CN104563147B - Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation - Google Patents

Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation Download PDF

Info

Publication number
CN104563147B
CN104563147B CN201410434541.5A CN201410434541A CN104563147B CN 104563147 B CN104563147 B CN 104563147B CN 201410434541 A CN201410434541 A CN 201410434541A CN 104563147 B CN104563147 B CN 104563147B
Authority
CN
China
Prior art keywords
pile
epimere
concrete
composite structure
hypomere
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410434541.5A
Other languages
Chinese (zh)
Other versions
CN104563147A (en
Inventor
齐新
卢永成
吴东升
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI URBAN TRANSPORTATION DESIGN INSTITUTE Co.,Ltd.
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201410434541.5A priority Critical patent/CN104563147B/en
Publication of CN104563147A publication Critical patent/CN104563147A/en
Application granted granted Critical
Publication of CN104563147B publication Critical patent/CN104563147B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/50Piles comprising both precast concrete portions and concrete portions cast in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a composite structure pile foundation applied to a karst area. The composite structure pile foundation comprises an upper pile section and a lower pile section and is characterized in that the upper pile section is a concrete tubular pile; the lower pile section is a reinforced concrete filled pile and penetrates through a karst cave in a rock layer; the upper end of the lower pile section stretches into the upper pile section to form the composite structure pile foundation. Compared with the prior art, the composite structure pile foundation has the advantages and effects that the upper pile section body is the concrete tubular pile and can be used as a protection cylinder of the lower filled pile section during construction; the cost of the steel protection cylinder in the conventional method in the prior art can be saved; a reinforcement cage and concrete of the lower filled pile section stretches into the upper tubular pile by a proper length, so that the upper section and the lower section are combined to be an integrated pile body and are jointly stressed; the composite structure pile foundation is convenient and quick to construct.

Description

It is applicable to combinative structure pile foundation and the construction method thereof of karst region
Technical field
The invention belongs to the stake technical field in civil engineering, be specifically related to be applicable to the combinative structure pile foundation of karst region and construction method thereof.
Background technology
When karst area construction building thing bored pile foundation, when boring runs into larger solution cavity, the slurry coat method in often holing runs off rapidly and causes the hole that collapses, and causes any property loss and workmen's injures and deaths, the most also schedule delays.For preventing this type of accident from occurring, it is common practice to squeezing into steel pipe casing as enclosed structure when boring is to scar, this steel pile casting is working measure, and permanent structure stress, it is not intended that it, also cannot be taken out after pile, costly.
Summary of the invention
It is an object of the invention to provide a kind of safe and economical combinative structure pile foundation being applicable to karst region.
For reaching above-mentioned purpose, the technical solution used in the present invention is as follows: be applicable to the combinative structure pile foundation of karst region, including epimere stake and hypomere stake, it is characterized in that: epimere stake is concrete tubular pile, hypomere stake is deposited reinforced concrete pile, hypomere stake, through the solution cavity in rock stratum, becomes combinative structure pile foundation in epimere stake is stretched in hypomere stake upper end.
In technique scheme, epimere concrete tubular pile has reinforced concrete pipe pile, prestressed concrete pipe pile.
In technique scheme, epimere concrete tubular pile is positioned in soil layer.
In technique scheme, epimere concrete tubular pile is precast construction, cast-in-place structural.
In technique scheme, hypomere solid pile is boring, punching, manually digging hole filling pile.
It is another object of the present invention to the construction method of a kind of safe and economical combinative structure pile foundation being applicable to karst region.
In order to achieve the above object, technical scheme is as follows: be applicable to the construction method of the combinative structure pile foundation of karst region, it is characterised in that the method comprises the following steps: A, epimere concrete tubular pile of constructing in overlying soil;B, utilize described concrete tubular pile as casing, hypomere deposited reinforced concrete pile of constructing, make described deposited reinforced concrete pile through the solution cavity in rock stratum, and the upper end of described hypomere deposited reinforced concrete pile is stretched in epimere concrete tubular pile.
The present invention compared with prior art has following advantages and effect: epimere pile body is concrete tubular pile, can also serve as the casing of construction hypomere bored concrete pile when construction, save the steel pile casting expense in current conventional method.Hypomere filling pile cage of reinforcement and concrete all stretch into epimere pile tube suitable length, make upper and lower section to be combined into a common stress of overall pile body, easy construction, quick.The effect of steel pile casting is replaced by the present invention with concrete tubular pile, and this concrete tubular pile can be combined into the common stress of permanent structure with the bored concrete pile constructed below again simultaneously, is therefore a kind of economical and practical piling strtucture, and economic benefit will be apparent upon.
Accompanying drawing explanation
Fig. 1 is pile foundation construction schematic flow sheet.
Fig. 2 is pile foundation organigram.
Detailed description of the invention
The present invention is described in further detail below in conjunction with the accompanying drawings.
See Fig. 1, Fig. 2, epimere stake-concrete tubular pile 4 of first constructing in overlying soil 1.The concrete tubular pile that sinking again of can first holing is prefabricated, it would however also be possible to employ cast-in-place method construction concrete tubular pile.Construct again hypomere stake, first carry out boring (rush, dig) hole 5, through the solution cavity 3 in rock stratum 2, after reaching designed elevation, transferring steel reinforcement cage and concrete perfusion, complete the construction of hypomere bored concrete pile 6, two sections of pile foundations have the adapter section 7 of suitable length to be combined as overall common stress.
Epimere concrete tubular pile can be reinforced concrete pipe pile, prestressed concrete pipe pile.Epimere concrete tubular pile is precast construction, cast-in-place structural.Hypomere stake is boring, punching, manually digging hole deposited reinforced concrete pile.

Claims (4)

1. it is applicable to the combinative structure pile foundation of karst region, including epimere stake and hypomere stake, it is characterized in that: epimere stake is concrete tubular pile, hypomere stake is deposited reinforced concrete pile, hypomere stake is through the solution cavity in rock stratum, becoming combinative structure pile foundation in epimere stake is stretched in hypomere stake upper end, upper and lower section of stake is combined into a common stress of overall pile body.
2. according to the combinative structure pile foundation described in claim 1, it is characterised in that: epimere concrete tubular pile is reinforced concrete pipe pile or prestressed concrete pipe pile.
3. according to the combinative structure pile foundation described in claim 1 or 2, it is characterised in that: epimere concrete tubular pile is precast construction or cast-in-place structural.
4. it is applicable to the construction method of the combinative structure pile foundation of karst region, it is characterised in that the method comprises the following steps: A, epimere concrete tubular pile of constructing in overlying soil;B, utilize described epimere concrete tubular pile as casing, construction hypomere deposited reinforced concrete pile, make described hypomere deposited reinforced concrete pile through the solution cavity in rock stratum, and the upper end of described hypomere deposited reinforced concrete pile stretches in epimere concrete tubular pile, epimere concrete tubular pile and hypomere deposited reinforced concrete pile is made to be combined into a common stress of overall pile body.
CN201410434541.5A 2014-08-29 2014-08-29 Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation Active CN104563147B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410434541.5A CN104563147B (en) 2014-08-29 2014-08-29 Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410434541.5A CN104563147B (en) 2014-08-29 2014-08-29 Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation

Publications (2)

Publication Number Publication Date
CN104563147A CN104563147A (en) 2015-04-29
CN104563147B true CN104563147B (en) 2017-01-11

Family

ID=53080159

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410434541.5A Active CN104563147B (en) 2014-08-29 2014-08-29 Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation

Country Status (1)

Country Link
CN (1) CN104563147B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6539566B2 (en) * 2015-10-29 2019-07-03 大亜ソイル株式会社 Construction method of cast-in-place concrete pile
CN105714772B (en) * 2016-02-22 2018-04-03 北龙建设集团有限公司 Karst area embedded rock pile pore-forming bores concrete dado method again
CN107339122B (en) * 2017-08-31 2020-02-11 徐州中国矿大岩土工程新技术发展有限公司 Construction method for treating goaf by steel pipe column
CN107859036B (en) * 2017-10-26 2019-10-11 湖北工业大学 A kind of in-situ deposited prefabricated composite structure stake and its construction method suitable for karst region
CN109707322B (en) * 2018-12-08 2024-06-21 深圳市勘察研究院有限公司 Karst cave isolation device and karst cave isolation method using same
CN111335309A (en) * 2020-04-17 2020-06-26 浙江省交通规划设计研究院有限公司 Large-diameter pipe pile, variable-diameter single pile and construction method of variable-diameter single pile

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59126821A (en) * 1983-01-10 1984-07-21 Aoki Kensetsu:Kk Erection work of foundation pile
CN1490467A (en) * 2003-08-05 2004-04-21 胡柏英 Composite friction pile structure and constructing method thereof
RU2276227C1 (en) * 2004-09-08 2006-05-10 Ахсар Николаевич Басиев Method for concrete pile shoe forming
CN201407051Y (en) * 2009-04-01 2010-02-17 中铁二院工程集团有限责任公司 Karst formation pile hole wall protection structure
CN102628269B (en) * 2012-04-27 2014-05-07 河海大学 Technical device for reducing negative frictional resistance on driven cast-in-place pile, and application method thereof

Also Published As

Publication number Publication date
CN104563147A (en) 2015-04-29

Similar Documents

Publication Publication Date Title
CN104563147B (en) Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation
CN101614125B (en) Construction method of V-level surrounding rock tunnel
CN107859036B (en) A kind of in-situ deposited prefabricated composite structure stake and its construction method suitable for karst region
CN106351670B (en) A kind of closed pre support tunnel structure
CN103758123B (en) The construction method of manually digging hole filling pile retaining wall lining
CN103321244B (en) Sand foundation existing building sets up the construction method of basement
WO2016058275A1 (en) Underground steel-concrete structure pipeline with spiral composite reinforcement ring on inner wall thereof and manufacturing method thereof
CN105696602A (en) Composite pile-anchor supporting method and structure for deepening excavation
CN208702421U (en) The tunnel support structure of existing pile foundation building is worn under a kind of
CN105569051A (en) Foundation pit support system of sandy pebble boulder geological stratification and construction method
CN105649073A (en) Static root drilling type construction method for planting piles
CN203213101U (en) Embedding grouting combined pile
CN101899831B (en) Active variable-stiffness leveling pile and construction method thereof
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN104131566B (en) A kind of basement is without the construction method of horizontal support foundation ditch
CN203222795U (en) Manual hole digging pile
CN110080779A (en) Tunnel tunnel bottom karst cave treatment construction method
CN204311456U (en) Foundation ditch strengthening structure
CN204186396U (en) A kind of shield tunnel surrounding formation reinforces channels configuration
CN105605335A (en) Large-caliber prestressed steel cylinder concrete pipe for jacking construction
CN203613568U (en) Anti-floating cement soil pile and anti-floating anchor rod combined anti-floating system
CN203594023U (en) Enhanced type long auger drilling pressure-grouting concrete pile
CN210658340U (en) Prefabricated dado
CN105002891B (en) A kind of cast-in-situ bored pile exempts from inter-pile soil excavation construction method
CN204401627U (en) To pull-type prestressed pipe pile pit supporting construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210629

Address after: 13 / F, 525 Jianguo East Road, Huangpu District, Shanghai 200025

Patentee after: SHANGHAI URBAN TRANSPORTATION DESIGN INSTITUTE Co.,Ltd.

Address before: 200092 No. two, 901 North Road, Yangpu District, Shanghai, Zhongshan

Patentee before: SHANGHAI MUNICIPAL ENGINEERING DESIGN INSTITUTE (Group) Co.,Ltd.