CN106121255A - Apparatus installed by a kind of Super High glass curtain wall - Google Patents

Apparatus installed by a kind of Super High glass curtain wall Download PDF

Info

Publication number
CN106121255A
CN106121255A CN201610470191.7A CN201610470191A CN106121255A CN 106121255 A CN106121255 A CN 106121255A CN 201610470191 A CN201610470191 A CN 201610470191A CN 106121255 A CN106121255 A CN 106121255A
Authority
CN
China
Prior art keywords
wall
connecting piece
supporting frame
curtain wall
buried
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610470191.7A
Other languages
Chinese (zh)
Inventor
周鹏华
余地华
朱海军
叶建
付国
胡佳楠
刘浩昆
刘磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Co Ltd
Original Assignee
China Construction Third Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Engineering Bureau Co Ltd filed Critical China Construction Third Engineering Bureau Co Ltd
Priority to CN201610470191.7A priority Critical patent/CN106121255A/en
Publication of CN106121255A publication Critical patent/CN106121255A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/167Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements

Abstract

The invention discloses a kind of Super High glass curtain wall and apparatus is installed, including oblique pull steel wire, brace, the pre-buried wall-connecting piece being arranged on multi-layer walls, support connecting bolt, driven hanging basket, cantilever supporting frame and hoisting electric gourd, the two ends of cantilever supporting frame connect undermost pre-buried wall-connecting piece and support connecting bolt respectively, oblique pull steel wire is connected between support connecting bolt and the pre-buried wall-connecting piece of the superiors, and brace is connected between support connecting bolt and the pre-buried wall-connecting piece in intermediate layer;Driven hanging basket and hoisting electric gourd is connected on i-beam track on cantilever supporting frame.The present invention can make management personnel's operation more conveniently, safely, fast, hommization, improve work comfort degree and work efficiency;Peace is torn open simple, can repeatedly recycle;Lifting efficiency is high, and installation rate is fast, and speed of application is greatly improved.

Description

Apparatus installed by a kind of Super High glass curtain wall
Technical field
The present invention relates to building engineering field, apparatus installed by specifically a kind of Super High glass curtain wall.
Background technology
In construction of super highrise building, curtain wall construction is a link important in whole engineering.The installation of curtain wall plate Situation directly affects the aspect such as indoor construction duration, outdoor buildings image progress.Additionally.The installation of curtain wall plate is many with lifting For outdoor overhead operation, operation easier is big, and danger coefficient is big.High-rise building is different from common building, it is impossible to by built etc. Method completes the installation of unit plate.Most of unit plates of curtain wall sizes are big, from great, it is impossible to installed by manpower, it is necessary to Various plant equipment auxiliary is taked to install.
The difficult point that conventional ultra high layer glass curtain wall is installed is that installation unit plate must use tower crane to coordinate, and when installing Between long, installation effectiveness is low, and installation risk is big.In addition, the position curtain wall plate size such as corner of building is special, Ren Yuancao Make space little, be difficult to find safely and effectively operating type.So, glass curtain wall installation difficulty based on high-rise building with choose War, traditional mounting means cannot meet all demands of job site.
Summary of the invention
It is an object of the invention to provide a kind of Super High glass curtain wall and apparatus is installed, to solve above-mentioned background technology The problem of middle proposition.
For achieving the above object, the present invention provides following technical scheme:
Apparatus installed by a kind of Super High glass curtain wall, including oblique pull steel wire, brace, be arranged on multi-layer walls pre-buried Wall-connecting piece, support connecting bolt, driven hanging basket, cantilever supporting frame and hoisting electric gourd, described cantilever supporting frame one end is connected to On undermost pre-buried wall-connecting piece, the cantilever supporting frame other end is provided with support connecting bolt, and described oblique pull steel wire is connected to prop up Between frame connecting bolt and the pre-buried wall-connecting piece of the superiors, described brace is connected to the pre-of support connecting bolt and intermediate layer Bury between wall-connecting piece;Being provided with two row's i-beam tracks on described cantilever supporting frame, described driven hanging basket is connected to outside The lower section of i-beam track, described hoisting electric gourd is arranged on the i-beam track of inner side, the electronic calabash of described lifting Lu Lian is connected to curtain wall unit plate.
As the further scheme of the present invention: described oblique pull steel wire, brace are tight with body of wall by pre-buried wall-connecting piece Connect.
As the further scheme of the present invention: be provided with limit switch and special electronic box on described hoisting electric gourd, The chain of hoisting electric gourd traction rises to limit and the most i.e. automatically powers off.
As the present invention further scheme: described hoisting electric gourd on i-beam track along track level side To moving freely.
Compared with prior art, the invention has the beneficial effects as follows:
The present invention can make management personnel's operation more conveniently, safely, fast, hommization, improve work comfort degree and work efficiency; Peace is torn open simple, can repeatedly recycle;Lifting efficiency is high, and installation rate is fast, and speed of application is greatly improved;By this invention, The demand that tower crane is used by curtain wall lifting can be reduced, it is to avoid the alien invasion that distance lifting in high-altitude brings collides with, lifts installation not The problem such as precisely;High-altitude is provided to build the outer scope of operation for operating personnel;Guarantee the safety of super-high buildings thing work progress, avoid Operation high and medium pendant thing;It is simple, convenient to make, and maintenance and repair is simple.
Accompanying drawing explanation
Fig. 1 is the structural representation of the present invention
In figure: 1-oblique pull steel wire;2-brace;The pre-buried wall-connecting piece of 3-;4-support bracket bolt connects;5-driven hanging basket;6-curtain wall list Unit's plate;7-cantilever supporting frame;8-hoisting electric gourd;9-i-beam track.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Describe, it is clear that described embodiment is only a part of embodiment of the present invention rather than whole embodiments wholely.Based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under not making creative work premise Embodiment, broadly falls into the scope of protection of the invention.
Referring to Fig. 1, in the embodiment of the present invention, a kind of Super High glass curtain wall installs apparatus, including oblique pull steel wire 1, brace 2, pre-buried wall-connecting piece 3, support bracket bolt connect 4, driven hanging basket 5, curtain wall unit plate 6, cantilever supporting frame 7, lifting electronic Calabash 8, i-beam track 9.
Cantilever supporting frame 7 one end is connected on undermost pre-buried wall-connecting piece 3, and cantilever supporting frame 7 other end is provided with support even Connecting bolt 4, oblique pull steel wire 1 is connected between support connecting bolt 4 and the pre-buried wall-connecting piece 3 of the superiors, and brace 2 is connected to prop up Between frame connecting bolt 4 and the pre-buried wall-connecting piece 3 in intermediate layer;Two row's i-beam tracks 9, electric crane are installed on cantilever supporting frame 7 Basket 5 is connected to the lower section of the i-beam track 9 in outside, and hoisting electric gourd 8 is arranged on the i-beam track 9 of inner side, lifting Electric block 8 connects curtain wall unit plate 6.
When structure wall is constructed and need to be arranged hanging basket layer, pre-buried wall-connecting piece 3 is installed in advance, and is cast in floor concrete In, it is ensured that wall-connecting piece has enough bearing capacities and stability.Pre-buried wall-connecting piece 3 installs, and structural floor is constructed to eminence Time, the brace 2 of hanging basket support is installed.Suspension arrangement is used to be conveyed to arrange at floor appointment, on pre-buried wall-connecting piece 3 Connecting plate and hook are installed.This connecting plate is two work lifting ropes and a safety rope so that it is hang down to putting to install and encorbelment The position of support 7.Climb plank is fastened by correct method by workmen with work lifting rope, checks and ascends a height on solid and reliable recoil Plate, fasten seat belts, slowly slide into along lifting rope and cantilever supporting frame 7 upper strata is installed intends installing the pre-buried wall-connecting piece of rigidity stiffener 3 positions, are hung on rigid components on the otic placode of pre-buried wall-connecting piece 3, securing bracket connecting bolt 4 and check firm.
Then slide to the installation site of cantilever lever of driven hanging basket 5 along work lifting rope, operator hang down a lifting rope To the opening of installation floor, lifting rope is toggled installed cantilever supporting frame 7 by the personnel in floor, and level moves on to peace lentamente Holding position, hands over the workmen to lifting rope;Workmen on lifting rope checks cantilever supporting frame 7 one end and post after installation dimension On face, preassembled embedded part otic placode connects, and puts on pin, outside the rigidity stiffener then hung down on upper strata is with cantilever lever End sockets, it is ensured that cantilever supporting frame 7 installs.
When all of parts installation and check firm errorless after, install i-beam track 9, first at cantilever supporting frame 7 Lay scaffold board above, as interim operating platform, then by near structure side order, i-beam track 9 is installed, first Hanging basket outside installation i-beam track 9, then lifts the i-beam track 9 of aluminum veneer inside installation.I-beam track 9 is pacified Install complete, hanging basket is installed successively and uses and lifting electric block 8.After above step is fully completed, installation driven hanging basket 5, and really The rope that ensures safety is connected firmly, and driven hanging basket 5 uses normally.Guarantee that whole device can normally handling level, vertically movable with peace Dress curtain wall unit plate 6.
The present invention can make management personnel's operation more conveniently, safely, fast, hommization, improve work comfort degree and work Efficiency;Peace is torn open simple, can repeatedly recycle;Lifting efficiency is high, and installation rate is fast, and speed of application is greatly improved;By this Invention, can reduce the demand that tower crane is used by curtain wall lifting, it is to avoid the alien invasion that distance lifting in high-altitude brings collides with, lifts peace Fill the problems such as the most accurate;High-altitude is provided to build the outer scope of operation for operating personnel;Guarantee super-high buildings thing work progress safety, Operation high and medium is avoided to fall thing;It is simple, convenient to make, and maintenance and repair is simple.
It is obvious to a person skilled in the art that the invention is not restricted to the details of above-mentioned one exemplary embodiment, Er Qie In the case of the spirit or essential attributes of the present invention, it is possible to realize the present invention in other specific forms.Therefore, no matter From the point of view of which point, all should regard embodiment as exemplary, and be nonrestrictive, the scope of the present invention is by appended power Profit requires rather than described above limits, it is intended that all by fall in the implication of equivalency and scope of claim Change is included in the present invention.Should not be considered as limiting involved claim by any reference in claim.

Claims (4)

1. an apparatus installed by Super High glass curtain wall, including oblique pull steel wire (1), brace (2), is arranged on multi-layer walls On pre-buried wall-connecting piece (3), support connecting bolt (4), driven hanging basket (5), cantilever supporting frame (7) and hoisting electric gourd (8), its Being characterised by, described cantilever supporting frame (7) one end is connected on undermost pre-buried wall-connecting piece (3), cantilever supporting frame (7) other end Being provided with support connecting bolt (4), described oblique pull steel wire (1) is connected to the pre-buried company of support connecting bolt (4) and the superiors Between wall part (3), described brace (2) is connected between the pre-buried wall-connecting piece (3) in support connecting bolt (4) and intermediate layer; Being provided with two row's i-beam tracks (9) on described cantilever supporting frame (7), described driven hanging basket (5) is connected to the I-shaped in outside The lower section of steel track (9), described hoisting electric gourd (8) is arranged on the i-beam track (9) of inner side, described lifting electricity Dynamic calabash (8) connects curtain wall unit plate (6).
2. according to the Super High glass curtain wall described in claims 1, apparatus is installed, it is characterised in that described oblique rollering steel Silk (1), brace (2) are by pre-buried wall-connecting piece (3) and body of wall compact siro spinning technology.
3. according to the Super High glass curtain wall described in claims 1, apparatus is installed, it is characterised in that described lifting electricity Being provided with limit switch and special electronic box on dynamic calabash (8), the chain that hoisting electric gourd (8) draws rises to limit height i.e. Automatically power off.
4. according to the Super High glass curtain wall described in claims 1, apparatus is installed, it is characterised in that described lifting electricity Dynamic calabash (8) moves freely along track horizontal direction on i-beam track (9).
CN201610470191.7A 2016-06-26 2016-06-26 Apparatus installed by a kind of Super High glass curtain wall Pending CN106121255A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610470191.7A CN106121255A (en) 2016-06-26 2016-06-26 Apparatus installed by a kind of Super High glass curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610470191.7A CN106121255A (en) 2016-06-26 2016-06-26 Apparatus installed by a kind of Super High glass curtain wall

Publications (1)

Publication Number Publication Date
CN106121255A true CN106121255A (en) 2016-11-16

Family

ID=57268831

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610470191.7A Pending CN106121255A (en) 2016-06-26 2016-06-26 Apparatus installed by a kind of Super High glass curtain wall

Country Status (1)

Country Link
CN (1) CN106121255A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109555302A (en) * 2019-01-04 2019-04-02 万华节能科技集团股份有限公司 A kind of the hanging basket bracket and its construction technology of thermal-insulating leakage-resistant crossed construction
CN110485698A (en) * 2019-08-28 2019-11-22 中国建筑第八工程局有限公司 Horizontally moveable hanging basket sliding system
CN112110330A (en) * 2020-09-21 2020-12-22 中建二局第一建筑工程有限公司 Curtain wall unit body rail hoisting system and method
CN113047595A (en) * 2021-03-25 2021-06-29 中国十七冶集团有限公司 External hanging basket installation structure of building wall and construction method thereof
CN113309363A (en) * 2021-06-30 2021-08-27 中建六局建设发展有限公司 Installation method of double-ring rail system of super high-rise unit type curtain wall
CN113734943A (en) * 2021-08-27 2021-12-03 湖北富烨装饰工程有限公司 Rail type hoisting tool for mounting building curtain wall
CN113914638A (en) * 2021-11-29 2022-01-11 中国建筑一局(集团)有限公司 Overhanging steel beam double-rail curtain wall hoisting system and curtain wall plate hoisting method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3460308A (en) * 1964-08-21 1969-08-12 Elcon Ag Manufacture of structural units
CN101514586A (en) * 2009-01-14 2009-08-26 北京江河幕墙股份有限公司 Hanger rail type electric hanging boat and high-rise long span house, bridge building construction method and use thereof
CN201433079Y (en) * 2009-05-26 2010-03-31 中国建筑第八工程局有限公司 High-altitude inclined supporting wire lifting device for construction curtain wall
CN103711301A (en) * 2013-12-30 2014-04-09 江河创建集团股份有限公司 Construction method and device for two-track movable electric basket and lifting hoist
CN204703534U (en) * 2015-05-27 2015-10-14 中建三局(厦门)建设有限公司 A kind of large-scale unit plates of curtain wall two-rail hanging apparatus

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3460308A (en) * 1964-08-21 1969-08-12 Elcon Ag Manufacture of structural units
CN101514586A (en) * 2009-01-14 2009-08-26 北京江河幕墙股份有限公司 Hanger rail type electric hanging boat and high-rise long span house, bridge building construction method and use thereof
CN201433079Y (en) * 2009-05-26 2010-03-31 中国建筑第八工程局有限公司 High-altitude inclined supporting wire lifting device for construction curtain wall
CN103711301A (en) * 2013-12-30 2014-04-09 江河创建集团股份有限公司 Construction method and device for two-track movable electric basket and lifting hoist
CN204703534U (en) * 2015-05-27 2015-10-14 中建三局(厦门)建设有限公司 A kind of large-scale unit plates of curtain wall two-rail hanging apparatus

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109555302A (en) * 2019-01-04 2019-04-02 万华节能科技集团股份有限公司 A kind of the hanging basket bracket and its construction technology of thermal-insulating leakage-resistant crossed construction
CN110485698A (en) * 2019-08-28 2019-11-22 中国建筑第八工程局有限公司 Horizontally moveable hanging basket sliding system
CN110485698B (en) * 2019-08-28 2021-07-09 中国建筑第八工程局有限公司 Sliding system capable of horizontally moving hanging basket
CN112110330A (en) * 2020-09-21 2020-12-22 中建二局第一建筑工程有限公司 Curtain wall unit body rail hoisting system and method
CN112110330B (en) * 2020-09-21 2023-03-14 中建二局第一建筑工程有限公司 Curtain wall unit body rail hoisting system and method
CN113047595A (en) * 2021-03-25 2021-06-29 中国十七冶集团有限公司 External hanging basket installation structure of building wall and construction method thereof
CN113309363A (en) * 2021-06-30 2021-08-27 中建六局建设发展有限公司 Installation method of double-ring rail system of super high-rise unit type curtain wall
CN113734943A (en) * 2021-08-27 2021-12-03 湖北富烨装饰工程有限公司 Rail type hoisting tool for mounting building curtain wall
CN113734943B (en) * 2021-08-27 2023-10-20 湖北富烨装饰工程有限公司 Rail mounted lifting device for building curtain installation
CN113914638A (en) * 2021-11-29 2022-01-11 中国建筑一局(集团)有限公司 Overhanging steel beam double-rail curtain wall hoisting system and curtain wall plate hoisting method

Similar Documents

Publication Publication Date Title
CN106121255A (en) Apparatus installed by a kind of Super High glass curtain wall
CN205077885U (en) Building core section of thick bamboo hydraulic pressure intelligence protection platform that climbs
CN109779244A (en) A kind of self-elevating type elevator hoistway exterior wall creeping formwork operating platform construction
CN103711301A (en) Construction method and device for two-track movable electric basket and lifting hoist
CN103603504B (en) The dynamo-electric heavy caliber standpipe of super highrise building is with the method for main body progress lifting construction
CN104477736A (en) Shaft elevator installation method
CN208814562U (en) A kind of visualization formula glass curtain wall plate vertical transit system
CN204899185U (en) Adhere to formula lift high altitude construction device
CN104929353A (en) Detachable stepwise automatic climbing operating platform for elevator shafts
CN203143872U (en) Mobile platform for elevator installation construction
CN103821375A (en) Hanging boat auxiliary hung ceiling curtain wall installing method
CN105040965A (en) Attached type raising and falling overhead working device and construction method
CN209145256U (en) The dedicated climbing frame of assembled architecture
CN204418629U (en) A kind of integrated form climbing frame
CN202441045U (en) Rail-type electric attached lifting scaffold
CN111762658A (en) Method for installing elevator in deep foundation pit construction by reverse construction method
CN107215748A (en) The special building hoist of hoistway and its installation method
CN203257106U (en) Multifunctional power-driven walking type walking system
CN114439213A (en) Shaft operation platform device and construction method thereof
CN114165061A (en) Construction method of vertical transportation system
CN113445723A (en) Construction platform for mounting overhanging structure curtain wall and mounting method
CN209704009U (en) A kind of construction of lift well safety protection structure
Gao Construction Technology and Key Points of Vertical Transportation in Shaft of Office Building
JP2878936B2 (en) Elevator installation method
CN103225390A (en) Hollow facade pulley guide attached-type lifting scaffold

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20161116

RJ01 Rejection of invention patent application after publication