JP2761527B2 - How to build structures - Google Patents

How to build structures

Info

Publication number
JP2761527B2
JP2761527B2 JP1242490A JP24249089A JP2761527B2 JP 2761527 B2 JP2761527 B2 JP 2761527B2 JP 1242490 A JP1242490 A JP 1242490A JP 24249089 A JP24249089 A JP 24249089A JP 2761527 B2 JP2761527 B2 JP 2761527B2
Authority
JP
Japan
Prior art keywords
construction
work
building
ground
constructed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1242490A
Other languages
Japanese (ja)
Other versions
JPH03107038A (en
Inventor
弘司 近藤
智章 市川
純一郎 前田
信博 奥山
岡野  正
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP1242490A priority Critical patent/JP2761527B2/en
Publication of JPH03107038A publication Critical patent/JPH03107038A/en
Application granted granted Critical
Publication of JP2761527B2 publication Critical patent/JP2761527B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 「産業上の利用分野」 この発明は、建築・土木構造物の構築方法に係り、特
に、構築作業の生産性向上を図りうる構造物の構築方法
に関するものである。
Description: TECHNICAL FIELD The present invention relates to a method for constructing a building or civil engineering structure, and more particularly to a method for constructing a structure capable of improving the productivity of construction work.

「従来の技術およびその課題」 建築・土木構造物の構築作業は、他の技術分野に比較
してその生産性向上の程度が大変遅れており、近年の労
働者不足の現象とあいまって構造物の構築作業の生産性
向上の達成は大きな課題となっている。
"Conventional technology and its problems" In the construction work of architectural and civil engineering structures, the degree of productivity improvement is much slower than in other technical fields, and in conjunction with the recent labor shortage phenomenon, Achieving higher productivity in construction work has become a major issue.

構造物の構築作業の生産性向上を阻害する要因の一つ
としては、建築・土木構造物の作業工程の特殊性があ
る。例えば、一般に複数階の建築物を構築する場合は、
最下階から順に上方に向って施工され、従って、構築作
業は常にその時点で構築が終了した部分の最上階で行な
われることとなる。このため、降雨、強風時等には作業
員が危険な状態にさらされ、あるいは作業を中止せざる
を得なくなることで、作業の進行状況が天候に大きく左
右される結果となる。
One of the factors that hinders the improvement of the productivity of the construction work of a structure is the peculiarity of the work process of the building and civil engineering structure. For example, when building a multi-storey building,
Construction is performed in order from the lowest floor to the top, so that the construction work is always performed on the top floor of the portion where the construction is completed at that time. For this reason, the worker is exposed to a dangerous state during rainfall, strong wind, or the like, or is forced to stop the work, so that the progress of the work greatly depends on the weather.

また、型枠等の仮設材や仮設機械も、作業の進行に伴
って順次上階に盛り替えたりあるいは積層する必要があ
り、最終的な解体撤去も含めて多くの手間や時間を必要
とすると共に、その作業自体危険性を伴う場合も多い。
当然、資材も作業の進行に伴って順次上階に運搬する必
要があり、その運搬作業に多くの手間や時間がかかると
共に、その管理も煩雑なものとなる。
In addition, temporary materials such as formwork and temporary machines also need to be re-arranged or stacked on the upper floor as the work progresses, requiring a lot of labor and time including final dismantling and removal. In addition, the work itself often involves danger.
Naturally, the materials also need to be transported to the upper floors sequentially as the operation progresses, and the transport operation takes a lot of trouble and time, and the management becomes complicated.

さらに、生産性向上のために構築作業の機械化を図ろ
うとする場合、前述のような作業現場の変化に対応しう
る機械の存在を必要とするが、一般に使用されている溶
接ロボット等の自動化機械は可搬性や作業状況の変化に
対する柔軟な対応といった面でその適用に問題が多い。
従って、機械化推進のためには各施工現場専用の機械を
用いるか、あるいは高度な機能を付加することで汎用性
を確保した機械を用いるしかなく、いずれにしてもコス
ト高を招いて現実的でない。
Furthermore, when attempting to mechanize construction work to improve productivity, it is necessary to have a machine that can respond to changes in the work site as described above, but automated machines such as welding robots that are commonly used Has many problems in its application in terms of portability and flexible response to changes in work conditions.
Therefore, in order to promote mechanization, there is no other choice but to use a machine dedicated to each construction site or use a machine that secures versatility by adding advanced functions, and in any case, it is costly and unrealistic .

近年、このような課題を解決することを目的として、
1階部分で構造物をその最上部から構築し、順次ジャッ
キアップしつつ下階部分へと構築を進める、いわゆるジ
ャッキアップ工法と呼ばれる工法が提案されている。こ
の工法によれば、構築物の構築作業を常時一定位置で行
うことができ、機材搬送の手間等を大幅に削減できて構
造物の構築作業の生産性向上を図ることができる。しか
しながら、構造物をジャッキアップする関係上、構築作
業中はこの構造物と地盤との間は縁が切れた状態にあ
り、地震力等の水平力が作用した場合に水平移動あるい
は転倒のおそれがあるため、現実の適用が困難である。
In recent years, with the aim of solving such issues,
There has been proposed a so-called jack-up construction method in which a structure is constructed from the uppermost portion on the first floor portion and the construction is progressively jacked up and progressed to the lower floor portion. According to this construction method, the construction work of the structure can always be performed at a fixed position, the labor for transporting the equipment and the like can be greatly reduced, and the productivity of the construction work of the structure can be improved. However, due to the jacking up of the structure, the edge between the structure and the ground is cut off during the construction work, and horizontal movement or falling may occur when horizontal force such as seismic force acts. Therefore, practical application is difficult.

この発明は前記事情に鑑みてなされたものであり、構
築作業の生産性向上を図ることができ、しかも構築作業
中でも水平力に対する対応を為しうる構造物の構築方法
の提供を目的としている。
The present invention has been made in view of the above circumstances, and it is an object of the present invention to provide a method of constructing a structure capable of improving productivity of a construction operation and capable of coping with a horizontal force even during the construction operation.

「課題を解決するための手段」 本発明は、構造物を構築するに際し、該構造物のコア
部の最下部を所定層分だけ構築した後、その上部におい
て該コア部の最上部を構築すると共に、当該構造物のコ
ア部を除く最上部を地上において構築してそれを前記コ
ア部の最上部に対して連結し、それら連結した最上部を
一括して揚重手段により上方に押し上げて仮支持し、そ
の後、仮支持した最上部の下部に連結せしめてその直下
の部分を地上において構築する工程と、それら連結した
構築部分を一括して押し上げて仮支持する工程とを順次
繰り返すことで構造物全体の構築を完成させるようにし
たものである。
“Means for Solving the Problems” In the present invention, when constructing a structure, after constructing the lowermost portion of the core portion of the structure by a predetermined layer, constructing the uppermost portion of the core portion at the upper portion thereof. At the same time, the uppermost part of the structure except for the core part is constructed on the ground, and it is connected to the uppermost part of the core part. Supporting, then connecting to the lower part of the temporarily supported uppermost part and building the part directly below it on the ground, and sequentially repeating the steps of pushing up these connected building parts collectively and temporarily supporting the structure It is intended to complete the construction of the whole thing.

「実施例」 以下、この発明の実施例について図面を参照して説明
する。
Hereinafter, embodiments of the present invention will be described with reference to the drawings.

第1図ないし第18図は、この発明の構造物の構築方法
を多層建築物の構築方法に適用した一実施例を示す図で
ある。以下、工程順に説明する。
FIGS. 1 to 18 are views showing an embodiment in which the method for constructing a structure of the present invention is applied to a method for constructing a multi-layer building. Hereinafter, description will be made in the order of steps.

(i)コア部構築 第2図に示すように、建築物の中央部に設けられたコ
ア部1を、建築物の他の部分に先行して構築を開始す
る。
(I) Construction of Core Part As shown in FIG. 2, construction of the core part 1 provided at the center of the building is started prior to the other parts of the building.

コア部1の構築高さは任意であるが、1層分程度であ
ると後述する構築中の水平力に対する躯体の支持が弱く
なり、一方、あまり多層に亙って先行して構築したので
は本工法の利点である工期短縮の効果が薄くなる。従っ
て、2層分程度を先行して構築することが好ましい。な
お、コア部1の下端は地盤G中に埋設しておく。
The construction height of the core part 1 is arbitrary, but if it is about one layer, the support of the skeleton against the horizontal force during construction described later becomes weak. The advantage of the construction method, which is the advantage of this method, is reduced. Therefore, it is preferable to construct about two layers in advance. The lower end of the core 1 is buried in the ground G.

コア部1の構築方法は任意であり、従来より周知のよ
うに、鉄筋を四角筒状に組み上げてその内外を型枠で包
囲し、この型枠内にコンクリートを打設して鉄筋コンク
リート造のコア部1を構築してもよい。本実施例では、
第8図ないし第9図に示すような自動上昇型枠2を使用
してコア部1を構築する。
The method of constructing the core part 1 is arbitrary, and as is well known in the art, a reinforcing steel bar is assembled into a rectangular tube, the inside and outside of which are surrounded by a mold, and concrete is poured into the mold to form a reinforced concrete core. The unit 1 may be constructed. In this embodiment,
The core part 1 is constructed using the automatic ascending formwork 2 as shown in FIGS.

この自動上昇型枠2は、略垂直方向に立設された仮設
支柱3と、この支柱3に沿って移動自在に取り付けられ
た型枠部4と、この型枠部4上部に配設されたジャッキ
5と、このジャッキ5上部に配設され、前記支柱3に沿
って移動自在とされたブラケット6とから概略構成され
ている。
The automatic ascending formwork 2 is provided with a temporary support 3 erected in a substantially vertical direction, a formwork 4 movably mounted along the support 3, and an upper portion of the formwork 4. It is roughly constituted by a jack 5 and a bracket 6 disposed on the jack 5 and movable along the column 3.

また、型枠部4は、前記ジャッキ5下方に位置するフ
レーム7と、このフレーム7の下部前後(第8図におい
て左右)からそれぞれ下方に延出され、フレーム7に回
動自在に支持された1対のヨーク8、8と、これらヨー
ク8、8の相対向する面にそれぞれ設けられた堰板9、
9と、相対向するヨーク8、8に向って突出された脱型
用ジャッキ10、10と、これら脱型用ジャッキ10、10間に
回動自在に連結されたロッド11とから構成されている。
Further, the formwork portion 4 extends downward from the frame 7 located below the jack 5 and the front and rear portions (left and right in FIG. 8) of the lower portion of the frame 7 and is rotatably supported by the frame 7. A pair of yokes 8, 8, and dam plates 9 provided on opposing surfaces of the yokes 8, 8;
9, a releasing jack 10, 10 protruding toward the opposed yokes 8, 8, and a rod 11 rotatably connected between the releasing jacks 10, 10. .

なお、これらジャッキ5とフレーム7、ジャッキ5と
ブラケット6、ブラケット6と支柱3、フレーム7と支
柱3はそれぞれボルト等により連結、固定可能とされて
いる。また、前記堰板9、9間の距離は、これらが互い
に平行に配置された状態で構築すべきコア部1の壁厚に
等しくなるように設定されている。
The jack 5 and the frame 7, the jack 5 and the bracket 6, the bracket 6 and the support 3, and the frame 7 and the support 3 can be connected and fixed by bolts or the like. The distance between the weir plates 9, 9 is set so as to be equal to the wall thickness of the core portion 1 to be constructed in a state where they are arranged in parallel with each other.

以上のような構成の自動上昇型枠2を用いてコア部1
を構築するには、フレーム7を支柱3に固定すると共に
ブラケット6を支柱3に対して移動自在な状態とし、次
いでジャッキ5を伸長させることでブラケット6のみを
上昇させた後、逆にブラケット6を支柱3に固定すると
共にフレーム7を支柱3に対して移動自在な状態とし、
今度はジャッキ5を短縮させることでフレーム7、すな
わち型枠部4全体を上昇させて堰板9、9間にコンクリ
ート打設用の間隙を形成する。そして、これら堰板9、
9間に鉄筋を配設した後にコンクリートを打設し、コン
クリートの硬化を待って前述した型枠部4上昇工程を行
い、これらコンクリート打設工程及び型枠部4上昇工程
を繰り返すことで、下部から上部に向ってコア部1を構
築するのである。そして、2層分のコア部1の構築が終
了したら、その上端を塞ぐようにコア内スラブ31を構築
する。
The core part 1 is formed using the automatic ascending formwork 2 having the above-described configuration.
Is constructed, the frame 7 is fixed to the column 3 and the bracket 6 is made movable with respect to the column 3, and then the jack 5 is extended to raise only the bracket 6. Is fixed to the support 3 and the frame 7 is movable with respect to the support 3,
Next, by shortening the jack 5, the frame 7, that is, the entire formwork portion 4 is raised, and a gap for concrete casting is formed between the dam plates 9, 9. And these dams 9,
Concrete is cast after the reinforcing bars are arranged between the steel sheets 9, and after the concrete is hardened, the above-described step of raising the form part 4 is performed. By repeating the concrete placing step and the step of raising the form part 4, the lower part is formed. The core part 1 is constructed from above to the upper part. When the construction of the core portion 1 for two layers is completed, the in-core slab 31 is constructed so as to cover the upper end thereof.

また、後述する躯体構築作業に先行して、第3図に示
すように、建築物の柱が立設される箇所の地面にもジャ
ッキ(揚重手段)12、12、…を設置する。これらジャッ
キ12、…は、後述する建築物の躯体上昇工程時に使用さ
れるものであり、最下階構築の際には建築物の躯体のほ
ぼ全体を押し上げるだけの能力を必要とする。但し、10
階建程度の建築物であれば、1000t程度の荷重を発生で
きれば十分であり、周知の油圧ジャッキ等が好適に適用
可能である。
Prior to the frame building work described later, jacks (lifting means) 12, 12,... Are also installed on the ground where the pillars of the building are erected, as shown in FIG. These jacks 12,... Are used at the time of a skeleton raising process of a building, which will be described later. When the lowest floor is constructed, it is necessary to have an ability to push up substantially the entire skeleton of the building. However, 10
In the case of a building of about a story, it is sufficient that a load of about 1000 t can be generated, and a well-known hydraulic jack or the like can be suitably applied.

さらに、第3図に示すように、スラブ型枠23およびコ
アスラブ型枠32をそれぞれ支柱25,33により支持して設
置する。
Further, as shown in FIG. 3, the slab form 23 and the core slab form 32 are supported and installed by the supports 25 and 33, respectively.

このスラブ型枠23は、第16図ないし第18図に示すよう
に、同一階に位置する梁14、…で囲繞される平面内に配
置される矩形板状のデッキプレート51と、このデッキプ
レート51上に配設されてスラブ24下面に埋殺される同様
に矩形板状の波状板52とからなり、このスラブ型枠23
は、仮設梁53、53を介して上記支柱25、…により支持さ
れている。
As shown in FIGS. 16 to 18, the slab formwork 23 includes a rectangular plate-like deck plate 51 arranged in a plane surrounded by beams 14,. The slab form frame 23 comprises a similarly rectangular plate-like wavy plate 52 which is disposed on
Are supported by the columns 25,... Via the temporary beams 53, 53.

なお、本実施例では、スラブ24の構築工程は後述する
柱及び梁構築工程に遅れて行なわれるため、スラブ型枠
23は地面から2層分だけ上方に離間されて配置されてい
る。同様に、コアスラブ型枠32も支柱33、…を介して建
築物の塔屋(第14図ないし第15図参照)の突出高さだけ
上方に離間されて配置されている。
In the present embodiment, since the slab 24 building process is performed later than the column and beam building process described below,
Reference numeral 23 is arranged two layers above the ground. Similarly, the core slab formwork 32 is also spaced upward by the projecting height of the tower of the building (see FIGS. 14 to 15) via the columns 33,.

(ii)躯体構築開始 2層分程度のコア部1を先行して構築したら、第4図
に示すように、このコア部1に沿って建築物の最上部か
ら柱、梁等の躯体の構築作業を開始する。なお、本実施
例の建築物はいわゆるセンターコア構造と呼ばれる構造
を採用しており、平面視した状態でコア部1が建築物の
略中央に位置している。但し、片コア構造であっても本
実施例に準じて行なえることは言うまでもない。
(Ii) Start of construction of the skeleton Once the core part 1 of about two layers has been constructed in advance, as shown in Fig. 4, construction of the skeleton such as columns and beams from the top of the building along this core part 1 Start working. The building according to the present embodiment employs a structure called a so-called center core structure, and the core unit 1 is located substantially at the center of the building in a plan view. However, it goes without saying that even a single-core structure can be performed according to the present embodiment.

建築物の躯体を構成する柱、梁としては、鉄骨造、鉄
筋コンクリート造、あるいは鉄骨鉄筋コンクリート造等
周知の柱、梁から任意に選択可能であるが、本実施例で
は柱13は鉄筋コンクリート造、梁14は鉄骨造とされてい
る。
The pillars and beams that constitute the building body of the building can be arbitrarily selected from well-known columns and beams such as steel structures, reinforced concrete structures, and steel-framed reinforced concrete structures. Is said to be steel framed.

すなわち、第10図ないし第12図に示すように、垂直方
向に延在する主筋15、15、…及びこれら主筋15、…の外
周に巻回された帯筋16、…が四角柱状のコンクリート17
内に埋設されて柱13が構成され、一方、梁14はH型鋼か
ら構成されている。このため、柱13と梁14との交叉部で
ある仕口部には特殊な仕口部材18が配設されている。
That is, as shown in FIGS. 10 to 12, the main reinforcements 15, 15,... Extending in the vertical direction, and the straps 16, wound around the outer periphery of the main reinforcements 15,.
The beam 13 is buried in the inside, while the beam 14 is made of H-section steel. For this reason, a special port member 18 is provided at the port, which is the intersection of the pillar 13 and the beam 14.

この仕口部材18は、第10図に示すように、梁14と同一
の断面形状を有するH型鋼が平面視十字状に交叉した形
状に形成された取付部材19と、前記柱13と同一幅に形成
されて取付部材19の中央部を囲繞する角筒状の端面箱20
と、端面箱20の上面または下面を塞ぐ矩形板状の柱用底
型枠21から概略構成されている。この柱用底型枠21に
は、前記主筋15、…に対応する位置に貫通孔22、…が穿
設されている。
As shown in FIG. 10, the connection member 18 has an attachment member 19 formed in a cross shape of an H-shaped steel having the same cross-sectional shape as the beam 14 in a cross shape in a plan view, and the same width as the column 13. And a rectangular end box 20 surrounding the center of the mounting member 19.
And a bottom plate frame 21 for a rectangular plate that covers the upper or lower surface of the end box 20. In the bottom frame 21 for columns, through holes 22 are formed at positions corresponding to the main bars 15,.

従って、取付部材19の四方から梁14、…が接合される
と共に、柱用底型枠21の貫通孔22、…に主筋15、…が挿
通されて固定され、さらに端面箱20内にコンクリート17
が打設されることで、柱13と梁14との接合が行なわれ
る。
Therefore, the beams 14 are joined from all sides of the mounting member 19, and the main reinforcements 15 are inserted and fixed in the through holes 22 of the bottom formwork 21 for columns.
The pillar 13 and the beam 14 are joined by being cast.

さて、前述の基礎工事が終了したら、第10図に示すよ
うに、地面に設置されたジャッキ12、…の上面に前記柱
用底型枠21を載置し、さらにその上に前記仕口部材18を
載置する。そして、ジャッキ12、…上に仕口部材18、…
が配設されたら、これら仕口部材18、…間を前記梁14、
…で連結する。
When the above-mentioned foundation work is completed, as shown in FIG. 10, the column bottom formwork 21 is placed on the upper surface of the jacks 12,... Installed on the ground, and the connection member is further placed thereon. Place 18 on it. And, on the jack 12, ... the connection member 18, on the ...
Is disposed, the beam 14,
Connect with ...

また、最初の構築作業においては、後述するジャッキ
12、…による押し上げ工程を省く目的で、3層分の梁1
4、14及びこの間に位置する柱13を同時に構築する。す
なわち、屋上を構成する梁14と、最上階及びその下の階
を構成する梁14、14である。従って、ジャッキ12、…直
上に配設された梁14、…及び仕口部材18、…から1層分
ないし2層分だけ上方に離間した位置に更に梁14、…及
び仕口部材18、…を配設する。これら梁14、…及び仕口
部材18、…は支柱25、…により支持すればよい。また、
前記コア部1に接する部分には、このコア部1を囲繞す
るように梁(図示略)を環状に架設しておく。
In addition, in the first construction work,
12, 3 beams 1
4, 14 and the pillar 13 located therebetween are simultaneously constructed. That is, the beam 14 that constitutes the rooftop, and the beams 14 that constitute the top floor and the floor below it. Therefore, the beams 14,... And the connecting members 18,... Are further separated by one or two layers from the jacks 12,. Is arranged. The connecting members 18 may be supported by the columns 25. Also,
A beam (not shown) is annularly provided around the core portion 1 so as to surround the core portion 1.

そして、これら上下方向に並設された仕口部材18、18
間に1層分より若干長目に切断された主筋15、…配設
し、その上下を前記柱用底型枠21、21に固定する。さら
に、主筋15、…の外周に帯筋16、…を巻回してから、こ
の周囲に柱用型枠26、…を配設する。これと同時に、ス
ラブ型枠23、…上にスラブ24用の鉄筋(図示せず)を配
設する。この状態で、柱13及びスラブ24のコンクリート
を打設し、所定の強度が発現した段階で柱用型枠26、…
の脱型を行う。以上により、コア部を除く構造物の最上
部が地上において構築される。なお、柱13のコンクリー
ト打設は、例えば第11図ないし第12図に示すように、上
階の柱13に柱用型枠26、…内に連通する貫通孔28を設け
ており、この貫通孔28を介して打設するような方法が挙
げられる。
Then, the connection members 18, 18 arranged in parallel in the vertical direction
The main bars 15, which are cut to be slightly longer than one layer, are disposed therebetween, and the upper and lower portions thereof are fixed to the column bottom formwork 21, 21. Are wound around the outer periphery of the main reinforcements 15, and then the column formwork 26,. At the same time, rebar (not shown) for the slab 24 is disposed on the slab formwork 23,. In this state, concrete for the columns 13 and the slabs 24 is cast, and when the predetermined strength is developed, the column formwork 26,.
Of the mold. As described above, the uppermost portion of the structure excluding the core portion is constructed on the ground. In addition, as shown in FIGS. 11 and 12, for example, as shown in FIGS. 11 and 12, a concrete hole of the pillar 13 is provided with a through hole 28 communicating with the pillar formwork 26,. For example, a method in which the material is cast through the hole 28 is used.

一方、第4図に示すように、コア部1の最上部たる塔
屋35の側壁部も同時に構築する。この塔屋35の構築には
前述した自動上昇型枠は使用し難いので、通常の塔屋施
工のように筒状の鉄筋を組んでその内外を型枠で囲繞し
てからコンクリートを打設するような構築方法が採られ
る。この場合、塔屋35と既に構築されているコア部1と
の間は縁切り状態としておく。
On the other hand, as shown in FIG. 4, the side wall of the tower 35, which is the uppermost part of the core 1, is also constructed at the same time. Since the above-mentioned automatic ascending formwork is difficult to use for the construction of this tower 35, it is difficult to construct concrete towers, construct a cylindrical reinforcing bar, surround the inside and outside with the form, and then cast concrete. A construction method is adopted. In this case, the space between the tower 35 and the core part 1 that has already been constructed is cut off.

(iii)躯体押し上げ 柱13、…が自立可能な状態まで硬化した段階で、第6
図に示すように、建築物の躯体を1層分上方に押し上げ
る。
(Iii) Pushing up the skeleton When the pillars 13,.
As shown in the figure, the building body of the building is pushed up by one layer.

まず、第5図に示すように、ジャッキ12、…を若干伸
長させてから前記塔屋35を既に構築された建築物の躯体
に連結する。
First, as shown in FIG. 5, the jacks 12,... Are slightly extended, and then the tower 35 is connected to the frame of the already constructed building.

この後、第13図(イ)に示すように、ジャッキ12、…
をさらに所定長さ伸長させる。次に、同図(ロ)に示す
ように、梁14、…と地面との間に支持材37、…を挿入
し、さらに、同図(ハ)に示すように、ジャッキ12、…
を元の位置に短縮してこのジャッキ12、…と仕口部材18
との間に補助材38、…を挿入する。そして、以上の工程
を繰り返して、同図(ニ)の状態を経て同図(ホ)に示
すように躯体を1層分押し上げた段階で、同図(ヘ)に
示すようにジャッキ6、…を元の位置に短縮して補助材
38、…を全て取り除く。
Thereafter, as shown in FIG.
Is further extended for a predetermined length. Next, as shown in FIG. 2 (b), support members 37,... Are inserted between the beams 14,... And the ground, and further, as shown in FIG.
To the original position, this jack 12, ... and the connection member 18
Insert auxiliary members 38,. Then, the above steps are repeated, and after the state shown in FIG. 5D, the frame is pushed up by one layer as shown in FIG. To the original position
38, remove all ...

なお、前記スラブ型枠23、…は支柱25、…を介して地
面に支持されているので、建築物の躯体の押し上げに伴
い型枠の脱型は自動的に行なわれる。
Since the slab formwork 23,... Is supported on the ground via the columns 25,..., The formwork is automatically removed as the frame of the building is pushed up.

(Iv)構築作業継続 建築物の躯体上昇工程が終了したら、前述の工程によ
り、第6図に示すように、既に構築された部分の直下階
に相当する柱13、梁14及びスラブ24構築作業を行う。そ
して、柱13、梁14及びスラブ24構築作業が終了したら、
前述のようにジャッキ12、…を用いて躯体を押し上げ、
さらにこれら工程を繰り返して、第1図ないし第7図に
示すように、順次下階へと建築物の構築作業を継続す
る。
(Iv) Continuing the construction work After the building frame raising step is completed, as shown in FIG. 6, the column 13, beam 14, and slab 24 construction work corresponding to the immediately lower floor of the already constructed part is performed by the above-described process. I do. And, when the construction work of the columns 13, beams 14, and slabs 24 is completed,
Push up the skeleton using jacks 12, as described above,
Further, these steps are repeated, and the construction work of the building is sequentially continued to the lower floor as shown in FIGS. 1 to 7.

このようにして、建築物の躯体部分は主に地上1階に
おいて構築され、構築が終了した部分については順次上
方に押し上げられてゆくので、外壁工事、設備工事、仕
上工事は地上2階以上の上階において作業階を決定して
行えばよい。
In this way, the skeleton of the building is mainly constructed on the first floor above the ground, and the completed construction is pushed up sequentially. The work floor may be determined on the upper floor.

例えば、階段を鉄骨造とするならば、この階段取付工
事は地上2階において行えばよい。一方、段階を鉄筋コ
ンクリート造とする場合、前述のスラブ24の場合と同様
に地面に底型枠だけ配置しておけば、躯体の押し上げ工
程時に自動的に脱型が行なわれて好ましい。
For example, if the stairs are made of steel, this stair mounting work may be performed on the second floor above the ground. On the other hand, when the step is made of reinforced concrete, it is preferable to dispose only the bottom formwork on the ground as in the case of the above-described slab 24, because the mold is automatically removed during the step of pushing up the frame.

このように、地上2階においてスラブ24、外壁、階段
の構築作業を行い、地上3階において間仕切壁、窓、電
気、設備作業を行い、地上4階において天井、電気、設
備作業を行い、地上5階において床等の仕上作業を行う
といったように、順次上階に移動するように従って建築
物の構築作業の工程が進行するようにすれば、各階の作
業を並行して行うことができ、大変能率的である。ま
た、各階における作業を固定化することで、資材、人材
の配置も明確化され、その管理も容易なものとなる。
In this way, the slab 24, the outer wall, and the stairs are constructed on the second floor above the ground, the partition walls, windows, electricity, and facility work are performed on the third floor above, and the ceiling, electricity, and facility work are performed on the fourth floor above the ground. If the process of building construction progresses as moving to the upper floor sequentially, such as finishing the floor on the fifth floor, the work on each floor can be performed in parallel, It is efficient. In addition, by fixing the work on each floor, the arrangement of materials and human resources is clarified, and the management thereof becomes easy.

なお、これら各階への資材や搬送は、前記コア部1内
に仮設リフトを設けて、この仮設リフトにより順次行え
ばよい。特に、本実施例では、重量を有する鉄骨、鉄筋
等は地面に吊り降ろせばよく、従って、仮設リフトも小
規模なもので済む。さらに、一般の建築物の構築作業で
あれば、前述のように各階における作業工程を定めて作
業を行えば5階程度まででほとんどの作業は完了するた
め、仮設リフトを設置すべき階数も少なくて済む。
The materials and transport to these floors may be performed by providing a temporary lift in the core unit 1 and sequentially using the temporary lift. In particular, in the present embodiment, the heavy steel frame, the reinforcing bar, and the like may be hung on the ground, and therefore the temporary lift may be small. Furthermore, in the case of construction work of a general building, if the work process on each floor is determined and the work is performed as described above, most work is completed up to about five floors, so that the number of floors on which a temporary lift should be installed is small. I can do it.

そして、以上のような工程を繰り返すことで建築物の
躯体構築作業を地上1階部分まで完了し、型枠等の仮設
機材を撤去すると共に、前述した電気、設備、仕上作業
が完了した時点で、第14図ないし第15図に示すような建
築物40の構築作業が完了する。
By repeating the above steps, the building construction of the building is completed up to the first floor, the temporary equipment such as formwork is removed, and the electricity, equipment, and finishing work described above are completed. The construction of the building 40 as shown in FIGS. 14 to 15 is completed.

このように、本実施例では、建築物40の躯体構築作業
を地上1階で行うと共に、建築物40の最上部から構築を
開始して、構築が終了した部分から順次ジャッキ12、…
を用いて躯体を押し上げることで順次下階へと建築物40
の構築作業を進めているので、躯体構築以外の作業も含
めて各作業を常時一定位置で行うことができる。しか
も、各作業を行う位置を地上1階等の低位置に固定して
いるため、型枠等の仮設材や仮設機械等の盛り替え、積
層、更には解体撤去等の手間がかからず、作業の生産性
向上に大きく寄与できる。そして、このようにして各作
業を一定位置で行えることから、例えば、溶接ロボット
等を地上1階に常設して溶接作業の自動化を図ることが
でき、各作業への自動化機械導入を現実のものとするこ
とができる。
As described above, in this embodiment, the skeleton building work of the building 40 is performed on the first floor above the ground, the building is started from the top of the building 40, and the jacks 12,.
The building 40 is sequentially raised to the lower floor by pushing up the building using
Since the construction work is proceeding, each work including the work other than the construction of the skeleton can always be performed at a fixed position. In addition, since the position where each work is performed is fixed at a low position such as the first floor above the ground, there is no need for reworking temporary materials such as formwork or temporary machines, stacking, dismantling and removing, etc. It can greatly contribute to the improvement of work productivity. And since each work can be performed at a fixed position in this way, for example, a welding robot or the like can be permanently installed on the first floor to automate the welding work, and the introduction of an automated machine into each work can be realized. It can be.

また、従来のように作業員が最上階にまで登らずに地
上に近い位置において作業することができ、その安全性
確保も容易なものとなる。
In addition, the worker can work at a position close to the ground without climbing to the top floor as in the related art, so that safety can be easily ensured.

さらに、本実施例では作業位置を固定することができ
るため、建築物40の建築作業全体を通して資材搬入工程
を一定のものとすることができ、手間、時間の削減が図
れると共に、管理が容易なものとなる。特に、本実施例
では、躯体構築作業を地上1階で行っているので、鉄
骨、鉄筋等の資材搬入は搬送用のトラックから水平移動
すれば足り、従来のように鉄骨等の大重量の部材を上階
に揚重する必要がないため、クレーン吊トラックのクレ
ーン程度で鉄骨等の搬入作業が十分可能である。
Further, in this embodiment, since the work position can be fixed, the material loading process can be made constant throughout the entire construction work of the building 40, and labor and time can be reduced, and management is easy. It will be. In particular, in the present embodiment, since the skeleton building work is performed on the first floor above the ground, it is sufficient to move materials such as steel frames and rebars horizontally from a transport truck, and as in the conventional case, heavy materials such as steel frames. Since it is not necessary to lift the cranes on the upper floor, the work of carrying in the steel frame or the like can be sufficiently performed with a crane of a crane suspension truck.

しかも、本実施例では建築物40の最上部から構築を開
始しているので、屋上の防水工事や塔屋の構築等手間の
かかる部分の工事が余裕をもって施工できる。
In addition, in the present embodiment, since the construction is started from the top of the building 40, it is possible to carry out the construction of the rooftop waterproofing work and the construction of the tower, which is troublesome, with a margin.

そして、本実施例では、建築物40の躯体構築に先立っ
てコア部1の最下部の構築を行っており、躯体構築作業
中や躯体押し上げ作業中に地震力等の水平力が作用して
も、コア部1の存在により構築中の躯体が地盤に支持さ
れ、建築物40の水平移動や転倒のおそれがなくて安全な
施工が可能となる。しかも、コア部1の最上部である塔
屋35と、コア部1の周囲の最上部の躯体とを連結した後
は、構築作業を行う地上部分は建築物の屋上部で覆われ
るので、天候に左右されずに作業を行える、という利点
もある。
In this embodiment, the lowermost part of the core part 1 is constructed prior to the construction of the skeleton of the building 40, and even if a horizontal force such as an earthquake force acts during the skeleton construction work or the skeleton building work. The construction under construction is supported by the ground due to the presence of the core portion 1, and there is no fear of the building 40 moving horizontally or overturning, thereby enabling safe construction. In addition, after connecting the tower 35, which is the uppermost part of the core part 1, to the uppermost skeleton around the core part 1, the above-ground part where the construction work is performed is covered by the rooftop of the building. There is also an advantage that work can be performed without being affected.

なお、この発明の構造物の構築方法は、その細部が前
記実施例に限定されず、種々の変形例が可能である。一
例として、前記実施例では柱が鉄筋コンクリート造、梁
が鉄骨造であったが、これに限定されず、例えば梁が鉄
筋コンクリート造であってもよい。この場合、前述した
スラブ24や階段のように地上1階に梁の底型枠を設けて
おけば、躯体押し上げ工程により自動的に脱型が行なわ
れて好ましい。
The details of the method of constructing a structure according to the present invention are not limited to the above-described embodiment, and various modifications are possible. As an example, in the above-described embodiment, the columns are made of reinforced concrete and the beams are made of steel. However, the present invention is not limited to this. For example, the beams may be made of reinforced concrete. In this case, it is preferable to provide a bottom formwork of the beam on the first floor above the ground as in the slab 24 and the stairs described above, because the mold is automatically removed by the frame lifting process.

「発明の効果」 以上詳細に説明したように、この発明は、構造物を構
築するに際し、該構造物のコア部の最下部を所定層分だ
け構築した後、その上部において該コア部の最上部を構
築すると共に、当該構造物のコア部を除く最上部を地上
において構築してそれを前記コア部の最上部に対して連
結し、それら連結した最上部を一括して揚重手段により
上方に押し上げて仮支持し、その後、仮支持した最上部
の下部に連結せしめてその直下の部分を地上において構
築する工程と、それら連結した構築部分を一括して押し
上げて仮支持する工程とを順次繰り返すことで構造物全
体の構築を完成させる方法であるので、構造物の構築作
業以外の作業も含めて各作業を常時一定位置で行うこと
ができる。
[Effects of the Invention] As described in detail above, the present invention, when constructing a structure, constructs the lowermost portion of the core portion of the structure by a predetermined layer, and then constructs the lowermost portion of the core portion at the upper portion. While constructing the upper part, the uppermost part except the core part of the structure is constructed on the ground, and it is connected to the uppermost part of the core part, and the connected uppermost parts are collectively lifted by lifting means. The process of connecting to the lower part of the temporarily supported uppermost part and constructing the part immediately below it on the ground, and the step of collectively pushing up these connected construction parts and temporarily supporting them are sequentially performed Since it is a method of completing the construction of the entire structure by repeating, each work including the work other than the construction work of the structure can always be performed at a fixed position.

しかも、構造物の構築作業を地上で行っているため、
型枠等の仮設材や仮設機械等の盛り替え、積層、更には
解体撤去等の手間がかからず、作業の生産性向上に大き
く寄与できる。さらに、作業位置が固定できることで、
各作業位置に自動化機械を常設する等することで、作業
の自動化を図りうる。また、従来のように作業員が最上
階にまで登らずに地上に近い位置において作業すること
ができ、その安全性確保も容易なものとなる。
In addition, because the construction work of the structure is done on the ground,
This eliminates the need for changing and stacking temporary materials such as formwork and temporary machines, laminating, and dismantling, thereby greatly contributing to improved work productivity. Furthermore, because the working position can be fixed,
By permanently installing an automation machine at each work position, the work can be automated. In addition, the worker can work at a position close to the ground without climbing to the top floor as in the related art, so that safety can be easily ensured.

さらに、作業位置の固定化により構造物の構築作業全
体を通して資材搬入工程を一定のものとすることがで
き、手間、時間の削減が図れると共に、管理が容易なも
のとなる。特に、この発明では、構造物の構築作業を地
上で行っているので、鉄骨、鉄筋等の資材搬入はトラッ
ク等からクレーン等で水平移動すれば足り、従来のよう
に鉄骨等の大重量の部材を上階に揚重する必要がないた
め、クレーン付トラックのクレーン程度で資材搬入作業
が十分可能である。
Further, by fixing the working position, the material carrying-in process can be made constant throughout the construction work of the structure, so that the labor and time can be reduced and the management can be easily performed. In particular, in the present invention, since the construction work of the structure is performed on the ground, it is sufficient to horizontally move materials such as steel frames and reinforcing bars from a truck or the like with a crane or the like. Since it is not necessary to lift the cargo to the upper floor, the work of carrying in the material can be sufficiently performed with the crane of the truck with the crane.

しかも、この発明では構造物の最上部から構築を開始
しているので、屋上の防水工事等手間のかかる部分の工
事が余裕をもって施工できる。
In addition, since construction is started from the top of the structure according to the present invention, construction of a troublesome portion such as rooftop waterproofing work can be performed with a margin.

そして、この発明では、構造物の躯体構築に先立って
コア部の最下部の構築を行っており、躯体構築作業中や
躯体押し上げ作業中に地震力等の水平力が作用しても、
コア部の存在により構築中の躯体が地盤に支持され、構
造物の水平移動や転倒のおそれがなくて安全な施工が可
能となる。しかも、構造物の最上部から構築を開始する
ので、構築作業を行う地上部分はこの構造物の屋上部に
より覆われ、天候を気にせずに構築作業を行うことがで
きる、という利点もある。
And, in this invention, the lowermost part of the core portion is constructed prior to the construction of the skeleton of the structure, and even when a horizontal force such as an earthquake force acts during the skeleton construction work or the skeleton pushing work,
Due to the presence of the core portion, the skeleton under construction is supported by the ground, and there is no risk of horizontal movement or falling of the structure, and safe construction is possible. In addition, since the construction is started from the top of the structure, the ground portion on which the construction work is performed is covered by the roof of the structure, and there is an advantage that the construction work can be performed without worrying about the weather.

【図面の簡単な説明】[Brief description of the drawings]

第1図ないし第18図は、この発明の一実施例である構造
物の構築方法を説明するための図であり、第1図は構築
途中の状態を示す断面図、第2図ないし第7図は工程の
順序を示す断面図、第8図は自動上昇型枠を示す正面
図、第9図は同平面図、第10図はジャッキ上への仕口部
材の配置方法を示す斜視図、第11図は鉄筋の配設方法を
示す斜視図、第12図は柱用型枠の配置状態を示す斜視
図、第13図は躯体上昇工程を示す断面図、第14図は本実
施例により構築された建築物の正面図、第15図は同平面
図、第16図ないし第18図はスラブ型枠を取り出して示し
た図であって、第16図は平面図、第17図は第16図のA−
A′線に沿う矢視断面図、第18図は第16図のB−B′線
に沿う矢視断面図である。 1……コア部、2……自動上昇型枠、4……型枠部、12
……ジャッキ(揚重手段)、13……柱、14……梁、24…
…スラブ、35……塔屋、40……建築物。
1 to 18 are views for explaining a method of constructing a structure according to one embodiment of the present invention. FIG. 1 is a cross-sectional view showing a state during construction, and FIGS. FIG. 8 is a sectional view showing the sequence of steps, FIG. 8 is a front view showing an automatic ascending formwork, FIG. 9 is a plan view of the same, FIG. 10 is a perspective view showing a method of arranging a connection member on a jack, FIG. 11 is a perspective view showing an arrangement method of a reinforcing bar, FIG. 12 is a perspective view showing an arrangement state of a column formwork, FIG. 13 is a cross-sectional view showing a frame raising process, and FIG. FIG. 15 is a front view of the constructed building, FIG. 15 is a plan view of the same, FIGS. 16 to 18 are diagrams showing the slab form taken out, FIG. 16 is a plan view, and FIG. A- in Fig. 16
FIG. 18 is a cross-sectional view taken along the line A ′, and FIG. 18 is a cross-sectional view taken along the line BB ′ of FIG. 1 ... core part, 2 ... automatic ascending formwork, 4 ... formwork part, 12
... jack (lifting means), 13 ... pillar, 14 ... beam, 24 ...
... Slab, 35 ... Tower, 40 ... Building.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 奥山 信博 東京都中央区京橋2丁目16番1号 清水 建設株式会社内 (72)発明者 岡野 正 東京都中央区京橋2丁目16番1号 清水 建設株式会社内 (56)参考文献 特公 昭50−27652(JP,B2) ────────────────────────────────────────────────── ─── Continuing on the front page (72) Inventor Nobuhiro Okuyama 2-16-1, Kyobashi, Chuo-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Tadashi Okano 2-16-1, Kyobashi, Chuo-ku, Tokyo Shimizu Construction Incorporated company (56) References JP-B-50-27652 (JP, B2)

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】構造物を構築するに際し、該構造物のコア
部の最下部を所定層分だけ構築した後、その上部におい
て該コア部の最上部を構築すると共に、当該構造物のコ
ア部を除く最上部を地上において構築してそれを前記コ
ア部の最上部に対して連結し、それら連結した最上部を
一括して揚重手段により上方に押し上げて仮支持し、そ
の後、仮支持した最上部の下部に連結せしめてその直下
の部分を地上において構築する工程と、それら連結した
構築部分を一括して押し上げて仮支持する工程とを順次
繰り返すことで構造物全体の構築を完成することを特徴
とする構造物の構築方法。
When constructing a structure, a lowermost portion of a core portion of the structure is constructed by a predetermined layer, and then an uppermost portion of the core portion is constructed at an upper portion thereof, and a core portion of the structure is constructed. The uppermost part except for the above was constructed on the ground and connected to the uppermost part of the core part, and the connected uppermost parts were collectively pushed upward by a lifting means and temporarily supported, and then temporarily supported. Complete the construction of the entire structure by sequentially repeating the process of connecting to the lower part of the uppermost part and building the part directly under the ground on the ground, and the step of pushing up the connected building parts collectively and temporarily supporting them A method for constructing a structure characterized by the following.
JP1242490A 1989-09-19 1989-09-19 How to build structures Expired - Lifetime JP2761527B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1242490A JP2761527B2 (en) 1989-09-19 1989-09-19 How to build structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1242490A JP2761527B2 (en) 1989-09-19 1989-09-19 How to build structures

Publications (2)

Publication Number Publication Date
JPH03107038A JPH03107038A (en) 1991-05-07
JP2761527B2 true JP2761527B2 (en) 1998-06-04

Family

ID=17089862

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1242490A Expired - Lifetime JP2761527B2 (en) 1989-09-19 1989-09-19 How to build structures

Country Status (1)

Country Link
JP (1) JP2761527B2 (en)

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL7306379A (en) * 1973-05-08 1974-11-12

Also Published As

Publication number Publication date
JPH03107038A (en) 1991-05-07

Similar Documents

Publication Publication Date Title
WO2015038805A1 (en) Concrete deck for an integrated building system assembly platfrom
CN106149868A (en) Prefabricated buildings architectural structure system and assembly method thereof
US10829927B2 (en) Vertical slip form construction system with multi-function platform, and method of constructing a building therewith
JPH09317183A (en) Construction method of building
CN115387378B (en) Semi-column-free assembled station based on superposed side walls and floor simple supports and method thereof
CN212772827U (en) Prefabricated through-long-column concrete assembled frame structure
JP2761527B2 (en) How to build structures
KR102266630B1 (en) Construction method of building with composite beam structure using module deck
JP6391134B2 (en) Dismantling method and dismantling system
CN111608270A (en) Prefabricated through long column concrete assembled frame structure and construction method thereof
JP2761526B2 (en) How to build structures
JPH08239906A (en) Construction of building
JP2761528B2 (en) How to build structures
CN111058476A (en) Beam lowering construction method of underground structure in reverse construction method
JP3225456B2 (en) How to build a building
US3435583A (en) Method of forming buildings
JP2536249B2 (en) Lift-down underground structure construction method
JP3445419B2 (en) Double slab construction method
JPH0657710A (en) Construction of concrete main tower
JP3234442B2 (en) Building and scrap type building method
JPH0681463A (en) Building method for stair
JP2777516B2 (en) Construction method of high-rise structure
JPH03107036A (en) Constructing method for structure
JPH1181679A (en) Construction for building
KR20060028889A (en) Structure for plastic slab deck system and downward construction method using the same