JPH04231509A - Laying method for cable - Google Patents

Laying method for cable

Info

Publication number
JPH04231509A
JPH04231509A JP41607990A JP41607990A JPH04231509A JP H04231509 A JPH04231509 A JP H04231509A JP 41607990 A JP41607990 A JP 41607990A JP 41607990 A JP41607990 A JP 41607990A JP H04231509 A JPH04231509 A JP H04231509A
Authority
JP
Japan
Prior art keywords
main
cable
steel frame
main cable
girder steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP41607990A
Other languages
Japanese (ja)
Other versions
JP2720339B2 (en
Inventor
Masami Kuromiya
黒宮 正美
Yuichiro Kasai
笠井 勇一郎
Tatsuo Okamoto
達雄 岡本
Hiroyuki Nishioka
博之 西岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP41607990A priority Critical patent/JP2720339B2/en
Publication of JPH04231509A publication Critical patent/JPH04231509A/en
Application granted granted Critical
Publication of JP2720339B2 publication Critical patent/JP2720339B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE:To lay easily and safely a main cable constituting a suspension structure such as suspension bridge between the steel skeletons of main tower in a short time. CONSTITUTION:A main beam steel skeleton 2 is laid between the main tower steel skeletons 1, and a main cable 7 is extended to the upside of the main beam steel skeleton 1. A hanger cable 13 is attached to the main cable 7 and repairing operations for rustproofed portions are made on the main beam steel skeletons 1. The main cable 7 is lifted up by a lifter such as wrecker truck directed to near the steel skeleton 1 and laid on the top of the steel skeleton 1, and the intermediate part of the main cable 7 is fixed to the saddle of the tower top. Both ends of the main cable 7 are fixed to the main beam steel skeleton 2.

Description

【発明の詳細な説明】[Detailed description of the invention]

【0001】0001

【産業上の利用分野】本発明は、吊り橋やそれに類する
吊り構造の構造物を構築する際におけるケーブルの架設
方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a cable installation method for constructing suspension bridges and similar suspension structures.

【0002】0002

【従来の技術】近年、土木建築の構造物において、長大
スパンによる無柱空間の構築方法は多種多様である。中
でも、吊り構造による構造物の長大スパン化は、特に、
土木分野では、吊り橋に例を見るように、歴史も古く、
将来的にもその有用性は明らかである。
BACKGROUND OF THE INVENTION In recent years, there have been a variety of methods for constructing column-free spaces with long spans in civil engineering structures. Among them, the long span of structures using suspended structures is especially important.
In the civil engineering field, as seen in suspension bridges, they have a long history.
Its usefulness in the future is clear.

【0003】ところで、吊り橋の施工は、一般に、メイ
ンケーブルを主塔鉄骨の塔頂部間に架設した後、主桁鉄
骨を主塔鉄骨間に架設するといった手順で行われている
[0003] Generally, suspension bridges are constructed using the following procedure: main cables are installed between the tops of main tower steel frames, and then main girder steel frames are installed between the main tower steel frames.

【0004】即ち、図7の(a)に示すように、主塔鉄
骨1,1を構築した後、図7の(b)に示すように、パ
イロットワイヤ(メインケーブル牽引用ワイヤ)10を
主塔鉄骨1,1の塔頂部間に架設し、当該パイロットワ
イヤ10の一端をウインチ9で引き寄せることにより、
パイロットワイヤ10の他端に接続したメインケーブル
7を展開して主塔鉄骨1,1の塔頂部間に架設し、しか
る後、図7の(c)に示すように、メインケーブル7に
吊り金物を介してハンガーケーブル13…を取り付け、
このハンガーケーブル13…で吊り下げ支持しつつ主塔
鉄骨1,1間に主桁鉄骨2を架設していたのである。
That is, as shown in FIG. 7(a), after constructing the main tower steel frames 1, 1, as shown in FIG. 7(b), the pilot wire (main cable pulling wire) 10 is connected to the main tower. By installing the pilot wire between the tower tops of the tower steel frames 1 and 1 and pulling one end of the pilot wire 10 with the winch 9,
The main cable 7 connected to the other end of the pilot wire 10 is expanded and installed between the tops of the main tower steel frames 1, 1, and then, as shown in FIG. 7(c), a hanging hardware is attached to the main cable 7. Attach the hanger cable 13 through the
The main girder steel frame 2 was erected between the main tower steel frames 1, 1 while being suspended and supported by the hanger cables 13.

【0005】しかしながら、上記のケーブル架設方法で
は、メインケーブル7の展開時、図7の(b)に示した
ように、塔頂部の前後でメインケーブル7が下方に大き
く折れ曲がるので、メインケーブル7を損傷しやすいば
かりでなく、メインケーブル7の展開(パイロットワイ
ヤ10による引き寄せ)に大きな力が必要で、ウインチ
9として大掛かりなものを設置しなければならず、しか
も、塔頂部に複雑なガイドローラを取り付ける必要があ
った。
However, in the above cable installation method, when the main cable 7 is deployed, the main cable 7 bends significantly downward before and after the tower top, as shown in FIG. 7(b). Not only is it easy to damage, but a large force is required to deploy the main cable 7 (pull by the pilot wire 10), a large-scale winch 9 must be installed, and a complicated guide roller is installed at the top of the tower. It needed to be installed.

【0006】また、メインケーブル7に対するハンガー
ケーブル取付け用の吊り金物の取付け作業や吊り金物に
対するハンガーケーブル13…の取付け作業が高所で行
われるため、複雑な仮設構造が必要で工期も長くなり、
安全管理上も難点があった。
[0006] Furthermore, since the work of attaching the hanging hardware for attaching the hanger cable to the main cable 7 and the work of attaching the hanger cable 13 to the hanging hardware are performed at a high place, a complicated temporary structure is required and the construction period becomes long.
There were also difficulties in terms of safety management.

【0007】[0007]

【発明が解決しようとする課題】海や深い谷のような条
件の悪い場所を施工対象とする場合、上記の従来方法に
依らざるを得ないかも知れない。しかし、例えば、道路
上を跨いで構築される吊り橋やそれに類する吊り構造の
構造物を構築する場合には、主塔鉄骨の近傍までクレー
ン車等の揚重機を乗り入れることが可能であるから、必
ずしも上記の従来方法を採用する必要はなく、また、主
桁鉄骨も、地上に立設した仮設支柱等で一時的に支持す
ることができるから、メインケーブルの架設に先行して
構築することも可能になる筈である。
[Problem to be Solved by the Invention] When construction is to be carried out in a place with poor conditions such as the sea or a deep valley, it may be necessary to rely on the above conventional method. However, for example, when constructing a suspension bridge that spans a road or a similar suspended structure, it is possible to drive a lifting machine such as a crane truck into the vicinity of the main tower steel frame, so it is not always possible to do so. There is no need to adopt the conventional method described above, and the main girder steel frame can also be temporarily supported with temporary struts erected on the ground, so it can be constructed prior to the erection of the main cable. It should be.

【0008】本発明は、上記の観点よりなされたもので
、その目的とするところは、短工期かつ低コストでメイ
ンケーブルを架設することができる品質及び安全管理上
も有利なケーブルの架設方法を提供することにある。
The present invention has been made from the above-mentioned viewpoint, and its object is to provide a cable installation method which is advantageous in terms of quality and safety management, and which allows main cables to be installed in a short construction period and at low cost. It is about providing.

【0009】[0009]

【課題を解決するための手段】上記の課題を解決するた
めに、本発明が講じた技術的手段は次の通りである。即
ち、本発明によるケーブルの架設方法は、主塔鉄骨間に
主桁鉄骨を架設した後、主桁鉄骨上にメインケーブルを
展開し、当該メインケーブルにハンガーケーブルを取り
付け、しかる後、揚重機により前記メインケーブルを主
塔鉄骨の塔頂部に揚重することを特徴としている。
[Means for Solving the Problems] The technical means taken by the present invention to solve the above problems are as follows. That is, in the cable installation method according to the present invention, after a main girder steel frame is erected between main tower steel frames, a main cable is deployed on the main girder steel frame, a hanger cable is attached to the main cable, and then a lifting machine is used to install a main girder steel frame. The main cable is lifted to the top of the main tower steel frame.

【0010】0010

【作用】上記の構成によれば、主桁鉄骨上でメインケー
ブルを展開するため、メインケーブルの展開時、メイン
ケーブルの折れ曲がりが少なくて、メインケーブルの展
開(パイロットワイヤによる引き寄せ)に大きな力を必
要とせず、複雑なガイドローラも必要としない。
[Operation] According to the above configuration, since the main cable is deployed on the main girder steel frame, there is less bending of the main cable when the main cable is deployed, and a large force is required to deploy the main cable (pulling by the pilot wire). No need for complicated guide rollers.

【0011】また、メインケーブルに対する諸作業、例
えば、ハンガーケーブル取付け用の吊り金物の取付け、
吊り金物に対するハンガーケーブルの取付け、メインケ
ーブルやハンガーケーブルにおける防錆処理部の手直し
等々が、全て主桁鉄骨上での作業によって行えるので、
高所作業が著しく低減することになる。
[0011] In addition, various operations on the main cable, such as attaching hanging hardware for attaching a hanger cable,
Attachment of the hanger cable to the hanging hardware, modification of the anti-corrosion treatment of the main cable and hanger cable, etc. can all be done while working on the main girder steel frame.
Work at heights will be significantly reduced.

【0012】0012

【実施例】図1の(a)に示すように、主塔鉄骨1,1
を構築した後、図1の(b)に示すように、主塔鉄骨1
,1間に主桁鉄骨2を架設する。3…は主塔鉄骨1,1
間の主桁鉄骨2を支持する仮設支柱、4…は主塔鉄骨1
,1よりも外側に位置する主桁鉄骨2を支持する本設支
柱である。
[Example] As shown in Fig. 1(a), main tower steel frames 1, 1
After constructing the main tower steel frame 1, as shown in Figure 1(b),
, 1, the main girder steel frame 2 will be erected. 3... is main tower steel frame 1,1
Temporary supports supporting the main girder steel frame 2 between, 4... are the main tower steel frames 1
, 1 is a permanent support supporting the main girder steel frame 2 located outside.

【0013】主桁鉄骨2の架設は、例えば、図3に示す
ように、仮設支柱3を備えた主桁鉄骨ユニット2aをク
レーン車等の揚重機5で吊り込んで、主塔鉄骨1に連結
し、以下、同様な仮設支柱3付きの主桁鉄骨ユニット2
aを継ぎ足して行くといった方法により行うことができ
る。
To construct the main girder steel frame 2, for example, as shown in FIG. 3, a main girder steel frame unit 2a equipped with temporary supports 3 is lifted by a lifting machine 5 such as a crane truck, and connected to the main tower steel frame 1. However, the main girder steel unit 2 with similar temporary supports 3 will be explained below.
This can be done by adding a.

【0014】図示しないが、予め、地上に必要本数の仮
設支柱3を所定間隔おきに立設しておき、しかる後、主
桁鉄骨ユニット2aの主塔鉄骨1に対する連結や継ぎ足
しを行うことによって、主塔鉄骨1,1間に主桁鉄骨2
を架設してもよい。いずれの場合も、仮設支柱3は、主
桁鉄骨2の支持が不要になった時点で撤去されるもので
ある。
Although not shown, the required number of temporary supports 3 are erected on the ground at predetermined intervals in advance, and then the main girder steel frame unit 2a is connected to and added to the main tower steel frame 1. Main girder steel frame 2 between main tower steel frame 1 and 1
may be constructed. In either case, the temporary supports 3 are removed when the support of the main girder steel frame 2 is no longer required.

【0015】スパンが比較的短い場合や主桁鉄骨ユニッ
ト2aの規模が小さい場合、図4に示すように、主塔鉄
骨1から仮設の吊りワイヤ6を垂下させ、当該吊りワイ
ヤ6で主桁鉄骨ユニット2aを支持しつつ主桁鉄骨2を
架設してもよい。
When the span is relatively short or the scale of the main girder steel frame unit 2a is small, a temporary suspension wire 6 is suspended from the main tower steel frame 1, as shown in FIG. The main girder steel frame 2 may be constructed while supporting the unit 2a.

【0016】しかる後、図1の(c)、図2の(a) 
 及び図2に示すように、主桁鉄骨2上にメインケーブ
ル7を展開する。即ち、主桁鉄骨2の一端側にメインケ
ーブル7が巻回されたドラム8を、他端側にはウインチ
9を夫々設置し、当該ウインチ9でパイロットワイヤ1
0の一端を引き寄せることにより、パイロットワイヤ1
0の他端に接続したメインケーブル7を主桁鉄骨2上に
展開するのである。図5中の7aはメインケーブル7先
端の定着用金物である。
After that, FIG. 1(c) and FIG. 2(a)
And as shown in FIG. 2, the main cable 7 is deployed on the main girder steel frame 2. That is, a drum 8 around which the main cable 7 is wound is installed at one end of the main girder steel frame 2, and a winch 9 is installed at the other end.
By pulling one end of pilot wire 1
The main cable 7 connected to the other end of the main girder steel frame 2 is deployed on the main girder steel frame 2. 7a in FIG. 5 is a fixing metal fitting at the tip of the main cable 7.

【0017】メインケーブル先端の定着用金物7aは台
車に載せて主桁鉄骨2上を移動させてもよいが、この実
施例では、図5に示すように、単管11aをクランプ1
1bによって適当な形状に連結すると共に、水平な単管
11aとその両側に連結された垂直な単管11aに夫々
樹脂製パイプ11cを回転自在に套嵌させてメインケー
ブル7用の走路11を形成し、前記定着用金物7aを橇
体12に搭載して、走路11上を移動させている。
The fixing hardware 7a at the tip of the main cable may be placed on a trolley and moved over the main girder steel frame 2, but in this embodiment, as shown in FIG.
1b in an appropriate shape, and a resin pipe 11c is rotatably fitted over the horizontal single pipe 11a and the vertical single pipes 11a connected on both sides thereof to form a running path 11 for the main cable 7. The fixing hardware 7a is mounted on a sled body 12 and moved on a running path 11.

【0018】メインケーブル7の展開後、主桁鉄骨2上
での作業によって、図6に示すように、メインケーブル
7に対するハンガーケーブル取付け用の吊り金物の取付
け、当該吊り金物に対するハンガーケーブル13…の取
付け、メインケーブル7やハンガーケーブル13…にお
ける防錆処理部の手直し等々を行う。
After the main cable 7 is deployed, work on the main girder steel frame 2 is performed to attach hanging hardware for attaching the hanger cable to the main cable 7, and to attach the hanger cable 13 to the hanging hardware, as shown in FIG. Installation, modification of the anti-corrosive parts of the main cable 7, hanger cable 13, etc.

【0019】しかる後、図2の(b)及び図6に示すよ
うに、主塔鉄骨1,1の近傍位置に乗り入れた揚重機5
により前記メインケーブル7を主塔鉄骨1,1の塔頂部
に揚重し、メインケーブル7の所定位置を塔頂部のサド
ル14に定着すると共に、メインケーブル7の両端を主
桁鉄骨2に定着する。15…は、メインケーブル7の両
端側に連結した惜しみワイヤ16…をメインケーブル7
の揚重に伴って少しずつ繰り出していくためのチルホー
ルである。
After that, as shown in FIG. 2(b) and FIG.
The main cable 7 is lifted to the top of the main tower steel frames 1, 1, and a predetermined position of the main cable 7 is fixed to the saddle 14 at the top of the tower, and both ends of the main cable 7 are fixed to the main girder steel frame 2. . 15... connects the loose wires 16... connected to both ends of the main cable 7 to the main cable 7.
This is a chill hole that is used to gradually extend the lift as the load is lifted.

【0020】この状態で、図2の(c)に示すように、
ハンガーケーブル13…の下端部を主桁鉄骨2に定着し
た後、前記仮設支柱3…を撤去するのである。
In this state, as shown in FIG. 2(c),
After the lower ends of the hanger cables 13 are fixed to the main girder steel frame 2, the temporary supports 3 are removed.

【0021】[0021]

【発明の効果】本発明は、上述した通り、主桁鉄骨上で
メインケーブルを展開するため、メインケーブルの展開
時、メインケーブルの折れ曲がりが少なくて、メインケ
ーブルの展開(パイロットワイヤによる引き寄せ)に大
きな力を必要としない。従って、ウインチとして比較的
小型のものを使用してメインケーブルの展開を行うこと
ができ、メインケーブルの損傷も少なくて済む。また、
メインケーブルに対する諸作業、例えば、ハンガーケー
ブル取付け用の吊り金物の取付け、吊り金物に対するハ
ンガーケーブルの取付け、メインケーブルやハンガーケ
ーブルにおける防錆処理部の手直し等々、が、全て主桁
鉄骨上での作業によって行われるので、高所作業が著し
く低減することになる。短工期かつ低コストでメインケ
ーブルを架設することができ、品質及び安全管理上も有
利である。
[Effects of the Invention] As described above, the present invention deploys the main cable on the main girder steel frame, so there is less bending of the main cable when the main cable is deployed, and it is easy to deploy the main cable (pulling by the pilot wire). Doesn't require a lot of force. Therefore, the main cable can be expanded using a relatively small winch, and damage to the main cable can be minimized. Also,
Various work on the main cable, such as installing hanging hardware for attaching the hanger cable, attaching the hanger cable to the hanging hardware, reworking the anti-corrosion treatment section of the main cable and hanger cable, etc., is all done on the main girder steel frame. This significantly reduces the need for work at heights. The main cable can be constructed in a short construction period and at low cost, and is also advantageous in terms of quality and safety management.

【図面の簡単な説明】[Brief explanation of the drawing]

【図1】本発明に係るケーブルの架設方法の工程説明図
である。
FIG. 1 is a process explanatory diagram of a cable installation method according to the present invention.

【図2】図1の工程に続く工程説明図である。FIG. 2 is a process explanatory diagram following the process of FIG. 1;

【図3】主桁鉄骨の架設方法の説明図である。FIG. 3 is an explanatory diagram of a method for constructing a main girder steel frame.

【図4】主桁鉄骨の別の架設方法の説明図である。FIG. 4 is an explanatory diagram of another method for constructing the main girder steel frame.

【図5】メインケーブルの展開工程を説明する要部の斜
視図である。
FIG. 5 is a perspective view of a main part illustrating a main cable deployment process.

【図6】メインケーブルの揚重工程を説明する要部の斜
視図である。
FIG. 6 is a perspective view of a main part illustrating a main cable lifting process.

【図7】従来例の説明図である。FIG. 7 is an explanatory diagram of a conventional example.

【符号の説明】[Explanation of symbols]

1…主塔鉄骨 2…主桁鉄骨 5…揚重機 7…メインケーブル 13…ハンガーケーブル 1...Main tower steel frame 2…Main girder steel frame 5... Lifting machine 7...Main cable 13...Hanger cable

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】  主塔鉄骨間に主桁鉄骨を架設した後、
主桁鉄骨上にメインケーブルを展開し、当該メインケー
ブルにハンガーケーブルを取り付け、しかる後、揚重機
により前記メインケーブルを主塔鉄骨の塔頂部に揚重す
ることを特徴とするケーブルの架設方法。
[Claim 1] After erecting the main girder steel frame between the main tower steel frames,
A method for constructing a cable, which comprises deploying a main cable on a main girder steel frame, attaching a hanger cable to the main cable, and then hoisting the main cable to the top of the main tower steel frame using a lifting machine.
JP41607990A 1990-12-28 1990-12-28 Cable laying method Expired - Fee Related JP2720339B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP41607990A JP2720339B2 (en) 1990-12-28 1990-12-28 Cable laying method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP41607990A JP2720339B2 (en) 1990-12-28 1990-12-28 Cable laying method

Publications (2)

Publication Number Publication Date
JPH04231509A true JPH04231509A (en) 1992-08-20
JP2720339B2 JP2720339B2 (en) 1998-03-04

Family

ID=18524326

Family Applications (1)

Application Number Title Priority Date Filing Date
JP41607990A Expired - Fee Related JP2720339B2 (en) 1990-12-28 1990-12-28 Cable laying method

Country Status (1)

Country Link
JP (1) JP2720339B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0655613A1 (en) 1993-11-30 1995-05-31 Nkk Corporation Temperature measuring device
CN104278637A (en) * 2014-09-23 2015-01-14 中铁大桥局集团第一工程有限公司 No-catwalk cableway erecting method for main cable strands of suspension bridge
JP2015042817A (en) * 2013-08-26 2015-03-05 東日本旅客鉄道株式会社 Aseismatic reinforcement structure of electrification pole and aseismatic reinforcement method of electrification pole
CN106049293A (en) * 2016-07-29 2016-10-26 四川天元机械工程股份有限公司 Method for installing stiffening beam of suspension bridge over navigable river and swing shift system used in method
CN106988220A (en) * 2017-03-13 2017-07-28 中交第四公路工程局有限公司 Tower structure and the method excessively of a kind of continous way suspension bridge cat road head-rope

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0655613A1 (en) 1993-11-30 1995-05-31 Nkk Corporation Temperature measuring device
JP2015042817A (en) * 2013-08-26 2015-03-05 東日本旅客鉄道株式会社 Aseismatic reinforcement structure of electrification pole and aseismatic reinforcement method of electrification pole
CN104278637A (en) * 2014-09-23 2015-01-14 中铁大桥局集团第一工程有限公司 No-catwalk cableway erecting method for main cable strands of suspension bridge
CN104278637B (en) * 2014-09-23 2016-04-06 中铁大桥局集团第一工程有限公司 A kind of main rope of suspension bridge strand is without the cableway erection method in cat road
CN106049293A (en) * 2016-07-29 2016-10-26 四川天元机械工程股份有限公司 Method for installing stiffening beam of suspension bridge over navigable river and swing shift system used in method
CN106049293B (en) * 2016-07-29 2017-10-13 德阳天元重工股份有限公司 Stiffening girder of suspension bridge installation method and used shifting system is swung on navigable river
CN106988220A (en) * 2017-03-13 2017-07-28 中交第四公路工程局有限公司 Tower structure and the method excessively of a kind of continous way suspension bridge cat road head-rope

Also Published As

Publication number Publication date
JP2720339B2 (en) 1998-03-04

Similar Documents

Publication Publication Date Title
JP2912222B2 (en) Bridge girder construction method
CN111039194A (en) Super-large crane final assembly process
CN109826082B (en) Construction method for installing decorative structure in multi-tower combined space of cable-stayed bridge
JP2894226B2 (en) Bridge construction method
JPH04231509A (en) Laying method for cable
CN212251443U (en) Special pipeline of old factory building dust removal pipeline transformation installation removes hoist device
JP2768282B2 (en) Bridge construction method
JPH10195826A (en) Bridge construction method and device thereof
JP3516056B2 (en) Rotary lift-up construction method for dome roof
JP2539150B2 (en) Bridge erection equipment
CN112411394B (en) Method for hoisting cable of half-through type space Y-shaped steel box arch bridge
JPH11147690A (en) Low head space reinforcing bar building-in device
JP2003120037A (en) Construction lifting system for multistoried building
JPH09227069A (en) Hung-moving method and device therefor
JP3297196B2 (en) Composite balance and method for loading heavy objects using composite balance
JP2593122B2 (en) Boiler installation method by small local block
JPH11269825A (en) Installation method of bridge girder and lifting equipment
CN220365282U (en) Electric translation type hanging basket
CN214527669U (en) Bridge steel case roof beam hoisting structure
JPH09279518A (en) King post used for cable trussed bridge and erection method thereof
JPH0835358A (en) Construction method for tower shaped structure and support structure used for the method
JPH09184294A (en) Method and device for erecting column
JPH1144093A (en) Tool for lifting external wall panel
CN109160423B (en) Lower hanging type multi-tower continuous span cable crane with T-shaped crown block and crown block tower span method thereof
CN116732887A (en) Bottom die bent construction method for super-high beam of super-large bridge main tower

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees