CN110002343A CN201910343624.6A CN201910343624A CN110002343A CN 110002343 A CN110002343 A CN 110002343A CN 201910343624 A CN201910343624 A CN 201910343624A CN 110002343 A CN110002343 A CN 110002343A
Authority
CN
China
Prior art keywords
truss
pipe gallery
prefabricated pipe
hoisting machine
self
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910343624.6A
Other languages
Chinese (zh)
Other versions
CN110002343B (en
Inventor
马运德
王兆伟
纪玲君
兰峰云
王永华
吴庆生
古驰
仪润修
马祖勇
李建伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
QINGDAO NO1 MUNICIPAL ENGINEERING Co Ltd
Qingdao Chang Yong Mechanical Engineering Co Ltd
Original Assignee
QINGDAO NO1 MUNICIPAL ENGINEERING Co Ltd
Qingdao Chang Yong Mechanical Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by QINGDAO NO1 MUNICIPAL ENGINEERING Co Ltd, Qingdao Chang Yong Mechanical Engineering Co Ltd filed Critical QINGDAO NO1 MUNICIPAL ENGINEERING Co Ltd
Priority to CN201910343624.6A priority Critical patent/CN110002343B/en
Publication of CN110002343A publication Critical patent/CN110002343A/en
Application granted granted Critical
Publication of CN110002343B publication Critical patent/CN110002343B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B66C13/08Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C17/00Overhead travelling cranes comprising one or more substantially horizontal girders the ends of which are directly supported by wheels or rollers running on tracks carried by spaced supports
    • B66C17/04Overhead travelling cranes comprising one or more substantially horizontal girders the ends of which are directly supported by wheels or rollers running on tracks carried by spaced supports with lifting beams, e.g. slewable beams, carrying load-engaging elements, e.g. magnets, hooks
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C9/00Travelling gear incorporated in or fitted to trolleys or cranes
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C9/00Travelling gear incorporated in or fitted to trolleys or cranes
    • B66C9/14Trolley or crane travel drives
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Environmental & Geological Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of prefabricated pipe galleries of self-driving type Urban Underground to be laid with hoisting machine and construction method, the hoisting machine includes truss and the driving mechanism that is installed on truss, truss front end is equipped with leading device, passes through removable pin axis connection between leading device and truss;The column bottom in four corners of truss is vertically arranged hydraulic cylinder, the support correction crossbeam that the setting of truss bottom can be packed up or be transferred;Crane trolley is equipped at the top of the truss, hoist engine is set in the middle part of the crane trolley, the hoist engine is connect by wirerope with the pulley blocks for being installed on crane trolley both ends and the pulley blocks for being installed on truss both ends, hanging beam is transversely and horizontally set at the top of the crane trolley, tensioner adjustment screw is installed on the hanging beam, tensioner adjustment screw bottom connects the hoist cable for lifting by crane prefabricated pipe gallery, hoisting machine disclosed in this invention and construction method can reduce construction cost, working efficiency is improved, security risk in construction is reduced, guarantees construction quality.

Description

A kind of prefabricated pipe gallery of self-driving type Urban Underground is laid with hoisting machine and construction method
Technical field
The present invention relates to a kind of prefabricated pipe gallery installation apparatus of Urban Underground, in particular to a kind of self-driving type Urban Underground Prefabricated pipe gallery is laid with hoisting machine and construction method.
Background technique
Currently, many cities in China, which have started to promote, builds underground pipe gallery, provides and more high-quality more pacify for urban construction Full service.Since the technology in China starts to walk evening, all kinds of problems is remained in the construction of underground pipe gallery, wherein most Common is to move horizontally piping lane, and piping lane scale of construction when due to construction is big, can be by crane by piping lane under open cut state Tunnel is hung in, but to be docked with leading portion piping lane and also need to move horizontally piping lane to achieve the purpose that contact with leading portion piping lane.
Existing technology is to guarantee piping lane position by crane and artificial construction by the way of manually adjusting, this Mode mounting process is cumbersome, and construction part span is big, if in place by piping lane movement, both taking time and effort, operating cost is high, and can not It is accurate to guarantee piping lane position, at the same crane when lifting is with adjustment position there is also security risk, piping lane is easy to touch between each other Hit influence construction quality.
Summary of the invention
In order to solve the above technical problems, the present invention provides a kind of prefabricated pipe galleries of self-driving type Urban Underground to be laid with lifting Machine and construction method realize independent ambulation to reach from tape drive mechanism, reduce construction cost, improve working efficiency, and reduction is applied Security risk, the purpose of guarantee construction quality in work.
In order to achieve the above objectives, technical scheme is as follows:
A kind of prefabricated pipe gallery laying hoisting machine of self-driving type Urban Underground, including truss and the driving being installed on truss Mechanism, the truss front end are equipped with leading device, pass through removable pin axis connection between the leading device and truss;The purlin The column bottom in four corners of frame is vertically arranged hydraulic cylinder, and the support correction that the truss bottom setting can be packed up or be transferred is horizontal Beam;Be equipped with crane trolley at the top of the truss, hoist engine be set in the middle part of the crane trolley, the hoist engine by wirerope with It is installed on the pulley blocks at crane trolley both ends and is installed on the pulley blocks connection at truss both ends, at the top of the crane trolley laterally It is horizontally disposed with hanging beam, tensioner adjustment screw is installed on the hanging beam, the connection of tensioner adjustment screw bottom is pre- for lifting by crane The hoist cable of pipe gallery processed.
In above scheme, the driving mechanism includes being set to the cycloidal planetary gear speed reducer of truss end and by cycloidal-pin wheel The driving wheel and driven wheel for being set to truss two sides that speed reducer drives pass through drive shaft one between the driving wheel of truss two sides It connects, is connected between the driven wheel of truss two sides by drive shaft two, pass through sprocket wheel between the drive shaft one and drive shaft two Connection, cycloidal planetary gear speed reducer are connect by sprocket wheel with drive shaft one, and the driving wheel and driven wheel are pair arranged side by side Wheel.
In above scheme, the leading device includes front guide bracket and the leading skate for being set to front guide bracket bottom, before described Strut is connected between at the top of saddle front end and truss, it is described leading by removable pin axis connection between the strut and truss It is articulated and connected between frame end and truss bottom.
In above scheme, the hanging beam is arranged two groups, is located at the rear and front end of crane trolley, and every group of hanging beam includes two Root, the hanging beam both ends open up strip groove, and the tensioner adjustment screw is set in the strip groove, the tensioner adjustment Adjustment handle is installed above screw rod.
In above scheme, setting two before and after support correction crossbeam, the support correction cross rail top slot and Along the longitudinally disposed round steel of crossbeam, it is wound with lifting rope on the round steel and is connect with truss bottom fixed beam, support correction crossbeam bottom Pull ring is respectively set in portion two sides, and the pull ring is connect by drawstring with the pulley and drawstring spool being mounted on truss, the cunning Wheel and drawstring spool are located at the two sides of support correction crossbeam, and hand crank, the truss bottom is arranged on the drawstring spool It also sets up for the fixed drag hook for supporting correction crossbeam.
A kind of prefabricated pipe gallery of self-driving type Urban Underground is laid with the construction method of hoisting machine, includes the following steps:
(1) prefabricated pipe gallery is successively hung in the tunnel dug using existing loop wheel machine, and has spliced 2-3 of front end Prefabricated pipe gallery, the steel strand wires hydraulic expanding then carried out between prefabricated pipe gallery are drawn, and realize nothing between prefabricated pipe gallery Seam docking;
(2) leading device is put down, is opened truss to mounted prefabricated pipe gallery using driving mechanism, so that Truss front end is fallen at the top of prefabricated pipe gallery to be assembled, and a prefabricated integrated pipe to be assembled is at least reserved in truss bottom Corridor;
(3) crane trolley position is adjusted by hoist engine, by sling hook at the top of the prefabricated pipe gallery of truss bottom On suspension hook, start hydraulic cylinder, entire truss is jacked up, is detached from ground so that prefabricated pipe gallery be sling;
(4) at this point, decentralization support correction crossbeam, falls within the weight of truss on support correction crossbeam, adjust crane trolley Position, splice itself and mounted prefabricated pipe gallery, transfer prefabricated pipe gallery, then take off hoist cable and suspension hook From, and the drawing of the steel strand wires hydraulic expanding between prefabricated pipe gallery is carried out, realize seamless interfacing;
(5) after lifting the prefabricated pipe gallery below end joist, support correction crossbeam is packed up, hydraulic cylinder is fallen after rise, is utilized Driving mechanism driving truss and leading device move forward, pre- below truss hoisting after the same method behind in-position Itself and the prefabricated pipe gallery seamless interfacing being installed after being all installed, are lifted leading dress by pipe gallery processed It sets, withdraws from truss.
In above scheme, when truss and prefabricated pipe gallery placement angle are there are when gap, spiral shell is adjusted by adjusting tensioner Position of the bar on hanging beam adjusts the position of hoist cable.
In above scheme, after hoist cable hooks prefabricated pipe gallery, hoist cable is tensed by adjusting tensioner adjustment screw, prevented Only hoist cable is detached from prefabricated pipe gallery.
In above scheme, when truss forms larger deviation post with prefabricated pipe gallery, supported by adjusting truss Position on correction crossbeam adjusts the position of hoist cable.
Through the above technical solutions, the prefabricated pipe gallery of self-driving type Urban Underground provided by the invention is laid with hoisting machine and applies Work method has the advantages that
1, this hoisting machine passes through cycloidal planetary gear speed reducer and driving wheel and driven wheel reality from tape drive mechanism on truss Existing independent ambulation needs not rely on external motivating force, and equipment volume optimization, space occupied are small, and driving force is big, and walking is convenient;
2, it is moved forward, can be fallen into the gap between piping lane to avoid the supporting leg of truss, even if having using leading skate One or two of leading skate is fallen into gap, nor affects on work progress, while passing through removable pin between leading device and truss Leading device can be folded up by axis connection after use, further decrease equipment volume, and walking is flexible;
3, the column bottom in four corners of truss is vertically arranged hydraulic cylinder, will utilize in prefabricated pipe gallery hoisting process Hydraulic cylinder jacks up entire truss, to realize the purpose sling prefabricated pipe gallery and be detached from ground, which can be saved The design of boom hoisting, can make weight more intensive at the top of crane trolley, improve construction efficiency;
4, the support correction crossbeam that the setting of truss bottom can be packed up or be transferred, the setting of support correction crossbeam, Ke Yi During mobile prefabricated pipe gallery, falls within the weight of truss on support correction crossbeam, reduce the pressure to bottom hydraulic cylinder Power;Meanwhile correction cross rail top being supported to contact by round steel with truss, it is point contact, is formed in truss and prefabricated pipe gallery When larger deviation post, by position of the external adjustable truss of bridge steel on support correction crossbeam, so as to adjust hoist cable Position;
5, hoist engine is set in the middle part of crane trolley, and hoist engine passes through wirerope and the pulley blocks for being installed on crane trolley both ends And it is installed on the pulley blocks connection at truss both ends, back-and-forth motion of the crane trolley at the top of truss is realized, using pulley blocks Form can reduce the operating rate of hoist engine, obtain bigger driving force, and crane trolley movement is more flexible;
5, it is transversely and horizontally set hanging beam at the top of crane trolley, tensioner adjustment screw, tensioner adjustment screw is installed on hanging beam Bottom connects the hoist cable for lifting by crane prefabricated pipe gallery, and hanging beam both ends open up strip groove, and tensioner adjustment screw is set to institute It states in strip groove, when truss and prefabricated pipe gallery placement angle are there are when gap, is being hung by adjusting tensioner adjustment screw Position on beam adjusts the position of hoist cable;After hoist cable hooks prefabricated pipe gallery, make to hang by adjusting tensioner adjustment screw Rope tenses, and hoist cable is prevented to be detached from prefabricated pipe gallery, and significantly adjustment can be achieved at the same time and finely tune by a small margin, can be rapidly achieved Correct position, it is simple and efficient to handle, it has a good application prospect;
6, driving wheel and driven wheel are two-wheel arranged side by side, and Two-wheeled can increase contact of the driving wheel with piping lane Area, increasing friction force improve the reliability of equipment;
7, it is realized by hand crank and supports the decentralization of correction crossbeam and lift, improved the safety of operation, reduce labour Risk.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described.
Fig. 1 is a kind of prefabricated pipe gallery laying hoisting machine construction of self-driving type Urban Underground disclosed in the embodiment of the present invention Process schematic;
Fig. 2 is the prefabricated pipe gallery paving of self-driving type Urban Underground that leading folding device disclosed in the embodiment of the present invention rises If hoisting machine structural schematic diagram;
Fig. 3 is that the prefabricated pipe gallery of self-driving type Urban Underground disclosed in the embodiment of the present invention is laid with hoisting machine top view;
Fig. 4 is driving mechanism schematic diagram disclosed in the embodiment of the present invention;
Fig. 5 is the correction header portion structural schematic diagram of support disclosed in the embodiment of the present invention.
In figure, 1, truss;2, cycloidal planetary gear speed reducer;3, driving wheel;4, driven wheel;5, drive shaft one;6, drive shaft two; 7, sprocket wheel;8, pin shaft;9, front guide bracket;10, leading skate;11, strut;12, hydraulic cylinder;13, hydraulic station;14, distribution box;15, Support correction crossbeam;16, round steel;17, lifting rope;18, fixed beam;19, pull ring;20, drawstring;21, pulley;22, drawstring spool; 23, hand crank;24, drag hook;25, crane trolley;26, hoist engine;27, wirerope;28, pulley blocks;29, hanging beam;30, tensioner tune Whole screw rod;31, hoist cable;32, strip groove;33, handle is adjusted;34, auxiliary wheel;35, generator.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description.
The present invention provides a kind of prefabricated pipe galleries of self-driving type Urban Underground to be laid with hoisting machine and construction method, the lifting Machine form of construction work is novel, at low cost, and splicing is accurate, and highly-safe, joining quality is reliable.
The prefabricated pipe gallery of self-driving type Urban Underground as shown in Figure 1 is laid with hoisting machine, including truss 1 and is installed on truss Driving mechanism on 1, driving mechanism include being set to the cycloidal planetary gear speed reducer 2 of 1 end of truss and being slowed down by cycloidal-pin wheel The driving wheel 3 and driven wheel 4 for being set to 1 two sides of truss that machine 2 drives, the settable auxiliary wheel 34 in truss front end and middle part, As shown in figure 4, being connected between the driving wheel 3 of 1 two sides of truss by drive shaft 1, pass through between the driven wheel 4 of 1 two sides of truss Drive shaft 26 connects, and is connected between drive shaft 1 and drive shaft 26 by sprocket wheel 7, and cycloidal planetary gear speed reducer 2 passes through sprocket wheel 7 It is connect with drive shaft one, driving wheel 3 and driven wheel 4 are two-wheel arranged side by side, and Two-wheeled can increase driving wheel 3 and pipe The contact area of corridor, increasing friction force improve the reliability of equipment.
1 front end of truss is equipped with leading device, is connected between leading device and truss 1 by removable pin 8;Leading device Including front guide bracket 9 and the leading skate 10 for being set to 9 bottom of front guide bracket, 9 front end of front guide bracket and truss connect strut between 1 top 11, it is connected between strut 11 and truss 1 by removable pin 8,9 end of front guide bracket and truss are articulated and connected between 1 bottom.Such as Shown in Fig. 2, after the completion of construction, pin shaft 8 can be removed, front guide bracket 9 is folded up, and strut 11 is fixed at the top of truss 1 and is locked Tightly.
The column bottom in 1 four corners of truss is vertically arranged hydraulic cylinder 12, hydraulic cylinder 12 be set to it is hydraulic on truss 1 Stand 13 and distribution box 14 connect, distribution box 14 connect with the generator 35 of 1 front end of truss, the fuel feeding of realization hydraulic cylinder 12 and confession Electricity.This hoisting machine realizes the power supply in equipment by included generator 35, and generator 35 passes through distribution box 14 and hoist engine 26 Connection.Limit sensors are arranged in 1 bottom of truss, and after truss 1 is by jack-up certain altitude, signal is can be transmitted to liquid in limit sensors Pressure station 13, fuel cut-off.Hydraulic station 13 simultaneously steel strand wires also between spliced prefabricated pipe gallery rise drawing provide it is hydraulic, It can be realized by the switching valve on oil feed line.Distribution box 14 is equipped with signal designation.
The support correction crossbeam 15 that the setting of 1 bottom of truss can be packed up or be transferred, supports and is arranged two before and after rectifying a deviation crossbeam 15 Root, as shown in figure 5, supporting correction 15 top-slitting of crossbeam and being wound with lifting rope along the longitudinally disposed round steel 16 of crossbeam, round steel 16 17 connect with 1 bottom fixed beam 18 of truss, and lifting rope 17 passes through the slot opened and connect with fixed beam 18.Support correction 15 bottom two of crossbeam Pull ring 19 is respectively set in side, and pull ring 19 is connect by drawstring 20 with the pulley 21 and drawstring spool 22 being mounted on truss 1, pulley 21 and drawstring spool 22 be located at the two sides of support correction crossbeam 15, hand crank 23 is set on drawstring spool 22, rotation is passed through Hand crank 23, drawstring 20 can be wound on drawstring spool 22 by support correction 15 pull-up of crossbeam or decentralization.1 bottom of truss is also set It sets for the fixed drag hook 24 for supporting correction crossbeam 15, after support correction crossbeam 15 is pulled up, branch is fixed by drag hook 24 Support correction crossbeam 15, prevents from falling down.When truss 1 is fallen on support correction crossbeam 15, truss 1 forms larger with prefabricated pipe gallery When deviation post, since truss 1 is contacted with support correction crossbeam 15 by round steel 16, it can easily adjust truss 1 and support Position on correction crossbeam 15 adjusts the position of hoist cable.Two groups of drawstrings 20 and pulley 21 are set on support correction crossbeam 15, are led to Crossing a drawstring spool 22 can drive two groups of drawstrings 20 by support correction 15 pull-up of crossbeam simultaneously.
It is equipped with crane trolley 25 at the top of truss 1, hoist engine 26 is set in the middle part of crane trolley 25, as shown in figure 3, hoist engine 26 By wirerope 27 and it is installed on the pulley blocks 28 at 25 both ends of crane trolley and is installed on the company of pulley blocks 28 at 1 both ends of truss It connects, the both ends of wirerope 27 are fixed on the pulley blocks 28 at 25 both ends of crane trolley.It is transversely and horizontally set at the top of crane trolley 25 Hanging beam 29,29 both ends of hanging beam, which are stretched out on the position of truss 1, is equipped with tensioner adjustment screw 30, the connection of 30 bottom of tensioner adjustment screw For lifting by crane the hoist cable 31 of prefabricated pipe gallery.
In the present embodiment, hanging beam 29 is arranged two groups, is located at the rear and front end of crane trolley 25, every group of hanging beam 29 includes Two, 29 both ends of hanging beam open up strip groove 32, and tensioner adjustment screw 30 is set in strip groove 32, can be in strip groove 32 Interior movement, when truss 1 and prefabricated pipe gallery placement angle are there are when gap, by adjusting tensioner adjustment screw 30 in strip groove Position in slot 32 adjusts the position of hoist cable 31.Adjustment handle 33 is installed, when 31 hook of hoist cable above tensioner adjustment screw 30 Firmly after prefabricated pipe gallery, hoist cable 31 is tensed by rotatable adjustment handle 33, hoist cable 31 is prevented to be detached from prefabricated pipe gallery.
A kind of prefabricated pipe gallery of self-driving type Urban Underground is laid with the construction method of hoisting machine, includes the following steps:
(1) prefabricated pipe gallery is successively hung in the tunnel dug using existing loop wheel machine, and has spliced 2-3 of front end Prefabricated pipe gallery, the steel strand wires hydraulic expanding then carried out between prefabricated pipe gallery are drawn, and realize nothing between prefabricated pipe gallery Seam docking;
(2) leading device is put down, truss 1 is opened to mounted prefabricated pipe gallery using driving mechanism, is made It obtains 1 front end of truss to fall at the top of prefabricated pipe gallery to be assembled, a prefabricated synthesis to be assembled is at least reserved in 1 bottom of truss Piping lane;
(3) 25 position of crane trolley is adjusted with pulley blocks 28 by hoist engine 26, by 31 hook of hoist cable in the pre- of 1 bottom of truss On suspension hook at the top of pipe gallery processed, starts hydraulic cylinder 12, entire truss 1 is jacked up, to prefabricated pipe gallery be sling de- From the ground;
(4) at this point, rotation hand crank 23, decentralization support correction crossbeam 15, make the weight of truss 1 fall within support correction crossbeam On 15, the position of crane trolley 25 is adjusted, splices that it with mounted prefabricated pipe gallery, transfers prefabricated pipe gallery, Dock it with mounted prefabricated pipe gallery, be then detached from hoist cable 31 and suspension hook, and carry out prefabricated pipe gallery it Between steel strand wires hydraulic expanding draw, realize seamless interfacing;
(5) after the prefabricated pipe gallery of 1 lower section of lifting end joist, support correction crossbeam 15 is packed up, is hung using drag hook 24 Firmly, hydraulic cylinder 12 is fallen after rise, and truss 1 declines, and is moved forward using driving mechanism driving truss 1 and leading device, behind in-position, The prefabricated pipe gallery of the lower section of truss hoisting 1 after the same method, it is seamless with the prefabricated pipe gallery that has been installed Docking, after being all installed, lifts leading device, withdraws from truss 1.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest scope of cause.

Claims (9)

1. a kind of prefabricated pipe gallery of self-driving type Urban Underground is laid with hoisting machine, which is characterized in that including truss and be installed on purlin Driving mechanism on frame, the truss front end are equipped with leading device, pass through removable pin between the leading device and truss Connection;The column bottom in four corners of truss is vertically arranged hydraulic cylinder, and the truss bottom setting can be packed up or be transferred Support rectify a deviation crossbeam;It is equipped with crane trolley at the top of the truss, hoist engine, the hoist engine are set in the middle part of the crane trolley It is connect by wirerope with the pulley blocks for being installed on crane trolley both ends and the pulley blocks for being installed on truss both ends, the loop wheel machine It is transversely and horizontally set hanging beam at the top of coaster, tensioner adjustment screw is installed on the hanging beam, tensioner adjustment screw bottom connects Connect the hoist cable for lifting by crane prefabricated pipe gallery.
2. the prefabricated pipe gallery of a kind of self-driving type Urban Underground according to claim 1 is laid with hoisting machine, which is characterized in that The driving mechanism includes being set to the cycloidal planetary gear speed reducer of truss end and being set to by what cycloidal planetary gear speed reducer drove The driving wheel and driven wheel of truss two sides are connected by drive shaft one between the driving wheel of truss two sides, truss two sides from It is connected between driving wheel by drive shaft two, is connected between the drive shaft one and drive shaft two by sprocket wheel, cycloidal-pin wheel slows down Machine is connect by sprocket wheel with drive shaft one, and the driving wheel and driven wheel are two-wheel arranged side by side.
3. the prefabricated pipe gallery of a kind of self-driving type Urban Underground according to claim 1 is laid with hoisting machine, which is characterized in that The leading device includes front guide bracket and the leading skate for being set to front guide bracket bottom, the front guide bracket front end and truss top Between connect strut, by removable pin axis connection between the strut and truss, between the front guide bracket end and truss bottom Articulated connection.
4. the prefabricated pipe gallery of a kind of self-driving type Urban Underground according to claim 1 is laid with hoisting machine, which is characterized in that The hanging beam is arranged two groups, is located at the rear and front end of crane trolley, and every group of hanging beam includes two, and the hanging beam both ends open up Strip groove, the tensioner adjustment screw are set in the strip groove, are equipped with adjustment above the tensioner adjustment screw Handle.
5. the prefabricated pipe gallery of a kind of self-driving type Urban Underground according to claim 1 is laid with hoisting machine, which is characterized in that Setting two before and after support correction crossbeam, the support correction cross rail top slot and along the longitudinally disposed round steel of crossbeam, Lifting rope is wound on the round steel to connect with truss bottom fixed beam, pull ring is respectively set in support correction crossbeam two sides of the bottom, The pull ring is connect by drawstring with the pulley and drawstring spool being mounted on truss, and the pulley and drawstring spool are located at The two sides of correction crossbeam are supported, hand crank is set on the drawstring spool, the truss bottom is also set up to be entangled for fixed support The drag hook of inclined crossbeam.
6. a kind of prefabricated pipe gallery of self-driving type Urban Underground as described in claim 1 is laid with the construction method of hoisting machine, It is characterized in that, includes the following steps:
(1) prefabricated pipe gallery is successively hung in the tunnel dug using existing loop wheel machine, and 2-3 for having spliced front end are prefabricated Pipe gallery, the steel strand wires hydraulic expanding then carried out between prefabricated pipe gallery are drawn, and it is seamless right between prefabricated pipe gallery to realize It connects;
(2) leading device is put down, is opened truss to mounted prefabricated pipe gallery using driving mechanism, so that truss Front end is fallen at the top of prefabricated pipe gallery to be assembled, and a prefabricated pipe gallery to be assembled is at least reserved in truss bottom;
(3) crane trolley position is adjusted by hoist engine, by suspension hook of the sling hook at the top of the prefabricated pipe gallery of truss bottom On, start hydraulic cylinder, entire truss is jacked up, is detached from ground so that prefabricated pipe gallery be sling;
(4) at this point, decentralization support correction crossbeam, falls within the weight of truss on support correction crossbeam, adjust the position of crane trolley It sets, splices that it with mounted prefabricated pipe gallery, transfer prefabricated pipe gallery, be then detached from hoist cable and suspension hook, and The steel strand wires hydraulic expanding carried out between prefabricated pipe gallery is drawn, and realizes seamless interfacing;
(5) after lifting the prefabricated pipe gallery below end joist, support correction crossbeam is packed up, hydraulic cylinder is fallen after rise, utilizes driving Mechanism driving truss and leading device move forward, prefabricated comprehensive below truss hoisting after the same method behind in-position It closes piping lane itself and the prefabricated pipe gallery seamless interfacing being installed after being all installed, are lifted leading device, removed Truss out.
7. the prefabricated pipe gallery of a kind of self-driving type Urban Underground according to claim 6 is laid with the construction method of hoisting machine, It is characterized in that, when truss and prefabricated pipe gallery placement angle are there are when gap, by adjusting tensioner adjustment screw in hanging beam On position adjust the position of hoist cable.
8. the prefabricated pipe gallery of a kind of self-driving type Urban Underground according to claim 6 is laid with the construction method of hoisting machine, It is characterized in that, tensing hoist cable after hoist cable hooks prefabricated pipe gallery by adjusting tensioner adjustment screw, prevent hoist cable de- From prefabricated pipe gallery.
9. the prefabricated pipe gallery of a kind of self-driving type Urban Underground according to claim 6 is laid with the construction method of hoisting machine, It is characterized in that, when truss and prefabricated pipe gallery form larger deviation post, by adjusting truss in support correction crossbeam On position adjust the position of hoist cable.
CN201910343624.6A 2019-04-26 2019-04-26 Self-driven urban underground prefabricated comprehensive pipe gallery laying hoisting machine and construction method Active CN110002343B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910343624.6A CN110002343B (en) 2019-04-26 2019-04-26 Self-driven urban underground prefabricated comprehensive pipe gallery laying hoisting machine and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910343624.6A CN110002343B (en) 2019-04-26 2019-04-26 Self-driven urban underground prefabricated comprehensive pipe gallery laying hoisting machine and construction method

Publications (2)

Publication Number Publication Date
CN110002343A true CN110002343A (en) 2019-07-12
CN110002343B CN110002343B (en) 2024-05-10

Family

ID=67174415

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910343624.6A Active CN110002343B (en) 2019-04-26 2019-04-26 Self-driven urban underground prefabricated comprehensive pipe gallery laying hoisting machine and construction method

Country Status (1)

Country Link
CN (1) CN110002343B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110863434A (en) * 2019-12-04 2020-03-06 中铁七局集团第三工程有限公司 Device for adjusting transverse pre-camber of steel box girder and construction method
CN110939156A (en) * 2019-12-30 2020-03-31 广州地铁设计研究院股份有限公司 Prefabricated plate positioning mechanism
CN114960926A (en) * 2022-05-16 2022-08-30 中国化学工程第四建设有限公司 Chemical pipe gallery structure and pipeline replacement method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05132960A (en) * 1991-11-12 1993-05-28 Kajima Doro Kk Burying method of common conduit and apparatus therefor
JPH07150767A (en) * 1992-12-16 1995-06-13 Takenaka Komuten Co Ltd Beam truss erecting method in building having overhead traveling crane
JPH10292317A (en) * 1997-02-19 1998-11-04 Yokogawa Buritsuji:Kk Installation method and device of bridge girder member
JP2012052289A (en) * 2010-08-31 2012-03-15 Kajima Corp Construction method for shield tunnel
CN103882811A (en) * 2014-04-03 2014-06-25 重庆建工桥梁工程有限责任公司 Bridge floor crane for cable-stayed bridge
CN106638687A (en) * 2016-11-16 2017-05-10 吉林省天祥建筑材料有限公司 Foundation-aid accurate and quick assembly technique for prefabricated assembly of comprehensive pipe rack
CN109295999A (en) * 2018-10-10 2019-02-01 中铁工程机械研究设计院有限公司 Prefabricated assembled pipe gallery fitting machine and its construction method
CN109440654A (en) * 2018-12-18 2019-03-08 合肥成基铁路工程科技有限公司 A kind of construction equipment and its construction method of achievable overpass beam of not closing a road to traffic
CN210103322U (en) * 2019-04-26 2020-02-21 青岛长永机械工程有限公司 Self-driven urban underground prefabricated comprehensive pipe gallery laying and hoisting machine

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05132960A (en) * 1991-11-12 1993-05-28 Kajima Doro Kk Burying method of common conduit and apparatus therefor
JPH07150767A (en) * 1992-12-16 1995-06-13 Takenaka Komuten Co Ltd Beam truss erecting method in building having overhead traveling crane
JPH10292317A (en) * 1997-02-19 1998-11-04 Yokogawa Buritsuji:Kk Installation method and device of bridge girder member
JP2012052289A (en) * 2010-08-31 2012-03-15 Kajima Corp Construction method for shield tunnel
CN103882811A (en) * 2014-04-03 2014-06-25 重庆建工桥梁工程有限责任公司 Bridge floor crane for cable-stayed bridge
CN106638687A (en) * 2016-11-16 2017-05-10 吉林省天祥建筑材料有限公司 Foundation-aid accurate and quick assembly technique for prefabricated assembly of comprehensive pipe rack
CN109295999A (en) * 2018-10-10 2019-02-01 中铁工程机械研究设计院有限公司 Prefabricated assembled pipe gallery fitting machine and its construction method
CN109440654A (en) * 2018-12-18 2019-03-08 合肥成基铁路工程科技有限公司 A kind of construction equipment and its construction method of achievable overpass beam of not closing a road to traffic
CN210103322U (en) * 2019-04-26 2020-02-21 青岛长永机械工程有限公司 Self-driven urban underground prefabricated comprehensive pipe gallery laying and hoisting machine

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110863434A (en) * 2019-12-04 2020-03-06 中铁七局集团第三工程有限公司 Device for adjusting transverse pre-camber of steel box girder and construction method
CN110939156A (en) * 2019-12-30 2020-03-31 广州地铁设计研究院股份有限公司 Prefabricated plate positioning mechanism
CN114960926A (en) * 2022-05-16 2022-08-30 中国化学工程第四建设有限公司 Chemical pipe gallery structure and pipeline replacement method
CN114960926B (en) * 2022-05-16 2023-05-02 中国化学工程第四建设有限公司 Chemical pipe gallery structure and pipe replacement method

Also Published As

Publication number Publication date
CN110002343B (en) 2024-05-10

Similar Documents

Publication Publication Date Title
CN110002343A (en) A kind of prefabricated pipe gallery of self-driving type Urban Underground is laid with hoisting machine and construction method
CN209322345U (en) The prefabricated inverted arch side box culvert loop wheel machine in tunnel with angle regulating function
CN109797833A (en) A kind of town road drain pipe construction equipment and method
CN106006398A (en) Track crane for underground coal mines
CN109667605A (en) A kind of manual imitation is laid with the construction method and laying rack of tunnel double-lining steel mesh
CN107055300A (en) A kind of escalator step erecting device and method
CN105484168B (en) Rotary hoisting equipment for stiffening beam of suspension bridge and erecting method of stiffening beam
CN209704593U (en) A kind of manual imitation is laid with the laying rack of tunnel double-lining steel mesh
CN205892575U (en) Fast set up traveling tower crane
CN213837961U (en) Concrete electric pole convenient to overhaul
CN210103322U (en) Self-driven urban underground prefabricated comprehensive pipe gallery laying and hoisting machine
CN208202586U (en) Conduit lifting device for the perfusion of power transmission tower concrete filled steel tube high-altitude
CN212374757U (en) Tower crane stable in installation
CN211114677U (en) Lifting mechanism for wall sanding machine
CN218493613U (en) Tunnel waterproof board paving and hanging trolley
CN216342231U (en) Simple platform for installing tunnel lining structure
CN216075114U (en) Pile guide
CN215165550U (en) Pile hanging device
CN205646631U (en) Cable fly line machine
CN216613496U (en) Automatic recovery unit of cable
CN105133681A (en) Track and walking combined use type cement soil wall construction equipment
CN213834375U (en) Wet seam template hoisting device of bridge
CN108775153A (en) Conduit lifting device and method for the perfusion of power transmission tower concrete filled steel tube high-altitude
CN210216177U (en) Anchor machine dragging system for beam erecting
CN207020373U (en) A kind of duct optical cable the construction line-putting device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant