JP3049300B2 - Construction method of beam truss in building with overhead traveling crane - Google Patents

Construction method of beam truss in building with overhead traveling crane

Info

Publication number
JP3049300B2
JP3049300B2 JP5316328A JP31632893A JP3049300B2 JP 3049300 B2 JP3049300 B2 JP 3049300B2 JP 5316328 A JP5316328 A JP 5316328A JP 31632893 A JP31632893 A JP 31632893A JP 3049300 B2 JP3049300 B2 JP 3049300B2
Authority
JP
Japan
Prior art keywords
building
truss
stage
overhead traveling
traveling crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP5316328A
Other languages
Japanese (ja)
Other versions
JPH07150767A (en
Inventor
邦彦 堀江
仁志 南川
直樹 清水
大介 深町
征洋 松葉
則夫 長谷川
明 阪
一秀 山内
文洋 石川
登 西垣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyo Electric Power Co Inc
Takenaka Corp
Tokyo Electric Power Services Co Ltd
Original Assignee
Tokyo Electric Power Co Inc
Takenaka Corp
Tokyo Electric Power Services Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Electric Power Co Inc, Takenaka Corp, Tokyo Electric Power Services Co Ltd filed Critical Tokyo Electric Power Co Inc
Priority to JP5316328A priority Critical patent/JP3049300B2/en
Publication of JPH07150767A publication Critical patent/JPH07150767A/en
Application granted granted Critical
Publication of JP3049300B2 publication Critical patent/JP3049300B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、天井走行クレーンを有
する建屋に於ける梁トラス建方方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for building a beam truss in a building having an overhead traveling crane.

【0002】[0002]

【従来の技術】例えば発電所におけるタービン建屋の如
く天井走行クレーンを有する建屋の鉄骨構造体の梁トラ
スの建方は、従来、先行建方の柱、壁鉄骨に対して比較
的小規模で揚重が容易な場合や規模が大きくても大型の
揚重クレーンでの持ち込みが可能である場合には、一括
で全スパン分建方に由り、又は規模の大きさにクレーン
の揚重能力を対応させ得ない事情がある場合には仮受ベ
ント構台で仮受けする分割建方に由るとするのが常識で
ある。
2. Description of the Related Art Conventionally, a beam truss of a steel structure of a building having an overhead traveling crane, such as a turbine building in a power plant, has conventionally been constructed in a relatively small scale with respect to columns and wall steel frames of the preceding building. If the weight is easy or if it is possible to bring in a large lifting crane even if the scale is large, the lifting capacity of the crane must be determined in accordance with the construction method for the entire span at one time, or to the size of the scale. It is common sense that if there is a situation that cannot be handled, it will be based on the split erection that is temporarily received by the temporary receiving vent gantry.

【0003】さらに、梁トラス建方後の建屋の天井仕上
げ等の後作業は下部から総足場を架設するか吊足場を全
域に架設して行なうのが常識となっている。
[0003] Further, it is a common sense that post-work such as finishing the ceiling of a building after constructing a beam truss is performed by erection of a total scaffold from a lower portion or erection of a suspended scaffold all over.

【0004】[0004]

【発明が解決しようとする課題】しかるに、一括建方、
ベント架設のいずれにあっても安全上建方中の梁トラス
の直下の同時作業は許容され得ない。よって、工期的に
歩掛は低下せざるを得ず工期の長期化が避け得ないとい
う問題点がある。一方、その後の仕上げ等の後作業にお
いては、下部からの足場、吊足場のいずれにおいても全
域に架けざるを得ず、仮設材のコストアップは避けられ
ない。さらに、前者の場合は、下部での同時作業が許容
されない不便があり、後者の場合は、吊り材のチェーン
等の仮設材を用いるための仕上げ未了部の発生すること
に由る別の手段で作業しなければないない欠点があっ
て、工期の長期化と新たな仮設コストのアップが避けら
れないという問題点がある。
[Problems to be solved by the invention]
Simultaneous work beneath the beam truss during construction is unacceptable for any of the vent erections. Therefore, there is a problem that the step must be reduced in the construction period and the construction period cannot be prolonged. On the other hand, in the subsequent work such as finishing, the scaffolding from the lower part and the suspension scaffolding must be extended over the entire area, and the cost of the temporary material is inevitably increased. Further, in the former case, there is an inconvenience that simultaneous work in the lower part is not allowed, and in the latter case, another means is required due to the occurrence of an unfinished part for using a temporary material such as a chain of a hanging material. However, there is a drawback that the work must be carried out at the same time, and there is a problem that it is unavoidable to lengthen the construction period and increase new temporary costs.

【0005】本発明は、従来の技術の有するこのような
問題点に鑑みてなされたものであり、梁トラス建方中に
あっても直下の作業が可能で、かつ、下部からの足場や
吊足場を大巾に削減してそれ以後の仕上げ等の後作業も
遂行し得て、著しく工期の短縮化、コスト低減化が可能
な天井走行クレーンを有する建屋に於ける梁トラス建方
方法を提供することを目的としている。
The present invention has been made in view of the above-mentioned problems of the prior art, and can perform work directly below even when a beam truss is being constructed. Provides a method of building a beam truss in a building with an overhead traveling crane that can greatly reduce the scaffolding and perform subsequent work such as finishing, thereby significantly shortening the construction period and reducing costs. It is intended to be.

【0006】[0006]

【課題を解決するための手段】上記目的を達成するため
に、本発明における天井走行クレーンを有する建屋に於
ける梁トラス建方方法は、天井走行クレーンを有する建
屋に於ける先行建方の柱壁鉄骨に設置されたクレーンガ
ーダーに、鉄骨建方構台,鉄骨建方以後の後作業用足
場,上下作業を可能とする防護構台,下部工事の為の揚
重設備基盤等の役を果たすトラベリングステージを仮設
し、しかる後、この仮設のトラベリングステージを移動
させながら一括若しくは分割建方の梁トラスの仕口合せ
等の前記の諸作業を順次とり行なうとしたものである。
In order to achieve the above object, a method of constructing a beam truss in a building having an overhead traveling crane according to the present invention comprises: A traveling stage that serves as a crane girder installed on the wall steel frame, serving as a steel frame gantry, a scaffold for post-work after the steel frame erection, a protective gantry that allows up and down work, and a lifting equipment base for substructure work. After that, while the temporary traveling stage is being moved, the above-mentioned various operations such as the jointing of the beam trusses of the collective or divided construction are sequentially performed.

【0007】[0007]

【作用】先行建方の壁鉄骨に設置されたクレーンガーダ
ーに仮設されたトラベリングステージは、移動式の鉄骨
建方構台,鉄骨建方以後の後作業用足場,上下作業を可
能とする防護構台,下部工事の為の揚重設備基盤を提供
することとなるので、建方中の梁トラスの直下での作業
が許容され、上下同時作業が可能となると共にステージ
上に簡易足場を組むことに由って梁トラス建方以後の仕
上げ等の後作業が下部からの足場、吊足場を要すること
なく遂行し得ることとなる。この結果、著しい工期の短
縮化、コスト低減化が期し得ることとなる。
The traveling stage temporarily mounted on a crane girder installed on the wall steel frame of the preceding building is a movable steel frame gantry, a scaffold for post-work after the steel frame erection, a protective gantry that allows up and down work, Since it will provide a lifting equipment base for substructure work, work directly under the beam truss being built is allowed, simultaneous work up and down is possible, and it is necessary to build a simple scaffold on the stage. Therefore, post work such as finishing after the construction of the beam truss can be performed without the need for a scaffold or a suspended scaffold from below. As a result, remarkable shortening of the construction period and cost reduction can be expected.

【0008】[0008]

【実施例】実施例について図面を参照して説明すると、
図1〜図18において柱壁鉄骨1,1′はクローラーク
レーン2,2′等を用いて先行建方され、クレーンガー
ダー3,…が設置される。当該クレーンガーダー3には
走行台車4,…を有する仮設のトラベリングステージ6
が架設される。この仮設のステージ6は例えば主桁17
にステージ架構18を接続させ、上面に全面足場5を敷
設することで構成されている。尚、主桁17を本設の走
行クレーンで代用させて有効利用を図るとしても良い。
ステージ6走行用としてクレーンガーター3上に確保さ
れねばならないレールは、仮設であっても良く、本設の
走行クレーン用に設けられるものを利用しても良い。
Embodiments will be described with reference to the drawings.
1 to 18, the column-wall steel frames 1, 1 ′ are erected in advance using crawler cranes 2, 2 ′, and crane girders 3 are installed. The crane girder 3 has a temporary traveling stage 6 having traveling carts 4,.
Is erected. The temporary stage 6 is, for example, a main girder 17
Is connected to the stage frame 18 and the entire surface scaffold 5 is laid on the upper surface. Incidentally, the main girder 17 may be replaced by a permanently installed traveling crane for effective use.
The rail that must be secured on the crane gutter 3 for traveling the stage 6 may be temporary or may be a rail provided for a main traveling crane.

【0009】このようなクレーンガーダー3上に仮設さ
れた当該トラベリングステージ6は、後行建方の梁トラ
ス7についての鉄骨建方構台,鉄骨建方以後の後作業用
足場、さらには、上下作業を可能とする防護構台、下部
工事の為の揚重設備基盤となり得る。梁トラス7は一括
建方であっても分割建方のいずれでも良く、図1,図3
にあっては分割建方の側でもって示しており、クローラ
ークレーン8若しくは9が3分割のトラス部材7a,7
b,7cを吊り込んでいる。
The traveling stage 6 temporarily provided on such a crane girder 3 includes a steel erection gantry for a beam truss 7 in a subsequent erection, a post-work scaffold after the steel erection, and a vertical operation. Can be used as a protective gantry and a lifting equipment base for substructure construction. The beam truss 7 may be either a one-piece construction or a divided construction.
Is shown on the side of the divided erection, and the crawler crane 8 or 9 is divided into three divided truss members 7a, 7
b and 7c are suspended.

【0010】ステージ6上で梁トラス7の鉄骨建方,仕
口合せ等がなされている間、ステージ6直下は防護され
ているので、図1,図2に示される如くオペレーション
フロアを提供する2〜3階鉄骨10の建方も同時進行で
施工できる。図9〜図17はこの工程を詳細に示す。す
なわち、ステージ6上に持ち込まれたトラス梁セット
7′をジャッキ上に受止し、結合本締を行なう。図中1
1はセット7′の転倒防止用建入治具である(図9)。
While the steel truss 7 is being constructed on the stage 6 and the joints are being constructed, the portion immediately below the stage 6 is protected, so that the operation floor is provided as shown in FIGS. The construction of the steel frame 10 on the third floor can be performed simultaneously. 9 to 17 show this step in detail. That is, the truss beam set 7 'brought on the stage 6 is received on the jack, and the main fastening is performed. 1 in the figure
Reference numeral 1 denotes a falling jig for preventing the set 7 'from falling (FIG. 9).

【0011】トラス梁セット7′についてのムクリ調整
のためのジャッキダウンを行なう(図10)。先行建方
の梁トラス7との間のつなぎ部12の接続を行なった
後、該先行建方の梁トラス7の仕口合せを完了する(図
11)。仕口合せを完了した梁トラス7については図示
省略の簡易足場をステージ6上に組んで塗装仕上その他
の仕上工事を施こすと共にステージ6の下では2〜3階
鉄骨10の建方を行なう(図12)。
A jack-down operation for adjusting the stiffness of the truss beam set 7 'is performed (FIG. 10). After the connection of the connecting portion 12 with the beam truss 7 of the preceding erection, the connection of the beam truss 7 of the preceding erection is completed (FIG. 11). For the beam truss 7 for which the joining has been completed, a simplified scaffold (not shown) is assembled on the stage 6 to perform painting and other finishing work, and to construct the second- or third-floor steel frame 10 under the stage 6 ( (FIG. 12).

【0012】ステージ6をトラベリングして上記の建方
をした鉄骨10を防護しておいて建入調整を行なう(図
13)。ステージ6上で既述の図9の工程をとり行なう
と共に該鉄骨10についての本締めを行なう(図1
4)。ステージ6上で既述の図10の工程を行なう(図
15)。
The stage 6 is traveled to protect the steel frame 10 constructed as described above, and the installation is adjusted (FIG. 13). The above-described process of FIG. 9 is performed on the stage 6 and the steel frame 10 is fully tightened (FIG. 1).
4). The above-described step of FIG. 10 is performed on the stage 6 (FIG. 15).

【0013】ステージ6上で既述の図11の工程を行な
う(図16)。叙上の要領を繰り返したら、安定した架
構部のコンクリート打設13を順次とり行なっていく
(図17)。叙上の下部作業は追随する揚重設備を伴な
うことに由って一層やり易すいが、図18はステージ6
を揚重設備基盤に利用した例を示す。すなわち、ステー
ジ6上に軌条14を敷設し、小型クレーン15を走行さ
せる。若しくは、ステージ6下面にX,Y方向移動可能
な天井吊りホイストクレーン16を組み付ける。
The above-described step of FIG. 11 is performed on the stage 6 (FIG. 16). After the above procedure is repeated, concrete placing 13 of the stable frame portion is sequentially performed (FIG. 17). The lower part above is easier to do because of the accompanying lifting equipment, but FIG.
The following shows an example in which the is used for the lifting equipment base. That is, the rail 14 is laid on the stage 6 and the small crane 15 is run. Alternatively, a ceiling suspended hoist crane 16 that can move in the X and Y directions is mounted on the lower surface of the stage 6.

【0014】尚、ステージ6は建屋の一方端から他方端
に向けて走行させても、中央から相反する方向に2台走
行させても良く、建屋の事情に応じて配慮すれば良い。
また、当然ながら終端に至って解体回収される。既述の
図9〜図11の梁トラス7建方の際、トラベリングステ
ージを本設の天井走行クレーンを利用した場合の本発明
にあっては、以下詳述の利点がある。
The stage 6 may be run from one end of the building to the other end, or two stages may be run in opposite directions from the center, depending on the circumstances of the building.
In addition, of course, they are dismantled and collected at the end. When the beam truss 7 shown in FIGS. 9 to 11 is constructed and the traveling stage uses a permanent overhead traveling crane, the present invention has the following advantages.

【0015】すなわち、図19〜図28に示す如く、梁
トラス分割建方にあっては、仮設のステージ6にトラス
部材受上用のジャッキ19が配置され(図19)、分割
のトラス部材7a、7c、7dが持ち込みされて所定の
ムクリ度合のもとに接合される(図20、図21、図2
2)。しかる後、ジャッキ19による支持力は開放され
(図23)て、トラス梁セット7′のムクリ度合が所定
通りであるか否かが確認される。
That is, as shown in FIG. 19 to FIG. 28, in the beam truss divided construction method, a jack 19 for receiving the truss member is arranged on the temporary stage 6 (FIG. 19), and the divided truss member 7a is provided. , 7c, 7d are brought in and joined under a predetermined degree of curl (FIGS. 20, 21, and 2).
2). Thereafter, the supporting force of the jack 19 is released (FIG. 23), and it is confirmed whether or not the degree of curl of the truss beam set 7 'is as specified.

【0016】ジャッキ19はレベルダウンをして支持力
開放にてレベルを降下させたトラス梁セット7′を新め
て支持し直し(図24)、この状態のもとにて既述の図
11に示すつなぎ部12の接続がとり行なわれるもので
あるが、これ等一連の工程は、図25〜図27に示され
る如く、指定のムクリでもって仰姿勢にしている先行建
方の梁トラス7の先端レベルよりもつなぎ部接続後の降
下代を見込んでムクリ度合を高いレベルに設定のトラス
梁セット7′との間には、当然のことながらレベル差が
あるため、つなぎ部12のブレース20,20′は長短
異寸法となる(図25(a),(b))。このレベルで
支持のもとつなぎ部12の接続がなされ、支持力が開放
されると、つなぎ部12接続による負荷により、先端は
少し降下する(図26)。
The jack 19 lowers the level and re-supports the truss beam set 7 'whose level has been lowered by releasing the supporting force (FIG. 24). In this state, the jack 19 has been described with reference to FIG. The connection of the connecting portion 12 shown in FIG. 25 is performed. A series of these steps is performed as shown in FIGS. 25 to 27. Naturally, there is a level difference between the truss beam set 7 'and the truss beam set 7' which is set to a higher level in anticipation of the descent allowance after the connection of the tie portion than the end level of the brace 20 of the tie portion 12. , 20 ′ have different lengths (FIGS. 25A and 25B). At this level, when the connecting portion 12 is connected under the support and the supporting force is released, the tip slightly lowers due to the load by the connecting portion 12 (FIG. 26).

【0017】さらに、この先きに接続がなされることに
よる新たな負荷で、ダウンするうえに、既述の図17の
コンクリート打設13でもってレベルはダウンする(図
27)。これ等の段階的レベルダウンを計算してムクリ
は算出決定されている。しかるに、終局的には同一寸法
にて落着かねばならないブレース20、20′に課せら
れる締結点誤差吸収能力は、上述の如くレベル差を有し
たままで接合をしなければならないもとでは、ルーズホ
ールでの吸収でしか対応し得ないが、これではその都度
再締結の必要が生じて工程増加の不利がある。
Furthermore, the level is lowered by the above-described concrete casting 13 in FIG. 17 in addition to the down due to the new load due to the earlier connection (FIG. 27). By calculating these gradual level reductions, the calculation is determined. However, the ability to absorb the fastening point error imposed on the braces 20, 20 ', which must ultimately be settled to the same size, is loose if the joining must be performed while maintaining the level difference as described above. This can only be achieved by absorption in the hall, but this requires re-fastening each time, which is disadvantageous in increasing the number of steps.

【0018】ところが持ち込みされるトラス梁セット
7′直下に位置する本発明の主桁17若しくは本設の走
行クレーン大重量であることを利用して叙上の不利を
解消することが可能である。すなわち、図28に示す如
く、トラス梁セット7′をつなぎ部12と接続するに際
し、大重量のためワイヤー21又はジャッキ22等の締
結材取付基盤たり得る主桁17若しくは走行クレーンよ
り締結材の持ち出しをして強制的にたわませて、既建込
みの梁トラス7の先端レベルに合わせ、かかる状態のも
のでつなぎ部12の接続を行なう。こうすると、同レベ
ルのためにブレース20、20′は同寸法にて締結され
ることとなり、締結のし直しも不必要化して工程上、品
質上でも好ましい。
It is possible to eliminate the disadvantages of the ordination by utilizing the main beam 17 or the traveling crane of the present setting is large weight of the [0018] However the present invention is located in the truss beam set 7 'immediately below that is bringing . That is, as shown in FIG. 28, when the truss beam set 7 'is connected to the connecting portion 12, the fastening material is taken out from the main girder 17 or the traveling crane which can serve as a fastening material mounting base such as the wire 21 or the jack 22 because of its heavy weight. Then, the connecting portion 12 is connected in such a state that it is in conformity with the tip level of the built-in beam truss 7. By doing so, the braces 20, 20 'are fastened to the same size because of the same level, and re-fastening becomes unnecessary, which is preferable in terms of process and quality.

【0019】[0019]

【発明の効果】本発明は、以上説明したように構成され
ているので、以下に記載されるような効果を奏する。地
面から立ち上げの足場若しくはベント設置が不可欠の従
来技術にあっては、絶対に上下同時作業は不可能であっ
たが、本発明にあっては可能であり、工期短縮、コスト
低減化の効果は著しい。
Since the present invention is configured as described above, it has the following effects. In the prior art where it is essential to set up a scaffold or vent from the ground, simultaneous work up and down was absolutely impossible. However, according to the present invention, it is possible, and the effects of shortening the construction period and reducing costs are achieved. Is remarkable.

【0020】また、特に組立,撤去の煩わしい仮設材を
有する仮受ベント工法,地面からの立上げ足場、吊足場
工法に比しては、 (1)ベント若しくは足場設置場所を平坦にする必要が
あり、障害物等がある場合は複雑な部材構成となり手間
が掛かる。 (2)ベント若しくは足場組立解体作業は高所作業で危
険性が高く作業性は低下し、工程増となる。 (3)ベント解体時は、既に上載構造物があるため非常
に危険を伴う作業となる。 (4)風並びに地震等による水平力に対して転倒しやす
い構造であるため、ワイヤーロープにより転倒防止対策
を講ずる必要がある。 (5)鉄骨建方を行う際、足場設備を完全に行う事がで
きず不安定作業が多くなる。特にベントとベント間の二
次部材取付け時は作業性が悪く安全性がかなり低下す
る。 等の難点が全く無く、有利である。
In addition, in particular, as compared with the temporary receiving vent method having a temporary material that is cumbersome to assemble and remove, the scaffold rising from the ground, and the suspending scaffold method, (1) the vent or the scaffold installation site needs to be flat. In the case where there is an obstacle or the like, a complicated member configuration is required and it takes time and effort. (2) Vent or scaffold assembling and disassembling work is a dangerous work at a high place, which reduces workability and increases the number of steps. (3) When the vent is dismantled, the operation is very dangerous because there is already an overlying structure. (4) Since the structure is easy to overturn against horizontal force due to wind, earthquake, etc., it is necessary to take measures to prevent overturning with a wire rope. (5) When constructing a steel frame, the scaffolding equipment cannot be completely completed and unstable work increases. In particular, when a secondary member is attached between the vents, workability is poor and safety is considerably reduced. There are no difficulties such as the above, which is advantageous.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明工法による建屋の正面図である。FIG. 1 is a front view of a building according to the method of the present invention.

【図2】本発明工法になる建屋の側面図である。FIG. 2 is a side view of a building according to the method of the present invention.

【図3】本発明工法になる建屋の平面図である。FIG. 3 is a plan view of a building according to the method of the present invention.

【図4】本発明工法に於けるトラベリングステージの平
面図である。
FIG. 4 is a plan view of a traveling stage in the method of the present invention.

【図5】図4中A−A矢視図である。FIG. 5 is a view taken in the direction of arrows AA in FIG. 4;

【図6】図4中B−B矢視図である。6 is a view taken in the direction of arrows BB in FIG. 4;

【図7】図4中C−C矢視図である。FIG. 7 is a view taken in the direction of the arrows CC in FIG. 4;

【図8】図4中D−D矢視図である。FIG. 8 is a view as viewed in the direction of the arrow DD in FIG. 4;

【図9】本発明工法の工程図である。FIG. 9 is a process chart of the method of the present invention.

【図10】本発明工法の工程図である。FIG. 10 is a process chart of the method of the present invention.

【図11】本発明工法の工程図である。FIG. 11 is a process chart of the method of the present invention.

【図12】本発明工法の工程図である。FIG. 12 is a process chart of the method of the present invention.

【図13】本発明工法の工程図である。FIG. 13 is a process chart of the method of the present invention.

【図14】本発明工法の工程図である。FIG. 14 is a process chart of the method of the present invention.

【図15】本発明工法の工程図である。FIG. 15 is a process chart of the method of the present invention.

【図16】本発明工法の工程図である。FIG. 16 is a process chart of the method of the present invention.

【図17】本発明工法の工程図である。FIG. 17 is a process chart of the method of the present invention.

【図18】トラベリングステージを揚重設備基盤とした
説明図である。
FIG. 18 is an explanatory view using a traveling stage as a lifting equipment base.

【図19】本発明のトラス梁セット建込工程図である。FIG. 19 is a truss beam set installation process diagram of the present invention.

【図20】本発明のトラス梁セット建込工程図である。FIG. 20 is a truss beam set installation process diagram of the present invention.

【図21】本発明のトラス梁セット建込工程図である。FIG. 21 is a truss beam set installation process diagram of the present invention.

【図22】本発明のトラス梁セット建込工程図である。FIG. 22 is a truss beam set installation process diagram of the present invention.

【図23】本発明のトラス梁セット建込工程図である。FIG. 23 is a truss beam set installation process diagram of the present invention.

【図24】本発明のトラス梁セット建込工程図である。FIG. 24 is a truss beam set installation process diagram of the present invention.

【図25】(a)は従来のトラス梁セットのムクリ説明
図,(b)はつなぎ部のブレース寸法説明図である。
FIG. 25A is an explanatory view of a conventional truss beam set, and FIG. 25B is an explanatory view of brace dimensions of a connecting portion.

【図26】従来のトラス梁セットのムクリ説明図であ
る。
FIG. 26 is an explanatory diagram of a conventional truss beam set.

【図27】従来のトラス梁セットのムクリ説明図であ
る。
FIG. 27 is an explanatory view of a conventional truss beam set.

【図28】本発明のつなぎ部接続仕様説明図である。FIG. 28 is an explanatory diagram of a connection portion connection specification of the present invention.

【符号の説明】[Explanation of symbols]

1,1′ 柱壁鉄骨 2,2′ クローラークレーン 3 クレーンガーダー 4 走行台車 5 全面足場板 6 トラベリングステージ 7 梁トラス 7a,7b,7c トラス部材 8,9 クローラークレーン 10 鉄骨 11 転倒防止用建入治具 12 つなぎ部 13 コンクリート打設 14 軌条 15 小型クレーン 16 天井吊りホイストクレーン 17 主桁 18 ステージ架構 19 ジャッキ 20,20′ ブレース 21 ワイヤー 22 ジャッキ DESCRIPTION OF SYMBOLS 1, 1 'Column-wall steel frame 2, 2' Crawler crane 3 Crane girder 4 Traveling trolley 5 Full-scale scaffolding board 6 Traveling stage 7 Beam truss 7a, 7b, 7c Truss member 8, 9 Crawler crane 10 Steel frame 11 Overturn prevention construction Tool 12 Joint 13 Concrete casting 14 Rail 15 Small crane 16 Overhead hoist crane 17 Main girder 18 Stage frame 19 Jack 20, 20 'Brace 21 Wire 22 Jack

───────────────────────────────────────────────────── フロントページの続き (72)発明者 堀江 邦彦 東京都中央区銀座八丁目21番1号 株式 会社竹中工務店 東京本店内 (72)発明者 南川 仁志 東京都中央区銀座八丁目21番1号 株式 会社竹中工務店 東京本店内 (72)発明者 清水 直樹 東京都中央区銀座八丁目21番1号 株式 会社竹中工務店 東京本店内 (72)発明者 深町 大介 東京都中央区銀座八丁目21番1号 株式 会社竹中工務店 東京本店内 (72)発明者 松葉 征洋 東京都中央区銀座八丁目21番1号 株式 会社竹中工務店 東京本店内 (72)発明者 長谷川 則夫 神奈川県横浜市鶴見区大黒町11番1号 東京電力株式会社 横浜火力建設所内 (72)発明者 阪 明 東京都千代田区内幸町1丁目1番3号 東京電力株式会社内 (72)発明者 山内 一秀 東京都千代田区内幸町2丁目1番4号 東電設計株式会社内 (72)発明者 石川 文洋 東京都千代田区内幸町2丁目1番4号 東電設計株式会社内 (72)発明者 西垣 登 東京都豊島区北大塚一丁目13番15号 宮 地建設工業株式会社内 (56)参考文献 特開 平2−8432(JP,A) 特公 昭58−6025(JP,B1) (58)調査した分野(Int.Cl.7,DB名) E04G 21/14 E04B 1/35 E04H 5/02 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Kunihiko Horie 8-21-1, Ginza, Chuo-ku, Tokyo Inside Takenaka Corporation Tokyo Main Store (72) Inventor Hitoshi Minamikawa 8-2-1, Ginza, Chuo-ku, Tokyo No. Takenaka Corporation Tokyo Main Store (72) Inventor Naoki Shimizu 8-21-1, Ginza, Chuo-ku, Tokyo Tokyo Main Company (72) Inventor Daisuke Fukamachi 8-21 Ginza, Chuo-ku, Tokyo No. 1 Takenaka Corporation, Tokyo Main Store (72) Inventor Masahiro Matsuba 8-21 Ginza, Chuo-ku, Tokyo Inside, Takenaka Corporation Tokyo Main Store (72) Inventor Norio Hasegawa Tsurumi-ku, Yokohama, Kanagawa 11-1 Daikokucho Tokyo Electric Power Company Yokohama Thermal Power Plant (72) Inventor 1-3-1 Uchisaiwaicho, Chiyoda-ku, Tokyo TEPCO (72) Inventor Kazuhide Yamauchi 2-1-1, Uchisaiwai-cho, Chiyoda-ku, Tokyo TEPCO Design Co., Ltd. (72) Inventor Fumihiro Ishikawa 2-1-1, Uchisaiwai-cho, Chiyoda-ku, Tokyo TEPCO Design Inc. (72) Inventor Noboru Nishigaki Miyachi Construction Industry Co., Ltd., 1-13-15 Kita-Otsuka, Toshima-ku, Tokyo (56) References JP-A-2-8432 (JP, A) JP-A-58-6025 (JP) , B1) (58) Field surveyed (Int. Cl. 7 , DB name) E04G 21/14 E04B 1/35 E04H 5/02

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 天井走行クレーンを有する建屋に於ける
先行建方の柱壁鉄骨に設置されたクレーンガーダーに、
鉄骨建方構台、鉄骨建方以後の後作業用足場、上下作業
を可能とする防護構台、下部工事の為の揚重設備基盤の
役を果たすトラベリングステージを仮設し、しかる後、
この仮設のトラベリングステージを移動させながら一括
若しくは分割建方の梁トラス仕口合せ等の前記の諸作業
を順次とり行なうとしたことを特徴とする天井走行クレ
ーンを有する建屋に於ける梁トラス建方方法。
1. A crane girder installed on a column wall steel frame of a preceding building in a building having an overhead traveling crane,
Temporarily set up a steel frame erected gantry, a scaffold for post-work after the steel frame erection, a protective gantry that allows up and down work, and a traveling stage that serves as a lifting equipment base for substructure work.
A beam truss construction method in a building having an overhead traveling crane, wherein the above-mentioned various operations such as beam truss jointing in a lump or divided construction are sequentially performed while moving the temporary traveling stage. Method.
【請求項2】 トラベリングステージを本設の天井走行
クレーンを利用してこれに連結構成するとした請求項1
記載の天井走行クレーンを有する建屋に於ける梁トラス
建方方法。
2. A traveling stage connected to a traveling stage using a permanent overhead traveling crane.
A method for building a beam truss in a building having the overhead traveling crane according to the above.
【請求項3】 主枠若しくは天井走行クレーンに懸け渡
した締結材でトラス梁セットのムクリを強制的に先行建
込みの梁トラス先端レベルにたわませ、かかる状態のも
とでつなぎ部接続を、ブレース同寸法にてとり行なうと
した請求項2記載の天井走行クレーンを有する建屋に於
ける梁トラス建方方法。
3. A truss beam set is forcibly deflected to a leading truss tip level by a fastening material suspended on a main frame or an overhead traveling crane, and under such a condition, a connection portion is connected. 3. The method for constructing a beam truss in a building having an overhead traveling crane according to claim 2, wherein the brace has the same dimensions.
JP5316328A 1992-12-16 1993-12-16 Construction method of beam truss in building with overhead traveling crane Expired - Lifetime JP3049300B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5316328A JP3049300B2 (en) 1992-12-16 1993-12-16 Construction method of beam truss in building with overhead traveling crane

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP35459292 1992-12-16
JP4-354592 1992-12-16
JP5316328A JP3049300B2 (en) 1992-12-16 1993-12-16 Construction method of beam truss in building with overhead traveling crane

Publications (2)

Publication Number Publication Date
JPH07150767A JPH07150767A (en) 1995-06-13
JP3049300B2 true JP3049300B2 (en) 2000-06-05

Family

ID=26568620

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5316328A Expired - Lifetime JP3049300B2 (en) 1992-12-16 1993-12-16 Construction method of beam truss in building with overhead traveling crane

Country Status (1)

Country Link
JP (1) JP3049300B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102409864B (en) * 2011-11-14 2014-04-09 中建钢构有限公司 Steel truss construction method and temporary reinforcing device used in hoisting process of same
KR101254621B1 (en) * 2012-12-24 2013-04-15 원인복 Construction method of office-factory composite building and structure thereby
CN103774856B (en) * 2014-01-24 2017-05-31 江苏沪武建设集团有限公司 A kind of gliding construction method of different shape heavy type girder steel of large span on Super High roofing
CN104866659B (en) * 2015-05-13 2018-09-18 江苏新蓝天钢结构有限公司 Steel construction integral hoisting method based on BIM
CN107355003B (en) * 2017-06-15 2020-04-07 上海二十冶建设有限公司 Modular construction method of large-span ultra-wide overweight truss
CN110002343B (en) * 2019-04-26 2024-05-10 青岛长永机械工程有限公司 Self-driven urban underground prefabricated comprehensive pipe gallery laying hoisting machine and construction method

Also Published As

Publication number Publication date
JPH07150767A (en) 1995-06-13

Similar Documents

Publication Publication Date Title
AU2010346421B2 (en) Scaffold and methods for installing or removing such a scaffold
JP2928948B2 (en) Construction method of large span roof
EP0480683B1 (en) Erection workbench and construction process
JP3049300B2 (en) Construction method of beam truss in building with overhead traveling crane
JP3069835B2 (en) Uchigumi scaffold structure
JP2745004B2 (en) Steel construction method
JP2942879B2 (en) Temporary house for all-weather construction
JP2874576B2 (en) Moving scaffold for retaining wall construction
JP2529067B2 (en) Crane flexible climbing method
JP3100574B2 (en) Suspended scaffold and its erection method
JP2779258B2 (en) Roof lift-up method
JP2876991B2 (en) Steel frame method for high-rise buildings
JP3214407B2 (en) Connection method of beam members and scaffolding equipment for work at height
JP2776128B2 (en) Lifting device for building frame
JP2690822B2 (en) Steel construction method for low-rise buildings
JPH0240064Y2 (en)
JP3848758B2 (en) Construction method for direct suspension of structures
JP3002054U (en) Tower crane with multiple main columns as tower mast
JP2634271B2 (en) Jack-up method and device
JPH0714007U (en) Curing net for construction work
JP2776140B2 (en) Temporary beam assembly equipment for building construction
JPH0475337B2 (en)
JPH11158817A (en) Balancing erection construction for bridge at height and transferable slinging lifting device therefor
JPH04297665A (en) Erection-working base for construction of structure
JP2000080794A (en) Construction method for temporary working scaffold- cum-working platform

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R370 Written measure of declining of transfer procedure

Free format text: JAPANESE INTERMEDIATE CODE: R370

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090331

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090331

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100331

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100331

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110331

Year of fee payment: 11

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120331

Year of fee payment: 12

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120331

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130331

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130331

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140331

Year of fee payment: 14

EXPY Cancellation because of completion of term