CN103774856B - A kind of gliding construction method of different shape heavy type girder steel of large span on Super High roofing - Google Patents

A kind of gliding construction method of different shape heavy type girder steel of large span on Super High roofing Download PDF

Info

Publication number
CN103774856B
CN103774856B CN201410034244.1A CN201410034244A CN103774856B CN 103774856 B CN103774856 B CN 103774856B CN 201410034244 A CN201410034244 A CN 201410034244A CN 103774856 B CN103774856 B CN 103774856B
Authority
CN
China
Prior art keywords
sliding
steel
slideway
hydraulic
slipping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410034244.1A
Other languages
Chinese (zh)
Other versions
CN103774856A (en
Inventor
刘荣
成张佳宁
曹松泉
唐咸国
王恩林
嵇立林
孙玉峰
嵇国星
王爱勇
杨杰
陆玉国
成军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Huwu Construction Group Co ltd
Nantong University
Nantong Textile Vocational Technology College
Original Assignee
Jiangsu Shanghai Construction Group Co Ltd
Nantong University
Nantong Textile Vocational Technology College
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Shanghai Construction Group Co Ltd, Nantong University, Nantong Textile Vocational Technology College filed Critical Jiangsu Shanghai Construction Group Co Ltd
Priority to CN201410034244.1A priority Critical patent/CN103774856B/en
Publication of CN103774856A publication Critical patent/CN103774856A/en
Application granted granted Critical
Publication of CN103774856B publication Critical patent/CN103774856B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明公开了一种大跨度异状重型钢梁在超高层屋面上的滑移施工方法,包括如下步骤:安装滑道预理件;安装滑道预理件;塔吊吊运架体;搭设支撑架体;分节组装钢梁;焊接两榀连杆;卸去梁底部支撑及胎架;安装滑道及推进器;安装液压控制系统;调试推进器控制系统;钢梁滑移到设计位置;纠校正偏钢梁位置;焊接钢梁两侧柱支脚;重复以上滑移第三根钢梁;拆除滑道及推进系统;拆除钢梁支撑架体。本发明具有的有益效果:本方法采用塔吊把分节的钢结构吊装到屋面、在屋面焊接组装钢梁,然后钢梁整体滑移的施工技术,解决了在高空塔吊无法吊大件的难题。

The invention discloses a sliding construction method of a large-span abnormal-shaped heavy-duty steel beam on a super-high-rise roof, comprising the following steps: installing a slideway preconditioner; installing a slideway preconditioner; lifting a frame body by a tower crane; erecting a support frame body ; Assemble the steel beam in sections; Weld the two connecting rods; Remove the beam bottom support and tire frame; Install the slideway and propeller; Install the hydraulic control system; Debug the propeller control system; The position of the partial steel beam; weld the column feet on both sides of the steel beam; repeat the above to slide the third steel beam; remove the slideway and propulsion system; remove the steel beam support frame. The invention has beneficial effects: the method adopts the construction technique of hoisting the segmented steel structure to the roof with a tower crane, welding and assembling steel beams on the roof, and then sliding the steel beam as a whole, which solves the problem that the tower crane cannot lift large pieces at high altitude.

Description

一种大跨度异状重型钢梁在超高层屋面上的滑移施工方法A sliding construction method of long-span abnormal-shaped heavy-duty steel beams on super-high-rise roofs

技术领域technical field

本发明涉及一种大跨度异状重型钢梁在超高层屋面上的滑移施工方法,属于建筑施工技术领域。The invention relates to a sliding construction method of a large-span abnormal-shaped heavy-duty steel beam on a super-high-rise roof, and belongs to the technical field of building construction.

背景技术Background technique

随着国民经济的发展及人民生活水平的不断提高,建筑师的作品表现的也越来越丰富多彩,且个性化十足,特别是外观及屋面的顶部设计独具一格。本工程建筑设计为美国NBBJ设计事务所,外观是杨帆起航的5艘大船。由于建筑立面效果,设计要求屋面的钢结构构件梁为重型钢梁,且造型特别复杂,给建造施工带来非常大的困难。传统的施工方法无法满足设计要求,需寻求新的技术手段来解决所面临的问题。With the development of the national economy and the continuous improvement of people's living standards, the works of architects are becoming more and more colorful and full of personality, especially the unique appearance and top design of the roof. The architectural design of this project is the American NBBJ design firm, and the appearance is 5 large ships set sail by Yang Fan. Due to the effect of the building facade, the design requires that the steel structure beams of the roof be heavy-duty steel beams, and the shape is particularly complicated, which brings great difficulties to the construction. Traditional construction methods cannot meet the design requirements, and new technical means need to be sought to solve the problems faced.

本方法所针对的屋面顶部设有五根大跨度异型重型钢梁(总重650吨),梁为全钢结构,截面0.8m×1.5m,箱型钢梁翼缘板和腹板均为38㎜厚钢板,箱型梁1.210吨/m,单榀钢梁最大重量108吨,最大跨度为52m,钢梁高20m~16.7m,钢结构梁采用整体滑移施工技术。The top of the roof targeted by this method is equipped with five large-span special-shaped heavy-duty steel beams (total weight 650 tons). The beams are all-steel structures with a cross-section of 0.8m×1.5m. The box girder is 1.210 tons/m, the maximum weight of a single steel beam is 108 tons, the maximum span is 52m, and the height of the steel beam is 20m to 16.7m. The steel structure beam adopts the overall sliding construction technology.

发明内容Contents of the invention

本发明的目的在于解决现有技术中存在的问题,提供了一种大跨度异状重型钢梁在超高层屋面上的滑移施工方法。The purpose of the present invention is to solve the problems existing in the prior art, and provides a sliding construction method of large-span abnormal-shaped heavy-duty steel beams on super-high-rise roofs.

为了实现上述目的,本发明的技术方案如下:In order to achieve the above object, the technical scheme of the present invention is as follows:

一种大跨度异状重型钢梁在超高层屋面上的滑移施工方法,其特征在于,包括如下步骤:A sliding construction method of large-span abnormal-shaped heavy-duty steel beams on super-high-rise roofs is characterized in that it includes the following steps:

安装滑道预理件;Install the slideway prefab;

塔吊吊运架体;Tower crane lifting frame body;

搭设支撑架体;set up a support frame;

分节组装钢梁;Sectionally assembled steel beams;

焊接两榀连杆;Weld two connecting rods;

卸去梁底部支撑及胎架;Remove the beam bottom support and tire frame;

安装滑道及推进器;Install slides and propellers;

安装液压控制系统;Install hydraulic control system;

调试推进器控制系统;Debug thruster control system;

钢梁滑移到设计位置;The steel beam slides to the design position;

纠校正偏钢梁位置;Correct the position of the deflection steel beam;

焊接钢梁两侧柱支脚;Column feet on both sides of the welded steel beam;

重复以上滑移第三根钢梁;Repeat above to slide the third steel beam;

拆除滑道及推进系统;Dismantling of slideway and propulsion system;

拆除钢梁支撑架体。Remove the steel beam support frame body.

作为一种优选方案,步骤A)中,滑移轨道中心线与钢架支座中心线重合,以减小滑移过程中桁架支座因受到偏心力而产生不利影响;滑移轨道选用200X200热轧H钢+16#槽钢,材质为Q235B,H钢按间距500mm焊接12mm厚筋板,利用滑移轨道的侧挡板与预埋件固定,轨道的侧挡板采用规格为-12×50×75mm的钢板,在滑移轨道两侧对称设置,间距为1000mm,起到对H钢翼缘加固、以及抵抗滑移支座处可能侧向推力的作用。本发明的有益效果主要体现在:经与传统的结构相比较分析测算,劲性阻尼结构增加了消能元件的费用,但钢筋用量、型钢用量和混凝土用量都有所降低。As a preferred solution, in step A), the center line of the sliding track coincides with the center line of the steel frame support, so as to reduce the adverse effect of the truss support on the truss support during the sliding process due to eccentric force; the sliding track is selected from 200X200 thermal Rolled H steel + 16# channel steel, the material is Q235B, the H steel is welded with 12mm thick rib plate at a distance of 500mm, and the side baffle of the sliding track is fixed with the embedded parts, and the specification of the side baffle of the track is -12×50 ×75mm steel plates are arranged symmetrically on both sides of the sliding track with a spacing of 1000mm, which serves to reinforce the flange of the H steel and resist the possible lateral thrust at the sliding support. The beneficial effects of the present invention are mainly reflected in: compared with the traditional structure, the rigid damping structure increases the cost of the energy dissipation element, but the amount of steel bar, section steel and concrete are all reduced.

本方法采用塔吊把分节的钢结构吊装到屋面、在屋面焊接组装钢梁,然后钢梁整体滑移的施工技术,解决了在高空塔吊无法吊大件的难题;缩短了工期,五榀重型钢结构梁,单栋楼近650吨钢结构安装仅仅用了40天完成安装,比计划工期减少了10天;本方法与传统的整榀吊装、桁架滑移等工艺相比,降低了材料浪费,节约钢材约20吨,按5000元/吨算,节省成本10万元;节省10天人工约500工,按250元/人,节省人工费用12.5万元;每栋楼合计节省费用22.5万,四栋楼合计节省费用90万元。This method uses the tower crane to hoist the segmented steel structure to the roof, weld and assemble the steel beams on the roof, and then the steel beams slide as a whole, which solves the problem that the tower crane cannot lift large parts at high altitudes; Steel structure beams, nearly 650 tons of steel structure installation in a single building took only 40 days to complete the installation, which is 10 days less than the planned construction period; compared with traditional whole-frame hoisting and truss sliding, this method reduces material waste , saving about 20 tons of steel, calculated at 5,000 yuan/ton, saving 100,000 yuan in cost; saving about 500 labor in 10 days, saving 125,000 yuan in labor costs at 250 yuan/person; saving 225,000 yuan in total for each building, A total of 900,000 yuan was saved for the four buildings.

附图说明Description of drawings

图1为本发明的方法的流程图。Figure 1 is a flow chart of the method of the present invention.

具体实施方式detailed description

本发明的工艺原理是钢梁构件在有效的位置上进行组装焊接,各条型钢梁成型后卸去支撑架进行滑移至设计位置。The technological principle of the present invention is that the steel girder components are assembled and welded at effective positions, and the supporting frame is removed after each steel girder is formed to slide to the designed position.

钢梁的基本构造是The basic structure of steel beams is

1、根据屋面钢梁的位置预埋固定滑道的钢板,钢板厚度为t=8mm,宽度b=400mm。1. Pre-embed the steel plate for fixing the slideway according to the position of the roof steel beam. The thickness of the steel plate is t=8mm and the width b=400mm.

2、根据屋面异型钢梁高度、形状及宽度,采用碗扣式钢管搭设满堂支撑架、满足承压及安全要求,并通过专业人员验收。开始根据每根梁的型状组装钢梁时,采用塔式起重机最大吊重量为5.5吨,每根梁需吊装21次,焊接完毕后须进行钢结构焊缝的探伤实验。设计为二级焊缝,20%探伤。合格后进行焊缝处的除锈补面漆处理。拆除支撑桁架。2. According to the height, shape and width of the special-shaped steel beams on the roof, bowl-shaped steel pipes are used to build the support frame to meet the pressure and safety requirements, and pass the professional inspection. When assembling the steel girders according to the shape of each girder, the maximum hoisting weight of the tower crane is 5.5 tons, and each girder needs to be hoisted 21 times. Designed as a secondary weld, 20% flaw detection. After qualified, the rust removal and finishing paint treatment on the weld seam shall be carried out. Remove the supporting trusses.

3、安装两侧滑道,检查滑道的稳固性,坡边设置为-1~2mm,安装滑靴,切除钢梁柱脚腹板,设置距地面空间尺寸。3. Install the slides on both sides, check the stability of the slides, set the slope to -1~2mm, install the slide shoes, cut off the web of the steel beam column foot, and set the space from the ground.

4、安装5台液压千斤顶及液压操作系统,调试设备情况开始滑移就位。4. Install 5 sets of hydraulic jacks and hydraulic operating system, and the debugging equipment starts to slip into place.

5、就位后进行校正,补装切掉的腹板开始焊接梁底脚,最后拆除钢梁支撑架体。5. Correction is carried out after it is in place, and the cut-off web plate is replaced to weld the beam foot, and finally the steel beam support frame is removed.

参见附图1,本发明具体包括如下步骤:Referring to accompanying drawing 1, the present invention specifically comprises the following steps:

A)安装滑道预理件;A) Install the slideway prefab;

B)塔吊吊运架体;B) The tower crane lifts the frame body;

C)搭设支撑架体;C) set up a support frame body;

D)分节组装钢梁;D) Assembling steel beams in sections;

E)焊接两榀连杆;E) welding two connecting rods;

F)卸去梁底部支撑及胎架;F) Remove the beam bottom support and tire frame;

G)安装滑道及推进器;G) Install slides and propellers;

H)安装液压控制系统;H) Install the hydraulic control system;

I)调试推进器控制系统;1) debugging the thruster control system;

J)钢梁滑移到设计位置;J) The steel beam slides to the design position;

K)纠校正偏钢梁位置;K) correcting the position of the deflection steel beam;

L)焊接钢梁两侧柱支脚;L) Column feet on both sides of the welded steel beam;

M)重复以上滑移第三根钢梁;M) Repeat above to slide the third steel beam;

N)拆除滑道及推进系统;N) Dismantle slideway and propulsion system;

O)拆除钢梁支撑架体。O) Remove the steel beam support frame body.

本发明的操作要点在于:The main points of operation of the present invention are:

1、滑道设计与施工1. Slide design and construction

1-1、滑道在整个水平推顶中起承重导向和横向限制滑板水平位移的作用。1-1. The slideway acts as a load-bearing guide and laterally restricts the horizontal displacement of the slide during the entire horizontal ejection.

1-2、对于单榀钢架而言,共设置3条滑道。1-2. For a single steel frame, a total of 3 slideways are set.

1-3、滑移将以屋顶800mm厚混凝土梁板作为滑移支撑,滑道主要布置于屋顶表面,并通长进行布置。1-3. The 800mm-thick concrete beam slab on the roof will be used as the sliding support for the sliding. The slideways are mainly arranged on the roof surface and arranged along the entire length.

1-4、滑道采用200X200H钢+16#槽钢进行设置,其槽口向上,H钢下表面通过间断焊固定于屋面专门用于滑移预埋件上。1-4. The slideway is set with 200X200H steel + 16# channel steel, the notch of which is upward, and the lower surface of H steel is fixed on the roof by intermittent welding, which is specially used for sliding embedded parts.

1-5、考虑到钢架在落架过程中,须拆除下部滑道,故各钢架之间的滑道划分成若干段通过临时连接进行组合。1-5. Considering that the lower slideway must be removed during the falling process of the steel frame, the slideways between the steel frames are divided into several sections and assembled through temporary connections.

1-6、保证各接头之间滑道之间的光顺,以确保组合梁在滑移过程中顶推稳定性。1-6. Ensure the smoothness of the slideways between the joints to ensure the stability of the push-up of the composite beam during the sliding process.

2、滑道安装2. Slide installation

2-1、滑移轨道结构在屋面钢结构滑移过程中,起到承重、导向和横向限制支座水平位移的作用。2-1. The sliding track structure plays the role of bearing, guiding and laterally limiting the horizontal displacement of the support during the sliding process of the roof steel structure.

2-2、滑移轨道中心线应尽量与钢架支座中心线重合,以减小滑移过程中桁架支座因受到偏心力而产生不利影响。2-2. The centerline of the sliding track should coincide with the centerline of the steel frame support as much as possible, so as to reduce the adverse effects of the eccentric force on the truss support during the sliding process.

2-3、滑移轨道选用200X200热轧H钢+16#槽钢,材质为Q235B,H钢按间距500mm焊接12mm厚筋板,利用滑移轨道的侧挡板与预埋件固定。2-3. The sliding track is made of 200X200 hot-rolled H steel + 16# channel steel, and the material is Q235B. The H steel is welded with 12mm thick ribs at a distance of 500mm, and is fixed by the side baffle and embedded parts of the sliding track.

2-4、轨道的侧挡板采用规格为-12×50×75mm的钢板,在滑移轨道两侧对称设置,间距为1000mm,起到对H钢翼缘加固、以及抵抗滑移支座处可能侧向推力的作用。2-4. The side baffles of the track are made of steel plates with a specification of -12×50×75mm, which are arranged symmetrically on both sides of the sliding track with a distance of 1000mm, which serves as a reinforcement for the H steel flange and a sliding support Possible side thrust effect.

3、滑块设计3. Slider design

3-1、利用钢架梁翼缘板设置滑块,每侧1个,中间钢架中部支架顶设置1组滑移装置,本工程共设置3个滑移工位。3-1. Use the flange plate of the steel frame beam to set the slider, one on each side, and one set of sliding devices on the top of the middle bracket of the middle steel frame. There are 3 sliding stations in this project.

3-2、两侧滑块设置成“雪橇”式,并将其前部制作成带一定弧度的型式。通过以上设计,可以有效防止滑移支座因滑道不平整卡住“啃轨”的情况出现。3-2. The sliders on both sides are set in a "sled" type, and the front part is made into a type with a certain radian. Through the above design, it can effectively prevent the sliding bearing from being stuck on the "rail" due to the unevenness of the slideway.

3-3、另外,滑道安装的顺直度、滑道中心距的控制等都是防止“卡轨”和“啃轨”的现象发生,现场施工过程中应严格进行工序检查。3-3. In addition, the straightness of the slideway installation and the control of the center distance of the slideway are all to prevent the phenomenon of "rail jamming" and "rail gnawing". The process inspection should be strictly carried out during the on-site construction process.

4顶推点型式4 push point types

4-1、液压顶推器前端通过销轴与被推移构件上的耳板进行连接固定,用以传递水平滑移顶推力。4-1. The front end of the hydraulic pusher is connected and fixed with the lug plate on the pushed member through the pin shaft, so as to transmit the horizontal sliding push force.

4-2、连接耳板厚度为20mm,材质Q345B。4-2. The thickness of the connecting ear plate is 20mm, and the material is Q345B.

4-3、本工程中,连接耳板预装在滑移支座底部附近,每个顶推点设置两块连接耳板。4-3. In this project, the connecting lugs are pre-installed near the bottom of the sliding support, and two connecting lugs are installed at each push point.

4-4、连接耳板分别与钢架翼板焊接连接,焊缝高度为8mm。4-4. The connecting ear plates are welded to the steel frame wing plates respectively, and the weld seam height is 8mm.

5、推顶液压设备选配5. Optional hydraulic equipment for jacking

5-1、满足屋面钢结构各顶推点理论滑移反力的要求,尽量使每台液压顶推器受载均匀。5-1. Satisfy the requirements of the theoretical slip reaction force at each jacking point of the roof steel structure, and try to make each hydraulic jacking unit loaded evenly.

5-2、尽量保证每台液压泵源系统驱动的液压设备数量相等,油管长度一致,减小延迟效应。5-2. Try to ensure that the number of hydraulic equipment driven by each hydraulic pump source system is equal, and the length of the oil pipe is consistent to reduce the delay effect.

5-3、在总体控制时,要认真考虑液压同步滑移系统的安全性和可靠性,降低工程风险。5-3. In the overall control, the safety and reliability of the hydraulic synchronous sliding system should be carefully considered to reduce engineering risks.

6、滑移同步控制6. Slip synchronous control

6-1、应尽量保证各个滑移顶推点的液压滑移设备配置系数基本一致;6-1. Try to ensure that the configuration coefficients of hydraulic sliding equipment at each sliding push point are basically consistent;

6-2、应保证滑移结构的稳定,以便滑移单元结构能正确就位,也即要求各个顶推点滑移过程中能够保持一定的同步性。6-2. The stability of the sliding structure should be ensured so that the sliding unit structure can be correctly positioned, that is to say, it is required to maintain a certain degree of synchronization during the sliding process of each pushing point.

6-3、将每次滑移集群的5台液压顶推器中的一台(主令点)的滑移速度和行程位移值设定为标准值,作为同步控制策略中速度和位移的基准。6-3. Set the sliding speed and stroke displacement value of one of the five hydraulic thrusters (master point) of each sliding cluster as the standard value, as the benchmark of speed and displacement in the synchronous control strategy .

6-4、在中央控制泵的控制下,其余4台液压顶推器分别以各自的位移量 来跟踪比对主令点,根据两点间位移量之差ΔL进行动态调整,保证各顶推点在滑移过程中始终保持同步。6-4. Under the control of the central control pump, the remaining 4 hydraulic pushers track and compare the main command point with their respective displacements, and dynamically adjust according to the difference ΔL in displacement between the two points to ensure that each pusher Points are always kept in sync during sliding.

6-5、通过两点确定一条直线的理论,保证屋面钢结构分组在整个滑移过程中的同步性和稳定性。6-5. The theory of determining a straight line through two points ensures the synchronization and stability of the roof steel structure grouping during the entire sliding process.

7、液压顶推滑移系统调试7. Debugging of hydraulic jacking and sliding system

7-1、顶推点及从动滑移点的临时措施结构状态检查;7-1. Structural status inspection of temporary measures at the push point and driven slip point;

7-2、屋面钢结构加固检查,架体的强度,稳定性及变形情况。7-2. Check the reinforcement of the roof steel structure, the strength, stability and deformation of the frame.

7-3、滑道内杂物是否清楚、黄油是否涂抹。7-3. Whether the debris in the slideway is clear and whether the butter is applied.

7-4、对滑移过程可能产生影响的障碍物检查、清除。7-4. Check and remove obstacles that may affect the sliding process.

7-5、检查液压泵站上所有阀或油管的接头是否有松动,检查溢流阀的调压弹簧处于是否完全放松状态。7-5. Check whether the joints of all valves or oil pipes on the hydraulic pump station are loose, and check whether the pressure regulating spring of the overflow valve is completely relaxed.

7-6、检查液压泵站控制柜与液压顶推器之间电源线、通讯电缆的连接是否正确。7-6. Check whether the connection of the power line and communication cable between the control cabinet of the hydraulic pump station and the hydraulic pusher is correct.

7-7、检查液压泵站与液压顶推器主油缸之间的油管连接是否正确。7-7. Check whether the oil pipe connection between the hydraulic pump station and the main oil cylinder of the hydraulic pusher is correct.

7-8、系统送电,检查液压泵主轴转动方向是否正确。7-8. When the system is powered on, check whether the rotation direction of the main shaft of the hydraulic pump is correct.

7-9、在液压泵站不启动的情况下,手动操作控制柜中相应按钮,检查电磁阀和截止阀的动作是否正常,截止阀编号和液压顶推器编号是否对应。7-9. When the hydraulic pump station does not start, manually operate the corresponding button in the control cabinet to check whether the action of the solenoid valve and the stop valve is normal, and whether the number of the stop valve corresponds to the number of the hydraulic pusher.

7-10、检查行程传感器,使就地控制盒中相应的信号灯发讯。7-10. Check the stroke sensor and make the corresponding signal light in the local control box send out a signal.

7-11、滑移前检查:启动液压泵站,调节一定的压力,伸缩液压顶推器主油缸:检查A腔、B腔的油管连接是否正确;检查截止阀能否截止对应的油缸。7-11. Inspection before sliding: Start the hydraulic pump station, adjust a certain pressure, extend the main cylinder of the hydraulic pusher: check whether the oil pipes in chamber A and chamber B are connected correctly; check whether the stop valve can stop the corresponding oil cylinder.

8、分级加载试滑移8. Graded loading test slip

8-1、待液压顶推系统设备检测无误后开始试滑移。经计算,确定液压顶推器所需的伸缸压力(考虑压力损失)和缩缸压力。8-1. After the hydraulic jacking system equipment is tested correctly, start to try sliding. After calculation, determine the cylinder extension pressure (considering pressure loss) and cylinder retraction pressure required by the hydraulic pusher.

8-2、开始试滑移时,液压顶推器伸缸压力逐渐上调,依次为所需压力的20%,40%,在一切都正常的情况下,可继续加载到60%,80%,90%,95%,100%。8-2. When the sliding test starts, the pressure of the extension cylinder of the hydraulic jack is gradually increased, which is 20% and 40% of the required pressure in turn. When everything is normal, it can continue to be loaded to 60%, 80%, 90%, 95%, 100%.

8-3、屋面钢结构滑移单元刚开始有移动时暂停顶推作业,保持液压顶推设备系统压力。对液压顶推器及设备系统、结构系统进行全面检查。8-3. When the roof steel structure sliding unit starts to move, the jacking operation is suspended, and the pressure of the hydraulic jacking equipment system is maintained. Carry out a comprehensive inspection of hydraulic ejectors, equipment systems, and structural systems.

8-4、在确认整体结构的稳定性及安全性绝无问题的情况下,才能开始正式顶推滑移。8-4. Only when it is confirmed that the stability and safety of the overall structure have absolutely no problems can the formal push and slide begin.

9、滑移过程控制要点9. Main points of sliding process control

9-1、在一切准备工作做完之后,且经过系统的、全面的检查无误后,现场滑移作业总指挥检查并发令后,才能进行正式进行滑移作业。9-1. After all the preparatory work is completed, and after a systematic and comprehensive inspection is correct, the general commander of the on-site skidding operation will check and issue an order before the formal skidding operation can be carried out.

9-2、在液压滑移过程中,注意观测设备系统的压力、荷载变化情况等,并认真做好记录工作。9-2. During the hydraulic sliding process, pay attention to observe the pressure and load changes of the equipment system, and carefully record the work.

9-3、在滑移过程中,测量人员应通过钢卷尺配合测量各牵引点位移的准确数值,以辅助监控滑移单元滑移过程的同步性。9-3. During the sliding process, the measuring personnel should cooperate with the steel tape to measure the accurate value of the displacement of each traction point, so as to assist in monitoring the synchronization of the sliding process of the sliding unit.

9-4、滑移过程中应密切注意滑道、液压顶推器、液压泵源系统等的工作状态。9-4. During the sliding process, pay close attention to the working status of the slideway, hydraulic pusher, hydraulic pump source system, etc.

9-5、现场各作业人员要确保信号畅通,统一指挥。9-5. All operators on site must ensure smooth signal and unified command.

10、预滑移10. Pre-slip

10-1、液压滑移设备系统安装完成后,先进行系统调试,各项工序都已就绪且经检查无误,开始推进屋盖滑移。10-1. After the installation of the hydraulic sliding equipment system is completed, the system debugging is carried out first, and all the procedures are ready and checked, and the roof sliding is started.

10-2、初始滑移单元为第一榀最外缘ZGJ1钢架,重约100吨,加载步骤按照爬行器最初加压为所需压力的40%、60%、80%,在一切都稳定的情况下,可加到100%。在钢架刚开始有位移后暂停。10-2. The initial sliding unit is the first outermost ZGJ1 steel frame, weighing about 100 tons. The loading steps are 40%, 60%, and 80% of the required pressure according to the initial pressure of the crawler. When everything is stable case, it can be added up to 100%. Pause after the steel frame has just started to move.

10-3、全面检查各设备运行正常情况:爬行器夹紧装置、滑移轨道及桁架受力等的变化情况。在一切正常情况下可正式开始滑移。10-3. Comprehensively check the normal operation of each equipment: changes in the clamping device of the crawler, the sliding track and the stress on the truss. Under normal circumstances, the sliding can be officially started.

11、正式滑移11. Formal slip

11-1、根据设计滑移荷载预先设定好泵源压力值,由此控制爬行器最大输出推力,保证整个滑移设施的安全。11-1. Pre-set the pump source pressure value according to the design slip load, thereby controlling the maximum output thrust of the crawler to ensure the safety of the entire slip facility.

11-2、在滑移过程中,测量人员应通过钢卷尺配合测量各滑移点位移的准确数值。11-2. During the sliding process, the surveyors should cooperate with the steel tape to measure the accurate value of the displacement of each sliding point.

11-3、在滑移过程中,测量人员应通过钢卷尺配合测量各滑移点位移的准确数值。11-3. During the sliding process, the surveyors should cooperate with the steel tape to measure the accurate value of the displacement of each sliding point.

11-4、控制系统通过传感器反馈距离信号,控制两组爬行器误差在10mm内,从而控制整个桁架的同步滑移。11-4. The control system feeds back the distance signal through the sensor to control the error of the two sets of crawlers within 10mm, thereby controlling the synchronous sliding of the entire truss.

11-5、滑移钢架基本无横向水平力,且滑移工况下钢架支座受力计算为安全,钢架对应轨道位置设横向挡块,整个滑移过程是安全可靠的。11-5. There is basically no horizontal horizontal force on the sliding steel frame, and the calculation of the force on the steel frame support under the sliding condition is safe. The steel frame is equipped with a horizontal stopper corresponding to the track position, and the entire sliding process is safe and reliable.

11-6、爬行器为液压系统,通过流量控制,爬行器的启动、停止加速度几乎为零,对轨道的冲击力很小。11-6. The crawler is a hydraulic system. Through flow control, the acceleration of the crawler's start and stop is almost zero, and the impact on the track is very small.

12、滑移过程观测12. Slip process observation

12-1、观测同步位移传感器,监测滑移同步情况。12-1. Observe the synchronous displacement sensor to monitor the sliding synchronous situation.

12-2、支座与轨道卡位状况。12-2. The position of the support and the track.

12-3、爬行器夹紧装置与轨道夹紧状况。12-3. Clamping status of crawler clamping device and track.

12-4、累积一次时,推进力变换值是否正常。12-4. When accumulating once, whether the propulsion conversion value is normal.

综上所述,仅为本发明的较佳实施例而已,并非用来限定本发明实施的范围,凡依本发明权利要求范围所述的形状、构造、特征及精神所为的均等变化与修饰,均应包括于本发明的权利要求范围内。In summary, these are only preferred embodiments of the present invention, and are not intended to limit the scope of the present invention. All equivalent changes and modifications are made in accordance with the shape, structure, characteristics and spirit described in the scope of the claims of the present invention. , should be included in the scope of the claims of the present invention.

Claims (1)

1. gliding construction method of a kind of large span different shape heavy type girder steel on Super High roofing, it is characterised in that including as follows Step:
A) slideway built-in fitting is installed;
Ramp design:
1-1, slideway play load-bearing and are oriented to and laterally limit slide plate level displacement in whole horizontal ejection;
1-2, for single Pin steelframes, altogether set 3 slideways;
1-3, sliding will be supported using roof 800mm thickness concrete beam plates as sliding, and slideway is mainly arranged in roof surface, and leads to Length is arranged;
1-4, slideway are configured using 200X200 hot rolling H steel+16# channel-section steels, and upwards, H steel lower surface passes through intermittent weld to its notch Roofing is fixed on dedicated on sliding built-in fitting;
1-5, in view of steelframe during the frame that falls, bottom slideway must be removed, therefore the slideway between each steelframe is divided into some sections It is combined by interim connection;
Fairing between 1-6, each joint of guarantee between slideway, to ensure combination beam pushing tow stability in slipping;
Slideway is installed:
2-1, sliding rail structure play load-bearing, are oriented to and laterally limit bearing horizontal position in layer Steel Structure slipping The effect of shifting;
2-2, sliding rail center line should try one's best and be overlapped with steelframe bearing center line, with truss support in reducing slipping because receiving Have a negative impact to eccentric force;
2-3, sliding rail use 200X200 hot rolling H steel+16# channel-section steels, and material is Q235B, and H steel welds 12mm by spacing 500mm Thick gusset, is fixed using the side shield and built-in fitting of sliding rail;
It is the steel plate of -12 × 50 × 75mm that 2-4, the side shield of track use specification, is symmetrical arranged in sliding rail both sides, spacing It is 1000mm, plays a part of to reinforce the H steel edge of a wing and resist possible lateral thrust at slip support abutment;
Slider designs:
3-1, sliding block is set using steelframe beam flange plate, per side 1, middle steelframe middle bracket top sets 1 group of slide device, altogether 3 sliding stations are set;
3-2, two side slides are arranged to Sledge type, and its front portion is fabricated into the pattern with certain radian;
3-3, the straight degree of slideway installation, the control of slideway centre-to-centre spacing are all the phenomenon generations for preventing clamp rail and gnawing rail, and scene is applied Process inspection is carried out during work;
B) tower crane handling support body;
C supporting frame) is set up;
D) merogenesis assembling girder steel;
E two Pin connecting rods) are welded;
F the support of beam bottom and moulding bed) are shed;
G) installation propeller:
1-1, hydraulic top thruster front end are attached fixation by bearing pin with the otic placode being passed on component, are used to transmit level cunning Move jacking force;
1-2, connection otic placode thickness are 20mm, material Q345B;
In advance near slip support abutment bottom, each pushing tow point sets two pieces of engaging lugs for 1-3, connection otic placode;
1-4, connection otic placode are welded to connect with steelframe wing plate respectively, and weld bead height is 8mm;
H) hydraulic control system is installed:
1-1, ensure each sliding pushing tow point hydraulic pressure slip device configuration coefficients it is basically identical;
1-2, ensure the stabilization of Sliding Structures so that sliding element structure can be correctly in place, namely require that each pushing tow point slid Certain synchronism can be kept in journey;
1-3, by every time sliding cluster 5 hydraulic top thrusters in one sliding velocity and travel displacement value be set as standard Value, as Strategy For Synchronization Control medium velocity and the benchmark of displacement;
1-4, under the control of central controlling pump, remaining 4 hydraulic top thruster tracked with respective displacement respectively comparison master Make a little, the difference Δ L according to point-to-point transmission displacement enters Mobile state adjustment, it is ensured that each pushing tow point remains same in slipping Step;
1-5, the theory that straight line is determined by 2 points, it is ensured that layer Steel Structure is grouped in the synchronism in whole slipping And stability;
I propeller control system) is debugged;
J) girder steel is slid onto design attitude:
1-1, after examination sliding is started after the detection of hydraulic pushing system equipment, determine to stretch cylinder pressure and contracting cylinder needed for hydraulic top thruster Pressure;
1-2, start examination sliding when, hydraulic top thruster is stretched cylinder pressure and is gradually raised, and is followed successively by the 20% of required pressure, 40%, after It is continuous to be loaded into 60%, 80%, 90%, 95%, 100%;
Suspend pushing tow operation when 1-3, layer Steel Structure sliding element just begin with mobile, keep hydraulic pushing device systems pressure Power, is checked hydraulic top thruster and device systems, structural system comprehensively;
1-4, in the case where confirming that integrally-built stability and security are no problem definitely, formal thrusting slip could be started;
Slipping key control point:
1-1, after all preparations are finished, and by system, comprehensively check it is errorless after, scene sliding operation always refer to Wave after checking and issuing an order, just can formally be entered line slip operation;
1-2, in hydraulic pressure slipping, splash pressure, the loads change situation of device systems, and conscientiously make a record work Make;
1-3, in slipping, survey crew should be by the exact value of each towing point displacement of steel tape conjunction measuring, with auxiliary Help the synchronism of monitoring sliding element slipping;
Slideway, hydraulic top thruster, the working condition of hydraulic pump source system should be kept a close eye in 1-4, slipping;
Pre- sliding:
After 1-1, hydraulic pressure slip device system installation, first carry out system debug, every operation it is all ready and on inspection without By mistake, propulsion roof system sliding is started;
2-2, initial slippage unit are a Pin outer most edge ZGJ1 steelframes, weigh about 100 tons, and load step initially adds according to crawl device 40%, 60%, 80% of the pressure for needed for is pressed, is suspended after steelframe just begins with displacement;
3-3, each equipment normal operation situation is checked comprehensively, the change feelings of crawl device clamping device, sliding rail and truss stress It is formal after condition to start sliding;
Formal sliding:
1-1, according to design the pre-set pump outlet pressure value of slip-load, thus control crawl device maximum output thrust, it is ensured that The safety of whole sliding facility;
1-2, in slipping, survey crew should be by the exact value of each creep setpoint displacement of steel tape conjunction measuring;
1-3, control system control two groups of crawl device errors in 10mm, so as to control whole by sensor feedback distance signal The synchronization-sliding of individual truss;
1-4, sliding steelframe are safety, steelframe correspondence substantially without steelframe calculation support under transverse horizontal force, and slip condition Orbital position sets horizontal block;
1-5, crawl device are hydraulic system, and by flow control, the startup of crawl device, acceleration at stall are to the impulsive force of track It is small;
Slipping is observed:
1-1, observation synchronous displacement sensor, monitor sliding synchronization situation;
1-2, bearing and track screens situation;
1-3, crawl device clamping device and railway clamping situation;
1-4, accumulation one time when, whether propulsive force transformed value normal;
K the inclined steel beam position of correction) is entangled;
L) welded steel beam two side columns leg;
M the 3rd girder steel is slid more than) repeating;
N slideway and propulsion system) are removed;
O girder steel supporting frame) is removed.
CN201410034244.1A 2014-01-24 2014-01-24 A kind of gliding construction method of different shape heavy type girder steel of large span on Super High roofing Expired - Fee Related CN103774856B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410034244.1A CN103774856B (en) 2014-01-24 2014-01-24 A kind of gliding construction method of different shape heavy type girder steel of large span on Super High roofing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410034244.1A CN103774856B (en) 2014-01-24 2014-01-24 A kind of gliding construction method of different shape heavy type girder steel of large span on Super High roofing

Publications (2)

Publication Number Publication Date
CN103774856A CN103774856A (en) 2014-05-07
CN103774856B true CN103774856B (en) 2017-05-31

Family

ID=50567563

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410034244.1A Expired - Fee Related CN103774856B (en) 2014-01-24 2014-01-24 A kind of gliding construction method of different shape heavy type girder steel of large span on Super High roofing

Country Status (1)

Country Link
CN (1) CN103774856B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104989114B (en) * 2015-07-15 2017-05-10 上海绿地建设(集团)有限公司 Sliding construction device and method for large-span arc-shaped roof
CN105804412B (en) * 2016-03-14 2018-04-17 中冶天工集团有限公司 Method for quickly correcting lateral over-limit displacement of slippage construction
CN106284668B (en) * 2016-08-29 2019-08-13 江苏江中集团有限公司 A method for installing roof trusses of large-span and large-space steel structures
CN106677542A (en) * 2016-12-08 2017-05-17 中铁三局集团建筑安装工程有限公司 Construction method of roof base truss structure
CN106677554B (en) * 2016-12-29 2019-03-19 中国石油天然气第一建设有限公司 A method of large scale equipment is translated with steel strand wires jack
CN112429666B (en) * 2020-10-16 2022-07-08 中国能源建设集团湖南火电建设有限公司 Installation method and installation system device of megawatt tower type photo-thermal power generation heat collector
CN115538790A (en) * 2022-09-02 2022-12-30 广州市机电安装有限公司 Installation method of long and narrow hyperboloid steel roof
CN115434434B (en) * 2022-09-06 2024-07-05 鞍钢建设集团有限公司 Overhead warehouse support beam sliding installation device
CN116971620A (en) * 2023-07-31 2023-10-31 中冶(上海)钢结构科技有限公司 An unloading-free positioning method for steel structure roofs after accumulated slippage
CN117090393B (en) * 2023-08-24 2025-09-26 中国十七冶集团有限公司 A method for installing a roof skylight steel frame

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07150767A (en) * 1992-12-16 1995-06-13 Takenaka Komuten Co Ltd Beam truss erection method in building with overhead traveling crane
CN101725255A (en) * 2009-11-13 2010-06-09 高申甫 Segmental slipping and assembling process of overhead large-span steel structure
CN202023298U (en) * 2011-03-25 2011-11-02 浙江八达建设集团有限公司 Roof truss-sectioned roof girder structure capable of being hoisted by cross type tower crane

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07150767A (en) * 1992-12-16 1995-06-13 Takenaka Komuten Co Ltd Beam truss erection method in building with overhead traveling crane
CN101725255A (en) * 2009-11-13 2010-06-09 高申甫 Segmental slipping and assembling process of overhead large-span steel structure
CN202023298U (en) * 2011-03-25 2011-11-02 浙江八达建设集团有限公司 Roof truss-sectioned roof girder structure capable of being hoisted by cross type tower crane

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
某体育馆工程大跨度钢梁吊装施工技术;林永雄;《广东建材》;20100630(第6期);说明书第【0004】-【0065】段 *

Also Published As

Publication number Publication date
CN103774856A (en) 2014-05-07

Similar Documents

Publication Publication Date Title
CN103774856B (en) A kind of gliding construction method of different shape heavy type girder steel of large span on Super High roofing
CN108468430B (en) Hoisting and sliding construction method for large-span unequal-height support steel truss structure
CN103967050B (en) Construction system of subway station
CN101200959B (en) Multi-point pushing and accumulative sliding construction method of steel roof truss
CN107013038B (en) A kind of steel structure slipping of building roof lighting Zhongting changes column construction method
CN103899335B (en) Synchronize tunneling operation system and the method for inverted arch synchronization lining
CN105696469A (en) A Construction Method for Pushing and Installing Steel Box Girder with Long-span and Two-way Longitudinal Slope of Extra-Large Bridge
CN109538238A (en) A kind of tunnel arch prefabricated segment construction device and control method
CN103132458B (en) Overall installation method of double-body separable combined beam
CN103821376B (en) Single-layer latticed shell high-altitude oblique rail accumulation slippage construction
CN101831874A (en) Multipoint synchronous push construction method for porous large-span continuous steel truss girder
CN104762882B (en) Bridge subsection hanging apparatus and hanging method
CN101126223A (en) Mobile integral construction platform, construction method thereof and special sling for the same
CN106087768B (en) A kind of method of the assembled mobile formwork in the narrow short transition time section of bridge tunnel
CN115095161A (en) A construction technology of hydraulic jacking and sliding of truss structure
CN109914266A (en) A kind of Large Steel pipeline overhead lifting vertical shift and promote construction method of installation
CN103821087A (en) Precast bridge deck space steel pipe concrete truss composite beam and construction method
CN207525777U (en) Prefabricated utility tunnel multidimension degree directional installation car
CN104372743A (en) Rapid construction method for trestle
CN203878979U (en) Bolt opposite-pulling type track sliding formwork
CN109629439B (en) Construction method of single-tower cable-stayed bridge
CN104060835A (en) Lifting-sliding construction method for single plane truss
CN114232488A (en) Method for erecting main beam of large-span cable-stayed bridge
CN203809016U (en) Inverted arch lining trolley and synchronous tunnel operating system
CN110241728B (en) A temporary steel beam support structure across an existing line and a steel beam construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Liu Rong

Inventor after: Yang Jie

Inventor after: Lu Yuguo

Inventor after: Cheng Jun

Inventor after: Cheng Zhangjianing

Inventor after: Cao Songquan

Inventor after: Tang Xianguo

Inventor after: Wang Enlin

Inventor after: Ji Lilin

Inventor after: Sun Yufeng

Inventor after: Ji Guoxing

Inventor after: Wang Aiyong

Inventor before: Cheng Zhangjianing

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20170418

Address after: 225267 Huashan Road, Jiangdu District, Jiangsu, No. 460, No.

Applicant after: JIANGSU HUWU CONSTRUCTION GROUP CO.,LTD.

Applicant after: JIANGSU College OF ENGINEERING AND TECHNOLOGY

Applicant after: NANTONG University

Address before: Tongzhou District Xingyuan road Jiangsu city of Nantong province sunshine mansion 226300 Building No. 63 room 2201

Applicant before: Cheng Zhangjianing

GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Liu Rong

Inventor after: Wang Aiyong

Inventor after: Yang Jie

Inventor after: Lu Yuguo

Inventor after: Cheng Jun

Inventor after: Cheng Zhangjianing

Inventor after: Cao Songquan

Inventor after: Tang Xianguo

Inventor after: Wang Ling

Inventor after: Wang Enlin

Inventor after: Ji Lilin

Inventor after: Sun Yufeng

Inventor after: Ji Guoxing

Inventor before: Liu Rong

Inventor before: Yang Jie

Inventor before: Lu Yuguo

Inventor before: Cheng Jun

Inventor before: Cheng Zhangjianing

Inventor before: Cao Songquan

Inventor before: Tang Xianguo

Inventor before: Wang Enlin

Inventor before: Ji Lilin

Inventor before: Sun Yufeng

Inventor before: Ji Guoxing

Inventor before: Wang Aiyong

CB03 Change of inventor or designer information
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170531