JP6302288B2 - Formwork installation method, formwork and underwater structure - Google Patents

Formwork installation method, formwork and underwater structure Download PDF

Info

Publication number
JP6302288B2
JP6302288B2 JP2014041760A JP2014041760A JP6302288B2 JP 6302288 B2 JP6302288 B2 JP 6302288B2 JP 2014041760 A JP2014041760 A JP 2014041760A JP 2014041760 A JP2014041760 A JP 2014041760A JP 6302288 B2 JP6302288 B2 JP 6302288B2
Authority
JP
Japan
Prior art keywords
formwork
pile
precast
tubular body
pillar part
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2014041760A
Other languages
Japanese (ja)
Other versions
JP2015166538A (en
Inventor
紀夫 滝口
紀夫 滝口
聰 鈴木
聰 鈴木
研三 藤原
研三 藤原
伸二 北崎
伸二 北崎
悦久 高田
悦久 高田
西尾 章
章 西尾
剛 小倉
剛 小倉
和弘 飯田
和弘 飯田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2014041760A priority Critical patent/JP6302288B2/en
Publication of JP2015166538A publication Critical patent/JP2015166538A/en
Application granted granted Critical
Publication of JP6302288B2 publication Critical patent/JP6302288B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

本発明は、水中に型枠を設置する型枠設置方法、型枠および水中構造物に関する。   The present invention relates to a mold installation method, a mold, and an underwater structure for installing a mold in water.

水中構造物を構築する際、水中に型枠を設置しコンクリートを打設する。型枠の設置方法としては、鋼管杭を水底の岩盤に打設し、隣り合う鋼管杭の間に鋼製型枠を設置することが一般的である(例えば、特許文献1参照)。   When constructing underwater structures, formwork is placed in the water and concrete is placed. As a method for installing the formwork, it is common to place a steel pipe pile on the bedrock of the water bottom, and to install a steel formwork between adjacent steel pipe piles (for example, see Patent Document 1).

特開2001−40630号公報JP 2001-40630 A

しかしながら、水底に杭を打設して鋼製型枠を設置する方法は、水中で型枠を形成することになるためダイバーによる水中作業の工程が多くなり負担が大きい。また型枠全体の剛性も弱くなりがちであり、コンクリートの打設時などに自立が困難で型枠の内部に支保工を必要とすることも多い。   However, the method of placing a pile on the bottom of the water and installing the steel formwork forms a formwork underwater, and therefore the number of underwater work processes by divers increases and the burden is large. In addition, the rigidity of the entire formwork tends to be weak, and it is difficult to stand by itself when placing concrete, and a support work is often required inside the formwork.

本発明は、前述した問題点に鑑みてなされたもので、その目的は、水中作業の軽減が可能であり、型枠が容易に自立可能な型枠設置方法等を提供することである。   The present invention has been made in view of the above-described problems, and an object of the present invention is to provide a mold installation method and the like that can reduce the underwater work and can easily stand the mold.

前述した目的を達成するための第1の発明は、隣り合う型枠パネル同士を、柱部および杭部を上下一体に有する管体の前記柱部により連結して形成されたプレキャスト型枠を、水底の掘削孔に前記杭部を挿入して配置することを特徴とする型枠設置方法である。
第2の発明は、隣り合う型枠パネル同士を、柱部および杭部を有する管体の前記柱部により連結して形成されたプレキャスト型枠を、水底の掘削孔に前記杭部を挿入して配置し、前記杭部は、側面に孔を有し、前記管体の内部からコンクリートを注入し、前記掘削孔内にコンクリートを充填することを特徴とする型枠設置方法である。
The first invention for achieving the above-described object is a precast formwork formed by connecting adjacent formwork panels with the pillar part of the tubular body having the pillar part and the pile part integrally in the vertical direction , It is a formwork installation method characterized by inserting and placing the pile portion in a drilling hole in the bottom of the water.
2nd invention inserts the said pile part in the excavation hole of a water bottom for the precast formwork formed by connecting adjacent formwork panels with the said pillar part of the tubular body which has a pillar part and a pile part. The pile portion has a hole on a side surface, injects concrete from the inside of the tubular body, and fills the excavation hole with concrete.

本発明では、予め型枠パネルと管体により組み立てたプレキャスト型枠を、管体の杭部を水底の掘削孔に挿入して設置することでダイバーによる水中作業の軽減が可能である。プレキャスト型枠は型枠パネルと管体により強固に組み立てることができ、杭部の長さを適切に定めることで、容易に自立させることが可能である。   In the present invention, it is possible to reduce the underwater work by the diver by installing the precast formwork assembled in advance with the formwork panel and the pipe by inserting the pile portion of the pipe into the excavation hole in the bottom of the water. The precast formwork can be firmly assembled by the formwork panel and the tube, and can be easily made independent by appropriately determining the length of the pile portion.

第2の発明では、前記杭部は、側面に孔を有し、前記管体の内部からコンクリートを注入し、前記掘削孔内にコンクリートを充填することにより、杭部を介してコンクリートを掘削孔に充填することで、プレキャスト型枠の根固めを行い確実に自立させることができる。 In the second aspect of the invention, the pile portion has a hole in the side surface, by injecting concrete from the interior of the tubular body, by filling concrete into the excavation hole, borehole concrete through the pile portion By filling in, the precast formwork can be solidified and reliably become independent.

前記柱部の下端部に仮受け治具が設けられ、前記掘削孔に、側面に孔を有する鞘管が配置され、前記鞘管は、前記水底から上端部が突出し、前記プレキャスト型枠の設置時に、前記杭部を前記鞘管に挿入し、前記仮受け治具を前記鞘管で支持することが望ましい。
これにより、鞘管で仮受け治具を支持してプレキャスト型枠を位置決めし、水底に不陸がある場合にも水平に設置できる。また鞘管により掘削孔を保護でき、杭部の挿入も容易である。
A temporary receiving jig is provided at a lower end portion of the pillar portion, and a sheath tube having a hole on a side surface is disposed in the excavation hole, and the upper end portion of the sheath tube projects from the water bottom, and the precast formwork is installed. Sometimes it is desirable to insert the pile portion into the sheath tube and support the temporary receiving jig with the sheath tube.
Accordingly, the temporary casting jig is supported by the sheath tube to position the precast formwork, and can be installed horizontally even when the bottom of the water is uneven. Further, the excavation hole can be protected by the sheath tube, and the pile portion can be easily inserted.

前記型枠パネルにスカート材が設けられ、前記プレキャスト型枠の設置時に、前記型枠と前記型枠の設置面との間の隙間を前記スカート材により塞ぐことが望ましい。
これにより、プレキャスト型枠と設置面との間に隙間が形成される場合でも、この隙間をスカート材により塞ぎ、型枠内部にコンクリートを好適に打設できる。
It is preferable that a skirt material is provided on the formwork panel, and a gap between the formwork and the installation surface of the formwork is closed by the skirt material when the precast formwork is installed.
Thereby, even when a gap is formed between the precast formwork and the installation surface, the gap can be closed with the skirt material, and concrete can be suitably placed inside the formwork.

前記型枠パネルは、鋼板に補強材を取り付けたものであることが望ましい。
これにより、型枠パネルの剛性を高めることができる。
The formwork panel is preferably a steel plate provided with a reinforcing material.
Thereby, the rigidity of a formwork panel can be improved.

前記プレキャスト型枠を、緊締材を用いて側方の設置面に緊締することが望ましい。
緊締材により、コンクリートの打設時などに型枠に作用する水平力を分散させ、設置面に負担させることができる。
It is desirable to fasten the precast form to the lateral installation surface using a fastening material.
The tightening material can disperse the horizontal force acting on the formwork when placing concrete, for example, and load it on the installation surface.

第3の発明は、隣り合う型枠パネル同士を、柱部および杭部を有する管体の前記柱部により連結して形成されたプレキャスト型枠を、水底の掘削孔に前記杭部を挿入して配置し、前記管体の上端部に、皿状部と、前記皿状部の上の前記皿状部より径の小さい筒状部とが設けられ、前記プレキャスト型枠の上に、隣り合う型枠パネル同士を、下端部の内部に受け具を有する管体により連結して形成されたプレキャスト型枠を、前記筒状部で前記受け具を支持して設置し、前記皿状部と、前記筒状部の外側とに充填材を充填することを特徴とする型枠設置方法である
これにより、必要な高さに応じてプレキャスト型枠を積み上げて設置でき、上部のプレキャスト型枠の位置固定も容易にできる。
3rd invention inserts the said pile part in the excavation hole of a water bottom for the precast formwork formed by connecting adjacent formwork panels with the said pillar part of the tubular body which has a pillar part and a pile part. Te was placed, the upper end of the tubular body, and a dish-shaped portion, and the diameters from dish small cylindrical portion on said dish-shaped portion is provided, on the precast mold, adjacent A precast formwork formed by connecting the formwork panels to each other with a tubular body having a receiver inside the lower end portion, supporting the receiver with the tubular portion, and the dish-shaped portion, It is a mold installation method characterized by filling a filler into the outside of the cylindrical part.
Thereby, the precast formwork can be stacked and installed according to the required height, and the position of the upper precast formwork can be easily fixed.

の発明は、水中に設置するプレキャスト型枠であって、隣り合う型枠パネル同士を、柱部および杭部を上下一体に有する管体の前記柱部により連結して形成されたことを特徴とするプレキャスト型枠である。
第5の発明は、水中に設置するプレキャスト型枠であって、隣り合う型枠パネル同士を、柱部および杭部を有する管体の前記柱部により連結して形成され、前記杭部は、側面に孔を有することを特徴とするプレキャスト型枠である。
第6の発明は、水中に設置するプレキャスト型枠であって、隣り合う型枠パネル同士を、柱部および杭部を有する管体の前記柱部により連結して形成され、前記柱部の下端部に、前記管体から外側に突出する仮受け治具が設けられたことを特徴とするプレキャスト型枠である。
第7の発明は、水中に設置するプレキャスト型枠であって、隣り合う型枠パネル同士を、柱部および杭部を有する管体の前記柱部により連結して形成され、前記管体の上端部に、皿状部と、前記皿状部の上の前記皿状部より径の小さい筒状部とが設けられたことを特徴とするプレキャスト型枠である。
4th invention is the precast formwork installed in water, Comprising: Adjacent formwork panels were formed by connecting the pillar part of the tubular body which has a pillar part and a pile part up and down integrally. It is a precast formwork characterized.
5th invention is the precast formwork installed in water, Comprising: Adjacent formwork panels are formed by connecting the pillar part of the tubular body which has a pillar part and a pile part, and the pile part is It is a precast formwork characterized by having a hole on a side surface.
6th invention is the precast formwork installed in water, Comprising: Adjacent formwork panels are connected and formed by the said pillar part of the tubular body which has a pillar part and a pile part, The lower end of the said pillar part A precast formwork characterized in that a temporary receiving jig protruding outward from the tubular body is provided in the part.
7th invention is the precast formwork installed in water, Comprising: Adjacent formwork panels are formed by connecting the pillar part of the tubular body having the pillar part and the pile part, and the upper end of the tubular body The precast mold is characterized in that the plate is provided with a dish-shaped portion and a cylindrical portion having a smaller diameter than the dish-shaped portion on the dish-shaped portion.

記型枠パネルにスカート材が設けられることが望ましい。
前記型枠パネルは、鋼板に補強材を取り付けたものであることが望ましい
It is desirable that the skirt member is provided in front Symbol formwork panels.
The formwork panel is preferably a steel plate provided with a reinforcing material .

の発明は、隣り合う型枠パネル同士を、柱部および杭部を上下一体に有する管体の前記柱部により連結して形成されたプレキャスト型枠が、水底の掘削孔に前記杭部を挿入して配置され、前記プレキャスト型枠内にコンクリートが打設されたことを特徴とする水中構造物である。
第9の発明は、隣り合う型枠パネル同士を、柱部および杭部を有する管体の前記柱部により連結して形成されたプレキャスト型枠が、水底の掘削孔に前記杭部を挿入して配置され、前記プレキャスト型枠内にコンクリートが打設され、前記杭部は、側面に孔を有することを特徴とする水中構造物である。
第10の発明は、隣り合う型枠パネル同士を、柱部および杭部を有する管体の前記柱部により連結して形成されたプレキャスト型枠が、水底の掘削孔に前記杭部を挿入して配置され、前記プレキャスト型枠内にコンクリートが打設され、前記柱部の下端部に、前記管体から外側に突出する仮受け治具が設けられたことを特徴とする水中構造物である。
第11の発明は、隣り合う型枠パネル同士を、柱部および杭部を有する管体の前記柱部により連結して形成されたプレキャスト型枠が、水底の掘削孔に前記杭部を挿入して配置され、前記プレキャスト型枠内にコンクリートが打設され、前記管体の上端部に、皿状部と、前記皿状部の上の前記皿状部より径の小さい筒状部とが設けられたことを特徴とする水中構造物である。
According to an eighth aspect of the present invention, there is provided a precast formwork formed by connecting adjacent formwork panels to each other by the pillar part of a tubular body having a pillar part and a pile part integrally in the vertical direction, and the pile part is formed in a drilling hole in a water bottom The underwater structure is characterized in that concrete is cast in the precast formwork.
According to a ninth aspect of the present invention, a precast formwork formed by connecting adjacent formwork panels to each other with the pillar part of a tubular body having a pillar part and a pile part inserts the pile part into an excavation hole in a water bottom. The underwater structure is characterized in that concrete is placed in the precast formwork, and the pile portion has a hole on a side surface.
In a tenth aspect of the present invention, a precast formwork formed by connecting adjacent formwork panels to each other with the pillar part of a tubular body having a pillar part and a pile part inserts the pile part into an excavation hole in a water bottom. The underwater structure is characterized in that concrete is placed in the precast formwork, and a temporary receiving jig is provided at the lower end portion of the pillar portion so as to protrude outward from the tubular body. .
In an eleventh aspect of the invention, a precast formwork formed by connecting adjacent formwork panels to each other by the pillar part of a tubular body having a pillar part and a pile part inserts the pile part into an excavation hole in a water bottom. The concrete is placed in the precast formwork, and the upper end portion of the tubular body is provided with a dish-shaped portion and a cylindrical portion having a smaller diameter than the dish-shaped portion on the dish-shaped portion. It is an underwater structure characterized by that.

本発明によれば、水中作業の軽減が可能であり、型枠が容易に自立可能な型枠設置方法等を提供することができる。   ADVANTAGE OF THE INVENTION According to this invention, the underwater work can be reduced and the form installation method etc. in which a formwork can become independent easily can be provided.

型枠1を示す図Diagram showing formwork 1 受け部5cを示す図The figure which shows the receiving part 5c 型枠設置方法を示す図Diagram showing how to install the formwork 型枠設置方法を示す図Diagram showing how to install the formwork 型枠設置方法を示す図Diagram showing how to install the formwork 型枠設置方法を示す図Diagram showing how to install the formwork 型枠設置方法を示す図Diagram showing how to install the formwork 型枠1aを示す図The figure which shows the formwork 1a 受け具41を示す図The figure which shows the receptacle 41 型枠設置方法を示す図Diagram showing how to install the formwork 台座10を示す図The figure which shows the base 10 型枠1の緊締を示す図Diagram showing tightening of formwork 1

以下、図面に基づいて、本発明の実施形態について説明する。   Hereinafter, embodiments of the present invention will be described with reference to the drawings.

(1.型枠1)
図1に、本発明の実施形態に係る型枠1(プレキャスト型枠)を示す。図1(a)は型枠1の側面を見た図、図1(b)は図1(a)の線A−Aによる断面図である。図1(c)は型枠1を上から見た図である。
(1. Formwork 1)
FIG. 1 shows a mold 1 (precast mold) according to an embodiment of the present invention. FIG. 1A is a view of the side surface of the mold 1, and FIG. 1B is a cross-sectional view taken along line AA in FIG. FIG.1 (c) is the figure which looked at the formwork 1 from the top.

この型枠1は、ダムの堤体の工事を行う際に、堤体近傍の水底に大規模なコンクリート構造物である台座(水中構造物)を構築するため設置するものとする。上記の台座は、堤体の工事箇所を周囲の水域から締め切る仮締切用の構造体を設置するために用いられる。   This formwork 1 is installed in order to construct a pedestal (underwater structure), which is a large-scale concrete structure, on the bottom of the water near the dam body when the dam body is constructed. The above pedestal is used to install a temporary closing structure that closes the construction site of the levee body from the surrounding water area.

型枠1は、コの字型の平面形状を有し、型枠パネル3、鋼管杭5(管体)、金網27、29(スカート材)等からなる。   The mold 1 has a U-shaped planar shape, and includes a mold panel 3, a steel pipe pile 5 (tube body), a wire mesh 27, 29 (skirt material), and the like.

型枠パネル3は、鋼板3bに水平方向の型鋼3a(補強材)を取付けて補強したものである。型鋼3aは例えばH型鋼とするが、これに限らず、例えばI型鋼などでもよい。本実施形態では複数の型枠パネル3をコの字型に並べて配置する。隣り合う型枠パネル3は、鋼管杭5によって連結される。   The formwork panel 3 is reinforced by attaching a horizontal steel plate 3a (reinforcing material) to the steel plate 3b. The shape steel 3a is, for example, an H shape steel, but is not limited thereto, and may be, for example, an I shape steel. In the present embodiment, a plurality of formwork panels 3 are arranged in a U-shape. Adjacent formwork panels 3 are connected by a steel pipe pile 5.

型枠1のコの字型平面の両端部では、型枠パネル3の側端部が、後述する型枠1の設置時に堤体の壁面に近接するように形成される。ただし、型枠パネル3の側端部は直線状に形成され、壁面の不陸等とは完全に一致しない。   At both ends of the U-shaped plane of the mold 1, the side edges of the mold panel 3 are formed so as to be close to the wall surface of the bank when the mold 1 described later is installed. However, the side edge part of the formwork panel 3 is formed in a straight line shape and does not completely coincide with the unevenness of the wall surface.

鋼管杭5は、柱部5aと杭部5bを上下に有する管体である。柱部5aには上記の型枠パネル3が連結される。杭部5bの先端は尖っており、側面には孔15が設けられる。柱部5aの下端部には、鋼管杭5の外側に突出する仮受け治具17が設けられる。   The steel pipe pile 5 is a pipe body which has the column part 5a and the pile part 5b up and down. The formwork panel 3 is connected to the column portion 5a. The tip of the pile portion 5b is pointed, and a hole 15 is provided on the side surface. A temporary receiving jig 17 that protrudes to the outside of the steel pipe pile 5 is provided at the lower end of the column portion 5a.

鋼管杭5の上端部には受け部5cが設けられる。図2は受け部5cの断面を示す図である。受け部5cは、鋼管杭5よりも径が大きい皿状部39bの上に、皿状部39bおよび鋼管杭5よりも径が小さい筒状部39aを設けたものである。   A receiving portion 5 c is provided at the upper end portion of the steel pipe pile 5. FIG. 2 is a view showing a cross section of the receiving portion 5c. The receiving part 5 c is provided with a cylindrical part 39 a having a diameter smaller than that of the dished part 39 b and the steel pipe pile 5 on the dished part 39 b having a diameter larger than that of the steel pipe pile 5.

金網27、29は型枠1に設けられるスカート材である。金網27は型枠パネル3の下端部に設けられる。金網29は、型枠1のコの字型平面の両端部に対応する型枠パネル3の側端部に設けられる。金網27、29には例えば亀甲金網が用いられ、ロール状に巻いた状態で型枠1の内側に取り付けられる。   The metal meshes 27 and 29 are skirt materials provided on the mold 1. The metal mesh 27 is provided at the lower end of the formwork panel 3. The metal mesh 29 is provided at the side end portion of the formwork panel 3 corresponding to both end portions of the U-shaped plane of the formwork 1. For example, a turtle shell metal mesh is used for the metal meshes 27 and 29 and is attached to the inside of the mold 1 in a state of being wound in a roll shape.

(2.型枠設置方法)
次に、本実施形態の型枠設置方法について説明する。本実施形態では、図3に示すように、まず堤体2近傍の水底21の岩盤の適切な位置に掘削孔9を先行して掘削し、掘削孔9に鞘管11を配置する。掘削孔9の平面位置は、型枠1の各鋼管杭5の位置に対応する。
(2. Forming method)
Next, the formwork installation method of this embodiment is demonstrated. In the present embodiment, as shown in FIG. 3, first, the excavation hole 9 is excavated in advance at an appropriate position of the bedrock of the bottom 21 near the dam body 2, and the sheath tube 11 is arranged in the excavation hole 9. The plane position of the excavation hole 9 corresponds to the position of each steel pipe pile 5 of the mold 1.

鞘管11は側面に孔13を有する管体であり、上端部を水底21から突出させる。この突出長さは、水底21の不陸の状態に応じたものとし、各鞘管11の上端の高さが等しく、かつ鞘管11の上端の高さが型枠1の設置箇所で最も水底21が高い箇所以上となるようにする。   The sheath tube 11 is a tube body having a hole 13 on the side surface, and the upper end portion protrudes from the water bottom 21. This projecting length is determined according to the state of the bottom of the water bottom 21, and the height of the upper end of each sheath tube 11 is equal, and the height of the upper end of the sheath tube 11 is the lowest at the installation location of the mold 1. 21 is made higher than the high part.

次いで、水上の台船等にて型枠パネル3と鋼管杭5を組み立てて形成した型枠1を、クレーン等の揚重機(不図示)で吊下ろし、図4に示すように堤体2に沿って水底21に設置する。   Next, the formwork 1 formed by assembling the formwork panel 3 and the steel pipe pile 5 with a surface boat or the like is hung by a lifting machine (not shown) such as a crane, and as shown in FIG. Along the bottom 21 is installed.

型枠1の設置時には、掘削孔9内の鞘管11に鋼管杭5の杭部5bを挿入し、鞘管11で仮受け治具17を支持して型枠1を位置決めし、水平に配置する。前記したように、鞘管11の上端部は、掘削孔9から水底21の不陸の状態に応じた量だけ突出しているため、型枠パネル3の下端部が水底21にぶつかることなく型枠1を配置できる。なお、型枠1の吊下ろし時には鋼管杭5の位置を掘削孔9に合わせるためダイバーによって誘導を行い、この際鋼管杭5の視認性を高めるため杭部5bの先端に白等の着色を施すようにしてもよい。   When installing the mold 1, the pile portion 5 b of the steel pipe pile 5 is inserted into the sheath pipe 11 in the excavation hole 9, the temporary receiving jig 17 is supported by the sheath pipe 11, the mold 1 is positioned, and is disposed horizontally. To do. As described above, the upper end portion of the sheath tube 11 protrudes from the excavation hole 9 by an amount corresponding to the uneven state of the bottom 21, so that the lower end of the form panel 3 does not hit the bottom 21. 1 can be placed. In addition, when the formwork 1 is suspended, guidance is performed by a diver to align the position of the steel pipe pile 5 with the excavation hole 9, and at this time, in order to improve the visibility of the steel pipe pile 5, the tip of the pile portion 5b is colored with white or the like. You may do it.

この後、図5(a)、(b)に示すように、ダイバー作業により金網27を型枠1の外側に広げ、型枠1と水底21との間の隙間に配置する。また同じく金網29を型枠1の外側に広げ、型枠1のコの字型平面の両端部と堤体2の壁面との間の隙間に配置する。こうして、型枠1と型枠1の設置面(水底21および堤体2の壁面)との間の隙間を金網27、29で塞ぐ。   Thereafter, as shown in FIGS. 5A and 5B, the metal net 27 is spread outside the mold 1 by diver work and is arranged in the gap between the mold 1 and the bottom 21. Similarly, the wire mesh 29 is spread outside the formwork 1 and disposed in a gap between the both ends of the U-shaped plane of the formwork 1 and the wall surface of the bank 2. In this way, the gaps between the mold 1 and the installation surface of the mold 1 (the bottom 21 and the wall surface of the bank 2) are closed with the metal meshes 27 and 29.

次に、鋼管杭5の内部にトレミー管を挿入し、鋼管杭5の内部からコンクリートを注入して掘削孔9に充填し、根固めを行う。   Next, a tremy pipe is inserted into the steel pipe pile 5, concrete is injected from the inside of the steel pipe pile 5, the excavation hole 9 is filled, and rooting is performed.

図6(a)、(b)は掘削孔9の水平方向の断面を示す。上記のようにコンクリートを注入すると、図6(a)に示す掘削孔9では、コンクリートが杭部5bの孔15、および鞘管11の孔13を通って外側に滲出し、図6(b)に示すように掘削孔9にコンクリート7が確実に充填される。この状態を図7に示す。なお、杭部5bの孔15、鞘管11の孔13の径は、コンクリート7の最大骨材径よりも大きくしておく。また、コンクリート7としては例えば水中不分離性コンクリートを用いるが、これに限ることはない。   6A and 6B show a cross section of the excavation hole 9 in the horizontal direction. When the concrete is poured as described above, in the excavation hole 9 shown in FIG. 6A, the concrete exudes to the outside through the hole 15 of the pile portion 5b and the hole 13 of the sheath tube 11, and FIG. 6B. As shown in FIG. 3, the concrete is filled in the excavation hole 9 reliably. This state is shown in FIG. In addition, the diameter of the hole 15 of the pile part 5 b and the hole 13 of the sheath tube 11 is set larger than the maximum aggregate diameter of the concrete 7. The concrete 7 is, for example, underwater non-separable concrete, but is not limited thereto.

本実施形態では、以上のようにして1段目の型枠1を設置した後、その上に、さらに図8に示す型枠1a(プレキャスト型枠)を積み上げる。図8(a)は型枠1aの側面を見た図、図8(b)は型枠1aを上から見た図である。   In the present embodiment, after the first-stage mold 1 is installed as described above, the mold 1a (precast mold) shown in FIG. 8 is further stacked thereon. 8A is a view of the side surface of the mold 1a, and FIG. 8B is a view of the mold 1a as viewed from above.

型枠1aは、型枠パネル3と鋼管杭5により型枠1と同様に形成されるが、鋼管杭5の杭部5bや仮受け治具17が省略される点で型枠1と異なる。鋼管杭5の下端部は型枠パネル3の下方に若干突出し、その内部に図9に示す受け具41が設けられる。受け具41は、鋼管杭5の内面から内側に突出する。なお、型枠1aでは、前記の金網27も省略される。   Although the formwork 1a is formed by the formwork panel 3 and the steel pipe pile 5 similarly to the formwork 1, it differs from the formwork 1 in that the pile portion 5b of the steel pipe pile 5 and the temporary receiving jig 17 are omitted. The lower end part of the steel pipe pile 5 protrudes slightly below the formwork panel 3, and the receiving tool 41 shown in FIG. 9 is provided therein. The receiving tool 41 protrudes inward from the inner surface of the steel pipe pile 5. In the mold 1a, the wire mesh 27 is also omitted.

上記の型枠1aも予め水上の台船等にて形成しておき、型枠1の上方からクレーン等の揚重機(不図示)で吊下ろし、図10(a)に示すように型枠1に積み重ねる。前記と同様、金網29を広げて型枠1aのコの字型平面の両端部と堤体2の壁面との間の隙間を塞ぐ。   The above-mentioned form 1a is also formed in advance on a surface boat or the like, suspended from above the form 1 with a lifting machine (not shown) such as a crane, and the form 1 as shown in FIG. 10 (a). Stack on. In the same manner as described above, the wire mesh 29 is widened to close the gap between the both ends of the U-shaped plane of the mold 1 a and the wall surface of the bank 2.

型枠1aの設置時には、図10(b)に示すように、型枠1の鋼管杭5の受け部5cの筒状部39aを型枠1aの鋼管杭5の下端部に挿入し、当該鋼管杭5の受け具41を筒状部39aで支持する。型枠1aの鋼管杭5の下端は皿状部39bの内側に位置する。   At the time of installation of the mold 1a, as shown in FIG. 10 (b), the tubular portion 39a of the receiving portion 5c of the steel pipe pile 5 of the mold 1 is inserted into the lower end of the steel pipe pile 5 of the mold 1a. The support 41 of the pile 5 is supported by the cylindrical portion 39a. The lower end of the steel pipe pile 5 of the formwork 1a is located inside the dish-like portion 39b.

次いで、皿状部39bおよび筒状部39aの外側に充填材として水中不分離性モルタル等のグラウト材43を充填する。本実施形態ではまず皿状部39bにグラウト材43を充填し、その後、型枠1aの鋼管杭5の側面に設けた開閉可能な孔(不図示)を介して筒状部39aの外側にグラウト材43を充填する。   Next, a grout material 43 such as an underwater inseparable mortar is filled as a filler on the outside of the dish-shaped portion 39b and the cylindrical portion 39a. In this embodiment, the dish-shaped portion 39b is first filled with the grout material 43, and then grouted outside the tubular portion 39a through an openable / closable hole (not shown) provided on the side surface of the steel pipe pile 5 of the mold 1a. The material 43 is filled.

本実施形態では、上記のようにして型枠1aが型枠1に固定される。ただし、固定方法はこれに限らない。例えば、型枠1の鋼管杭5の受け部5cに替えて、鋼管杭5の上端部に外側に突出するフランジを設け、また型枠1aの鋼管杭5の受け具41に替えて、鋼管杭5の下端部に同じく外側に突出するフランジを設ける。これらのフランジにはボルト孔を形成しておく。この場合、ボルト孔の位置を合わせてフランジ同士を重ね、ボルトを用いてフランジ同士を接合することで型枠1aを型枠1に固定できる。   In the present embodiment, the mold 1a is fixed to the mold 1 as described above. However, the fixing method is not limited to this. For example, instead of the receiving portion 5c of the steel pipe pile 5 of the formwork 1, a flange projecting outward is provided at the upper end of the steel pipe pile 5, and the steel pipe pile 5 is changed to the support 41 of the steel pipe pile 5 of the formwork 1a. A flange is also provided at the lower end of 5 and projects outward. Bolt holes are formed in these flanges. In this case, the formwork 1a can be fixed to the formwork 1 by matching the positions of the bolt holes, overlapping the flanges, and joining the flanges using bolts.

こうして型枠1、1aを設置した後、型枠1、1a内にコンクリートを打設する。コンクリートには例えば水中不分離性コンクリートを用いるが、これに限ることはない。   After the molds 1 and 1a are thus installed, concrete is placed in the molds 1 and 1a. For example, underwater non-separable concrete is used as the concrete, but it is not limited thereto.

コンクリートが硬化すると、水底21に台座が構築される。図11は型枠1、1a内にコンクリート23を打設して構築した台座10を上から見た図である。本実施形態では型枠1、1aは撤去せず、埋設型枠とする。必要に応じて各型枠1、1aの鋼管杭5の内部にコンクリートを充填してもよい。   When the concrete is hardened, a pedestal is constructed on the bottom 21. FIG. 11 is a top view of the base 10 constructed by placing concrete 23 in the molds 1 and 1a. In this embodiment, the molds 1 and 1a are not removed, but are embedded molds. If necessary, concrete may be filled in the steel pipe piles 5 of the molds 1, 1a.

このように、本実施形態によれば、予め型枠パネル3と鋼管杭5により組み立てた型枠1を、鋼管杭5の杭部5bを水底21の掘削孔9に挿入して設置することでダイバーによる水中作業の軽減が可能である。型枠1は型枠パネル3と鋼管杭5により強固に組み立てることができ、杭部5bの長さを適切に定めることで、容易に自立させることが可能である。また型枠パネル3としては、鋼板3bに補強材である型鋼3aを取り付けて用いるので剛性も高く、これらにより型枠内部の支保工を省略することができ、型枠内部のコンクリートの打設も容易になる。   Thus, according to this embodiment, the mold 1 assembled in advance by the mold panel 3 and the steel pipe pile 5 is installed by inserting the pile portion 5b of the steel pipe pile 5 into the excavation hole 9 of the water bottom 21. It is possible to reduce underwater work by divers. The formwork 1 can be firmly assembled by the formwork panel 3 and the steel pipe pile 5, and can be easily made independent by appropriately determining the length of the pile part 5b. Moreover, as the formwork panel 3, the steel plate 3b is used by attaching the form steel 3a which is a reinforcing material, so that the rigidity is high, so that the support work inside the formwork can be omitted, and the concrete inside the formwork can be placed. It becomes easy.

また、杭部5bは側面に孔15を有し、鋼管杭5の内部からコンクリートを注入して掘削孔9内にコンクリートを充填することで、型枠1の根固めを行い確実に自立させることができる。   Moreover, the pile part 5b has the hole 15 on the side surface, and injects concrete from the inside of the steel pipe pile 5 and fills the excavation hole 9 with concrete, thereby solidifying the formwork 1 and allowing it to stand on its own. Can do.

また、型枠1の設置時には、型枠1の鋼管杭5の仮受け治具17を水底21から突出した鞘管11で支持するので、水底21に不陸があっても型枠1を水平に設置できる。また、鞘管11によって掘削孔9を保護して掘削孔9の崩壊等を防ぐことができ、杭部5bの挿入も容易である。   In addition, when the mold 1 is installed, the temporary receiving jig 17 of the steel pipe pile 5 of the mold 1 is supported by the sheath tube 11 protruding from the water bottom 21, so that the mold 1 can be placed horizontally even if the water bottom 21 is uneven. Can be installed. Further, the excavation hole 9 can be protected by the sheath tube 11 to prevent the excavation hole 9 from collapsing, and the pile portion 5b can be easily inserted.

また、型枠1と設置面との間の隙間は金網27、29により塞ぐので、型枠1を設置面の不陸等に追従させ型枠内部にコンクリートを好適に打設できる。また、金網27、29は型枠1の外側に広げるので、コンクリートの断面欠損も生じない。   In addition, since the gap between the mold 1 and the installation surface is closed by the metal meshes 27 and 29, the mold 1 can follow the unevenness of the installation surface and the concrete can be suitably placed inside the mold. Moreover, since the metal nets 27 and 29 are spread outside the mold 1, there is no cross-sectional defect of the concrete.

なお、スカート材としては金網27、29の代わりに繊維等によるジオグリッドやジオテキスタイルなども用いることができる。ただし、金網27、29は適度な剛性を有するので、水中での設置等が容易にできる利点がある。   As the skirt material, a geogrid or geotextile made of fibers or the like can be used in place of the wire nets 27 and 29. However, since the metal meshes 27 and 29 have appropriate rigidity, there is an advantage that the installation in the water can be easily performed.

さらに、本実施形態では、型枠1の上に型枠1aを積み上げ、この際、前記のように型枠1aの鋼管杭5の受け具41を型枠1の鋼管杭5の筒状部39aで支持し、皿状部39bおよび筒状部39aの外側にグラウト材43を充填する。こうして、必要な高さに応じて型枠1aを積み上げて設置でき、かつボルト接合時のような高精度の型枠1aの位置合わせも不要で型枠1aの位置固定が容易にできる。   Furthermore, in this embodiment, the formwork 1a is piled up on the formwork 1, and at this time, the receiving part 41 of the steel pipe pile 5 of the formwork 1a is used as described above, and the tubular portion 39a of the steel pipe pile 5 of the formwork 1 is used. The grout material 43 is filled on the outside of the dish-like portion 39b and the cylindrical portion 39a. In this way, the mold 1a can be stacked and installed according to the required height, and the position of the mold 1a can be easily fixed without requiring high-precision alignment of the mold 1a as in the case of bolting.

なお、本実施形態では、コの字型平面の型枠1を例示したが、型枠の形状はこれに限ることはなく、水中構造物の形状や設置箇所に応じて適切に定めることができる。また、型枠1の適用対象も、上記した台座10の構築時に限らず、各種の水中構造物の構築時に適用できる。その例として、水底の橋脚基部や、海岸から離れて設置する離岸堤の基部等の構築時にコンクリートを打設するようなケースにも適用できる。   In addition, in this embodiment, although the U-shaped plane formwork 1 was illustrated, the shape of the formwork is not limited to this, and can be appropriately determined according to the shape and installation location of the underwater structure. . Further, the application target of the mold 1 is not limited to when the pedestal 10 is constructed, but can be applied when various underwater structures are constructed. As an example, the present invention can be applied to a case in which concrete is placed at the time of construction such as a pier base at the bottom of a water bottom or a base of a breakwater installed away from the coast.

また、本実施形態では型枠1、1aを2段に積み上げたが、これに限ることはない。前記と同様にして型枠1aを順次積み上げることで、必要な高さまで型枠を任意の複数段積み上げることが可能である。あるいは1段目の型枠1のみ設置するようなケースも考えられる。最上段の型枠については前記の受け部5cを省略することも可能である。   Moreover, although the formwork 1 and 1a were piled up in two steps in this embodiment, it does not restrict to this. By sequentially stacking the molds 1a in the same manner as described above, it is possible to stack any number of molds to a required height. Alternatively, a case where only the first-stage formwork 1 is installed is also conceivable. The receiving portion 5c can be omitted for the uppermost formwork.

さらに、必要に応じて、図12に示すように堤体2の壁面にアンカ45を設け、該アンカ45に連結したターンバックル47(緊締材)の端部を型枠1に取り付けて型枠1を堤体2に緊締してもよい。図では1段目の型枠1を緊締する例を示したが、2段目以降の型枠1aも同様にして緊締可能である。これにより、コンクリートの打設時などに型枠に作用する水平力を分散させ、堤体2に負担させることができる。   Further, as shown in FIG. 12, an anchor 45 is provided on the wall surface of the bank body 2 as required, and an end of a turn buckle 47 (tightening material) connected to the anchor 45 is attached to the mold 1 to form the mold 1 May be fastened to the dam body 2. In the drawing, an example in which the first-stage mold 1 is fastened is shown, but the second-stage and subsequent molds 1a can be fastened in the same manner. Thereby, the horizontal force which acts on a formwork at the time of placement of concrete, etc. can be disperse | distributed, and the dam body 2 can be borne.

以上、添付図を参照しながら、本発明の実施形態を説明したが、本発明の技術的範囲は、前述した実施形態に左右されない。当業者であれば、特許請求の範囲に記載された技術的思想の範疇内において各種の変更例または修正例に想到し得ることは明らかであり、それらについても当然に本発明の技術的範囲に属するものと了解される。   As mentioned above, although embodiment of this invention was described referring an accompanying drawing, the technical scope of this invention is not influenced by embodiment mentioned above. It is obvious for those skilled in the art that various modifications or modifications can be conceived within the scope of the technical idea described in the claims, and these are naturally within the technical scope of the present invention. It is understood that it belongs.

1、1a………型枠
2………堤体
3………型枠パネル
3a………型鋼
3b………鋼板
5………鋼管杭
5a………柱部
5b………杭部
7………コンクリート
9………掘削孔
11………鞘管
13、15………孔
17………仮受け治具
21………水底
27、29………金網
DESCRIPTION OF SYMBOLS 1, 1a ......... Formwork 2 ......... Body 3 ......... Formwork panel 3a ......... Steel 3b ......... Steel 5 ......... Pipe pile 5a ......... Column part 5b ......... Pile part 7 ……… Concrete 9 ……… Drilling hole 11 ……… Sheath tube 13, 15 ……… Hole 17 ……… Temporary receiving jig 21 ……… Water bottom 27, 29 ……… Wire mesh

Claims (14)

隣り合う型枠パネル同士を、柱部および杭部を上下一体に有する管体の前記柱部により連結して形成されたプレキャスト型枠を、
水底の掘削孔に前記杭部を挿入して配置することを特徴とする型枠設置方法。
A precast formwork formed by connecting adjacent formwork panels with the pillar part of the tubular body integrally having a pillar part and a pile part.
A method for installing a form, characterized in that the pile portion is inserted into a drilling hole in the bottom of the water.
隣り合う型枠パネル同士を、柱部および杭部を有する管体の前記柱部により連結して形成されたプレキャスト型枠を、
水底の掘削孔に前記杭部を挿入して配置し、
前記杭部は、側面に孔を有し、
前記管体の内部からコンクリートを注入し、前記掘削孔内にコンクリートを充填することを特徴とする型枠設置方法。
A precast formwork formed by connecting adjacent formwork panels with the pillar part of the tubular body having a pillar part and a pile part,
Insert and place the pile into the drilling hole in the bottom of the water ,
The pile portion has a hole on a side surface,
A method for installing a form , wherein concrete is poured from the inside of the tubular body, and the concrete is filled into the excavation hole .
前記柱部の下端部に仮受け治具が設けられ、
前記掘削孔に、側面に孔を有する鞘管が配置され、
前記鞘管は、前記水底から上端部が突出し、
前記プレキャスト型枠の設置時に、前記杭部を前記鞘管に挿入し、前記仮受け治具を前記鞘管で支持することを特徴とする請求項2に記載の型枠設置方法。
A temporary receiving jig is provided at the lower end of the column part,
In the excavation hole, a sheath pipe having a hole on a side surface is arranged,
The sheath tube has an upper end protruding from the water bottom,
3. The mold installation method according to claim 2, wherein the pile portion is inserted into the sheath pipe and the temporary receiving jig is supported by the sheath pipe when the precast mold is installed.
前記型枠パネルにスカート材が設けられ、
前記プレキャスト型枠の設置時に、前記プレキャスト型枠と前記プレキャスト型枠の設置面との間の隙間を前記スカート材により塞ぐことを特徴とする請求項1から請求項3のいずれかに記載の型枠設置方法。
A skirt material is provided on the formwork panel,
At the time of installation of the precast mold, the mold according to claims 1 to claim 3 in which the gap between the precast mold and the precast formwork installation surface, characterized in that blocked by said skirt member Frame installation method.
隣り合う型枠パネル同士を、柱部および杭部を有する管体の前記柱部により連結して形成されたプレキャスト型枠を、
水底の掘削孔に前記杭部を挿入して配置し、
前記管体の上端部に、皿状部と、前記皿状部の上の前記皿状部より径の小さい筒状部とが設けられ、
前記プレキャスト型枠の上に、
隣り合う型枠パネル同士を、下端部の内部に受け具を有する管体により連結して形成されたプレキャスト型枠を、
前記筒状部で前記受け具を支持して設置し、
前記皿状部と、前記筒状部の外側とに充填材を充填することを特徴とする型枠設置方法。
A precast formwork formed by connecting adjacent formwork panels with the pillar part of the tubular body having a pillar part and a pile part,
Insert and place the pile into the drilling hole in the bottom of the water ,
The upper end of the tubular body is provided with a dish-shaped part and a cylindrical part having a smaller diameter than the dish-shaped part on the dish-shaped part,
On the precast formwork,
A precast formwork formed by connecting adjacent formwork panels to each other with a tubular body having a receptacle inside the lower end,
Supporting the receiver with the tubular part and installing it,
The mold installation method characterized by filling the said plate-shaped part and the outer side of the said cylindrical part with a filler .
水中に設置するプレキャスト型枠であって、
隣り合う型枠パネル同士を、柱部および杭部を上下一体に有する管体の前記柱部により連結して形成されたことを特徴とするプレキャスト型枠。
A precast formwork to be installed in the water,
A precast formwork formed by connecting adjacent formwork panels to each other by the pillar part of a tubular body having a pillar part and a pile part integrally in the vertical direction .
水中に設置するプレキャスト型枠であって、
隣り合う型枠パネル同士を、柱部および杭部を有する管体の前記柱部により連結して形成され
前記杭部は、側面に孔を有することを特徴とするプレキャスト型枠。
A precast formwork to be installed in the water,
It is formed by connecting adjacent formwork panels together with the pillar part of the tubular body having the pillar part and the pile part ,
The said pile part has a hole in a side surface, The precast formwork characterized by the above-mentioned .
水中に設置するプレキャスト型枠であって、
隣り合う型枠パネル同士を、柱部および杭部を有する管体の前記柱部により連結して形成され
前記柱部の下端部に、前記管体から外側に突出する仮受け治具が設けられたことを特徴とするプレキャスト型枠。
A precast formwork to be installed in the water,
It is formed by connecting adjacent formwork panels together with the pillar part of the tubular body having the pillar part and the pile part ,
A precast formwork characterized in that a provisional receiving jig protruding outward from the tubular body is provided at a lower end portion of the column portion .
水中に設置するプレキャスト型枠であって、
隣り合う型枠パネル同士を、柱部および杭部を有する管体の前記柱部により連結して形成され
前記管体の上端部に、皿状部と、前記皿状部の上の前記皿状部より径の小さい筒状部とが設けられたことを特徴とするプレキャスト型枠。
A precast formwork to be installed in the water,
It is formed by connecting adjacent formwork panels together with the pillar part of the tubular body having the pillar part and the pile part ,
A precast formwork , wherein an upper end portion of the tubular body is provided with a dish-shaped portion and a cylindrical portion having a smaller diameter than the dish-shaped portion on the dish-shaped portion .
前記型枠パネルにスカート材が設けられたことを特徴とする請求項から請求項のいずれかに記載のプレキャスト型枠。 The precast formwork according to any one of claims 6 to 9 , wherein a skirt material is provided on the formwork panel. 隣り合う型枠パネル同士を、柱部および杭部を上下一体に有する管体の前記柱部により連結して形成されたプレキャスト型枠が、水底の掘削孔に前記杭部を挿入して配置され、
前記プレキャスト型枠内にコンクリートが打設されたことを特徴とする水中構造物。
A precast formwork formed by connecting adjacent formwork panels together with the pillar part of a tubular body having a pillar part and a pile part integrated vertically is arranged by inserting the pile part into an excavation hole in the bottom of the water. ,
An underwater structure characterized in that concrete is cast in the precast formwork.
隣り合う型枠パネル同士を、柱部および杭部を有する管体の前記柱部により連結して形成されたプレキャスト型枠が、水底の掘削孔に前記杭部を挿入して配置され、
前記プレキャスト型枠内にコンクリートが打設され
前記杭部は、側面に孔を有することを特徴とする水中構造物。
A precast formwork formed by connecting adjacent formwork panels with the pillar part of the tubular body having a pillar part and a pile part is arranged by inserting the pile part into a drilling hole in the bottom of the water,
Concrete is cast in the precast formwork ,
The said pile part has a hole in a side surface, The underwater structure characterized by the above-mentioned .
隣り合う型枠パネル同士を、柱部および杭部を有する管体の前記柱部により連結して形成されたプレキャスト型枠が、水底の掘削孔に前記杭部を挿入して配置され、
前記プレキャスト型枠内にコンクリートが打設され
前記柱部の下端部に、前記管体から外側に突出する仮受け治具が設けられたことを特徴とする水中構造物。
A precast formwork formed by connecting adjacent formwork panels with the pillar part of the tubular body having a pillar part and a pile part is arranged by inserting the pile part into a drilling hole in the bottom of the water,
Concrete is cast in the precast formwork ,
An underwater structure characterized in that a temporary receiving jig is provided at the lower end portion of the column portion so as to protrude outward from the tubular body .
隣り合う型枠パネル同士を、柱部および杭部を有する管体の前記柱部により連結して形成されたプレキャスト型枠が、水底の掘削孔に前記杭部を挿入して配置され、
前記プレキャスト型枠内にコンクリートが打設され
前記管体の上端部に、皿状部と、前記皿状部の上の前記皿状部より径の小さい筒状部とが設けられたことを特徴とする水中構造物。
A precast formwork formed by connecting adjacent formwork panels with the pillar part of the tubular body having a pillar part and a pile part is arranged by inserting the pile part into a drilling hole in the bottom of the water,
Concrete is cast in the precast formwork ,
An underwater structure in which an upper end portion of the tubular body is provided with a dish-shaped portion and a cylindrical portion having a smaller diameter than the dish-shaped portion on the dish-shaped portion .
JP2014041760A 2014-03-04 2014-03-04 Formwork installation method, formwork and underwater structure Active JP6302288B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2014041760A JP6302288B2 (en) 2014-03-04 2014-03-04 Formwork installation method, formwork and underwater structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2014041760A JP6302288B2 (en) 2014-03-04 2014-03-04 Formwork installation method, formwork and underwater structure

Publications (2)

Publication Number Publication Date
JP2015166538A JP2015166538A (en) 2015-09-24
JP6302288B2 true JP6302288B2 (en) 2018-03-28

Family

ID=54257523

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014041760A Active JP6302288B2 (en) 2014-03-04 2014-03-04 Formwork installation method, formwork and underwater structure

Country Status (1)

Country Link
JP (1) JP6302288B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6647856B2 (en) * 2015-12-22 2020-02-14 株式会社熊谷組 Grout joint structure
CN110707632B (en) * 2019-11-08 2020-11-20 南京聚联输变电安装有限责任公司 Waterproof and leaking stoppage process for cable hole
CN111305146B (en) * 2020-03-13 2022-04-08 东南大学 Method for enhancing safety degree of overall structure of full-straight-pile high-pile wharf convex angle section

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59126821A (en) * 1983-01-10 1984-07-21 Aoki Kensetsu:Kk Erection work of foundation pile
JP2959803B2 (en) * 1990-04-29 1999-10-06 武茂 下ノ原 Formwork panel
JPH0748818A (en) * 1993-08-05 1995-02-21 Mitsui Constr Co Ltd Construction method for structure
JP2868725B2 (en) * 1996-04-09 1999-03-10 株式会社森長組 Seawall repair method
JP3395944B2 (en) * 1996-07-23 2003-04-14 鹿島建設株式会社 Underwater formwork method
JP2000178973A (en) * 1998-12-14 2000-06-27 Taito Seiko Kk Formwork for pouring concrete underwater
JP2002201639A (en) * 2000-12-28 2002-07-19 Nagashima Kogyo:Kk Excavation foot protection liquid filling construction method, and pile pipe for excavation foot protection liquid filling construction method
CN1284908C (en) * 2002-08-02 2006-11-15 陈泽 Underwater building member, its installing and use method

Also Published As

Publication number Publication date
JP2015166538A (en) 2015-09-24

Similar Documents

Publication Publication Date Title
KR20060092552A (en) The non-strut down framework construction method of having used cast in place concrete pile
JP6263864B2 (en) Seawall
JP6302288B2 (en) Formwork installation method, formwork and underwater structure
JP4914062B2 (en) Two-tiered retaining wall and its construction method
JP5229913B2 (en) Slope reinforcement method
JP5309378B2 (en) Self-supporting retaining wall
KR101734026B1 (en) Retaining Wal1 Construction Method Using PHC Pile
JP2008223339A (en) Pile head strengthening method for hollow pile and pile head strengthening reinforcement material
KR101262357B1 (en) Inclined Earth Retaining Structure Method
JP6192972B2 (en) Calvert
KR101210368B1 (en) Uniting Method of Temporary earth wall with basement exterior Wall using Couplers and Bolts.
JP3603130B2 (en) Root-wound reinforcement structure for column bases such as steel columns
KR101296856B1 (en) Reinforcement structure for wall of underground structure and construction method of underground structure using the same
KR20100113957A (en) Joint structure and method for constructing slab of underground structures using the same
JP6461690B2 (en) Foundation structure and foundation construction method
KR102277470B1 (en) Basement Composite Wall Using Retaing Wall And Method for Constructing the Same
JP5432814B2 (en) Construction method of concrete body for septic tank protection
KR102355446B1 (en) Vertical underground structure and method for constructing the same
JPH1077644A (en) Earthquake resisting pile foundation construction method
JP5480745B2 (en) Reinforcement method for existing foundations for structures
KR20100094139A (en) Wall structure and building method of the same
JP5327992B2 (en) Seismic reinforcement structure for existing buildings
JP2011157719A (en) Earth retaining method
JP6792239B2 (en) Scuttling prevention device for steel pipe piles and scuttling prevention method
CN103485365A (en) Installation method of underground concrete wall formwork of row pile supporting structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20161104

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20170719

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20170808

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20170927

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20180227

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20180302

R150 Certificate of patent or registration of utility model

Ref document number: 6302288

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250