JP2634271B2 - Jack-up method and device - Google Patents

Jack-up method and device

Info

Publication number
JP2634271B2
JP2634271B2 JP712290A JP712290A JP2634271B2 JP 2634271 B2 JP2634271 B2 JP 2634271B2 JP 712290 A JP712290 A JP 712290A JP 712290 A JP712290 A JP 712290A JP 2634271 B2 JP2634271 B2 JP 2634271B2
Authority
JP
Japan
Prior art keywords
jack
columns
equipment
lifting
assembled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP712290A
Other languages
Japanese (ja)
Other versions
JPH03212564A (en
Inventor
壱州 山下
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Heavy Industries Ltd
Original Assignee
Mitsubishi Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Heavy Industries Ltd filed Critical Mitsubishi Heavy Industries Ltd
Priority to JP712290A priority Critical patent/JP2634271B2/en
Publication of JPH03212564A publication Critical patent/JPH03212564A/en
Application granted granted Critical
Publication of JP2634271B2 publication Critical patent/JP2634271B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、例えば火力発電用、その他ボイラなどの据
付けに適用されるジャッキアップ方法および装置に関す
る。
Description: BACKGROUND OF THE INVENTION The present invention relates to a jack-up method and apparatus applied for installation in, for example, thermal power generation and other boilers.

〔従来の技術〕[Conventional technology]

従来の機器のジャッキアップ工法としては例えば特開
昭62−185964号(特願昭61−27969号)に記載の工法な
どがある。第10図はその工法の説明図である。図におい
て、本工法は第10図に示すように多数柱による支持架構
を建てた後、予め地上で一体に組まれたトップ梁のみを
トップ梁の所定の位置に設定し、それから据付けようと
する各機器を単体または小ブロックに分解してクレーン
またはウインチなどで地上から所定の場所に吊揚げて据
付けるものである。
As a conventional jack-up method for equipment, there is, for example, a method described in JP-A-62-185964 (Japanese Patent Application No. 61-27969). FIG. 10 is an explanatory view of the method. In the figure, this method is to build a support frame with many columns as shown in Fig. 10, then set only the top beam that has been integrated on the ground in advance to the predetermined position of the top beam, and then try to install it Each device is disassembled into a single unit or a small block, and is lifted to a predetermined place from the ground by a crane or a winch and installed.

〔発明が解決しようとする課題〕[Problems to be solved by the invention]

上記のように、従来の機器のジャッキアップ工法にお
いてはトップ梁を所定の位置に設置した後、各機器を単
体または小ブロックにて吊揚げ、高所で据付けている。
この場合、トップ梁と各機器とを予め地上で一体にして
吊揚げることができれば作業が捗るのであるが、一体に
して吊揚げられない理由は吊揚げ時の支持架構が片持梁
のために不安定であり、吊揚げ荷重に制限があるからで
ある。このために作業の能率が悪く、また作業の危険性
が高い。
As described above, in the conventional jack-up method of equipment, after the top beam is installed at a predetermined position, each equipment is lifted by a single unit or a small block and installed at a high place.
In this case, if the top beam and each device can be lifted integrally on the ground in advance, the work will progress.However, the reason why the lifting cannot be performed integrally is that the support frame at the time of lifting is because the cantilever is used. This is because it is unstable and the lifting load is limited. For this reason, work efficiency is low, and work risk is high.

〔課題を解決するための手段〕[Means for solving the problem]

本発明に係るジャッキアップ方法は上記課題の解決を
目的にしており、各節ごとに分解可能な複数の組立て柱
を互いに間隔を設けて建て、上記組立て柱内に梁の両端
をそれぞれ挿入し、上記組立て柱を各節ごとに分解およ
び復旧しながら上記組立て柱に装着した揚上装置により
上記梁の両端をジャッキアップすることを特徴としてい
る。
The jack-up method according to the present invention is aimed at solving the above-described problem, and a plurality of disassembly columns that can be disassembled for each node are installed at intervals, and both ends of the beam are inserted into the assembly columns, respectively. Both ends of the beam are jacked up by a lifting device mounted on the assembly column while disassembling and restoring the assembly column for each node.

また、本発明に係るジャッキアップ装置は、互いに間
隔を設けて建てられ各節ごとに分解可能な複数の組立て
柱と、両端がそれぞれ上記複数の組立て柱内に挿入され
た梁と、上記複数の組立て柱にそれぞれ装着され、上記
梁の両端をジャッキアップする揚上装置とを備えたこと
を特徴としている。
In addition, the jack-up device according to the present invention includes a plurality of assembled columns that are built at intervals from each other and that can be disassembled for each node, beams whose both ends are respectively inserted into the plurality of assembled columns, A lifting device that is mounted on each of the assembling columns and jacks up both ends of the beam.

〔作用〕[Action]

即ち、本発明に係るジャッキアップ方法および装置に
おいては、各節ごとに分解可能な複数の組立て柱にそれ
ぞれ揚上装置を装着し、この揚上装置により複数の組立
て柱内にそれぞれ入した梁の両端を組立て柱を各節ごと
に分解および復旧しながらジャッキアップするようにし
ており、梁の両端が組立て柱内に挿入されているので支
持架構に対する偏心荷重がなくなって安定し、例えば梁
および梁に据付ける各機器を予め地上で一体にしてジャ
ッキアップすることも可能である。
That is, in the jack-up method and apparatus according to the present invention, a lifting device is attached to each of a plurality of disassembled columns that can be disassembled for each node, and the lifting devices are used to remove beams that are respectively inserted into the plurality of assembled columns. Both ends are assembled so that jacks are jacked up while disassembling and restoring columns at each node.Because both ends of the beam are inserted into the assembled columns, eccentric loads on the support frame are eliminated and it is stable, for example, beams and beams It is also possible to jack up the equipment to be installed on the ground beforehand.

〔実施例〕〔Example〕

第1図乃至第9図は本発明の一実施例に係る機器のジ
ャッキアップ工法の説明図である。図において、本実施
例に係る機器のジャッキアップ工法は火力発電用ボイラ
の据付けに適用されており、先ず第1図に示すように4
本組立て柱1およびトラスガーダー2を地上で組立てて
支持架構を建てる。次いで、第2図に示すようにトップ
大梁3の両端をこの支持架構の4本組立て柱1内に内側
のブレースを取外して挿入し、トップ梁4をトップ大梁
3に固定した後このトップ梁4に吊棒受梁5を取付け
る。次に、第3図に示すように予め地上で組立てられた
トップ梁4を4本組立て柱1の中途に設置したウインチ
およびワイヤで中間階から吊揚げ、トップ大梁3の下部
にジャッキアップ用のロッド受梁6を取付ける。また、
上部には雨水よけの仮設屋根7を取付ける。そして、第
4図に示すように4本組立て柱1のトップにジャッキア
ップ装置8を取付け、ジャッキアップ用ロッド9を4本
組立て柱1内に挿入する。
FIG. 1 to FIG. 9 are illustrations of a jack-up method for equipment according to one embodiment of the present invention. In the figure, the jack-up method for equipment according to the present embodiment is applied to the installation of a boiler for thermal power generation, and first, as shown in FIG.
The assembling columns 1 and the truss girder 2 are assembled on the ground to build a support frame. Next, as shown in FIG. 2, both ends of the top girders 3 are removed and inserted into the four-assembly columns 1 of the support frame, and the top girders 4 are fixed to the top girders 3 and then inserted. Attach the hanging bar receiver 5 to Next, as shown in FIG. 3, four top beams 4 pre-assembled on the ground are lifted from the middle floor by a winch and a wire installed in the middle of the four assembling columns 1, and jack-ups are provided under the top girders 3. Attach the rod support 6. Also,
A temporary roof 7 for rainwater protection is mounted on the upper part. Then, as shown in FIG. 4, a jack-up device 8 is attached to the top of the four-post assembly column 1, and the four jack-up rods 9 are inserted into the four-post assembly column 1.

このようにセットした後、第5図に示すように4本組
立て柱1の内側のブレース10および継ぎ材を順次取外す
とともに復旧しながら、トップ梁4をジャッキアップ装
置8により徐々に吊揚げ、トップ梁4に機器吊棒11を取
付ける。次いで、第6図乃至第8図に示すようにトップ
梁4を吊揚げながら機器の上部12、中間部13、下部14を
それぞれ据付けて行く。なお、第6図(b)に示すよう
に正面方向の点線で表わすトラスガーダー2はトップ梁
4を吊揚げる際の障害となるので取外しておき、トップ
梁4の吊揚げ後に取付ける。4本組立て柱1はトラスガ
ーダー2外側の鉄骨で補強されているので転倒は防止さ
れる。また、一点鎖線で表わす4本組建て柱1の内側の
ブレース10は、トップ大梁3の通過時のみ取外す。ま
た、機器の各部12,13,14は小ブロックにしてトラスガー
ター2の開口部から支持架構内に搬入し、中ブロックに
組立てる。そして、第8図に示すようにトップレベルに
トップ梁4を設定してトップ大梁3の支持梁15を規定の
位置に取付け、トップ大梁3をジャッキダウンした後ジ
ャッキアップ用のロッド受梁6を取外す。最後に、第9
図に示すようにジャッキアップ装置8を取外し、仮設屋
根7も撤去する。
After setting in this manner, the top beam 4 is gradually lifted by the jack-up device 8 while the brace 10 and the joint material inside the four-assembly column 1 are sequentially removed and restored as shown in FIG. Attach the equipment hanging rod 11 to the beam 4. Next, as shown in FIGS. 6 to 8, the upper part 12, the middle part 13, and the lower part 14 of the equipment are installed while lifting the top beam 4. As shown in FIG. 6 (b), the truss girder 2 indicated by a dotted line in the front direction is obstructed when the top beam 4 is lifted, so it is removed and attached after the top beam 4 is lifted. Since the four assembling columns 1 are reinforced by the steel frame outside the truss girder 2, overturning is prevented. In addition, the brace 10 inside the four-piece column 1 indicated by the chain line is removed only when the top girders 3 pass. Each part 12, 13 and 14 of the equipment is made into a small block, carried into the support frame from the opening of the truss garter 2, and assembled into a middle block. Then, as shown in FIG. 8, the top beam 4 is set at the top level, the support beam 15 of the top beam 3 is mounted at a specified position, the top beam 3 is jacked down, and the jack up rod receiving beam 6 is moved. Remove. Finally, the ninth
As shown in the figure, the jack-up device 8 is removed, and the temporary roof 7 is also removed.

第10図に示す従来の支持架構においては、吊揚げ時に
多数柱が片持梁となるために支持架構に偏心荷重が掛っ
て不安定となり、吊揚げ時の荷重が制限されるが、本工
法においては4本組立て柱1内にトップ大梁3を挿入す
ることにより支持架構に偏心荷重が掛からなくなり、ト
ップ梁4とトップ梁4に据付けられる各機器とを一体に
してジャッキアップし、据付けることが可能となる。こ
れにより、支持架構の地上における組込みが可能とな
り、立柱から機器の据付け開始までの期間が短縮され
る。また、各機器の据付け作業が地上で行えるために作
業能率がアップするとともに、作業が安定し安全とな
る。また、地上において組立てる際にトップ梁4の上部
に仮設屋根7を設置できるので雨天時の作業が可能とな
り、据付工程の短縮が行える。また、トップ梁4および
各機器全体を吊揚げるためのジャッキアップ装置8は必
要であるが、従来の工法において機器単体または小ブロ
ックを吊揚げる大型クレーン,ウインチなどの装置が不
要となる。
In the conventional supporting frame shown in FIG. 10, the eccentric load is applied to the supporting frame due to the multiple columns being cantilevered during lifting, and the supporting frame becomes unstable, and the load during lifting is limited. In the above, the eccentric load is not applied to the supporting frame by inserting the top girders 3 into the four-assembly columns 1, and the top beam 4 and each device installed on the top beam 4 are jacked up integrally and installed. Becomes possible. As a result, the support frame can be installed on the ground, and the period from the upright to the start of installation of the device can be shortened. In addition, since the installation work of each device can be performed on the ground, the work efficiency is improved, and the work is stable and safe. In addition, since the temporary roof 7 can be installed above the top beam 4 when assembling on the ground, work in rainy weather becomes possible, and the installation process can be shortened. In addition, although the jack-up device 8 for lifting the top beam 4 and each device as a whole is required, the conventional construction method does not require a device such as a large crane or a winch for lifting a single device or a small block.

〔発明の効果〕〔The invention's effect〕

本発明に係るジャッキアップ方法および装置は前記の
通りであり、梁および梁に据付ける各機器を予め地上で
一体にしてジャッキアップすることが可能であるので、
作業の能率がアップするとともに、作業の危険性が減少
する。
The jack-up method and apparatus according to the present invention are as described above, and it is possible to jack up the beam and each device to be installed on the beam integrally on the ground in advance,
The work efficiency is improved and the danger of the work is reduced.

【図面の簡単な説明】[Brief description of the drawings]

第1図乃至第9図は本発明の一実施例に係る機器のジャ
ッキアップ工法の説明図で第1図(a)、第2図
(a)、第3図乃至第5図、第6図(a)、第7図、第
8図(a)、第9図(a)はそれぞれ支持架構の側面
図、第1図(b)および第9図(b)は正面図、第2図
(b)、第8図(b)は平面図、第1図(c)は同図
(a)におけるc−c断面図、第6図(b)は同図
(a)におけるb−b断面図、第10図は従来の機器のジ
ャッキアップ工法の説明図で同図(a)は支持架構の正
面図、同図(b)は側面図、同図(c)は平面図であ
る。 1……4本組立て柱、2……トラスガーダー、 3……トップ大梁、4……トップ梁、 5……吊棒受梁、6……ロッド受梁、 7……仮設屋根、8……ジャッキアップ装置、 9……ロッド、10……ブレース、 11……機器吊棒、12……機器の上部、 13……機器の中間部、14……機器の下部、 15……支持梁。
1 to 9 are explanatory views of a jack-up method for equipment according to an embodiment of the present invention, and are shown in FIGS. 1 (a), 2 (a), 3 to 5 and 6, and FIGS. (A), FIG. 7, FIG. 8 (a), FIG. 9 (a) are side views of the support frame, FIG. 1 (b) and FIG. 9 (b) are front view, FIG. b), FIG. 8 (b) is a plan view, FIG. 1 (c) is a sectional view taken along line cc in FIG. 1 (a), and FIG. 6 (b) is a sectional view taken along line bb in FIG. FIG. 10 is an explanatory view of a conventional jack-up method for equipment, wherein FIG. 10 (a) is a front view of a support frame, FIG. 10 (b) is a side view, and FIG. 10 (c) is a plan view. 1 ... 4 pillars, 2 ... truss girder, 3 ... top girders, 4 ... top beams, 5 ... hanging rod beams, 6 ... rod beams, 7 ... temporary roof, 8 ... Jack-up device, 9… Rod, 10… Brace, 11… Equipment hanging rod, 12 …… Equipment upper part, 13 …… Equipment middle part, 14 …… Equipment lower part, 15 …… Support beam.

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】各節ごとに分解可能な複数の組立て柱を互
いに間隔を設けて建て、上記組立て柱内に梁の両端をそ
れぞれ挿入し、上記組立て柱を各節ごとに分解および復
旧しながら上記組立て柱に装着した揚上装置により上記
梁の両端をジャッキアップすることを特徴とするジャッ
キアップ方法。
1. A plurality of assembled columns that can be disassembled for each node are spaced apart from each other, and both ends of the beam are inserted into the assembled columns, and the assembled columns are disassembled and restored for each node. A jack-up method, wherein both ends of the beam are jacked up by a lifting device mounted on the assembly column.
【請求項2】互いに間隔を設けて建てられ各節ごとに分
解可能な複数の組立て柱と、両端がそれぞれ上記複数の
組立て柱内に挿入された梁と、上記複数の組立て柱にそ
れぞれ装着され上記梁の両端をジャッキアップする揚上
装置とを備えたことを特徴とするジャッキアップ装置。
2. A plurality of assembling columns which are spaced apart from each other and can be disassembled at each node, a beam having both ends inserted into the plurality of assembling columns, respectively, and mounted on the plurality of assembling columns respectively. A jack-up device comprising a lifting device for jacking up both ends of the beam.
JP712290A 1990-01-18 1990-01-18 Jack-up method and device Expired - Fee Related JP2634271B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP712290A JP2634271B2 (en) 1990-01-18 1990-01-18 Jack-up method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP712290A JP2634271B2 (en) 1990-01-18 1990-01-18 Jack-up method and device

Publications (2)

Publication Number Publication Date
JPH03212564A JPH03212564A (en) 1991-09-18
JP2634271B2 true JP2634271B2 (en) 1997-07-23

Family

ID=11657271

Family Applications (1)

Application Number Title Priority Date Filing Date
JP712290A Expired - Fee Related JP2634271B2 (en) 1990-01-18 1990-01-18 Jack-up method and device

Country Status (1)

Country Link
JP (1) JP2634271B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007107787A (en) * 2005-10-12 2007-04-26 Babcock Hitachi Kk Installation method of boiler facility

Also Published As

Publication number Publication date
JPH03212564A (en) 1991-09-18

Similar Documents

Publication Publication Date Title
JP2928948B2 (en) Construction method of large span roof
EP0480683A1 (en) Erection workbench and construction process
JP2634271B2 (en) Jack-up method and device
JP2927320B2 (en) How to assemble a large hanging boiler
JP3049300B2 (en) Construction method of beam truss in building with overhead traveling crane
JPH04353105A (en) Erecting method for bridge girder
JPH1061193A (en) Method of building steel frame structure and device therefor
JPH0387503A (en) Assembling method of steam generator provided with steam boiler
JPH10280543A (en) Construction method of dome-like roof
JP2946074B2 (en) Large roof erection method
JP2529067B2 (en) Crane flexible climbing method
JPH06101348A (en) Method for constructing tower
JP2871468B2 (en) How to build a building
JP3546225B2 (en) How to build building structures
JP3368483B2 (en) Bridge pier construction method
JP3139854B2 (en) Collapse prevention frame
JP2876991B2 (en) Steel frame method for high-rise buildings
JP2994205B2 (en) Structural assembly method
JP2776140B2 (en) Temporary beam assembly equipment for building construction
JPS6152305B2 (en)
JPH0959924A (en) Slab form construction method
JP2653630B2 (en) How to raise the temporary roof
JPH04247176A (en) Level raising method of steel tower for power-transmission
SU724669A1 (en) Method of erecting a vertical structure
AU600833B2 (en) A method of building structures

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees