JP2003055985A - Connecting method of column to pile - Google Patents

Connecting method of column to pile

Info

Publication number
JP2003055985A
JP2003055985A JP2001244076A JP2001244076A JP2003055985A JP 2003055985 A JP2003055985 A JP 2003055985A JP 2001244076 A JP2001244076 A JP 2001244076A JP 2001244076 A JP2001244076 A JP 2001244076A JP 2003055985 A JP2003055985 A JP 2003055985A
Authority
JP
Japan
Prior art keywords
casing
pile
construction
steel pipe
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001244076A
Other languages
Japanese (ja)
Inventor
Shinichiro Nozawa
伸一郎 野澤
Hajime Fujisawa
一 藤沢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
East Japan Railway Co
Original Assignee
East Japan Railway Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by East Japan Railway Co filed Critical East Japan Railway Co
Priority to JP2001244076A priority Critical patent/JP2003055985A/en
Publication of JP2003055985A publication Critical patent/JP2003055985A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To enhance the efficiency of work execution to attain the shortening of the term of construction and the saving of construction cost by dispensing with a chemical injection, and dispensing with a footing construction which was performed by a work near a track and the construction of a temporary earth retaining work. SOLUTION: This connecting method comprises a process for rotationally press-fitting a casing and applying it over a hole wall protective range; a process for drilling the casing as a hole wall protective work and placing concrete in the drilled hole to construct a concrete pile 2; and a process for using the upper end of the casing as an outside steel pipe 30 of socket connecting, building a column 8 in the outside steel pipe, and connecting it to the concrete pile.

Description

【発明の詳細な説明】 【0001】 【発明の属する技術分野】本発明は柱と杭の接合する方
法に関する。 【0002】 【従来の技術】ボーリング機械を使った場所打ちコンク
リート杭の施工法として、掘削孔内に泥水を満たして孔
壁を防護し、泥水の循環により掘削土砂の排出を行って
コンクリート杭を施工することが行われている。このよ
うな場所打ちコンクリート杭の施工法は、地盤に掘削孔
を形成するため、地盤を緩めることがあり、そのため軟
弱地盤の場合には、薬液注入により孔壁を防護する方法
が用いられている。 【0003】図5はそのような施工法の例を示す図で、
鉄道の既存の軌道1に近接して小型リバースサーキュレ
ーション工法により場所打ちコンクリート杭2を施工す
るに際し、口元ケーシング3の下方に薬液注入を行って
地盤改良を施して改良地盤4を形成し、その上で掘削を
行うことで、孔壁崩壊を防止し、軌道1の支持地盤の変
状を防止することが行われている。 【0004】このように施工した場所打ちコンクリート
杭に、例えば、駅構内で橋上駅舎や自由通路の柱を接合
する場合には、図6に示すように、場所打ちコンクリー
ト杭2の上部にフーチング5を設け、これにアンカーフ
レーム6を埋め込んで、鋼管柱7を接合する方法がとら
れる。この場合、アンカーフレーム6の引き抜き剪断耐
力を確保するため、フーチング5は所定の幅が必要とな
る。 【0005】 【発明が解決しようとする課題】図6に示すような従来
の柱と杭の接合方法では、場所打ちコンクリート杭を施
工するために薬液注入を行っており、コストがかかると
共に軌道が変状する場合があり、さらにフーチングに所
定の幅が必要でアンカーフレームの製作費用がかかると
ともに、フーチングを構築するための掘削作業や仮土留
工7の施工が必要であり、営業線に近接している工事の
ような場合、線路を閉鎖しての作業となり、コスト増に
なってしまう。本発明は上記課題を解決するためのもの
で、薬液注入を不要とし、線路近接作業で行っていたフ
ーチング構築と、仮土留工の施工を不要とし、施工を効
率化し、工期の短縮および工事費の節減を図ることを目
的とする。 【0006】 【課題を解決するための手段】本発明の柱と杭の接合方
法、ケーシングを回転圧入して孔壁保護範囲に渡って施
工する工程と、前記ケーシングを孔壁防護工として削孔
し、削孔内にコンクリートを打設してコンクリート杭を
施工する工程と、前記ケーシングをソケット接合の外側
鋼管として使用し、該外側鋼管内に柱を建て込んでコン
クリート杭に接合する工程とからなることを特徴とす
る。 【0007】 【発明の実施の形態】以下、本発明の実施の形態を図面
を参照しつつ説明する。本発明の場所打ちコンクリート
杭と柱の接合方法は、従来のように薬液注入による地盤
改良を施すことに代えて、ケーシングを用いて孔壁を防
護し、上端のケーシングを利用して杭と柱を接合するよ
うにしたものである。 【0008】図1は掘削機でケーシングを圧入して孔壁
防護工とする杭の施工法を説明する図である。ケーシン
グ20は先端ケーシング21、中間ケーシング22、継
ぎ手部材23からなり、これらはいずれも鋼管を主材と
して製作され、先端ケーシング21の先端部には掘削刃
やコンポジット(図示省略)が設けられ、中間ケーシン
グの先端部には先端ケーシング21と他の中間ケーシン
グとを連結するためのソケット部(図示省略)が一体に
設けられ、継ぎ手部材23は掘削機10に連結するため
のフランジやその周囲に設けられた補強リブ(図示省
略)を有し、また、先端ケーシング、中間ケーシング、
継ぎ手部材には、図示は省略するが互いに連結するため
の連結部材、相互の相対回転を拘束するための突起や切
り欠きがそれぞれ対応する位置に形成されている。 【0009】削孔する際し、まず掘削機10を設置し、
それに継ぎ手部材23を介して先端ケーシング21を連
結し、掘削機10によりケーシング20を地盤中に回転
圧入する。先端ケーシング21のほぼ全長を回転圧入し
た後、先端ケーシング21と継ぎ手部材23との間に中
間ケーシング22を継ぎ足し、さらに回転圧入する。こ
うして所要本数の中間ケーシング22を継ぎ足してケー
シング20を孔壁保護範囲Hに渡って設置した後、最上
段の中間ケーシング22と継ぎ手部材23との連結を解
いて継ぎ手部材を中間ケーシングから取り外し、掘削機
10から継ぎ手部材を取り外して掘削機ロッド11およ
び掘削ビット12を取り付ける。そして、地中に設置さ
れたケーシング20内を通して掘削機10により泥水を
循環させつつ掘削を行う。所定深度まで掘削を行った
後、図2に示すように、鉄筋籠13等の芯材を挿入し、
杭頭位置までコンクリートを打設して杭2を施工する。
ついで、孔壁防護工に用いたケーシング20の最上段を
ソケット鋼管30として用い、図3に示すように、ソケ
ット鋼管30にコンクリート充填鋼管柱8を建て込み、
環状コンクリート31を打設して場所打ち杭2に鋼管柱
8を接合する。 【0010】図4は場所打ちコンクリート2とコンクリ
ート充填鋼管柱8を接合した状態を示す縦断面図であ
り、ソケット鋼管30で鋼管柱を拘束することにより、
従来のようにフーチングを構築することをせず、しかも
引き抜き剪断力を確保することができる。 【0011】なお、ケーシングは掘削機により回転させ
て引き抜くようにし、ソケット接合用の外側鋼管として
使用するケーシングのみ残すようにしてもよく、或いは
埋め殺しにして最上段のケーシングをソケット接合用の
外側鋼管として用いるようにしてもよい。 【0012】 【発明の効果】以上のように本発明によれば、孔壁防護
用のケーシング上端を接合用のソケット用の外側鋼管と
して利用することにより、従来、線路隣接作業で行って
いたフーチング構築と仮土留工の施工が不要となり、ま
た、薬液注入を行う必要がないので、軌道の変状がな
く、施工が効率化し、工期の短縮および工事費の節減を
図ることが可能となる。
Description: BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for joining a pillar and a pile. 2. Description of the Related Art As a method for constructing a cast-in-place concrete pile using a boring machine, a drill pile is filled with muddy water to protect the hole wall, and the excavated soil is discharged by circulating the muddy water to form a concrete pile. Construction is being done. The construction method of such cast-in-place concrete piles may loosen the ground because excavation holes are formed in the ground. Therefore, in the case of soft ground, a method of protecting the hole wall by injecting a chemical is used. . FIG. 5 shows an example of such a construction method.
When the cast-in-place concrete pile 2 is constructed by the small reverse circulation method in the vicinity of the existing track 1 of the railway, a chemical solution is injected below the mouth casing 3 to improve the ground, and the improved ground 4 is formed. By excavating above, the collapse of the hole wall is prevented, and the deformation of the support ground of the track 1 is prevented. [0004] In the case of joining a cast-in-place concrete pile constructed in this way with, for example, a bridge station building or a pillar of a free passage in a station yard, as shown in FIG. Is provided, and the anchor frame 6 is embedded therein, and the steel pipe column 7 is joined. In this case, the footing 5 needs a predetermined width in order to secure the pull-out shear strength of the anchor frame 6. [0005] In the conventional method of joining a pillar and a pile as shown in FIG. 6, a chemical solution is injected to construct a cast-in-place concrete pile, which is costly and requires a track. The footing may be deformed, and the footing requires a certain width, and the production cost of the anchor frame is increased. In addition, the excavation work for constructing the footing and the construction of the temporary earth retaining work 7 are required. In such a case, the work is performed by closing the track, which increases costs. The present invention has been made to solve the above-described problems, and eliminates the need for injection of a chemical solution, eliminates the need for footing construction and temporary soil retaining work that were performed during track proximity work, streamlines construction, shortens construction time, and reduces construction costs. The goal is to save money. SUMMARY OF THE INVENTION A method of joining a column and a pile according to the present invention, a step of rotationally press-fitting a casing and constructing the same over a hole wall protection range, and drilling the casing as a hole wall protection work. Then, casting concrete into the drilled hole and constructing a concrete pile, and using the casing as an outer steel pipe of a socket joint, erecting a column in the outer steel pipe and joining the concrete pile. It is characterized by becoming. Embodiments of the present invention will be described below with reference to the drawings. The method for joining a cast-in-place concrete pile and a column according to the present invention uses a casing to protect the hole wall and replace the pile and the column using the casing at the upper end, instead of performing the ground improvement by injecting a chemical solution as in the conventional method. Are joined. FIG. 1 is a diagram for explaining a method of constructing a pile as a hole wall protection work by press-fitting a casing with an excavator. The casing 20 includes a tip casing 21, an intermediate casing 22, and a joint member 23, all of which are manufactured using a steel pipe as a main material, and a drilling blade or a composite (not shown) is provided at a tip portion of the tip casing 21. A socket portion (not shown) for connecting the front end casing 21 and another intermediate casing is integrally provided at a front end portion of the casing, and a joint member 23 is provided on a flange for connecting to the excavator 10 and around the same. Having a reinforcing rib (not shown), a tip casing, an intermediate casing,
Although not shown, a coupling member for coupling with each other, and a projection and a notch for restraining relative rotation of each other are formed in the joint members at corresponding positions. When drilling, first, the excavator 10 is installed,
The tip casing 21 is connected thereto via a joint member 23, and the casing 20 is rotationally pressed into the ground by the excavator 10. After rotationally press-fitting substantially the entire length of the distal casing 21, an intermediate casing 22 is added between the distal casing 21 and the joint member 23, and further rotationally press-fitted. After the required number of intermediate casings 22 are added and the casing 20 is installed over the hole wall protection range H, the connection between the uppermost intermediate casing 22 and the joint member 23 is released, the joint member is removed from the intermediate casing, and excavation is performed. The coupling member is removed from the drilling machine 10, and the excavator rod 11 and the drilling bit 12 are mounted. Then, excavation is performed while circulating muddy water by the excavator 10 through the casing 20 installed underground. After excavation to a predetermined depth, as shown in FIG.
Pile 2 is constructed by casting concrete to the pile head position.
Next, the uppermost stage of the casing 20 used for the hole wall protection was used as the socket steel pipe 30, and as shown in FIG.
An annular concrete 31 is cast and the steel pipe column 8 is joined to the cast-in-place pile 2. FIG. 4 is a longitudinal sectional view showing a state where the cast-in-place concrete 2 and the concrete-filled steel pipe column 8 are joined together.
The pulling shear force can be ensured without constructing the footing as in the related art. The casing may be rotated by an excavator and pulled out, and only the casing used as the outer steel pipe for socket connection may be left, or the uppermost casing may be buried and the outer casing for socket connection may be left out. It may be used as a steel pipe. As described above, according to the present invention, by using the upper end of the casing for protecting the hole wall as the outer steel pipe for the socket for joining, the footing conventionally performed in the work adjacent to the track is used. Since the construction and the construction of the temporary earth retaining work are not required, and there is no need to inject the chemical solution, the track is not deformed, the construction is more efficient, the construction period can be shortened, and the construction cost can be reduced.

【図面の簡単な説明】 【図1】 ケーシングを回転圧入して孔壁防護工とする
場所打ちコンクリート杭の施工法の説明図である。 【図2】 ケーシングをソケット鋼管とする杭と柱の接
合法の説明図である。 【図3】 ソケット接合を説明する概念図である。 【図4】 杭と柱を接合した状態を示す縦断面図であ
る。 【図5】 薬液注入による孔壁防護工を用いた杭施工法
の説明図である。 【図6】 フーチングを介した杭と柱の接合法を説明す
る図である。 【符号の説明】 2…場所打ちコンクリート杭、8…鋼管柱、10…掘削
機、11…ロッド、12…掘削ビット、13…鉄筋籠、
20…ケーシング、21…先端ケーシング、22…中間
ケーシング、23…継ぎ手部材、30…ソケット用外側
鋼管、31…管状コンクリート。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is an explanatory diagram of a method of constructing a cast-in-place concrete pile serving as a hole wall protector by rotationally press-fitting a casing. FIG. 2 is an explanatory view of a method for joining a pile and a column using a casing as a socket steel pipe. FIG. 3 is a conceptual diagram illustrating socket joining. FIG. 4 is a longitudinal sectional view showing a state where a pile and a column are joined. FIG. 5 is an explanatory view of a pile construction method using hole wall protection by chemical injection. FIG. 6 is a diagram illustrating a method of joining a pile and a column via footing. [Description of Signs] 2 ... Cast-in-place concrete pile, 8 ... Steel pipe column, 10 ... Excavator, 11 ... Rod, 12 ... Drilling bit, 13 ... Reinforced basket,
20 ... Casing, 21 ... Tip casing, 22 ... Intermediate casing, 23 ... Joint member, 30 ... Outer steel pipe for socket, 31 ... Tubular concrete.

Claims (1)

【特許請求の範囲】 【請求項1】 ケーシングを回転圧入して孔壁保護範囲
に渡って施工する工程と、前記ケーシングを孔壁防護工
として削孔し、削孔内にコンクリートを打設してコンク
リート杭を施工する工程と、前記ケーシングをソケット
接合の外側鋼管として使用し、該外側鋼管内に柱を建て
込んでコンクリート杭に接合する工程と、からなる柱と
杭の接合方法。
Claims: 1. A step of rotationally press-fitting a casing to perform construction over a hole wall protection area, drilling the casing as a hole wall protection work, and placing concrete in the hole. A method of joining a pillar and a pile, comprising: a step of constructing a concrete pile by using the casing as an outer steel pipe of a socket joint; and a step of building a pillar in the outer steel pipe and joining the pillar to a concrete pile.
JP2001244076A 2001-08-10 2001-08-10 Connecting method of column to pile Pending JP2003055985A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001244076A JP2003055985A (en) 2001-08-10 2001-08-10 Connecting method of column to pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001244076A JP2003055985A (en) 2001-08-10 2001-08-10 Connecting method of column to pile

Publications (1)

Publication Number Publication Date
JP2003055985A true JP2003055985A (en) 2003-02-26

Family

ID=19074067

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001244076A Pending JP2003055985A (en) 2001-08-10 2001-08-10 Connecting method of column to pile

Country Status (1)

Country Link
JP (1) JP2003055985A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005264446A (en) * 2004-03-16 2005-09-29 East Japan Railway Co Method of joining cast-in place pile and steel pipe column
JP2006328666A (en) * 2005-05-23 2006-12-07 Okumura Corp Construction method for integrating pile with column
KR101029285B1 (en) * 2008-10-08 2011-04-18 한국건설기술연구원 Connecting Structure Steel Composite Bent and Cast In a Place Concrete Pile and Constructing Method Thereof
KR101077034B1 (en) * 2008-12-10 2011-10-26 한국건설기술연구원 Connecting Structure Steel Composite Bent and Cast In a Place Concrete Pile and Constructing Method Thereof
USRE44444E1 (en) 2004-03-26 2013-08-20 Victaulic Company Method of joining pipes in end to end relation
JP2016216975A (en) * 2015-05-19 2016-12-22 鹿島建設株式会社 Installation method of earth anchor

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62284825A (en) * 1986-06-04 1987-12-10 Nippon Kokan Kk <Nkk> Joint construction of column and pile of structure
JPH0393923A (en) * 1989-09-06 1991-04-18 Mitsui Constr Co Ltd Connection method of steel pillar of cast-in-place pile and connection structure
JPH11172692A (en) * 1997-12-16 1999-06-29 Sato Benec Co Ltd Execution of column constitution member

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62284825A (en) * 1986-06-04 1987-12-10 Nippon Kokan Kk <Nkk> Joint construction of column and pile of structure
JPH0393923A (en) * 1989-09-06 1991-04-18 Mitsui Constr Co Ltd Connection method of steel pillar of cast-in-place pile and connection structure
JPH11172692A (en) * 1997-12-16 1999-06-29 Sato Benec Co Ltd Execution of column constitution member

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005264446A (en) * 2004-03-16 2005-09-29 East Japan Railway Co Method of joining cast-in place pile and steel pipe column
USRE44444E1 (en) 2004-03-26 2013-08-20 Victaulic Company Method of joining pipes in end to end relation
JP2006328666A (en) * 2005-05-23 2006-12-07 Okumura Corp Construction method for integrating pile with column
JP4611113B2 (en) * 2005-05-23 2011-01-12 株式会社奥村組 Integrated construction method of pile and column
KR101029285B1 (en) * 2008-10-08 2011-04-18 한국건설기술연구원 Connecting Structure Steel Composite Bent and Cast In a Place Concrete Pile and Constructing Method Thereof
KR101077034B1 (en) * 2008-12-10 2011-10-26 한국건설기술연구원 Connecting Structure Steel Composite Bent and Cast In a Place Concrete Pile and Constructing Method Thereof
JP2016216975A (en) * 2015-05-19 2016-12-22 鹿島建設株式会社 Installation method of earth anchor

Similar Documents

Publication Publication Date Title
KR100847352B1 (en) Supporting tube assembly for tunnel supporting method with grouted steel pipe in the borehole and supporting method of using thereof
JP3211673B2 (en) Simple temporary bridge temporary pier construction method
JP5274145B2 (en) Cast-in-place pile and its construction method
KR100852724B1 (en) Supporting tube assembly for tunnel grouting including plastic extension tube with cutting grooove and friction resistance enriched surface and tunnel supporting method of using thereof
WO2000032906A1 (en) Sardine-bone construction method for large-section tunnel
JP2002070048A (en) Construction method for steel core of column in inverted construction system, and plier and steel pipe pile used for the method
JP2007009505A (en) Foundation reinforcing method
JP2874561B2 (en) Fore piling method with stiffening of the leading leg using a shaft
JP2003055985A (en) Connecting method of column to pile
JP4373824B2 (en) Joining method of cast-in-place pile and steel pipe column
JP4269301B2 (en) Cross-section expansion method for existing tunnels
JPS59126821A (en) Erection work of foundation pile
JP4341029B2 (en) Pile foundation method
JP2002047648A (en) Cast-in-place concrete pile construction method
JP2003184499A (en) Large diameter lock bolt anchor for natural ground reinforcement
JP5495874B2 (en) Removal method of shield excavator
JP2721950B2 (en) Ground improvement method for tunnel excavation and surrounding area
JP3200240B2 (en) Filling method of self-hardening material in ground reinforcement method
JPS61151325A (en) Method of reinforcing pile head part against horizontal force
JP2617267B2 (en) Rock anchoring method for steel pipe piles
JPH0468407B2 (en)
JPH073777A (en) Method for constructing self-supporting land slide protection wall
JP4178273B2 (en) Construction method of structural pillars using ready-made piles
JP2004278250A (en) Method for positioning concrete pile
JP2000328560A (en) Method of creating steel pipe column row earth retaining wall

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050622

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050713

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050909

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20051221

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060215

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060302

A911 Transfer of reconsideration by examiner before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20060307

A912 Removal of reconsideration by examiner before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A912

Effective date: 20060502