JP2928948B2 - Construction method of large span roof - Google Patents
Construction method of large span roofInfo
- Publication number
- JP2928948B2 JP2928948B2 JP2228962A JP22896290A JP2928948B2 JP 2928948 B2 JP2928948 B2 JP 2928948B2 JP 2228962 A JP2228962 A JP 2228962A JP 22896290 A JP22896290 A JP 22896290A JP 2928948 B2 JP2928948 B2 JP 2928948B2
- Authority
- JP
- Japan
- Prior art keywords
- roof
- large span
- span roof
- pillars
- temporary
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【発明の詳細な説明】 「産業上の利用分野」 この発明は、大規模展示場や多目的ホールあるいは競
技場などの屋根として好適な大スパン屋根の施工法に関
する。The present invention relates to a method for constructing a large span roof suitable as a roof for a large-scale exhibition hall, a multipurpose hall, a stadium, and the like.
「従来の技術」 近年、広大な空間を確保することのできる大スパン屋
根の施工が種々実施されている。従来の施工法として
は、大スパン屋根を予め揚重クレーンの揚重能力や作業
スペースなどを考慮した大きさ及び重量のユニットに予
め分割して地上で大組みしておき、ついで各屋根ユニッ
トの架設位置に仮設支柱または本設柱を立て、大組みし
た各屋根ユニットを揚重クレーンにより吊り上げて所定
の仮設支柱または本設往の柱頭間に架設し、全ての屋根
ユニットを組み上げるようにしている。そして、屋根ユ
ニット全体を接合後、仮設支柱を撤去し、その後屋根の
外表面に仕上げ用屋根材を貼りるようにしている。[Background Art] In recent years, various constructions of large span roofs capable of securing a vast space have been implemented. As a conventional construction method, large-span roofs are divided in advance into units of size and weight that take into account the lifting capacity of crane cranes and work space, and assembled large on the ground. Temporary columns or main columns are erected at the erection position, and each large roof unit is lifted by a lifting crane and erected between predetermined temporary columns or capitals of the main column, and all roof units are assembled. . Then, after joining the entire roof unit, the temporary support columns are removed, and then a finishing roof material is attached to the outer surface of the roof.
「発明が解決しようとする課題」 しかしながら、上記従来の施工法によれば、揚重する
屋根ユニットの全てに対して架設範囲に仮設支柱を立て
ておく必要があり、立てる仮設支柱の本数が多数とな
り、使用する鉄骨量も膨大となるなど、仮設設備や仮設
費用が多大となっていた。したがって、それらの点は施
工費用の削減を図る上での阻害要因となっていた。However, according to the above-mentioned conventional construction method, it is necessary to set up temporary supports in the installation area for all the roof units to be lifted, and the number of temporary supports to be set up is large. As a result, the amount of steel frames used becomes enormous, so that temporary facilities and temporary construction costs are large. Therefore, those points have been a hindrance in reducing the construction cost.
また、屋根仕上げ材は屋根ユニットの全体の組み上げ
が終了した時点で別途に施工され、それ以前は同時に施
工することができないため、工期の短縮化を有効に図る
ことができなかった。In addition, the roof finishing material is separately constructed when the entire assembly of the roof unit is completed, and cannot be performed simultaneously before that, so that it was not possible to effectively shorten the construction period.
また、大スパン屋根の吊り上げ中に大スパン屋根が風
や地震等の水平力を受けると、大スパン屋根が振動し
て、大スパン屋根が支柱に衝突したり、リフトアップ作
業に支障をきたす恐れがあり、さらには大スパン屋根の
吊り上げ終了後、大スパン屋根の長時間の吊り下げ状態
時において、地震時には大スパン屋根の屋根重量に応じ
た地震力がまともに支柱に加わるため、仮設支柱設計用
の地震力が大きくなる問題があった。In addition, if the large span roof receives horizontal force such as wind or earthquake while the large span roof is being lifted, the large span roof may vibrate, causing the large span roof to collide with the column or hinder the lifting work. In addition, after the lifting of the large span roof, if the large span roof is suspended for a long time, the seismic force according to the roof weight of the large span roof is added to the pillars in the event of an earthquake. There was a problem that the seismic force for use became large.
この発明は、上記事情に鑑みてなされたもので、地上
で組んだ大スパン屋根を安全にかつ効率よくリフトアッ
プさせることができ、仮設作業の省力化を図るととも
に、大スパン屋根の施工費用の低減化および工期の短縮
化を図ることのできる大スパン屋根の施工法を提供する
ことを目的としている。The present invention has been made in view of the above circumstances, and it is possible to safely and efficiently lift a large-span roof assembled on the ground, to save labor for temporary work, and to reduce the construction cost of a large-span roof. It is an object of the present invention to provide a method for constructing a large span roof that can reduce the time and the construction period.
「課題を解決するための手段」 この発明にかかる大スパン屋根の施工法は、大スパン
屋根をその架設範囲で地組みし、ついで地組みした大ス
パン屋根を仮設の支柱に沿って吊り上げ、さらに本設の
外周柱相互に大スパン屋根を降ろしてその間に架設する
ようにした大スパン屋根の施工法であって、前記大スパ
ン屋根の吊り上げを、上下に受梁を有するステップロッ
ドを大スパン屋根に係止してこれをジャッキアップする
ことにより行い、前記ステップロッドの上下の受梁にバ
ックアップ用の吊材の上下端が連結したことを特徴とし
ている。"Means for solving the problem" The method for constructing a large span roof according to the present invention is to lay the large span roof in the erection range, and then lift the grounded large span roof along the temporary columns, A method for constructing a large-span roof in which a large-span roof is lowered between main pillars and erected between the main-span pillars. In this case, the upper and lower ends of the backup hanging member are connected to upper and lower receiving beams of the step rod.
また、本発明の大スパン屋根の施工法は、大スパン屋
根を外周柱相互に降ろす前に、吊り上げた状態の大スパ
ン屋根を対応する外周柱の柱頭部に仮定着させておくこ
とを特徴としている。Further, the method for constructing a large span roof according to the present invention is characterized in that, before lowering the large span roof to the outer peripheral columns, the suspended large span roof is assumed to be attached to the capital of the corresponding outer peripheral column. I have.
また、本発明の大スパン屋根の施工法は、各支柱とこ
れに面する大スパン屋根の一部との間に、大スパン屋根
の吊り上げ中に大スパン屋根が支柱に衝突する時の衡撃
力を吸収するガイド機溝を設け、当該ガイド機構に沿っ
て大スパン屋根を吊り上げるようにしたことを特徴とし
ている。In addition, the method for constructing a large span roof according to the present invention is characterized in that the striking between the strut and a part of the large span roof facing the strut when the large span roof collides with the strut while the large span roof is being lifted. It is characterized in that a guide machine groove for absorbing a force is provided, and a large span roof is lifted along the guide mechanism.
また、本発明の大スパン屋根の施工法は、大スパン屋
根を吊り上げた以降、外周柱を本設するまでの間、各支
柱とこれに面する大スパン屋根の一部との間に設けたス
ラストサポートにより大スパン屋根の水平方向への挙動
を拘束しておくことを特徴としている。Further, the method for constructing a large span roof according to the present invention is provided between each support and a part of the large span roof facing the same until the outer pillar is permanently installed after the large span roof is lifted. The feature is that the horizontal movement of the large span roof is restricted by the thrust support.
「作用」 大スパン屋根の吊り上げを、上下に受梁を有するステ
ップロッドを大スパン屋根に係止してこれをジャッキア
ップすることにより行い、前記ステップロッドの上下の
受梁にバックアップ用の吊材の上下端を連結することに
より、大スパン屋根の吊り上げ以降から外周柱を建方す
るまでの間の吊り下げ状態において、万一ステップロッ
ドが金属疲労や風力や地震力により破断する事態が生じ
ても吊材によりバックアップ体制を取り、大スパン屋根
の落下事故対策を取ることができる。[Operation] Lifting of the large span roof is performed by locking a step rod having a support beam on the upper and lower sides to the large span roof and jacking it up. By connecting the upper and lower ends of the large-roof roof, the step rod may break due to metal fatigue, wind force or seismic force in the suspended state from the lifting of the large span roof to the construction of the outer pillar. Also, a back-up system can be provided with hanging materials to take measures against a large-span roof falling accident.
また、大スパン屋根を外周柱相互に降ろす前に、吊り
上げた状態の大スパン屋根を対応する外周柱の柱頭部に
仮定着させておくことにより、外周柱建方時に突風など
により外周柱の自由端側が大きく変形して倒壊したりす
ることなく、大スパン屋根をジャッキダウンさせて外周
柱の柱頭部との精度のよい接合が可能となる。これによ
り外周柱の柱頭部相互に対する大スパン屋根の納まりが
よくなる。Also, before lowering the large-span roof to the outer pillars, the suspended large-span roof is assumed to be attached to the capital of the corresponding outer pillars, so that the outer pillars can be freely released due to gusts etc. The large-span roof can be jacked down without any significant deformation of the end side and collapsing, and accurate joining with the column cap of the outer peripheral column becomes possible. Thereby, the fit of the large span roof with respect to the column caps of the outer peripheral columns is improved.
また、各支柱とこれに面する大スパン屋根の一部との
間に、大スパン屋根の吊り上げ中に大スパン屋根が支柱
に衡突する時の衡撃力を吸収できるガイド機構を設け、
このガイド機構に沿って大スパン屋根を吊り上げること
により、大スパン屋根の吊り上げ時において支柱と大ス
パン屋根との衡突によるねじれや変形、支柱に対する多
大な水平力が加わることを防止できる。In addition, between each strut and a part of the large span roof facing it, a guide mechanism that can absorb the striking force when the large span roof collides with the strut during lifting of the large span roof,
By lifting the large span roof along this guide mechanism, it is possible to prevent a torsion or deformation due to a balance between the support and the large span roof and a large horizontal force on the support when the large span roof is lifted.
また、大スパン屋根を吊り上げた以降、外周柱を本設
するまでの間、各支柱とこれに面する大スパン屋根の一
部との間に設けたスラストサポートにより大スパン屋根
の水平方向への挙動を拘束しておくことにより、長期に
わたる外周柱の建方時において、地震が起きた場合に大
スパン屋根の振れ止め防止対策を取ることができる。In addition, after the large span roof is lifted, the thrust support provided between each strut and a part of the large span roof facing it is used for horizontal extension of the large span roof until the outer pillars are installed. By constraining the behavior, it is possible to take measures to prevent a large span roof from swaying in the event of an earthquake during the long-term construction of the outer pillar.
「実施例」 以下、図面を参照して本発明の一実施例を説明する。Hereinafter, an embodiment of the present invention will be described with reference to the drawings.
本発明にかかる大スパン屋根の施工法は、屋根(大ス
パン屋根)1の架設範囲に仮設柱2および本設柱3を立
てるとともに、これらの仮設柱2、本設柱3に支持させ
る形で大スパン屋根1を地組みし、ついで地組みした大
スパン屋根1を仮設支柱6に沿って吊り上げ、さらに外
周柱4を本設するとともに、大スパン屋根1を外周柱4
相互に降ろしてその間に架設し、しかる後、仮設支柱6
を撤去して屋根1を施工することを基本方法としてい
る。The method for constructing a large span roof according to the present invention is to form a temporary pillar 2 and a permanent pillar 3 in an installation area of a roof (large span roof) 1 and to support the temporary pillar 2 and the permanent pillar 3 on the temporary pillar 2 and the permanent pillar 3. The large span roof 1 is laid on the ground, and then the large span roof 1 is lifted along the temporary support columns 6, and the outer peripheral columns 4 are permanently installed.
Lowering each other, erection between them, and then temporary support 6
The basic method is to remove the roof and construct the roof 1.
以下、第1図ないし第4図などに従い屋根1の施工手
順を説明する。Hereinafter, the construction procedure of the roof 1 will be described with reference to FIG. 1 to FIG.
[仮設柱・本設柱その他の建方] 第1図に示すように、まず屋根1の架設範囲に下部構
造体である所望の仮設柱2および本設柱3の建方を行
う。同様に屋根1の地組み時に屋根1を各仮設柱2およ
び本設柱3とともに支持する鉄骨サポート柱5と、屋根
1をリフトアップするための仮設支柱6との建方を行
う。前記仮設支柱6は第5図に示すように架設範囲内の
6箇所に立てるとともに、それぞれの仮設支柱6…は荷
揚げ用のタワークレーン7の架台も兼用する。[Temporary Pillars, Permanent Pillars, and Other Construction Methods] First, as shown in FIG. 1, desired temporary pillars 2 and permanent pillars 3, which are lower structures, are constructed in the construction area of the roof 1. Similarly, when the roof 1 is laid, the steel support columns 5 for supporting the roof 1 together with the temporary columns 2 and the main columns 3 and the temporary columns 6 for lifting up the roof 1 are constructed. As shown in FIG. 5, the temporary supports 6 are erected at six locations within the erection range, and each temporary support 6 also serves as a platform for a tower crane 7 for unloading.
[屋根鉄骨トラスの地組および仕上げ] ついで、第2図に示すように、屋根1の躯体を構成す
る屋根鉄骨トラス8について所定の高さで仮設柱2、鉄
骨サポート柱5、本設柱3の上で地組みを行う。この時
点での屋根鉄骨トラス8の重量は全て仮設柱2、鉄骨サ
ポート柱5、および本設柱3により支持する。[Structure and Finish of Roof Steel Frame Truss] Next, as shown in FIG. 2, a temporary column 2, a steel frame support column 5, and a permanent column 3 of a roof steel truss 8 constituting a frame of the roof 1 at a predetermined height. Perform terrain on. At this time, the weight of the roof steel truss 8 is all supported by the temporary columns 2, the steel support columns 5, and the permanent columns 3.
またこの時点で屋根鉄骨トラス8に対しては、外板や
ステンレス防水等の屋根仕上げ材を施し、トップライト
9その他の取付けも同時に施工する。一方、各仮説文柱
6…の上面には屋根1をリフトアップするためのジャッ
キ10をそれぞれ設置する。At this time, the roof steel truss 8 is provided with a roof finishing material such as an outer plate or stainless steel waterproofing, and the top light 9 and other components are simultaneously installed. On the other hand, jacks 10 for lifting up the roof 1 are installed on the upper surfaces of the hypothetical posts 6, respectively.
[屋根のリフトアップ] 屋根1の屋根鉄骨トラス8には、第6図および第7図
に示すように屋根1を吊り上げるためのステップロッド
11を取り付ける。このステップロッド11は上下に屋根鉄
骨トラス8を挾む受梁12、13を備えたもので、上部受梁
12にはジャッキ10により吊り上げられるステップロッド
11が保持され、下部受梁13は屋根鉄骨トラス8の下弦材
8aを下方から受けるようになっている。[Roof Lift-Up] The roof steel truss 8 of the roof 1 has a step rod for lifting the roof 1 as shown in FIG. 6 and FIG.
Attach 11 This step rod 11 has beams 12 and 13 sandwiching the roof steel truss 8 at the top and bottom.
Step rod 12 is lifted by jack 10
11 is held and the lower support 13 is the lower chord of the roof steel truss 8
8a is received from below.
[屋根の地切り時の安全対策] そして、屋根鉄骨トラス8のリフトアップを行うにあ
たっては、屋根鉄骨トラス8の下部が本設柱3などから
離れる際に接触して傷付けやすいことから、外周柱24の
建方時の安全作業を確保するために、屋根鉄骨トラス8
に対し以下の安全対策を講じる。[Safety measures at the time of roof truss] When lifting up the roof steel truss 8, since the lower part of the roof steel truss 8 is likely to be in contact with and damaged when it separates from the main pillar 3, etc. In order to ensure safe work during the construction of 24, the roof steel truss 8
Take the following safety measures for.
すなわち、屋根鉄骨トラス8の地組み時においては、
第8図および第9図に示すように、屋根鉄骨トラス8の
仮設構台(仮設柱2および鉄骨サポート柱5)への定着
部として下弦材8aの下にトラス束材15を介して地組用ベ
ース16あるいはプレート17を取り付けるようにしてい
る。また第10図に示すように、前者の地組用ベース16は
屋根鉄骨トラス8の外周部の三隅に、後者のプレート17
は地組用ベース16の間の外周部に取付けるようにしてい
る。したがって、屋根鉄骨トラス8の地組み後は地組用
ベース16およびプレート17をそのままの取付状態とし、
この状態でリフトアップを開始する。これにより、屋根
鉄骨トラス8の地切りの際に屋根鉄骨トラス8の下部が
本設柱3や仮設構台などによって傷付くのを防止でき
る。In other words, when the roof steel truss 8 is laid,
As shown in FIGS. 8 and 9, as a fixing portion of the roof steel truss 8 to the temporary gantry (the temporary column 2 and the steel support column 5), the truss bundle member 15 is used under the lower chord member 8a via the truss bundle member 15. The base 16 or the plate 17 is attached. Also, as shown in FIG. 10, the former ground-forming base 16 is provided at the three corners of the outer periphery of the roof steel truss 8 with the latter plate 17.
Are mounted on the outer peripheral portion between the ground bases 16. Therefore, after the framing of the roof steel truss 8, the framing base 16 and the plate 17 are attached as they are,
Lift-up is started in this state. Accordingly, it is possible to prevent the lower portion of the roof steel truss 8 from being damaged by the main pillar 3 or the temporary gantry when the roof steel truss 8 is cut off.
[鉄骨サポート柱の撤去および屋根の計測] 屋根鉄骨トラス8を仮設構台から地切りした後は、鉄
骨サポート柱5を撤去する。また地切りした状態の屋根
鉄骨トラス8についてリフトアップをスムーズかつ安全
に実施できるようにリフトアップする前に各変位の計測
を行い、計測データを基礎にして屋根鉄骨トラス8をリ
フトアップ準備状態にセットする。[Removal of Steel Support Column and Measurement of Roof] After the roof steel truss 8 is cut off from the temporary gantry, the steel support column 5 is removed. In addition, before the lift-up of the roofed steel truss 8 in the ground-cut state is performed so that the lift-up can be carried out smoothly and safely, each displacement is measured, and the roof steel truss 8 is put into the preparation state for the lift-up based on the measurement data. set.
[屋根の吊り上げ] そして、この状態から6箇所の仮設支柱6に設けた各
ジャッキ10を一斉に稼動して、ステップロッド11を引き
上げ、屋根鉄骨トラス8の吊り上げを開始する。各ジャ
ッキ10の制御は地上の指令室から行う。[Lifting of Roof] Then, from this state, the jacks 10 provided on the six temporary columns 6 are simultaneously operated, the step rod 11 is pulled up, and the lifting of the roof steel truss 8 is started. Control of each jack 10 is performed from a command room on the ground.
[屋根のリフトアップ作業における安全対策] 屋根鉄骨トラス8のリフトアップ作業においては、リ
フトアップ時における屋根鉄骨トラス8の振れによる仮
設支柱6とのねじれや屋根鉄骨トラス8と支柱との接触
を防止するため、次ぎのような安全対策を講じる。[Safety Measures for Roof Lift-Up Work] In the lift-up work of the roof steel truss 8, twist of the roof steel truss 8 due to runout of the roof steel truss 8 at the time of lift-up and contact of the roof steel truss 8 with the support pillar are prevented. In order to do so, take the following safety measures.
すなわち、第11図に示すように、仮設支柱6とこれに
面する屋根鉄骨トラス8の一部に屋根鉄骨トラス8の水
平方向のガイド機構18を設け、屋根鉄骨トラス8をガイ
ド機構18に沿って吊り上げ、屋根鉄骨トラス8の水平方
向への振れ止めを行う。That is, as shown in FIG. 11, the temporary support 6 and a part of the roof steel truss 8 facing the temporary support 6 are provided with a horizontal guide mechanism 18 for the roof steel truss 8, and the roof steel truss 8 is moved along the guide mechanism 18. Then, the roof truss 8 is prevented from swinging in the horizontal direction.
ガイド機構18は、本実施例では、第12図ないし第14図
に示すように仮設支柱6の一面に面して配したH形鋼19
の両端を、屋根鉄骨トラス8の交差して隣合う下弦材8a
のリブ8b相互に掛け渡すとともに、H形鋼19の仮設支柱
6に面する側に衡突力を吸収するゴムマット等の弾性部
材20をアングル材20aにより取り付けて構成したもので
ある。かかるガイド機構18は、第11図に示すように1本
の仮設支柱6の周囲を囲む形で4つ設置し、全体では合
計して24箇所設置することになる。In this embodiment, the guide mechanism 18 is an H-shaped steel 19 disposed on one surface of the temporary support 6 as shown in FIG. 12 to FIG.
Both ends of the lower chord material 8a crossing and adjacent to the roof steel truss 8
And an elastic member 20 such as a rubber mat that absorbs a collision force is attached to the side of the H-shaped steel 19 facing the temporary support 6 by an angle member 20a. As shown in FIG. 11, four such guide mechanisms 18 are installed so as to surround one temporary support column 6, and a total of 24 guide mechanisms 18 are installed.
かかるガイド機構18は、各仮設支柱6…の周囲を囲む
ように設けるようにしたから、屋根鉄骨トラス8の吊り
上げ時に屋根鉄骨トラス8の水平方向への振れを拘束
し、吊り上げ方向には拘束しない構造となっている。し
たがって、大スパン屋根1の吊り上げ時に屋根鉄骨トラ
ス8が仮設支柱6に衡突する際の衡突力と風圧力による
生じる振れを所定の数値以下に規制することができ、屋
根鉄骨トラス8の吊り上げを安全にかつ確実に、スムー
ズに行うことができる。また、それぞれの仮設支柱6は
ガイド機構18の弾性部材20により囲まれているので、屋
根鉄骨トラス18や仮設支柱6が傷付くのを防止すること
ができる。Since the guide mechanism 18 is provided so as to surround the periphery of each temporary support column 6..., The roof steel truss 8 is restrained from swinging in the horizontal direction when the roof steel truss 8 is lifted, and is not restrained in the lifting direction. It has a structure. Therefore, when the roof steel truss 8 collides with the temporary support 6 when the large span roof 1 is lifted, it is possible to restrict the vibration caused by the striking force and wind pressure to a predetermined value or less, and the roof steel truss 8 is lifted. Can be performed safely, reliably and smoothly. Further, since the respective temporary supports 6 are surrounded by the elastic members 20 of the guide mechanism 18, it is possible to prevent the roof steel truss 18 and the temporary supports 6 from being damaged.
[屋根の仮固定] このようにしてガイド機構18で案内しつつ屋根鉄骨ト
ラス8をリフトアップにより第3図に示すように所定の
高さ位置まで吊り上げたら、屋根鉄骨トラス8を仮設支
柱6に仮固定する。[Temporary Fixing of Roof] When the roof steel truss 8 is lifted up to a predetermined height as shown in FIG. 3 while being guided by the guide mechanism 18 in this way, the roof steel truss 8 is attached to the temporary support 6. Temporarily fix.
[屋根の吊り上げ終了時における振れ止め対策] 屋根鉄骨トラス8の吊り上げ終了後、屋根鉄骨トラス
8は外周柱24の建方時において長期にわたり(約1.5ケ
月)吊り下げ状態にあるため、その期間中に地震が起き
た場合の振れ止め対策を講じる。[Measures to Prevent Sway at the End of Roof Lifting] After the roof steel truss 8 has been lifted, the roof steel truss 8 has been suspended for a long time (about 1.5 months) when the outer peripheral columns 24 are constructed. Take anti-sway measures in the event of an earthquake.
すなわち、第15図および第16図に示すように、屋根鉄
骨トラス8にリフトアップ前に取り付けたガイド機構18
を利用して、仮設支柱6の柱部分にスラストサポート21
を取り付ける。このスラストサポート21は、ガイド機構
18のうち弾性部材20を撤去したガイド片19をそのまま残
して用いるもので、このガイド片19の仮設支柱6に面す
る側に断面コ字形の取付片22をボルト22aにより止め、
取付片22に仮設支柱6の柱部分に拘束される挾持部23を
設けた構造としたものである。That is, as shown in FIGS. 15 and 16, the guide mechanism 18 attached to the roof steel truss 8 before the lift-up is performed.
Using the thrust support 21 on the pillar portion of the temporary support 6
Attach. This thrust support 21 has a guide mechanism
The guide piece 19 from which the elastic member 20 has been removed is used as it is, and the mounting piece 22 having a U-shaped cross section is fixed to the side of the guide piece 19 facing the temporary support column 6 with a bolt 22a.
The mounting piece 22 has a structure in which a holding portion 23 which is restrained by a pillar portion of the temporary support 6 is provided.
かかるスラストサポート21は、本実施例では、仮設支
柱6の周囲を囲む形で1本につき4箇所設置し、合計24
箇所設置する。このようなスラストサポート21を設ける
ことにより、地震時に仮設支柱6に水平力が生じて屋根
鉄骨トラス8に振れが生じようとしても、スラストサポ
ート21が仮設支柱6により水平方向への移動が拘束され
るから、屋根鉄骨トラス8の振れを有効に防止すること
ができる。したがって、仮設支柱の変形や衡突による破
損等を防止することができる。In this embodiment, four such thrust supports 21 are provided so as to surround the periphery of the temporary support column 6, and a total of 24
Place. By providing such a thrust support 21, even if a horizontal force is generated in the temporary support 6 during an earthquake and the roof steel truss 8 is likely to run out, the movement of the thrust support 21 in the horizontal direction is restricted by the temporary support 6. Therefore, the deflection of the roof steel truss 8 can be effectively prevented. Therefore, it is possible to prevent the temporary support column from being deformed or damaged due to a collision.
[屋根の吊り上げ終了後におけるステップロッドの破断
事故対策] リフトアップ作業中は短時間で行なわれるが、リフト
アップ完了後は外周柱24を建方するまで、比較的長期間
(約1.5ケ月)にわたり、その間は屋根1は吊り下げ状
態にあるため、屋根鉄骨トラス8が突風や地震により屋
根鉄骨トラス8が振れた場合、ステップロッド11に限界
を越える応力が生じて破断が起きる恐れがある。このた
め、ステップロッド11が万一破断したとしても屋根1が
落下しないように落下防止対策を講じる。[Countermeasures against breakage of the step rod after completion of lifting of the roof] It is performed in a short time during the lift-up work, but after the lift-up is completed, it takes a relatively long time (about 1.5 months) until the outer pillar 24 is built. Meanwhile, since the roof 1 is in a suspended state, if the roof steel truss 8 is shaken by a gust or an earthquake, the step rod 11 may be subjected to a stress exceeding the limit and breakage may occur. For this reason, a fall prevention measure is taken to prevent the roof 1 from falling even if the step rod 11 is broken.
すなわち、第6図および第7図に示すように1本のス
テップロッド11の上下に設けた上部受梁12および下部受
梁13に対しバックアップ用の2本の吊り材25の両端をそ
れぞれ固定しておく。吊り材25は、上部受梁12とその下
方の束材26とに両端を固定した上部吊り材25aと、束材2
6と下部受梁13とに両端を固定した下部吊り材25bとから
構成する。かかる構成の吊り材25によれば、1本のステ
ップロッド11が万一破断した場合には、ただちに2本の
吊り材25がその部分の屋根鉄骨トラス8の重量を支持す
るようになっている。That is, as shown in FIG. 6 and FIG. 7, both ends of the two suspension members 25 for backup are fixed to the upper support beam 12 and the lower support beam 13 provided above and below one step rod 11, respectively. Keep it. The suspending member 25 includes an upper suspending member 25a having both ends fixed to the upper support beam 12 and a bundle member 26 thereunder, and a bundle member 2
6 and a lower suspension member 25b having both ends fixed to the lower receiving beam 13. According to the hanging member 25 having such a configuration, in the event that one step rod 11 is broken, the two hanging members 25 immediately support the weight of the roof steel truss 8 in that portion. .
[外周柱の建方] 一方、屋根1の架設範囲には第4図に示すように外周
柱24の建方を行う。第18図に示すように、外周柱24は第
1節部分24aおよび第2節部分24bの建方を終了した時点
でゆがみ直しおよび建入れの調整を行い、第3節部分24
cの建方前に本締めを実施する。なお、第17図に示すよ
うに外周柱24の三隅においては第2節部分24bの本締め
後に転倒防止のために控え網27を取る。控え網27は所定
の引き抜き力に耐えられる鋼製ワイヤーから構成し、両
端を第2節部分24b上端と仮設構台との間に定着させ
る。[How to Build Outer Pillars] On the other hand, as shown in FIG. As shown in FIG. 18, when the outer pillar 24 completes the construction of the first section 24a and the second section 24b, the outer pillar 24 is re-skewed and adjusted for the third section 24a.
Perform final tightening before the construction of c. In addition, as shown in FIG. 17, at the three corners of the outer peripheral post 24, a retaining net 27 is formed after the second joint portion 24b is fully tightened in order to prevent falling. The stay net 27 is made of a steel wire that can withstand a predetermined pulling force, and both ends are fixed between the upper end of the second joint portion 24b and the temporary gantry.
[外周柱の建方時における突風対策] かかる外周柱24においては第18図に示すように第3節
部分24cまでは本締めにより自立状態で突風に対処でき
る。しかし、最上部の第4節部分24dまで建方が完了し
た時点では自立状態では突風により倒壊のおそれがあ
り、損傷を受けるおそれがある。そこで、以下のような
対策を講じる。[Countermeasures against gusts when constructing outer peripheral columns] In such outer peripheral columns 24, as shown in FIG. 18, gusts can be dealt with in a self-supporting state up to the third node portion 24c by final fastening. However, at the time when the building is completed up to the fourth section 24d at the top, there is a risk of collapse due to a gust and a possibility of being damaged in the self-standing state. Therefore, the following measures are taken.
すなわち、第19図ないし第22図に示すように、第4節
部分24dの建方後に、屋根鉄骨トラス8の下端を柱頭部
に定着させる。第10図に示すような屋根鉄骨トラス8の
下端の三隅部分に対しては、第19図および第20図に示す
トラス束材15に取り付けた断面T字形の地組用ベース16
を用いて、この地組用ベース16と柱頭部に取り付けた断
面逆T字形の取付用ピース28とを互いに連結する。また
第10図に示すような屋根鉄骨トラス8の下端の残りの部
分に対しては、第21図および第22図に示すトラス束材15
の下端に取り付けたプレート17を用いて、このプレート
17と柱頭部に取り付けたプレート29とを互いに連結す
る。これにより、突風時に外周柱24の倒壊等を防止し得
るとともに、屋根鉄骨トラス8のジャッキダウン前に屋
根鉄骨トラス8と外周柱24との納まりを良好にできる。That is, as shown in FIGS. 19 to 22, the lower end of the roof steel truss 8 is fixed to the capital after the fourth section 24d is constructed. At three corners at the lower end of the roof steel truss 8 as shown in FIG. 10, a T-shaped cross section base 16 attached to a truss bundle 15 shown in FIGS.
The grounding base 16 and the mounting piece 28 having an inverted T-shaped cross section mounted on the column capital are connected to each other by using the above. In addition, the remaining portion of the lower end of the roof steel truss 8 as shown in FIG. 10 is applied to the truss bundle 15 shown in FIG. 21 and FIG.
Using a plate 17 attached to the lower end of the
17 and the plate 29 attached to the capital are connected to each other. Thus, the outer pillar 24 can be prevented from collapsing or the like in the event of a gust, and the roof steel truss 8 and the outer pillar 24 can be properly fitted before the roof steel truss 8 is jacked down.
[屋根のジャッキダウン開始] つぎに、外周柱24の柱頭部に下端部を仮定着させた屋
根鉄骨トラス8のジャッキダウンを開始する。この場
合、外周柱24の建方精度や屋根鉄骨トラス8の製作精度
を考慮して、屋根鉄骨トラス8のジャッキダウンをスム
ーズに行えるように、屋根鉄骨トラス8における下弦
材、上弦材、ラチス材等の連結部分はその本締めを保留
する。[Start of Roof Jack Down] Next, the jack down of the roof steel truss 8 with the lower end assumed on the column cap of the outer peripheral column 24 is started. In this case, the lower chord material, the upper chord material and the lattice material of the roof steel truss 8 are taken into consideration so that the roof steel truss 8 can be smoothly jacked down in consideration of the construction accuracy of the outer peripheral columns 24 and the manufacturing accuracy of the roof steel truss 8. And the like are suspended from the final fastening.
[屋根の柱頭部との定着・接合] 屋根鉄骨トラス8のジャッキダウンが完了したら、屋
根鉄骨トラス8の下端部を外周柱24の柱頭部に定着させ
るとともに、外周柱24の柱頭部に対し屋根鉄骨トラス8
の下端を接合する。同時に屋根鉄骨トラス8における下
弦材、上弦材、ラチス材の本締めを行う。[Fixing / joining of roof steel truss 8] When jacking down of the roof steel truss 8 is completed, the lower end of the roof steel truss 8 is fixed to the capital of the outer peripheral column 24, and the roof is attached to the capital of the outer column 24. Steel truss 8
Join the lower ends of At the same time, the lower chord material, the upper chord material, and the lattice material in the roof steel truss 8 are fully tightened.
[リフトアップ張力の解除] そして、屋根鉄骨トラス8に取り付けていたリフトア
ップ用のステップロッド11を外してリフトアップ張力を
解除し、屋根鉄骨トラス8を外周柱24上に自立状態に架
設する。[Release of Lift-Up Tension] Then, the lift-up tension is released by removing the lift-up step rod 11 attached to the roof steel truss 8, and the roof steel truss 8 is erected on the outer peripheral column 24 in a self-supporting state.
[仮設支柱の撤去] 仮設支柱6上のジャッキ10は解体し、仮設支柱6はそ
の後撤去する。[Removal of temporary column] The jack 10 on the temporary column 6 is dismantled, and the temporary column 6 is subsequently removed.
以上の作業により、屋根1の架設作業が完了する。 With the above operation, the installation work of the roof 1 is completed.
本実施例によれば、屋根1の地組みから架設に至るま
で安全にかつ確実に各作業を実施するとともに、これら
の作業をスムーズに効率良く行うことができる。According to the present embodiment, it is possible to perform each operation safely and reliably from the ground construction of the roof 1 to the erection, and to perform these operations smoothly and efficiently.
また、屋根1の屋根鉄骨トラス8を吊り上げる前に架
設範囲にて地組みすることにより、トラス材ごとに架設
範囲全体にわたって仮設支柱を立てる必要がなくなるの
で、仮設支柱に必要な膨大な鉄骨量を削減し、仮設工数
を低減し、仮設費用を低減することができる。また、屋
根仕上げ材などを吊り上げ前の屋根トラス8に予め施工
しておくことにより、屋根1の工事を地上で組むことが
でき、作業の安全を確保できるとともに、工期の短縮を
図ることができる。さらには、仮設支柱6をタワークレ
ーンの架台に兼用することにより仮設工事の省力化が図
れる。Also, by laying the truss 8 in the erection area before lifting the roof steel truss 8 of the roof 1, it is not necessary to erect temporary supports for the entire erection area for each truss material. It is possible to reduce the number of man-hours for temporary construction and reduce the cost for temporary construction. In addition, by constructing the roof truss 8 in advance on the roof truss 8 before lifting, the construction of the roof 1 can be assembled on the ground, work safety can be ensured, and the construction period can be shortened. . Further, by using the temporary support column 6 also as a stand of a tower crane, labor saving in temporary construction can be achieved.
「発明の効果」 本発明は、大スパン屋根をその架設範囲で地組みし、
ついで地組みした大スパン屋根を仮設の支柱に沿って吊
り上げ、さらに本設の外周柱相互に大スパン屋根を降ろ
してその間に架設するようにした大スパン屋根の施工法
であって、大スパン屋根の吊り上げを、上下に受梁を有
するステップロッドを大スパン屋根に係止してこれをジ
ャッキアップすることにより行い、前記ステップロッド
の上下の受梁にバックアップ用の吊材の上下端を連結す
るようにしたから、大スパン屋根の吊り上げ以降から外
周柱を建方するまでの間の比較的長期にわたる吊り下げ
状態において、万一ステップロッドが金属疲労や風力や
地震力により破断する事態が生じても、吊材によりバッ
クアップ体制を取ることができ、大スパン屋根の落下事
故対策を取ることができる。"Effects of the Invention" The present invention lays a large span roof in its construction area,
Then, the large span roof is lifted along the temporary pillars, and the large span roof is lowered to the outer peripheral pillars of the main building. Is carried out by engaging a step rod having a support beam on the upper and lower sides with a large span roof and jacking it up, and connecting the upper and lower ends of the backup suspending material to the upper and lower support beams of the step rod. Therefore, in the state of suspension for a relatively long time from the lifting of the large span roof to the construction of the outer pillar, the step rod may break due to metal fatigue, wind force or seismic force. In addition, a back-up system can be provided by using hanging materials, and measures can be taken to prevent a large-span roof from falling.
また、本発明によれば、大スパン屋根を外周柱相互に
降ろす前に、吊り上げた状態の大スパン屋根を対応する
外周柱の柱頭部に仮定着させておくようにしたから、外
周柱建方時に突風などにより外周柱の自由端側が大きく
変形して倒壊したりすることなく、大スパン屋根を降ろ
して外周柱の柱頭部に対し精度のよい接合が可能とな
る。これにより外周柱の柱頭部相互に対する大スパン屋
根の納まりを良くすることができる。Further, according to the present invention, before lowering the large-span roof to the outer pillars, the large-span roof in a suspended state is assumed to be attached to the column caps of the corresponding outer pillars. Sometimes, the free end side of the outer pillar is largely deformed and not collapsed due to gusts or the like, and the large-span roof can be lowered to enable accurate joining to the column cap of the outer pillar. This makes it possible to improve the fit of the large span roof with respect to the column caps of the outer peripheral columns.
また、本発明によれば、各支柱とこれに面する大スパ
ン屋根の一部との間に、大スパン屋根の吊り上げ中に、
大スパン屋根が支柱に衡突する時の衝撃力を吸収するガ
イド機構を設け、このガイド機構に沿って大スパン屋根
を吊り上げるようにしたから、大スパン屋根の吊り上げ
時において支柱と大スパン屋根との衝突によるねじれや
変形、突風による破損を防止することができ、安全にか
つ確実に、スムーズにリフトアップ作業を行うことがで
きる。According to the present invention, between each pillar and a part of the large span roof facing the same, during the lifting of the large span roof,
A guide mechanism to absorb the impact force when the large span roof collides with the support is provided, and the large span roof is lifted along this guide mechanism. It is possible to prevent torsion, deformation, and damage due to gusts due to collision of the vehicle, and to perform lift-up operation safely, reliably, and smoothly.
また、本発明によれば、大スパン屋根を吊り上げた以
降、外周柱を本設するまでの間、各支柱とこれに面する
大スパン屋根の一部との間に設けたスラストサポートに
より大スパン屋根の水平方向への挙動を拘束しておくよ
うにしたから、比較的長期にわたる外周柱の建方時にお
いて、地震が起きた場合に大スパン屋根の振れ止め防止
対策を取ることができ、大スパン屋根の安全な施工が可
能となる。Further, according to the present invention, after the large span roof is lifted, a large span is provided by the thrust support provided between each support and a part of the large span roof facing the same until the outer peripheral columns are permanently installed. Since the horizontal behavior of the roof is restrained, it is possible to take measures to prevent large-span roofs from swaying in the event of an earthquake during the construction of outer pillars for a relatively long period of time. Safe construction of span roof is possible.
第1図ないし第4図は本発明にかかる屋根の施工手順を
示す図であって、第1図は仮設柱と本設柱の建方作業を
示す図、第2図は屋根鉄骨トラスの地組作業を示す図、
第3図は屋根のリフトアップ作業を示す図、第4図は屋
根のリフトアップ完了後の図、第5図は架設範囲におけ
る仮設支柱とジャッキの設置位置を示す平面図、第6図
および第7図はステップロッドを示す側面図と正面図、
第8図および第9図は屋根鉄骨トラスの端部下面の要部
を示す側面図、第10図は屋根鉄骨トラスの平面図、第11
図はガイド機構の配置を示す屋根鉄骨トラスの平面図、
第12図ないし第13図はガイド機構を示すもので、第12図
はガイド機構の設置状態を示す平面図、第13図はガイド
機構の縦断面図、第14図は第12図のA−A矢視図、第15
図および第16図はスラストサポートを示すもので、第15
図はスラストサポートの設置状態を示す要部平面図、第
16図はスラストサポートの縦断面図、第17図は屋根にお
ける外周柱の側面図、第18図は外周柱の側面図、第19図
ないし第22図は屋根鉄骨トラスと外周柱の柱頭部との仮
定着構造を示すもので、第19図および第20図は側面図お
よび正面図、第21図および第22図は別構造例を示す側面
図および正面図である。 1……屋根(大スパン屋根)、6……仮設支柱(支
柱)、24……外周柱、11……ステップロッド、12、13…
…受梁(上部受梁、下部受梁)、18……ガイド機構、21
……スラストサポート、25……吊り材。1 to 4 are views showing a construction procedure of a roof according to the present invention. FIG. 1 is a view showing how to construct a temporary column and a permanent column, and FIG. A diagram showing the assembly work,
FIG. 3 is a view showing a lift-up operation of the roof, FIG. 4 is a view after the completion of the lift-up of the roof, FIG. 5 is a plan view showing installation positions of the temporary columns and jacks in the installation area, FIG. 6 and FIG. FIG. 7 is a side view and a front view showing a step rod,
8 and 9 are side views showing the main part of the lower surface of the end of the roof steel truss, FIG. 10 is a plan view of the roof steel truss, and FIG.
The figure is a plan view of the roof steel truss showing the arrangement of the guide mechanism,
12 to 13 show a guide mechanism, FIG. 12 is a plan view showing an installed state of the guide mechanism, FIG. 13 is a longitudinal sectional view of the guide mechanism, and FIG. View from arrow A, 15th
Figures and 16 show the thrust support.
The figure is a plan view of the main part showing the installed state of the thrust support.
Fig. 16 is a longitudinal sectional view of the thrust support, Fig. 17 is a side view of the outer peripheral pillar on the roof, Fig. 18 is a side view of the outer peripheral pillar, Figs. 19 and 20 are a side view and a front view, and FIGS. 21 and 22 are a side view and a front view showing another example of the structure. 1 ... Roof (Large span roof), 6 ... Temporary column (column), 24 ... Peripheral column, 11 ... Step rod, 12, 13 ...
… Receiving beam (upper receiving beam, lower receiving beam), 18 …… Guide mechanism, 21
... thrust support, 25 ... hanging material.
Claims (4)
ついで地組みした大スパン屋根を仮設の支柱に沿って吊
り上げ、さらに本設の外周柱相互に大スパン屋根を降ろ
してその間に架設するようにした大スパン屋根の施工法
において、大スパン屋根の吊り上げは、上下に受梁を有
するステップロッドを大スパン屋根に係止してこれをジ
ャッキアップすることにより行い、前記ステップロッド
の上下の受梁にはバックアップ用の吊材の上下端が連結
されていることを特徴とする大スパン屋根の施工法。(1) A large span roof is laid in its construction area,
Then, the large span roof is lifted along the temporary pillars, and the large span roof is lifted down between the main outer pillars and installed between them. Is performed by locking a step rod having upper and lower receiving beams to a large span roof and jacking up the step rod, and upper and lower ends of a backup hanging material are connected to the upper and lower receiving beams of the step rod. Construction method for large span roofs.
ついで地組みした大スパン屋根を仮設の支柱に沿って吊
り上げ、さらに本設の外周柱相互に大スパン屋根を降ろ
してその間に架設するようにした大スパン屋根の施工法
において、大スパン屋根を外周柱相互に降ろす前に、吊
り上げた状態の大スパン屋根を対応する外周柱の柱頭部
に仮定着させておくことを特徴とする大スパン屋根の施
工法。2. A large span roof is laid in its erection area,
Then, the large span roof was lifted along the temporary pillars, and the large span roof was lowered to the outer peripheral pillars of the main building. A method of constructing a large span roof, wherein a large span roof in a suspended state is assumed to be attached to a column cap of a corresponding peripheral pillar before lowering the pillars.
ついで地組みした大スパン屋根を仮設の支柱に沿って吊
り上げ、さらに本設の外周柱相互に大スパン屋根を降ろ
してその間に架設するようにした大スパン屋根の施工法
において、各支柱とこれに面する大スパン屋根の一部と
の間に、大スパン屋根の吊り上げ中に大スパン屋根が支
柱に衡突する時の衝撃力を吸収するガイド機構を設け、
当該ガイド機構に沿って大スパン屋根を吊り上げるよう
にしことを特徴とする大スパン屋根の施工法。3. A large span roof is laid in its construction area,
Next, in the construction method of the large span roof, the large span roof was lifted along the temporary pillars, and the large span roofs were lowered to the outer peripheral pillars of the main building and installed between them. A guide mechanism that absorbs the impact force when the large span roof collides with the support during the lifting of the large span roof is provided between a part of the large span roof facing
A method of constructing a large span roof, wherein the large span roof is lifted along the guide mechanism.
ついで地組みした大スパン屋根を仮設の支柱に沿って吊
り上げ、さらに本設の外周柱相互に大スパン屋根を降ろ
してその間に架設するようにした大スパン屋根の施工法
において、大スパン屋根を吊り上げた以降、外周柱を本
設するまでの間、各支柱とこれに面する大スパン屋根の
一部との間に設けたスラストサポートにより大スパン屋
根の水平方向への挙動を拘束しておくことを特徴とする
大スパン屋根の施工法。4. A large span roof is laid in its construction area,
Then, the large span roof is lifted along the temporary pillars, and the large span roof is lifted down between the permanent pillars and the large span roof is installed between them. After that, until the outer pillars are permanently installed, restrain the horizontal movement of the large span roof by the thrust support provided between each pillar and a part of the large span roof facing it. Construction method of large span roof characterized by the following.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2228962A JP2928948B2 (en) | 1990-08-30 | 1990-08-30 | Construction method of large span roof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2228962A JP2928948B2 (en) | 1990-08-30 | 1990-08-30 | Construction method of large span roof |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH04111829A JPH04111829A (en) | 1992-04-13 |
| JP2928948B2 true JP2928948B2 (en) | 1999-08-03 |
Family
ID=16884595
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2228962A Expired - Fee Related JP2928948B2 (en) | 1990-08-30 | 1990-08-30 | Construction method of large span roof |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2928948B2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105888262A (en) * | 2016-04-14 | 2016-08-24 | 中国十七冶集团有限公司 | Construction method for large-span pipe corridor pipeline |
Families Citing this family (24)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH07269010A (en) * | 1994-04-01 | 1995-10-17 | Tomoe Corp | Support structure of suspension roof |
| CN101611203B (en) * | 2007-02-20 | 2011-03-02 | 东急建设株式会社 | Construction method of large space building |
| CN101225712B (en) | 2008-01-04 | 2012-04-04 | 中国电力科学研究院 | Latticed holding pole having optimal steel-aluminum ratio |
| CN101225711B (en) | 2008-01-04 | 2012-05-23 | 中国电力科学研究院 | Latticed holding pole with horizontally-rotatable head |
| CN102465598A (en) * | 2010-11-05 | 2012-05-23 | 江苏邗建集团有限公司 | Construction method of high-altitude cast-in-place arch truss |
| CN102635209B (en) * | 2012-05-23 | 2014-10-08 | 中建二局第三建筑工程有限公司 | Cornice steel skeleton and bracket steel skeleton for large-span big roof of pseudo-classic architecture and construction method of cornice steel skeleton and bracket steel skeleton |
| CN103225408B (en) * | 2013-04-18 | 2015-05-20 | 南通大学 | Construction method for long-span net rack multiple-mast independent type integral lifting |
| CN103410330B (en) * | 2013-07-16 | 2016-04-20 | 中铁三局集团有限公司 | Asymmetric variable cross-section different curve extra-heavy duty type large span steel truss hanging method |
| CN103726710A (en) * | 2013-12-31 | 2014-04-16 | 国家电网公司 | Lattice type derrick of electric transmission line |
| CN104060840A (en) * | 2014-06-25 | 2014-09-24 | 广州市第三建筑工程有限公司 | The construction method of using the bolt ball truss hoist to lift the large-span dome grid |
| CN104153589B (en) * | 2014-08-27 | 2016-04-27 | 中国建筑第二工程局有限公司 | Method for detecting lifting capacity of lifting point of roof steel truss |
| CN104594560A (en) * | 2015-01-30 | 2015-05-06 | 柳忠东 | Prefabricated frame column |
| CN105064697A (en) * | 2015-07-15 | 2015-11-18 | 安徽跨宇钢结构网架工程有限公司 | Roof grid elevating method |
| CN106013601A (en) * | 2016-06-24 | 2016-10-12 | 宝钢钢构有限公司 | Large-span roof steel truss structure and accumulative slipping construction technology |
| JP6878898B2 (en) * | 2017-01-16 | 2021-06-02 | 株式会社大林組 | Roof frame construction method |
| CN106703419B (en) * | 2017-01-22 | 2019-02-12 | 中国十七冶集团有限公司 | Long-span roofing truss installation at high altitude slip control method |
| CN109113346A (en) * | 2018-09-19 | 2019-01-01 | 上海市机械施工集团有限公司 | A kind of plastic stone rockery abnormal complex steel supporting structure construction method |
| CN109989590B (en) * | 2019-04-09 | 2024-01-23 | 中建一局集团建设发展有限公司 | Auxiliary fixing device for mounting roof overlong steel beam and hoisting method of steel beam |
| CN111877790B (en) * | 2020-07-01 | 2021-11-09 | 上海建工集团股份有限公司 | Construction method for integrally jacking and replacing new and old steel roof |
| CN114033051A (en) * | 2021-12-09 | 2022-02-11 | 中建八局发展建设有限公司 | Large-span hyperbolic truss construction process based on steel structure spherical curtain cinema engineering |
| CN115506604B (en) * | 2022-10-19 | 2023-07-25 | 安徽富煌钢构股份有限公司 | Method for installing first truss of large-span steel structure |
| CN116241103A (en) * | 2022-11-16 | 2023-06-09 | 中国一冶集团有限公司 | Large-span curved surface single-layer reticulated shell mounting support steel frame structure and construction method |
| CN117328686A (en) * | 2023-11-30 | 2024-01-02 | 北京建工集团有限责任公司 | Method for installing main truss and steel structure of column-free building |
| CN118881026B (en) * | 2024-09-30 | 2025-01-24 | 上海建工四建集团有限公司 | A large-span sports stadium roof grid lifting mechanism and construction method |
-
1990
- 1990-08-30 JP JP2228962A patent/JP2928948B2/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105888262A (en) * | 2016-04-14 | 2016-08-24 | 中国十七冶集团有限公司 | Construction method for large-span pipe corridor pipeline |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH04111829A (en) | 1992-04-13 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2928948B2 (en) | Construction method of large span roof | |
| EP0480683B1 (en) | Erection workbench and construction process | |
| JP2927320B2 (en) | How to assemble a large hanging boiler | |
| JP3049300B2 (en) | Construction method of beam truss in building with overhead traveling crane | |
| JP2979039B2 (en) | Large space building construction equipment | |
| JP3061560B2 (en) | Tent warehouse and its construction method | |
| JP2950726B2 (en) | Construction method of multi-layer suspension structure | |
| CN113323403A (en) | Roof atrium membrane structure steel truss erecting platform structure and construction method thereof | |
| JP2690822B2 (en) | Steel construction method for low-rise buildings | |
| JP3546225B2 (en) | How to build building structures | |
| JP2779258B2 (en) | Roof lift-up method | |
| JP3115942B2 (en) | Building construction method | |
| JP3328790B2 (en) | High-rise building assembly method | |
| JP2595614Y2 (en) | Push-up rack for large span structures | |
| JP3139854B2 (en) | Collapse prevention frame | |
| JP3128178B2 (en) | How to build a tent frame | |
| JP2634271B2 (en) | Jack-up method and device | |
| JP3124152B2 (en) | Collapse prevention frame | |
| JP2024053180A (en) | Construction methods for wooden buildings | |
| JP2776140B2 (en) | Temporary beam assembly equipment for building construction | |
| JPH04297665A (en) | Erection-working base for construction of structure | |
| JP2888913B2 (en) | External wall panel mounting method | |
| JP2575796Y2 (en) | External curing frame | |
| JPH0539637A (en) | Construction method for domed roof and heavy hoist therefor | |
| JP3324807B2 (en) | Column-beam pre-assembled reinforced body and pre-assembled reinforced construction method using it |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |