JP3445419B2 - Double slab construction method - Google Patents

Double slab construction method

Info

Publication number
JP3445419B2
JP3445419B2 JP24841795A JP24841795A JP3445419B2 JP 3445419 B2 JP3445419 B2 JP 3445419B2 JP 24841795 A JP24841795 A JP 24841795A JP 24841795 A JP24841795 A JP 24841795A JP 3445419 B2 JP3445419 B2 JP 3445419B2
Authority
JP
Japan
Prior art keywords
floor
slab
concrete
precast concrete
cotter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP24841795A
Other languages
Japanese (ja)
Other versions
JPH0967824A (en
Inventor
清人 増村
克己 岡村
洋一 大垣
育夫 松村
孝昭 清水
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP24841795A priority Critical patent/JP3445419B2/en
Publication of JPH0967824A publication Critical patent/JPH0967824A/en
Application granted granted Critical
Publication of JP3445419B2 publication Critical patent/JP3445419B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、仮設施設に兼用す
る上面コッター付きハーフプレキャストコンクリート版
等を用いた二重スラブ構築法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a double slab construction method using a half precast concrete slab with an upper surface cotter that also serves as a temporary facility.

【0002】[0002]

【従来の技術】複数の地下階を有する鉄骨鉄筋コンクリ
ート造等の建物では、通常、地下躯体の最下部に二重ス
ラブが形成される。この二重スラブは、掘削地盤の根切
底に設けた耐圧版から基礎梁を起立させ、該基礎梁の上
端に床版を連ねて形成される。このことは、地下一階か
ら下層階へと順次に躯体を構築する逆打工法の場合でも
最下階の二重スラブに関する限り変わるところがない。
例えば、地下階が3階の場合の逆打工法では、一般に次
の作業手順で行われている。 (1) 地下二階の床梁躯体完了後、地下三階の床レベルま
で地盤を掘削して、その根切底に仮設捨コンクリートを
打ち、該仮設捨コンクリート床を作業床として地下三階
の地下外壁、柱等を構築する。この際、その地下外壁に
補強を要するときは、該地下外壁と当階天井の適宜な梁
との間に斜め切梁を仮設する。 (2) 地盤を上記捨コンクリート共々最終掘削・床付け
し、適宜地業の上、所要の配筋をし、コンクリートを打
設して、耐圧版を構築する。 (3) 耐圧版の上に、仮設作業通路架台用枠組足場を組み
立てて、該枠組足場を架台にして仮設作業通路を設けた
後、該仮設作業通路を使用してその耐圧版の上に基礎梁
型枠を組み立て、該型枠内に所要の配筋を施し、コンク
リートを打設して、耐圧版に打継ぎした基礎梁を構築す
る。基礎梁型枠、仮設作業通路、枠組足場及び前述の斜
め切梁は、基礎梁の打設コンクリートに所定の強度が発
現した後に、適宜に解体撤去する。 (4) 基礎梁で囲成される各ピットに、それぞれ床版せき
板、各ピット毎の開口形成用せき板、端太材、大引材等
から成る床版型枠を組み立て、また、耐圧版上の各所に
所要の型枠サポートを林立させて、それらの床版型枠を
支保した後、それらの床版型枠乃至基礎梁の上に所要の
配筋を施し、コンクリートを打設して、基礎梁と打継ぎ
した地下三階の床の床版を構築する。それらの床版型枠
及び型枠サポートは、打設した床版コンクリートに所定
の強度が発現した後に解体し、開口形成用せき板で形成
された各ピットの開口から搬出する。 (5) ピット内作業完了後、ピット内仮設材搬出用開口を
塞ぐ。
2. Description of the Related Art In a building such as a steel-framed reinforced concrete structure having a plurality of basements, a double slab is usually formed at the bottom of an underground structure. This double slab is formed by erecting a foundation beam from a pressure plate provided at the root cut bottom of the excavated ground and connecting a floor slab to the upper end of the foundation beam. This is the same as far as the double slab on the bottom floor is concerned even in the case of the reverse striking method in which the frame is constructed sequentially from the first basement floor to the lower floors.
For example, in the reverse driving method when the basement floor is the third floor, the following work procedure is generally performed. (1) After the floor beam structure of the second basement floor is completed, excavate the ground to the floor level of the third basement floor, strike temporary waste concrete at the root cutting bottom, and use the temporary waste concrete floor as the working floor Build outer walls, pillars, etc. At this time, when the underground outer wall needs to be reinforced, an oblique cutting beam is temporarily installed between the underground outer wall and an appropriate beam on the ceiling of the floor. (2) The ground will be finally excavated and floored together with the above-mentioned waste concrete, and after appropriate ground work, the required bar arrangement will be made and concrete will be placed to construct a pressure plate. (3) After assembling the frame work scaffold for temporary work passage platform on the pressure resistant plate and using the frame work scaffold as a platform to provide the temporary work passage, the temporary work passage is used to form a foundation on the pressure plate. A beam form is assembled, a required reinforcement is given in the form, concrete is poured, and a foundation beam is jointed to a pressure plate. The foundation beam formwork, temporary work passage, framework scaffolding and the above-mentioned diagonal cutting beams will be appropriately dismantled and removed after the concrete strength of the foundation beam has reached a certain level of strength. (4) Assemble the floor slabs, which consist of floor slabs, opening-forming slabs for each pit, thick timbers, and hauling timbers, in each pit surrounded by foundation beams, and withstand pressure. After arranging the required formwork supports in various places on the slab and supporting those slab forms, the required reinforcements are placed on those slab forms and foundation beams, and concrete is placed. To build a floor slab for the basement beam and the third floor below ground. The slab formwork and the formwork support are dismantled after the slab concrete that has been cast exhibits a predetermined strength, and then disassembled and carried out through the openings of the pits formed by the opening forming dams. (5) After completing the work in the pit, close the opening for the temporary material discharge in the pit.

【0003】[0003]

【発明が解決しようとする課題】しかし、このような二
重スラブ構築法では、次のような問題点がある。 基
礎梁施工時に、各所に仮設作業通路及びこれを架設する
枠組足場を要し、また、床版の施工時に、各所で床版せ
き板、ピット内仮設材搬出開口形成用せき板、端太材、
大引材等から成る床版型枠を要するとともに、これらの
床版型枠を支保するための多数の型枠サポート材を要し
て、膨大な仮設資材が必要である。 上述の膨大な仮
設資材の搬入・搬出、組立・解体に、多くの手間や時間
がかかり、工期が長引く原因になっている。 特に、
閉ざされた暗くて狭い空間のピット内で、多量の仮設資
材について、搬入・搬出、組立・解体等の作業を要する
ため、作業が容易でないだけでなく、品質の低下を招い
ており、また、作業環境が悪く、作業員の安全上、衛生
上の問題を生じている。 床版には、仮設資材、その
他の資材、作業用機械器具の搬入・搬出、作業員の出入
り等のために、各ピット毎に少なくとも一つの開口(い
わゆるダメ穴)を要することから、ピット内作業完了後
にそれらの開口を塞ぐ後処理が必要である。 総じ
て、かなりのコスト高その他の不都合を生じている。
However, such a double slab construction method has the following problems. Temporary work passages and frame scaffolds for erection of these are required at the time of foundation beam construction, and at the time of construction of floor slabs, floor slabs, pits for forming temporary material carrying-out openings in pits, and thick timber. ,
In addition to requiring a floor slab formwork made of a large drawing material and the like, a large number of formwork support materials for supporting these floor slab formwork are required, and a huge amount of temporary material is required. It takes a lot of labor and time to carry in and carry out, assemble and dismantle the enormous amount of temporary materials, which is a cause of prolonging the construction period. In particular,
In a closed, dark and narrow space pit, a large amount of temporary materials require work such as loading / unloading, assembling / disassembling, etc., which is not only difficult to work, but also leads to deterioration in quality. The working environment is bad, causing safety and hygiene problems for workers. Since the floor slab requires at least one opening (so-called useless hole) for each pit for loading / unloading temporary materials, other materials, working machinery / equipment, and workers in / out, etc. Post-treatment is required to close those openings after the work is completed. As a whole, it causes considerable cost and other disadvantages.

【0004】ところで、従来の逆打工法には、 A.施工済みの上階の床版から垂下させた複数の鋼棒で
下層階の床版型枠を吊り(吊型枠)、該床版型枠を地下
各階の掘削作業の進捗状況に合わせて順次に下層階へと
降下させてはその階の床版を施工する工法(特公昭52-3
3895号公報)。 B.複数階の地下階のプレキャストコンクリートスラブ
を上階部にて予め重ねた状態で吊材により吊るし、これ
らのプレキャストコンクリートスラブを地下各階の掘削
作業の進捗状況に合わせて下層階へと降下させては上の
ものから順に各階の床版として組み込んで行く工法(特
開平3-262833号公報)。がある。また、現場打ちコンク
リート層とで複合構造を形成するハーフプレキャストコ
ンクリート版として、 C.表面に一定間隔毎に多数の短柱状凹陥部を形成した
合成床用プレキャストコンクリート版(特公平2-14500
号公報)。があり、該ハーフプレキャストコンクリート
版による合成床構法がある。しかし、これらの工法等で
も、上述の問題点は解決できない。
By the way, the conventional reverse hitching method includes: The floor slab formwork of the lower floor is hung with a plurality of steel rods hung from the slab of the constructed upper floor (suspension formwork), and the slab formwork is sequentially arranged according to the progress of the excavation work on each underground floor. A method of lowering the floor to the lower floor and constructing the floor slab on that floor (Japanese Patent Publication No. 52-3
3895 publication). B. Suspend precast concrete slabs on the basement floors of multiple floors in the upper floor in a state of being stacked in advance, and lower these precast concrete slabs to the lower floors according to the progress of the excavation work on each basement floor. A construction method in which the floor slabs for each floor are incorporated in order from the top (JP-A-3-262833). There is. As a half precast concrete slab that forms a composite structure with a cast-in-place concrete layer, C.I. Precast concrete slab for synthetic floors with a large number of short columnar recesses formed on the surface at regular intervals (Japanese Patent Publication No. 2-14500).
Issue). There is a synthetic floor construction method using the half precast concrete slab. However, the above problems cannot be solved even by these construction methods.

【0005】そこで、本発明は、二重スラブの施工にお
いて、床版の一部を形成するハーフプレキャストコンク
リート版又は本設の打込型枠をなすプレキャストコンク
リート版を一定の状態で合理的に利用することにより、
上述の種々の問題点を解決しようとするものである。
Therefore, in the present invention, in the construction of a double slab, a half precast concrete slab forming a part of a floor slab or a precast concrete slab forming a permanent setting form is reasonably used in a certain state. By doing
The present invention is intended to solve the various problems described above.

【0006】[0006]

【課題を解決するための手段】請求項1の発明は、逆打
工法の終段で、掘削地盤の根切底に設けた耐圧版から基
礎梁を起立させ、該基礎梁の上端に床版を連ねた二重ス
ラブにおいて、前記床版の施工に当たり、前記基礎梁で
囲成される各ピット毎に床版の一部を形成する上面コッ
ター付きハーフプレキャストコンクリート版を用い、こ
れらの上面コッター付きハーフプレキャストコンクリー
ト版を、それぞれ使用すべき原位置で作製するととも
に、床版として使用する前に、それぞれ上階のスラブか
ら垂下させた複数の吊材により本設位置以上の所定レベ
ルに吊り上げ、足場板をわたして、作業通路その他の仮
設使用に供し、該仮設使用のもとに耐圧版及び基礎梁を
構築した後、上記足場板を撤去し、各上面コッター付き
ハーフプレキャストコンクリート版を各ピットの基礎梁
周縁部に定置させて各ピットを閉塞させ、これらの上面
コッター付きハーフプレキャストコンクリート版及び基
礎梁の上に床配筋を施し、現場打コンクリートを打設し
て、該打設コンクリートと各上面コッター付きハーフプ
レキャストコンクリート版とがコッターを介して一体に
結合した合成床版を構築することを特徴とする。
According to the invention of claim 1, at the final stage of the reverse driving method, a foundation beam is erected from a pressure plate provided at the root cutting bottom of the excavated ground, and a floor slab is provided at the upper end of the foundation beam. In the double slab that is connected with, in the construction of the floor slab, using a half precast concrete slab with a top cotter that forms a part of the slab for each pit surrounded by the foundation beam, with these top cotters Half-precast concrete slabs are made in their original positions where they should be used, and before they are used as floor slabs, they are hoisted to a specified level above the main installation position with a plurality of suspending materials suspended from the slabs on the upper floors, respectively. After providing the board for temporary use such as a work corridor, constructing a pressure resistant plate and foundation beam based on the temporary use, remove the scaffold board, and half precast with each top cotter The crepe slab is placed on the periphery of the foundation beam of each pit to close each pit, floor reinforced concrete is placed on these half-precast concrete slabs with top cotters and foundation beams, and in-place concrete is placed. It is characterized by constructing a synthetic floor slab in which the cast concrete and each half-precast concrete slab with an upper surface cotter are integrally connected via a cotter.

【0007】請求項2の発明は、逆打工法の終段で、掘
削地盤の根切底に設けた耐圧版から基礎梁を起立させ、
該基礎梁の上端に床版を連ねた二重スラブにおいて、最
下階の前記掘削地盤を、まず、最下階床レベルまで第1
段根切し、該第1段根切底に仮設捨コンクリートを打設
して作業床を形成し、該作業床上で、使用すべき原位置
の上面コッター付きハーフプレキャストコンクリート版
を、前記基礎梁による囲成で形成される各ピット毎に作
製し、これらの上面コッター付きハーフプレキャストコ
ンクリート版を、床版として使用する前に、それぞれ上
階のスラブから垂下させた複数の吊材により本設位置以
上の所定レベルにジャッキアップさせて吊り上げ、か
つ、足場板をわたして、作業通路その他の仮設使用に供
し、次いで、該仮設使用のもとに、前記掘削地盤を上記
仮設捨コンクリート共々に更に地業レベルまで第2段根
切し、該第2段根切底に埋殺捨コンクリートを打設し、
該埋殺捨コンクリートの上に耐圧版及び基礎梁を構築し
た後、上記足場板を撤去し、各上面コッター付きハーフ
プレキャストコンクリート版を各ピットの基礎梁周縁部
に定置させて各ピットを閉塞させ、これらの上面コッタ
ー付きハーフプレキャストコンクリート版及び基礎梁の
上に、床配筋を施し、現場打コンクリートを打設して、
該打設コンクリートと各上面コッター付きハーフプレキ
ャストコンクリート版とがコッターを介して一体に結合
した合成床版を構築することを特徴とする。
According to the second aspect of the invention, in the final stage of the reverse driving method, the foundation beam is erected from the pressure plate provided at the root cutting bottom of the excavated ground,
In the double slab in which a floor slab is connected to the upper end of the foundation beam, the excavated ground on the bottom floor is first moved to the bottom floor level.
A root precut concrete slab with an upper surface cotter at the original position to be used is formed on the work floor by step-cutting and placing a temporary waste concrete on the bottom of the first step root. Each half of the pits formed by enclosing the slab by the above, and before using these half-precast concrete slabs with top cotters as floor slabs, the main installation position was hung with a plurality of suspension members suspended from the slabs on the upper floor. Jack up to the above predetermined level and lift it, and use the scaffolding board to provide temporary use for work passages and the like, and then, under the temporary use, further excavate the excavated ground together with the temporary waste concrete. The second step root cutting to the industrial level, and the buried concrete is placed on the second step root cutting bottom,
After constructing a pressure resistant plate and a foundation beam on the buried concrete, the scaffolding plate was removed, and each top cotter-equipped half precast concrete plate was placed on the peripheral portion of the foundation beam of each pit to close each pit. On these half-precast concrete slabs with top cotters and foundation beams, floor reinforcement is applied and in-situ concrete is placed.
It is characterized by constructing a synthetic floor slab in which the cast concrete and each half-precast concrete slab with an upper surface cotter are integrally connected via a cotter.

【0008】[0008]

【発明の実施の形態】図面は、本発明に係る実施の形態
を示し、その内、図1乃至図4の(1) 乃至(9は、逆打工
法で施工する地下階が3階の鉄骨鉄筋コンクリート造又
は鉄筋コンクリート造の建物における二重スラブ構築法
の作業手順を示している。以下、この作業手順に基づい
て構築法を順次に説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The drawings show an embodiment according to the present invention, in which (1) to (9) in FIGS. 1 to 4 are steel frames of which the basement floor is the third floor constructed by the reverse driving method. The working procedure of the double slab construction method in a reinforced concrete construction or a building of reinforced concrete construction is shown, and the construction method will be sequentially described below based on this work procedure.

【0009】(1) 地下二階躯体の構築(図1) 逆打工法により地下二階躯体を構築する。つまり、地盤
1を地下二階の床の梁下レベルまで根切し、その根切底
に仮設捨コンクリート2を打設し、地山を支保工反力と
して該仮設捨コンクリート上に直に梁型枠3を、また、
発泡合成樹脂ブロック、パイプサポート等によるスラブ
支保工4を介してスラブ型枠5を配し、これらの型枠内
に配筋を施し、コンクリートを打設して、地下二階のス
ラブ6を構築する。また、図示してないが、逆打工法に
おける通常の施工手段により地下二階の地下外壁、柱等
を構築する。
(1) Construction of the second-floor basement structure (Fig. 1) The second-floor basement structure is constructed by the reverse driving method. In other words, the ground 1 is root-cut to the level below the beam on the floor of the second basement floor, and the temporary waste concrete 2 is placed at the bottom of the root, and the ground is directly supported on the temporary waste concrete as beam reaction force. Frame 3 again
A slab formwork 5 is arranged through a slab support structure 4 such as a foam synthetic resin block and a pipe support, reinforcement is given in these formworks, and concrete is placed to construct a slab 6 on the second basement floor. . Although not shown in the figure, the underground outer wall, pillars, etc. on the second basement floor are constructed by the usual construction means in the reverse construction method.

【0010】(2) 地下三階部分の第1段根切と地下三階
躯体等の施工(図1) 地下三階部分の地盤1を地下三階の床レベル付近まで上
記仮設捨コンクリート2共々に第1段根切する。この
際、合わせて前回の上記梁型枠3、スラブ支保工4及び
スラブ型枠5を解体撤去する。また、地下三階部分の第
1段根切底に作業床用仮設捨コンクリート7を打って作
業床8を仮設する(図1(3) 参照)。そして、図示して
ないが、該作業床8の上で、逆打工法における通常の施
工手段により地下三階躯体の地下外壁、柱等を構築し、
その地下外壁に補強を要するときは、該地下外壁と当階
天井の適宜な梁との間に斜め切梁を仮設する。
(2) First-stage root cutting of the third-floor basement and construction of the third-floor skeleton (Fig. 1) The ground 1 of the third-floor basement up to the floor level of the third-floor basement and the above-mentioned temporary concrete 2 First step is root cutting. At this time, the previous beam form 3, slab support 4 and slab form 5 are disassembled and removed together. In addition, the work floor 8 is temporarily installed by striking the temporary waste concrete 7 for the work floor on the bottom of the first-step root cutting on the third basement (see Fig. 1 (3)). Then, although not shown, on the work floor 8, an underground outer wall, a pillar, etc. of the basement on the third floor of the basement are constructed by a normal construction means in the reverse construction method,
When the underground outer wall needs to be reinforced, diagonal beams are temporarily installed between the underground outer wall and an appropriate beam on the ceiling of the floor.

【0011】(3) 上面コッター付きハーフプレキャスト
コンクリート版の作製(図1) 仮設した上記作業床8の上に、後に平面形状格子状に構
築される基礎梁の各ピットに対応させて、剥離材9を直
接に塗布し、かつ、所要形状の木製のPC型枠10を固定
して、使用すべき原位置の上面コッター付きハーフプレ
キャストコンクリート版11を各々作製する。具体的な
作製手段としては、例えば、そのPC型枠10内に配
筋、所要のマンホール孔型枠を配し、コンクリートを打
設し、その打設コンクリートの上に、ベニヤ板にコッタ
ー(凹凸)形成用シートを貼り付けたコッター型材を載
せて圧下させるとともに、振動を加えて打設コンクリー
トを隙間なく密実に行き渡らせ、所定強度が発現するま
で養生させる。
(3) Manufacture of half precast concrete slab with top cotter (Fig. 1) On the above-mentioned work floor 8 which has been temporarily installed, a release material is made to correspond to each pit of the foundation beam which is later constructed in a planar lattice shape. 9 is directly applied, and a wooden PC form 10 having a required shape is fixed, and half precast concrete slabs 11 with an upper surface cotter to be used in situ are prepared. As a concrete production means, for example, a bar arrangement, a required manhole hole formwork are arranged in the PC formwork 10, concrete is placed, and a cotter (unevenness) is put on a plywood board on the placed concrete. A cotter mold material to which a forming sheet is attached is placed and pressed down, and vibration is applied so that the poured concrete is spread evenly and closely without any gap, and cured until a predetermined strength is exhibited.

【0012】(4) 上面コッター付きハーフプレキャスト
コンクリート版の仮設使用(図2) 各上面コッター付きハーフプレキャストコンクリート版
11の四隅から吊棒12を鉛直に起立させ、これらの吊棒12
をそれぞれ地下二階のスラブ6に小孔13を穿設して貫通
させ、また、そのスラブ6上にそれらの吊棒12に対応さ
せて各々ジャッキ架台14を置き、これらのジャッキ架台
にそれぞれジャッキ15を装備させて、各吊棒12をそれぞ
れジャッキアップさせることにより、各上面コッター付
きハーフプレキャストコンクリート版11を作業床8から
約1m上昇させる。その後、各吊棒12の上端部を座金16
とナット17で上記スラブ6に固定し(図2(5) 参照)、
それらジャッキ架台14及びジャッキ15は、取り外して他
へと転用する。なお、上記吊棒12は、ワイヤーその他の
吊材でもよい(以下同じ)。また、各上面コッター付き
ハーフプレキャストコンクリート版11間に、適宜に足場
板18を掛けわたし(図5参照)、所要の仮設手摺19及び
幅木20を取り付けて作業通路21や資材置場等を仮設す
る。
(4) Temporary use of half precast concrete slabs with top cotters (Fig. 2) Half precast concrete slabs with top cotters
From the four corners of 11, the hanging rods 12 are erected vertically.
Through the small holes 13 in the slab 6 on the second basement, and the jack mounts 14 are placed on the slab 6 so as to correspond to the suspension rods 12, and the jacks 15 are respectively attached to these jack mounts. , And each hanging rod 12 is jacked up to raise each half-precast concrete slab 11 with a top cotter about 1 m from the working floor 8. Then, attach the upper end of each hanging rod 12 to the washer 16
And fix it to the slab 6 with the nut 17 (see Fig. 2 (5)).
The jack base 14 and the jack 15 are removed and diverted to another. The suspension rod 12 may be a wire or other suspension material (the same applies hereinafter). Moreover, scaffolding boards 18 are appropriately hung between the half precast concrete slabs 11 with top cotters (see FIG. 5), and the required temporary handrails 19 and skirting boards 20 are attached to temporarily install work passages 21 and material storage areas. .

【0013】(5) 地下三階部分の第2段根切(図2) 上記作業通路21等を使用して、上記PC型枠10を撤去
し、また、前記掘削地盤1を上記作業床8共々に地業レ
ベルまで第2段根切する。この場合の上記作業通路21等
から根切底までの距離は、例えば、5m程度となる。な
お、建物が杭基礎を採用している場合には、この際に杭
頭を斫る。その後、その第2段根切底に地業として埋殺
捨コンクリート22を打設し、かつ、該埋殺捨コンクリー
トと上記作業通路21との間に仮設階段23を設ける(図3
(6) 参照)。
(5) Second stage root cutting of the third basement (Fig. 2) The PC formwork 10 is removed using the working passage 21 and the like, and the excavated ground 1 is replaced with the working floor 8 The second stage root cutting will be done together to the geotechnical level. In this case, the distance from the work passage 21 or the like to the root cutting bottom is, for example, about 5 m. If the building uses pile foundations, the pile heads will be removed at this time. After that, buried concrete 22 is placed as a ground work on the second step root cutting bottom, and temporary stairs 23 are provided between the buried concrete and the work passage 21 (see FIG. 3).
(See (6)).

【0014】(6) 耐圧版の構築(図3) 上記作業通路21、仮設階段23等を使用して、上記埋殺捨
コンクリート22の上に配筋を施し、コンクリートを打設
して、耐圧版24を構築する。
(6) Construction of pressure-resistant plate (Fig. 3) Using the work passage 21, the temporary stairs 23, etc., a bar is arranged on the above-mentioned buried concrete 22 and concrete is placed to withstand pressure. Build version 24.

【0015】(7) 基礎梁の構築(図3) 上記作業通路21、仮設階段23等を使用して、出来上がっ
た耐圧版24の上に梁筋を配筋し、基礎梁型枠(図示せ
ず)を組み立て、該基礎梁型枠内にコンクリートを打設
して上記耐圧版24のコンクリートに打継ぎし、該打設
コンクリートに所定の強度が発現した後、その基礎梁型
枠を解体撤去して、上記耐圧版24から起立する平面形状
格子状の基礎梁25を構築する。
(7) Construction of foundation beam (Fig. 3) Using the above work passage 21, temporary stairs 23, etc., beam reinforcement is arranged on the pressure-resistant plate 24 thus completed, and the foundation beam form (not shown) is provided. No.) is assembled, concrete is placed in the foundation beam formwork and is spliced to the concrete of the pressure plate 24, and after the predetermined strength is developed in the placement concrete, the foundation beam formwork is dismantled and removed. Then, the foundation beam 25 in the form of a grid in plan view standing upright from the pressure plate 24 is constructed.

【0016】(8) 上面コッター付きハーフプレキャスト
コンクリート版の定置(図4) 上記作業通路21や資材置場等を形成する足場板18や仮設
手摺19及び幅木20、仮設階段23等を全て撤去し、また、
地下二階のスラブ6上において、各上面コッター付きハ
ーフプレキャストコンクリート版11の四隅の吊棒12に対
して再びジャッキ架台14及びジャッキ15を係合させ、か
つ、各吊棒12から座金16とナット17を取り外して、それ
らの吊棒12をジャッキダウンさせることにより、各上面
コッター付きハーフプレキャストコンクリート版11を下
降させ、もって、各上面コッター付きハーフプレキャス
トコンクリート版11の周縁部を、上記基礎梁25の囲成内
部に形成された各ピット26の基礎梁周縁部上に、ノロ止
材(図示せず)を介して定置させて、各ピット26を閉塞
させる。その後、それらのジャッキ架台14及びジャッキ
15、吊棒12等を取り除き、地下二階のスラブ6の各小孔
13を塞ぐ。
(8) Placement of half-precast concrete slab with top cotter (Fig. 4) Remove all of the above-mentioned work passage 21, scaffolding plate 18, temporary handrail 19, skirting board 20, temporary stairs 23, etc. forming material storage ,Also,
On the slab 6 on the second basement floor, the jack mounts 14 and the jacks 15 are engaged again with the hanging rods 12 at the four corners of each half-precast concrete slab 11 with the upper surface cotter, and the washer 16 and the nut 17 from each hanging rod 12 are engaged. By removing, by jacking down those hanging rods 12, the half precast concrete slab 11 with each upper surface cotter is lowered, and thus, the peripheral edge of each half precast concrete slab 11 with each upper surface cotter, of the above-mentioned foundation beam 25. The pits 26 are closed by placing them on the peripheral edge portion of the foundation beam of each pit 26 formed inside the enclosure via a sloppy stopper (not shown). Then, those jack mounts 14 and jacks
Each small hole of the slab 6 on the 2nd basement floor after removing 15 and hanging rod 12 etc.
Block 13

【0017】(9) 合成床版の構築(図4) 定置させたそれらの上面コッター付きハーフプレキャス
トコンクリート版11及び基礎梁25の上に床配筋を施し、
コンクリートを打設してそれらの上面コッター付きハー
フプレキャストコンクリート版11及び基礎梁25に打継ぎ
し、そして、打設コンクリートと各上面コッター付きハ
ーフプレキャストコンクリート版とは、コッターを介し
て一体に結合させて合成床版27を構築する(図6参
照)。
(9) Construction of composite floor slab (Fig. 4) Floor reinforcement is applied on the half precast concrete slab 11 with a top cotter and the foundation beam 25 which are fixed,
Pour concrete and pour them into the half-precast concrete slab with top cotter 11 and foundation beam 25, and place the cast concrete and each half-precast concrete slab with top cotter together through the cotter. A synthetic floor slab 27 is constructed (see FIG. 6).

【0018】[0018]

【発明の効果】本発明によれば、掘削地盤の根切底に設
けた耐圧版から基礎梁を起立させ、該基礎梁の上端に床
版を連ねた二重スラブにおいて、前記床版の施工に、そ
の床版の一部を形成する上面コッター付きハーフプレキ
ャストコンクリート版11を、床版として使用する前に、
当該使用箇所にて本設位置以外の所定レベルに吊って仮
設使用に供しているので、基礎梁の施工時に要する仮設
の作業通路や資材置場等の大半を該上面コッター付きハ
ーフプレキャストコンクリート版11で兼用できて、基礎
梁施工時に要する仮設の作業通路や資材置場等のための
仮設資材を極力少なくでき、また、その後に、その床版
の一部を形成する上面コッター付きハーフプレキャスト
コンクリート版11を本設位置に定置させ、現場打コンク
リートを打設して前記床版を構築するので、床版の施工
時には、従来必要とされていた膨大な仮設資材、すなわ
ち、各所での床版せき板、ピット内仮設材搬出開口形成
用せき板、端太材、大引材等から成る床版型枠、並び
に、これらの床版型枠を支保するための多数の型枠サポ
ート材は、一切不要となり、したがって、仮設資材を大
幅に低減できる。また、上述のように、基礎梁施工時に
要する仮設の作業通路や資材置場等のための仮設資材を
極力少なくでき、床版の施工時に床版型枠や型枠サポー
ト材が一切不要であるから、その組立・解体、搬入・搬
出の手間や時間、経費も大幅に低減でき、工期を短縮で
きる。そして、従来、閉ざされた暗くて狭い空間のピッ
ト内で行われていた、多量の仮設資材についての搬入・
搬出、組立・解体等の作業を一切無くすることができる
ので、作業を容易にすることができ、高品質を確保で
き、作業環境を改善できて、作業員の安全上、衛生上の
問題を解決できる。勿論、床版には、従来のように、仮
設資材、その他の資材、作業用機械器具の搬入・搬出、
作業員の出入り等のために各ピット毎に開口(いわゆる
ダメ穴)を設ける必要がないから、それらの開口を塞ぐ
後処理も不要である。総じて、大幅にコストダウンで
き、安全性、経済性、施工性、品質の向上を図ることが
できる。
According to the present invention, in a double slab in which a foundation beam is erected from a pressure plate provided at the root cutting bottom of excavated ground, and a floor slab is connected to the upper end of the foundation beam, the floor slab is constructed. In, before using the half precast concrete slab 11 with a top cotter forming a part of the floor slab, as a floor slab,
Since it is used for temporary use by suspending it at a predetermined level other than the permanent position at the use location, most of the temporary work passages and material storage areas required for the construction of the foundation beams are the half precast concrete slab 11 with the upper cotter. It can also be used as a temporary work passage for constructing foundation beams and temporary materials for material storage etc. can be reduced as much as possible, and after that, a half precast concrete slab with a top cotter 11 that forms a part of the floor slab is used. Since the floor slab is constructed by placing it in the permanent position and pouring in-place concrete, a huge amount of temporary material that has been conventionally required at the time of construction of the floor slab, that is, a floor slab at each place, It is not necessary to use a floor slab form made of a weir board for forming the temporary material unloading opening in the pit, a thick timber, a pulling bar, etc., and a large number of form support materials for supporting these floor slab forms. Therefore, the temporary materials can be significantly reduced. Further, as described above, it is possible to minimize the temporary materials required for the construction of the foundation beams, such as temporary work passages and material storage areas, and no floor slab formwork or formwork support material is required during floor slab construction. , The time and cost of assembling / disassembling and carrying in / out can be greatly reduced, and the construction period can be shortened. And, in the past, a large amount of temporary material was carried in and carried out in a closed, dark and narrow space pit.
Since the work of carrying out, assembling, dismantling, etc. can be completely eliminated, work can be facilitated, high quality can be secured, the work environment can be improved, and safety and hygiene problems for workers can be avoided. Solvable. Of course, in the floor slab, as in the past, temporary materials, other materials, loading and unloading of working machinery and equipment,
Since it is not necessary to provide openings (so-called useless holes) for each pit for the entry and exit of workers, post-processing for closing those openings is also unnecessary. Overall, the cost can be significantly reduced, and safety, economy, workability, and quality can be improved.

【0019】又上面コッター付きハーフプレキャストコ
ンクリート版11は、使用すべき原位置で作製するので、
仮設使用の際には、その場でそれを少々吊り上げ、本設
使用の際には、その場でそれを下ろせばよいから、搬
送、搬入、揚重などが一切不要で、その取り扱いが簡単
かつ容易である。更に床版を、ハーフプレキャストコン
クリート版の上に現場打コンクリートを打設一体化させ
て合成床版としているので、その厚さが格別に厚くなる
ことはない。床版を、上面コッター付きハーフプレキャ
ストコンクリート版11の上に現場打コンクリートを打設
一体化させて合成床版27としているので、その上面コッ
ターによりハーフプレキャストコンクリート版と現場打
コンクリートとの付着性を格段に高めることができる。
本発明によれば、それぞれの具体的工程により、相応に
作業手順を合理化でき、作業を手順よく遂行できる。
Since the half precast concrete slab 11 with a top cotter is manufactured at the original position to be used,
For temporary use, it can be lifted up a little on the spot, and for permanent use, it can be lowered on the spot, so there is no need for transportation, loading, or lifting, and handling is simple and easy. It's easy. Furthermore, since the floor slab is made into a synthetic floor slab by pouring and integrating on-site cast concrete on the half precast concrete slab, the thickness does not become particularly thick. The floor slab is a synthetic floor slab 27 that is made by injecting and integrating in-situ cast concrete on the half precast concrete slab with top cotter 11 to make it an adhesive property between the half precast concrete slab and in-situ concrete. It can be increased significantly.
According to the present invention, the work procedure can be rationalized and the work can be performed according to the specific steps.

【図面の簡単な説明】[Brief description of drawings]

【図1】 本発明に係る一の実施の形態を示し、作業手
順(1) 乃至(3) を示す手順説明図である。
FIG. 1 is a procedure explanatory view showing an embodiment according to the present invention and showing work procedures (1) to (3).

【図2】 同実施の形態における作業手順(4) 乃至(5)
を示す手順説明図である。
FIG. 2 is a work procedure (4) to (5) in the same embodiment.
FIG.

【図3】 同実施の形態における作業手順(6) 乃至(7)
を示す手順説明図である。
FIG. 3 is a work procedure (6) to (7) in the same embodiment.
FIG.

【図4】 同実施の形態における作業手順(8) 乃至(9)
を示す手順説明図である。
FIG. 4 is a work procedure (8) to (9) in the same embodiment.
FIG.

【図5】 同実施の形態における上面コッター付きハー
フプレキャストコンクリート版による作業通路及び資材
置場の平面配置図である。
FIG. 5 is a plan layout view of a work passage and a material yard by a half precast concrete slab with a top cotter in the same embodiment.

【図6】 同実施の形態における合成床版の拡大截断側
面図である。
FIG. 6 is an enlarged cutaway side view of the composite floor slab according to the same embodiment.

【符号の説明】[Explanation of symbols]

1…地盤 2…仮設捨コンクリ
ート 3…梁型枠 4…スラブ支保工 5…スラブ型枠 6…スラブ 7…作業床用仮設捨コンクリート 8…作業床 9…剥離材 10…PC型枠 11…上面コッター付きハーフプレキャストコンクリート
版 12…吊棒 13…小孔 14…ジャッキ架台 15…ジャッキ 16…座金 17…ナット 18…足場板 19…仮設手摺 20…幅木 21…作業通路 22…埋殺捨コンクリート 23…仮設階段 24…耐圧版 25…基礎梁 26…ピット 27…合成床版
1 ... Ground 2 ... Temporary abandoned concrete 3 ... Beam form 4 ... Slab support 5 ... Slab form 6 ... Slab 7 ... Temporary abandoned concrete for work floor 8 ... Work floor 9 ... Release material 10 ... PC form 11 ... Top Half precast concrete plate with cotter 12… Suspension rod 13… Small hole 14… Jack stand 15… Jack 16… Washer 17… Nut 18… Scaffolding board 19… Temporary handrail 20… Baseboard 21… Work passage 22… Abandoned concrete 23 … Temporary stairs 24… Pressure plate 25… Foundation beams 26… Pits 27… Composite floor slabs

───────────────────────────────────────────────────── フロントページの続き (72)発明者 松村 育夫 東京都中央区銀座八丁目21番1号 株式 会社 竹中工務店 東京本店内 (72)発明者 清水 孝昭 東京都中央区銀座八丁目21番1号 株式 会社 竹中工務店 東京本店内 (56)参考文献 特開 平6−167031(JP,A) 特開 平3−262833(JP,A) 特開 平3−100225(JP,A) 特開 平4−49333(JP,A) 特開 平7−189396(JP,A) (58)調査した分野(Int.Cl.7,DB名) E02D 29/00 E04B 5/38 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Ikuo Matsumura Inventor Ikuo Matsumura 8-21-1 Ginza, Chuo-ku, Tokyo Stock Company Takenaka Corporation Tokyo Main Store (72) Inventor Takaaki Shimizu 8-21-1 Ginza, Chuo-ku, Tokyo No. Stock Company Takenaka Corporation Tokyo Main Store (56) Reference JP 6-167031 (JP, A) JP 3-262833 (JP, A) JP 3-100225 (JP, A) JP 4-49333 (JP, A) JP-A-7-189396 (JP, A) (58) Fields investigated (Int.Cl. 7 , DB name) E02D 29/00 E04B 5/38

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 逆打工法の終段で、掘削地盤の根切底に
設けた耐圧版から基礎梁を起立させ、該基礎梁の上端に
床版を連ねた二重スラブにおいて、前記床版の施工に当
たり、前記基礎梁で囲成される各ピット毎に床版の一部
を形成する上面コッター付きハーフプレキャストコンク
リート版を用い、これらの上面コッター付きハーフプレ
キャストコンクリート版を、それぞれ使用すべき原位置
で作製するとともに、床版として使用する前に、それぞ
れ上階のスラブから垂下させた複数の吊材により本設位
置以上の所定レベルに吊り上げ、足場板をわたして、作
業通路その他の仮設使用に供し、該仮設使用のもとに耐
圧版及び基礎梁を構築した後、上記足場板を撤去し、各
上面コッター付きハーフプレキャストコンクリート版を
各ピットの基礎梁周縁部に定置させて各ピットを閉塞さ
せ、これらの上面コッター付きハーフプレキャストコン
クリート版及び基礎梁の上に床配筋を施し、現場打コン
クリートを打設して、該打設コンクリートと各上面コッ
ター付きハーフプレキャストコンクリート版とがコッタ
ーを介して一体に結合した合成床版を構築することを特
徴とする二重スラブ構築法。
1. A double slab in which a foundation beam is erected from a pressure plate provided at the root cutting bottom of the excavated ground at the final stage of the reverse driving method, and the floor slab is connected to the upper end of the foundation beam. In the construction of, using the half precast concrete slab with the top cotter that forms a part of the floor slab for each pit surrounded by the foundation beam, these half precast concrete slabs with the top cotter should be used respectively. Before using it as a floor slab, lift it up to a predetermined level above the main installation position with a plurality of hanging materials that are hung from the slabs on the upper floor and use it as a scaffolding board for temporary use such as work corridors. After constructing pressure resistant plates and foundation beams based on the temporary use, the scaffolding boards were removed and the half precast concrete slabs with top cotters were installed around the foundation beams of each pit. Placed at the edge to close each pit, give floor reinforcement to these half precast concrete slabs with top cotters and foundation beams, pour on-site cast concrete, and place the cast concrete and each top cotter A double slab construction method characterized by constructing a synthetic floor slab integrally joined with a half precast concrete slab with a cotter.
【請求項2】 逆打工法の終段で、掘削地盤の根切底に
設けた耐圧版から基礎梁を起立させ、該基礎梁の上端に
床版を連ねた二重スラブにおいて、最下階の前記掘削地
盤を、まず、最下階床レベルまで第1段根切し、該第1
段根切底に仮設捨コンクリートを打設して作業床を形成
し、該作業床上で、使用すべき原位置の上面コッター付
きハーフプレキャストコンクリート版を、前記基礎梁に
よる囲成で形成される各ピット毎に作製し、これらの上
面コッター付きハーフプレキャストコンクリート版を、
床版として使用する前に、それぞれ上階のスラブから垂
下させた複数の吊材により本設位置以上の所定レベルに
ジャッキアップさせて吊り上げ、かつ、足場板をわたし
て、作業通路その他の仮設使用に供し、次いで、該仮設
使用のもとに、前記掘削地盤を上記仮設捨コンクリート
共々に更に地業レベルまで第2段根切し、該第2段根切
底に埋殺捨コンクリートを打設し、該埋殺捨コンクリー
トの上に耐圧版及び基礎梁を構築した後、上記足場板を
撤去し、各上面コッター付きハーフプレキャストコンク
リート版を各ピットの基礎梁周縁部に定置させて各ピッ
トを閉塞させ、これらの上面コッター付きハーフプレキ
ャストコンクリート版及び基礎梁の上に、床配筋を施
し、現場打コンクリートを打設して、該打設コンクリー
トと各上面コッター付きハーフプレキャストコンクリー
ト版とがコッターを介して一体に結合した合成床版を構
築することを特徴とする二重スラブ構築法。
2. A double slab in which a foundation beam is erected from a pressure plate provided at the root cutting bottom of the excavated ground at the final stage of the reverse driving method, and a floor slab is connected to the upper end of the foundation beam. First, the excavated ground of No. 1 is root-cut to the lowest floor level,
Forming a working floor by placing temporary waste concrete on the step root cutting bottom, and on the working floor, a half precast concrete plate with an upper surface cotter to be used in-situ is formed by surrounding with the foundation beam Produced for each pit, these half precast concrete slabs with top cotter,
Before using it as a floor slab, jack it up to a predetermined level above the main installation position with a plurality of suspenders hanging from the slabs on the upper floor and lift the scaffolding board to temporarily use it as a work corridor or other temporary use. Then, under the temporary use, the excavated ground is further second-stage root cut to the groundwork level together with the temporary waste concrete, and the second-stage root cutting bottom is filled with buried waste concrete. Then, after constructing a pressure resistant plate and a foundation beam on the buried concrete, remove the scaffolding plate and place each half-precast concrete plate with a top cotter on the periphery of the foundation beam of each pit to form each pit. Blocked, floor reinforcement is placed on these half precast concrete slabs with top cotters and foundation beams, and on-site cast concrete is cast, and the cast concrete and each top cotter are placed. Double slab construction method and can Precast concrete panel which is characterized in that to construct a synthetic deck coupled together via a cotter.
JP24841795A 1995-08-31 1995-08-31 Double slab construction method Expired - Fee Related JP3445419B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24841795A JP3445419B2 (en) 1995-08-31 1995-08-31 Double slab construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24841795A JP3445419B2 (en) 1995-08-31 1995-08-31 Double slab construction method

Publications (2)

Publication Number Publication Date
JPH0967824A JPH0967824A (en) 1997-03-11
JP3445419B2 true JP3445419B2 (en) 2003-09-08

Family

ID=17177815

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24841795A Expired - Fee Related JP3445419B2 (en) 1995-08-31 1995-08-31 Double slab construction method

Country Status (1)

Country Link
JP (1) JP3445419B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102444143B (en) * 2011-11-14 2014-10-08 成都新艺置业有限公司 Construction method for cancelling operation channel for facades of basement
JP2016223084A (en) * 2015-05-28 2016-12-28 大成建設株式会社 Construction method of underground structure by inverted construction method
JP7129290B2 (en) * 2018-09-14 2022-09-01 大成建設株式会社 Building floor structure for rebuilding

Also Published As

Publication number Publication date
JPH0967824A (en) 1997-03-11

Similar Documents

Publication Publication Date Title
US5528877A (en) Concrete building frame construction method
US10829927B2 (en) Vertical slip form construction system with multi-function platform, and method of constructing a building therewith
RU2220258C1 (en) Process of erection of multilevel underground structure ( variants )
JP3445419B2 (en) Double slab construction method
KR0179708B1 (en) Working method for underground structure of a building
JP3399873B2 (en) How to build a dome structure
JP2980567B2 (en) How to replace the bearing device
JP2001329700A (en) Temporary jointing method for column during building demolition in jack system
CN111058476A (en) Beam lowering construction method of underground structure in reverse construction method
JPS61109827A (en) Construction of basement
JP2761527B2 (en) How to build structures
CN116575480B (en) Construction method for supporting steel pipe of deep foundation pit penetrating through basement floor slab
JP2761528B2 (en) How to build structures
JP2777516B2 (en) Construction method of high-rise structure
JP2967452B2 (en) Building construction methods and lightweight floor slabs
JPH0932295A (en) Construction method for concrete structure
JP2761526B2 (en) How to build structures
JPH08291526A (en) Construction method for underground structure
JP2696486B2 (en) Building construction method
KR20220112000A (en) Descent apparatus downward construction system method using thereof
JPH03107036A (en) Constructing method for structure
JPH07268813A (en) Construction method of concrete structure
JP2751988B2 (en) Building construction equipment
JPH07150570A (en) Suspending scaffold construction method to construct caisson
JP3238510B2 (en) Construction method of preceding slab floor

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080627

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080627

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090627

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100627

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100627

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110627

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110627

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120627

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees