JPS5894598A - Level drilling method and drill guide used therein - Google Patents

Level drilling method and drill guide used therein

Info

Publication number
JPS5894598A
JPS5894598A JP19160181A JP19160181A JPS5894598A JP S5894598 A JPS5894598 A JP S5894598A JP 19160181 A JP19160181 A JP 19160181A JP 19160181 A JP19160181 A JP 19160181A JP S5894598 A JPS5894598 A JP S5894598A
Authority
JP
Japan
Prior art keywords
drill
drilling
tunnel
long pipe
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP19160181A
Other languages
Japanese (ja)
Other versions
JPS6229597B2 (en
Inventor
小野 開司
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SANKAI ROTSUKU KOGYO KK
Original Assignee
SANKAI ROTSUKU KOGYO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SANKAI ROTSUKU KOGYO KK filed Critical SANKAI ROTSUKU KOGYO KK
Priority to JP19160181A priority Critical patent/JPS5894598A/en
Publication of JPS5894598A publication Critical patent/JPS5894598A/en
Publication of JPS6229597B2 publication Critical patent/JPS6229597B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 本発明は発破を使用しない無振動の掘削を可能とした主
として都市部における坑道掘削方法及びそれに用いる穿
孔ガイドの構造に関するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for excavating shafts, mainly in urban areas, which enables vibration-free excavation without using blasting, and a structure of a drilling guide used therein.

都市部における地下道、地下鉄トンネル、地下下水道、
地下ケープA/)ンネルなどのトンネル、電柱等の埋設
竪坑などの掘削は、ビμや人家などの建造物への影響あ
るいは人体への危害を少なくするために、発破作業によ
ることが極めて困難であり、、また、さく号機や発破作
業による場合は掘削道の壁面にも多数のクラックが入り
、通常はコンクリート覆工や支保工を設置しないと掘進
することが困難な場合が多い。
Underground passages, subway tunnels, underground sewers in urban areas,
Underground Cape A/) It is extremely difficult to excavate tunnels such as tunnels, underground shafts such as utility poles, etc. by blasting in order to reduce the impact on buildings such as buildings and houses, and to reduce the risk of harm to the human body. Yes, and in the case of drilling or blasting, many cracks appear on the walls of the excavation road, and it is often difficult to excavate without installing concrete lining or shoring.

本発明は、従来の発破による掘削に代る無振動掘削につ
いて種々検討の結果開発したもので、穿孔・亀裂・破砕
の繰返しによる掘削を基本とするものである。更に詳し
くは、トンネル、竪坑等の坑道の掘削面にドリル穿孔の
多数連続体で坑道の形を抜き、穿孔連続体で囲まれた小
区画内の適当部位にもドIJ /7穿孔すると共に、そ
の孔内部にロックスプリッタ、ブレーカー又は膨張剤を
挿入して前記小区画毎に亀裂・破砕して掘削することを
特徴とする。ここでドリル穿孔の多数連続体はトリμ穿
孔位置を順次ずらせながら行うが、隣接する穴を間断な
く連続させることは穿孔技術上極めて困難ヤある。そこ
で、穿孔連続体を容易に形成する。ためのアタッチメン
トとなるドリル穿孔ガイドをも開発したのである。
The present invention was developed as a result of various studies regarding vibration-free excavation as an alternative to conventional excavation by blasting, and is based on excavation by repeated drilling, cracking, and crushing. More specifically, the shape of the tunnel is extracted from the excavated surface of a shaft such as a tunnel or a shaft by a series of multiple drill holes, and the IJ/7 is also drilled at appropriate locations within the small section surrounded by the series of drill holes. The method is characterized in that a rock splitter, breaker, or expansion agent is inserted into the hole to crack and crush each of the small sections for excavation. Here, a large number of consecutive drill holes are performed while sequentially shifting the tri-μ drilling positions, but it is extremely difficult in terms of drilling technology to make adjacent holes consecutive without any interruption. Therefore, a continuous perforation body is easily formed. They also developed a drill hole guide that serves as an attachment for this purpose.

以下、図面によって本発明を具体的かつ詳細に説明する
Hereinafter, the present invention will be explained specifically and in detail with reference to the drawings.

第1図はトンネル掘削面を示す正面図、第2図は穿孔ガ
イドの側面図、第3図は同平面図である。
FIG. 1 is a front view showing the tunnel excavation surface, FIG. 2 is a side view of the drilling guide, and FIG. 3 is a plan view thereof.

図から明らかなように、坑道の掘削面外周(1)に沿う
部分にドIJ ffで外周穿孔(2)の連続体を形成し
てトンネルの形を抜き、次いで、掘削トンネル内部に1
図のように十字の内部穿孔(3)の連続体で坑道を数区
画、この倒では4区画に分けて小区画(4)とする畠こ
れらドリル穿孔により形成された外周穿孔(2)と内部
穿孔(3)との連続体で小区画(4)に自由面を形成さ
せるのである。続いて小区画(4)内に1〜数ケ所の独
立穿孔(5)を形成する。ドリル穿孔は、例えば空剣圧
を利用したダウンザホールド1ノルを用いるのが好まし
・く、これにより100〜200m 1N 、深さ10
00〜3000wMの9孔が可能である。
As is clear from the figure, a series of outer circumferential perforations (2) are formed along the outer circumference (1) of the excavated surface of the tunnel using the IJ ff to create a tunnel shape, and then one hole is placed inside the excavated tunnel.
As shown in the figure, the tunnel is divided into several sections with a series of cross-shaped internal drilling holes (3), or in this case, it is divided into four sections to form small sections (4). A free surface is formed in the small section (4) in series with the perforation (3). Subsequently, one to several independent perforations (5) are formed within the small section (4). For drilling, it is preferable to use, for example, a down-the-hold 1Nor using empty sword pressure.
9 holes of 00-3000 wM are possible.

坑道の掘削面外周(1)に沿う外周穿孔(2゛1の連続
性は掘削面に脆弱部分が有為場合等の理由によって部分
的に穿孔を省くことができるので、それ#1ど厳密なも
のでなくてもよいが2、十字に交わる内部穿孔(3)の
連続性は上述した自由面を形成させるうえで重要である
。そのために、第2図及び第3図に示す穿孔ガイドが使
用される。穿孔ガイドは、円孤状凹み部(2)のある長
尺パイプαBとその円孤状凹み部(2)の基部に設けた
真円のドリルガイドIJング0東を本体とする。長尺パ
イプ卸は先に等孔した穴内へ挿入できる太さと長さであ
り、ガイドリング(至)はその内径がドリル径よりやや
大で、ドリルが挿通できるだけの大きさを必要とする。
Peripheral drilling along the outer periphery of the tunnel excavation surface (1) (2) The continuity of 1 can be partially omitted due to reasons such as when there is a weak part on the excavation surface, so it is not strictly necessary such as #1. 2. The continuity of the internal perforations (3) intersecting each other in a cross shape is important in forming the above-mentioned free surface.For this purpose, the perforation guide shown in Figs. 2 and 3 is used. The main body of the drilling guide is a long pipe αB having a circular concave portion (2) and a perfectly circular drill guide IJ provided at the base of the circular concave portion (2). The long pipe has a thickness and length that allows it to be inserted into the previously drilled hole, and the guide ring must have an inner diameter slightly larger than the drill diameter and be large enough to allow the drill to pass through.

ドリル作業に際して、ガイドリングが動くと安定性が悪
いので、長尺バイブQ11内の数ケ所に回り止めパー挿
通穴α菊を設け、その穴から外方へ向って回り止めパー
(ト)を油圧ホイストα呻で突出させて長尺パイプ0υ
を固定し、ガイドリング(至)の位置を安定させ机 以上で穿孔作業を終り、次に穿孔連続体により分割され
た小区画(4)の自由面を利用して亀裂作業に移る。
During drilling, if the guide ring moves, the stability will be poor, so we provided several holes for inserting detents in the long vibrator Q11, and hydraulically inserted the detents outward from the holes. Hoist α makes the long pipe stick out 0υ
is fixed, the position of the guide ring (to) is stabilized, and the drilling work is completed above the desk. Next, the cracking work is started using the free surface of the small section (4) divided by the drilling continuum.

亀裂作業は、前述の独立穿孔(5)に内圧をかけて小区
画毎に亀裂を発生させる。内圧のかけ方は孔の内部から
外方へ物理的に押し広げる方法と、化学的反応による膨
張圧を利用する方法等公知の方法が利用できる。前者の
物理的方法には油圧式ロックスプリッターが好適で、ま
たブレーカ−も使用できる。前者の場合、独立穿孔の内
部へロックヌブリッターのウェッジセット部を挿入し、
ウェッジが油圧シリンダーによへり50トン程の力で押
し出され、独立穿孔(5)の内面にはその10倍以上の
力が加わり、亀裂が入るのである。また、化学的方法に
は、膨張剤として例えば特殊なケイ酸塩を主体とする無
機化合物と特殊な有機化合物からなる商品名「プライス
ター」が利用できる。このような亀裂作業は岩磐が硬い
場合に必要で軟弱な場合は前記小区画、(4)の自由面
付近からブレーカ−により破砕する方法が直ちに採用で
きる。
In the cracking operation, internal pressure is applied to the above-mentioned independent perforations (5) to generate cracks in each small section. As for how to apply internal pressure, known methods can be used, such as a method of physically pushing outward from the inside of the hole, and a method of using expansion pressure caused by a chemical reaction. For the former physical method, a hydraulic lock splitter is suitable, and a breaker can also be used. In the former case, insert the wedge set part of the locking nubrator into the inside of the independent hole,
The wedge is pushed out by a hydraulic cylinder with a force of about 50 tons, and more than 10 times that force is applied to the inner surface of the independent perforation (5), causing cracks to form. Further, in the chemical method, as an expanding agent, for example, the trade name "Plystar", which is made of an inorganic compound mainly consisting of a special silicate and a special organic compound, can be used. Such cracking work is necessary when the rock is hard, but when it is soft, a method of crushing it using a breaker from the vicinity of the free surface of the small section (4) can be immediately adopted.

亀裂の発生した小区画は、次いで破砕作業に移る。破砕
はさく号機やブレーカ−による通常の方法であるから簡
単である。
The cracked parcels are then subjected to crushing operations. Crushing is easy because it is a normal method using a drilling machine or breaker.

本工法による1回の掘削長さは、最初の穿孔深さに近く
、通常1500〜6000sI+ である。破壊完了後
は再び坑道の掘削面外周(1)に沿う部分にドIJ A
/で外周穿孔(2)の連続体を形成し、次いで内部穿孔
(3)の連続体を形成して周囲に自由面を有する小区画
(4)とし、その内部に独立穿孔(5)を形成して油圧
式ロックスプリッター等で小区画(4)に亀裂を入れた
後にさく号機等で破砕除去する作む順次繰返すのである
。したがって、発破を使用しない工法であるから振動も
なく、危険も少いうえに掘削面に亀裂が入らないので、
コンクリート覆工や支保工が不要となるなどの優れた効
果が得られる。
The length of one excavation using this method is close to the initial drilling depth, usually 1500 to 6000 sI+. After the destruction is complete, do IJA again along the outer periphery of the excavated surface (1) of the tunnel.
/ to form a continuum of outer peripheral perforations (2), then a continuum of internal perforations (3) to form a small section (4) with a free surface around it, and an independent perforation (5) inside thereof. Then, cracks are created in the small section (4) using a hydraulic lock splitter, etc., and then the cracks are crushed and removed using a drilling machine, etc., and the process is repeated one after another. Therefore, since the construction method does not use blasting, there is no vibration, there is little danger, and there are no cracks in the excavated surface.
Excellent effects such as eliminating the need for concrete lining or shoring can be obtained.

以下実施例によって更に具体的に本方法を説明する。The present method will be explained in more detail below with reference to Examples.

実施例1 花崗岩磐上ヘコンクリート電柱を直立させる工事におい
て本工法を利用した。
Example 1 This construction method was used in construction to erect a concrete utility pole on top of granite rock.

竪穴は500鯵0.2.57ffであり、ドリルに全長
3m、直径114鯛ダのものを使用し、第2図に示す穿
孔ガイドを用いて8本の穿孔でほぼ外周穿孔の連続体と
なった。次いでその中央に1個の45舅真の独立穿孔を
形成し、油圧式ロックヌプリツタ(全長450m)で割
岩し、ブレーカ−で破砕しながら2.5mに掘ね下げた
。所要時間は、約2時間で穿孔を完了し、亀裂破砕に約
40分を要し、3時間足らずで上記竪穴が完了した。
The diameter of the vertical hole was 0.2.57 ff, and a drill with a total length of 3 m and a diameter of 114 dah was used. Using the drilling guide shown in Figure 2, 8 holes were made to form a continuous series of holes on the periphery. Ta. Next, an independent bore hole with a diameter of 45 mm was formed in the center, and the rock was split with a hydraulic rock nut (total length: 450 m), and the rock was broken down with a breaker to a depth of 2.5 m. The required time was approximately 2 hours to complete the drilling, approximately 40 minutes to break the cracks, and the above-mentioned shaft was completed in less than 3 hours.

この工法では深い竪穴ができるので、巻くコンクリート
量も少なく、安定した電柱を立てることができる。
This construction method allows for the creation of deep pits, so less concrete is needed to wrap the poles, and the poles can be erected more stably.

なお、従来は、最初からブレーカ−を使用し、直径約1
m、深さ約1mの穴にして多量のコンクリート巻きによ
って支持していたのである。
Conventionally, a breaker was used from the beginning, and the diameter was approximately 1
It was a hole about 1 meter deep and supported by a large amount of concrete.

実施例2 第1図に示す高さ2.2 m 、幅2.4 m 、長さ
約60mの人道用トンネルの岩磐掘削に木工法を応用し
た。
Example 2 The woodworking method was applied to the rock excavation of a human tunnel of 2.2 m in height, 2.4 m in width, and about 60 m in length as shown in FIG.

キャタピラ台車に2基のダウンザホールドリルを装着し
、全長3000111のパイロットビットとLCyリー
マ−を併用してリーマ−回転径212mで第2図、第3
図に示す穿孔ガイドによって順次外周穿孔と十字形の内
部穿孔をして4つの小区画に分けてそれぞれ自白面を形
成した。
Two down-the-hole drills are mounted on a caterpillar truck, and a pilot bit with a total length of 3000111 and an LCy reamer is used in conjunction with the reamer rotation diameter of 212 m as shown in Figures 2 and 3.
Using the perforation guide shown in the figure, outer peripheral perforations and cross-shaped internal perforations were sequentially performed to divide the specimen into four small sections, each forming a confession surface.

次いで、各小区画内に1〜3ケ所の100su*、15
00 smの独立穿孔をして、これにウェッジ径951
m、長さ1000mの大型油圧式破壊機(ピッカーHB
B−1000、株式会社山本鉄工所製)の先端を挿入し
て亀裂を発生させ、さく号機で破砕して掘削した。本゛
工法による掘進速度Fi3ff当り約48時間であった
Next, 1 to 3 locations of 100su*, 15
Make an independent hole of 00 sm and insert a wedge diameter of 951 into this.
1,000m long hydraulic breaking machine (Picker HB)
B-1000 (manufactured by Yamamoto Iron Works Co., Ltd.) was inserted to generate a crack, which was then crushed and excavated using a drilling machine. The excavation speed using this construction method was approximately 48 hours per Fi3ff.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はトンネル掘削面を示す正面図、第2図は穿孔ガ
イドの側面図、第6図は藺平面図である。 (1)  坑道の掘削面外周 (2)  外周穿孔(3
)内部穿孔    (4)小区画 (5)独立穿孔    αυ 長尺バイブ■ 円弧状凹
み部  a] ガイドリングα尋 回り止めバー−通穴
 09  回り止めパーαd 油圧ホイスト 以  上 出願人 有限会社 山開ロック工業 代理人弁理士森  廣三部 %2図
FIG. 1 is a front view showing the tunnel excavation surface, FIG. 2 is a side view of the drilling guide, and FIG. 6 is a plan view. (1) Outer circumference of excavated surface of tunnel (2) Perimeter drilling (3
) Internal perforation (4) Small section (5) Independent perforation αυ Long vibrator ■ Arc-shaped concave part a] Guide ring α fathom Rotation bar - Through hole 09 Rotation prevention par αd Hydraulic hoist or more Applicant Yamagai Lock Co., Ltd. Industrial agent patent attorney Hirozo Mori %2 diagram

Claims (1)

【特許請求の範囲】 1 トンネル、竪坑等の坑道の掘削面にドリル穿孔の多
数連続体で自由面を形成し、穿孔連続体で囲まれた小区
画内の適当部位にもドリル穿孔すゐと共に、その孔内部
にロックスプリッタ、ブレーカ−又は膨張剤を挿入して
前記小区画毎に破壊掘削することを特徴とする坑道掘削
方法。 2 穿孔連続体を形成するために、円孤状凹み部のある
長尺パイプと該円孤状凹み部の基部に設けたドリルガイ
ドリングのある穿孔ガイドを使用し、該穿孔ガイドの長
尺パイプを穿孔済穴へ挿入し、ガイドリングにドリルを
挿通しながらドリル穿孔を行う特許請求の範囲第1項記
載の坑道掘削方法。 3 円弧状凹み部のある長尺パイプと該円孤状凹み部の
基部に設けた真円のドリルガイドリングと、前記長尺パ
イプ内数個所の回り止めバー挿通゛穴と、回り止めパー
を長尺パイプから穿孔土中へ突出させる油圧又は空圧ホ
イストとからなることを特徴とする坑道掘削用穿孔ガイ
ド。
[Scope of Claims] 1. A free surface is formed by a series of multiple drill holes on the excavation surface of a mine shaft such as a tunnel or a shaft, and appropriate portions are also drilled at appropriate locations within the small section surrounded by the series of drill holes. A method for excavating a tunnel, characterized in that a rock splitter, breaker, or expansion agent is inserted into the hole and destructive excavation is carried out in each of the small sections. 2. In order to form a continuous drilling body, a long pipe with a circular concave portion and a drilling guide with a drill guide ring provided at the base of the circular concave portion are used, and the long pipe of the boring guide is 2. The method for excavating a tunnel according to claim 1, wherein the drill is inserted into the drilled hole and the drill is inserted through the guide ring. 3. A long pipe with an arc-shaped recess, a perfectly circular drill guide ring provided at the base of the arc-shaped recess, holes for inserting detent bars at several places in the long pipe, and detent bars. A drilling guide for tunnel excavation, characterized by comprising a hydraulic or pneumatic hoist that projects from a long pipe into the drilling soil.
JP19160181A 1981-11-28 1981-11-28 Level drilling method and drill guide used therein Granted JPS5894598A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP19160181A JPS5894598A (en) 1981-11-28 1981-11-28 Level drilling method and drill guide used therein

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP19160181A JPS5894598A (en) 1981-11-28 1981-11-28 Level drilling method and drill guide used therein

Publications (2)

Publication Number Publication Date
JPS5894598A true JPS5894598A (en) 1983-06-04
JPS6229597B2 JPS6229597B2 (en) 1987-06-26

Family

ID=16277346

Family Applications (1)

Application Number Title Priority Date Filing Date
JP19160181A Granted JPS5894598A (en) 1981-11-28 1981-11-28 Level drilling method and drill guide used therein

Country Status (1)

Country Link
JP (1) JPS5894598A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61155589A (en) * 1984-12-27 1986-07-15 太平洋セメント株式会社 Drilling method of rock
WO2015108098A1 (en) * 2014-01-20 2015-07-23 鹿島建設株式会社 Dismantling method
JP2015137454A (en) * 2014-01-20 2015-07-30 鹿島建設株式会社 Demolition method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6467266B2 (en) * 2015-03-31 2019-02-06 サンコーテクノ株式会社 Drilling jig, drilling method and construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61155589A (en) * 1984-12-27 1986-07-15 太平洋セメント株式会社 Drilling method of rock
JPH0319356B2 (en) * 1984-12-27 1991-03-14 Onoda Cement Co Ltd
WO2015108098A1 (en) * 2014-01-20 2015-07-23 鹿島建設株式会社 Dismantling method
JP2015137454A (en) * 2014-01-20 2015-07-30 鹿島建設株式会社 Demolition method

Also Published As

Publication number Publication date
JPS6229597B2 (en) 1987-06-26

Similar Documents

Publication Publication Date Title
JPH08170484A (en) Construction method of large cross section tunnel
JPH06212870A (en) Cement soil device of underground drill
CN110374091A (en) A kind of rectangle friction pile mechanical hole building construction method
JP2007332559A (en) Removal method for existing underground pile
KR20050040044A (en) Ground boring method using double rock excavation
JPS5894598A (en) Level drilling method and drill guide used therein
JP4253801B2 (en) Tunnel construction method
JP2846227B2 (en) Tunnel excavation method
JPH07229386A (en) Excavation method for tunnel of flat and large cross section
RU2059815C1 (en) Method for mining of steeply dipping underground formations
JPS60119816A (en) Formation of continuous pile
RU2059073C1 (en) Method for development of mineral deposits
JP2004218378A (en) Removing method for existing pile
JP3052195B2 (en) Drilling method and equipment for large diameter pits
JP2006057258A (en) Removal method for foundation pile
JPH05171654A (en) Execution construction of landslid protection pile and execution method
JPH08165895A (en) Excavating method for large-cross section tunnel
JPH06346699A (en) Excavation method of underground space
JP2002167759A (en) Execution method of foundation pile
JPS6124511B2 (en)
JP2000145354A (en) Deep foundation excavation method in bedrock
JPS63289114A (en) Head for drill casing
JP2675858B2 (en) Vertical shaft excavation method
JPS6141832Y2 (en)
JPH0319356B2 (en)