JP2745083B2 - Tunnel construction method - Google Patents

Tunnel construction method

Info

Publication number
JP2745083B2
JP2745083B2 JP2410585A JP41058590A JP2745083B2 JP 2745083 B2 JP2745083 B2 JP 2745083B2 JP 2410585 A JP2410585 A JP 2410585A JP 41058590 A JP41058590 A JP 41058590A JP 2745083 B2 JP2745083 B2 JP 2745083B2
Authority
JP
Japan
Prior art keywords
tunnel
water
continuous underground
underground wall
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2410585A
Other languages
Japanese (ja)
Other versions
JPH04289396A (en
Inventor
二郎 猪瀬
平門 入江
宏文 中込
禎 助川
京平 今井
Original Assignee
帝都高速度交通営団
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 帝都高速度交通営団 filed Critical 帝都高速度交通営団
Priority to JP2410585A priority Critical patent/JP2745083B2/en
Publication of JPH04289396A publication Critical patent/JPH04289396A/en
Application granted granted Critical
Publication of JP2745083B2 publication Critical patent/JP2745083B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、トンネルを開削して築
造するトンネル築造工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a tunnel construction method for digging and building a tunnel.

【0002】[0002]

【従来の技術】従来のトンネルの開削式築造工法を図3
及び図4に従って説明する。図3はトンネル断面図、図
4はその平面図である。まず、トンネル構造体線の両側
に、連続地中壁による土留2を設置し、同時に坑内の略
中央部に中間鋼杭4を設ける。次に、この土留2と中間
鋼杭4を支えとしてH形鋼か又はI形鋼などの路面受桁
6を架け、その上に覆工板8を敷き並べる。以後、支保
工(切梁)10を架設しながら、掘削坑内の地下水12
を揚水機械14,16,18で揚水し、掘削機械20に
より掘削を進める。所定深さの掘削が完了した時点で、
基礎敷コンクリートを打設し、トンネル底面からトンネ
ル構造体60の築造を進め、トンネル構造体60の立ち
上がりに伴って、支保工10を順次撤去していく。トン
ネル構造体60が完成すると、トンネル構造体60の上
を土砂で埋め戻し、その埋戻しが路面に近づくと、覆工
板8及び路面受桁6を撤去し、路面を復旧する。
2. Description of the Related Art A conventional tunnel open-cut construction method is shown in FIG.
And FIG. FIG. 3 is a sectional view of the tunnel, and FIG. 4 is a plan view thereof. First, on both sides of the tunnel structure line, the earth retaining wall 2 with the continuous underground wall is installed, and at the same time, the intermediate steel pile 4 is provided substantially in the center of the pit. Next, a road surface girder 6 such as an H-section steel or an I-section steel is supported by the soil retaining member 2 and the intermediate steel pile 4 as supports, and a lining plate 8 is laid thereon. After that, while erection (cutting beam) 10 is erected, groundwater 12
Is pumped by the pumping machines 14, 16, 18 and excavation is advanced by the excavating machine 20. When excavation of the specified depth is completed,
The foundation concrete is cast, the construction of the tunnel structure 60 is advanced from the bottom of the tunnel, and the support 10 is sequentially removed as the tunnel structure 60 rises. When the tunnel structure 60 is completed, the tunnel structure 60 is backfilled with earth and sand. When the backfill approaches the road surface, the lining plate 8 and the road surface receiving girder 6 are removed, and the road surface is restored.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、上記従
来の工法によると、トンネル内の地下水12を揚水する
ので、図3におけるトンネル周囲の地下水位線22に比
べて、土留背面地盤において曲線24に示すような地下
水位の低下が生じる。この地下水位の低下により、土留
背面地盤において地盤沈下が発生することとなる。ま
た、図5に模式的に示すように、支保工10を架設する
前にトンネルの深さに応じて土留2が僅かながら変位
し、その変位領域26が大きくなるにつれて地盤沈下領
域28も拡大することとなる。このような問題により、
従来工法を重要構造物が近接し、かつ地下水位が高い場
所で採用する際には、補助工法として、薬液注入,特殊
セメント注入による土留背面の地盤改良を行なう必要が
あった。また、土留根入部が砂地盤の場合にはボイリン
グ防止として、土留根入長の延長、薬液,特殊セメント
注入による土留根入部の地盤改良が必要とされていた。
従って、これらの地盤改良工事を行なうために建設費用
が高額になり、また、施工期間も長くなる問題点があっ
た。
However, according to the above-mentioned conventional construction method, since the groundwater 12 in the tunnel is pumped, the groundwater level line 22 around the tunnel in FIG. Such a drop in groundwater level occurs. Due to the decrease in the groundwater level, land subsidence occurs in the ground behind the soil retention. Further, as schematically shown in FIG. 5, before the shoring 10 is erected, the earth retaining part 2 is slightly displaced in accordance with the depth of the tunnel, and the ground subsidence area 28 is enlarged as the displacement area 26 is increased. It will be. Due to these problems,
When the conventional method is used in a place where important structures are close to each other and the groundwater level is high, it is necessary to improve the ground at the backside of the retaining soil by injecting a chemical solution or special cement as an auxiliary method. In addition, when the embankment was sandy, it was necessary to extend the embankment length and improve the soil in the embankment by injecting chemicals and special cement to prevent boiling.
Accordingly, there is a problem that construction costs are high and the construction period is long in order to perform these ground improvement works.

【0004】[0004]

【課題を解決するため手段】本発明のトンネル築造方法
は、上記土留背面地盤の変化は主に土留の変位と地下水
位の低下によって生ずることに着目し、先行地中梁(横
断連続地中壁)の施工により土留の変位をなくし、水中
掘削の施工により地下水位の低下を生じさせることな
く、トンネルを築造することにある。即ち、本発明は、
トンネル構造体線の両側に、連続地中壁からなる土留
設置してトンネルを築造する開削式トンネル築造工法に
おいて、前記土留間に土留の変位を防止する対圧強度を
有する横断連続地中壁をトンネル長さ方向に適宜間隔を
おいて設置する横断連続地中壁設置工程と、前記横断連
続地中壁を設置後、地下水の水位以上の掘削は常法によ
る掘削を行ない、地下水の水位以下の掘削は坑内に水を
満たして行なう掘削工程と 、前記掘削後、前記水を満た
した状態でトンネルの底面に基礎敷コンクリートを打設
するコンクリート打設工程と、前記基礎敷コンクリート
の硬化後、土留間の水を排出する水排出工程と、水の排
出後、前記基礎敷コンクリート側からトンネル構造体を
築造し、その完了後横断連続地中壁を取り壊すトンネル
構造体築造工程と、を備えたことを特徴としている。
The tunnel construction method according to the present invention focuses on the fact that the above-mentioned change in the ground behind the lands is mainly caused by the displacement of the lands and a decrease in the groundwater level, and the preceding underground beam (transverse continuous underground wall) is used. The purpose of the present invention is to eliminate the displacement of earth retaining by the construction of the tunnel, and to construct the tunnel without causing the groundwater level to be lowered by the construction of the underwater excavation. That is, the present invention
On both sides of the tunnel structure line, the earth retaining consisting underground diaphragm walls
In the open-cut tunnel construction method of installing and constructing a tunnel, the counter pressure strength for preventing the displacement of the soil during the soil is described.
The continuous continuous underground wall with a proper spacing in the length direction of the tunnel
The step of installing a continuous underground wall,
After installing the extension wall, excavation above the groundwater level is carried out by a standard method.
Excavation below the groundwater level
A digging step to be performed with filling, and after the digging, filling with the water.
Pile foundation concrete on the bottom of the tunnel
Concrete casting process and the foundation concrete
After the hardening of the water, a water discharging process to discharge the water between
After exiting, remove the tunnel structure from the foundation concrete side
Tunnel that builds and tears down continuous underground wall after completion
And a structure building process .

【0005】[0005]

【作用】トンネル構造体の両側に設置された土留間の掘
削に先行して土留の変位が防止される対圧強度を有する
断連続地中壁が設置されていることにより、掘削の深
度如何にかかわらず土圧による土留の変位を横断連続地
中壁で確実に防止する。また、地下水の水位以下の掘削
は坑内に水を満たして行なう水中掘削の施工によるもの
であることから、土留背面の地下水位は低下せず、地盤
沈下等の地盤変状も防止する。
[Action] having a pair pressure strength of the displacement of the earth retaining prior to drilling <br/> cutting between earth retaining provided on both sides of the tunnel structure is prevented
By cross-cutting underground diaphragm walls have been installed, reliably preventing the displacement of the earth retaining by soil pressure regardless depth whether drilling in cross underground diaphragm walls. Drilling below groundwater level
Is a result of the construction of underwater excavation performed by filling the mine with water , so that the groundwater level at the back of the soil does not decrease and the ground deformation such as land subsidence is prevented.

【0006】[0006]

【実施例】以下、本発明に係るトンネル築造工法の実施
例を図面に基づいて詳細に説明する。図1は本発明のト
ンネル築造工法の一実施例を説明するためのトンネル横
断面図、図2はその平面図である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments of the tunnel construction method according to the present invention will be described below in detail with reference to the drawings. FIG. 1 is a cross-sectional view of a tunnel for explaining one embodiment of the tunnel construction method of the present invention, and FIG. 2 is a plan view thereof.

【0007】まず、従来の工法と同じ様に、トンネル構
造体線の両側に、土留2(連続地中壁)を設置する。
First, in the same manner as in the conventional construction method, soil retaining members 2 (continuous underground walls) are installed on both sides of the tunnel structure line.

【0008】次に、横断連続地中壁40(先行地中梁)
を土留2の内側に設置する。この時、路面受桁6及ひ覆
工板8を架ける支えとして、横断連続地中壁40の略中
央部にH形鋼4を埋め込む。このH形鋼4を支えとし
て、路面受桁6をかけ、その上に覆工板8を敷き並べ
る。この横断連続地中壁40は図2に示すように土留2
にほぼ直交するように設置される。この横断連続地中壁
40は土留2の変位を防止するために設けられ、トンネ
ルが設けられる地盤の土圧に対抗できる程度の所定の強
度を備えている。また、それらの架設間隔dも土留2の
変位を防止するに十分な間隔が選定される。
Next, the transverse continuous underground wall 40 (preceding underground beam)
Is installed inside the soil retaining 2. At this time, the H-section steel 4 is buried in a substantially central part of the continuous underground wall 40 as a support for mounting the road surface girder 6 and the lining plate 8. With the H-section steel 4 as a support, a road surface girder 6 is hung, and a lining plate 8 is laid thereon. As shown in FIG.
It is installed so as to be almost orthogonal to. The continuous underground wall 40 is provided in order to prevent the displacement of the earth retaining member 2 and has a predetermined strength enough to withstand the earth pressure of the ground where the tunnel is provided. In addition, the erection distance d is selected to be sufficient to prevent the displacement of the earth retaining member 2.

【0009】次に、トンネルの掘削作業を進める。ここ
で地下水位22以上の土砂は従来と同じ地上掘削機械を
用いて掘削し、地下水位22以下の掘削はトンネル坑内
に水を満たし、水中掘削機械46を用いて水中で掘削を
行なう。この時、トンネル坑内の水位12はトンネル坑
外周囲の地盤の地下水位22と同じであり、従来の工法
のようには変化しないので、土留2の背面における地下
水低下による地盤沈下を防ぐことができる。
Next, the excavation work of the tunnel proceeds. Here, earth and sand having a groundwater level of 22 or higher is excavated using the same ground excavation machine as before, and excavation with a groundwater level of 22 or lower is filled with water in a tunnel pit, and excavation is performed underwater using an underwater excavation machine 46. At this time, the water level 12 in the tunnel pit is the same as the ground water level 22 of the ground around the outside of the tunnel pit, and does not change as in the conventional construction method. .

【0010】次に、掘削が終了した時点で、水中で基礎
敷コンクリート50を打設し、コンクリートが硬化して
から、水の排水を行なった後で、横断連続地中壁40間
のトンネル底面から構造体60の築造を進め、その築造
が完了してから、横断連続地中壁40を取り壊し、この
取り壊された横断連続地中壁部分トンネル構造体60
を築造する。最後にトンネル構造体60が完成すると、
トンネル構造体60の上を土砂で埋めて戻し、その埋戻
しが路面に近づくと、覆工板8及び路面受桁6を撤去
し、路面を復旧して作業を終了する。
Next, when the excavation is completed, the foundation concrete 50 is poured in water, and after the concrete has hardened, water is drained. The construction of the structure 60 is advanced from, and after the construction is completed, the crossing continuous underground wall 40 is demolished.
Tunnel demolished transverse continuous underground wall substructures 60
To build. Finally, when the tunnel structure 60 is completed,
The top of the tunnel structure 60 is buried with earth and sand, and when the backfill approaches the road surface, the lining plate 8 and the road receiving girder 6 are removed, the road surface is restored, and the work is completed.

【0011】[0011]

【発明の効果】以上、説明したように、本発明のトンネ
ル築造工法によれば、トンネル構造体の両側に設置され
た土留間に、掘削に先行して土留の変位が防止される対
圧強度を有する横断連続地中壁がトンネルの長さ方向に
適宜間隔を配して設置されていることにより、掘削の深
度如何にかかわらず土圧による土留の変位を横断連続地
中壁で確実に防止することができる。また、地下水の水
位以下の掘削は坑内に水を満たして水中掘削を行なうこ
とにより、地下水の水位低下を防止できるので、地盤改
良やボイリング防止対策等の補助工法を施こさなくても
地盤沈下やボイリング等の地盤変状を防止できてトンネ
ル築造の施行期間を短縮でき、かつトンネルの築造を低
建設費用で行なうことができ、トンネル構造体を重要構
造物に近接して築造するときの工法として最適である。
Effect of the Invention] As described above, according to the tunnel construction method of the present invention, between earth retaining provided on both sides of the tunnel structure, pair pressure strength of the displacement of the earth retaining is prevented prior to drilling Crossing continuous underground wall with
By disposing them at appropriate intervals, the displacement of the earth retaining due to earth pressure can be surely prevented at the transverse continuous ground wall regardless of the excavation depth. Also, groundwater
By position to perform the following drilling underwater excavation filled with water in downhole, it is possible to prevent a drawdown of groundwater, soil improvement and Boiling of prevention such as auxiliary method of subsidence and Boiling like without straining facilities Prevents ground deformation, shortens the construction period of tunnel construction, and enables low-cost construction of tunnels, making it ideal as a construction method when building tunnel structures close to important structures. .

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明のトンネル築造工法の一実施例を説明す
るための横断面図である。
FIG. 1 is a cross-sectional view for explaining one embodiment of a tunnel construction method of the present invention.

【図2】本発明のトンネル築造工法の一実施例を説明す
るための平面図である。
FIG. 2 is a plan view for explaining one embodiment of the tunnel construction method of the present invention.

【図3】従来のトンネル築造工法を説明するための横断
面図である。
FIG. 3 is a cross-sectional view for explaining a conventional tunnel construction method.

【図4】従来のトンネル築造工法を説明するための平面
図である。
FIG. 4 is a plan view for explaining a conventional tunnel construction method.

【図5】土留の変位と地盤沈下の状態を説明するための
横断面図である。
FIG. 5 is a cross-sectional view for explaining a state of soil displacement and land subsidence.

【符号の説明】[Explanation of symbols]

2 土留 22 地下水位 4 中間鋼杭 40 横断連続地
中壁 6 路面受桁 46 水中掘削機
械 8 覆工板 48 クレーン車 12 トンネル内水位 50 基礎敷コ
ンクリート
2 Soil 22 Groundwater level 4 Intermediate steel pile 40 Crossing continuous underground wall 6 Road girder 46 Underwater excavating machine 8 Lining plate 48 Crane truck 12 Tunnel water level 50 Foundation concrete

───────────────────────────────────────────────────── フロントページの続き (72)発明者 助川 禎 茨城県那珂郡東海村舟石川807番地3 (72)発明者 今井 京平 東京都国分寺市東戸倉二丁目24番10号 (56)参考文献 特開 昭51−42328(JP,A) 特開 平1−121414(JP,A) 特開 昭60−226917(JP,A) ──────────────────────────────────────────────────続 き Continued on the front page (72) Inventor Tadashi Sukekawa 807-3, Funaishikawa, Tokai-mura, Naka-gun, Ibaraki Pref. JP-A-51-42328 (JP, A) JP-A-1-121414 (JP, A) JP-A-60-226917 (JP, A)

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】トンネル構造体線の両側に、連続地中壁か
らなる土留2を設置してトンネルを築造する開削式トン
ネル築造工法において、前記土留2,2間に土留2の変
位を防止する対圧強度を有する横断連続地中壁40をト
ンネル長さ方向に適宜間隔をおいて設置する横断連続地
中壁設置工程と、前記横断連続地中壁40を設置後、地
下水の水位以上の掘削は常法による掘削を行ない、地下
水の水位以下の掘削は坑内に水を満たして行なう掘削工
程と、前記掘削後、前記水を満たした状態でトンネルの
底面に基礎敷コンクリート50を打設するコンクリート
打設工程と、前記基礎敷コンクリート50の硬化後、土
留2,2間の水を排出する水排出工程と、水の排出後、
前記基礎敷コンクリート側からトンネル構造体60を築
造し、その完了後横断連続地中壁40を取り壊し、この
取り壊された横断連続地中壁部分にトンネル構造体60
を築造するトンネル構造体築造工程と、を備えたことを
特徴とするトンネル築造工法。
In an open-cut tunnel construction method in which a tunnel is constructed by installing a soil retaining wall consisting of a continuous underground wall on both sides of a tunnel structure body line, a change of the retaining soil between the soil retaining parts is performed.
The continuous underground wall 40 having the counter pressure strength to prevent
Crossing continuous ground installed at appropriate intervals along the length of the channel
After the middle wall installation step and the installation of the transverse continuous underground wall 40,
Excavation above the sewage level is carried out by conventional methods, and
Excavation below the water level is performed by filling the mine with water.
After the excavation, the tunnel is filled with the water.
Concrete to put foundation concrete 50 on the bottom
After the casting step and the hardening of the foundation concrete 50,
A water discharging step for discharging water between the dome 2 and the water, and after discharging the water,
A tunnel structure 60 is constructed from the concrete foundation side.
After the completion, the transversal continuous underground wall 40 was demolished,
A tunnel structure 60 is provided on the demolished section of the continuous underground wall.
And a tunnel structure building process for building a tunnel .
JP2410585A 1990-12-14 1990-12-14 Tunnel construction method Expired - Fee Related JP2745083B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2410585A JP2745083B2 (en) 1990-12-14 1990-12-14 Tunnel construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2410585A JP2745083B2 (en) 1990-12-14 1990-12-14 Tunnel construction method

Publications (2)

Publication Number Publication Date
JPH04289396A JPH04289396A (en) 1992-10-14
JP2745083B2 true JP2745083B2 (en) 1998-04-28

Family

ID=18519729

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2410585A Expired - Fee Related JP2745083B2 (en) 1990-12-14 1990-12-14 Tunnel construction method

Country Status (1)

Country Link
JP (1) JP2745083B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010063695A (en) * 1999-12-24 2001-07-09 이관희 Method For Deviding And Constructing Underground Tunnel Having Large Cross-section

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5142328A (en) * 1974-10-07 1976-04-09 Japan Dev & Construction Chikatetsudoto niokeru kaishokoho
JPH01121414A (en) * 1987-11-06 1989-05-15 Toa Harbor Works Co Ltd Excavation work of ground

Also Published As

Publication number Publication date
JPH04289396A (en) 1992-10-14

Similar Documents

Publication Publication Date Title
KR20130081971A (en) Precast concrete wall and method for constructing underground permanent wall using the precast concrete wall
US3250075A (en) Method of retaining wall construction and anchoring
US4496268A (en) Method and apparatus for constructing reinforced concrete walls in the earth
JP2002146811A (en) Construction method for underwater structure foundation
JP2002115260A (en) Extension method for basement
JP2003193495A (en) Underground structure constructing method
KR20030065963A (en) A method of constrution method for tunnel of structure pipe
CN113882431B (en) Construction method for dismantling cofferdam at end head
JP2745083B2 (en) Tunnel construction method
JP3125171B2 (en) How to build underground structures
WO2009139510A1 (en) Construction method for continuous cut-off wall using overlap casing
KR200296444Y1 (en) Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method
JPH0415878B2 (en)
KR100654973B1 (en) Earth Retaining Wall Structure Using Precast Concrete Pile and Construction Method Thereof
KR970007379B1 (en) Method and apparatus for open shield
KR200224758Y1 (en) Structure of caisson soil protection four concret caisson
KR102610909B1 (en) Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking
JP3728659B2 (en) Basement extension method
KR100367516B1 (en) Stabilization method for a construction floating by floatage
JP3794097B2 (en) Construction method for underground structures
JP2005307688A (en) Construction method for earth retaining wall for newly built underground skeleton and construction method for newly built skeleton by use of its method
JP3113982B2 (en) Tunnel construction method on soft ground
JPH11166242A (en) Underground space constructing method and supporting structure in underground space construction
JPH09279609A (en) Building method of precast reinforced concrete-made underground structure
KR100543284B1 (en) The method of constructing support wall to use as pillar and slab

Legal Events

Date Code Title Description
S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees