JPS60119816A - Formation of continuous pile - Google Patents
Formation of continuous pileInfo
- Publication number
- JPS60119816A JPS60119816A JP22820683A JP22820683A JPS60119816A JP S60119816 A JPS60119816 A JP S60119816A JP 22820683 A JP22820683 A JP 22820683A JP 22820683 A JP22820683 A JP 22820683A JP S60119816 A JPS60119816 A JP S60119816A
- Authority
- JP
- Japan
- Prior art keywords
- pipe
- casing pipe
- auger
- excavated
- excavation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
- E02D5/385—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
- E21B7/20—Driving or forcing casings or pipes into boreholes, e.g. sinking; Simultaneously drilling and casing boreholes
- E21B7/201—Driving or forcing casings or pipes into boreholes, e.g. sinking; Simultaneously drilling and casing boreholes with helical conveying means
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は連続杭造成方法に係り、特に岩盤層に連続杭を
造成するのに適した連続杭造成方法に関する。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method for constructing continuous piles, and particularly to a method for constructing continuous piles suitable for constructing continuous piles in rock layers.
遮水壁、連続壁、土溜め等に用いられる連続杭は、単孔
を一部重複させて掘削することにより造成される。従来
、崩壊層を含んだこの単孔の掘削はアースオーガ等によ
る同時ケーシング工法により掘削しているが、アースオ
ーガによる掘削は土砂等の軟弱層については比較的能率
よく掘削できるものの、転石層や、硬質岩盤については
掘削不能になる不具合があった。Continuous piles used for impermeable walls, continuous walls, earthen basins, etc. are constructed by excavating single holes that partially overlap. Conventionally, this single hole excavation that includes a collapsed layer has been carried out using a simultaneous casing method using an earth auger, etc. However, although excavation using an earth auger is relatively efficient for digging soft layers such as earth and sand, , there was a problem that made it impossible to excavate hard rock.
本発明は、このような事情に鑑みてなされたもので、大
口径エアハンマトリルによって硬質岩盤についても能率
よく連続杭を造成することができる連続杭造成方法を提
案することを目的としている。The present invention has been made in view of these circumstances, and an object of the present invention is to propose a continuous pile construction method that can efficiently create continuous piles even on hard rock using a large-diameter air hammer drill.
本発明は、前記目的を達成する為に、孔壁を保護するケ
ーシングパイプと、前記ケーシングパイプ内部を通過可
能な掘削装置とを用い、前記掘削装置の掘削孔にケーシ
ングパイプを追従させて孔壁を保護しながら掘削する同
時ケーシング工法により岩盤層に着きするまでの崩壊層
を掘削し、前記ケーシングパイプを地中に残置した状態
で、前記掘削装置を回収し、その後前記ケーシングパイ
プ内にエアハンマドリルを挿入して硬質岩ff1lTF
Qを掘削し、次に掘削孔にセメンl及び固化剤による杭
を造成し、以下掘削孔を一部重複さ−lて前記同時ケー
シング工法から前記杭造成までの作業を繰返して連続杭
を造成することを特徴としている。In order to achieve the above object, the present invention uses a casing pipe that protects the hole wall and a drilling device that can pass through the inside of the casing pipe, and makes the casing pipe follow the excavation hole of the drilling device to prevent the hole wall. The collapsed layer is excavated until reaching the bedrock layer using the simultaneous casing construction method, which excavates while protecting the casing, and the excavation equipment is recovered with the casing pipe remaining underground, and then an air hammer drill is inserted into the casing pipe. Insert hard rockff1lTF
Drill Q, then create a pile using cement and a solidifying agent in the excavated hole, and then partially overlap the excavated holes and repeat the steps from the simultaneous casing method to the pile creation to create a continuous pile. It is characterized by
以上添f+J図面に従って本発明に係る連続杭造成方法
の好ましい実施例を詳説する。A preferred embodiment of the continuous pile construction method according to the present invention will be described in detail in accordance with the attached drawings F+J.
(11崩壊層の掘削
第1図乃至第3図は同時ゲーシンクエ法の1種であるケ
ーシングパイプ・オーガ掘削を示し、第1図はオーガの
杭芯セット状態を示している。第1図に於いて、10は
ベースマシン、12は下端部にビットを備えた掘削用厚
肉ゲージングパイプ、14はスクリュウ状の回転刃を持
つオーガ、1石はベースマシン10のボスト18に設け
られたオーガ回転装置、20は同じくボスト18に設け
られたケーシングパイプ回転装置、21はケーシングパ
イプ12のガイド′である。オーガ14は第1図に示す
ようにしてその中心を杭芯に七ソトされ、この状態でオ
ーガ回転装置16でオーガを回転させると共にケーシン
グパイプ回転装置20でケーシングパイプ12を逆方向
に回転し、第2図で示すように掘削し、掘削屑はオーガ
のスクリュー作用により地上へ送出される6尚、第2図
で符号22で示すのは土砂等からなる軟弱な崩壊層、2
4で示すのは硬質岩盤層である。第3図に示すように崩
壊層22の掘削が終了してケーシングパイプ12が岩盤
層24に着きすると、掘削不可能となるのでケーシング
パイプ12を建込んだ状態でオーガ14のみを引き抜く
。この場合、掘削孔26の孔壁はケーシングパイプ12
で保護されているので崩壊するようなことはない。また
ケーシングパイプ12内には掘削土砂27が残留しζい
る。(11) Excavation of Collapsed Layer Figures 1 to 3 show casing pipe and auger excavation, which is a type of simultaneous geosinking method, and Figure 1 shows the auger pile core set. 10 is a base machine, 12 is a thick-walled gauging pipe for drilling with a bit at the lower end, 14 is an auger with a screw-shaped rotating blade, and 1 stone is an auger rotation device provided on the post 18 of the base machine 10. , 20 is a casing pipe rotation device also provided on the post 18, and 21 is a guide' for the casing pipe 12.The auger 14 is rotated around the center of the pile as shown in FIG. The auger rotation device 16 rotates the auger, and the casing pipe rotation device 20 rotates the casing pipe 12 in the opposite direction to excavate as shown in FIG. 2, and the excavated debris is sent to the ground by the screw action of the auger. In addition, in Fig. 2, the reference numeral 22 indicates a soft collapsed layer consisting of earth and sand, etc.
4 is a hard rock layer. As shown in FIG. 3, when the excavation of the collapsed layer 22 is completed and the casing pipe 12 reaches the bedrock layer 24, it becomes impossible to excavate, so only the auger 14 is pulled out with the casing pipe 12 erected. In this case, the hole wall of the drilled hole 26 is connected to the casing pipe 12.
It is protected by , so there is no chance of it collapsing. Further, excavated soil 27 remains inside the casing pipe 12.
次に第4図に示すように厚肉ケーシングパイプ12内に
孔壁保護用パイプ28を加振機30を用いて挿入し、続
いて第5図に示すように孔壁保護用パイプ28を残して
厚内ケーシングパイプ12を引き抜く。このように厚内
ケーシングパイプ12を薄肉孔壁保護用パイプ28に代
えるのは、掘削に使用するケーシングパイプは強大なト
ルクと耐力を必要とする為剛性の高い専用厚肉ケーシン
グパイプ12を必要とするが、掘削後の孔壁部1裏防止
用ゲーシングバイゾには剛性の商いケーシングパイプは
必要でなく、+rli 111iな厚肉ケーシングパイ
プ12ば他の掘削箇所に用いて有効利用を図る為である
。Next, as shown in FIG. 4, the hole wall protection pipe 28 is inserted into the thick-walled casing pipe 12 using the vibrator 30, and then, as shown in FIG. 5, the hole wall protection pipe 28 is left in place. and pull out the thick inner casing pipe 12. The reason why the thick inner casing pipe 12 is replaced with the thin-walled hole wall protection pipe 28 is that the casing pipe used for excavation requires a large torque and proof strength, so a dedicated thick-walled casing pipe 12 with high rigidity is required. However, the rigid casing pipe for preventing the back of the hole wall 1 after excavation does not require a rigid casing pipe, and the +rli 111i thick casing pipe 12 can be used effectively at other excavated locations.
(2)岩盤層の掘削
第6図は孔壁保護用パイプ2B内にエアハンマドリル3
0を挿入し、岩盤層を掘削する状態を示し、ベースマシ
ン10のボスト18にはエアハンマドリル30が回転装
置34、掘管35とともに設けられている。エアハンマ
ドリル30のビット32には回転装置34によって回転
力が与えられると共にコンプレッサ37から圧縮空気が
送られ図示しないエアハンマ機構により衝撃力が加えら
れ、岩盤層24をすJ率よく掘削することができる。ピ
ント32は、エアハンマ機構から直接衝撃力を受けるア
ンビル36に着脱自在に設けられ、損傷したビット32
のみを交換することができるので経済的す1果が大きく
、これにより大口径の岩盤掘削が容易に可能となる。勿
論ビット32は、通雷のアンビルと一体構造の単体ビッ
トを使用することもできる。また、ビット32を拡縮自
在に構成すれば、岩盤24の掘削に於いても同時ケーシ
ング工法が可能となる。第7図はエアハンマドリル30
による岩盤24の掘削状態を示し、掘削屑は、エアハン
マドリルの排気エアによって地上へ噴出する。(2) Drilling of the rock layer Figure 6 shows the air hammer drill 3 inside the hole wall protection pipe 2B.
An air hammer drill 30 is installed on the boss 18 of the base machine 10 along with a rotating device 34 and a drilling pipe 35. A rotational force is applied to the bit 32 of the air hammer drill 30 by a rotating device 34, compressed air is sent from a compressor 37, and an impact force is applied by an air hammer mechanism (not shown), so that the rock layer 24 can be excavated with high efficiency. . The focus 32 is removably installed on an anvil 36 that receives direct impact from the air hammer mechanism, and is used to remove damaged bits 32.
This has a large economical effect because only the screw can be replaced, and this makes it easier to excavate large diameter rock. Of course, the bit 32 can also be a single bit that is integrally constructed with the anvil of the torpedo. Further, if the bit 32 is configured to be expandable and contractible, a simultaneous casing method can be used when excavating the rock mass 24. Figure 7 shows air hammer drill 30
The excavated debris is ejected to the ground by the exhaust air of the air hammer drill.
(3)コンクリートの打設
第8図は、エアハンマドリル30を孔壁保護用パイプ2
8から引抜いた後、コンクリートを打設する状態および
連続杭の造成状態を示し、第9図は第8図上でIX −
IX線に沿う平面図である。第8図に於いて38はミキ
サー、40はボノパ、42はポンプ、43はインジェク
ションパイプである。ポンプ42からはセメント及び固
化剤例えばコンクリートが孔壁保護用パイプ28内に打
設され、その後孔壁保護用パイプ28が抜管される。前
記掘削並びにコンクリートの打設は、第10図に示すよ
うに(図の斜線部分がコンクリート)一本置きに行って
もよいし、コンクリートが固化すれば第11図に示すよ
うに連続掘削してもよい。又第12図のように既掘削札
内にH型のガイド44等を設けることにより連続掘削す
ることもできる第13図乃至第15図は本発明に係る他
の実施例が示されている。第14図に示すように崩壊層
22に大径の岩45が転在している場合には、オーガ掘
削では掘削能率が低下する。この為、エアハンマドリル
46によるアンダリーミング掘削(特願昭57−187
268号明細書参照)によってケーシングパイプ12を
建込む。即ち、第14図に示すようにビット48をケー
シングパイプ12の外径より大径に拡げた拡径状態にし
てアンダリーミング掘削し、これによりケーシングパイ
プ12を同時建込みし、崩壊層22の掘削終了後ビット
48を縮径状態にしてケーシングパイプ12がら抜き去
り、エアハンマドリル46を挿入し、岩盤を掘削する。(3) Concrete pouring Figure 8 shows the air hammer drill 30 being inserted into the hole wall protection pipe 2.
Figure 9 shows the state of pouring concrete and the construction of continuous piles after pulling out from Figure 8.
It is a top view along the IX line. In FIG. 8, 38 is a mixer, 40 is a bonopa, 42 is a pump, and 43 is an injection pipe. Cement and a solidifying agent such as concrete are poured into the hole wall protection pipe 28 from the pump 42, and then the hole wall protection pipe 28 is removed. The above-mentioned excavation and concrete placement may be carried out every other place as shown in Fig. 10 (shaded areas in the figure are concrete), or once the concrete has solidified, continuous excavation may be carried out as shown in Fig. 11. Good too. Furthermore, as shown in FIG. 12, continuous excavation can be performed by providing an H-shaped guide 44 or the like within the already excavated tag. FIGS. 13 to 15 show other embodiments of the present invention. As shown in FIG. 14, when large-diameter rocks 45 are scattered in the collapsed layer 22, the excavation efficiency of auger excavation decreases. For this purpose, under reaming drilling using an air hammer drill 46 (patent application 1987-187) was carried out.
268). That is, as shown in FIG. 14, the bit 48 is expanded to a larger diameter than the outer diameter of the casing pipe 12 to perform under-reaming excavation, thereby simultaneously erecting the casing pipe 12 and excavating the collapsed layer 22. After finishing, the bit 48 is reduced in diameter, the casing pipe 12 is removed, the air hammer drill 46 is inserted, and the rock is excavated.
第13図に於いて46aはエアハンマドリル46の回転
装置、47ばケーシングパイプの回転装置である。尚、
ケーシングパイプ12の建込みは、アンダーリーミング
掘削であるので第13図のようなケーシングパイプ回転
装置47を使用しないで第14図に示すように掘削孔口
元に設置するパワージヤツキ49によってケーシングパ
イプを掘削と同時に押込むことも可能である。続いての
操作は前記第4図及至第8図までの操作と同様なのでそ
の説明は省略する。また、上記エアハンマドリルのアン
ダリーミングエ法によれば、エアハンマドリルビットを
交換することなく岩盤1台をそのまま目的深度まで掘削
することも可能である。In FIG. 13, 46a is a rotating device for the air hammer drill 46, and 47 is a rotating device for the casing pipe. still,
Since the casing pipe 12 is constructed by under-reaming excavation, the casing pipe is excavated by a power jack 49 installed at the mouth of the excavation hole as shown in Fig. 14, without using the casing pipe rotating device 47 as shown in Fig. 13. It is also possible to push in at the same time. The subsequent operations are the same as those shown in FIGS. 4 to 8, so their explanation will be omitted. Further, according to the under-reaming method of the air hammer drill described above, it is also possible to excavate a single rock to a target depth without replacing the air hammer drill bit.
面、第11図に示すようにコンクリート打設後、シート
パイル50を建込み、連続杭の遮水壁を造成することが
できる。As shown in FIG. 11, after concrete is poured, sheet piles 50 are erected to create a water-shielding wall of continuous piles.
尚、土留め杭の場合は、ケーシングパイプ(又はH剛)
を建込んだ後コンクリートを注入し、建込んだ状態で杭
を造成する。In addition, in the case of earth retaining piles, casing pipe (or H rigid)
After erecting the building, concrete is poured and piles are created while the building is erected.
以上説明したように本発明に係る連続杭造成方法によれ
ば、崩壊層は同時ケーシング工法により掘削することに
より掘削孔の孔壁の崩壊を防ぎ、また崩壊層に続<Wg
Wtに対してはエアハンマドリルにより掘削するので能
・IX的な連続杭の掘削を行なうことができる。As explained above, according to the continuous pile construction method of the present invention, the collapse layer is excavated by the simultaneous casing method to prevent collapse of the borehole wall, and the collapse layer is
Since Wt is excavated using an air hammer drill, it is possible to perform continuous pile excavation in the IX type.
第1図及至第3図はケーシングパイプオーガ掘削による
崩壊層の掘削状態を示す図面で、WSt図はケーシング
パイプオーガ掘削機の正面図、第2図はオーガによる掘
削状態を示す断面図、第3図はオーガ掘削終了後、ケー
シングパイプを残置した状態を示す断面図、第4図並び
に第5図はケーシングパイプパイプの交換を示す断面図
、第6図並びに第7図はエアハンマドリルによる岩盤層
の掘削状態を示す断面図、第8図はコンクリートの打設
状態を示す説明図、第9図は第8図上で■−■線に沿う
断面図、第10図並びに第11図は掘削並びにコンクリ
ート打設の順序を示す説明図、第12図は既掘削孔にガ
イ1′を建て込んで掘削する状態を示す説明図、第13
図乃至第15図は本発明に係る他の実施例を示す図面で
、第13図はエアハンマドリル掘削機の正面図、第14
図並びに第15図は岩を含む崩壊層の掘削状態を示す断
面図である。
12・・・ケーシングパイプ、14・・・オーガ、22
・・・崩壊層、 24・・・岩盤層、 28・・・孔壁
保護用パイプ、30・・・エアハンマトリル、38・・
・ミキサ、42・・・ポンプ、 43・・・インジェク
ションパイプ。
第4図
第5図
上
ハ
第6図
第7図
第14因
第15因Figures 1 to 3 are drawings showing the state of excavation of the collapsed layer by casing pipe auger excavation, WSt is a front view of the casing pipe auger excavator, Fig. 2 is a cross-sectional view showing the state of excavation by the auger, and Fig. The figure is a cross-sectional view showing the state in which the casing pipe remains after auger excavation, Figures 4 and 5 are cross-sectional views showing the replacement of the casing pipe, and Figures 6 and 7 are Fig. 8 is an explanatory diagram showing the state of concrete placement; Fig. 9 is a sectional view taken along the line ■-■ in Fig. 8; Figs. 10 and 11 show the excavation and concrete placement. Figure 12 is an explanatory diagram showing the order of pouring.
Figures 15 to 15 are drawings showing other embodiments of the present invention, in which Figure 13 is a front view of an air hammer drill excavator, and Figure 14 is a front view of an air hammer drill excavator.
This figure and FIG. 15 are cross-sectional views showing the state of excavation of a collapsed layer containing rocks. 12...Casing pipe, 14...Auger, 22
... Collapse layer, 24... Rock layer, 28... Hole wall protection pipe, 30... Air hammer trill, 38...
・Mixer, 42...Pump, 43...Injection pipe. Figure 4 Figure 5 Top C Figure 6 Figure 7 Figure 14 Factor 15
Claims (1)
可能な掘削装置とを用い、前記掘削装置の掘削孔にケー
シングパイプを追従させて孔壁を保護しながら掘削する
同時ケーシング工法により岩盤層に着きするまでの崩壊
層を掘削し、前記ケーシングパイプを地中に残置した状
態で前記掘削装置を回収し、その後前記ケーシングパイ
プ内にエアハンマドリルを挿入して硬質岩盤層を掘削し
、次に掘削孔にセメント及び固、他剤による杭を造成し
、以下掘削孔を一部重複さ−L′C前記同時う一−シン
グエ法から前記杭造成までの作業を繰返して連続杭を造
成することを特徴とする岩盤1腎の連続杭造成方法。Using a casing pipe and a drilling device that can pass through the inside of the casing pipe, the casing pipe follows the excavation hole of the drilling device and excavates while protecting the hole wall, until reaching the bedrock layer. The collapsed layer is excavated, the drilling equipment is recovered with the casing pipe left underground, and then an air hammer drill is inserted into the casing pipe to excavate the hard rock layer, and then cement and A rock mass characterized in that a continuous pile is created by creating piles using hardening and other agents, and repeating the operations from the above-mentioned simultaneous method to the above-mentioned pile creation by partially overlapping the excavated holes. 1. Continuous pile construction method for one kidney.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP22820683A JPS60119816A (en) | 1983-12-02 | 1983-12-02 | Formation of continuous pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP22820683A JPS60119816A (en) | 1983-12-02 | 1983-12-02 | Formation of continuous pile |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS60119816A true JPS60119816A (en) | 1985-06-27 |
JPS6332930B2 JPS6332930B2 (en) | 1988-07-01 |
Family
ID=16872853
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP22820683A Granted JPS60119816A (en) | 1983-12-02 | 1983-12-02 | Formation of continuous pile |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS60119816A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62206119A (en) * | 1986-03-05 | 1987-09-10 | Okumura Constr Co Ltd | Construction of continuous cut-off wall |
JP2002047647A (en) * | 2000-08-03 | 2002-02-15 | Nkk Corp | Steel pipe pile and executing method therefor |
CN102002943A (en) * | 2010-10-11 | 2011-04-06 | 昆明捷程桩工有限责任公司 | Construction method of rock-socketed secant filling pile |
JP2016079568A (en) * | 2014-10-10 | 2016-05-16 | 株式会社竹中工務店 | Construction method of underground continuous wall |
CN111335306A (en) * | 2020-03-19 | 2020-06-26 | 中铁六局集团有限公司 | Rapid construction method for deep and thick hard rock section drilled pile |
JP2020169455A (en) * | 2019-04-02 | 2020-10-15 | 株式会社丸徳基業 | Construction method of soil cement continuous wall |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS51125912A (en) * | 1975-04-17 | 1976-11-02 | Seiko Kogyo Kk | Sheathing wall construction method |
JPS5898521A (en) * | 1981-12-09 | 1983-06-11 | Takenaka Komuten Co Ltd | Constructing method for pier |
-
1983
- 1983-12-02 JP JP22820683A patent/JPS60119816A/en active Granted
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS51125912A (en) * | 1975-04-17 | 1976-11-02 | Seiko Kogyo Kk | Sheathing wall construction method |
JPS5898521A (en) * | 1981-12-09 | 1983-06-11 | Takenaka Komuten Co Ltd | Constructing method for pier |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62206119A (en) * | 1986-03-05 | 1987-09-10 | Okumura Constr Co Ltd | Construction of continuous cut-off wall |
JP2002047647A (en) * | 2000-08-03 | 2002-02-15 | Nkk Corp | Steel pipe pile and executing method therefor |
CN102002943A (en) * | 2010-10-11 | 2011-04-06 | 昆明捷程桩工有限责任公司 | Construction method of rock-socketed secant filling pile |
JP2016079568A (en) * | 2014-10-10 | 2016-05-16 | 株式会社竹中工務店 | Construction method of underground continuous wall |
JP2020169455A (en) * | 2019-04-02 | 2020-10-15 | 株式会社丸徳基業 | Construction method of soil cement continuous wall |
CN111335306A (en) * | 2020-03-19 | 2020-06-26 | 中铁六局集团有限公司 | Rapid construction method for deep and thick hard rock section drilled pile |
Also Published As
Publication number | Publication date |
---|---|
JPS6332930B2 (en) | 1988-07-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS60119816A (en) | Formation of continuous pile | |
KR20050040044A (en) | Ground boring method using double rock excavation | |
GB2154630A (en) | Construction method for foundation piling | |
JP3165997B2 (en) | Casting method and equipment for sheet piles | |
JP2822687B2 (en) | Excavation method | |
JP2001271365A (en) | Construction method for underground structure | |
JP2006083573A (en) | All casing method and its apparatus | |
JPS5827366B2 (en) | Head reinforcement pile construction equipment | |
JPH03257215A (en) | Pile constructing method | |
JPH0421013B2 (en) | ||
GB2137678A (en) | Method and apparatus for pile construction | |
JP2924355B2 (en) | Construction method of pile body | |
JP3052195B2 (en) | Drilling method and equipment for large diameter pits | |
JPS6013118A (en) | Pile erection work and excavation head for forming consolidated perforated wall therefor | |
JP2000355941A (en) | Building and its construction method | |
JP2002167759A (en) | Execution method of foundation pile | |
JPH0442493B2 (en) | ||
JP2006009468A (en) | Driving method of inner excavation type steel pipe sheet pile and the steel pipe sheet pile used therefor | |
JP3099041B2 (en) | Pile construction method | |
JPS62206119A (en) | Construction of continuous cut-off wall | |
JPS5894598A (en) | Level drilling method and drill guide used therein | |
JP2006037491A (en) | Expanded head pile and construction method of expanded head pile | |
JP2002047648A (en) | Cast-in-place concrete pile construction method | |
JPS63289114A (en) | Head for drill casing | |
JPH0247498A (en) | Construction of tunnel |