevent the subsidence and collapse of the ground above the cavity without causing pollution in the ground where there is a cavity, and it is possible to construct foundation piles that reliably support the structure. It can be done.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明工法になる基礎杭の切断面図第2図(イ
)〜(へ)は本発明工法の動作順序を示す説明図である
。 (1〕中空内管杭(既製コンクリート杭、鋼管杭等)(
2)構築物 (3)中空性管杭1管杭) (4)空 洞 (5)プレボーリングによる孔 (6)セメントミルク又はモルタル (7)砂 (8)バッカー (9)スリット 0〔注入パイプ (1υモンケン 特許出願人 株式会社青木建設 第1図 第2図 (イ)                    (ロ
)第2図 (ム)                 (ニ)第2 (ホ) (へ)
FIG. 1 is a cross-sectional view of a foundation pile according to the construction method of the present invention. FIGS. (1) Hollow inner pipe piles (ready-made concrete piles, steel pipe piles, etc.) (
2) Structure (3) Hollow pipe pile (1 pipe pile) (4) Cavity (5) Hole by pre-boring (6) Cement milk or mortar (7) Sand (8) Backer (9) Slit 0 [Injection pipe ( 1υ Monken Patent Applicant Aoki Construction Co., Ltd. Figure 1 Figure 2 (A) (B) Figure 2 (M) (D) 2nd (E) (F)

Claims (1)

【特許請求の範囲】[Claims] 基礎杭を建込む地盤中に空洞又は極めて透水性の高い層
の存在する場合先ず該空洞又は極めて透水性の高い層の
下部の堅固な地層まで穿孔を行ない次に該孔に建て込ん
だ場合にその位置が空洞又は極めて透水性の高い層の頂
部の直上位置にあるように途中にパッカーを外周に装着
しかつ先端にスリットを有する中空外管を建て込み、こ
の中空外管内に更に中空内管を建て込み、該中空内管の
内部へモルタルを注入して下端開口部より溢流させ更に
外管のスリットを通って中空外管の外部へもモルタルを
通して根固めを行ない引き続いて外管頂部より外管と孔
壁との間の空隙内にモルタルを充填して前記パッカー以
降からモルタルが空洞又は極めて透水性の高い層に向っ
て溢流しないようにした基礎杭の建込み工法。
If there is a cavity or an extremely permeable layer in the ground where the foundation pile is to be erected, first drill a hole to the solid stratum below the cavity or extremely permeable layer, and then build into the hole. A hollow outer tube with a slit at the tip and a packer attached to the outer periphery is installed in the middle so that the position is directly above the top of the cavity or a layer with extremely high water permeability, and a hollow inner tube is installed inside this hollow outer tube. The mortar is injected into the inside of the hollow inner pipe and overflows from the lower end opening, and the mortar is passed through the slit in the outer pipe to the outside of the hollow outer pipe to perform foot protection, and then from the top of the outer pipe. A construction method for foundation piles in which mortar is filled in the gap between the outer pipe and the hole wall to prevent the mortar from overflowing from the packer onward toward the cavity or an extremely permeable layer.
JP118783A 1983-01-10 1983-01-10 Erection work of foundation pile Granted JPS59126821A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP118783A JPS59126821A (en) 1983-01-10 1983-01-10 Erection work of foundation pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP118783A JPS59126821A (en) 1983-01-10 1983-01-10 Erection work of foundation pile

Publications (2)

Publication Number Publication Date
JPS59126821A true JPS59126821A (en) 1984-07-21
JPS6146610B2 JPS6146610B2 (en) 1986-10-15

Family

ID=11494444

Family Applications (1)

Application Number Title Priority Date Filing Date
JP118783A Granted JPS59126821A (en) 1983-01-10 1983-01-10 Erection work of foundation pile

Country Status (1)

Country Link
JP (1) JPS59126821A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102162249A (en) * 2011-05-20 2011-08-24 大连宜华建设集团有限公司 Construction method of pre-stressed high-strength concrete (PHC) pipe piles in deep ocean backfill area
CN104563147A (en) * 2014-08-29 2015-04-29 上海市政工程设计研究总院(集团)有限公司 Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation
JP2015166538A (en) * 2014-03-04 2015-09-24 鹿島建設株式会社 Form installation method, form and underwater structure
CN106049467A (en) * 2016-08-02 2016-10-26 中铁六局集团有限公司 Method for treating slurry leakage of bored pile through percussion drill under complex geology
JP2016223208A (en) * 2015-06-02 2016-12-28 株式会社トーヨーアサノ Pile foundation structure
JP2017082513A (en) * 2015-10-29 2017-05-18 大亜ソイル株式会社 Cast-in-place concrete pile and construction method thereof
CN108894214A (en) * 2018-08-27 2018-11-27 孙德明 A kind of solution cavity geological environment bored concrete pile and its bore forming method
CN113338259A (en) * 2021-06-02 2021-09-03 中地君豪高科股份有限公司 Construction method for treating karst cave of pile bottom bearing layer

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111549775A (en) * 2020-05-29 2020-08-18 贵州建工集团第一建筑工程有限责任公司 Hole pile construction method under karst geological condition

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102162249A (en) * 2011-05-20 2011-08-24 大连宜华建设集团有限公司 Construction method of pre-stressed high-strength concrete (PHC) pipe piles in deep ocean backfill area
JP2015166538A (en) * 2014-03-04 2015-09-24 鹿島建設株式会社 Form installation method, form and underwater structure
CN104563147A (en) * 2014-08-29 2015-04-29 上海市政工程设计研究总院(集团)有限公司 Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation
JP2016223208A (en) * 2015-06-02 2016-12-28 株式会社トーヨーアサノ Pile foundation structure
JP2017082513A (en) * 2015-10-29 2017-05-18 大亜ソイル株式会社 Cast-in-place concrete pile and construction method thereof
CN106049467A (en) * 2016-08-02 2016-10-26 中铁六局集团有限公司 Method for treating slurry leakage of bored pile through percussion drill under complex geology
CN108894214A (en) * 2018-08-27 2018-11-27 孙德明 A kind of solution cavity geological environment bored concrete pile and its bore forming method
CN113338259A (en) * 2021-06-02 2021-09-03 中地君豪高科股份有限公司 Construction method for treating karst cave of pile bottom bearing layer

Also Published As

Publication number Publication date
JPS6146610B2 (en) 1986-10-15

Similar Documents

Publication Publication Date Title
CN105604001B (en) Drilling tool is stirred in the stake of stiff-core cement soil cylinder and the rotation of construction method and tubular
CN107023002A (en) Down-the-hole impacts churning composite pile pile making method
JPS59126821A (en) Erection work of foundation pile
JPS5985028A (en) Steel pipe pile and laying work thereof
JP4872561B2 (en) Construction method of ready-made piles
JPH04185813A (en) Formation of soil-cement composite pile
JPS5847823A (en) Construction of in-place concrete pile
JPH0841870A (en) Method of connection precast concrete pile
JP2001271347A (en) Drop method for ready-made pile
JPH03257215A (en) Pile constructing method
JP2002054164A (en) Center of column and construction method therefor
JP2003055985A (en) Connecting method of column to pile
JPS6013118A (en) Pile erection work and excavation head for forming consolidated perforated wall therefor
JP3200240B2 (en) Filling method of self-hardening material in ground reinforcement method
JP4178273B2 (en) Construction method of structural pillars using ready-made piles
JPS601451B2 (en) Water stop mountain stop wall construction method using Benoto pile excavator
JPS58120918A (en) Burying method for pile
JPH0442493B2 (en)
JPH0641956A (en) Execution method for high proof stress cast-in-place concrete pile, etc.
JP2001073367A (en) Embedding construction method for steel pipe pile
JPS5869924A (en) Construction of sheathing wall having upper part consisting of underground continuous wall and lower part of pillar-row pile
JPH10183613A (en) Construction method for pile
JPH0412328B2 (en)
JPH0415849B2 (en)
JPS6133086B2 (en)