JP2004278250A - Method for positioning concrete pile - Google Patents

Method for positioning concrete pile Download PDF

Info

Publication number
JP2004278250A
JP2004278250A JP2003074865A JP2003074865A JP2004278250A JP 2004278250 A JP2004278250 A JP 2004278250A JP 2003074865 A JP2003074865 A JP 2003074865A JP 2003074865 A JP2003074865 A JP 2003074865A JP 2004278250 A JP2004278250 A JP 2004278250A
Authority
JP
Japan
Prior art keywords
pile
concrete
hole
concrete pile
welding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2003074865A
Other languages
Japanese (ja)
Inventor
Yugo Asamatsu
裕吾 浅松
Kinya Machino
欽哉 町野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP2003074865A priority Critical patent/JP2004278250A/en
Publication of JP2004278250A publication Critical patent/JP2004278250A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a method for positioning a concrete pile by which the working ratio of a pile driver is improved and the term of work can be shortened while stable welding can be conducted. <P>SOLUTION: When the concrete pile is positioned, excavation work in which a drilled pit 3 is formed by using the pile driver 2 is conducted while a lower pile 11 is inserted into a temporary pit 20 previously formed at a place separate from the pile 3. Welding work in which an upper pile 12 transported by a crane 8 is extended to the lower pile 11 is conducted, and the extended concrete pile 10D is moved to a section immediately above the pit 3 by using the crane 8 and inserted into the pit 3. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

【0001】
【発明の属する技術分野】
本発明は、地盤に掘削された削孔内に少なくとも2本以上の既製のコンクリート杭を継ぎ足したものを挿入して建て込むコンクリート杭の建て込み方法に関するものである。
【0002】
【従来の技術】
従来、地盤に既製のコンクリート杭を建て込む方法としては、例えば、図2(a)〜(d)に示すように、地盤1を、アースオーガー等の杭打機2を用いて、硬質地盤である支持層1Aに達する深さまで掘削し、この掘削された削孔3にセメントミルク4を注入した後、既製のコンクリート杭10を挿入して根固めし、更に固定液5を注入して上記コンクリート杭10の周辺を固定して上記コンクリート杭10を建て込むセメントミルク工法や、上記削孔3にコンクリート杭10を挿入した後、最終打撃を行って上記コンクリート杭10を更に地盤1内に打込んで根固めする先端拡大根固め工法がある。
ところで、コンクリート杭10の長さは、一般に、運搬等の関係上、15〜20m程度であるので、支持層1Aの深さ、すなわち、上記削孔3の深さが深い場合には、複数本のコンクリート杭を継ぎ足して建て込む必要がある。具体的には、図3(a)に示すように、まず、杭打機2を用いて所定の深さに掘削された削孔3に、下杭11をその杭頭が地上面から出るくらいまで挿入し、バックホーなどの重機6に、上記下杭11をワイヤ7等により保持するとともに、上記杭打機2のオーガー(スクリュー部)に代えて上杭12を取付け、上記上杭12の下端部を上記下杭11の上端部に乗せる。そして、上杭12の下端部の継手と下杭11の上端部の継手とを溶接し上記下杭11に上記上杭12を継ぎ足した後、この継ぎ足されたコンクリート杭を回転させながら上記削孔3内に挿入して建て込む。
【0003】
【発明が解決しようとする課題】
しかしながら、上記従来の方法では、杭打機2を下杭11と上杭12との継ぎ足し作業に用いているため、溶接作業の間は掘削作業ができないといった問題点があった。また、溶接作業を掘削した土砂が残っている削孔3の周りで行っているため足元の状態が悪いだけでなく、下杭11の保持も不安定であるので、安定した作業ができず、溶接の仕上がりが悪かった。
【0004】
本発明は、従来の問題点に鑑みてなされたもので、杭打機の稼動率を上げて工期の短縮を図ることができるとともに、安定した溶接を行うことのできるコンクリート杭の建て込み方法を提供することを目的とする。
【0005】
【課題を解決するための手段】
本発明の請求項1に記載の発明は、地盤を所定の深さまで掘削し、この掘削された削孔に少なくとも2本以上の既製のコンクリート杭を継ぎ足したものを挿入して建て込むコンクリート杭の建て込み方法であって、予め仮穴を設け、この仮穴に下側となる杭を設置してこの杭の上側に上側となる杭を継ぎ足した後、上記継ぎ足されたコンクリート杭を、クレーン等の他の挿入手段を用いて、上記削孔に挿入するようにしたことを特徴とするものである。これにより、杭打機は掘削作業のみを行えばよいので、杭打機の稼動率を上げて工期の短縮を図ることが可能となる。また、下側となる杭を安定して保持できるとともに、溶接作業を行う足元がよいので、安定した溶接を行うことが可能となる。
【0006】
【発明の実施の形態】
以下、本発明の実施の形態について、図面に基づき説明する。
図1(a),(b)は、本実施の形態に係るコンクリート杭の建て込み方法を示す図である。本例では、まず、アースオーガー等の杭打機2を用いて、地盤1を硬質地盤である支持層1Aに達する深さまで掘削して削孔3を形成する掘削作業を行うとともに、上記削孔3から離れた場所に予め設けておいた仮穴20に下杭11を挿入し、この下杭11の上側に、例えば、相番クローラクレーン等の揚重機8により運搬された上杭12を乗せて、この上杭12の下端部の継手と下杭11の上端部の継手とを溶接して上記下杭11に上記上杭12を継ぎ足す。このとき、上記仮穴20の深さとしては、下杭11を挿入した時に、その杭頭が地上面から出る程度の深さとする。また、上記仮穴20の周囲に溶接足場となる作業床21を設置する。上記下杭11の大部分は、上記仮穴20内に収納されているので、従来のワイヤによる支持に比べて下杭11の支持安定性は格段によい。更に、本例では、溶接作業を掘削した土砂などの障害物のない箇所に設置された作業床21上で行うことができるので、溶接作業を安定して行うことができ、溶接の仕上がり度を向上させることができる。
掘削作業が完了し杭打機2が次の掘削現場に移動した後、上記継ぎ足されたコンクリート杭10Dを、上記揚重機8を用いて、上記削孔3の直上まで移動し、セメントミルク4が注入された削孔3内に挿入する。
なお、上記コンクリート杭10Dを挿入する際、削孔壁の崩壊等により、揚重機8では所定深さまで挿入できない場合には、上記杭打機2を呼び戻して上記コンクリート杭10Dを取付け、上記コンクリート杭10Dを回転させながら上記削孔3内に回転圧入するようにすればよい。
【0007】
このように、本実施の形態では、杭打機2を用いて削孔3を形成する掘削作業を行うとともに、上記削孔3から離れた場所に予め設けておいた仮穴20に下杭11を挿入し、この下杭11に、揚重機8により運搬された上杭12を継ぎ足す溶接作業を行い、この継ぎ足されたコンクリート杭10Dを、上記揚重機8を用いて、上記削孔3の直上まで移動し、セメントミルク4が注入された削孔3内に挿入するようにしたので、杭打機2の稼動率(掘削している時間)を大幅に向上させることができる。また、仮穴20により下杭11を安定して保持できるとともに、仮穴20近傍は足元がよいので、安定した溶接を短時間で行うことができる。したがって、溶接の仕上がり度や作業時間についても向上させることができる。更に、揚重機8においても、従来はコンクリート杭の荷下しにしか使用していなかったが、コンクリート杭の建て込み時にも使用することによって稼動率を向上させることができる。これらの向上により、工期が短縮され、また、コストも削減される結果となる。
【0008】
なお、上記実施の形態では、セメントミルク工法を用いたコンクリート杭10Dの建て込み方法について説明したが、これに限るものではなく、上述した先端拡大根固め工法においても適用可能である。
また、建て込むコンクリート杭としては、下杭11と上杭12の2本の杭を継ぎ足したものに限るものではなく、3本以上であってもよい。なお、この場合には、仮穴も複数設ける必要がある。
【0009】
【発明の効果】
以上説明したように、本発明によれば、2本以上の既製のコンクリート杭を建て込む際に、予め仮穴を設け、この仮穴に下側となる杭を設置してこの杭の上側に上側となる杭を継ぎ足した後、上記継ぎ足されたコンクリート杭を、クレーン等の他の挿入手段を用いて、上記削孔に挿入するようにしたので、杭打機の稼動率が向上し、工期の短縮を図ることができる。また、下側となる杭を安定して保持できるとともに、溶接作業を行う足元がよいので、安定した溶接を短時間で行うことができる。
【図面の簡単な説明】
【図1】本発明の実施の形態に係るコンクリート杭の建て込み方法を示す図である。
【図2】従来のセメントミルク工法の概要を示す図である。
【図3】従来のコンクリート杭の建て込み方法を示す図である。
【符号の説明】
1 地盤、1A 支持層、2 杭打機、3 削孔、4 セメントミルク、
8 揚重機、10D コンクリート杭、11 下杭、12 上杭、20 仮穴、
21 作業床。
[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a method for installing a concrete pile, which is constructed by inserting at least two or more ready-made concrete piles into a drilled hole excavated in the ground.
[0002]
[Prior art]
Conventionally, as a method of embedding a ready-made concrete pile in the ground, for example, as shown in FIGS. 2A to 2D, the ground 1 is hardened by using a pile driver 2 such as an earth auger. After excavating to a depth reaching a certain support layer 1A, cement milk 4 is poured into the drilled hole 3, a ready-made concrete stake 10 is inserted and solidified. A cement milk method in which the periphery of the pile 10 is fixed and the concrete pile 10 is erected, or after the concrete pile 10 is inserted into the hole 3, a final blow is performed to further drive the concrete pile 10 into the ground 1. There is a method of expanding the tip with roots.
By the way, since the length of the concrete pile 10 is generally about 15 to 20 m due to transportation or the like, when the depth of the support layer 1A, that is, the depth of the hole 3 is large, a plurality of concrete piles 10 are required. It is necessary to build concrete piles by adding them. Specifically, as shown in FIG. 3A, first, the lower pile 11 is inserted into the drilled hole 3 excavated to a predetermined depth using the pile driving machine 2 so that the pile head comes out of the ground surface. To the heavy machine 6 such as a backhoe, holding the lower pile 11 with the wire 7 and the like, and attaching an upper pile 12 in place of the auger (screw portion) of the pile driver 2, and a lower end of the upper pile 12. The part is placed on the upper end of the lower pile 11. Then, the joint at the lower end of the upper pile 12 and the joint at the upper end of the lower pile 11 are welded, the upper pile 12 is added to the lower pile 11, and the drilling is performed while rotating the added concrete pile. Insert into 3 and build.
[0003]
[Problems to be solved by the invention]
However, in the above-mentioned conventional method, since the pile driver 2 is used for adding the lower pile 11 and the upper pile 12, there is a problem that the excavation operation cannot be performed during the welding operation. In addition, since the welding work is performed around the drilled hole 3 where the excavated earth and sand remains, not only the condition of the feet is poor, but also the holding of the lower pile 11 is unstable, so that stable work cannot be performed. The finish of welding was bad.
[0004]
The present invention has been made in view of the conventional problems, and it is possible to increase the operation rate of a pile driver, shorten the construction period, and provide a method for installing a concrete pile capable of performing stable welding. The purpose is to provide.
[0005]
[Means for Solving the Problems]
The invention according to claim 1 of the present invention relates to a concrete pile which is formed by excavating the ground to a predetermined depth, inserting at least two or more ready-made concrete piles into the excavated hole, and building the pile. A method of erection, in which a temporary hole is provided in advance, a lower pile is installed in the temporary hole, and an upper pile is added to an upper side of the pile. Characterized in that it is inserted into the hole by using another insertion means. Thus, since the pile driver only needs to perform the excavation work, it is possible to increase the operation rate of the pile driver and shorten the construction period. In addition, the lower pile can be stably held, and the feet for performing the welding operation are good, so that stable welding can be performed.
[0006]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
FIGS. 1A and 1B are diagrams showing a method for installing a concrete pile according to the present embodiment. In this example, first, using a pile driver 2 such as an earth auger, the ground 1 is excavated to a depth reaching the support layer 1A, which is a hard ground, to perform a drilling operation for forming a drilled hole 3 and the drilling operation. The lower pile 11 is inserted into a temporary hole 20 provided in advance at a location away from the upper pile 3, and the upper pile 12 transported by a lifting machine 8 such as a phase number crawler crane is placed on the lower pile 11. Then, the joint at the lower end of the upper pile 12 and the joint at the upper end of the lower pile 11 are welded to add the upper pile 12 to the lower pile 11. At this time, the depth of the temporary hole 20 is set to such a depth that the pile head comes out of the ground surface when the lower pile 11 is inserted. A work floor 21 serving as a welding scaffold is installed around the temporary hole 20. Since most of the lower pile 11 is housed in the temporary hole 20, the support stability of the lower pile 11 is remarkably improved as compared with the conventional wire support. Furthermore, in this example, since the welding operation can be performed on the work floor 21 installed in a place where there is no obstacle such as excavated earth and sand, the welding operation can be performed stably, and the degree of finish of welding can be reduced. Can be improved.
After the excavation work is completed and the pile driver 2 moves to the next excavation site, the added concrete pile 10D is moved to a position directly above the borehole 3 by using the lifting machine 8, and the cement milk 4 is removed. It is inserted into the drilled hole 3.
When the concrete pile 10D is inserted, if the drilling machine 8 cannot be inserted to a predetermined depth due to collapse of a drilled wall or the like, the pile driver 2 is recalled, and the concrete pile 10D is attached. What is necessary is just to rotationally press-fit into the hole 3 while rotating the 10D.
[0007]
As described above, in the present embodiment, the excavation work for forming the drill hole 3 using the pile driving machine 2 is performed, and the lower pile 11 is inserted into the temporary hole 20 provided in advance in a place away from the drill hole 3. Is inserted into the lower pile 11, and a welding operation of adding the upper pile 12 transported by the lifting machine 8 is performed, and the added concrete pile 10D is subjected to the drilling 3 by using the lifting machine 8. Since the mortar is moved right above and is inserted into the drilled hole 3 into which the cement milk 4 has been injected, the operation rate of the pile driver 2 (time during excavation) can be greatly improved. In addition, since the lower pile 11 can be stably held by the provisional hole 20 and the foot is good near the provisional hole 20, stable welding can be performed in a short time. Therefore, it is possible to improve the finished degree of welding and the working time. Further, the lifting machine 8 has been conventionally used only for unloading concrete piles. However, the use of the lifting machine 8 at the time of building concrete piles can improve the operation rate. These improvements result in shortened construction periods and reduced costs.
[0008]
In the above-described embodiment, the method of embedding the concrete pile 10D using the cement milk method has been described.
The concrete pile to be built is not limited to the two piles of the lower pile 11 and the upper pile 12, but may be three or more. In this case, it is necessary to provide a plurality of temporary holes.
[0009]
【The invention's effect】
As described above, according to the present invention, when two or more ready-made concrete piles are erected, provisional holes are provided in advance, a lower pile is installed in the temporary holes, and After adding the pile on the upper side, the added concrete pile is inserted into the borehole using another insertion means such as a crane, so that the operation rate of the pile driver is improved, Can be shortened. In addition, the lower pile can be stably held and the step of performing the welding operation is good, so that stable welding can be performed in a short time.
[Brief description of the drawings]
FIG. 1 is a view showing a method for installing a concrete pile according to an embodiment of the present invention.
FIG. 2 is a diagram showing an outline of a conventional cement milk method.
FIG. 3 is a view showing a conventional method of installing a concrete pile.
[Explanation of symbols]
1 ground, 1A support layer, 2 pile driver, 3 drill hole, 4 cement milk,
8 lifting machine, 10D concrete pile, 11 lower pile, 12 upper pile, 20 temporary hole,
21 Work floor.

Claims (1)

地盤を所定の深さまで掘削し、この掘削された削孔に少なくとも2本以上の既製のコンクリート杭を継ぎ足したものを挿入して建て込むコンクリート杭の建て込み方法において、予め仮穴を設け、この仮穴に下側となる杭を設置してこの杭の上側に上側となる杭を継ぎ足した後、上記継ぎ足されたコンクリート杭を上記削孔に挿入するようにしたことを特徴とするコンクリート杭の建て込み方法。Excavating the ground to a predetermined depth, in the method of embedding concrete piles to be inserted by inserting at least two or more ready-made concrete piles into the drilled hole, temporary holes are provided in advance, After placing the lower pile in the temporary hole and adding the upper pile to the upper side of the pile, the concrete pile thus added is inserted into the borehole. How to build.
JP2003074865A 2003-03-19 2003-03-19 Method for positioning concrete pile Pending JP2004278250A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003074865A JP2004278250A (en) 2003-03-19 2003-03-19 Method for positioning concrete pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003074865A JP2004278250A (en) 2003-03-19 2003-03-19 Method for positioning concrete pile

Publications (1)

Publication Number Publication Date
JP2004278250A true JP2004278250A (en) 2004-10-07

Family

ID=33290328

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003074865A Pending JP2004278250A (en) 2003-03-19 2003-03-19 Method for positioning concrete pile

Country Status (1)

Country Link
JP (1) JP2004278250A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1705917A2 (en) 2005-03-22 2006-09-27 Nissan Motor Co., Ltd. Detection apparatus and method
JP2007308932A (en) * 2006-05-17 2007-11-29 Ok Soil:Kk Soil improvement method
US7899211B2 (en) 2005-12-07 2011-03-01 Nissan Motor Co., Ltd. Object detecting system and object detecting method
JP2018003433A (en) * 2016-07-01 2018-01-11 西松建設株式会社 Construction method of double pipe pile and double pipe pile

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1705917A2 (en) 2005-03-22 2006-09-27 Nissan Motor Co., Ltd. Detection apparatus and method
US7899211B2 (en) 2005-12-07 2011-03-01 Nissan Motor Co., Ltd. Object detecting system and object detecting method
JP2007308932A (en) * 2006-05-17 2007-11-29 Ok Soil:Kk Soil improvement method
JP2018003433A (en) * 2016-07-01 2018-01-11 西松建設株式会社 Construction method of double pipe pile and double pipe pile

Similar Documents

Publication Publication Date Title
JP3211673B2 (en) Simple temporary bridge temporary pier construction method
JP2006328716A (en) Structure and method for underpinning of existing structure and method of constructing new structure near existing structure
KR20110041391A (en) Pile structure
JP2009263966A (en) Removal method of existing pile
JP2004278250A (en) Method for positioning concrete pile
JP2007308951A (en) Method of constructing outer peripheral column by inverted construction method
JP4831511B2 (en) Construction method of foundation pile
JP2005264446A (en) Method of joining cast-in place pile and steel pipe column
JP3165997B2 (en) Casting method and equipment for sheet piles
JP2001271365A (en) Construction method for underground structure
JP4101282B1 (en) Foundation pile construction method
JP2003055985A (en) Connecting method of column to pile
JP5140515B2 (en) Installation method of underground floor pillar and construction method of underground structure
JPS60119816A (en) Formation of continuous pile
JP4137172B1 (en) Reinforcing bar construction in cast-in-place pile
JP4314681B2 (en) Reverse strut construction method
JP2002167759A (en) Execution method of foundation pile
JP2003003459A (en) Joint grout method
JP2000297430A (en) Cast-in-place concrete pile by pulling out steel pipe form
JP3098975B2 (en) Pile driving method for concrete pile
JP6403300B1 (en) How to embed sheet pile
JP2005264452A (en) Construction method of pile foundation, and construction device for pile foundation
JP2004011241A (en) Burying method of pile and excavating device used therefor
JP2001073367A (en) Embedding construction method for steel pipe pile
JP3815258B2 (en) How to build a true pillar

Legal Events

Date Code Title Description
A621 Written request for application examination

Effective date: 20060203

Free format text: JAPANESE INTERMEDIATE CODE: A621

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20071203

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20071218

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080215

A131 Notification of reasons for refusal

Effective date: 20080311

Free format text: JAPANESE INTERMEDIATE CODE: A131

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080417

A02 Decision of refusal

Effective date: 20080729

Free format text: JAPANESE INTERMEDIATE CODE: A02