JPH07150767A - Beam truss erecting method in building having overhead traveling crane - Google Patents

Beam truss erecting method in building having overhead traveling crane

Info

Publication number
JPH07150767A
JPH07150767A JP31632893A JP31632893A JPH07150767A JP H07150767 A JPH07150767 A JP H07150767A JP 31632893 A JP31632893 A JP 31632893A JP 31632893 A JP31632893 A JP 31632893A JP H07150767 A JPH07150767 A JP H07150767A
Authority
JP
Japan
Prior art keywords
building
erection
truss
overhead traveling
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP31632893A
Other languages
Japanese (ja)
Other versions
JP3049300B2 (en
Inventor
Kunihiko Horie
邦彦 堀江
Hitoshi Namikawa
仁志 南川
Naoki Shimizu
直樹 清水
Daisuke Fukamachi
大介 深町
Yukihiro Matsuba
征洋 松葉
Norio Hasegawa
則夫 長谷川
Akira Saka
明 阪
Kazuhide Yamauchi
一秀 山内
Fumihiro Ishikawa
文洋 石川
Noboru Nishigaki
登 西垣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MIYAJI KENSETSU KOGYO KK
TOUDEN SEKKEI KK
Takenaka Komuten Co Ltd
Tokyo Electric Power Company Holdings Inc
Original Assignee
MIYAJI KENSETSU KOGYO KK
TOUDEN SEKKEI KK
Tokyo Electric Power Co Inc
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MIYAJI KENSETSU KOGYO KK, TOUDEN SEKKEI KK, Tokyo Electric Power Co Inc, Takenaka Komuten Co Ltd filed Critical MIYAJI KENSETSU KOGYO KK
Priority to JP5316328A priority Critical patent/JP3049300B2/en
Publication of JPH07150767A publication Critical patent/JPH07150767A/en
Application granted granted Critical
Publication of JP3049300B2 publication Critical patent/JP3049300B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To shorten the construction period and reduce the cost in the beam truss erection of a building having an overhead traveling crane. CONSTITUTION:A traveling stage 6 serving as a steel frame erecting rack, a post-work scaffold after the steel frame erection, a protective rack allowing the vertical work, and a lifting facility foundation for the lower section work is temporarily installed on a crane girder 3 installed on precedingly erected pillar wall steel frames 1, 1' of a building having an overhead traveling crane. Various work such as the connection matching of beam trusses 7 in package erection or split erection is performed in sequence while the temporary traveling stage 6 is moved. The temporary facility is simplified, the vertical work can be performed, thus the construction period is sharply shortened, and the cost can be reduced.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、天井走行クレーンを有
する建屋に於ける梁トラス建方方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a beam truss in a building having an overhead traveling crane.

【0002】[0002]

【従来の技術】例えば発電所におけるタービン建屋の如
く天井走行クレーンを有する建屋の鉄骨構造体の梁トラ
スの建方は、従来、先行建方の柱、壁鉄骨に対して比較
的小規模で揚重が容易な場合や規模が大きくても大型の
揚重クレーンでの持ち込みが可能である場合には、一括
で全スパン分建方に由り、又は規模の大きさにクレーン
の揚重能力を対応させ得ない事情がある場合には仮受ベ
ント構台で仮受けする分割建方に由るとするのが常識で
ある。
2. Description of the Related Art The construction of a beam truss of a steel structure in a building having an overhead traveling crane, such as a turbine building in a power plant, has conventionally been carried out on a relatively small scale with respect to the columns and walls of the preceding construction. If the weight is easy or if it is possible to bring in a large lifting crane even if the scale is large, the lifting capacity of the crane can be increased depending on the erection for the entire span or the size. If there are circumstances that cannot be dealt with, it is common sense to rely on the split erection to temporarily receive at the temporary reception vent gantry.

【0003】さらに、梁トラス建方後の建屋の天井仕上
げ等の後作業は下部から総足場を架設するか吊足場を全
域に架設して行なうのが常識となっている。
Further, it is common sense to perform post-work such as ceiling finishing of the building after erection of beam trusses by constructing a total scaffold from the bottom or suspending scaffolds over the entire area.

【0004】[0004]

【発明が解決しようとする課題】しかるに、一括建方、
ベント架設のいずれにあっても安全上建方中の梁トラス
の直下の同時作業は許容され得ない。よって、工期的に
歩掛は低下せざるを得ず工期の長期化が避け得ないとい
う問題点がある。一方、その後の仕上げ等の後作業にお
いては、下部からの足場、吊足場のいずれにおいても全
域に架けざるを得ず、仮設材のコストアップは避けられ
ない。さらに、前者の場合は、下部での同時作業が許容
されない不便があり、後者の場合は、吊り材のチェーン
等の仮設材を用いるための仕上げ未了部の発生すること
に由る別の手段で作業しなければないない欠点があっ
て、工期の長期化と新たな仮設コストのアップが避けら
れないという問題点がある。
[Problems to be Solved by the Invention]
For safety reasons, simultaneous work directly below the beam truss during erection cannot be allowed in any of the vent installations. Therefore, there is a problem in that the production cycle is unavoidably reduced and the construction period cannot be extended. On the other hand, in post-processing such as finishing after that, it is inevitable that the scaffold from the bottom and the suspension scaffold are laid all over the area, and the cost of the temporary material is inevitable. Further, in the case of the former, there is an inconvenience that simultaneous work in the lower part is not allowed, and in the case of the latter, another means due to the occurrence of an unfinished portion for using a temporary material such as a chain of hanging materials. However, there is a problem that it is necessary to work in, and there is a problem that the construction period is prolonged and new temporary construction costs are inevitable.

【0005】本発明は、従来の技術の有するこのような
問題点に鑑みてなされたものであり、梁トラス建方中に
あっても直下の作業が可能で、かつ、下部からの足場や
吊足場を大巾に削減してそれ以後の仕上げ等の後作業も
遂行し得て、著しく工期の短縮化、コスト低減化が可能
な天井走行クレーンを有する建屋に於ける梁トラス建方
方法を提供することを目的としている。
The present invention has been made in view of the above-mentioned problems of the prior art. It is possible to work directly under the beam truss, even when the beam truss is being built, and to scaffold or suspend from the bottom. Providing a beam truss erection method in a building with an overhead traveling crane that can significantly reduce the scaffolding and perform post-work such as finishing after that, which can significantly shorten the construction period and cost. The purpose is to do.

【0006】[0006]

【課題を解決するための手段】上記目的を達成するため
に、本発明における天井走行クレーンを有する建屋に於
ける梁トラス建方方法は、天井走行クレーンを有する建
屋に於ける先行建方の柱壁鉄骨に設置されたクレーンガ
ーダーに、鉄骨建方構台,鉄骨建方以後の後作業用足
場,上下作業を可能とする防護構台,下部工事の為の揚
重設備基盤等の役を果たすトラベリングステージを仮設
し、しかる後、この仮設のトラベリングステージを移動
させながら一括若しくは分割建方の梁トラスの仕口合せ
等の前記の諸作業を順次とり行なうとしたものである。
In order to achieve the above object, a beam truss erection method in a building having an overhead traveling crane according to the present invention is a pillar of a preceding erection in a building having an overhead traveling crane. The crane girder installed on the wall steel frame, steel frame erection platform, scaffolding for post-work after steel frame erection, protective pedestal that enables vertical work, traveling stage that serves as a lifting equipment base for substructure work, etc. Then, while temporarily moving the temporary traveling stage, the above-mentioned various operations such as the jointing of the beam trusses of the collective or divided construction are sequentially performed.

【0007】[0007]

【作用】先行建方の壁鉄骨に設置されたクレーンガーダ
ーに仮設されたトラベリングステージは、移動式の鉄骨
建方構台,鉄骨建方以後の後作業用足場,上下作業を可
能とする防護構台,下部工事の為の揚重設備基盤を提供
することとなるので、建方中の梁トラスの直下での作業
が許容され、上下同時作業が可能となると共にステージ
上に簡易足場を組むことに由って梁トラス建方以後の仕
上げ等の後作業が下部からの足場、吊足場を要すること
なく遂行し得ることとなる。この結果、著しい工期の短
縮化、コスト低減化が期し得ることとなる。
[Operation] The traveling stage temporarily installed on the crane girder installed on the wall steel frame of the preceding erection is the movable steel framing gantry, the scaffolding for post-work after the steel erection, the protective gantry that enables up and down work, Since it will provide a lifting equipment base for substructure work, work directly under the beam truss being built is allowed, simultaneous vertical work is possible, and a simple scaffold is built on the stage. Therefore, post-work such as finishing after erection of beam truss can be performed without the need for scaffolding or suspension scaffolding from below. As a result, it is possible to significantly reduce the construction period and cost.

【0008】[0008]

【実施例】実施例について図面を参照して説明すると、
図1〜図18において柱壁鉄骨1,1′はクローラーク
レーン2,2′等を用いて先行建方され、クレーンガー
ダー3,…が設置される。当該クレーンガーダー3には
走行台車4,…を有する仮設のトラベリングステージ6
が架設される。この仮設のステージ6は例えば主桁17
にステージ架構18を接続させ、上面に全面足場5を敷
設することで構成されている。尚、主桁17を本設の走
行クレーンで代用させて有効利用を図るとしても良い。
ステージ6走行用としてクレーンガーター3上に確保さ
れねばならないレールは、仮設であっても良く、本設の
走行クレーン用に設けられるものを利用しても良い。
EXAMPLES Examples will be described with reference to the drawings.
1 to 18, the column wall steel frames 1 and 1'are erected in advance using crawler cranes 2 and 2'and the crane girders 3 are installed. The crane girder 3 has a temporary traveling stage 6 having traveling carriages 4, ...
Is erected. This temporary stage 6 is, for example, a main girder 17
Is connected to the stage frame 18, and the entire surface of the scaffold 5 is laid on the upper surface. Incidentally, the main girder 17 may be replaced by a traveling crane which is permanently installed to effectively utilize the crane.
The rail that must be secured on the crane garter 3 for traveling the stage 6 may be a temporary rail or may be a rail provided for a main traveling crane.

【0009】このようなクレーンガーダー3上に仮設さ
れた当該トラベリングステージ6は、後行建方の梁トラ
ス7についての鉄骨建方構台,鉄骨建方以後の後作業用
足場、さらには、上下作業を可能とする防護構台、下部
工事の為の揚重設備基盤となり得る。梁トラス7は一括
建方であっても分割建方のいずれでも良く、図1,図3
にあっては分割建方の側でもって示しており、クローラ
ークレーン8若しくは9が3分割のトラス部材7a,7
b,7cを吊り込んでいる。
The traveling stage 6 temporarily installed on the crane girder 3 has a steel frame erection structure for the beam truss 7 of the trailing construction, a scaffolding for post-working after the steel framing, and further vertical work. It can be used as a protective gantry that can be used as a base and as a lifting equipment base for substructure work. The beam truss 7 may be a collective erection or a divided erection.
, The crawler crane 8 or 9 is divided into three truss members 7a and 7a.
Suspending b and 7c.

【0010】ステージ6上で梁トラス7の鉄骨建方,仕
口合せ等がなされている間、ステージ6直下は防護され
ているので、図1,図2に示される如くオペレーション
フロアを提供する2〜3階鉄骨10の建方も同時進行で
施工できる。図9〜図17はこの工程を詳細に示す。す
なわち、ステージ6上に持ち込まれたトラス梁セット
7′をジャッキ上に受止し、結合本締を行なう。図中1
1はセット7′の転倒防止用建入治具である(図9)。
While the beam truss 7 is being erected on the stage 6 while the steel frame is being erected, the joints, etc. are being provided, the area directly below the stage 6 is protected, so that an operation floor is provided as shown in FIGS. ~ The construction of the 3rd floor steel frame 10 can also be done simultaneously. 9 to 17 show this process in detail. That is, the truss beam set 7 ′ brought onto the stage 6 is received on the jack, and the main fastening is performed. 1 in the figure
Reference numeral 1 is a fall-prevention installation jig for the set 7 '(FIG. 9).

【0011】トラス梁セット7′についてのムクリ調整
のためのジャッキダウンを行なう(図10)。先行建方
の梁トラス7との間のつなぎ部12の接続を行なった
後、該先行建方の梁トラス7の仕口合せを完了する(図
11)。仕口合せを完了した梁トラス7については図示
省略の簡易足場をステージ6上に組んで塗装仕上その他
の仕上工事を施こすと共にステージ6の下では2〜3階
鉄骨10の建方を行なう(図12)。
Jack down for adjusting the truss beam set 7'is performed (FIG. 10). After connecting the connecting portion 12 to the beam truss 7 of the preceding erection, the assembling of the beam truss 7 of the preceding erection is completed (FIG. 11). For the beam truss 7 which has completed the finishing, a simple scaffold (not shown) is assembled on the stage 6 to perform painting and other finishing work, and under the stage 6, the second to third floor steel frames 10 are erected ( (Fig. 12).

【0012】ステージ6をトラベリングして上記の建方
をした鉄骨10を防護しておいて建入調整を行なう(図
13)。ステージ6上で既述の図9の工程をとり行なう
と共に該鉄骨10についての本締めを行なう(図1
4)。ステージ6上で既述の図10の工程を行なう(図
15)。
[0012] The stage 6 is traveled to protect the steel frame 10 constructed as described above, and the installation adjustment is performed (Fig. 13). The steps shown in FIG. 9 are performed on the stage 6 and the steel frame 10 is finally tightened (see FIG. 1).
4). The above-described process of FIG. 10 is performed on the stage 6 (FIG. 15).

【0013】ステージ6上で既述の図11の工程を行な
う(図16)。叙上の要領を繰り返したら、安定した架
構部のコンクリート打設13を順次とり行なっていく
(図17)。叙上の下部作業は追随する揚重設備を伴な
うことに由って一層やり易すいが、図18はステージ6
を揚重設備基盤に利用した例を示す。すなわち、ステー
ジ6上に軌条14を敷設し、小型クレーン15を走行さ
せる。若しくは、ステージ6下面にX,Y方向移動可能
な天井吊りホイストクレーン16を組み付ける。
The above-described process of FIG. 11 is performed on the stage 6 (FIG. 16). After repeating the above procedure, the concrete placing 13 of the stable frame is sequentially performed (Fig. 17). The lower part of the work is easier to carry out due to the accompanying lifting equipment.
The following shows an example of using the above as a lifting equipment base. That is, the rail 14 is laid on the stage 6 and the small crane 15 is run. Alternatively, the ceiling hoist crane 16 that is movable in the X and Y directions is attached to the lower surface of the stage 6.

【0014】尚、ステージ6は建屋の一方端から他方端
に向けて走行させても、中央から相反する方向に2台走
行させても良く、建屋の事情に応じて配慮すれば良い。
また、当然ながら終端に至って解体回収される。既述の
図9〜図11の梁トラス7建方の際、トラベリングステ
ージを本設の天井走行クレーンを利用した場合の本発明
にあっては、以下詳述の利点がある。
The stage 6 may be run from one end to the other end of the building, or two stages may be run in opposite directions from the center, depending on the circumstances of the building.
Also, of course, it is disassembled and collected at the end. In the case of constructing the beam truss 7 of FIGS. 9 to 11 described above, the present invention in the case of using the overhead traveling crane having the traveling stage as the main installation has the following detailed advantages.

【0015】すなわち、図19〜図28に示す如く、梁
トラス分割建方にあっては、仮設のステージ6にトラス
部材受上用のジャッキ19が配置され(図19)、分割
のトラス部材7a,7c,7bが持ち込みされて所定の
ムクリ度合のもとに接合される(図20,図21,図2
2)。しかる後、ジャッキ中19による支持力は開放さ
れ(図23)て、トラス梁セット7′のムクリ度合が所
定通りであるか否かが確認される。
That is, as shown in FIGS. 19 to 28, in the beam truss division erection, the jack 19 for receiving the truss members is arranged on the temporary stage 6 (FIG. 19) to divide the truss members 7a. , 7c, 7b are brought in and joined under a predetermined degree of muffle (FIGS. 20, 21, and 2).
2). After that, the supporting force by the jack 19 is released (FIG. 23), and it is confirmed whether the truss beam set 7'has a predetermined degree of makuri.

【0016】ジャッキ19はレベルダウンをして支持力
開放にてレベルを降下させたトラス梁セット7′を新め
て支持し直し(図24)、この状態のもとにて既述の図
11に示すつなぎ部12の接続がとり行なわれるもので
あるが、これ等一連の工程は、図25〜図27に示され
る如く、指定のムクリでもって仰姿勢にしている先行建
方の梁トラス7の先端レベルよりもつなぎ部接続後の降
下代を見込んでムクリ度合を高いレベルに設定のトラス
梁セット7′との間には、当然のことながらレベル差が
あるため、つなぎ部12のブレース20,20′は長短
異寸法となる(図25(a),(b))。このレベルで
支持のもとつなぎ部12の接続がなされ、支持力が開放
されると、つなぎ部12接続による負荷により、先端は
少し降下する(図26)。
In the jack 19, the truss beam set 7 ′ whose level has been lowered to lower the level by releasing the supporting force is newly supported again (FIG. 24), and under this state, the above-mentioned FIG. The connecting portion 12 shown in Fig. 25 is connected, and the series of steps are as shown in Figs. 25 to 27. Since there is a level difference with the truss beam set 7'which has a high degree of makuri in consideration of the descent amount after connecting the connecting part from the tip level, the brace 20 of the connecting part 12 , 20 'have different lengths and short dimensions (FIGS. 25 (a) and 25 (b)). At this level, when the connecting portion 12 of the support is connected and the supporting force is released, the tip is slightly lowered due to the load due to the connecting portion 12 connection (FIG. 26).

【0017】さらに、この先きに接続がなされることに
よる新たな負荷で、ダウンするうえに、既述の図17の
コンクリート打設13でもってレベルはダウンする(図
27)。これ等の段階的レベルダウンを計算してムクリ
は算出決定されている。しかるに、終局的には同一寸法
にて落着かねばならないブレース20、20′に課せら
れる締結点誤差吸収能力は、上述の如くレベル差を有し
たままで接合をしなければならないもとでは、ルーズホ
ールでの吸収でしか対応し得ないが、これではその都度
再締結の必要が生じて工程増加の不利がある。
Further, a new load due to the connection made earlier leads to the down, and the concrete pouring 13 shown in FIG. 17 also lowers the level (FIG. 27). The mukuri is calculated and determined by calculating these gradual level-downs. However, the fastening point error absorbing ability imposed on the braces 20 and 20 'which must be settled down with the same size finally becomes loose when the joining is performed with the level difference as described above. Although it can be dealt with only by absorption in the hall, this requires re-fastening each time, which has the disadvantage of increasing the number of processes.

【0018】ところが持ち込みされるトラス梁セット
7′直下に位置する本発明の主桁17若しくは本設の走
行クレーン大重量であることを利用して叙上の不利を解
消することが可能である。すなわち、図28に示す如
く、トラス梁セット7′をつなぎ部12と接続するに際
し、大重量のためワイヤー21又はジャッキ22等の締
結材取付基盤たり得る主桁17若しくは走行クレーンよ
り締結材の持ち出しをして強制的にたわませて、既建込
みの梁トラス7の先端レベルに合わせ、かかる状態のも
とでつなぎ部12の接続を行なう。こうすると、同レベ
ルのためにブレース20,20′は同寸法にて締結され
ることとなり、締結のし直しも不必要化して工程上,品
質上でも好ましい。
However, it is possible to eliminate the above disadvantages by utilizing the fact that the main girder 17 of the present invention located directly below the truss beam set 7'to be brought in or the heavy weight of the traveling crane of the present invention is used. That is, as shown in FIG. 28, when connecting the truss beam set 7 ′ to the connecting portion 12, the fastening material is taken out from the main girder 17 or the traveling crane which can be a fastening material mounting base such as the wire 21 or the jack 22 due to its large weight. Then, it is forcibly bent to match the tip level of the beam truss 7 already built, and the joint portion 12 is connected under such a state. In this case, the braces 20 and 20 'are fastened with the same size because of the same level, and refastening is not necessary, which is preferable in terms of process and quality.

【0019】[0019]

【発明の効果】本発明は、以上説明したように構成され
ているので、以下に記載されるような効果を奏する。地
面から立ち上げの足場若しくはベント設置が不可欠の従
来技術にあっては、絶対に上下同時作業は不可能であっ
たが、本発明にあっては可能であり、工期短縮、コスト
低減化の効果は著しい。
Since the present invention is constructed as described above, it has the following effects. In the prior art in which a scaffolding to be launched from the ground or a vent installation is indispensable, it is absolutely impossible to work up and down at the same time. Is remarkable.

【0020】また、特に組立,撤去の煩わしい仮設材を
有する仮受ベント工法,地面からの立上げ足場、吊足場
工法に比しては、 (1)ベント若しくは足場設置場所を平坦にする必要が
あり、障害物等がある場合は複雑な部材構成となり手間
が掛かる。 (2)ベント若しくは足場組立解体作業は高所作業で危
険性が高く作業性は低下し、工程増となる。 (3)ベント解体時は、既に上載構造物があるため非常
に危険を伴う作業となる。 (4)風並びに地震等による水平力に対して転倒しやす
い構造であるため、ワイヤーロープにより転倒防止対策
を講ずる必要がある。 (5)鉄骨建方を行う際、足場設備を完全に行う事がで
きず不安定作業が多くなる。特にベントとベント間の二
次部材取付け時は作業性が悪く安全性がかなり低下す
る。 等の難点が全く無く、有利である。
Further, compared with the temporary receiving vent construction method having a temporary material which is cumbersome to assemble and remove, the scaffold for starting up from the ground, and the suspension scaffold construction method, (1) it is necessary to make the vent or scaffold installation place flat. However, if there are obstacles, etc., it will take complicated work because of the complicated member structure. (2) Venting or scaffolding assembly dismantling work is a work at a high place and is highly dangerous, resulting in a decrease in workability and an increase in processes. (3) When dismantling the vent, there is already an overlying structure, so it is extremely dangerous work. (4) Since the structure makes it easy to fall against horizontal forces such as wind and earthquakes, it is necessary to take measures to prevent falls with wire rope. (5) When constructing a steel frame, the scaffolding equipment cannot be completely implemented, and unstable work increases. Especially when the secondary member is installed between the vents, the workability is poor and the safety is considerably reduced. It is advantageous because there are no difficulties such as.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明工法による建屋の正面図である。FIG. 1 is a front view of a building manufactured by the method of the present invention.

【図2】本発明工法になる建屋の側面図である。FIG. 2 is a side view of a building according to the method of the present invention.

【図3】本発明工法になる建屋の平面図である。FIG. 3 is a plan view of a building according to the method of the present invention.

【図4】本発明工法に於けるトラベリングステージの平
面図である。
FIG. 4 is a plan view of a traveling stage in the method of the present invention.

【図5】図4中A−A矢視図である。5 is a view on arrow AA in FIG. 4. FIG.

【図6】図4中B−B矢視図である。6 is a view taken along the line BB in FIG.

【図7】図4中C−C矢視図である。FIG. 7 is a view on arrow CC in FIG.

【図8】図4中D−D矢視図である。FIG. 8 is a view taken in the direction of arrows D-D in FIG. 4.

【図9】本発明工法の工程図である。FIG. 9 is a process drawing of the method of the present invention.

【図10】本発明工法の工程図である。FIG. 10 is a process drawing of the method of the present invention.

【図11】本発明工法の工程図である。FIG. 11 is a process drawing of the method of the present invention.

【図12】本発明工法の工程図である。FIG. 12 is a process drawing of the method of the present invention.

【図13】本発明工法の工程図である。FIG. 13 is a process drawing of the method of the present invention.

【図14】本発明工法の工程図である。FIG. 14 is a process drawing of the method of the present invention.

【図15】本発明工法の工程図である。FIG. 15 is a process drawing of the method of the present invention.

【図16】本発明工法の工程図である。FIG. 16 is a process drawing of the method of the present invention.

【図17】本発明工法の工程図である。FIG. 17 is a process drawing of the method of the present invention.

【図18】トラベリングステージを揚重設備基盤とした
説明図である。
FIG. 18 is an explanatory diagram in which the traveling stage is based on a lifting equipment.

【図19】本発明のトラス梁セット建込工程図である。FIG. 19 is a process drawing of the truss beam set installation process of the present invention.

【図20】本発明のトラス梁セット建込工程図である。FIG. 20 is a process drawing of the truss beam set installation process of the present invention.

【図21】本発明のトラス梁セット建込工程図である。FIG. 21 is a process drawing of the truss beam set installation process of the present invention.

【図22】本発明のトラス梁セット建込工程図である。FIG. 22 is a process diagram for installing the truss beam set of the present invention.

【図23】本発明のトラス梁セット建込工程図である。FIG. 23 is a process diagram for installing the truss beam set of the present invention.

【図24】本発明のトラス梁セット建込工程図である。FIG. 24 is a process diagram for installing the truss beam set of the present invention.

【図25】(a)は従来のトラス梁セットのムクリ説明
図,(b)はつなぎ部のブレース寸法説明図である。
FIG. 25 (a) is an explanatory view of a conventional truss beam set, and FIG. 25 (b) is an explanatory view of a brace size of a connecting portion.

【図26】従来のトラス梁セットのムクリ説明図であ
る。
FIG. 26 is an explanatory view of a conventional truss beam set.

【図27】従来のトラス梁セットのムクリ説明図であ
る。
FIG. 27 is an explanatory diagram of a conventional truss beam set.

【図28】本発明のつなぎ部接続仕様説明図である。FIG. 28 is an explanatory view of a joint connection specification of the present invention.

【符号の説明】[Explanation of symbols]

1,1′ 柱壁鉄骨 2,2′ クローラークレーン 3 クレーンガーダー 4 走行台車 5 全面足場板 6 トラベリングステージ 7 梁トラス 7a,7b,7c トラス部材 8,9 クローラークレーン 10 鉄骨 11 転倒防止用建入治具 12 つなぎ部 13 コンクリート打設 14 軌条 15 小型クレーン 16 天井吊りホイストクレーン 17 主桁 18 ステージ架構 19 ジャッキ 20,20′ ブレース 21 ワイヤー 22 ジャッキ 1,1 'Column wall steel 2,2' Crawler crane 3 Crane girder 4 Traveling trolley 5 Full scaffolding plate 6 Traveling stage 7 Beam truss 7a, 7b, 7c Truss member 8,9 Crawler crane 10 Steel frame 11 Fall prevention construction Tool 12 Connecting part 13 Concrete pouring 14 Rail 15 Small crane 16 Ceiling hoist crane 17 Main girder 18 Stage frame 19 Jack 20, 20 'Brace 21 Wire 22 Jack

───────────────────────────────────────────────────── フロントページの続き (72)発明者 堀江 邦彦 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内 (72)発明者 南川 仁志 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内 (72)発明者 清水 直樹 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内 (72)発明者 深町 大介 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内 (72)発明者 松葉 征洋 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内 (72)発明者 長谷川 則夫 神奈川県横浜市鶴見区大黒町11番1号 東 京電力株式会社横浜火力建設所内 (72)発明者 阪 明 東京都千代田区内幸町1丁目1番3号 東 京電力株式会社内 (72)発明者 山内 一秀 東京都千代田区内幸町2丁目1番4号 東 電設計株式会社内 (72)発明者 石川 文洋 東京都千代田区内幸町2丁目1番4号 東 電設計株式会社内 (72)発明者 西垣 登 東京都豊島区北大塚一丁目13番15号 宮地 建設工業株式会社内 ─────────────────────────────────────────────────── ─── Continued Front Page (72) Inventor Kunihiko Horie 8-21-1, Ginza Ginza, Chuo-ku, Tokyo Stock company Takenaka Corporation Tokyo Main Store (72) Inventor Hitoshi Minagawa 8-21 Ginza, Chuo-ku, Tokyo No. 1 Takenaka Corporation Tokyo Main Store (72) Inventor Naoki Shimizu 8-21-1, Ginza, Chuo-ku, Tokyo Shareholder Takenaka Corporation Tokyo Main Store (72) Inventor Daisuke Fukamachi Ginza, Chuo-ku, Tokyo 8-21-1-1 Takenaka Corporation Tokyo Main Store (72) Inventor Seiyo Matsuba 8-21-1 Ginza, Chuo-ku, Tokyo Takenaka Corporation Tokyo Head Office (72) Inventor Norio Hasegawa Kanagawa 11-11 Daikokucho, Tsurumi-ku, Yokohama-shi, Tochi Electric Power Co., Inc. Yokohama Thermal Power Plant (72) Inventor Han Akira 1-3-1, Uchisaiwaicho, Chiyoda-ku, Tokyo Tokyo Electric Power Co., Inc. Inside the company (72) Inventor Kazuhide Yamauchi 2-4 Uchisaiwaicho, Chiyoda-ku, Tokyo Toden Design Co., Ltd. (72) Inventor Fumihiro Ishikawa 2-4-4 Uchisaiwaicho, Chiyoda-ku, Tokyo Todendesign Co., Ltd. (72) Inventor Noboru Nishigaki 1-13-15 Kitaotsuka, Toshima-ku, Tokyo Miyaji Construction Industry Co., Ltd.

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 天井走行クレーンを有する建屋に於ける
先行建方の柱壁鉄骨に設置されたクレーンガーダーに、
鉄骨建方構台,鉄骨建方以後の後作業用足場,上下作業
を可能とする防護構台,下部工事の為の揚重設備基盤等
の役を果たすトラベリングステージを仮設し、しかる
後、この仮設のトラベリングステージを移動させながら
一括若しくは分割建方の梁トラス仕口合せ等の前記の諸
作業を順次とり行なうとしたことを特徴とする天井走行
クレーンを有する建屋に於ける梁トラス建方方法。
1. A crane girder installed on a pillar wall steel frame of a preceding building in a building having an overhead traveling crane,
A steel frame erection gantry, post-scaffolding for post-steel erection, a protection gantry that enables vertical work, a traveling stage that serves as a lifting equipment base for lower construction, etc. are temporarily installed. A method for constructing a beam truss in a building having an overhead traveling crane, characterized in that the above-mentioned various operations such as jointing a beam truss for collective or divided construction are sequentially performed while moving a traveling stage.
【請求項2】 トラベリングステージを本設の天井走行
クレーンを利用してこれに連結構成するとした請求項1
記載の天井走行クレーンを有する建屋に於ける梁トラス
建方方法。
2. The traveling stage is constructed so as to be connected to the overhead traveling crane which is permanently installed.
Beam truss erection method in a building having the above described overhead traveling crane.
【請求項3】 主枠若しくは天井走行クレーンに懸け渡
した締結材でトラス梁セットのムクリを強制的に先行建
込みの梁トラス先端レベルにたわませ、かかる状態のも
とでつなぎ部接続を、ブレース同寸法にてとり行なうと
した請求項2記載の天井走行クレーンを有する建屋に於
ける梁トラス建方方法。
3. The truss beam set is forced to bend to the tip level of the pre-installed beam truss with the fastening material hung on the main frame or overhead traveling crane, and the joint connection is made under such a condition. The method for constructing a beam truss in a building having an overhead traveling crane according to claim 2, wherein the braces have the same dimensions.
JP5316328A 1992-12-16 1993-12-16 Construction method of beam truss in building with overhead traveling crane Expired - Lifetime JP3049300B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5316328A JP3049300B2 (en) 1992-12-16 1993-12-16 Construction method of beam truss in building with overhead traveling crane

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP4-354592 1992-12-16
JP35459292 1992-12-16
JP5316328A JP3049300B2 (en) 1992-12-16 1993-12-16 Construction method of beam truss in building with overhead traveling crane

Publications (2)

Publication Number Publication Date
JPH07150767A true JPH07150767A (en) 1995-06-13
JP3049300B2 JP3049300B2 (en) 2000-06-05

Family

ID=26568620

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5316328A Expired - Lifetime JP3049300B2 (en) 1992-12-16 1993-12-16 Construction method of beam truss in building with overhead traveling crane

Country Status (1)

Country Link
JP (1) JP3049300B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102409864A (en) * 2011-11-14 2012-04-11 中建钢构有限公司 Steel truss construction method and temporary reinforcing device used in hoisting process of same
KR101254621B1 (en) * 2012-12-24 2013-04-15 원인복 Construction method of office-factory composite building and structure thereby
CN104866659A (en) * 2015-05-13 2015-08-26 江苏新蓝天钢结构有限公司 Steel structure integral hoisting method based on BIM
CN103774856B (en) * 2014-01-24 2017-05-31 江苏沪武建设集团有限公司 A kind of gliding construction method of different shape heavy type girder steel of large span on Super High roofing
CN107355003A (en) * 2017-06-15 2017-11-17 上海二十冶建设有限公司 The modular construction method of large span ultra-wide is overweight truss
CN110002343A (en) * 2019-04-26 2019-07-12 青岛长永机械工程有限公司 A kind of prefabricated pipe gallery of self-driving type Urban Underground is laid with hoisting machine and construction method

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102409864A (en) * 2011-11-14 2012-04-11 中建钢构有限公司 Steel truss construction method and temporary reinforcing device used in hoisting process of same
KR101254621B1 (en) * 2012-12-24 2013-04-15 원인복 Construction method of office-factory composite building and structure thereby
CN103774856B (en) * 2014-01-24 2017-05-31 江苏沪武建设集团有限公司 A kind of gliding construction method of different shape heavy type girder steel of large span on Super High roofing
CN104866659A (en) * 2015-05-13 2015-08-26 江苏新蓝天钢结构有限公司 Steel structure integral hoisting method based on BIM
CN104866659B (en) * 2015-05-13 2018-09-18 江苏新蓝天钢结构有限公司 Steel construction integral hoisting method based on BIM
CN107355003A (en) * 2017-06-15 2017-11-17 上海二十冶建设有限公司 The modular construction method of large span ultra-wide is overweight truss
CN107355003B (en) * 2017-06-15 2020-04-07 上海二十冶建设有限公司 Modular construction method of large-span ultra-wide overweight truss
CN110002343A (en) * 2019-04-26 2019-07-12 青岛长永机械工程有限公司 A kind of prefabricated pipe gallery of self-driving type Urban Underground is laid with hoisting machine and construction method
CN110002343B (en) * 2019-04-26 2024-05-10 青岛长永机械工程有限公司 Self-driven urban underground prefabricated comprehensive pipe gallery laying hoisting machine and construction method

Also Published As

Publication number Publication date
JP3049300B2 (en) 2000-06-05

Similar Documents

Publication Publication Date Title
AU2010346421B2 (en) Scaffold and methods for installing or removing such a scaffold
EP0480683A1 (en) Erection workbench and construction process
JPH04111829A (en) Method for constructing large-span roof
CN107419907B (en) A kind of steel-making tower steel structure platform is staggered installation of welding method
JPH07150767A (en) Beam truss erecting method in building having overhead traveling crane
JP2745004B2 (en) Steel construction method
CN111704058A (en) Hoisting device
JP2942879B2 (en) Temporary house for all-weather construction
JP2004270377A (en) Column-beam preassembled reinforcement body, and preassembled reinforcement method using the same
JP3100574B2 (en) Suspended scaffold and its erection method
JPH01322064A (en) Scaffold erection method for construction work performing temporary general grounding using scaffolding steel pipe
CN218714838U (en) Self-lifting heavy-load construction platform
JPH11117523A (en) Lifting work platform for elevator parking and method using the same
JP2621748B2 (en) All-weather temporary shed
JP2690822B2 (en) Steel construction method for low-rise buildings
JP2779258B2 (en) Roof lift-up method
JP2876991B2 (en) Steel frame method for high-rise buildings
JPH1179602A (en) Work floor device for installing elevator
JP2004076525A (en) Temporary stage
SU1726703A1 (en) Method of constructing ferroconcrete span structure
CN115506563A (en) Self-lifting heavy-load construction platform and construction method thereof
JPH0437897B2 (en)
JPH04297665A (en) Erection-working base for construction of structure
JPH0468431B2 (en)
JPH11256811A (en) Installation method of chain suspended staircase and staircase scaffold

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R370 Written measure of declining of transfer procedure

Free format text: JAPANESE INTERMEDIATE CODE: R370

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090331

Year of fee payment: 9

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 9

Free format text: PAYMENT UNTIL: 20090331

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 10

Free format text: PAYMENT UNTIL: 20100331

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 10

Free format text: PAYMENT UNTIL: 20100331

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110331

Year of fee payment: 11

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120331

Year of fee payment: 12

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120331

Year of fee payment: 12

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130331

Year of fee payment: 13

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130331

Year of fee payment: 13

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 14

Free format text: PAYMENT UNTIL: 20140331

EXPY Cancellation because of completion of term