JPH07173848A - Underground space construction method - Google Patents

Underground space construction method

Info

Publication number
JPH07173848A
JPH07173848A JP5344202A JP34420293A JPH07173848A JP H07173848 A JPH07173848 A JP H07173848A JP 5344202 A JP5344202 A JP 5344202A JP 34420293 A JP34420293 A JP 34420293A JP H07173848 A JPH07173848 A JP H07173848A
Authority
JP
Japan
Prior art keywords
tunnels
underground
retaining materials
excavation
mountain retaining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP5344202A
Other languages
Japanese (ja)
Inventor
Hisashi Nomoto
寿 野本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nishimatsu Construction Co Ltd
Original Assignee
Nishimatsu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nishimatsu Construction Co Ltd filed Critical Nishimatsu Construction Co Ltd
Priority to JP5344202A priority Critical patent/JPH07173848A/en
Publication of JPH07173848A publication Critical patent/JPH07173848A/en
Pending legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

PURPOSE:To secure an underground space with safety and efficiency by building at least four tunnels underground and installing an earth retaining material in the horizontal and vertical directions from inside the tunnels so that the tunnels may be closed. CONSTITUTION:Four tunnels 1 are built up based on a longitudinal ridge of an excavation scheduled rectangular parallelepiped as its central axis. Earth retaining materials 2a and 2b in the horizontal and vertical directions are installed from inside the tunnels in such a fashion that they may close the region between the tunnels 1. Using a steel pipe circular-shaped in cross section, earth retaining materials 2a and 2b which adjoin each of the earth retaining materials 2 and 2b and provided with a cut-off blade are used in the case when an underground water level is high. Then, the internal parts of the space closed by the earth retaining materials 2a and 2b are excavated so as to obtain a space whose size is specified. This construction makes it possible to prevent the ground collapse even when an initial scheduled site is excavated and omit the ground excavation from the ground to the ceiling site which is scheduled for excavation and secure the underground space with safety and efficiency.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は地下空間築造方法に関す
るもので、特に、地下ホーム拡径部、地下駅等のトンネ
ル軸方向の断面積が変化する地下構造物の構築に好適
な、または地下に大断面の空間を得るに適した地下空間
築造方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an underground space, and is particularly suitable for constructing an underground structure such as a diameter expansion part of an underground platform or an underground station whose sectional area in the axial direction of the tunnel changes, or underground. The present invention relates to an underground space construction method suitable for obtaining a large-section space.

【0002】[0002]

【従来の技術】従来、この種の複雑な形状の構築物を地
下に築造するには、開削工法が一般的に採用され実施さ
れている。また、一部に開削工法に代え、異形断面シー
ルド工法も提案されている。
2. Description of the Related Art Conventionally, an excavation method has been generally adopted and practiced for constructing a complex structure of this kind underground. In addition, in place of the open-cut method, a modified cross-section shield method has also been proposed.

【0003】[0003]

【発明が解決しようとする課題】しかし、上記開削工法
は、地下空間の断面を変化させることが可能で、大断面
の地下空間を得ることも可能であるが、地上からの施工
であるため、地下築造物が道路下を予定してる場合であ
れば道路の一部を占用することにより、交通渋滞を招く
等の支障を来すという課題を有している。
However, the above-mentioned excavation method can change the cross section of the underground space, and it is also possible to obtain a large cross-section underground space, but since it is construction from the ground, If an underground structure is planned to be under the road, occupying a part of the road causes a problem such as causing traffic congestion.

【0004】また、道路下には電気配線、ガス管、上下
水道管、電話線等の地下埋設物が錯綜している場合に
は、これら地下埋設物の切り回しまたは防護工法が必要
となり、経済的にも工期的にも無駄が多いという課題を
有していた。
Further, when underground wiring such as electric wiring, gas pipes, water and sewer pipes, telephone lines and the like are complicated under the road, it is necessary to turn around or protect the underground underground, which is economical. There was a problem that there was a lot of waste both in terms of time and construction period.

【0005】さらに、最近はこれら地下築造物の築造深
度は益々深くなる傾向を有し、深度が深くなるにしたが
って、開削工法は大規模・難工事となり、工費はかさ
み、工期は長くなるという課題を有している。
Further, recently, the depth of construction of these underground structures tends to be deeper and deeper, and as the depth becomes deeper, the excavation method becomes large-scale and difficult construction, the construction cost is high, and the construction period becomes long. have.

【0006】また、従来の異形断面シールド工法は、異
形といっても現段階では複円形、楕円等の単円断面では
ないものであって、一部途中でトンネル径を縮径する方
法は提案されているが、地下空間の断面積を途中で適宜
変化させることまでは実現できていないという課題を有
している。また、異形断面シールド工法の断面の大きさ
は特に制約を有さないが、シールド機の製造価格、切羽
の安定のための土圧、泥水圧の設定の困難性等の要因
で、実際には直径十数メートル以下のものしが施工実績
がない。したがって、この種異形断面シールド工法で断
面積を変化させたり、大断面の地下空間を得るには、拡
径事後工法が必要となり、さらには、この拡径事後工法
は地盤崩壊を防ぐため薬液注入等の補助工法が原則とし
て必要となりこの拡径事後工法は危険性と工費増大を伴
うという課題を有していた。
Further, the conventional irregular cross-section shield construction method is not a single circular cross section such as a double circle or an ellipse at this stage even though it is called an irregular shape, and a method of reducing the tunnel diameter in the middle is proposed. However, there is a problem that it cannot be realized until the cross-sectional area of the underground space is appropriately changed on the way. In addition, although the size of the cross-section of the modified cross-section shield method is not particularly limited, due to factors such as the manufacturing cost of the shield machine, the earth pressure for stabilizing the face, the difficulty of setting the mud pressure, etc. Those with a diameter of a few dozen meters or less have no construction record. Therefore, in order to change the cross-sectional area and obtain a large cross-section underground space by this type of variant cross-section shield method, a diameter expansion post-construction method is required. As a general rule, an auxiliary construction method such as this is required, and this post-diameter expansion construction method has a problem that it involves danger and an increase in construction cost.

【0007】そこで、本発明は上記課題に鑑みなされた
もので、地下に予め複雑な形状の構造物を構築するため
の空間を、安全・効率的に確保できる地下空間築造方法
を提供することを目的としたものである。
Therefore, the present invention has been made in view of the above problems, and it is an object of the present invention to provide a method for constructing an underground space in which a space for constructing a structure having a complicated shape in advance can be secured safely and efficiently. It is intended.

【0008】[0008]

【課題を解決するための手段】上記の目的に沿い、先述
特許請求の範囲を要旨とする本発明の構成は前述課題を
解決するために、地下にトンネル1を少なくも4本以上
築造し、該トンネル1内より横方向の山留材2a,2
a,2a・・・及び縦方向の山留材2b,2b,2b・
・・を該トンネル1,1,1・・・間を閉合するように
設置し、該山留材2a,2b群によって閉合された内部
を掘削する技術的手段を講じたものである。
In order to solve the above-mentioned problems, the structure of the present invention, which is based on the above-mentioned claims and has the above-mentioned object, has at least four or more tunnels 1 built underground, Mountain retaining materials 2a, 2 laterally from inside the tunnel 1
a, 2a ... and vertical mountain retaining materials 2b, 2b, 2b.
.. are installed so as to close the tunnels 1, 1, 1 ... And the technical means for excavating the inside closed by the group of mountain retaining materials 2a, 2b is taken.

【0009】また、「請求項2」の発明は、地下にトン
ネル1を少なくも2本以上築造し、該トンネル1内より
横方向の山留材2a,2a,2a・・・を該トンネル
1,1間を閉合するように設置し、さらに、両トンネル
内より縦方向の山留材2b,2b,2b・・・を夫々必
要根入れ深さまで設置し、門形に設置された山留材2
a,2b群内を掘削する技術的手段を講じたものであ
る。
Further, in the invention of "claim 2", at least two or more tunnels 1 are constructed underground, and the mountain retaining materials 2a, 2a, 2a ... , 1 are installed so that they are closed, and further, the mountain retaining materials 2b, 2b, 2b, etc. in the vertical direction from inside both tunnels are installed to the required rooting depth, and the mountain retaining materials are installed in a gate shape. Two
The technical means for excavating the inside of the a and 2b groups was taken.

【0010】[0010]

【作用】次に本発明の作用を説明する。本発明法は掘削
予定部位の上部及び側部に予め山留材2a,2b群を設
置してあるので、掘削予定部位を掘削しても地盤崩壊が
防がれる作用を呈する。
Next, the operation of the present invention will be described. According to the method of the present invention, since the group of mountain retaining materials 2a and 2b are installed in advance on the upper and side portions of the planned excavation site, even if the planned excavation site is excavated, the ground collapse can be prevented.

【0011】また、本発明工法は予め掘削したトンネル
1,1,1・・・から上記山留材2a,2b群を設置す
るので、地上には全く影響を与えず、さらに、地上から
掘削予定部位の天井部位までの地盤掘削を省略できる作
用を呈する。
Further, since the method of the present invention installs the group of mountain retaining materials 2a, 2b from the tunnels 1, 1, 1 ... Excavated in advance, it does not affect the ground at all, and the excavation from the ground is planned. Exhibits the effect of omitting ground excavation to the ceiling part of the part.

【0012】さらに、本発明工法は地下空間に築造する
構造物に対して相当の余裕を有した空間を掘削する必要
性を有するも、開削工法に比較しては掘削量は比較にな
らないほど少なくてすみ、異形断面シールド工法等で得
た地下空間を後に拡径する工法に比較しては、地盤改良
等の補助工法を省略できる作用を呈するものである。
Further, although the method of the present invention requires excavation of a space having a considerable margin for the structure to be built in the underground space, the excavation amount is so small that it cannot be compared with the open-cut method. Compared with the method of expanding the diameter of the underground space obtained by the Tesumi, modified section shield method, etc., the auxiliary method such as ground improvement can be omitted.

【0013】[0013]

【実施例】次に、本発明の実施例を添附図面に従って説
明すれば以下の通りである。図中、1,1,1・・・が
地下に構築したトンネルである。
Embodiments of the present invention will be described below with reference to the accompanying drawings. In the figure, 1, 1, 1 ... Are tunnels built underground.

【0014】上記トンネル1は、発進・到達立坑または
発進・到達口を設け(図示せず)、シールド工法、NA
TM工法、山岳工法等のトンネルを築造できるものであ
ればいずれの方法でもよく、その断面形状は円形の他、
馬蹄形、矩形その他の非円形でもよい。
The tunnel 1 is provided with a start / reach shaft or a start / reach opening (not shown), a shield construction method, an NA.
Any method can be used as long as it can build a tunnel such as the TM method and the mountain method, and the cross-sectional shape is circular as well as
It may be horseshoe-shaped, rectangular or other non-circular shape.

【0015】上記トンネル1は、少なくも4本以上築造
し、該トンネル1内より横方向及び縦方向の山留材2
a,2b群を該トンネル1,1,1・・・間を閉合する
ように設置する。すなわち、「図1」は地下に直方体の
空間を掘削する例で、掘削予定直方体の長手方向稜線を
中心軸とするトンネル1を4本構築する。なお、このト
ンネル1,1,1・・・は必ずしも平行に築造する必要
はなく、掘削予定空間の大きさ形状に適応して設ければ
よいのは無論である。
The tunnel 1 is constructed by at least four or more, and the mountain retaining material 2 extending in the lateral and vertical directions from the inside of the tunnel 1.
The groups a and 2b are installed so that the tunnels 1, 1, 1 ... Are closed. That is, "Fig. 1" is an example of excavating a rectangular parallelepiped space underground, and four tunnels 1 are constructed with a longitudinal axis of the rectangular parallelepiped to be excavated as a central axis. It is needless to say that the tunnels 1, 1, 1 ... Are not necessarily required to be constructed in parallel and may be provided in accordance with the size and shape of the planned excavation space.

【0016】そして、上記トンネル1内より設置する山
留材2a,2b群も従来公知なものが使用でき、通常、
断面が円形または四角形等の鋼管製パイプが使用され、
地下水位が高い場合は各山留材2a,2bに隣り合う山
留材2a,2bと適当な範囲で重なり合う止水用翼を取
り付けた従来公知なものをもの使用してもよいのは無論
であり、さらには、外部土水圧に耐えられるように管内
部にコンクリート等を充填してもよいものである。
The group of mountain retaining materials 2a and 2b installed from the inside of the tunnel 1 can be any conventionally known one, and usually,
A steel pipe with a circular or rectangular cross section is used,
When the groundwater level is high, it goes without saying that it is also possible to use a conventionally known one in which water retaining blades that overlap the mountain retaining materials 2a and 2b adjacent to each other in a proper range are attached to the respective mountain retaining materials 2a and 2b. In addition, the pipe may be filled with concrete or the like so as to withstand the external earth pressure.

【0017】さらに、上記山留材2a,2bは鋼管製に
代え地中連続壁工法や泥水固化工法等の場所打ち工法に
よる壁体を使用してもよいものである。なお、この地中
連続壁工法や泥水固化工法も従来公知なものであるので
その説明は省略する。
Further, the mountain retaining materials 2a and 2b may be made of steel pipes and may be wall bodies formed by a cast-in-place construction method such as an underground continuous wall construction method or a muddy water solidification construction method. The underground continuous wall construction method and the muddy water solidification construction method are well known in the art, and therefore their explanations are omitted.

【0018】なお、上記においてトンネル1を4本以上
としたのは、上記山留材2a,2b群を上下左右で囲む
ためで、4本のトンネルを略平行方向に方向に設けるこ
とで、上下左右を山留材2で囲うことが可能となる。な
お、一対の隣り合うトンネルの距離が長い場合はその間
に「図2」に示すように中間トンネル1a,1aを設け
てもよいものであり、上下左右ばかりでなく図奥手前側
をも山留材2b群で囲う必要性を有する場合(掘削する
地下空間の奥手前側が地上に開口する場合は、山留材2
a,2b群は開口方向に不要であることはいうまでもな
い。)は奥と手前の上下に二本ずつの合計8本以上のト
ンネルを築造して縦方向の山留材2b群を設置してもよ
いが、この場合は、トンネル1,1,1・・・を掘削す
るために設けた立坑より横方向の山留材2a群を設置す
るのが効率的である。
In the above description, the reason why the number of tunnels 1 is four or more is to enclose the group of mountain retaining materials 2a and 2b vertically and horizontally, and by providing four tunnels in a direction substantially parallel, It is possible to surround the left and right with the mountain retaining material 2. When the distance between a pair of adjacent tunnels is long, intermediate tunnels 1a, 1a may be provided between them as shown in FIG. When it is necessary to enclose it with a group of timber 2b (If the front side of the underground space to be excavated opens to the ground,
It goes without saying that the groups a and 2b are unnecessary in the opening direction. ) May construct a total of 8 or more tunnels, two at the top and two at the back, and install a group of mountain retaining materials 2b in the vertical direction. In this case, the tunnels 1, 1, 1 ... It is efficient to install a group of mountain retaining materials 2a in the lateral direction from the vertical shaft provided for excavating.

【0019】そして、上記山留材2a,2b群によって
(一部トンネル1,1,1・・・を含む)閉合された内
部を掘削して地下に所定の大きさの目的の空間を得る。
Then, the inside closed by the group of mountain retaining materials 2a and 2b (including some tunnels 1, 1, 1 ...) Is excavated to obtain a target space of a predetermined size underground.

【0020】上記山留材2a,2b群内の掘削は、両側
の発進・到達立坑または発進・到達口より行えばよい
が、トンネル1の中間に山留材2a,2b群で囲まれた
掘削範囲内に開口する図示しない掘削口を設けて、この
掘削口より掘削を開始してもよい。
The excavation in the group of mountain retaining materials 2a and 2b may be performed from the starting and reaching shafts or the starting and reaching entrances on both sides, but the excavation surrounded by the group of mountain retaining materials 2a and 2b in the middle of the tunnel 1. It is also possible to provide an unillustrated excavation opening that opens within the range and start excavation from this excavation opening.

【0021】なお、上記掘削に際して、「図2」の中間
トンネル1aの支保が必要となるので、この中間トンネ
ル1aには中柱3,3,3・・・を予め設置しておく。
この中柱3,3,3・・・は中間トンネル1a内より山
留材2と同様にして設置すればよいが、山留材2,2,
2・・・は止水のために相互に連続して設けるが、この
中柱3,3,3・・・上方の中間トンネル1aの支保に
必要な間隔を有して設ければ良いものである。
Since it is necessary to support the intermediate tunnel 1a shown in FIG. 2 during the excavation, the intermediate pillars 3, 3, 3 ... Are installed in advance in this intermediate tunnel 1a.
The middle pillars 3, 3, 3 ... May be installed from inside the intermediate tunnel 1a in the same manner as the mountain retaining material 2, but the mountain retaining materials 2, 2,
2 ... are continuously provided to stop the water, but these may be provided with a space necessary for supporting the intermediate pillars 3, 3, 3 ... Upper intermediate tunnel 1a. is there.

【0022】また、上記掘削に際し、山留材2a,2b
群のみでは側部土水圧に抵抗できない場合は、掘削過程
で切梁4,4,4・・・を設けてもよいものである。
When excavating, the mountain retaining materials 2a and 2b are used.
If the group alone cannot resist the lateral soil water pressure, the beams 4, 4, 4 ... May be provided during the excavation process.

【0023】上記によって得られる地下空間は上下左右
(必要に応じては奥手前)を山留材2a,2b群で囲ま
れることになるが、地下空間の下面の山留材2a,2
a,2a・・・は、この地下空間内に構築物を築造する
際に一部または全部を破壊撤去したり、地下構築物の築
造後は通常不要となったりするものであるから、この地
下空間の下面の山留材2a,2a,2a・・・を省略す
ることが効率的な場合もあり、「請求項2」の工法で
は、地下にトンネル1を少なくも2本以上築造し、該ト
ンネル1内より横方向の山留材2a,2a,2a・・・
を該トンネル1,1間を閉合するように設置し、さら
に、両トンネル1,1内より縦方向の山留材2b,2
b,2b・・・を夫々必要根入れ深さまで設置し、門形
に設置された山留材2a,2b群内を掘削するようにな
してある。
The underground space obtained by the above is surrounded by groups of mountain retaining materials 2a and 2b on the upper, lower, left and right sides (in front of the rear if necessary).
a, 2a ... are those that destroy or remove a part or all of the structure when constructing a structure in this underground space, or are usually unnecessary after the construction of an underground structure. In some cases, it may be efficient to omit the mountain retaining materials 2a, 2a, 2a ... On the lower surface. In the construction method of claim 2, at least two tunnels 1 are constructed underground and the tunnel 1 Mountain retaining materials 2a, 2a, 2a ...
Are installed so that the tunnels 1 and 1 are closed, and the mountain retaining members 2b and 2 extending in the vertical direction from the inside of both tunnels 1 and 1
b, 2b ... Are respectively installed up to the required depth of rooting, and the group of mountain retaining materials 2a, 2b installed in a gate shape are excavated.

【0024】すなわち、縦方向の山留材2b,2b,2
b・・・の下端まで地下空間を掘削せず、地下空間の床
面Fを縦方向の山留材2b,2b,2b・・・の途中ま
での深さにとどめることで、この縦方向の山留材2b,
2b,2b・・・の下部が周囲から地下空間床面Fに加
わる土水圧に抗するようになすことができる。
That is, the vertical mountain retaining members 2b, 2b, 2
By not excavating the underground space to the lower end of b ..., but keeping the floor surface F of the underground space at a depth halfway along the vertical mountain retaining materials 2b, 2b, 2b ... Mountain retaining material 2b,
The lower part of 2b, 2b ... Can be made to resist the earth pressure applied to the floor space F of the underground space from the surroundings.

【0025】なお、この縦方向の山留材2b,2b,2
b・・・を夫々必要根入れ深さまで設置する方法は、掘
削する地下空間の床面F下方にはトンネル1を必要とし
ないので該トンネル1は2本以上であればよい。しか
し、この方法で「図3」「図4」の奥手前方向にも山留
材2,2,2・・・を設置する場合は「請求項1」の説
明で使用した立坑の使用はできないので、奥手前方向に
も横方向のトンネル1を築造する必要があり、トンネル
1は合計4本が平面方形または台形等に連通する(交叉
方向のトンネルどうしは上下にずれても差し支えない)
ようになすことが必要となる。
In addition, the vertical mountain retaining members 2b, 2b, 2
In the method of installing b ... to the required rooting depth, the tunnel 1 is not required below the floor surface F of the underground space to be excavated, so that the number of tunnels 1 may be two or more. However, when the mountain retaining materials 2, 2, 2 ... Are also installed in the front direction of “FIG. 3” and “FIG. 4” by this method, the shaft used in the description of “claim 1” cannot be used. Therefore, it is necessary to build a tunnel 1 in the lateral direction also in the front direction, and a total of 4 tunnels 1 communicate with a flat square or trapezoid (the tunnels in the crossing direction may be vertically displaced).
It is necessary to do so.

【0026】なお、上記のようして得た地下空間内には
所望の構築物を構築して、この地下構築物の外側空間部
は、必要に応じて埋め戻しを行うものである。
The desired structure is constructed in the underground space obtained as described above, and the outer space portion of this underground structure is backfilled as necessary.

【0027】[0027]

【発明の効果】本発明は上記のごときであるので、掘削
する地下空間予定部位は予め山留材2a,2b群によっ
て囲まれるので、地盤崩壊の心配なく安全容易に掘削で
きる地下空間築造方法を提供できるものである。
EFFECTS OF THE INVENTION Since the present invention is as described above, a planned underground space to be excavated is surrounded by a group of mountain retaining materials 2a and 2b in advance. Can be provided.

【0028】また、本発明は、上記掘削が地下よりの掘
削であるので、掘削容量も効率的に低減でき、かつ、地
上及び地上近くの埋設物に影響を受けない地下空間築造
方法を提供できるものである。
Further, since the above-mentioned excavation is underground, the excavation capacity can be efficiently reduced, and a method for constructing an underground space that is not affected by the above-ground and buried objects near the above-ground can be provided. It is a thing.

【0029】また、本発明は地下に複雑な構築物を築造
する場合であっても、その地下構築物が余裕をもって収
納できる大きさの地下空間を確保しておけば、後にこの
地下構築物を築造することができ、そのための多少の余
掘は従来法の開削工法に比較しては微少であるし、従来
の事後拡径工法に比較しては地盤崩壊が山留材2a,2
b群で防止でき地盤改良工法が不要となるので、地下に
断面形状が変化する構築物を築造するには経済的で効率
的な地下空間築造方法を提供できるものである。
Further, according to the present invention, even in the case of constructing a complicated structure underground, if an underground space of a size capable of accommodating the underground structure is secured, this underground structure can be constructed later. However, the amount of excess excavation for that is small compared to the conventional excavation method, and the ground collapse is more likely to occur than the conventional post-expansion method.
Since it can be prevented by the group b and the ground improvement method is not required, it is possible to provide an economical and efficient underground space construction method for constructing a structure with a varying sectional shape underground.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明地下空間築造方法を説明する概念的斜視
図である。
FIG. 1 is a conceptual perspective view illustrating an underground space construction method of the present invention.

【図2】別の実施例概念的斜視図である。FIG. 2 is a conceptual perspective view of another embodiment.

【図3】さらに、もう一つの実施例概念的斜視図であ
る。
FIG. 3 is a conceptual perspective view of another embodiment.

【図4】さらに、もう一つの実施例概念的斜視図であ
る。
FIG. 4 is a conceptual perspective view of another embodiment.

【符号の説明】[Explanation of symbols]

1 トンネル 2 山留材 1 tunnel 2 Yamadome wood

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 地下にトンネル1を少なくも4本以上築
造し、該トンネル1内より横方向の山留材2a,2a,
2a・・・及び縦方向の山留材2b,2b,2b・・・
を該トンネル1,1,1・・・間を閉合するように設置
し、該山留材2a,2b群によって閉合された内部を掘
削する地下空間築造方法。
1. At least four or more tunnels 1 are constructed underground, and mountain retaining members 2a, 2a, 2a, 2a
2a ... and vertical mountain retaining materials 2b, 2b, 2b ...
Is installed so as to close the tunnels 1, 1, 1 ... And the underground space construction method for excavating the inside closed by the group of mountain retaining materials 2a, 2b.
【請求項2】 地下にトンネル1を少なくも2本以上築
造し、該トンネル1内より横方向の山留材2a,2a,
2a・・・を該トンネル1,1間を閉合するように設置
し、さらに、両トンネル内より縦方向の山留材2b,2
b,2b・・・を夫々必要根入れ深さまで設置し、門形
に設置された山留材2a,2b群内を掘削する地下空間
築造方法。
2. At least two tunnels 1 are constructed underground, and the mountain retaining members 2a, 2a, 2a, 2a, 2a, 2a,
2a ... are installed so that the tunnels 1 and 1 are closed, and the mountain retaining members 2b and 2 extending in the vertical direction from the inside of both tunnels.
b, 2b ... are installed up to the required depth of rooting, respectively, and an underground space construction method for excavating the group of mountain retaining materials 2a, 2b installed in a gate shape.
JP5344202A 1993-12-17 1993-12-17 Underground space construction method Pending JPH07173848A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5344202A JPH07173848A (en) 1993-12-17 1993-12-17 Underground space construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5344202A JPH07173848A (en) 1993-12-17 1993-12-17 Underground space construction method

Publications (1)

Publication Number Publication Date
JPH07173848A true JPH07173848A (en) 1995-07-11

Family

ID=18367425

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5344202A Pending JPH07173848A (en) 1993-12-17 1993-12-17 Underground space construction method

Country Status (1)

Country Link
JP (1) JPH07173848A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103469816A (en) * 2013-09-16 2013-12-25 铁道第三勘察设计院集团有限公司 Integrated pipe trench structure applied to interregional ground line roadbed of urban rail transit project

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103469816A (en) * 2013-09-16 2013-12-25 铁道第三勘察设计院集团有限公司 Integrated pipe trench structure applied to interregional ground line roadbed of urban rail transit project

Similar Documents

Publication Publication Date Title
KR100289256B1 (en) Tunnel construction method in shallow toffee area
JP2001032673A (en) Tunnel work execution method
JP2000179299A (en) Large-section tunnel construction method
KR20000065282A (en) tubular roof tunnel construction method
JP3135188B2 (en) Construction method of underground cavity
KR100322845B1 (en) tubular roof tunnel construction method
JPH07173848A (en) Underground space construction method
JP2005002671A (en) Underpinning method and viaduct
JPH03279600A (en) Construction method of large cavity
JPS6117696A (en) Construction of underground head
JP2004316126A (en) Work execution method for large section tunnel and deformed section shield boring machine
JPH07139300A (en) Method for constructing underground construction
JP3026134B2 (en) How to build underground structures under roads
JP2004316125A (en) Work execution method for large sectional tunnel and deformed section shield machine
JPS62220616A (en) Construction work for underground space
JPH02300422A (en) Construction of underground structure
JP3710106B2 (en) How to build a shield start base
JP2004124615A (en) Construction method of great-depth underground cavity
JP2846248B2 (en) Earth retaining wall and construction method
JPH0726877A (en) Construction method of underground structure
JP3646698B2 (en) Construction method for underground structures
JP2005194764A (en) Tunnel connecting method
JP3865468B2 (en) How to build a tunnel
JP2949623B1 (en) How to build a tunnel
JP2003206697A (en) Construction method of underground structure