JPH1144093A - Tool for lifting external wall panel - Google Patents

Tool for lifting external wall panel

Info

Publication number
JPH1144093A
JPH1144093A JP21821897A JP21821897A JPH1144093A JP H1144093 A JPH1144093 A JP H1144093A JP 21821897 A JP21821897 A JP 21821897A JP 21821897 A JP21821897 A JP 21821897A JP H1144093 A JPH1144093 A JP H1144093A
Authority
JP
Japan
Prior art keywords
panel
scaffold
horizontal beam
tool
attached
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP21821897A
Other languages
Japanese (ja)
Inventor
Taiji Nawatani
泰司 縄谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Metal Mining Co Ltd
Original Assignee
Sumitomo Metal Mining Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Metal Mining Co Ltd filed Critical Sumitomo Metal Mining Co Ltd
Priority to JP21821897A priority Critical patent/JPH1144093A/en
Publication of JPH1144093A publication Critical patent/JPH1144093A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve the safety by providing a guide means which is attached to a horizontal beam to vertically move the horizontal beam along a vertical pipe of a scaffold. SOLUTION: The position of arms 25 with respect to a horizontal beam 21 of a tool 20 is adjusted corresponding to the intervals of steel pipes of a scaffold formed outside a building frame and the distance between the building frame and the scaffold to fix the arms 25 to the beam 21 by means of bolts 26 and nuts. Next, a jig 23 of the tool 20 is fixed to an anchor nut opened at the upper end of a panel 1 and upper side wires 22 are connected to a hook of a crane using a chain block 1. The hook of the crane is brought close to the scaffold to engage pulleys 27 of the arms 25 with the steel pipes of the scaffold and the panel 1 is lowered along the steel pipes, while the pulleys 27 are caused to roll with respect to the steel pipes. Since the beam 21 is supported by the scaffold through the pulleys 27, even if the panel 1 is lowered, it does not vibrate and safety can be improved.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、建築物の躯体の上
方から軽量気泡コンクリート(ALC)パネルやPCパ
ネルなどの外壁用パネルを吊り込んで、躯体に取り付け
る際に使用する外壁用パネル吊り込み用工具に関するも
のである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for suspending an exterior wall panel such as a lightweight cellular concrete (ALC) panel or a PC panel from above a skeleton of a building and attaching the panel to the skeleton. It relates to tools for use.

【0002】[0002]

【従来の技術】従来、図6に示すように、建築物の鉄筋
躯体2に、幅が600ミリを越える幅広のALCパネル
などの外壁用パネル1を取り付けて外壁を構成する場合
には、躯体2に取り付け金具(図示せず)を固定し、躯
体2の外側には鉄パイプを組み立てた足場4を仮設す
る。一方、パネル1の裏面には所望位置に取り付け金具
(図示せず)を固定し、このパネル1の上端の小口面に
パネル吊り込み用工具10(以下、単に工具という場合
もある)を取り付け、クレーン3で工具10を吊り上げ
て、躯体2と足場4との間に上方から吊り込んで、躯体
2に取り付け金具で仮止めしてから工具10の治具13
(図5参照)をパネル1から取り外すようにしている。
2. Description of the Related Art Conventionally, as shown in FIG. 6, when an outer wall panel 1 such as a wide ALC panel having a width of more than 600 mm is attached to a reinforcing steel frame 2 of a building to form an outer wall, the frame is formed as follows. 2, a mounting bracket (not shown) is fixed, and a scaffold 4 in which an iron pipe is assembled is temporarily provided outside the frame 2. On the other hand, a mounting bracket (not shown) is fixed at a desired position on the back surface of the panel 1, and a panel hanging tool 10 (hereinafter, sometimes simply referred to as a tool) is mounted on a small edge surface at an upper end of the panel 1. The tool 10 is lifted by the crane 3, suspended from above between the skeleton 2 and the scaffold 4, temporarily fixed to the skeleton 2 with a fitting, and then the jig 13 of the tool 10 is fixed.
(See FIG. 5) is detached from the panel 1.

【0003】この吊り込み用工具は、パネルの寸法や躯
体への取り付け構造に応じて種々の構造のものが使用さ
れている。例えば、図5に示すような工具10では、断
面がI字状の水平ビーム11の上端中央部にはクレーン
フックに懸垂される一対のワイヤ12が取り付けられ、
水平ビーム11の下端にはパネル1の上端の小口面に係
止する一対のワイヤ14が取り付けられている。そし
て、この工具10を使用してパネル1を懸垂する場合に
は、パネルに埋設され、上端小口面に開口したアンカー
ナット1aに、工具10の治具13を螺合させてからこ
の工具10のワイヤ12をクレーン3のフックに懸垂さ
せる。
[0003] Various types of hanging tools are used depending on the dimensions of the panel and the mounting structure on the frame. For example, in a tool 10 as shown in FIG. 5, a pair of wires 12 suspended from a crane hook are attached to the center of the upper end of a horizontal beam 11 having an I-shaped cross section.
At the lower end of the horizontal beam 11, a pair of wires 14 that are engaged with the fore-edge surface of the upper end of the panel 1 are attached. When the panel 1 is suspended using the tool 10, the jig 13 of the tool 10 is screwed into the anchor nut 1 a buried in the panel and opened on the upper end small surface. The wire 12 is suspended from the hook of the crane 3.

【0004】[0004]

【発明が解決しようとする課題】前述のように、吊り込
んだパネル1は下方階から躯体へ順次取り付けていく
が、躯体2と足場4との間の隙間は通常300〜500
ミリ程度と狭いので、パネル1を吊り込む際に、パネル
1が振り子のように前後に振れ、足場4や躯体2に衝突
してパネル1の面が損傷し、その補修に手数と費用がか
かったり、足場4上の作業員の安全上の問題があった。
As described above, the suspended panel 1 is sequentially attached to the skeleton from the lower floor, and the gap between the skeleton 2 and the scaffold 4 is usually 300 to 500.
When the panel 1 is hung, the panel 1 swings back and forth like a pendulum and collides with the scaffold 4 and the skeleton 2, damaging the surface of the panel 1 and requiring time and effort to repair it. And there was a safety problem for workers on the scaffold 4.

【0005】また、この振れを防止するためには、足場
4上ばかりでなく、躯体2側の各階に複数の作業員を配
置し、またパネル1を遅い速度で降下させて、階の上下
の作業員が連携して作業する必要があるので、多くの作
業時間と工数とがかかる問題もあった。そして、これら
の問題は当然建築物の階層が高くなればなるほど、また
風があればあるほど、増大する。
In order to prevent this swing, a plurality of workers are arranged not only on the scaffold 4 but also on each floor on the side of the frame 2, and the panel 1 is lowered at a low speed to allow the panel 1 to move up and down. There is also a problem that a lot of work time and man-hours are required because workers need to work in cooperation. And, of course, these problems increase as the level of the building increases and as the wind increases.

【0006】したがって、本発明の目的は、建築物の躯
体の上方から外壁用パネルを吊り込んで、躯体に取り付
ける際に、パネルの振れを防止し、安全に作業すること
ができる外壁パネルの吊り込み用工具を提供するもので
ある。
SUMMARY OF THE INVENTION Accordingly, an object of the present invention is to suspend an outer wall panel by suspending an outer wall panel from above a skeleton of a building and preventing the panel from swinging when the panel is attached to the skeleton. It is intended to provide a mounting tool.

【0007】[0007]

【課題を解決するための手段】前述の目的を達成するた
めに、本発明のパネル吊り込み用工具は、上部でクレー
ンのフックに懸垂され、かつ下部でパネルを吊る水平ビ
ームと、該水平ビームに取り付けられて足場の垂直パイ
プに沿って前記水平ビームを上下動させるように前記水
平ビームに取り付けられたガイド手段とを有するもので
ある。
In order to achieve the above-mentioned object, a panel hanging tool according to the present invention comprises a horizontal beam suspended from a hook of a crane at an upper portion and hanging a panel at a lower portion, and the horizontal beam. And a guide means attached to the horizontal beam so as to move the horizontal beam up and down along the vertical pipe of the scaffold.

【0008】この工具は、上部でクレーンのフックに一
対のワイヤで懸垂され、下部でパネルの上端小口面に設
けられた例えばアンカーボルトのような係止手段と係合
する治具を下端に有する一対のワイヤでパネルを吊るよ
うに構成されているのが好ましい。
This tool has a jig at the lower end which is suspended by a pair of wires on the hook of the crane at the upper part and which engages with a locking means such as an anchor bolt provided at the lower end face of the panel at the lower part. Preferably, the panel is configured to be suspended by a pair of wires.

【0009】ガイド手段は、水平ビームの両端に取り付
けられた一対のアームと、該アームの先端に取り付けら
れた回転可能な滑車とから成ることが好ましい。また、
一対のアームはそれらの間の間隔が調節可能であり、か
つ水平ビームに対して突出する長さが調節可能であるよ
うに構成されているのが好ましい。
The guide means preferably comprises a pair of arms attached to both ends of the horizontal beam, and a rotatable pulley attached to a tip of the arm. Also,
Preferably, the pair of arms are configured such that the distance between them is adjustable and the length of protrusion relative to the horizontal beam is adjustable.

【0010】また、滑車は足場の鉄製のパイプに吸着さ
れて移動可能であるように着磁されていることが好まし
い。
The pulley is preferably magnetized so as to be movable by being attracted to an iron pipe of the scaffold.

【0011】[0011]

【発明の実施の形態】次に、本発明の実施例を説明す
る。図1は、本発明のパネル吊り込み用工具でパネルを
懸垂した状態を示す斜視図であり、図2は、パネル吊り
込み工具を使用してパネルを吊り込む状態を説明するた
めの側面図であり、図3は、図2の(A)部の拡大側面
図であり、図4は、図3で示す滑車だけを示す平面図で
ある。
Next, embodiments of the present invention will be described. FIG. 1 is a perspective view showing a state in which a panel is hung by a panel hanging tool of the present invention, and FIG. 2 is a side view for explaining a state in which a panel is hung by using a panel hanging tool. FIG. 3 is an enlarged side view of the portion (A) of FIG. 2, and FIG. 4 is a plan view showing only the pulley shown in FIG.

【0012】本発明のパネル吊り込み工具20は、従来
例の工具10と同様に、断面がI字状の水平ビーム21
を有し、水平ビーム21は中央のウエッブと、上部フラ
ンジと、下部フランジとから成る。水平ビーム21のウ
エッブの上端中央部にはクレーンのフックに懸垂される
一対のワイヤ22が取り付けられており、水平ビーム2
1のウエッブの下端には、パネル1の上端小口面におい
てパネル1のアンカーナット(図示せず)に係止された
治具23を懸垂する一対のワイヤ24が取り付けられて
いる。
The panel hanging tool 20 of the present invention has a horizontal beam 21 having an I-shaped cross section, similarly to the conventional tool 10.
And the horizontal beam 21 comprises a central web, an upper flange and a lower flange. At the center of the upper end of the web of the horizontal beam 21, a pair of wires 22 suspended from a hook of a crane is attached.
At the lower end of the web 1, a pair of wires 24 are attached to suspend the jig 23 locked on an anchor nut (not shown) of the panel 1 on the upper edge of the panel 1.

【0013】図3に示すように、水平ビーム21の上部
フランジの両端には複数の孔21cが適切な間隔で形成
されている。水平ビームの長手方向に直角な方向に一対
のL字状のアーム25がその水平部分でボルト26とナ
ット26a(図3)によって水平ビームに固定されてい
る。このアーム25の先端には滑車27が取り付けられ
ている。滑車27は、図4に示すように、アーム25の
先端に固定された断面コの字型の支持フレーム27c
と、支持フレーム27cに取り付けられた水平軸27b
と、水平軸27bに回転可能に取り付けらえたローラ2
7aからなる。
As shown in FIG. 3, a plurality of holes 21c are formed at both ends of the upper flange of the horizontal beam 21 at appropriate intervals. A pair of L-shaped arms 25 are fixed to the horizontal beam at their horizontal parts by bolts 26 and nuts 26a (FIG. 3) in a direction perpendicular to the longitudinal direction of the horizontal beam. A pulley 27 is attached to the tip of the arm 25. The pulley 27 is, as shown in FIG. 4, a support frame 27c having a U-shaped cross section fixed to the tip of the arm 25.
And a horizontal shaft 27b attached to the support frame 27c
And a roller 2 rotatably mounted on a horizontal shaft 27b.
7a.

【0014】ローラ27aは円周方向に凹部が形成され
ており、この凹部の断面形状は、足場4の垂直に配置さ
れた鉄パイプ4aの断面の円形形状に適合するように、
断面が半円形状に形成されている。したがって、ローラ
27aは鉄パイプ4aに沿って上下動でき、水平ビーム
21を足場4の鉄パイプ4aに沿ってガイドすることに
なる。なお、ローラ27aは、鉄パイプ4aに吸着され
て外れないように着磁されていることが好ましい。この
着磁方向は面方向でも軸方向でもよい。
The roller 27a is formed with a concave portion in the circumferential direction, and the cross-sectional shape of the concave portion matches the circular shape of the cross-section of the vertically arranged iron pipe 4a of the scaffold 4.
The cross section is formed in a semicircular shape. Therefore, the roller 27a can move up and down along the iron pipe 4a, and guides the horizontal beam 21 along the iron pipe 4a of the scaffold 4. The roller 27a is preferably magnetized so as not to be attracted to the iron pipe 4a and come off. This magnetization direction may be a plane direction or an axial direction.

【0015】また、アーム25の水平部分には、その内
の少なくとも1つを用いて水平ビーム21の上部フラン
ジに固定するための複数の孔25aが形成されている。
アーム25の孔25aのいずれかと水平ビーム21の上
部フランジの孔21cのいずれかを組み合わせて固定す
ることにより、一対の滑車27の間の間隔や水平ビーム
21からの突出長さが調整できるようになっている。こ
のため、足場4の鉄パイプ4aの間隔に合わせることが
でき、また足場4と水平ビーム21、したがって、パネ
ル1との間隔を適切に選ぶことができる。
The horizontal portion of the arm 25 is formed with a plurality of holes 25a for fixing to the upper flange of the horizontal beam 21 using at least one of them.
By fixing one of the holes 25a of the arm 25 and one of the holes 21c of the upper flange of the horizontal beam 21 in combination, the distance between the pair of pulleys 27 and the protruding length from the horizontal beam 21 can be adjusted. Has become. Therefore, the distance between the scaffold 4 and the horizontal beam 21 and thus the distance between the panel 1 and the scaffold 4 can be appropriately selected.

【0016】また、水平ビーム21のウエッブの上端に
はワイヤ22をシャックル22aに取り付けるための一
対の孔21aが中心から等距離の位置に形成されてい
る。また、水平ビーム21のウエッブの下端には中心か
ら等間隔で複数の孔21bが形成されている。したがっ
て、懸垂するパネルの幅に応じてワイヤ24の間隔を適
切に選択できる。
A pair of holes 21a for attaching the wire 22 to the shackle 22a are formed at the upper end of the web of the horizontal beam 21 at the same distance from the center. A plurality of holes 21b are formed at the lower end of the web of the horizontal beam 21 at equal intervals from the center. Therefore, the interval between the wires 24 can be appropriately selected according to the width of the suspended panel.

【0017】次に、本発明の工具20の用い方を説明す
る。最初に、躯体2に取り付け金具(図示せず)を取り
付け、躯体2の外側には鉄パイプ4aを組み立てて構成
した足場4を、躯体2の上端部よりもやや高い位置まで
仮設する。一方、この足場4の鉄パイプ4aの間隔と、
躯体2に対する足場4との距離に応じて、工具20の水
平ビーム21に対してアーム25の位置を調節してボル
ト26とナット26aによってアーム25を水平ビーム
21に固定する。
Next, how to use the tool 20 of the present invention will be described. First, a mounting bracket (not shown) is attached to the skeleton 2, and a scaffold 4 constructed by assembling an iron pipe 4a outside the skeleton 2 is temporarily provided to a position slightly higher than the upper end of the skeleton 2. On the other hand, the distance between the iron pipes 4a of the scaffold 4 and
The position of the arm 25 is adjusted with respect to the horizontal beam 21 of the tool 20 according to the distance between the scaffold 4 and the frame 2, and the arm 25 is fixed to the horizontal beam 21 by bolts 26 and nuts 26 a.

【0018】躯体2に取り付けられた取り付け金具に対
して固定される取り付け金具(図示せず)をパネル1の
裏面に取り付る。パネル1の上端小口面に開口するアン
カーナット1aが予め埋設されており、このアンカーナ
ット1aに工具20の治具23を固定する。工具20の
上部のワイヤ22をクレーン4のフックにチェーンブロ
ック7を用いて懸垂させる。なお、治具23は2つのリ
ング金具23a、23b(図1)の組み合わせを用いて
直交する2つの水平軸に対して回動可能に支持されてお
り、治具23とパネル1を固定するボルト23c(図
1)やパネル1のアンカーナット1aに無理な応力が作
用しないようになっている。
A mounting bracket (not shown) fixed to the mounting bracket mounted on the frame 2 is attached to the back surface of the panel 1. An anchor nut 1a, which is open at the upper edge surface of the panel 1, is embedded in advance, and the jig 23 of the tool 20 is fixed to the anchor nut 1a. The wire 22 on the upper part of the tool 20 is suspended from the hook of the crane 4 using the chain block 7. The jig 23 is supported by a combination of two ring fittings 23a and 23b (FIG. 1) so as to be rotatable about two orthogonal horizontal axes, and a bolt for fixing the jig 23 to the panel 1 is provided. 23c (FIG. 1) and the anchor nut 1a of the panel 1 are not subjected to excessive stress.

【0019】この状態で、パネル1を躯体2と足場4と
の間に上方から吊り込むが、このとき、クレーン4のフ
ック7を足場4に接近させ、工具20のアーム25の滑
車27を足場4の鉄パイプ4aに係合させ、滑車27を
鉄パイプ4aに対してを転動させながら、鉄パイプ4a
に沿ってパネル1を降下させる(図2参照)。その後、
前述の作業を繰り返し、パネル1を躯体2の下層から躯
体2に順次取り付けていく。
In this state, the panel 1 is suspended from above from between the frame 2 and the scaffold 4. At this time, the hook 7 of the crane 4 is brought closer to the scaffold 4, and the pulley 27 of the arm 25 of the tool 20 is moved to the scaffold. 4 and the pulley 27 is rolled with respect to the iron pipe 4a.
The panel 1 is lowered along (see FIG. 2). afterwards,
The above operation is repeated, and the panel 1 is sequentially attached to the skeleton 2 from the lower layer of the skeleton 2.

【0020】このとき、工具20の水平ビーム21は滑
車27で足場4に支持されているので、パネル1を降下
させても振れることはない。そのため、作業員5は屋上
とパネル1を取り付ける階だけに配置すればよく、各階
に配置する必要はない。また、高速で降下させ、チェー
ンブロック7で微調整することができるので、パネル取
り付けのための作業員の数が少なくて済み、その上、作
業時間も短縮できる。作業効率と安全性が向上し、パネ
ルの損傷も防止できる。
At this time, since the horizontal beam 21 of the tool 20 is supported on the scaffold 4 by the pulley 27, it does not swing even if the panel 1 is lowered. Therefore, the worker 5 may be arranged only on the roof and the floor where the panel 1 is mounted, and need not be arranged on each floor. In addition, since it can be lowered at a high speed and finely adjusted by the chain block 7, the number of workers for mounting the panel can be reduced, and the working time can be shortened. Work efficiency and safety are improved, and panel damage can be prevented.

【0021】なお、アーム25を固定した水平ビーム2
1を用いてもよいが、アームの間の間隔や水平ビーム2
1からの突出の長さを調整可能にした方が建築現場の状
況に対応し易いので望ましい。また、滑車27を必ずし
も着磁しなくともよいが、着磁した方がパネル1を取り
外し、工具20を引き上げる際に滑車27が足場のパイ
プ4aから外れないので、安全で効率的である。
The horizontal beam 2 to which the arm 25 is fixed
1 may be used, but the distance between the arms and the horizontal beam 2
It is desirable to make the length of the protrusion from 1 adjustable so that it can be easily adapted to the situation at the construction site. Although the pulley 27 does not necessarily need to be magnetized, the magnetized one is safe and efficient because the pulley 27 does not come off the scaffold pipe 4a when the panel 1 is removed and the tool 20 is pulled up.

【0022】[0022]

【発明の効果】以上説明したように、本発明のパネル吊
り込み工具では、工具でパネルを吊り込む場合に、アー
ム先端の滑車を足場のパイプに沿って降下させれば、パ
ネルが面方向に振れることがない。したがって、作業員
の安全性が向上するばかりでなく、作業員を各階に配置
する必要がなく、高速で降下させることができるので、
作業効率が向上するし、パネルの損傷も防止することが
できる。
As described above, in the panel hanging tool of the present invention, when the panel is hung by a tool, the pulley at the end of the arm is lowered along the pipe of the scaffold, and the panel is moved in the plane direction. There is no swing. Therefore, not only the safety of the worker is improved, but also it is not necessary to arrange the worker on each floor, and the worker can descend at a high speed.
Work efficiency is improved, and damage to the panel can be prevented.

【0023】アーム間の間隔やアームの突出長さを調整
可能にしておけば、建築現場で足場を構成するパイプ間
の幅や足場と躯体との間隔が相違しても容易に対応する
ことができるので便利である。さらに、滑車を着磁して
おけば、この滑車が足場の鉄パイプに吸着しながら移動
するので、パネルを取り外し、工具を引き上げる際に
も、パイプから外れることがなく円滑に作業することが
できて好都合である。
If the distance between the arms and the protruding length of the arms can be adjusted, even if the width between the pipes constituting the scaffold or the distance between the scaffold and the frame at the construction site is different, it is possible to easily cope with the difference. It is convenient because you can do it. In addition, if the pulley is magnetized, the pulley moves while adsorbing to the iron pipe of the scaffold, so when removing the panel and pulling up the tool, you can work smoothly without detaching from the pipe. It is convenient.

【図面の簡単な説明】[Brief description of the drawings]

【図1】図1は、本発明のパネル吊り込み用工具でパネ
ルを懸垂した状態を示す斜視図である。
FIG. 1 is a perspective view showing a state in which a panel is suspended by a panel hanging tool of the present invention.

【図2】図2は、パネル吊り込み工具を使用してパネル
を吊り込む状態を説明するための側面図である。
FIG. 2 is a side view for explaining a state in which a panel is hung using a panel hanger.

【図3】図3は、図2の(A)部の拡大側面図である。FIG. 3 is an enlarged side view of a part (A) of FIG. 2;

【図4】図4は、図3で示す滑車だけを示す平面図であ
る。
FIG. 4 is a plan view showing only the pulley shown in FIG. 3;

【図5】図5は、従来例の工具でパネルを懸垂した状態
を示す斜視図である。
FIG. 5 is a perspective view showing a state where a panel is suspended by a conventional tool.

【図6】図6は、従来例の工具を使用してパネルを吊り
込む状態を説明するための側面図である。
FIG. 6 is a side view for explaining a state in which a panel is hung using a conventional tool.

【符号の説明】[Explanation of symbols]

1 パネル 2 躯体 3 クレーン 4 足場 4a 鉄パイプ 20 工具 21 水平ビーム 22、24 ワイヤ 23 治具 25 アーム 27 滑車 DESCRIPTION OF SYMBOLS 1 Panel 2 Body 3 Crane 4 Scaffold 4a Iron pipe 20 Tool 21 Horizontal beam 22, 24 Wire 23 Jig 25 Arm 27 Pulley

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 上部でクレーンのフックに懸垂され、か
つ下部でパネルを吊る水平ビームと、該水平ビームに取
り付けられて足場のパイプに沿って前記水平ビームを上
下動させるように前記水平ビームに取り付けられたガイ
ド手段とを有することを特徴とする外壁用パネル吊り込
み用工具。
1. A horizontal beam suspended at an upper portion from a hook of a crane and hanging a panel at a lower portion, the horizontal beam being attached to the horizontal beam so as to move the horizontal beam up and down along a pipe of a scaffold. A tool for hanging a panel for an outer wall, comprising a guide means attached to the panel.
【請求項2】 請求項1記載のパネル吊り込み用工具に
おいて、前記水平ビームは、上部でクレーンのフックに
一対のワイヤで懸垂され、パネルの上端小口面に設けら
れた係止手段と係合する治具を下端に有するパネルを一
対のワイヤで吊ることを特徴とするパネル吊り込み用工
具。
2. The panel hanging tool according to claim 1, wherein the horizontal beam is suspended by a pair of wires on a hook of a crane at an upper part, and is engaged with a locking means provided on an upper edge surface of the panel. A panel hanging tool, wherein a panel having a jig at a lower end thereof is hung by a pair of wires.
【請求項3】 請求項1記載のパネル吊り込み用工具に
おいて、前記ガイド手段は、前記水平ビームの両端に取
り付けられた一対のアームと、該アームの先端に取り付
けられた回転可能な滑車とから成ることを特徴とするパ
ネル吊り込み用工具。
3. The panel hanging tool according to claim 1, wherein the guide means comprises a pair of arms attached to both ends of the horizontal beam, and a rotatable pulley attached to a tip of the arm. A tool for hanging a panel, comprising:
【請求項4】 請求項3記載のパネル吊り込み用工具に
おいて、前記一対のアームはそれらの間の間隔が調節可
能であり、かつ前記水平ビームに対して突出する長さが
調節可能であるように前記水平ビームに取り付けられる
ことを特徴とするパネル吊り込み用工具。
4. The panel hanging tool according to claim 3, wherein a distance between the pair of arms is adjustable, and a length of the arm protruding with respect to the horizontal beam is adjustable. A panel hanging tool attached to the horizontal beam.
【請求項5】 請求項3記載のパネル吊り込み用工具に
おいて、前記滑車は足場の鉄製のパイプに吸着されて移
動可能であるように着磁されていることを特徴とするパ
ネル吊り込み用工具。
5. The panel hanging tool according to claim 3, wherein the pulley is magnetized so as to be movable by being attracted to an iron pipe of a scaffold. .
JP21821897A 1997-07-29 1997-07-29 Tool for lifting external wall panel Pending JPH1144093A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21821897A JPH1144093A (en) 1997-07-29 1997-07-29 Tool for lifting external wall panel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21821897A JPH1144093A (en) 1997-07-29 1997-07-29 Tool for lifting external wall panel

Publications (1)

Publication Number Publication Date
JPH1144093A true JPH1144093A (en) 1999-02-16

Family

ID=16716472

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21821897A Pending JPH1144093A (en) 1997-07-29 1997-07-29 Tool for lifting external wall panel

Country Status (1)

Country Link
JP (1) JPH1144093A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014122468A (en) * 2012-12-20 2014-07-03 Toda Constr Co Ltd Exterior wall damage prevention jig for scaffold
CN104831846A (en) * 2015-04-17 2015-08-12 中国建筑第八工程局有限公司 Hoisting method for indoor inclined curtain wall super-large glass
CN105019664A (en) * 2014-04-30 2015-11-04 中冶天工集团有限公司 High-altitude slipping installation method for compartment-type electric room

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014122468A (en) * 2012-12-20 2014-07-03 Toda Constr Co Ltd Exterior wall damage prevention jig for scaffold
CN105019664A (en) * 2014-04-30 2015-11-04 中冶天工集团有限公司 High-altitude slipping installation method for compartment-type electric room
CN105019664B (en) * 2014-04-30 2017-10-03 中冶天工集团有限公司 The air translation Method for Installation of case room formula electric panel room
CN104831846A (en) * 2015-04-17 2015-08-12 中国建筑第八工程局有限公司 Hoisting method for indoor inclined curtain wall super-large glass
CN104831846B (en) * 2015-04-17 2017-04-12 中国建筑第八工程局有限公司 Hoisting method for indoor inclined curtain wall super-large glass

Similar Documents

Publication Publication Date Title
JPH1113275A (en) Aerial expansion type suspended scaffold and its construction
JPH09158470A (en) Prefabricated scaffolding for bridge pier
CN110040646B (en) Method for fixing electric hoist on factory building roof
JPH1144093A (en) Tool for lifting external wall panel
JPH05178561A (en) Installation method for guide rail for elevator
JP2002302382A (en) Vertically suspending method of long size material
JPH04231509A (en) Laying method for cable
CN112377672A (en) Old factory dust removal pipeline reconstruction and installation method and special pipeline moving and hoisting device thereof
JP4222990B2 (en) Floor opening device, floor opening method
JP2006322208A (en) Fixing method of lightweight cellular concrete panel
JP3193334B2 (en) Gondola steady rest device
JPS5846437B2 (en) Youji Yuufredomesouchi
CN110130601A (en) Integrated decoration keeps the temperature assembled exterior-protecting wall panel and its installation method
CN212222248U (en) Riser hoisting device
JP2905039B2 (en) Long pipe hanging method and its equipment
JPH0813775A (en) Narrow space construction method for external finishing panel and device thereof
CN220578705U (en) Lifting and installing device for high-altitude pipeline fixing frame
JP3297196B2 (en) Composite balance and method for loading heavy objects using composite balance
JPH10140718A (en) Method of external-wall panel installation construction
JPH08209849A (en) Installation construction of ceiling and attic facility
JP2000087353A (en) Earth retaining strut and positioning method thereof
JP2974572B2 (en) How to install a balcony
JP2997022B2 (en) Plumbing method and plumbing equipment structure
JPS6118296Y2 (en)
JP2591690B2 (en) Hoisting winch for reinforcement ring