JP3135188B2 - Construction method of underground cavity - Google Patents

Construction method of underground cavity

Info

Publication number
JP3135188B2
JP3135188B2 JP06130586A JP13058694A JP3135188B2 JP 3135188 B2 JP3135188 B2 JP 3135188B2 JP 06130586 A JP06130586 A JP 06130586A JP 13058694 A JP13058694 A JP 13058694A JP 3135188 B2 JP3135188 B2 JP 3135188B2
Authority
JP
Japan
Prior art keywords
underground cavity
steel pipe
shaft
square steel
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP06130586A
Other languages
Japanese (ja)
Other versions
JPH07331998A (en
Inventor
康郎 二宮
好信 居相
正彦 三浦
哲治 保岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP06130586A priority Critical patent/JP3135188B2/en
Publication of JPH07331998A publication Critical patent/JPH07331998A/en
Application granted granted Critical
Publication of JP3135188B2 publication Critical patent/JP3135188B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、地下空洞の構築工法に
関し、特に、地表面より下方に構築設置される、トンネ
ルやその他の地下構造物からなる地下空洞の構築工法に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an underground cavity, and more particularly to a method for constructing an underground cavity comprising a tunnel or other underground structure, which is constructed and installed below the ground surface.

【0002】[0002]

【従来の技術】従来より、地表面より下方に構築設置さ
れる地下空洞、例えば地下トンネルやその他の地下構造
物からなる地下空洞の構築工法として、一般に、開削工
法やシールド工法が知られている。
2. Description of the Related Art Conventionally, as a construction method of an underground cavity constructed and installed below the ground surface, for example, an underground cavity made up of an underground tunnel and other underground structures, an open-cutting method and a shield method are generally known. .

【0003】開削工法は、鋼矢板や地中連続壁などによ
る各種の山留支保工を併用しつつ、地表面からトンネル
等の地下構造物を設置する深さまで地盤を開削し、地下
構造物を構築した後に、これの上方に土砂を埋戻して地
盤を復旧するものである。
In the excavation method, the ground is excavated from the ground surface to a depth at which an underground structure such as a tunnel is to be installed, while using various types of shoring by steel sheet piles and underground continuous walls. After the construction, the earth and sand is buried above it to restore the ground.

【0004】一方、シールド工法は、主として、都市部
等において、開削工法に必要な作業領域が確保できない
場合や、地下水を多く含む軟弱な地盤に対して採用され
るトンネル工法で、地中所定深度まで掘削形成した発進
立坑から到達立坑に向けて、筒状のシールド掘進機を地
中に掘削推進させるとともに、掘進機の後方にセグメン
トと呼ばれる覆工体を筒状に設置することにより、当該
覆工体により周囲を強固に覆われたトンネルすなわち地
下空洞を構築するものである。
[0004] On the other hand, the shield method is a tunnel method which is mainly used in an urban area or the like when a working area required for the open-cutting method cannot be secured or when the ground is soft and contains a large amount of groundwater. From the starting shaft excavated and formed to the reaching shaft, a cylindrical shield excavator is excavated and propelled underground, and a lining body called a segment is installed in a tubular shape behind the excavator, thereby forming the covering. This is to construct a tunnel, that is, an underground cavity, whose surroundings are firmly covered by the body.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、従来の
地下空洞を構築する工法では、上記開削工法による場合
には、特に都市部等においては、地表面の交通が遮断さ
れること等により付近の住民の環境を害することになる
ため、地表面に広大な作業領域を確保することが困難で
あるとともに、地上から地下空洞の設置位置まで広範囲
に亘って多量の地盤を掘削しかつ埋戻す必要を生じるた
め、地下空洞を構築する位置が深くなるに従って不経済
になり、またその作業に危険が伴うことになる。
However, in the conventional method of constructing an underground cavity, in the case of the above-mentioned excavation method, especially in an urban area or the like, traffic on the ground surface is cut off and the like. It is difficult to secure a vast working area on the ground surface, and it is necessary to excavate and backfill a large amount of ground from the ground to the installation position of the underground cavity. Therefore, the deeper the position where the underground cavity is constructed, the more uneconomical, and the work is dangerous.

【0006】また、上記シールド工法による場合には、
開削部分として発進立坑及び到達立坑のみの領域を確保
し、掘削することができれば良いため、近隣住民の環境
に与える影響を極力回避することができるとともに、掘
削土量等の低減を図ることができるが、その一方で、ト
ンネルの掘削断面に応じた高価な専用のシールド掘進機
を製作する必要があるため、特に断面形状が大きいトン
ネルや円形以外の変形断面のトンネルを構築する場合に
は不経済になるともに、構築作業に困難が伴うことにな
る。
In the case of the above shield method,
Since it is only necessary to secure the area of the starting shaft and the reaching shaft as the excavated part and excavate, it is possible to minimize the influence on the environment of the nearby residents and reduce the amount of excavated soil etc. However, on the other hand, it is necessary to manufacture an expensive dedicated shield machine corresponding to the tunnel cross section, which is uneconomical especially when constructing a tunnel with a large cross section or a tunnel with a deformed cross section other than circular. At the same time, the construction work will be difficult.

【0007】一方、地中深部に構築形成される地下構造
物は、その頂面をアーチ型に形成することが、周囲から
の土圧に耐える構造として有利であることが一般に知ら
れている。
On the other hand, it is generally known that an underground structure constructed and formed deep underground is advantageous in that its top surface is formed as an arch as a structure that can withstand the earth pressure from the surroundings.

【0008】そこで、本発明は、かかる課題に鑑みてな
されたもので、地表面からの開削部分を低減し、かつ掘
削土量を当該地下空洞部分に相当する最小限のものに留
めることができるとともに、専用の掘削機械を用いるこ
となく既存のトンネル工法を組み合わせて、アーチ状の
天頂面を有する強固かつ大断面の地下空洞を経済的に構
築することのできる地下空洞の構築工法を提供すること
を目的とするものである。
Therefore, the present invention has been made in view of such a problem, and it is possible to reduce an excavated portion from the ground surface and to reduce the amount of excavated soil to a minimum amount corresponding to the underground hollow portion. To provide an underground cavity construction method that can economically construct a strong and large-section underground cavity with an arch-shaped zenith surface by combining existing tunneling methods without using a dedicated excavation machine It is intended for.

【0009】[0009]

【課題を解決するための手段】上記目的を達成するた
め、本発明の地下空洞の構築工法は、地下空洞の構築予
定箇所を挾んでその両端に導坑掘削用及び角型鋼管の推
進作業用の坑道を掘削形成する工程と、該各坑道から地
下空洞の左右両側壁ラインに沿って一対の導坑を掘削形
成する工程と、構築すべき地下空洞の天端部において上
記掘削形成した一方の坑道から他方の坑道に向かって地
下空洞の縦断方向に角型鋼管をアーチ状の横断面に沿っ
て多数列推進設置することにより、地下空洞の天端部分
を覆って当該角型鋼管を密接状態でアーチ状に配置する
とともに、前記導坑内に側壁コンクリートを打設しかつ
前記設置した角型鋼管内に中詰コンクリートを打設し
て、側壁部と天端部とが一体となって地下空洞の本坑部
分を覆う外殻体を構築形成する工程と、該外殻体により
覆われた本坑部分を掘削するとともに、該本坑部分に地
下空洞の本体を構築する工程とからなるものである。
発明においては、前記多数列の角型鋼管が、先行する角
型鋼管の推進後にそれぞれが継ぎ足し接合されることが
好ましい。
In order to achieve the above object, the method of constructing an underground cavity according to the present invention is intended for excavation of a shaft and the propulsion work of a square steel pipe at both ends of an underground cavity to be constructed. Excavating and forming a tunnel, a step of excavating and forming a pair of guide shafts from each of the tunnels along the left and right side wall lines of the underground cavity, and one of the excavation and formation at the top end of the underground cavity to be constructed A number of square steel pipes are propelled and installed along the arch-shaped cross section in the longitudinal direction of the underground cavity from the tunnel to the other tunnel, covering the top end of the underground cavity and keeping the square steel pipe in close contact Arranged in the shape of an arch, cast concrete in the side wall in the shaft and cast concrete in the installed square steel pipe, the side wall and the top end are integrated into the underground cavity. Build an outer shell to cover the main shaft A step of forming, together with the drilling Honko portion covered by the outer shell, is made of a step of constructing a body of underground cavities in the main pit portion. Book
In the present invention, the multiple rows of square-shaped steel pipes have a leading corner.
After propulsion of shaped steel pipes, each can be added and joined
preferable.

【0010】[0010]

【作用】本発明は、構築すべき地下空洞の両端に導坑掘
削用及び角型鋼管の推進作業用の坑道を掘削形成し、こ
の坑道より地下空洞の左右両側壁の導坑を形成し、また
角型鋼管及び中詰コンクリートにより天端部に構築した
アーチ状の外殻体の内部にて本坑の掘削を行うものであ
るため、天端部より上方の地盤をも開削する場合に比
べ、地上からの開削部分を坑道と地上とを連通する立坑
に相当する領域のみに留めることができる。また、天端
部に角型鋼管を推進設置する作業は坑道から行うため場
所をとらず、掘削環境の影響を最小限に抑さえることが
できるとともに、アーチ状の横断面に沿った多数の列に
多数の角型鋼管をトンネル縦断方向に直線推進して設置
することにより、アーチ状の天頂面を有する地下空洞を
容易に形成することができる。そして、地下空洞の本坑
部分の掘削作業は、天端部と側壁部が一体となって本坑
部分を覆う、予め構築形成された強固なアーチ状の外殻
体の内方において行われることとなるため、周囲の地盤
の崩壊を生じることなく安全かつ容易に掘削作業を行な
うことができる。
According to the present invention, excavations are formed at both ends of an underground cavity to be constructed for excavation of a shaft and for propulsion work of a square steel pipe. In addition, since the main pit is excavated inside the arched outer shell constructed at the top end using square steel pipes and filled concrete, compared with the case of excavating the ground above the top end In addition, the excavated portion from the ground can be limited only to the area corresponding to the shaft connecting the tunnel and the ground. In addition, the work for propelling and installing square steel pipes at the top end is performed from the tunnel, so it takes up little space, minimizing the impact of the excavation environment, and providing a large number of rows along the arch-shaped cross section. By installing a large number of square steel pipes in a straight line in the longitudinal direction of the tunnel, an underground cavity having an arch-shaped zenith surface can be easily formed. And the excavation work of the main shaft part of the underground cavity is performed inside a strong arched outer shell body that is built in advance and the main shaft part and the side wall part integrally cover the main shaft part Therefore, excavation work can be performed safely and easily without causing collapse of the surrounding ground.

【0011】[0011]

【実施例】以下、本発明を図示の実施例に基づいて説明
する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to the illustrated embodiments.

【0012】この実施例において構築すべき地下空洞1
0は、図1に示すように、2つのトンネル11を連ねて
成るいわゆる2連式の大断面トンネルである。
Underground cavity 1 to be constructed in this embodiment
Numeral 0 is a so-called double-section large-section tunnel formed by connecting two tunnels 11 as shown in FIG.

【0013】この実施例の構築工法においては、まず、
地下空洞10の構築予定箇所を挾んで、図2に示すよう
に、二連式のトンネル11の両端側に、地表面12から
トンネルを構築する深さまで、導坑掘削用及び角型鋼管
の推進作業用の坑道としての発進用及び到達用の立坑1
2を掘削形成する。各立坑12は、例えば、地中連続壁
工法やシートパイル工法等により周囲の地盤を山留した
後に、当該山留壁を補強しながらこれの内部の地盤を順
次下方に掘り下げてゆくことにより、容易に所定の深度
まで掘削形成することができる。
In the construction method of this embodiment, first,
As shown in FIG. 2, the construction site of the underground cavity 10 is sandwiched, and as shown in FIG. Shaft 1 for starting and reaching as a working tunnel
Excavation 2 is formed. Each shaft 12, for example, after piercing the surrounding ground by the underground continuous wall construction method or sheet pile construction method, etc., by sequentially digging down the ground inside thereof while reinforcing the retaining wall, Excavation can be easily performed to a predetermined depth.

【0014】立坑12を所定深度まで構築したら、次
に、この発進側の立坑12内より、構築すべき地下空洞
10の左右の側壁14と、左右の各トンネル11の側壁
14を兼ねるとともに地下空洞10を左右のトンネル1
1に分割する中央の側壁14とを構築するための三列の
一段目の導坑13を、各々到達側の立坑12に向かって
掘削形成し、該導坑13から適宜基礎杭を下方に打設設
置するとともに、図示してない型枠を設けて側壁コンク
リート21を打設して、側壁14の下段部分を構築した
後、側壁14の上段部分を構築するための二段目の導坑
15を掘削形成する。この実施例の場合、側壁14の上
段部分のコンクリート21はこの時点ではまだ打設しな
い。なお、この実施例では、構築する地下空洞10の高
さ等に鑑みて、二段の導坑13,15に分割して導坑を
掘削するが、地架空洞10の大きさ等によっては必ずし
も分割する必要はない。
After the shaft 12 is constructed to a predetermined depth, the underground cavity is used as the left and right side walls 14 of the underground cavity 10 to be constructed and the side walls 14 of each of the left and right tunnels 11 from the starting side shaft 12. 10 left and right tunnel 1
First-stage shafts 13 for constructing the three-row first-stage shafts 13 for constructing the central side wall 14 that is to be divided into 1 are formed toward the reaching shaft 12 on the arrival side, and the foundation piles are appropriately driven downward from the shafts 13. In addition to the installation and installation, a formwork (not shown) is provided and the side wall concrete 21 is cast to construct the lower part of the side wall 14, and then the second pit 15 for constructing the upper part of the side wall 14. Drilling to form. In this embodiment, the concrete 21 in the upper part of the side wall 14 has not yet been cast at this time. In this embodiment, in consideration of the height and the like of the underground cavity 10 to be constructed, the shaft is excavated by dividing the shaft into two-stage shafts 13 and 15. There is no need to split.

【0015】第二段目の導坑15の掘削終了後、構築す
べき地下空洞10の縦断方向すなわち各トンネル11の
天端部の縦断方向に、予め立坑12内に搬入可能なサイ
ズに形成された略矩形断面のブロック状の角型鋼管17
を、各トンネル11の天頂部分のアーチ状の横断面に沿
った多数の列において、トンネルの縦断方向に直線推進
することにより、多数の角型鋼管17が縦横にマトリッ
クス状に密接配置されて一体化した、トンネル11を覆
う外殻体18のアーチ状の天端部16が形成される。
After the excavation of the second shaft 15 is completed, it is formed in advance in the longitudinal direction of the underground cavity 10 to be built, that is, in the longitudinal direction of the top end of each tunnel 11, in a size that can be carried into the shaft 12. Block-shaped square steel pipe 17 having a substantially rectangular cross section 17
Are linearly propelled in the longitudinal direction of the tunnel in a number of rows along the arch-shaped cross section of the zenith portion of each tunnel 11, whereby a number of square steel pipes 17 are closely arranged vertically and horizontally in a matrix and integrated. An arched top end 16 of the outer shell 18 covering the tunnel 11 is formed.

【0016】即ち、角型鋼管17を密接状態で設置する
には、例えば、まずアーチ状の天端横断面の始端に位置
する第1列目の角型鋼管17aを、既存のトンネル工法
である推進工法により、発進側の立坑12に設置した推
進ジャッキを用いて、後方にブロック状の角型鋼管17
aを順次連設しつつ到達側の立坑12に向かってトンネ
ル11の縦断方向に掘削推進することにより、発進側の
立坑12から到達側の立坑12まで直線状に連設する第
1列目の鋼管列が設置される。次いで、アーチ状の天端
横断面に沿った第2列目の角型鋼管17bを、設置され
た第1列目の角型鋼管17aに隣接して、発進側の立坑
12から到達側の立坑12まで同様の方法により推進設
置する。以下アーチ状の天端横断面上の各列について、
同様の操作を順次繰り返し、最後にアーチの終端に属す
る最終列の角型鋼管17kを推進設置して、各トンネル
11のアーチ状の天端部16を形成する。
That is, in order to install the square steel pipes 17 in close contact with each other, for example, first, the first row of square steel pipes 17a located at the beginning of the arched top cross section is formed by an existing tunnel method. By the propulsion method, a block-shaped square steel pipe 17 is provided rearward using a propulsion jack installed in the shaft 12 on the starting side.
In the first column, the excavation is carried out in the longitudinal direction of the tunnel 11 toward the arrival-side shaft 12 while sequentially connecting the shafts a to the arrival-side shaft 12 from the start-side shaft 12 to the arrival-side shaft 12. Steel pipe rows will be installed. Next, the square-shaped steel pipes 17b in the second row along the arch-shaped cross section of the top end are placed adjacent to the installed square-shaped steel pipes 17a in the first row from the shaft 12 on the starting side to the shaft on the reaching side. Propulsion installation is performed by the same method up to 12. Below, for each row on the arched top cross section,
The same operation is sequentially repeated, and finally, the square-shaped steel pipe 17k in the last row belonging to the end of the arch is propelled and installed to form the arched top end 16 of each tunnel 11.

【0017】なお、各ブロック状の角型鋼管17は、そ
の側面に開口が形成されたものを用いることが好まし
く、かかる角型鋼管17によれば、各鋼管列を横断して
補強用の鉄筋を配筋することができ、また、内部に打設
される中詰コンクリートは、各鋼管列を横断して流通す
ることになるため、各角型鋼管17が一体化してさらに
強固なアーチ状の天端部16が形成されることになる。
It is preferable that each block-shaped square steel pipe 17 has an opening formed on a side surface thereof. According to such a square steel pipe 17, a reinforcing reinforcing bar extends across each steel pipe row. In addition, since the filled concrete poured into the inside is distributed across each steel pipe row, each square steel pipe 17 is integrated to form a stronger arch-shaped. The top end 16 will be formed.

【0018】上記の後、アーチ状の天端部16を構成す
る各角型鋼管17の内部に中詰コンクリート19を打設
するとともに、二段目の導坑15内には、かかる天端部
16の端部を巻き込みつつ、一段目の導坑13内に形成
された上記側壁14の下段部分の上方に、これと一体化
して側壁14の上段部分の側壁コンクリート21を打設
する。これによって、地下空洞10の外周には、アーチ
状の天端部16と側壁14が一体となって強固に地下空
洞10の本坑20の部分を覆う、外殻体18すなわちア
ーチシェルが形成される。
After the above, a filling concrete 19 is poured into each of the square steel pipes 17 constituting the arch-shaped top end portion 16, and the top end portion is placed in the second shaft 15. While rolling the end portion of the side wall 16, the side wall concrete 21 of the upper part of the side wall 14 is cast over the lower part of the side wall 14 formed in the first shaft 13. As a result, an outer shell 18, that is, an arch shell, is formed on the outer periphery of the underground cavity 10, in which the arch-shaped top end 16 and the side wall 14 integrally cover the main shaft 20 of the underground cavity 10. You.

【0019】最後に、上記アーチ状の外殻体18で囲ま
れた本坑20の部分を掘削し、以て目的とする地下空洞
10の構築を図る。この本坑20の掘削作業は、予め構
築形成された強固な外殻体18の内方において行われる
ので、周囲の地盤の崩壊を生じることがなく、安全かつ
迅速に行うことができる。なお、発生する掘削土砂は、
各立坑12を介して地上に搬出される。
Finally, a portion of the main shaft 20 surrounded by the arched outer shell 18 is excavated to construct a target underground cavity 10. Since the excavation work of the main shaft 20 is performed inside the strong outer shell 18 constructed and formed in advance, the excavation work can be performed safely and quickly without causing the collapse of the surrounding ground. The excavated sediment generated is
It is carried out to the ground via each shaft 12.

【0020】本坑20の掘削作業が完了したら、形成さ
れた作業空間内で地下空洞10の本体の構築作業を行
う。すなわち、図1に示すように、地下空洞10の底版
70及びインバート部73を形成するとともに、外殻体
18の側壁14と天端部16の内側に二次覆工としての
内側壁71及び上床版72を形成し、さらに種々の内装
を施工する。
When the excavation work of the main shaft 20 is completed, the construction work of the main body of the underground cavity 10 is performed in the formed working space. That is, as shown in FIG. 1, the bottom plate 70 and the inverted portion 73 of the underground cavity 10 are formed, and the inner wall 71 and the upper floor as a secondary lining are formed inside the side wall 14 and the top end 16 of the outer shell 18. The plate 72 is formed, and various interiors are further constructed.

【0021】なお、底版70は、角型鋼管17を、立坑
12の底部から、上述の外殻体18の天端部16におけ
る推進設置作業と同様の作業によって設置することによ
り設けることもできる。かかる方法によれば、本坑20
は、掘削作業に先立って、底面を含むその全周が外殻体
18によって覆われることになるため、より安全に本坑
20の掘削作業を行なうことができる。
The bottom plate 70 can also be provided by installing the square steel pipe 17 from the bottom of the shaft 12 by the same operation as the above-described propulsion installation at the top end 16 of the outer shell 18. According to such a method, the main shaft 20
Prior to the excavation work, the entire periphery including the bottom surface is covered with the outer shell body 18, so that the excavation work of the main shaft 20 can be performed more safely.

【0022】そして、上記地下空洞10の構築工法によ
れば、地上からの開削部分を最小限発進立坑12に相当
する領域のみとすることができる。また、天端部16に
角型鋼管17を推進設置する作業は発進側の立坑12か
ら行うため場所をとらず、掘削環境の影響を最小限に抑
さえることができる。また、各立坑12を介して、施工
箇所への資機材の搬入搬出作業及び掘削土砂の搬出作業
等を行うことができる。更に、導坑13,15内におけ
る側壁コンクリート21の打設構築作業や角型鋼管17
内への中詰コンクリート19の打設作業も、コンクリー
トポンプ等により既存の技術を用いて容易に行なうこと
ができる。そして、地下空洞10の本坑20の部分の掘
削作業は、天端部16と側壁部14が一体となって本坑
20の部分を覆う、予め構築形成された強固な外殻体1
8の内方において、周囲の地盤の崩壊を生じることなく
安全かつ容易に行なうことができる。
According to the method of constructing the underground cavity 10, the cut-out portion from the ground can be reduced to only the area corresponding to the starting shaft 12. In addition, since the work of propelling and installing the square steel pipe 17 at the top end 16 is performed from the starting shaft 12 on the starting side, no space is required and the influence of the excavation environment can be minimized. In addition, it is possible to carry out the work of loading and unloading materials and equipment to the construction site, and to carry out the work of unloading excavated earth and sand through the shafts 12. Furthermore, the construction work of placing the side wall concrete 21 in the shafts 13 and 15 and the square steel pipe 17
The work of placing the filled concrete 19 in the interior can be easily performed by using a conventional technique by a concrete pump or the like. The excavation work of the main shaft 20 of the underground cavity 10 is performed by forming the strong outer shell 1 formed in advance, in which the top end portion 16 and the side wall portion 14 integrally cover the main shaft 20.
8 can be performed safely and easily without causing collapse of the surrounding ground.

【0023】なお、上記実施例では、角型鋼管17を推
進設置した後に上段部分の側壁14のコンクリート21
を打設したが、二段目の導坑15を掘削形成した後、角
型鋼管17の推進設置の前に側壁コンクリート21を打
設しておいて、この側壁14を、第1列目の角型鋼管1
7a及び最終列の角型鋼管17kを推進設置する際のガ
イドとして機能させてもよい。
In the above embodiment, after the square steel pipe 17 is propelled and installed, the concrete
However, after excavating and forming the second-stage pit 15, the side wall concrete 21 is cast before the propulsion installation of the square steel pipe 17, and the side wall 14 is placed in the first row. Square steel pipe 1
It may be made to function as a guide at the time of propulsion installation of 7a and the square steel pipe 17k of the last row.

【0024】また、上記実施例では、導坑13,15の
掘削用及び角型鋼管17の推進作業用の坑道して、トン
ネル11の両端側において地表面からトンネル11を構
築する深さまで開削形成した発進用及び到達用の立坑1
2を使用したが、この発明はこれに限定されるものでは
なく、たとえば、トンネル11の両端側の地表面に各立
坑12のための開削領域を確保することができない場合
には、図3に示すように、トンネル11の両端側から離
れて開削作業に支障のない位置に立坑30を掘削形成
し、ここから側方に掘り進んだ水平トンネル31を介し
て、トンネル11の両端側に導坑13,15の掘削用及
び角型鋼管17の推進作業用の坑道32を掘削形成する
こともできる。
In the above embodiment, the tunnels for excavating the shafts 13 and 15 and for propelling the square steel pipe 17 are formed by excavation from both the ground surface to the depth where the tunnel 11 is to be constructed at both ends of the tunnel 11. Shaft for starting and reaching 1
2 is used, but the present invention is not limited to this. For example, when it is not possible to secure an open area for each shaft 12 on the ground surface at both ends of the tunnel 11, FIG. As shown in the figure, a shaft 30 is excavated and formed at a position away from both ends of the tunnel 11 so as not to hinder the excavation work, and a shaft is dug to the both ends of the tunnel 11 via a horizontal tunnel 31 dug from the side. Tunnel 32 for excavation of 13 and 15 and for propulsion work of square steel pipe 17 can be formed by excavation.

【0025】[0025]

【発明の効果】以上詳細に説明したように、本発明によ
れば、地表面からの開削部分は、坑道と地上とを連通す
る立坑に相当する領域のみとなり、この坑道より地下空
洞の左右両側壁の導坑を形成し、また角型鋼管及び中詰
コンクリートにより天端部に構築したアーチ状外殻体の
内部にて本坑の掘削を行うものであるため、天端部から
上方の地盤をも開削する場合に比べ掘削土量を極めて少
なく抑えることができる。また、天端部に角型鋼管を推
進設置する作業は坑道から行うため場所をとらず、作業
中の周囲の環境への影響を最小限に抑さえることができ
る。
As explained in detail above, according to the present invention, the cut-out portion from the ground surface is only the area corresponding to the shaft which connects the tunnel with the ground, and the left and right sides of the underground cavity from this tunnel. Since the main shaft is to be excavated inside the arched outer shell constructed at the top end using a square steel pipe and filled concrete, the main shaft will be excavated. The amount of excavated soil can be extremely reduced as compared with the case of excavation. In addition, since the work of propelling and installing the square steel pipe at the top end is performed from the tunnel, it does not take up much space, and the influence on the surrounding environment during the work can be minimized.

【0026】また、地下空洞の天端部は、角型鋼管及び
中詰コンクリートによりアーチ状の外殻体として構築さ
れるので、強固かつ大断面の地下空洞を経済的に構築す
ることができる。そして、地下空洞の本坑部分の掘削作
業は、この天端部と側壁部が一体となって本坑部分を覆
う予め強固に構築形成された外殻体の内方において行わ
れるため、周囲の地盤の崩壊を生じることなく安全かつ
容易に作業を行なうことができる。
Further, since the top end of the underground cavity is constructed as an arch-shaped outer shell made of square steel pipe and filled concrete, a strong and large-sized underground cavity can be economically constructed. Since the excavation work of the main shaft part of the underground cavity is performed inside the outer shell body that is formed firmly in advance and firmly formed so that the top end and the side wall part integrally cover the main shaft part, Work can be performed safely and easily without causing ground collapse.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の工法により構築される地下空洞を例示
した横断面図である。
FIG. 1 is a cross-sectional view illustrating an underground cavity constructed by the method of the present invention.

【図2】本発明の工法における立坑及び導坑の平面的な
位置関係を例示した概略平面図である。
FIG. 2 is a schematic plan view illustrating a planar positional relationship between a shaft and a shaft in the method of the present invention.

【図3】地下空洞の両端側から離れて掘削形成した立坑
から掘り進んで導坑掘削用の坑道を形成する場合の一実
施例を示す説明図である。
FIG. 3 is an explanatory view showing an embodiment in a case where a tunnel for excavation is formed by digging from a shaft excavated and formed apart from both ends of an underground cavity.

【符号の説明】[Explanation of symbols]

10 地下空洞 11 トンネル 12 立坑(導坑) 13 一段目の導坑 14 側壁 15 二段目の導坑 16 天端部 17 角型鋼管 17a 第1列目の角型鋼管 17b 第2列目の角型鋼管 17k 最終列の角型鋼管 18 外殻体 19 中詰コンクリート 20 本坑 21 側壁コンクリート 32 坑道 DESCRIPTION OF SYMBOLS 10 Underground cavity 11 Tunnel 12 Vertical shaft (Gall) 13 First stage shaft 14 Side wall 15 Second stage shaft 16 Top end 17 Square steel pipe 17a First row square steel pipe 17b Second row corner Steel pipe 17k Square steel pipe in the last row 18 Outer shell 19 Filling concrete 20 Main shaft 21 Side wall concrete 32 Tunnel

───────────────────────────────────────────────────── フロントページの続き (72)発明者 三浦 正彦 宮城県仙台市青葉区上杉1−6−11 株 式会社大林組東北支店内 (72)発明者 保岡 哲治 東京都千代田区神田司町2丁目3番地 株式会社大林組東京本社内 (56)参考文献 特開 平3−279600(JP,A) ────────────────────────────────────────────────── ─── Continuing on the front page (72) Inventor Masahiko Miura 1-6-11 Uesugi, Aoba-ku, Sendai, Miyagi Pref. Obayashi Gumi Tohoku Branch (72) Inventor Tetsuharu Hooka 2-3-3 Kandaji-cho, Chiyoda-ku, Tokyo Address Obayashi Corporation Tokyo head office (56) References JP-A-3-279600 (JP, A)

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 地下空洞の構築予定箇所を挾んでその両
端に導坑掘削用及び角型鋼管の推進作業用の坑道を掘削
形成する工程と、該各坑道から地下空洞の左右両側壁ラ
インに沿って一対の導坑を掘削形成する工程と、構築す
べき地下空洞の天端部において上記掘削形成した一方の
坑道から他方の坑道に向かって地下空洞の縦断方向に角
型鋼管をアーチ状の横断面に沿って多数列推進設置する
ことにより、地下空洞の天端部分を覆って当該角型鋼管
を密接状態でアーチ状に配置するとともに、前記導坑内
に側壁コンクリートを打設しかつ前記設置した角型鋼管
内に中詰コンクリートを打設して、側壁部と天端部とが
一体となって地下空洞の本坑部分を覆う外殻体を構築形
成する工程と、該外殻体により覆われた本坑部分を掘削
するとともに、該本坑部分に地下空洞の本体を構築する
工程とからなることを特徴とする地下空洞の構築工法。
1. A step of excavating and forming tunnels for excavation of a shaft and propulsion work of a square steel pipe at both ends of a place where an underground cavity is to be constructed. Excavating and forming a pair of shafts along an arched steel pipe in the longitudinal direction of the underground cavity from one of the excavated and formed tunnels to the other at the top end of the underground cavity to be constructed. By arranging a large number of rows along the cross section, the rectangular steel pipe is arranged in an arched shape in close contact with the top end of the underground cavity, and side wall concrete is poured into the shaft and the installation is performed. Casting the filled concrete into the square steel pipe thus formed, and forming and forming an outer shell covering the main shaft portion of the underground cavity by integrating the side wall and the top end, and covering the outer shell with the outer shell. The excavated main shaft was excavated and A method of constructing an underground cavity in a pit portion.
【請求項2】 前記多数列の角型鋼管は、先行する角型2. The multi-column square steel pipe is formed of a preceding square steel pipe.
鋼管の推進後にそれぞれが継ぎ足し接合されることを特It is noted that they are added and joined after the steel pipe is propelled.
徴とする請求項1に記載の地下空洞の構築工法。The construction method of an underground cavity according to claim 1, wherein the underground cavity is constructed.
JP06130586A 1994-06-13 1994-06-13 Construction method of underground cavity Expired - Fee Related JP3135188B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP06130586A JP3135188B2 (en) 1994-06-13 1994-06-13 Construction method of underground cavity

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP06130586A JP3135188B2 (en) 1994-06-13 1994-06-13 Construction method of underground cavity

Publications (2)

Publication Number Publication Date
JPH07331998A JPH07331998A (en) 1995-12-19
JP3135188B2 true JP3135188B2 (en) 2001-02-13

Family

ID=15037757

Family Applications (1)

Application Number Title Priority Date Filing Date
JP06130586A Expired - Fee Related JP3135188B2 (en) 1994-06-13 1994-06-13 Construction method of underground cavity

Country Status (1)

Country Link
JP (1) JP3135188B2 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4625815B2 (en) * 2007-01-20 2011-02-02 株式会社アルファシビルエンジニアリング Non-open-cutting construction method for underground structures
CN104061007B (en) * 2014-06-13 2016-06-15 长江勘测规划设计研究有限责任公司 Super-span dome reserved center, a kind of nuclear reactor cavern, underground rock pillar construction technology
CN104120739A (en) * 2014-08-11 2014-10-29 北京市政建设集团有限责任公司 Multi-pilot tunnel excavation one-off arching construction method
CN104775828B (en) * 2015-03-27 2017-04-05 广东省建筑设计研究院 A kind of high stability rectangular cross section subterranean tunnel construction and its construction method
CN105019474B (en) * 2015-07-29 2017-09-26 上海市政工程设计研究总院(集团)有限公司 A kind of genuine reconstruction structure and its reconstruction method
CN108019211B (en) * 2018-01-23 2023-09-12 中国铁路设计集团有限公司 Water-intercepting curtain in pilot tunnel of water-rich sandy pebble stratum and construction method thereof
CN110700311A (en) * 2019-07-01 2020-01-17 中建五局土木工程有限公司 One-step molding construction method for open-cut large-span double-hole broken line arch tunnel large-volume concrete

Also Published As

Publication number Publication date
JPH07331998A (en) 1995-12-19

Similar Documents

Publication Publication Date Title
JP3135188B2 (en) Construction method of underground cavity
KR100289256B1 (en) Tunnel construction method in shallow toffee area
JP2000352296A (en) Method o constructing passage just under underground structure
JP2000179299A (en) Large-section tunnel construction method
JP4226954B2 (en) Underpinning method and viaduct
JPH1136338A (en) Construction method of underground structure
GB2076449A (en) Process for the construction of an underground structure and a strucutre thus obtained
JP2893349B2 (en) Large section tunnel structure and its construction method.
JP4303512B2 (en) Construction method of large section tunnel
JP2000291398A (en) Underground structure and construction method therefor
JP4214033B2 (en) Construction method of shaft
JPS6117696A (en) Construction of underground head
JP3511145B2 (en) How to build underground structures
JPH0654016B2 (en) Underground space construction method
JPH07331997A (en) Constructing method of rock cavern
JPS6018769B2 (en) Construction method of underground structure
JP2004316125A (en) Work execution method for large sectional tunnel and deformed section shield machine
JP2932197B2 (en) Excavation method for large or very large tunnel
JPS61186623A (en) Method of building foundation of building
JP2846248B2 (en) Earth retaining wall and construction method
JPH0366452B2 (en)
JPH0726877A (en) Construction method of underground structure
JP3865468B2 (en) How to build a tunnel
JPS63201295A (en) Method of protective construction of existing tunnel
JP2005307688A (en) Construction method for earth retaining wall for newly built underground skeleton and construction method for newly built skeleton by use of its method

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071201

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081201

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091201

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101201

Year of fee payment: 10

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101201

Year of fee payment: 10

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111201

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121201

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121201

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131201

Year of fee payment: 13

LAPS Cancellation because of no payment of annual fees