JPH1181682A - Election for large panel - Google Patents

Election for large panel

Info

Publication number
JPH1181682A
JPH1181682A JP24412197A JP24412197A JPH1181682A JP H1181682 A JPH1181682 A JP H1181682A JP 24412197 A JP24412197 A JP 24412197A JP 24412197 A JP24412197 A JP 24412197A JP H1181682 A JPH1181682 A JP H1181682A
Authority
JP
Japan
Prior art keywords
large panel
jig
rope
panel
mounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP24412197A
Other languages
Japanese (ja)
Inventor
Tadaki Yoshioka
忠喜 吉岡
Tsutomu Teshigawara
勉 勅使河原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Asahi Chemical Industry Co Ltd
Original Assignee
Asahi Chemical Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Asahi Chemical Industry Co Ltd filed Critical Asahi Chemical Industry Co Ltd
Priority to JP24412197A priority Critical patent/JPH1181682A/en
Publication of JPH1181682A publication Critical patent/JPH1181682A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a large panel locating method capable of easily slinging and locating a large panel in a stable state without damaging it at the time of a strong wind and without requiring an assisting worker at the time of location. SOLUTION: A pair of rope insertion metals 7 are protruded on the side face of the horizontal rod 2 of a locating jig 1 erecting a large panel 8, and a pair of guide ropes 12 are vertically stretched on the building skeleton side face of an outer scaffold 11 provided along a building skeleton 9. The guide ropes 12 are inserted into the rope insertion metals 7, the erecting jig 1 is vertically moved along the guide ropes 12, and the large panel 8 is erected on the building skeleton 9.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は表面仕上げが施され
た軽量気泡コンクリート板(ALC板)、PCコンクリ
ート板等の大型パネルを地上より揚重機等で吊り上げて
建物躯体に建込む方法に係り、特に建込み時に介添え用
の作業員を不要とすることが出来、かつ強風時等にも大
型パネルを損傷することなく容易に安定した状態で吊り
上げて建込むことが出来る大型パネルの建込み方法に関
するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of hoisting a large panel such as a lightweight cellular concrete board (ALC board) or PC concrete board having a surface finish from the ground by a hoist or the like and building it into a building frame. In particular, the present invention relates to a method of mounting a large panel which can eliminate a need for an assisting worker at the time of building and can be easily lifted and stably built in a strong wind without damaging the large panel. Things.

【0002】[0002]

【従来の技術】従来、表面仕上げが施されたALC板、
PCコンクリート板等の大型パネルを高層建物躯体に建
込む場合には、大型パネルを屋上又は地上より建込み用
の揚重機で吊り上げ、建物躯体と外部足場とで形成され
る隙間の最上部より落とし込みながら、大型パネルを建
物躯体の所定位置に建込み、この大型パネルを所定の取
付金物で建物躯体に取付固定していた。
2. Description of the Related Art Conventionally, an ALC plate having a surface finish,
When building large panels, such as PC concrete boards, in a high-rise building frame, lift the large panels from the roof or from the ground with a lifting machine and drop it from the top of the gap formed between the building frame and the external scaffold. Meanwhile, a large panel was built at a predetermined position in the building frame, and the large panel was attached and fixed to the building frame with predetermined mounting hardware.

【0003】[0003]

【発明が解決しようとする課題】然るに、前述の従来の
大型パネルの建込み方法では、大型パネルが吊上時の振
動等で揺れて、その一部が建物躯体や足場に接触して傷
や損傷を受け易い問題があった。また、このような傷や
損傷の発生を防止するためには、大型パネルの建込み時
に専用の介添え用作業員を配置する必要があり、人件費
が増大する問題もあった。
However, in the above-described conventional method of mounting a large panel, the large panel is shaken by vibration or the like at the time of lifting, and a part of the large panel comes into contact with a building frame or a scaffold, thereby causing damage or damage. There was a problem that was easily damaged. Also, in order to prevent the occurrence of such scratches or damages, it is necessary to arrange a dedicated assistant for installing a large-sized panel, and there has been a problem that labor costs increase.

【0004】かつ、表面仕上げ等の化粧が既に施された
パネルを建込む場合には、慎重に取り扱わなければなら
ないので、建込みスピードが遅くなり、作業効率が悪く
なる問題があった。更に、強風時には大型パネルの建込
みが出来ない等の問題があった。
[0004] In addition, when laying a panel that has already been subjected to makeup such as surface finishing, it must be handled with care, and thus there has been a problem that the laying speed is reduced and the work efficiency is reduced. In addition, there was a problem that large panels could not be built in strong winds.

【0005】本発明に係る大型パネルの建込み方法は、
前述の従来の問題点に鑑み開発された全く新しい技術で
あって、特に側面にロープ挿通金具を突設した特殊な建
込み用治具を使用すると共に、外部足場の建物躯体側の
面にガイドロープを垂直に張設し、このガイドロープを
ロープ挿通金具に挿通して、建込み用治具をガイドロー
プに添って安定して昇降させることによって大型パネル
を損傷させずに安定した状態で、かつ高速度で建物躯体
に建込むことが出来るようにした全く新しい技術を提供
するものである。
[0005] The method of mounting a large panel according to the present invention is as follows.
This is a completely new technology developed in view of the above-mentioned conventional problems.In particular, a special mounting jig with a rope insertion fitting protruding on the side is used, and a guide is provided on the surface of the external scaffold on the building frame side. The rope is stretched vertically, this guide rope is inserted into the rope insertion bracket, and the mounting jig is stably moved up and down along the guide rope, so that it is stable without damaging the large panel, It also provides a completely new technology that enables the building to be built into a building frame at a high speed.

【0006】[0006]

【課題を解決するための手段】本発明に係る大型パネル
の建込み方法は、前述の従来の問題点を根本的に改善し
た技術であって、その発明の要旨は、大型パネルを屋上
又は地上より揚重機等で吊り上げて建物躯体に建込む方
法に於いて、前記大型パネルを吊り上げる建込み用治具
の側面にロープ挿通金具を突設し、前記建物躯体に沿っ
て設けられた外部足場の建物躯体側の面にガイドロープ
を垂直に張設し、かつ該ガイドロープを前記建込み用治
具のロープ挿通金具内に挿通し、該建込み用治具をガイ
ドロープに沿って昇降させながら大型パネルを建物躯体
に建込むように構成したことを特徴とした大型パネルの
建込み方法である。
SUMMARY OF THE INVENTION The method for installing a large panel according to the present invention is a technique which fundamentally improves the above-mentioned conventional problems, and the gist of the invention is that the large panel is mounted on a roof or on the ground. In a method of being lifted by a lifting machine or the like and being built in a building frame, a rope insertion fitting is protruded from a side surface of a mounting jig for lifting the large panel, and an external scaffold provided along the building frame. A guide rope is vertically stretched on the surface of the building frame side, and the guide rope is inserted into a rope insertion metal fitting of the construction jig, and the construction jig is raised and lowered along the guide rope. This is a method for mounting a large panel, wherein a large panel is configured to be built in a building frame.

【0007】本発明に於いては、前述のように、大型パ
ネルを吊り上げることが出来る建込み用治具の側面にロ
ープ挿通金具を突設し、かつ外部足場の建物躯体側の面
にガイドロープを垂直に張設し、該ガイドロープをロー
プ挿通金具内に挿通し、建込み用治具をガイドロープに
沿って昇降するように構成したので、建込み用治具で吊
り上げられた大型パネルをガイドロープに沿って安定し
た状態で吊り上げて建物躯体に建込むことが出来る。
[0007] In the present invention, as described above, a rope insertion fitting protrudes from the side of a mounting jig capable of suspending a large panel, and a guide rope is provided on a surface of the external scaffold on the side of the building frame. Is vertically stretched, the guide rope is inserted into the rope insertion metal fitting, and the construction jig is configured to move up and down along the guide rope, so that the large panel suspended by the construction jig can be used. It can be lifted in a stable state along the guide rope and built into the building frame.

【0008】[0008]

【発明の実施の形態】図により本発明に係る大型パネル
の建込み方法の一実施例を具体的に説明すると、図1は
本発明に係る建込み方法の要部の構成を示す斜視説明
図、図2は図1に係る建込み方法の全体の構成を示す側
面図である。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a perspective view showing the construction of a main part of a method for mounting a large panel according to the present invention. FIG. 2 is a side view showing the entire configuration of the mounting method according to FIG.

【0009】図1に於いて、1は建込み用治具であっ
て、横棒2の上面に一対のフック3を介して吊上ロープ
4が取付けられ、かつ横棒2の下面には一対のチェーン
5を介してマルカン6が夫々取付けられて構成されてい
る。また、建込み用治具1の横棒2の側面には、U字形
のロープ挿通金具7が左右に夫々突設されている。
In FIG. 1, reference numeral 1 denotes a mounting jig, on which a lifting rope 4 is mounted on an upper surface of a horizontal bar 2 via a pair of hooks 3, and a pair of lower surfaces of the horizontal bar 2 are mounted. The mark 5 is attached through the chain 5 of each. Further, on the side surface of the horizontal bar 2 of the mounting jig 1, a U-shaped rope insertion metal fitting 7 is provided so as to project right and left, respectively.

【0010】8は大型パネルであって、その外表面には
表面仕上げが施されている。この大型パネル8は、その
上部小口面に埋設されたアンカーナット(図示せず)に
前記マルカン6を螺合することによって、建込み用治具
1で吊り下げられている。
Reference numeral 8 denotes a large panel whose outer surface is surface-finished. The large panel 8 is suspended by the mounting jig 1 by screwing the markan 6 to an anchor nut (not shown) embedded in the upper small face.

【0011】図1及び図2に於いて、9は建物躯体であ
って、その最上階には揚重機10が設置されている。1
1は建物躯体9に沿って構築された外部足場であって、
この外部足場11の建物躯体側の面の最上部と最下部と
に亘っては2本一対のガイドロープ12が垂直に張設さ
れており、このガイドロープ12の下部はレバーブロッ
ク等を介して外部足場11の下端部に緊結されている。
In FIGS. 1 and 2, reference numeral 9 denotes a building frame, and a hoist 10 is installed on the top floor. 1
1 is an external scaffold constructed along the building frame 9,
A pair of guide ropes 12 are vertically extended over the uppermost and lowermost portions of the surface of the external scaffold 11 on the building skeleton side, and the lower portion of the guide ropes 12 is connected via a lever block or the like. It is tied to the lower end of the external scaffold 11.

【0012】前述の構成に於いて、本発明に係る方法を
実施するに当たっては、建込み用治具1のロープ挿通用
金具7内にガイドロープ12を挿通し、ガイドロープ1
2の下部を外部足場11に緊結し、この状態で建込み用
治具1で大型パネル8を吊り上げる。次に、揚重機10
を作動することによって建込み治具1をガイドロープ1
2に沿って上昇せしめ、大型パネル8が建物躯体9の所
定の位置に来た時に、図示しない所定のパネル取付金具
を用いて大型パネル8を建物躯体9に建込み固定する。
In carrying out the method according to the present invention in the above configuration, the guide rope 12 is inserted into the rope insertion metal fitting 7 of the mounting jig 1 and the guide rope 1
The lower part of 2 is fastened to the external scaffold 11, and in this state, the large-sized panel 8 is lifted by the jig 1 for construction. Next, the lifting machine 10
The jig 1 is moved by operating the guide rope 1
When the large panel 8 comes to a predetermined position of the building frame 9, the large panel 8 is erected and fixed to the building frame 9 by using a predetermined panel mounting bracket (not shown).

【0013】このように建込まれた大型パネル8から
は、そのアンカーナットに螺合されたマルカン6を解除
させることによって、建込み用治具1を大型パネル8よ
り取り外し、次の大型パネル8の建込みに備えることが
出来る。
From the large panel 8 erected in this way, the jig 1 for mounting is removed from the large panel 8 by releasing the marcan 6 screwed to the anchor nut, and the next large panel 8 Can be prepared.

【0014】本発明の建込み方法に於いては、建込み用
治具1のロープ挿通用金具7内にガイドロープ12を挿
通し、建込み用治具1をガイドロープ12に沿って昇降
するようにしたので、建込み用治具1を極めて安定した
状態で昇降することが出来る。従って、建込み用治具1
で吊り上げる大型パネル8が振動や風等によって揺れる
ことがなく、そのために大型パネル8が建物躯体9、外
部足場11等に接触して損傷することを防止出来る。
In the mounting method of the present invention, the guide rope 12 is inserted into the rope insertion metal fitting 7 of the mounting jig 1, and the mounting jig 1 is moved up and down along the guide rope 12. As a result, the mounting jig 1 can be moved up and down in an extremely stable state. Therefore, the mounting jig 1
The large panel 8 hung by the vibration does not shake due to vibration, wind, or the like, so that the large panel 8 can be prevented from contacting and damaging the building frame 9, the external scaffold 11, and the like.

【0015】また、本発明の方法を実施する場合には、
従来のような専用の介添え用の作業員を省略することが
出来る。更に強風時にも大型パネル8の建込み作業が安
定した状態で実施することが出来る。しかも大型パネル
8を高速度で吊り上げて建込むことが出来る。
When the method of the present invention is carried out,
It is possible to dispense with a special-purpose assisting worker as in the related art. Further, the work of installing the large panel 8 can be performed in a stable state even in a strong wind. Moreover, the large panel 8 can be lifted and built at a high speed.

【0016】[0016]

【発明の効果】本発明に係る大型パネルの建込み方法
は、前述の構成と作用とを有するので、次のような多大
な効果を有している。
The method for mounting a large-sized panel according to the present invention has the above-described structure and operation, and therefore has the following great effects.

【0017】(1)大型パネルを吊り上げる建込み用治
具をガイドロープに添って昇降させるので、大型パネル
を揺らすことなく、安定した状態で建物躯体に建込むこ
とが出来る。(2)従って、化粧の施された大型パネル
に傷や損傷を与えることなく、建込むことが出来る。
(1) Since the mounting jig for lifting the large panel is moved up and down along the guide rope, the large panel can be stably built in the building frame without shaking. (2) Therefore, it is possible to set up the large-sized panel without giving any damage or damage to the panel.

【0018】(3)パネルの建込み時には専用の介添え
用の作業員を省略することが出来る。(4)強風時にも
パネルの建込み作業を実施することが出来る。(5)パ
ネルの建込み作業をスピード化して作業効率を挙げるこ
とが出来る。
(3) When the panel is erected, a special assistant can be omitted. (4) Panel installation work can be performed even in strong winds. (5) It is possible to speed up the work of laying panels and to increase the work efficiency.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係る建込み方法の要部の構成を示す斜
視説明図である。
FIG. 1 is a perspective explanatory view showing a configuration of a main part of a mounting method according to the present invention.

【図2】図1に係る建込み方法の全体の構成を示す側面
図である。
FIG. 2 is a side view showing the entire configuration of the mounting method according to FIG. 1;

【符号の説明】[Explanation of symbols]

1 建込み用治具 2 横棒 3 フック 4 吊上ロープ 5 チェーン 6 マルカン 7 ロープ挿通金具 8 大型パネル 9 建物躯体 10 揚重機 11 外部足場 12 ガイドロープ DESCRIPTION OF SYMBOLS 1 Construction jig 2 Horizontal bar 3 Hook 4 Lifting rope 5 Chain 6 Markan 7 Rope insertion fitting 8 Large panel 9 Building frame 10 Lifting machine 11 External scaffold 12 Guide rope

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】大型パネルを屋上又は地上より揚重機等で
吊り上げて建物躯体に建込む方法に於いて、前記大型パ
ネルを吊り上げる建込み用治具の側面にロープ挿通金具
を突設し、前記建物躯体に沿って設けられた外部足場の
建物躯体側の面にガイドロープを垂直に張設し、かつ該
ガイドロープを前記建込み用治具のロープ挿通金具内に
挿通し、該建込み用治具をガイドロープに沿って昇降さ
せながら大型パネルを建物躯体に建込むように構成した
ことを特徴とした大型パネルの建込み方法。
In a method of hoisting a large panel from a roof or the ground by a lifting machine or the like and building it in a building frame, a rope insertion fitting is protruded from a side of a mounting jig for hoisting the large panel. A guide rope is vertically stretched on a surface of the external scaffold provided along the building skeleton on the building skeleton side, and the guide rope is inserted into a rope insertion fitting of the mounting jig, and the A method of mounting a large panel, wherein a large panel is built into a building frame while a jig is moved up and down along a guide rope.
JP24412197A 1997-09-09 1997-09-09 Election for large panel Pending JPH1181682A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24412197A JPH1181682A (en) 1997-09-09 1997-09-09 Election for large panel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24412197A JPH1181682A (en) 1997-09-09 1997-09-09 Election for large panel

Publications (1)

Publication Number Publication Date
JPH1181682A true JPH1181682A (en) 1999-03-26

Family

ID=17114080

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24412197A Pending JPH1181682A (en) 1997-09-09 1997-09-09 Election for large panel

Country Status (1)

Country Link
JP (1) JPH1181682A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1496173A1 (en) * 2003-07-11 2005-01-12 Paroc Group Oy Ab Method and arrangement for installing sandwich panels in tall buildings
WO2016167706A1 (en) * 2015-04-13 2016-10-20 Brunkeberg Systems Ab A lifting jig for lifting elements along the fagade of a building
JP2020176454A (en) * 2019-04-19 2020-10-29 日鉄エンジニアリング株式会社 Exterior panel hanging tool and exterior panel hanging method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1496173A1 (en) * 2003-07-11 2005-01-12 Paroc Group Oy Ab Method and arrangement for installing sandwich panels in tall buildings
WO2016167706A1 (en) * 2015-04-13 2016-10-20 Brunkeberg Systems Ab A lifting jig for lifting elements along the fagade of a building
US10280047B2 (en) 2015-04-13 2019-05-07 Brunkeberg Systems Ab Lifting jig for lifting elements along the facade of a building
JP2020176454A (en) * 2019-04-19 2020-10-29 日鉄エンジニアリング株式会社 Exterior panel hanging tool and exterior panel hanging method

Similar Documents

Publication Publication Date Title
JP2008248664A (en) Hoisting method of curtain wall
JPH1181682A (en) Election for large panel
JPH0220354Y2 (en)
JP2002364178A (en) Material lifting device
AU2004209463A1 (en) Hoist for construction material
JP2000169059A (en) Installation method of elevator
JP2957167B1 (en) Escalator truss lifting jig
JP2001354374A (en) Lifting device in hoistway of elevator
JPH02176075A (en) Hanging method and apparatus of wall pannel for building
JP2669254B2 (en) Side wall panel mounting method
JP2001316074A (en) Lifting jig for lifted cargo and its use
JPH0736001Y2 (en) Detachable lifting device
JP2004076525A (en) Temporary stage
JPH035567A (en) Temporary installation method for working suspension scaffold
JPH07157274A (en) Hanging jig for alc plate
JPH0411162A (en) Mast removing device of elevator for construction
JP3306336B2 (en) Passenger conveyor installation equipment
JP2003292268A (en) Load receiving bracket
JPH0388685A (en) Method for vertically providing guide rail of elevator
JPH02300081A (en) Installation work method for elevator
JP2001287881A (en) Elevator for construction and its installation method
JPH1144093A (en) Tool for lifting external wall panel
JPH10167613A (en) Installation device for elevator guide rail
JPS647149Y2 (en)
JPH11264246A (en) Object lifting method