CN104831846B - Hoisting method for indoor inclined curtain wall super-large glass - Google Patents

Hoisting method for indoor inclined curtain wall super-large glass Download PDF

Info

Publication number
CN104831846B
CN104831846B CN201510185374.XA CN201510185374A CN104831846B CN 104831846 B CN104831846 B CN 104831846B CN 201510185374 A CN201510185374 A CN 201510185374A CN 104831846 B CN104831846 B CN 104831846B
Authority
CN
China
Prior art keywords
curtain wall
glass
cladding glass
cladding
vehicle frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510185374.XA
Other languages
Chinese (zh)
Other versions
CN104831846A (en
Inventor
唐际宇
黄业信
王维
郭胜文
梁秋莹
张皆科
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201510185374.XA priority Critical patent/CN104831846B/en
Publication of CN104831846A publication Critical patent/CN104831846A/en
Application granted granted Critical
Publication of CN104831846B publication Critical patent/CN104831846B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Abstract

The invention discloses a hoisting method for indoor inclined curtain wall super-large glass. The hoisting method comprises the steps that a girder frame perpendicular to the length direction of a curtain wall under construction is arranged on the top beam of the curtain wall under construction; an elevating mechanism capable of translating along the length direction of the girder frame is slidably arranged on the girder frame; a sucking disc is arranged on the elevating mechanism; curtain wall stay cables are arranged on the top beam and the bottom part structure of the curtain wall under construction in a stretching and drawing way; linking members used for installing curtain wall glass of the curtain wall under construction are arranged on the curtain wall stay cables, and the linking members are provided with linking grooves; curtain wall glass is installed; the girder frame is moved to the position above the installing position of curtain wall glass to be installed, curtain wall glass is adsorbed on the sucking disc, and curtain wall glass is moved to the installing position by utilizing the elevating mechanism and is installed in the linking grooves of the linking members; and the steps for installing curtain wall glass are repeated, and all curtain wall glass is installed completely according to the preset installing sequence of curtain wall glass. Curtain wall glass can bidirectionally move in horizontal and vertical directions so that construction is high-efficiency.

Description

The hanging method of indoor inclined curtain wall super large glass
Technical field
The present invention relates to technical field of building construction, refers in particular to a kind of lifting side of indoor inclined curtain wall super large glass Method.
Background technology
At present, newly-built large-scale public and civil buildings, the particularly building of large space, large span, more and more adopt With glass curtain wall, but the difficult problem of those skilled in the art is always perplexed in the construction of this kind of large space glass curtain wall, particularly For the indoor inclined curtain wall using oversize glass, difficulty of construction is greatly increased.Therefore, it is necessary to find a kind of new pin Construction method to the indoor inclined curtain wall using oversize glass.
The content of the invention
In view of the problems referred to above, the invention provides a kind of hanging method of indoor inclined curtain wall super large glass, including:
The purlin vehicle frame vertical with the length direction of curtain wall to be onstructed is set on the back timber of curtain wall to be onstructed;
Slide on the purlin vehicle frame and the elevating mechanism that can be translated along the length direction of the purlin vehicle frame is set;
Sucker is set on the elevating mechanism;
The tensioning curtain wall inhaul cable on the polycrystalline substance of the back timber and curtain wall to be onstructed;
The fastener of the cladding glass for being provided for installing curtain wall to be onstructed on the curtain wall inhaul cable, the fastener tool There is docking groove;
Cladding glass is installed:The purlin vehicle frame is moved to the top of the installation site of cladding glass to be installed, will be described Cladding glass is adsorbed on the sucker, the cladding glass is moved to into the installation site using the elevating mechanism and is pacified In the docking groove loaded on the fastener;
The step of repeating the installation cladding glass, according to the default erection sequence of cladding glass, by whole curtain wall glass Glass is installed.
The hanging method of interior inclined curtain wall super large glass of the invention, it is real using purlin vehicle frame and elevating mechanism compound mode Existing cladding glass both can be moved in the horizontal direction, can vertically be moved again, exactly can be installed cladding glass In place, simple to operate, high construction efficiency.
The hanging method of interior inclined curtain wall super large glass of the invention further improvement is that, on the top of curtain wall to be onstructed The purlin vehicle frame vertical with the length direction of curtain wall to be onstructed is set on beam, including:
Operating platform is set up, the operating platform is connected with the polycrystalline substance;And
The purlin vehicle frame is fixed on the back timber by connecting tooling on the operating platform.
The hanging method of interior inclined curtain wall super large glass of the invention further improvement is that the operating platform is button The full hall steel pipe scaffold of part formula, the full hall steel pipe scaffold of the fastener type is set up using layering, including:
Foot is put in vertical rod, and bar of sweeping the floor is set up on the ground;
Bridging and horizontal brace are set up on the bar of sweeping the floor;And
Set up the scaffold and the bridging in circumferential perimeter of intermediate rest part.
The hanging method of interior inclined curtain wall super large glass of the invention further improvement is that the elevating mechanism is electricity Dynamic calabash, the electric block includes hoist engine, the pulley on the hoist engine being slideably positioned on the purlin vehicle frame Group and the hook member for sucker described in hook block, the hook member is hung at by being set around the hoist cable of the assembly pulley The assembly pulley.
The hanging method of interior inclined curtain wall super large glass of the invention further improvement is that the sucker is eight pawls electricity Dynamic sucker, the eight pawls electric sucking disc includes chassis, the multiple adsorption pieces being uniformly laid on the chassis and is flexibly connected Connecting rod on the chassis.
Further improvement is that for the hanging method of interior inclined curtain wall super large glass of the invention, the cladding glass is inhaled Before investing on the sucker, also include:Tied up with two ropes is used to adjust institute in the cladding glass with respect to two sidepieces The angle of cladding glass is stated, tied up with two ropes is used to protect the cladding glass at the middle part of the cladding glass.
The hanging method of interior inclined curtain wall super large glass of the invention further improvement is that, using the elevating mechanism The cladding glass is moved into place and is installed in the docking groove of the fastener, including:
First the cladding glass is moved in the horizontal direction with the installation site in same by the elevating mechanism One vertical plane;
Again the cladding glass is vertically moved to into the installation site by the elevating mechanism;And
The cladding glass is installed in the docking groove of the fastener.
Further improvement is that for the hanging method of interior inclined curtain wall super large glass of the invention, the cladding glass is pacified After in the fastener, also include:
The patch protection gummed paper on the cladding glass of glue-line both sides;And
Gluing is carried out to the cladding glass, the protection gummed paper is removed after the completion of gluing.
Further improvement is that for the hanging method of interior inclined curtain wall super large glass of the invention, it is default according to cladding glass Erection sequence, whole cladding glass is installed, including:
The purlin vehicle frame is moved to the top of the installation site of the first row cladding glass of curtain wall to be onstructed;
Each cladding glass in first row cladding glass, any one the curtain wall glass wherein in first row cladding glass are installed The installation steps of glass include:The cladding glass is adsorbed on the sucker, using the elevating mechanism by the curtain wall glass Glass moves to the installation site and is installed in the docking groove of the fastener;And
After each cladding glass installation in the first row cladding glass, the purlin vehicle frame is moved to into next column The installation site of cladding glass simultaneously continues to install next column cladding glass, until all cladding glass in whole curtain wall are installed Finish.
The hanging method of interior inclined curtain wall super large glass of the invention further improvement is that, by whole cladding glass Multiple installation regions are divided into, a purlin vehicle frame is respectively provided with each installation region with each installing zone The cladding glass is installed in domain.
Description of the drawings
Fig. 1 is the flow chart of the hanging method of interior inclined curtain wall super large glass of the invention.
Fig. 2 is the lifting schematic diagram of the hanging method of interior inclined curtain wall super large glass of the invention.
Specific embodiment
In order that the objects, technical solutions and advantages of the present invention become more apparent, it is right below in conjunction with drawings and Examples The present invention is further elaborated.It should be appreciated that specific embodiment described herein is only to explain the present invention, not For limiting the present invention.
Refer to Fig. 1 and Fig. 2, Fig. 1 be interior inclined curtain wall super large glass of the invention hanging method flow chart, Fig. 2 It is the lifting schematic diagram of the hanging method of interior inclined curtain wall super large glass of the invention.Coordinate referring to shown in Fig. 1 and Fig. 2, this The hanging method of bright indoor inclined curtain wall super large glass, including:
Step S101:Before formal construction, microcomputer modelling emulation lifting is first carried out, including:
1st, Holistic modeling
According to the design data that designing institute provides, threedimensional model, mould are set up using the large-scale 3D design softwares of Rhinoceros Intend on-site actual situations.
2nd, local structure modeling
According to design requirement, and the related specification of Related product, instrument sets up 3D models.
3rd, glass hanging simulation
1) it is in place before cladding glass lifting, installation and the inspection of cladding glass protective measure
2) cladding glass both vertically and horizontally simulates transport.
3) adjustment of cladding glass installation direction and sizing.
Because cladding glass is lifted by crane indoors, the width of cladding glass is more than the distance between two drag-lines, cladding glass Outdoor can be just put into by rotational translation, after hand fit's adjustment, the final shaping.
With reference to shown in Fig. 2, after the completion of microcomputer modelling emulation lifting, arrange on the back timber 10 of curtain wall to be onstructed and wait to apply The vertical purlin vehicle frame 20 of the length direction of work curtain wall, including:
Operating platform is set up, the operating platform is connected with the polycrystalline substance of curtain wall to be onstructed, connected mode can be adopted With the throwing support of steel pipe it is fixed, using shaped steel or steel pipe fix be rigidly connected, the flexible connection of steel wire rope, drawknot construction must lead to Cross Force Calculation, it is ensured that the stability in the large of support body;
It is on the operating platform that purlin vehicle frame 20 is affixed by connecting tooling 210 after the completion of the operating platform is set up On the back timber 10 of curtain wall to be onstructed.
Wherein, the operating platform is the full hall steel pipe scaffold of fastener type, and the full hall steel pipe scaffold of the fastener type is adopted Layering is set up, including:
Foot is put in vertical rod, and bar of sweeping the floor is set up on the ground;
Bridging and horizontal brace are set up on the bar of sweeping the floor;And
Set up the scaffold and the bridging in circumferential perimeter of intermediate rest part.
Step S102:With reference to shown in Fig. 2, slide on purlin vehicle frame 20 and arrange what is can translated along the length direction of purlin vehicle frame 20 Elevating mechanism 40.Preferably, elevating mechanism 40 is electric block, and the electric block includes being slideably positioned on purlin vehicle frame 20 Hoist engine, the assembly pulley on the hoist engine and the hook member for sucker described in hook block, the hook member by around The assembly pulley is hung at located at the hoist cable of the assembly pulley.It is specific as follows:
(1) electric block using hoist engine set assembly pulley lifting, note during lifting tie rope must take protective measure in case Injury device, according to equipment weight itself, selects lifting rope suspender.
(2) gap adjustment:The walking wheel rim inner side of electric block and the track edge of a wing gap of purlin vehicle frame 20, it is ensured that Between 3mm~5mm, realized by pad adjustment.
(3) detection before electric block lifting:The running status of electric block lifting speed reducing is detected before lifting whether just Often, steel wire rope whether take out tightly, control knob wiring it is whether correct, it is ensured that equipment safety is used.
Step S103:With reference to shown in Fig. 2, sucker 50 is set on elevating mechanism 40.Specifically, sucker 50 is that eight pawls are electronic Sucker, minification is 1.2m × 0.9m, and development size is 2.5m × 1.4m, and suction is 800kg, the eight pawls electric sucking disc bag Include chassis 510, the multiple adsorption pieces 520 being uniformly laid on chassis 510 and the connecting rod being movably connected on chassis 510 530, connecting rod 530 can realize 360 ° of rotations and 90 ° of upsets relative to chassis 510.Preferably, by the connecting rod of sucker 50 530 are arranged in the hook member of elevating mechanism 40.
Step S104:The tensioning curtain wall inhaul cable on the polycrystalline substance of back timber 10 and curtain wall to be onstructed.Treat purlin vehicle frame 20, lifting After mechanism 40, sucker 50 and the curtain wall inhaul cable all installations, test run and examination are carried out, specifically included:
1st, truss car system test run
After switching on power, first check whether the rotation direction of each motor is consistent with the direction of control knob, then press again The following steps test run:
1) no-load (no load) test:Each mechanism is started under zero load carries out positive and negative test running, checks whether control run is correct, limit Whether the position electrical equipment such as device work is reliable etc..
2) static load test:In the situation that travelling mechanism is motionless, examination is carried out with 1.25 times of rated load and is hung, load is lifted away from Ground about 100mm, hanging 10 minutes, each mechanism should be normal.
3) dynamic load test:Under conditions of static load result of the test is good, dynamic load is carried out with 1.1 times of rated load and is hanged Sky test, experimental period is 40s;6s is risen, stops 14s, drop 6s, stop 14s, so carry out 15 cycles, each position is estimated after experiment It is without exception then qualified.
2nd, truss car examination is hung, checks and accepts
1) organize management to carry out test run to truss car, electric block to inspect for acceptance, it is qualified afterwards with eight pawl electric sucking discs to curtain Wall glass carries out examination and hangs.
2) lift by crane after cladding glass absorption, when cladding glass handling height is similar, shutheight lifting makes electronic calabash Reed during close installation site, is adjusted by the installer of scaffold to glass surface translation is installed to cladding glass.With reference to The adjustable function of eight pawl electric sucking discs is adjusted to cladding glass installation site, angle, direction, and system operation normally puts into afterwards Use.
Step S105:After the completion of examination, it is provided for that the cladding glass of curtain wall to be onstructed is installed on the curtain wall inhaul cable Fastener, the fastener has docking groove, specifically includes:
1st, surveying setting-out
1) according to the complexity and the technical difficulty of precision controlling of job site, determine using local controlled after first overall control The general thought of system, by coordinate system the measurement technique of location control is carried out.
2) because main stress structure is built upon on the basis of civil engineering, therefore the foundation for installing tracking and command network that curtain wall is installed is just According to the SURVEYING CONTROL NETWORK of civil engineering.
3) measured using total powerstation and level gauge, accuracy of instrument is 2 ", and censorship is qualified could use.
2nd, reverse interface is installed
The glass determined by Deepen Design drawing separates, and installs fastener on the curtain wall inhaul cable, it is ensured that installation site In ± 1mm, under glass gravity load, splice system has displacement to tolerance, now by adjusting clamping plate part system fading margin.
Step S106:Cladding glass is installed:Purlin vehicle frame 20 is moved to the top of the installation site of cladding glass to be installed, Cladding glass 60 is adsorbed on the adsorption piece 520 of sucker 50, cladding glass 60 is moved to into the peace using elevating mechanism 40 Holding position is simultaneously installed in the docking groove of the fastener, is specifically included:
1st, lifting prepares
1) before installation exercise, technology should be carried out to the personnel of participation operation and safety is told somebody what one's real intentions are, make each operation people The all clear and definite content of member, the method for employing, technical measures and the safety problem that should be noted that.
2) packaging, transport and storage:During glass processing, it is necessary to enter line label to every block of glass, in-site installation is checked the number Take a seat.Before glass is installed, must be transported in the glass storage rack that glass is specified and preserve, glass applications rope is fastened in transportation, Prevent glass from falling damaged.
3) glass is stacked by size dispersion, the various materials needed for each work surface in a pre-installation should be in place.Cladding glass Should clean totally, and be stacked by erection sequence.
4) should carry out checking the perpendicularity of verification glass fixture before lifting, whether absolute altitude, levelness meets design requirement.Separately Whether enough, there is the barrier of without hindrance installation exercise in outer Inspection face, if any should give removing.
2nd, lifting sequence is determined
Glass hanging follows the order of computer simulation emulation and carries out, to guarantee glass hanging safety, structure safety, lifting The minimum principle of deflection value afterwards.
3rd, assistance platform prepares
Operating platform people from station position that glass outer side is set up completely spreads scaffold board, and two people are ready at all times to scoop out glass, work as glass Near when, hand steered stabilized glass immediately.
4th, glass hanging
1) colligation rope:Before cladding glass 60 is lifted by crane, tied up at glass top Liang Ge angles, for coarse adjustment glass with two ropes Angle, while also protecting cladding glass 60 to touch other objects because of mobile inertia and be damaged.
2) glass is adsorbed:First the surface dirt of cladding glass 60, dirt are wiped totally, notes correctly judging inside and outside face. Sucker 50 has vacuum pump and hydraulic means, and with mechanical engagement cladding glass 60 is picked up, and 360 ° of manual rotation is finely tuned before and after realization 100mm stretches, and the elevation angle adjusts 10 °, along central axis ± 10 °.
3) lifting movement:Guarantee that sucker 50 is inhaled after steady cladding glass 60, slowly at the uniform velocity lift by crane, first complete the shifting of horizontal direction It is dynamic, then slowly glass moved vertically to into installation site again.During handling cladding glass 60, two are put down from scaffold Rope pinions the both sides of cladding glass 60 as lead, so that glass transports to the adjustment of relevant position.
4) frame is entered:Cladding glass 60 in place when, personnel should as early as possible catch sucker 50 on scaffold, the stable cladding glass of control 60, the rope that indoors installer was tied up on cladding glass 60 by before of standing is adjusted to cladding glass 60, while logical Cross the installation site of the adjustable function to cladding glass 60 of combined with sucking disc 50, angle, direction to be adjusted, man-computer cooperation is by curtain wall The diagonal brace of glass 60 goes out installs outer frame, pushes away be pressed into after aligning in the fastener further back, and upper and lower, left and right insert depth wants one Cause.When groove is arranged at top, top is allowed first to enter groove;When groove is arranged at bottom, cladding glass 60 should be slowly put in fastener notch, Immediately fastener is fixed with foam-filled rod, prevent fastener from swinging in groove and cause cracking.
5) adjustment is fixed:After the glass installation of every Pin, plate adjustment should be carried out, the standard of glass adjustment is " horizontal Flat, vertically, face is put down ", adjustment glass glue-line is in the same size.After the completion of cladding glass adjustment, the close of surrounding should be as early as possible fixed Potting pad, alignment error is controlled in ± 3mm, accumulates it, in the control of each layer, distribution, is digested.
Further, after cladding glass 60 is installed in the fastener, also include:
The patch protection gummed paper on the cladding glass of glue-line both sides;And
Gluing is carried out to the cladding glass, the protection gummed paper is removed after the completion of gluing.It is specific as follows:
1) glass is wiped clean using " dimethylbenzene " and defat cotton yarn before gluing, during gluing, outside is led to by scaffold, inner side Cross raising crosshead realize it is two-sided while gluing.
2) patch protects gummed paper, gummed paper to paste the design requirement that meet glue-line on the glass of glue-line both sides before gluing.
3) continuous uniform, operation order is wanted to be during gluing:First erect after horizontal stroke, from top to bottom.To accomplish glue-line and base after injecting glue Material is firmly bonded imporosity, and glue-line is smooth round and smooth.
4) during next day gluing, glue-line junction should clear up the glue head accomplished fluently, and cut off the glue tail of gluing, to ensure to beat twice Glue is completely embedded unification.
5) after glass cement is modified, glass sized paper should will be pasted onto in time and be removed, after glass adhesive curing, should clean inside and outside Glass, properly protect mark.
6) from top to bottom, cleaning Hou Bao relevant departments carry out an acceptance inspection cleaning glass, it is qualified by inspection after, outer behaviour is removed immediately Make scaffold.
Step S107:The step of repeating the installation cladding glass, according to the default erection sequence of cladding glass, will be all Cladding glass install, specifically include:
Purlin vehicle frame 20 is moved to the top of the installation site of the first row cladding glass of curtain wall to be onstructed;
Each cladding glass in first row cladding glass, any one the curtain wall glass wherein in first row cladding glass are installed The installation steps of glass include:Cladding glass 60 is adsorbed on the adsorption piece 520 of sucker 50, using elevating mechanism 40 by curtain wall glass Glass 60 moves to the installation site and is installed in the docking groove of the fastener;And
After each cladding glass installation in the first row cladding glass, the purlin vehicle frame is moved to into next column The installation site of cladding glass simultaneously continues to install next column cladding glass, until all cladding glass in whole curtain wall are installed Finish.Wherein, same row cladding glass takes mode from the bottom up to be installed.
Especially, in a preferred embodiment of the present invention, whole cladding glass is divided into into multiple installation regions, It is respectively provided with a purlin vehicle frame in each installation region the curtain wall glass is installed in each installation region Glass.Cladding glass in each installation region can be synchronous installation, or be installed respectively.
The hanging method of interior inclined curtain wall super large glass of the invention, it is real using purlin vehicle frame and elevating mechanism compound mode Existing cladding glass both can be moved in the horizontal direction, can vertically be moved again, exactly can be installed cladding glass In place, simple to operate, high construction efficiency.
The beneficial effect of the hanging method of interior inclined curtain wall super large glass of the invention is:
1) take microcomputer modelling analogue simulation, determine scientific and rational glass install section, erection sequence, transport and Mounting means, a construction molding.
2) using the hollow ultrawhite LOW-E glass of toughened rubber-laminated vacuum, self-destruction rate is lowered.
3) the reasonable piecemeal of glass, control glass weight is within 500kg, it is to avoid install glass using large-scale crane, while Reduce the construction Deformation of inclined curtain wall.
4) glass hanging may move electronic truss using external scaffolding over height stacking operation platform as operating platform using two-way Car is carried out with reference to eight pawl electric sucking discs, simple to operate, high construction efficiency.
The above is only presently preferred embodiments of the present invention, and any pro forma restriction is not done to the present invention, though So the present invention is disclosed above with preferred embodiment, but is not limited to the present invention, any to be familiar with this professional technology people Member, in the range of without departing from technical solution of the present invention, when using the technology contents of the disclosure above make it is a little change or repair The Equivalent embodiments for equivalent variations are adornd, as long as being the content without departing from technical solution of the present invention, according to the technology reality of the present invention Any simple modification, equivalent variations and modification that confrontation above example is made, still fall within the scope of technical solution of the present invention It is interior.

Claims (10)

1. a kind of hanging method of indoor inclined curtain wall super large glass, it is characterised in that include:
The purlin vehicle frame vertical with the length direction of curtain wall to be onstructed is set on the back timber of curtain wall to be onstructed;
Slide on the purlin vehicle frame and the elevating mechanism that can be translated along the length direction of the purlin vehicle frame is set;
Sucker is set on the elevating mechanism;
The tensioning curtain wall inhaul cable on the polycrystalline substance of the back timber and curtain wall to be onstructed;
The fastener of the cladding glass for being provided for installing curtain wall to be onstructed on the curtain wall inhaul cable, the fastener has refutes Access slot;
Cladding glass is installed:The purlin vehicle frame is moved to the top of the installation site of cladding glass to be installed, by the curtain wall Glass is adsorbed on the sucker, the cladding glass is moved to into the installation site using the elevating mechanism and is installed on In the docking groove of the fastener;
The step of repeating the installation cladding glass, according to the default erection sequence of cladding glass, whole cladding glass is pacified Install complete.
2. the hanging method of interior inclined curtain wall super large glass as claimed in claim 1, it is characterised in that in curtain wall to be onstructed Back timber on the purlin vehicle frame vertical with the length direction of curtain wall to be onstructed is set, including:
Operating platform is set up, the operating platform is connected with the polycrystalline substance;And
The purlin vehicle frame is fixed on the back timber by connecting tooling on the operating platform.
3. the hanging method of interior inclined curtain wall super large glass as claimed in claim 2, it is characterised in that the operating platform Expire hall steel pipe scaffold for fastener type, the full hall steel pipe scaffold of the fastener type is set up using layering, including:
Foot is put in vertical rod, and bar of sweeping the floor is set up on the ground;
Bridging and horizontal brace are set up on the bar of sweeping the floor;And
Set up the scaffold and the bridging in circumferential perimeter of intermediate rest part.
4. the hanging method of interior inclined curtain wall super large glass as claimed in claim 1, it is characterised in that the elevating mechanism For electric block, the electric block is including the hoist engine being slideably positioned on the purlin vehicle frame, on the hoist engine Assembly pulley and the hook member for sucker described in hook block, the hook member is hung by being set around the hoist cable of the assembly pulley Located at the assembly pulley.
5. the hanging method of interior inclined curtain wall super large glass as claimed in claim 1, it is characterised in that the sucker is eight Pawl electric sucking disc, the eight pawls electric sucking disc includes chassis, multiple adsorption pieces and the activity being uniformly laid on the chassis The connecting rod being connected on the chassis.
6. the hanging method of interior inclined curtain wall super large glass as claimed in claim 1, it is characterised in that by the curtain wall glass Before glass is adsorbed on the sucker, also include:Tied up with two ropes is used to adjust in the cladding glass with respect to two sidepieces The angle of the cladding glass is saved, tied up with two ropes is used to protect the cladding glass at the middle part of the cladding glass.
7. the hanging method of interior inclined curtain wall super large glass as claimed in claim 1, it is characterised in that using the lifting The cladding glass is moved into place and is installed in the docking groove of the fastener by mechanism, including:
First the cladding glass is moved in the horizontal direction with the installation site in same perpendicular by the elevating mechanism Face directly;
Again the cladding glass is vertically moved to into the installation site by the elevating mechanism;And
The cladding glass is installed in the docking groove of the fastener.
8. the hanging method of interior inclined curtain wall super large glass as claimed in claim 7, it is characterised in that by the curtain wall glass After glass is installed in the fastener, also include:
The patch protection gummed paper on the cladding glass of glue-line both sides;And
Gluing is carried out to the cladding glass, the protection gummed paper is removed after the completion of gluing.
9. the hanging method of interior inclined curtain wall super large glass as claimed in claim 1, it is characterised in that according to cladding glass Default erection sequence, whole cladding glass is installed, including:
The purlin vehicle frame is moved to the top of the installation site of the first row cladding glass of curtain wall to be onstructed;
Each cladding glass in installation first row cladding glass, wherein any one cladding glass in first row cladding glass Installation steps include:The cladding glass is adsorbed on the sucker, is moved the cladding glass using the elevating mechanism Move the installation site and be installed in the docking groove of the fastener;And
After each cladding glass installation in the first row cladding glass, the purlin vehicle frame is moved to into next column curtain wall The installation site of glass simultaneously continues to install next column cladding glass, until all cladding glass in whole curtain wall are installed.
10. the as claimed in any one of claims 1-9 wherein hanging method of interior inclined curtain wall super large glass, it is characterised in that Whole cladding glass is divided into into multiple installation regions, a purlin vehicle frame is respectively provided with each installation region with The cladding glass is installed in each installation region.
CN201510185374.XA 2015-04-17 2015-04-17 Hoisting method for indoor inclined curtain wall super-large glass Active CN104831846B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510185374.XA CN104831846B (en) 2015-04-17 2015-04-17 Hoisting method for indoor inclined curtain wall super-large glass

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510185374.XA CN104831846B (en) 2015-04-17 2015-04-17 Hoisting method for indoor inclined curtain wall super-large glass

Publications (2)

Publication Number Publication Date
CN104831846A CN104831846A (en) 2015-08-12
CN104831846B true CN104831846B (en) 2017-04-12

Family

ID=53810016

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510185374.XA Active CN104831846B (en) 2015-04-17 2015-04-17 Hoisting method for indoor inclined curtain wall super-large glass

Country Status (1)

Country Link
CN (1) CN104831846B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107558672A (en) * 2016-06-30 2018-01-09 中建八局装饰工程有限公司 Sloping roof super large glaziers method
CN106337520A (en) * 2016-10-28 2017-01-18 广州机施建设集团有限公司 The construction technology of large-cell point glass curtain wall
CN106869516A (en) * 2017-03-08 2017-06-20 上海市全保建筑帷幕有限公司 Electric sucking disc coordinates steam crane to change glass process
CN107503454A (en) * 2017-08-14 2017-12-22 中建八局第三建设有限公司 Super large width bend glass curtain wall mechanization installation method
CN110409838A (en) * 2019-07-22 2019-11-05 湖北香榭丽舍幕墙装饰工程有限公司 Big glass hanging method suitable for narrow construction site
CN110344525A (en) * 2019-07-25 2019-10-18 广东世纪达建设集团有限公司 A kind of super large plate apleuria full glass curtain wall construction method of installation
CN110439293B (en) * 2019-08-24 2021-05-14 陕西建工第九建设集团有限公司 Auxiliary installation equipment for glass curtain wall
CN114215235B (en) * 2021-12-06 2023-07-07 中建八局第二建设有限公司 Super high-rise inclined double-layer special-shaped curtain wall construction device and method
CN114233021A (en) * 2021-12-27 2022-03-25 上海市机械施工集团有限公司 Installation method of bulletproof glass
CN114718329B (en) * 2022-04-20 2024-05-07 广州市第三建筑工程有限公司 Curtain wall installation equipment, use method and curtain wall installation construction method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08284419A (en) * 1995-04-17 1996-10-29 Taisei Corp Suspending jig for outer wall material fitting work and fitting method using that jig
JPH09310500A (en) * 1996-05-21 1997-12-02 Takenaka Komuten Co Ltd Large building lifting method
JPH1144093A (en) * 1997-07-29 1999-02-16 Sumitomo Metal Mining Co Ltd Tool for lifting external wall panel
CN2784492Y (en) * 2004-11-24 2006-05-31 白宝鲲 Hoisting system of glass curtain wall
CN2923902Y (en) * 2006-07-27 2007-07-18 白宝鲲 Suspending system of point-supporting type curtain wall
CN101109195A (en) * 2007-08-20 2008-01-23 北京江河幕墙股份有限公司 Single-layer bidirectional double-rope curtain wall support structure
CN102296830A (en) * 2010-06-22 2011-12-28 武汉凌云建筑装饰工程有限公司 Self-walking track mounting system for special-shaped frame glass curtain wall
CN202542734U (en) * 2012-01-18 2012-11-21 南车青岛四方机车车辆股份有限公司 Glass hoisting and installing device
CN103216105A (en) * 2013-04-18 2013-07-24 成军 Construction method of overhanging inhaul cable type hyperbolic glass curtain wall

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08284419A (en) * 1995-04-17 1996-10-29 Taisei Corp Suspending jig for outer wall material fitting work and fitting method using that jig
JPH09310500A (en) * 1996-05-21 1997-12-02 Takenaka Komuten Co Ltd Large building lifting method
JPH1144093A (en) * 1997-07-29 1999-02-16 Sumitomo Metal Mining Co Ltd Tool for lifting external wall panel
CN2784492Y (en) * 2004-11-24 2006-05-31 白宝鲲 Hoisting system of glass curtain wall
CN2923902Y (en) * 2006-07-27 2007-07-18 白宝鲲 Suspending system of point-supporting type curtain wall
CN101109195A (en) * 2007-08-20 2008-01-23 北京江河幕墙股份有限公司 Single-layer bidirectional double-rope curtain wall support structure
CN102296830A (en) * 2010-06-22 2011-12-28 武汉凌云建筑装饰工程有限公司 Self-walking track mounting system for special-shaped frame glass curtain wall
CN202542734U (en) * 2012-01-18 2012-11-21 南车青岛四方机车车辆股份有限公司 Glass hoisting and installing device
CN103216105A (en) * 2013-04-18 2013-07-24 成军 Construction method of overhanging inhaul cable type hyperbolic glass curtain wall

Also Published As

Publication number Publication date
CN104831846A (en) 2015-08-12

Similar Documents

Publication Publication Date Title
CN104831846B (en) Hoisting method for indoor inclined curtain wall super-large glass
CN101936073B (en) Construction method of combined hidden frame curtain wall of glass and corrugated aluminum sheet
CN106193618B (en) A kind of aerial steel structure truss construction of Long span
WO2021012971A1 (en) Integral lifting construction method for ultra-large hyperbolic integrated unit aluminium plate curtain walls
CN106437178A (en) Integral lifting construction method and integral lifting construction device of veranda of multi-layer steel structure
CN113356597A (en) Lifting process of large-span net rack and truss combined roof
CN111576691B (en) Frame type glass curtain wall mounting method and glass curtain wall system
CN108952178B (en) Bidirectional angular displacement accumulation lifting method for irregular free-form surface steel roof
CN106121255A (en) Apparatus installed by a kind of Super High glass curtain wall
CN107724574B (en) All-transparent louver glass double skin aspiratory curtain wall equivalent space construction technology
CN114319884A (en) Construction method of glass curtain wall
CN113090040A (en) Installation device and method for vertical prefabricated part
CN112411641A (en) Post-disaster house deviation rectifying device and method
CN109653518B (en) Assembly type component efficient pre-assembly equipment capable of quality inspection and electromagnetic hoisting fine adjustment
CN117284942A (en) Construction equipment system and construction method of modularized building
CN104060838B (en) A kind of vestibule divides into groups aerial group to Method for Installation
CN109594697B (en) Construction method and structure of super high-rise built-in unit glass curtain wall
CN108894509B (en) Steel structure assembly type house prefabricated sandwich heat-insulation external wall panel construction method without external frame
CN116427599A (en) Hyperboloid serrated building edge super high-rise curtain wall construction method
Iturralde et al. Comparison of automated and robotic support bodies for building facade upgrading
CN111232808A (en) Transverse installation method of prefabricated modular elevator
CN205653104U (en) Walking crane of cell board curtain installation
CN103912089B (en) A kind of construction method of the lifting furred ceiling of auditorium
WO2008000054A1 (en) Autoliftable bridge crane system for building and tower construction
CN210152143U (en) A connection structure for concrete cladding panel hoist and mount construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant