KR20000065282A - tubular roof tunnel construction method - Google Patents

tubular roof tunnel construction method Download PDF

Info

Publication number
KR20000065282A
KR20000065282A KR1019990011390A KR19990011390A KR20000065282A KR 20000065282 A KR20000065282 A KR 20000065282A KR 1019990011390 A KR1019990011390 A KR 1019990011390A KR 19990011390 A KR19990011390 A KR 19990011390A KR 20000065282 A KR20000065282 A KR 20000065282A
Authority
KR
South Korea
Prior art keywords
steel pipe
tunnel
main steel
sub
main
Prior art date
Application number
KR1019990011390A
Other languages
Korean (ko)
Other versions
KR100322844B1 (en
Inventor
김기형
Original Assignee
김기형
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=19578502&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=KR20000065282(A) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by 김기형 filed Critical 김기형
Priority to KR1019990011390A priority Critical patent/KR100322844B1/en
Publication of KR20000065282A publication Critical patent/KR20000065282A/en
Application granted granted Critical
Publication of KR100322844B1 publication Critical patent/KR100322844B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Abstract

PURPOSE: A pipe structure tunnel construction method is provided to construct a tunnel in downtown safely and precisely by excavating after a side wall is completed, and reduce the vibration and the noise. CONSTITUTION: A pipe structure tunnel construction method comprises the steps of; forming a vertical pit to the designed depth of tunnel(1); pressing a main(110) or a sub steel pipe(120) in the lateral direction of tunnel by a hydraulic jack; pressing a sub steel pipe from one main steel pipe to the other main steel pipe; excavating from a main steel pipe downward to make a space for side wall of tunnel during maintaining the sheeting; forming a side wall of tunnel by concreting in the space that is formed in the inside of main steel pipe; forming a roof by concreting into the one main steel pipe and into the sub-steel pipe and then into the other main steel pipe; excavating the inside of tunnel after the concrete of main and sub steel pipe; and forming a concrete layer in the floor of tunnel.

Description

관 구조 터널 건조공법{tubular roof tunnel construction method}Tubular roof tunnel construction method

본 발명은 관 구조 터널 건조공법에 관한 것으로, 상세하게는 공사중 시민의 보행이나 상업활동 및 교통의 지장을 주지 않고 안전하게 시공할 수 있도록 하는 관 구조 터널 건조공법에 관한 것이다.The present invention relates to a tubular tunnel construction method, and more particularly, to a tubular tunnel construction method that can be safely installed without disturbing citizens walking, commercial activities and traffic during construction.

일반적으로 터널은 흙이나 바위를 파서 지표면 아래에 만든 공간으로 거의 수평이며 가는 모양의 긴 통로를 말한다. 위쪽에서 재래지반을 남기고 땅속을 파 들어가 만들어진 것이 보통이지만, 지표에서부터 홈모양으로 파고 들어가 그 속에 터널구조물을 만든 다음 다시 묻는 개착공법에 의한 것도 터널에 포함된다. 이 공법은 도시내의 도로 아래에 비교적 얕은 지하철도를 만들 때 이용된다. 오늘날에는 터널의 용도나 양상이 다양화되어 지하발전소용의 대공동, 지하의 자동차주차장이나 각종창고, 지하정유시설이나 지하도로등 흙이나 바위가 붕괴하여 떨어지는 것을 막으면서 땅속을 파서 공간을 만들고, 영구적으로 재래지반을 지지하는 구조물을 건설하는 것도 넓은 뜻으로 터널이라 한다.In general, tunnels are spaces created by digging soil or rock and beneath the surface of the earth. It is usually made by digging up the ground leaving the ground in the upper part, but it is also included in the tunnel by digging into the groove shape from the surface, making the tunnel structure in it, and then burying it again. This technique is used to create a relatively shallow subway road under the roads in the city. Today, the use and aspects of tunnels are diversified, digging into the ground, preventing dirt and rocks from collapsing and falling down, such as large cavities for underground power plants, underground car parking lots, warehouses, underground refineries, and underground roads. Constructing a structure that permanently supports conventional ground is also broadly called a tunnel.

터널의 용도는 철도, 도로 터널 등의 교통용 터널과, 수력발전, 관개 등을 위한 수로 터널 및, 상하수도, 전선로 등의 관로 터널 등이 있다. 이 밖에 지하발전소, 변전소 및 석유류 저장용 지하공동 등도 터널 기술을 적용한 지하건조물로서 터널에 포함시킬 수 있다. 또 터널은 굴착의 대상이 되는 지질에 따라서 암석터널과 토사터널로 나누며, 시공 장소, 시공 방법에 따라 산악터널, 도시터널, 수저터널, 개착터널, 실드터널, 침매터널 등으로 세분된다.The use of the tunnel includes traffic tunnels such as railroads and road tunnels, water tunnels for hydroelectric power generation, irrigation, and pipeline tunnels such as water and sewage and wire lines. In addition, underground power plants, substations, and underground cavities for storing oil can also be included in tunnels as tunnels. Tunnels are divided into rock and earth tunnels according to the geology to be excavated, and they are subdivided into mountain tunnels, urban tunnels, cutlery tunnels, open tunnels, shield tunnels and immersion tunnels depending on the construction site and construction method.

이러한 터널은 여러가지 건조방법으로 개발되어 현재까지 진행되었으나 시민의 보행이나 상업활동 및 교통의 지장을 줄 뿐만 아니라 토압의 변화 및 지반의 거동이 심하게 발생되어 인근 구조물에 악영향을 미치게 되는 문제점이 있었다. 그러므로 시민의 보행이나 상업활동 및 교통 등에서 발생되는 불편함과 피해를 최소하고 안전하게 시공할 수 있는 터널 건조방법의 개발이 지속적으로 요구되었다.These tunnels have been developed by various construction methods, but have been progressed up to now, but not only do people's walking, commercial activities, and traffic problems, but also have a problem that adversely affects nearby structures due to severe earth pressure changes and ground behaviors. Therefore, there has been a continuous demand for the development of tunnel construction methods that can minimize and safely construct inconveniences and damages caused by citizens' walking, commercial activities and traffic.

따라서 본 발명의 주 목적은 흙파기를 최소로 억제하고 루프 및 측벽이 완성된 후 흙파기를 실시하여 지반의 거동 및 토압의 변화를 최소화하여 안전하고 정확하게 도심에서 터널을 건조할 수 있도록 하는 데 있다.Therefore, the main object of the present invention is to minimize the excavation and minimize the change of ground behavior and earth pressure by digging after completion of the roof and sidewall to safely and accurately build the tunnel in the city .

본 발명의 다른 목적은 시민의 보행이나 상업활동 및 교통의 지장을 최소화하여 터널 건조로 인한 주변생활의 불편함을 최소화하도록 하는 데 있다.Another object of the present invention is to minimize the inconvenience of people walking or commercial activities and traffic to minimize the inconvenience of surrounding life due to tunnel construction.

본 발명의 다른 목적은 소음 및 진동을 최소화하여 쾌적한 공사 환경을 제공하는 데 있다.Another object of the present invention is to provide a pleasant construction environment by minimizing noise and vibration.

본 발명의 다른 목적은 터널 시공지역의 주변 구조물에 대하여 안전성을 유지시킬 수 있도록 하는 데 있다.Another object of the present invention is to maintain safety for the surrounding structure of the tunnel construction area.

도 1 은 본 발명의 관 구조 터널 건조공법 중 메인강관 압입상태를 나타낸 측면도.1 is a side view showing a main steel pipe indentation state of the pipe structure tunnel drying method of the present invention.

도 2 는 본 발명의 관 구조 터널 건조공법 중 메인강관 압입상태를 나타낸 평면도.Figure 2 is a plan view showing a main steel pipe indentation state of the pipe structure tunnel drying method of the present invention.

도 3 은 본 발명의 관 구조 터널 건조공법 중 메인강관에서 서브강관 압입상태를 나타낸 측면도.Figure 3 is a side view showing a sub-steel pipe indentation state in the main steel pipe of the pipe structure tunnel construction method of the present invention.

도 4 는 본 발명의 관 구조 터널 건조공법 중 메인강관에서 서브강관 압입상태를 나타낸 평면도.Figure 4 is a plan view showing a sub-steel pipe indentation state in the main steel pipe of the pipe structure tunnel drying method of the present invention.

도 5 는 본 발명의 관 구조 터널 건조공법 중 메인강관에서 팀버를 설치상태를 나타낸 정면도.5 is a front view showing a timber installation state in the main steel pipe of the tubular structure tunnel construction method of the present invention.

도 6 은 본 발명의 관 구조 터널 건조공법 중 팀버 트랜치를 상세하게 나타낸 평면도.Figure 6 is a plan view showing in detail the timber trench of the tubular tunnel construction method of the present invention.

도 7 은 본 발명의 관 구조 터널 건조공법 중 팀버 트랜치를 상세하게 나타낸 정면도.Figure 7 is a front view showing in detail the timber trench of the tubular tunnel construction method of the present invention.

도 8 은 본 발명의 관 구조 터널 건조공법 중 관내에 콘크리트 타설 순서를 나타낸 콘크리트 채움 순서도.8 is a concrete filling flowchart showing a concrete pouring sequence in the pipe during the tunnel construction method of the tubular structure of the present invention.

도 9 는 본 발명의 관 구조 터널 건조공법 중 터널 내부 흙파기 및 바닥 콘크리트 타설 순서도.9 is a flow chart illustrating the excavation and ground concrete in the tunnel during the tubular tunnel construction method of the present invention.

도 10 은 본 발명의 관 구조 터널 건조공법으로 루프의 일측에만 메인강관을 설치하여 완성시킨 터널을 나타낸 사시도.Figure 10 is a perspective view showing a tunnel completed by installing the main steel pipe only on one side of the loop by the tube structure tunnel drying method of the present invention.

도 11 은 본 발명의 관 구조 터널 건조공법으로 루프의 양측에 메인강관을 설치하여 완성시킨 터널을 나타낸 사시도.Figure 11 is a perspective view showing a tunnel completed by installing the main steel pipe on both sides of the loop by the tube structure tunnel drying method of the present invention.

*도면의 주요 부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *

1; 터널 10; 유압잭One; Tunnel 10; Hydraulic Jack

110; 메인강관 120; 서브강관110; Main steel pipe 120; Sub steel pipe

130; 콘크리트팀버 140; 서포트130; Concrete timber 140; support

위와 같은 목적을 달성하기 위하여 본 발명의 터널 건조공법은 지표에서 수직으로 터널의 시공위치 까지 수직갱을 형성시키는 단계와, 상기 수직갱을 형성시킨 후 수직갱에서 압입수단을 이용하여 메인강관을 터널의 루프 좌우단에서 터널의 길이방향으로 순차로 연결하여 압입하는 단계와, 상기 압입된 좌우 메인강관 중 일측 메인강관에서 타측 메인강관으로 서브강관을 압입하는 단계와, 상기 메인강관에서 하향으로 토류벽을 유지하면서 굴착하는 단계와, 상기 메인강관에 하향으로 형성된 공간에 콘크리트를 타설하여 터널 측벽을 형성시키는 단계와, 상기 일측 메인강관에 콘크리트를 타설하는 단계와, 상기 서브강관에 콘크리트를 타설하는 단계와, 상기 타측 메인강관에 콘크리트를 타설하는 단계와, 상기 타측 메인강관 콘크리트 타설 후 터널의 내부 흙파기 단계 및, 상기 터널 내부 흙파기 완료후 터널 바닥에 콘크리트를 설치하는 단계로 구성함이 그 기술적 구성상의 기본 특징으로 한다.In order to achieve the above object, the tunnel drying method of the present invention comprises the steps of forming a vertical shaft from the ground to the construction position of the tunnel vertically, and after forming the vertical shaft, the main steel pipe is left and right by means of a press-fit means in the vertical shaft. In step, the step of connecting in the longitudinal direction of the tunnel in order to press-in, the step of press-in the sub-steel pipe from the main steel pipe on the other side of the pressed left and right main steel pipe to the other main steel pipe, and excavation while maintaining the earth wall downward from the main steel pipe And pouring concrete into a space formed downward in the main steel pipe to form a tunnel sidewall, pouring concrete into the one main steel pipe, and pouring concrete into the sub steel pipe, and the other side. Placing concrete on the main steel pipe, and the concrete pouring after the other main steel pipe The inside of the box and the soil digging step, consists of steps for installing a concrete floor tunnel after completion of the destruction Tunnel soil shall be based on the feature that the technical configuration.

위와 같이 구성된 본 발명의 바람직한 실시 예를 첨부된 도면을 참조하면서 상세히 설명하면 다음과 같다.When described in detail with reference to the accompanying drawings a preferred embodiment of the present invention configured as described above are as follows.

도 1 은 본 발명의 관 구조 터널 건조공법 중 메인강관 압입상태를 나타낸 측면도이고, 도 2 는 본 발명의 관 구조 터널 건조공법 중 메인강관 압입상태를 나타낸 평면도이며, 도 3 은 본 발명의 관 구조 터널 건조공법 중 메인강관에서 서브강관 압입상태를 나타낸 측면도이고, 도 4 는 본 발명의 관 구조 터널 건조공법 중 메인강관에서 서브강관 압입상태를 나타낸 평면도이며, 도 5 는 본 발명의 관 구조 터널 건조공법 중 메인강관에서 팀버를 설치상태를 나타낸 정면도이고, 도 6 은 본 발명의 관 구조 터널 건조공법 중 팀버 트랜치를 상세하게 나타낸 평면도이며, 도 7 은 본 발명의 관 구조 터널 건조공법 중 팀버 트랜치를 상세하게 나타낸 정면도이고, 도 8 은 본 발명의 관 구조 터널 건조공법 중 관내에 콘크리트 타설 순서를 나타낸 콘크리트 채움 순서도이며, 도 9 는 본 발명의 관 구조 터널 건조공법 중 터널 내부 흙파기 및 바닥 콘크리트 타설 순서도이고, 도 10 은 본 발명의 관 구조 터널 건조공법으로 루프의 일측에만 메인강관을 설치하여 완성시킨 터널을 나타낸 사시도이며, 도 11 은 본 발명의 관 구조 터널 건조공법으로 루프의 양측에 메인강관을 설치하여 완성시킨 터널을 나타낸 사시도이다.1 is a side view showing a main steel pipe indentation state of the tube structure tunnel drying method of the present invention, Figure 2 is a plan view showing a main steel pipe indentation state of the tube structure tunnel drying method of the present invention, Figure 3 is a pipe structure of the present invention Figure 4 is a side view showing a sub-steel pipe indentation state in the main steel pipe of the tunnel drying method, Figure 4 is a plan view showing a sub-steel pipe indentation state in the main steel pipe of the tunnel construction method of the present invention, Figure 5 is a pipe structure tunnel construction of the present invention 6 is a plan view showing the timber trench in the tubular tunnel construction method of the present invention in detail, Figure 7 is a timber trench of the tubular tunnel construction method of the present invention. Figure 8 is a front view showing in detail, Figure 8 is a concrete filling order showing the concrete placing sequence in the pipe during the pipe structure tunnel construction method of the present invention FIG. 9 is a flow chart illustrating the excavation of soil inside a tunnel and a bottom concrete pouring process in a tubular tunnel construction method of the present invention, and FIG. 10 is a tunnel in which a main steel pipe is installed only at one side of a loop by the tubular tunnel construction method of the present invention. 11 is a perspective view showing the tunnel completed by installing the main steel pipe on both sides of the loop by the pipe structure tunnel drying method of the present invention.

도 1 내지 도 11 에 나타낸 바와 같이, 본 발명의 터널 건조공법은 지표에서 수직으로 터널(1)의 시공위치 까지 수직갱을 형성시키는 단계와, 상기 수직갱을 형성시킨 후 수직갱에서 압입수단을 이용하여 메인강관(110)을 터널(1)의 루프 좌우단에서 터널의 길이방향으로 순차로 연결하여 압입하는 단계와, 상기 압입된 좌우 메인강관(110) 중 일측 메인강관(110)에서 타측 메인강관(110)으로 서브강관(120)을 압입하는 단계와, 상기 메인강관(110)에서 하향으로 토류벽을 유지하면서 굴착하여 터널(1)측벽용 공간을 형성시키는 단계와, 상기 메인강관(110)에 하향으로 형성된 공간에 콘크리트를 타설하여 터널(1)측벽을 형성시키는 단계와, 상기 일측 메인강관(110) 서브강관(120) 타측 메인강관(110)에 순차적으로 콘크리트를 채워 경화시키는 단계와, 상기 메인강관(110) 서브강관(120)의 내부 콘크리트 경화후 터널(1)의 내부 흙파기 단계 및, 상기 터널(1) 내부 흙파기 완료후 터널(1) 바닥에 콘크리트를 설치하는 단계로 구성한다.As shown in Figures 1 to 11, the tunnel drying method of the present invention is to form a vertical shaft to the construction position of the tunnel (1) vertically from the surface, and after the vertical shaft is formed by using a press-in means in the vertical shaft Connecting the steel pipe 110 in the longitudinal direction of the tunnel at the right and left ends of the loop of the tunnel 1 and pressing the steel pipe 110, and the other main steel pipe 110 from one of the main steel pipes 110 of the pressed left and right main steel pipes 110. Press-fitting the sub steel pipe (120), excavating and maintaining the earth wall downward from the main steel pipe (110) to form a space for the tunnel (1) side wall, and downward in the main steel pipe (110) Placing concrete in the formed space to form the tunnel (1) side wall, the step of filling the concrete in the main steel pipe 110, the other side main steel pipe 110, the other side of the main steel pipe 110, and hardened sequentially, the main steel pipe (110) After the internal concrete hardening of the sub-steel pipe 120, and the internal soil digging step of the tunnel (1), and after the completion of the internal soil excavation of the tunnel (1) comprises a step of installing concrete on the bottom of the tunnel (1).

도 1 과 도 2 에 나타낸 바와 같이, 메인강관(110)과 서브강관(120)을 지중에서 관입하기 위하여 터널(1)의 위치까지 수직갱을 구축하고 수직갱의 내부에 유압잭(10) 등의 압입수단을 설치하여 터널(1)의 루프에 해당하는 좌우단에 메인강관(110)을 소정심도까지 연결하면서 압입하며 메인강관(110)의 압입으로 유입되는 흙은 제거한다.As shown in Figure 1 and 2, in order to penetrate the main steel pipe 110 and sub-steel pipe 120 in the ground to build a vertical shaft up to the position of the tunnel (1) and press-in means such as a hydraulic jack 10 in the interior of the vertical shaft Install and press the main steel pipe 110 to the predetermined depth to the left and right ends corresponding to the loop of the tunnel (1) to remove the dirt introduced by the press-fit of the main steel pipe (110).

도 3 과 도 4 에 나타낸 바와 같이, 메인강관(110)의 압입이 완료되면 일측 메인강관(110) 내부에 압입수단인 유압잭(10)을 설치하고 일측 메인강관(110)에서 타측 메인강관(110)으로 서브강관(120)을 압입하여 연결하되, 좌우 메인강관(110)의 서브강관(120) 연결부분은 절개하여 상호 연통되게 연결한 다음 서브강관(120)의 압입으로 유입된 흙을 제거한다.As shown in FIG. 3 and FIG. 4, when the press-fitting of the main steel pipe 110 is completed, the hydraulic jack 10, which is a press-fit means, is installed in one main steel pipe 110, and the other main steel pipe 110 is installed at one main steel pipe 110. The sub-steel pipe 120 is pressed in and connected, but the connection parts of the sub-steel pipes 120 of the left and right main steel pipes 110 are incised and connected to each other, and then the soil introduced by the indentation of the sub-steel pipes 120 is removed. .

도 5 내지 도 7 에 나타낸 바와 같이, 서브강관(120)의 설치가 완료되면 좌우 메인강관(110)의 내부 하측을 절개하고 절개부분을 통하여 하향으로 굴착한다. 이때, 굴착면의 붕괴를 방지하기 위하여 양면에 콘크리트 팀버(130)를 설치하면서 지하방향으로 소정심도까지 굴착한다. 여기서 콘크리트 팀버(130) 사이에는 서포트(140)를 설치하여 양면에 설치된 콘크리트 팀버(130)를 지지하도록 한다.5 to 7, when the installation of the sub-steel pipe 120 is completed, the inner lower side of the left and right main steel pipe 110 is cut and excavated downward through the incision. At this time, while installing the concrete timber 130 on both sides in order to prevent the collapse of the excavation surface is excavated to a predetermined depth in the underground direction. Here, by installing the support 140 between the concrete timber 130 to support the concrete timber 130 installed on both sides.

도 8 에 나타낸 바와 같이, 터널(10)의 측벽 형성을 위한 팀버 트랜치가 완료되면 먼저 좌우 팀버 트래치의 내부에 철근 엮음 후 콘크리트를 채워 터널(1)의 측벽을 형성시킨 다음 일측 메인강관(110)과 서브강관(120) 및 타측 메인강관(110)에 차례로 콘크리트를 채워 터널(1)의 루프를 형성시킨다.As shown in FIG. 8, when the timber trenches for forming the sidewalls of the tunnel 10 are completed, first, the sidewalls of the tunnel 1 are formed by weaving reinforcing bars inside the left and right timber traps, and then filling the concrete to form one side main steel pipe 110. The sub steel pipe 120 and the other main steel pipe 110 in order to fill the concrete to form a loop of the tunnel (1).

도 9 에 나타낸 바와 같이, 팀버 트랜치와 서브강관(120) 및 메인강관(110)에 충진된 콘크리트가 모두 경화되면 터널의 루프 하측의 흙을 파내고 좌우 측벽의 하부 내측에 바닥 콘크리트를 설치하여 도 11 과 같이 터널(1)을 박스 형상으로 형성시킨다.As shown in FIG. 9, when the concrete filled in the timber trench, the sub-steel pipe 120 and the main steel pipe 110 is cured, the soil under the roof of the tunnel is excavated and the bottom concrete is installed inside the lower side of the left and right side walls. The tunnel 1 is formed into a box like 11.

한편 도 10 에 나타낸 바와 같이, 터널(1)의 루프 일측에만 메인강관(110)을 압입하고 메인강관(110)에서 루프의 타측으로 서브강관(120)을 압입하되, 서브강관(120)의 타측에서 터널(1)의 길이 방향으로 서브강관(120)의 하부를 절개하여 상기와 같이 하향으로 팀버 트랜치를 형성하고, 팀버 트랜치 내부에 콘크리트를 채워 터널(1)의 측벽을 형성할 수 도 있다.Meanwhile, as shown in FIG. 10, the main steel pipe 110 is pressed into only one side of the loop of the tunnel 1 and the sub steel pipe 120 is pressed into the other side of the loop from the main steel pipe 110, but the other side of the sub steel pipe 120 is pressed. In the lower portion of the sub-steel pipe 120 in the longitudinal direction of the tunnel (1) to form a timber trench downward as described above, and fill the concrete inside the timber trench may form a sidewall of the tunnel (1).

여기서, 본 발명은 콘크리트에 각종 보강소재 또는 철근의 묶음을 이용하여 콘크리트의 타설후 강도를 향상시킬 수 있도록 한다.Here, the present invention to improve the strength after the concrete is poured by using a bundle of various reinforcing materials or reinforcement to the concrete.

여기서 본 발명의 터널(1)은 그 크기를 국한 하는 것이 아니며 메인강관(110)이나 서브강관(120)의 규격를 달리하여 시공하고자 하는 터널(1)의 규모에 알맞게 조절하여 사용한다.Here, the tunnel 1 of the present invention is not limited to its size, and is used by adjusting the size of the tunnel 1 to be constructed by varying the specifications of the main steel pipe 110 or the sub steel pipe 120.

이상에서 살펴본 바와 같이, 본 발명의 터널 건조공법은 지표에서 수직으로 터널(1)의 시공위치 까지 수직갱을 형성시키는 단계와, 상기 수직갱을 형성시킨 후 수직갱에서 압입수단을 이용하여 메인강관(110)을 터널(1)의 루프 좌우단에서 터널의 길이방향으로 순차로 연결하여 압입하는 단계와, 상기 압입된 좌우 메인강관(110) 중 일측 메인강관(110)에서 타측 메인강관(110)으로 서브강관(120)을 압입하는 단계와, 상기 메인강관(110)에서 하향으로 토류벽을 유지하면서 굴착하여 터널(1)측벽용 공간을 형성시키는 단계와, 상기 메인강관(110)에 하향으로 형성된 공간에 콘크리트를 타설하여 터널(1)측벽을 형성시키는 단계와, 상기 일측 메인강관(110) 서브강관(120) 타측 메인강관(110)에 순차적으로 콘크리트를 채워 경화시키는 단계와, 상기 메인강관(110) 서브강관(120)의 내부 콘크리트 경화후 터널(1)의 내부 흙파기 단계 및, 상기 터널(1) 내부 흙파기 완료후 터널(1) 바닥에 콘크리트를 설치하는 단계로 구성하므로 안전하고 정확하게 도심에서 터널을 건조할 수 있고, 특히 시민의 보행이나 상업활동 및 교통의 흐름에 방해되는 요소가 적어 터널 건조로 인한 주변생활의 불편함을 최소화하며, 또한 소음 및 진동을 최소화하여 쾌적한 공사환경을 제공할 뿐만 아니라 터널의 측벽과 루프를 형성시킨 경화시킨 다음 터널 내부측 흙을 제거하므로 토압의 변화와 지반의 거동이 거의 없고 이로 인하여 터널 시공지역의 주변 구조물에 미치는 악영향이 제거하여 안전하게 시공할 수 있는 효과가 있다.As described above, the tunnel drying method of the present invention comprises the steps of forming a vertical shaft up to the construction position of the tunnel 1 vertically from the ground, and after forming the vertical shaft, the main steel pipe 110 by using a press-fit means in the vertical shaft. The step of connecting the inlet in the longitudinal direction of the tunnel in the right and left ends of the loop of the tunnel (1), and the sub-steel pipe from one of the main steel pipe 110 of the pressed left and right main steel pipe 110 to the other main steel pipe 110 Pressing 120, excavating while maintaining the earth wall downward from the main steel pipe 110 to form a space for the tunnel (1) side wall, concrete in the space formed downward in the main steel pipe (110) Forming the tunnel (1) side wall, and filling concrete in the main steel pipe (110) sub steel pipe (120) and the other main steel pipe (110) in order to harden, and the main steel pipe (110) sub River After the internal concrete hardening of the 120 (120) the internal soil digging step of the tunnel, and after the completion of the internal soil digging tunnel (1) consists of the step of installing concrete on the bottom of the tunnel (1) safely and accurately the tunnel in the city It can be built, and in particular, there are few elements that hinder the walking, commercial activities and traffic flow of citizens, which minimizes the inconvenience of surrounding life due to tunnel construction, and also provides a pleasant construction environment by minimizing noise and vibration. After hardening by forming the tunnel sidewalls and loops, the soil inside the tunnel is removed, so there is little change in earth pressure and ground behavior, thereby removing the adverse effects on the surrounding structures of the tunnel construction area, which makes it safe to construct. .

Claims (2)

지표에서 수직으로 터널(1)의 시공위치 까지 수직갱을 형성시키는 단계와,Forming a vertical shaft from the ground to the construction position of the tunnel 1 vertically; 상기 수직갱을 형성시킨 후 수직갱에서 압입수단을 이용하여 메인강관(110)을 터널(1)의 루프 좌우단에서 터널의 길이방향으로 순차로 압입하여 연결하는 단계와,Forming the vertical shaft and then connecting the main steel pipe 110 by pressing in the vertical shaft sequentially from the left and right ends of the loop 1 in the longitudinal direction of the tunnel; 상기 압입된 좌우 메인강관(110) 중 일측 메인강관(110)에서 타측 메인강관(110)으로 서브강관(120)을 압입하는 단계와,Press-fitting the sub-steel pipe 120 from one of the main steel pipes 110 to the other main steel pipe 110 of the press-fitted left and right main steel pipes 110; 상기 메인강관(110)에서 하향으로 토류벽을 유지하면서 굴착하여 터널(1)측벽용 공간을 형성시키는 단계와,Excavating while maintaining the earth wall downward from the main steel pipe 110 to form a space for the tunnel 1 side wall; 상기 메인강관(110)에 하향으로 형성된 공간에 콘크리트를 타설하여 터널(1)측벽을 형성시키는 단계와,Pouring concrete into a space formed downward in the main steel pipe 110 to form a tunnel 1 side wall; 상기 일측 메인강관(110) 서브강관(120) 타측 메인강관(110)에 순차적으로 콘크리트를 채워 경화시키는 루프형성단계와,A loop forming step of sequentially filling concrete to one side of the main steel pipe 110 and the sub steel pipe 120 to the other main steel pipe 110; 상기 메인강관(110) 서브강관(120)의 내부 콘크리트 경화후 터널(1)의 내부 흙파기 단계 및,An internal soil digging step of the tunnel 1 after the internal concrete hardening of the main steel pipe 110 and the sub steel pipe 120; 상기 터널(1) 내부 흙파기 완료후 터널(1) 바닥에 콘크리트를 설치하는 박닥 완료단계로 구성한 것을 특징으로 하는 관 구조 터널 건조공법.Pipe tunnel construction method, characterized in that consisting of a bakbak complete step of installing concrete on the bottom of the tunnel (1) after the completion of the excavation of the inside of the tunnel (1). 제 1 항에 있어서The method of claim 1 상기 터널(1)의 루프 일측에만 메인강관(110)을 압입하고 메인강관(110)에서 루프의 타측으로 서브강관(120)을 압입하되, 서브강관(120)의 타측에서 터널(1)의 길이 방향으로 팀버 트랜치를 구축하여 터널(1)의 측벽을 형성하도록 구성한 것을 특징으로 하는 관 구조 터널 건조공법.The main steel pipe 110 is pressed into only one side of the loop of the tunnel 1, and the sub steel pipe 120 is pressed into the other side of the loop from the main steel pipe 110, but the length of the tunnel 1 is at the other side of the sub steel pipe 120. A tubular tunnel construction method, characterized in that the side wall of the tunnel (1) by forming a timber trench in the direction.
KR1019990011390A 1999-04-01 1999-04-01 tubular roof tunnel construction method KR100322844B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1019990011390A KR100322844B1 (en) 1999-04-01 1999-04-01 tubular roof tunnel construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019990011390A KR100322844B1 (en) 1999-04-01 1999-04-01 tubular roof tunnel construction method

Publications (2)

Publication Number Publication Date
KR20000065282A true KR20000065282A (en) 2000-11-06
KR100322844B1 KR100322844B1 (en) 2002-02-07

Family

ID=19578502

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019990011390A KR100322844B1 (en) 1999-04-01 1999-04-01 tubular roof tunnel construction method

Country Status (1)

Country Link
KR (1) KR100322844B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100439968B1 (en) * 2002-02-02 2004-07-15 백상현 A method of constrution method for tunnel of structure pipe
KR100794609B1 (en) * 2006-01-13 2008-01-14 신일씨엔아이(주) Construction method of underground structure using concrete filled pipe roof and concrete wall
KR100805189B1 (en) * 2006-09-12 2008-02-21 신일씨엔아이(주) Construction method of underground structure characterized by going side by side wall construction and excavation

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100991630B1 (en) 2010-05-17 2010-11-04 이병택 A container sleeve push ahead type tunnel manufacture method
KR101041301B1 (en) 2010-07-29 2011-06-14 이평우 Method for digging tunnel
KR101407631B1 (en) 2012-07-25 2014-06-13 쌍용건설 주식회사 Underground tunnel structure and construction method for underground tunnel structure using presssed pipe
KR20160074977A (en) 2014-12-19 2016-06-29 한국건설기술연구원 Rock shed tunnel structure using concrete filled steel tube, and construction method for the same
KR101674476B1 (en) 2015-05-08 2016-11-10 한국철도기술연구원 Trench shield apparatus for near-surface transit tunnel and the near-surface transit tunnel rapid construction method using the same
KR102122675B1 (en) 2019-01-15 2020-06-15 티알이엔씨(주) Underground structure construction method with internal joint ring on thrust tube for continuous steel joint structure
KR102029429B1 (en) 2019-02-22 2019-10-07 티알이엔씨(주) Underground structure construction method with internal joint ring on thrust tube for continuous steel joint structure

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06336894A (en) * 1993-03-31 1994-12-06 Rocksoil Spa Constructing method of large-diametral tunnel

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100439968B1 (en) * 2002-02-02 2004-07-15 백상현 A method of constrution method for tunnel of structure pipe
KR100794609B1 (en) * 2006-01-13 2008-01-14 신일씨엔아이(주) Construction method of underground structure using concrete filled pipe roof and concrete wall
KR100805189B1 (en) * 2006-09-12 2008-02-21 신일씨엔아이(주) Construction method of underground structure characterized by going side by side wall construction and excavation

Also Published As

Publication number Publication date
KR100322844B1 (en) 2002-02-07

Similar Documents

Publication Publication Date Title
KR100794609B1 (en) Construction method of underground structure using concrete filled pipe roof and concrete wall
KR20100115019A (en) Panel joint for construction for underground diaphragm well and underground diaphragm well constructing method using the same
KR100322844B1 (en) tubular roof tunnel construction method
KR20070076553A (en) Construction method of underground structure using concrete filled pipe roof and concrete wall
KR100805189B1 (en) Construction method of underground structure characterized by going side by side wall construction and excavation
KR100618597B1 (en) Cast in place concrete pile using vibro magnetic shovel hammer, and the construction method of this
KR100322845B1 (en) tubular roof tunnel construction method
KR100289256B1 (en) Tunnel construction method in shallow toffee area
KR100439968B1 (en) A method of constrution method for tunnel of structure pipe
JP3896351B2 (en) Construction method of underground wall and construction method of underpass
KR101037860B1 (en) A assemble type mold construction structure for tunnel building
JPS6158640B2 (en)
CN210507517U (en) Combined member suitable for retaining wall heightening
CN210315908U (en) Immersed tube type inspection well
KR100311122B1 (en) tubular roof tunnel construction method
KR200296444Y1 (en) Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method
JPH0415878B2 (en)
KR20080101855A (en) Underground structure construction by using underground steel inserts
KR102610909B1 (en) Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking
KR100429283B1 (en) Construction Method using Precast Concrete for Diaphragm Wall
JPS5936058B2 (en) How to construct a structure using underground continuous walls
JPH10102490A (en) Method of constructing underground structure
KR200375610Y1 (en) Cast in place concrete pile using vibro magnetic shovel hammer
KR20040023915A (en) Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method and construction method thereof
JP2745083B2 (en) Tunnel construction method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
O035 Opposition [patent]: request for opposition
O035 Opposition [patent]: request for opposition
O122 Withdrawal of opposition [patent]
J204 Request for invalidation trial [patent]
J301 Trial decision

Free format text: TRIAL DECISION FOR INVALIDATION REQUESTED 20130313

Effective date: 20131227

Free format text: TRIAL NUMBER: 2013100000574; TRIAL DECISION FOR INVALIDATION REQUESTED 20130313

Effective date: 20131227

FPAY Annual fee payment
J2X1 Appeal (before the patent court)

Free format text: INVALIDATION

Free format text: TRIAL NUMBER: 2014200000867; INVALIDATION

J302 Written judgement (patent court)

Free format text: JUDGMENT (PATENT COURT) FOR INVALIDATION REQUESTED 20140129

Effective date: 20141121

Free format text: TRIAL NUMBER: 2014200000867; JUDGMENT (PATENT COURT) FOR INVALIDATION REQUESTED 20140129

Effective date: 20141121

FPAY Annual fee payment

Payment date: 20150119

Year of fee payment: 14

FPAY Annual fee payment

Payment date: 20160217

Year of fee payment: 15

FPAY Annual fee payment

Payment date: 20180206

Year of fee payment: 17

LAPS Lapse due to unpaid annual fee