JP2745004B2 - Steel construction method - Google Patents

Steel construction method

Info

Publication number
JP2745004B2
JP2745004B2 JP16940790A JP16940790A JP2745004B2 JP 2745004 B2 JP2745004 B2 JP 2745004B2 JP 16940790 A JP16940790 A JP 16940790A JP 16940790 A JP16940790 A JP 16940790A JP 2745004 B2 JP2745004 B2 JP 2745004B2
Authority
JP
Japan
Prior art keywords
steel frame
frame
crane
steel
pinned
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP16940790A
Other languages
Japanese (ja)
Other versions
JPH0460059A (en
Inventor
行正 山田
潤朗 合田
英二 大久保
裕之 甲野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP16940790A priority Critical patent/JP2745004B2/en
Publication of JPH0460059A publication Critical patent/JPH0460059A/en
Application granted granted Critical
Publication of JP2745004B2 publication Critical patent/JP2745004B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 「産業上の利用分野」 本発明は、鉄骨建方法に関する。Description: FIELD OF THE INVENTION The present invention relates to a steel frame construction method.

「従来の技術」 従来の鉄骨建方は、骨組架構の形状,重量が運搬上の
制約を大きく受けることから、単材の形で現場に運搬し
たのち、タワークレーンあるいは移動式クレーンによる
積上げ方式でもって立体的に骨組架構を組立てている。
"Conventional technology" In conventional steel frame construction, since the shape and weight of the framed structure are greatly restricted in transportation, they are transported to the site in the form of a single material and then stacked using a tower crane or mobile crane. The frame structure is assembled three-dimensionally.

叙上クレーンは、単材の重量及び作業半径,鉄骨構築
物の高さ等から選定される。
The lifting crane is selected based on the weight and working radius of the single material, the height of the steel structure, and the like.

「発明が解決しようとする課題」 しかし、従来の建方では、 (1) 単材を現場で組立てるものであるので、構築時
間が長くかかり、また、仕口誤差が重って大きな累積誤
差となり、本接合前の建直し調整にかなりの手間を要す
る。
"Problems to be Solved by the Invention" However, in the conventional construction method, (1) Since a single material is assembled on site, it takes a long construction time, and a large accumulation error due to a large overlap error. However, it takes a considerable amount of time to adjust the rebuilding before the actual joining.

(2) 作業の大部分が高所で行われることとなるた
め、作業が困難で作業能率が低上に危険が多く工期も長
くかかるが、高所で組立て作業を行なうとび職の技能は
一般的に低下してきており、また高所作業に要求される
仮設安全対策はより厳しくなってきているという難点が
ある。
(2) Since most of the work is performed at high altitudes, the work is difficult, the work efficiency is low, and there are many dangers and the construction period is long, but the skill of assembling work at high altitude is common. The problem is that temporary safety measures required for work at heights are becoming stricter.

(3) 構築物が高くなれば大型のクレーンを使用しな
ければならないため、その輸送費や稼働費は膨大なもの
となり、更にトラッククレーンはもちろんのこと、クラ
イミングクレーンを用いる場合にも、構造物の外側に設
置しなければならず、クレーン据付のためのかなり広い
余分なスペースとクレーン設備のための基礎工事または
地盤の養生を要するが、ほとんどの現場は、周囲に建物
が密集していることが多いことなどにより、材料の搬
入、取扱い、足場の確保などが難かしいこと、または障
害物であって、クレーンの搬入が不可能な現場には対応
し得ない。
(3) If the structure becomes high, a large crane must be used, so the transportation and operating costs become enormous. Furthermore, not only when using a truck crane but also when using a climbing crane, the structural It must be installed outside and requires a fair amount of extra space for crane installation and foundation work or ground curing for crane installations, but most sites have a dense surrounding building Due to the large number, it is difficult to carry in, handle, and secure a scaffolding of materials, or it is impossible to cope with an obstruction where a crane cannot be carried in.

等の問題点がある。And so on.

本発明は、単材の組立てを不安定な足場のもとでする
ことなく、充分な管理が期し得る地組みにてなし得ると
共に別段大型のクレーンを必要とすることなくして僅か
な高所作業のみでもって建方がし得る従来手段の難点の
起因である大型クレーンを必要とする高所作業での単材
の組立てという常識から脱した新規な鉄骨建方法を提供
することを目的としている。
The present invention is capable of assembling a single piece of material on an unstable scaffold, in a terrain where sufficient control can be expected, and working at a slightly higher place without the need for a specially large crane. It is an object of the present invention to provide a new steel building method which departs from the common sense of assembling single materials at a high place requiring a large crane, which is one of the drawbacks of the conventional means that can be built only by a conventional method.

「課題を解決するための手段」 上記目的を達成するために、本発明の鉄骨建方法は、
隣立する本設鉄骨群中の少なくとも安定架構最小単位分
の本設鉄骨を、その基端を所定位置にピン止めした状態
で小型クレーンで地組みし、次いで起立させて組付けて
少なくとも安定架構最小単位分を完成させ、以下、順次
隣接位置の本設鉄骨をその基端をピン止めした状態で小
型クルーンで地組みし、これを先行起立の本設鉄骨上端
に配置した滑車を介してウインチで起立させると共に当
該先行起立本設鉄骨にジョイントさせていって鉄骨架構
を構築し、建直し調整のうえ該ピン止め部を固定すると
したものである。
"Means for solving the problem" In order to achieve the above object, the steel-frame building method of the present invention,
At least the minimum unit of the stable steel frame of the adjacent group of permanent steel frames is erected with a small crane with its base end pinned at a predetermined position, and then erected and assembled to at least the stable frame. After completing the minimum unit, the main steel frames at the adjacent positions are sequentially laid with small crunes with their base ends pinned, and this is winched via a pulley arranged at the upper end of the front standing main steel frame. Then, the steel frame is connected to the pre-standing standing steel frame to construct a steel frame, and the pinned portion is fixed after rebuilding and adjustment.

「作用」 上記のように構成された本発明の工法によるならば、
本設鉄骨は、地組みにより高品質,迅速に仕上げられ、
組立てに際しては小型のクレーンがあれば済む。仕上げ
られた本設鉄骨は基端がピン止めされているので、ウイ
ンチによって簡単に起立され、クレーンによることなく
して高層架構が立ち上がることとなる。
[Operation] According to the method of the present invention configured as described above,
The main steel frame is finished with high quality and quick by the terrain,
When assembling, a small crane is sufficient. The finished steel frame is pinned at the base end, so that it can be easily raised by a winch, and a high-rise frame can be raised without using a crane.

高所作業は、先行起立の本設鉄骨に対しての後行起立
の本設鉄骨に付設の持ち出し梁のジョイントのみであ
り、単材を組立てる従来手段に比し極めて少なくなる。
The work at height is only a joint of a take-out beam attached to the main standing steel frame of the preceding standing main steel frame with respect to the preceding standing main steel frame, which is extremely small as compared with the conventional means of assembling a single member.

「実施例」 実施例について図面を参照して説明すると、第1図に
おいて、鉄骨架構1における起立した本設鉄骨2,…は、
次記する要領で立設される。すなわち、図中右側に示す
如く基礎打ちを完了した基盤3上の所定の位置に合わせ
てその基端をピン止め4した状態にて小型クレーン(図
示省略)を用いて本設鉄骨2は地組みする。
[Example] An example will be described with reference to the drawings. In Fig. 1, the standing steel frames 2, ... in the steel frame 1 are:
It will be erected as described below. That is, as shown on the right side of the drawing, the permanent steel frame 2 is grounded by using a small crane (not shown) in a state where the base end is pinned 4 at a predetermined position on the base 3 where the foundation is completed. I do.

尚、図中5,…、6,…は地組み時に取付けられる持ち出
し梁,控えである。
In the figure, 5, ..., 6, ... are take-out beams and stays attached at the time of ground assembling.

上記の如く地組みされた本設鉄骨2は、先端を持ち上
げれば起立するからワイヤー等で引き上げて起立させる
(図示省略)。
Since the permanent steel frame 2 assembled as described above rises when the tip thereof is lifted, it is raised by a wire or the like and raised (not shown).

この要領を少なくとも安定架構の最小単位分に相当す
る本設鉄骨(2,3本)に適用し、図示例の如く最小の安
定架構1′を先ず構築する。
This procedure is applied to at least the permanent steel frames (two or three) corresponding to the minimum unit of the stable frame, and the minimum stable frame 1 'is first constructed as shown in the illustrated example.

基本となる安定架構1′が完成したならば、順次隣接
位置の本設鉄骨2を既述の要領で地組みする。該安定架
構1′の側端に位置する本設鉄骨2上端に滑車7を配置
し、これに地上のウインチ8からのワイヤー9を掛けた
うえ上記の地組みされた本設鉄骨2の先端に取付けた滑
車10に掛け渡す等にて掛け、図示の如く引き起こす。起
立された本設鉄骨2は、先行起立の本設鉄骨2にジョイ
ントされる。以下、これを繰り返して架構を完成させて
いく。
When the basic stable frame 1 'is completed, the permanent steel frames 2 at the adjacent positions are sequentially laid in the manner described above. A pulley 7 is arranged at the upper end of the permanent steel frame 2 located at the side end of the stable frame 1 ′, and a wire 9 from a winch 8 on the ground is hung on the pulley 7. Hang it by hanging it over the attached pulley 10, etc., and raise it as shown in the figure. The upright standing steel frame 2 is joined to the preceding standing upright steel frame 2. Hereinafter, this is repeated to complete the frame.

「発明の効果」 本発明は、以上説明したように構成されているので、
以下に記載されるような効果を奏する。
[Effect of the Invention] Since the present invention is configured as described above,
The following effects are obtained.

(1)小型クレーンで地組みすることでクレーンの費用
の低減ができる。
(1) The cost of the crane can be reduced by laying the ground with a small crane.

(2)障害物あるいは大型クレーンが入れないとか設置
できない狭い場所での建方が可能である。
(2) It can be built in a narrow place where obstacles or large cranes cannot be installed or installed.

(3)高所作業を少なくすることで安全性が向上する。(3) Safety is improved by reducing work at height.

【図面の簡単な説明】[Brief description of the drawings]

第1図は本発明の鉄骨建方法の要領の説明図である。 1……鉄骨架構、1′……安定架構、2……本設鉄骨、
3……基盤、4……ピン止め、5……持ち出し梁、6…
…控え、7……滑車、8……ウインチ、9……ワイヤ
ー、10……滑車。
FIG. 1 is an explanatory view of the point of the steel frame building method of the present invention. 1 ... steel frame, 1 '... stable frame, 2 ... permanent steel frame,
3 ... foundation 4 ... pinning 5 ... take-out beam 6 ...
... ahead, 7 ... pulley, 8 ... winch, 9 ... wire, 10 ... pulley.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 甲野 裕之 広島県広島市中区橋本町10番10号 株式 会社竹中工務店広島支店内 (56)参考文献 特開 昭45−3745(JP,A) ──────────────────────────────────────────────────続 き Continuation of the front page (72) Inventor Hiroyuki Kono 10-10 Hashimotocho, Naka-ku, Hiroshima-shi, Hiroshima Inside the Hiroshima branch of Takenaka Corporation (56) References JP-A-45-3745 (JP, A)

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】隣立する本設鉄骨群中の少なくとも安定架
構最小単位分の本設鉄骨を、その基端を所定位置にピン
止めした状態で小型クレーンで地組みし、次いで起立さ
せて組付けて少なくとも安定架構最小単位分を完成さ
せ、以下、順次隣接位置の本設鉄骨をその基端をピン止
めした状態で小型クルーンで地組みし、これを先行起立
の本設鉄骨上端に配置した滑車を介してウインチで起立
させると共に当該先行起立本設鉄骨にジョイントさせて
いって鉄骨架構を構築し、建直し調整のうえ該ピン止め
部を固定するとしたことを特徴とする鉄骨建方法。
1. A small crane with a base end pinned at a predetermined position to form a ground of at least a minimum unit of a stable frame in a group of adjacent permanent steel frames, and then stands up. At least the minimum unit of the stable frame was completed, and the main steel frames at adjacent positions were sequentially laid with small crane with the base end pinned, and this was placed at the upper end of the main steel frame standing up front. A steel frame building method, comprising: erecting with a winch via a pulley and jointing to the preceding upright standing steel frame to construct a steel frame, adjusting the rebuilding, and fixing the pinned portion.
JP16940790A 1990-06-27 1990-06-27 Steel construction method Expired - Fee Related JP2745004B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16940790A JP2745004B2 (en) 1990-06-27 1990-06-27 Steel construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16940790A JP2745004B2 (en) 1990-06-27 1990-06-27 Steel construction method

Publications (2)

Publication Number Publication Date
JPH0460059A JPH0460059A (en) 1992-02-26
JP2745004B2 true JP2745004B2 (en) 1998-04-28

Family

ID=15886030

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16940790A Expired - Fee Related JP2745004B2 (en) 1990-06-27 1990-06-27 Steel construction method

Country Status (1)

Country Link
JP (1) JP2745004B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09183626A (en) * 1995-12-28 1997-07-15 Central Glass Co Ltd Reinforced thin glass plate
US6858553B2 (en) 2000-10-03 2005-02-22 Nippon Sheet Glass Co., Ltd. Glass composition
EP1245545B1 (en) 2001-03-30 2011-08-10 Asahi Glass Company Ltd. Glass plate and method for tempering a glass plate
CN102505860B (en) * 2011-10-21 2013-01-02 温州建设集团有限公司 Novel Lifting method for irregularly-shaped steel structure member
JP7374063B2 (en) * 2020-11-10 2023-11-06 大成建設株式会社 Body raising system and how to install the body vertically
WO2022261797A1 (en) * 2021-06-15 2022-12-22 马克双 Single-hook type manual butt joint steel structure frame

Also Published As

Publication number Publication date
JPH0460059A (en) 1992-02-26

Similar Documents

Publication Publication Date Title
US20190338529A1 (en) Modular stair system
JP2745004B2 (en) Steel construction method
CN210002931U (en) tool type protection system for telescopic adjustment of construction of super high-rise outer frame column
JP3049300B2 (en) Construction method of beam truss in building with overhead traveling crane
WO2008000054A1 (en) Autoliftable bridge crane system for building and tower construction
CN114482561A (en) Steel structure roof installation method
JP2942879B2 (en) Temporary house for all-weather construction
JPS6037257B2 (en) Construction method for floor panels using deck plates
JP2585174B2 (en) How to fix scaffolding for temporary tents
JP2858891B2 (en) Construction method of large span dome roof
JP3100574B2 (en) Suspended scaffold and its erection method
CN212688719U (en) Bridge vase-shaped pier body protective bracket
JP2690822B2 (en) Steel construction method for low-rise buildings
JP2854389B2 (en) Steel construction method
JP2779258B2 (en) Roof lift-up method
JPH04319172A (en) Skeleton building construction workbench
JP2579813B2 (en) Multipurpose long span ceiling moving scaffold
JP2994205B2 (en) Structural assembly method
JP2761526B2 (en) How to build structures
JP2761527B2 (en) How to build structures
JPS61158537A (en) Building of iron skeletal
JP2997449B1 (en) Rebar assembling work scaffold and construction method of rebar structure using this work scaffold
CN109930758A (en) Tilting nuclear power station transport channel system and its construction method
JPS6333543B2 (en)
JPS6366983B2 (en)

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees