CN201433079Y - High-altitude inclined supporting wire lifting device for construction curtain wall - Google Patents

High-altitude inclined supporting wire lifting device for construction curtain wall Download PDF

Info

Publication number
CN201433079Y
CN201433079Y CN2009200729798U CN200920072979U CN201433079Y CN 201433079 Y CN201433079 Y CN 201433079Y CN 2009200729798 U CN2009200729798 U CN 2009200729798U CN 200920072979 U CN200920072979 U CN 200920072979U CN 201433079 Y CN201433079 Y CN 201433079Y
Authority
CN
China
Prior art keywords
track
rope
fixed
altitude
curtain
Prior art date
Application number
CN2009200729798U
Other languages
Chinese (zh)
Inventor
丁志强
田宝吉
武志宏
张耀龙
车杰
Original Assignee
中国建筑第八工程局有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中国建筑第八工程局有限公司 filed Critical 中国建筑第八工程局有限公司
Priority to CN2009200729798U priority Critical patent/CN201433079Y/en
Application granted granted Critical
Publication of CN201433079Y publication Critical patent/CN201433079Y/en

Links

Abstract

The utility model provides a high-altitude inclined supporting wire lifting device for a construction curtain wall, which comprises a ropy track formed by two parallel ropes, a track hanger, a windlass, a support piece capable of sliding along the ropy track, and a sling. The track hanger is fixed at the top of a building; one ends of the parallel ropes of the ropy track are fixed on the track hanger and the other ends thereof are fixed on the ground; the support piece is arranged on the ropy track in a sliding manner through a sliding part arranged on the support piece; the windlass is fixedbelow the track hanger; the sling wound on the windlass is connected with the support piece through a pulley block; and the windlass can be used to drive the sling to pull the curtain wall unit placedon the support piece to a set position. By adopting the technical scheme, the construction progress is greatly quickened, the life cycle of equipment is shortened, the construction cost is reduced, and the construction is free from the influence of foggy days owning to the adoption of the ropy track for lifting.

Description

The rope overhead hoist is tiltedly held in a kind of building curtain wall high-altitude

Technical field

The utility model relates to the overhead hoist of building engineering field, and specifically in the building curtain wall work progress, the rope overhead hoist is tiltedly held in the high-altitude that is used for handling curtain wall unit body.

Background technology

Building curtain wall is to make one deck ornament at building external, can play the effect that decorative appearance beautifies building and energy savings.In the work progress of building curtain wall, be on the exterior wall that is mounted to building with one one of employed cell cube in the building curtain wall, the construction characteristic of this building curtain wall unit body is that block-by-block is successively constructed from bottom to top, and because the construction characteristic of this building curtain wall can't utilize exterior wall scaffold in the work progress of building curtain wall; And because the weight of curtain wall unit body is bigger, every of the cell cube of some material reaches 260kg, and building curtain wall is also different according to the height of different its installations of engineering, the setting height(from bottom) of some engineering construction curtain wall will reach more than hundred meters, therefore the curtain wall unit body can not be placed on the hanging basket the inside installs, generally all be directly with winch pulling hoist cable, with the handling of curtain wall unit body to desired height, install by operating personal then, it only has single hoist cable to hang liter in the handling process, and demand side is to rocking and problem such as rotation in hanging the process of liter; And will consider also that in the middle of handling upper air current, sea fog or the like factor all gives the handling of glass curtain wall unit plate and the adverse effect that installation brings, construction is difficulty very.In view of the above shortcoming of prior art, be necessary to propose a kind of building curtain wall overhead hoist, to solve the difficulty in the building curtain wall work progress.

Summary of the invention

The technical problems to be solved in the utility model is to provide a kind of building curtain wall high-altitude tiltedly to hold the rope overhead hoist, the rope form track is set between ground and roof, by the curtain wall unit body is positioned in the supporting parts, curtain wall unit body to be installed is cooperated the position of the handling of rope form orbitally stable with a winch by hoist cable, to solve the deficiency in the existing curtain wall unit body construction installation process to installation.

For solving above technical matters, the utility model provides a kind of building curtain wall high-altitude tiltedly to hold the rope overhead hoist, it comprises a track suspension bracket, a winch, an and hoist cable, it is characterized in that: also comprise the rope form track that two parallel ropes constitute, one have can be along the supporting parts of rope form slide, and described track suspension bracket is fixed in the top of building body; Two parallel ropes, one end of described rope form track is fixed in described track suspension bracket, and the other end is fixed on the ground; Described supporting parts is mounted slidably on these two parallel tracks by the sliding part on it; Described winch is fixed in the below of described track suspension bracket; Described hoist cable is set around on the winch, and by being connected with described supporting parts at its end behind the assembly pulley.

Further improvement of the utility model is: two parallel ropes of described rope form track are cable wire.

Further improvement of the utility model is: described supporting parts comprises a steel pipe and a supporting plate, and wherein this supporting plate is connected with this steel pipe, is respectively equipped with two sliding parts in addition in the two ends of this steel pipe.

Further improvement of the utility model is: described assembly pulley is made up of two fixed pulleys, and wherein first fixed pulley is fixed in the below of described suspension bracket, and second fixed pulley is fixed in the place ahead of described winch.

Further improvement of the utility model is: described hoist cable is a steel rope.

Further improvement of the utility model is: described sliding part is a steel ring.

By above-described technical scheme, the rope overhead hoist is tiltedly held in the building curtain wall high-altitude that the utility model provides, by the rope form track that between ground and suspension bracket, is provided with, the curtain wall unit body that needs handling is positioned over and can utilizes an assembly pulley and a winch will treat that by a hoist cable pulling supporting parts curtain wall unit body handling of handling is to required setting height(from bottom) along on the supporting parts of rope form slide; Utilize this technical scheme, accelerating construction progress greatly shortens the equipment operating cycles, has reduced engineering cost, and in work progress owing to adopt track delivery, and not to be subjected to the influence of foggy weather.

Description of drawings

Fig. 1 is the front elevation of the overhead hoist of the utility model one preferred embodiment;

Fig. 2 is the lateral plan of the overhead hoist of the utility model one preferred embodiment; And

Fig. 3 is the partial perspective view of the utility model one preferred embodiment.

The specific embodiment

The utility model is described in further detail below in conjunction with the drawings and specific embodiments.

With reference to figure 1 is the front elevation of the overhead hoist of the utility model one preferred embodiment, and Fig. 2 is the lateral plan of the overhead hoist of the utility model one preferred embodiment, simultaneously with reference to figure 3.The utility model building curtain wall high-altitude is tiltedly held the rope overhead hoist and is comprised a track suspension bracket 10, and this track suspension bracket 10 is fixed on the roof 20 of building; Article two, the rope form track 30 that constitutes of parallel rope, two parallel ropes of this rope form track 30 are cable wire in this embodiment, and the one end is fixed on the track suspension bracket 10, the other end is fixed on the ground, thereby forms bevelled rope form track 30 between ground and track suspension bracket 10; One supporting parts 40, described in this embodiment supporting parts 40 is for comprising a steel pipe 41 and a supporting plate 42, wherein this supporting plate 42 is connected by the ring-type cable wire with this steel pipe 41, be respectively equipped with two sliding parts in addition in the two ends of this steel pipe 41, this two sliding part is two steel rings 43 that are fixed on the steel pipe 41 in this embodiment, and these two steel rings 43 are sheathed on respectively on two ropes of rope form track 30, and curtain wall unit body 80 is to be positioned on the supporting plate 42 in the handling process; One winch 50, this winch 50 is fixed in the below of track suspension bracket; One assembly pulley 60, in this embodiment, assembly pulley 60 comprises first fixed pulley 61 and second fixed pulley 62, and wherein first fixed pulley 61 is fixed in the below of track suspension bracket 10, and second fixed pulley 62 is fixed in the place ahead of winch 50; One hoist cable 70, this hoist cable 70 are set around on the winch 50 and by described assembly pulley 60, are located on the described supporting plate 40 at its terminal hook, by these winch 50 pulling hoist cables 70, can make supporting plate 40 slowly rise to the desired position along rope form track 30.

In concrete work progress, two rope form tracks must be strained exceptionally straight fixation between ground and roofing, with each parts all after the installation, curtain wall unit body 80 is positioned on the described supporting plate 42, operate winch 50 then, curtain wall unit body 80 is promoted to the position of installation with hoist cable 70 pulling supporting plate 42 slowly, by activity crane operation person is installed then, puts down suspension hook, hang the hanger of cell cube, slowly lifting, cell cube is moved to rational position, and cell cube below installation personnel hooks cell cube bottom clamp with long cleek, moves cell cube to installation site, and lay down hoist cable rapidly, then with hand steered firmly cell cube; And cooperate with the top operating personal, this cell cube is mounted on the body of wall.

From the above, the utility model is curtain wall unit body 80 to be promoted in the position process of installation at hoist cable 70 pulling supporting plates 42, two the parallel rope form tracks 30 of arranging in pairs or groups, allow the supporting plate 42 that is placed with curtain wall unit body 80 can be to the liter of hanging oneself under stable status, can not wave to avoid taking place safety misadventure, simultaneously because rope form track of the present utility model 30 cooperates the constructional difficulties degree in the time of can solving upper air current or foggy weather bad visibility.

Be understandable that the detailed description of the foregoing description is in order to set forth and explain principle of the present utility model rather than to the qualification of protection domain of the present utility model.Under the prerequisite that does not break away from purport of the present utility model, one of ordinary skill in the art can be made modification by the understanding to the principle of being instructed of technique scheme on these embodiment bases, changes and changes.Therefore protection domain of the present utility model by appended claim with and be equal to and limit.

Claims (6)

1, the rope overhead hoist is tiltedly held in a kind of building curtain wall high-altitude, it comprises a track suspension bracket, a winch, and a hoist cable, it is characterized in that: also comprise the rope form track that two parallel ropes constitute, one have can be along the supporting parts of rope form slide, and described track suspension bracket is fixed in the top of building body; Two parallel ropes, one end of described rope form track is fixed in described track suspension bracket, and the other end is fixed on the ground; Described supporting parts is mounted slidably on these two parallel tracks by the sliding part on it; Described winch is fixed in the below of described track suspension bracket; Described hoist cable is set around on the winch, and by being connected with described supporting parts at its end behind the assembly pulley.
2, the rope overhead hoist is tiltedly held in building curtain wall as claimed in claim 1 high-altitude, and it is characterized in that: two parallel ropes of described rope form track are cable wire.
3, the rope overhead hoist is tiltedly held in building curtain wall as claimed in claim 1 or 2 high-altitude, and it is characterized in that: described supporting parts is for comprising a steel pipe and a supporting plate, and wherein this supporting plate is connected with this steel pipe, is respectively equipped with two sliding parts in addition in the two ends of this steel pipe.
4, the rope overhead hoist is tiltedly held in building curtain wall as claimed in claim 1 or 2 high-altitude, and it is characterized in that: described assembly pulley is made up of two fixed pulleys, and wherein first fixed pulley is fixed in the below of described suspension bracket, and second fixed pulley is fixed in the place ahead of described winch.
5, the rope overhead hoist is tiltedly held in building curtain wall as claimed in claim 1 or 2 high-altitude, and it is characterized in that: described hoist cable is a steel rope.
6, the rope overhead hoist is tiltedly held in building curtain wall as claimed in claim 3 high-altitude, and it is characterized in that: described sliding part is a steel ring.
CN2009200729798U 2009-05-26 2009-05-26 High-altitude inclined supporting wire lifting device for construction curtain wall CN201433079Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009200729798U CN201433079Y (en) 2009-05-26 2009-05-26 High-altitude inclined supporting wire lifting device for construction curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009200729798U CN201433079Y (en) 2009-05-26 2009-05-26 High-altitude inclined supporting wire lifting device for construction curtain wall

Publications (1)

Publication Number Publication Date
CN201433079Y true CN201433079Y (en) 2010-03-31

Family

ID=42051889

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009200729798U CN201433079Y (en) 2009-05-26 2009-05-26 High-altitude inclined supporting wire lifting device for construction curtain wall

Country Status (1)

Country Link
CN (1) CN201433079Y (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101913542A (en) * 2010-06-30 2010-12-15 浙江鸿翔建设集团有限公司 Curtain wall unit lifting device and construction method thereof
CN101934994A (en) * 2010-08-30 2011-01-05 广东省第四建筑工程公司 Building high-altitude vertical hoisting double-guide cable system and assisting method
CN102031875A (en) * 2010-12-24 2011-04-27 青建集团股份公司 Method for installing precast slab
CN102283157A (en) * 2011-07-16 2011-12-21 蓬莱市安源水产有限公司 Sea cucumber pond reversing device
CN102777048A (en) * 2012-06-06 2012-11-14 苏州金螳螂幕墙有限公司 Vertical transportation device
CN103790390A (en) * 2014-03-06 2014-05-14 中国建筑第二工程局有限公司 Glass plate hoisting system for large-span dome glass curtain wall construction and construction method thereof
CN104929377A (en) * 2015-06-30 2015-09-23 中国五冶集团有限公司 Loading system used for vertical conveying of large venue curtain wall veneer
CN104960855A (en) * 2015-06-12 2015-10-07 中国建筑第八工程局有限公司 Transporting device for spherical surface curtain wall structure and transporting method
CN105019668A (en) * 2015-06-30 2015-11-04 中国五冶集团有限公司 Transporting apparatus suitable for curtain veneers of different sizes
CN106121255A (en) * 2016-06-26 2016-11-16 中建三局集团有限公司 Apparatus installed by a kind of Super High glass curtain wall
CN106586908A (en) * 2016-11-16 2017-04-26 上海市建筑装饰工程集团有限公司 Vertical stone conveying lifting basket inside external wall scaffold
CN106586907A (en) * 2016-11-16 2017-04-26 上海市建筑装饰工程集团有限公司 Installation and use method of stone vertical-conveyance lifting basket inside external wall scaffold
CN106946163A (en) * 2017-05-03 2017-07-14 武汉科技大学 Drum type filter screen A shapes frame installs special tooling
CN107190991A (en) * 2017-07-10 2017-09-22 北京江河幕墙系统工程有限公司 The special-shaped curtain wall vertical lifting system of glass plate
WO2018064714A1 (en) * 2016-10-04 2018-04-12 Ginco Industries Pty Ltd Moving system, method of moving an item and related components
CN110844847A (en) * 2019-11-14 2020-02-28 上海宝冶集团有限公司 High-altitude material conveying protection device for building

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101913542A (en) * 2010-06-30 2010-12-15 浙江鸿翔建设集团有限公司 Curtain wall unit lifting device and construction method thereof
CN101913542B (en) * 2010-06-30 2013-06-19 浙江鸿翔建设集团有限公司 Curtain wall unit lifting device and construction method thereof
CN101934994A (en) * 2010-08-30 2011-01-05 广东省第四建筑工程公司 Building high-altitude vertical hoisting double-guide cable system and assisting method
CN102031875A (en) * 2010-12-24 2011-04-27 青建集团股份公司 Method for installing precast slab
CN102031875B (en) * 2010-12-24 2013-01-02 青建集团股份公司 Method for installing precast slab
CN102283157A (en) * 2011-07-16 2011-12-21 蓬莱市安源水产有限公司 Sea cucumber pond reversing device
CN102777048A (en) * 2012-06-06 2012-11-14 苏州金螳螂幕墙有限公司 Vertical transportation device
CN103790390A (en) * 2014-03-06 2014-05-14 中国建筑第二工程局有限公司 Glass plate hoisting system for large-span dome glass curtain wall construction and construction method thereof
CN103790390B (en) * 2014-03-06 2015-11-18 中国建筑第二工程局有限公司 The glass plate Lift-on/Lift-off System of large-span domes Glass Curtain Wall Construction and construction method thereof
CN104960855A (en) * 2015-06-12 2015-10-07 中国建筑第八工程局有限公司 Transporting device for spherical surface curtain wall structure and transporting method
CN105019668A (en) * 2015-06-30 2015-11-04 中国五冶集团有限公司 Transporting apparatus suitable for curtain veneers of different sizes
CN104929377A (en) * 2015-06-30 2015-09-23 中国五冶集团有限公司 Loading system used for vertical conveying of large venue curtain wall veneer
CN104929377B (en) * 2015-06-30 2017-03-08 中国五冶集团有限公司 For the Load System that large stadium curtain wall decoration panel is vertically transported
CN106121255A (en) * 2016-06-26 2016-11-16 中建三局集团有限公司 Apparatus installed by a kind of Super High glass curtain wall
WO2018064714A1 (en) * 2016-10-04 2018-04-12 Ginco Industries Pty Ltd Moving system, method of moving an item and related components
CN106586907A (en) * 2016-11-16 2017-04-26 上海市建筑装饰工程集团有限公司 Installation and use method of stone vertical-conveyance lifting basket inside external wall scaffold
CN106586908B (en) * 2016-11-16 2019-07-12 上海市建筑装饰工程集团有限公司 Stone Vertical transports hanging basket in exterior wall scaffold
CN106586907B (en) * 2016-11-16 2019-04-09 上海市建筑装饰工程集团有限公司 The installation and application of Stone Vertical transport hanging basket in exterior wall scaffold
CN106586908A (en) * 2016-11-16 2017-04-26 上海市建筑装饰工程集团有限公司 Vertical stone conveying lifting basket inside external wall scaffold
CN106946163A (en) * 2017-05-03 2017-07-14 武汉科技大学 Drum type filter screen A shapes frame installs special tooling
CN107190991A (en) * 2017-07-10 2017-09-22 北京江河幕墙系统工程有限公司 The special-shaped curtain wall vertical lifting system of glass plate
CN110844847A (en) * 2019-11-14 2020-02-28 上海宝冶集团有限公司 High-altitude material conveying protection device for building

Similar Documents

Publication Publication Date Title
CN205653092U (en) Tower crane of band plate material bracket
CN102409838B (en) Moveable operating platform and method for constructing suspended ceiling of roof by using same
CN202080836U (en) Material lifting equipment for aerial operation
CN201545635U (en) Holding rod with double flat arms
CN204983613U (en) Hoist and mount system of cell board curtain installation
CN104278637B (en) A kind of main rope of suspension bridge strand is without the cableway erection method in cat road
CN206203720U (en) A kind of roofing device for hoisting
CN106121234B (en) A kind of mounting tool and installation method of roof large span large-diameter pipeline
CN105565146B (en) Suspension hook holding structure, crane and suspension hook fixing means
CN201971572U (en) Movable arm type tower crane with suspension arm possible of being folded for dismounting
CN203855328U (en) Novel hoisting machine
CN104948211A (en) Large mining height end-mining net hanging process
CN205489264U (en) Hydraulic pressure assembled crossing structure
CN202400722U (en) Device for hoisting heavy object with large length-width ratio
CN201809077U (en) Portable curtain wall material lifting device
CN102756975A (en) Method for hoisting rolling mill housing
CN103086279B (en) Vertical transportation construction method for building construction
CN201228207Y (en) Portable window hoister
CN202245811U (en) Combined curtain wall hoisting equipment
CN102910532B (en) Method for butting and hoisting large box type derricks in air
CN104088449B (en) Safe and fast double-track construction platform of super high-rise curtain wall
CN103991800A (en) Roof surface crane for building
CN102536249A (en) Fast construction method of headframe lifting system
CN206502579U (en) Power pole hoisting device
CN104495632A (en) Expanded type suspension rope lifting and hoisting system

Legal Events

Date Code Title Description
GR01 Patent grant
C14 Grant of patent or utility model
CX01 Expiry of patent term

Granted publication date: 20100331

CX01 Expiry of patent term