JPH08291526A - Construction method for underground structure - Google Patents
Construction method for underground structureInfo
- Publication number
- JPH08291526A JPH08291526A JP7097011A JP9701195A JPH08291526A JP H08291526 A JPH08291526 A JP H08291526A JP 7097011 A JP7097011 A JP 7097011A JP 9701195 A JP9701195 A JP 9701195A JP H08291526 A JPH08291526 A JP H08291526A
- Authority
- JP
- Japan
- Prior art keywords
- column
- hollow
- pile
- foundation
- underground structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は地下構築物の構築方法に
係るものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an underground structure.
【0002】[0002]
【従来の技術】地下構造部を有する構築物の構築に際し
ては、地下構造部の地下周辺地盤の崩壊や沈下を防止す
るため、同周辺地盤に山留めを行い、軟弱地盤に対して
は杭地業を行い、地上部から一次掘削を行って前記山留
壁に腹起しと切梁を使用した水平支保工で支承して所定
の基礎地盤まで掘削し、基礎工事を行って上部へと躯体
を構築し、さらに地上部へと構築していく。2. Description of the Related Art When constructing a structure having an underground structure part, in order to prevent the collapse and subsidence of the underground surrounding part of the underground structure part, the surrounding ground is piled up and the pile land business is applied to the soft ground. Performed primary excavation from the above-ground part, supported by horizontal support using ridges and cut beams on the mountain retaining wall, excavated to the specified foundation ground, and carried out foundation construction to construct the skeleton to the upper part Then, it will be further built on the ground.
【0003】前記の構築方法の他に、地下工事と地上躯
体工事を同時に行っていく逆打工法がある。この逆打工
法は周辺地盤に山留めを行い、軟弱地盤に対しては杭地
業を行った後、山留めに対する腹起しと切梁を使用した
水平支保工を省略し、地上部に施工されたトップスラブ
から順次下層部へと構築し、最後に基礎を構築するもの
である。In addition to the above-mentioned construction method, there is a reverse driving method in which underground construction and ground construction work are simultaneously performed. This reverse driving method was carried out on the ground part, after carrying out mountain retaining on the surrounding ground and piling ground for soft ground, omitting upset for mountain retaining and horizontal support work using cutting beams. It is to build from the top slab to the lower layers, and finally to build the foundation.
【0004】[0004]
【発明が解決しようとする課題】地下構築物の建設工事
に際しては、建設する規模や立地条件によってその施工
法を検討し、最適な施工法によって行うが、特に立地条
件の悪い市街地や、工期に余裕がない場合など、前記型
枠の組立、鉄筋の加工組立と殆どが現場において夫々の
専門職によって施工されるため、多くの作業時間を要
し、且つ建設資材の搬出入等に伴う騒音や振動で建設現
場周辺の環境を損い、また地下における狭隘な場所での
作業は重労働を伴い、施工性に悪影響を及ぼすという問
題があった。[Problems to be Solved by the Invention] When constructing an underground structure, the construction method should be examined according to the scale of construction and location conditions, and the optimal construction method should be used. Since there is no such thing, most of the above-mentioned formwork assembly, rebar processing and assembly is performed by each professional at the site, so much work time is required, and noise and vibration associated with the loading and unloading of construction materials are required. However, there is a problem that the environment around the construction site is damaged, and that work in a narrow underground place involves heavy labor and adversely affects the workability.
【0005】本発明は前記従来技術の有する問題点に鑑
みて提案されたもので、その目的とするところは、逆打
ち工法を採用し、構成部材として工業化製品を採用し、
作業性を向上し、工期の短縮を図り、建設現場周辺の環
境を損うことのない地下構築物の構築方法を提供する点
にある。The present invention has been proposed in view of the above-mentioned problems of the prior art. The object of the present invention is to employ a reverse construction method and industrial products as constituent members,
The point is to improve workability, shorten the construction period, and provide a method for constructing an underground structure that does not damage the environment around the construction site.
【0006】[0006]
【課題を解決するための手段】前記の目的を達成するた
め、本発明に係る地下構築物の構築方法によれば、地下
構築物が構築されるべき地下外周地盤に山留壁を築造
し、現場打ちコンクリート杭を造成するとともに、同杭
に地下構築物を支持する中間杭を設置して地下の一次掘
削を行い、次いで前記中間杭に中空プレキャストコンク
リート柱を立設し、同プレキャストコンクリート柱間に
プレキャストコンクリート梁を架設したのち、同プレキ
ャストコンクリート梁間に型枠兼用床材を架設し、同型
枠兼用床材に補強鉄筋を配筋して前記中空プレキャスト
コンクリート柱の中空部と一体に床コンクリートを打設
するとともに基礎地盤まで掘削して基礎を構築し、同基
礎と前記中空プレキャストコンクリート柱を支持する下
部柱を構築するものである。[Means for Solving the Problems] In order to achieve the above object, according to the method for constructing an underground structure according to the present invention, a mountain retaining wall is constructed on the underground outer ground where the underground structure is to be constructed, and it is cast on site. While constructing concrete piles, installing intermediate piles that support underground structures on the piles and performing primary underground excavation, then standing hollow precast concrete columns on the intermediate piles and precast concrete between the precast concrete columns. After erection of the beams, a formwork / floor material is erected between the precast concrete beams, and reinforcing steel bars are laid on the formwork / floor material to pour floor concrete integrally with the hollow parts of the hollow precast concrete columns. Along with that, the foundation is constructed by excavating to the foundation ground, and the lower pillar that supports the foundation and the hollow precast concrete pillar is constructed. A.
【0007】請求項2の発明によれば前記中空プレキャ
ストコンクリート柱は一階層に相当する柱高さより梁成
を短くし、柱頂部においては上部躯体と接合する柱筋を
伸長し、柱下端部においては下部躯体と接合する柱筋を
伸長してなり、柱断面における中心部に設けた空洞部を
介して前記中間杭と一体にコンクリートを打設するもの
である。According to the second aspect of the present invention, the hollow precast concrete column has a beam length shorter than the column height corresponding to one floor, and at the top of the column, the column bar that is joined to the upper frame is extended, and at the bottom end of the column. Is a structure in which a column bar connected to the lower frame is extended, and concrete is poured integrally with the intermediate pile through a cavity provided in the center of the column cross section.
【0008】[0008]
【作用】本発明によれば前記したように、地下構築物が
構築されるべき地下外周地盤に山留壁を築造して周辺地
盤の崩壊を防止し、場所打ちコンクリート杭を造成する
とともに、地下構築物を支持する中間杭を前記現場打ち
コンクリート杭に設置して、地下の一次掘削を行ったの
ち、前記中間杭に中空プレキャストコンクリート柱を立
設し、同中空プレキャストコンクリート柱間に亘ってプ
レキャストコンクリート梁を架設し、このように地下階
の柱梁を構築したのち、前記プレキャストコンクリート
梁間に型枠兼用床材を架設し、同型枠兼用床材に補強鉄
筋を配筋して、床コンクリートを前記中空プレキャスト
コンクリート柱の中空部と一体に打設することによって
地下構築物の殆んどの構築作業を工場生産された部材に
よる現場での組立作業のみで行い、基礎地盤までの掘削
工程と、掘削後の基礎構築工程と、同基礎と前記中空プ
レキャストコンクリート柱を支持する下部柱を構築する
工程によって、地下構築物を能率よく構築するものであ
る。According to the present invention, as described above, a mountain retaining wall is constructed on the underground outer ground where the underground structure is to be constructed to prevent the surrounding ground from collapsing, a cast-in-place concrete pile is constructed, and the underground structure is constructed. After installing the intermediate pile to support the in-situ concrete pile and performing the underground primary excavation, the hollow precast concrete pillar is erected on the intermediate pile, and the precast concrete beam spans between the hollow precast concrete pillars. After constructing the basement and beam in the basement floor in this way, erection of the floor material that also serves as the formwork between the precast concrete beams, and reinforcing reinforcing bars are laid on the floor material that also serves as the formwork, and the floor concrete is hollowed. On-site assembly of most underground construction work with factory-manufactured components by placing them integrally with the hollow part of the precast concrete columns The underground construction is efficiently constructed by the excavation process to the foundation ground, the foundation construction process after excavation, and the process of constructing the foundation and the lower pillar supporting the hollow precast concrete pillar. .
【0009】請求項2の発明によれば、前記中空プレキ
ャストコンクリート柱は一階層に相当する高さより梁成
を短くし、柱頂部より柱筋が伸長しているため、後から
構築される上部躯体に接合でき、下部も同様に柱筋を伸
長し、下部躯体と接合できる。而して前記中空部にコン
クリートを打設することにより柱としての構造性能が得
られ、さらに中空部におけるコンクリートと中間杭とが
付着摩擦により上部構造体を支持する。According to the second aspect of the present invention, the hollow precast concrete column has a beam formation shorter than the height corresponding to one floor and the column reinforcement extends from the column top. Therefore, the upper skeleton constructed later is constructed. Can be joined to, and the lower part also extends the columnar muscles and can be joined to the lower frame. Then, by placing concrete in the hollow portion, structural performance as a pillar can be obtained, and further, concrete in the hollow portion and the intermediate pile support the upper structure by adhesion friction.
【0010】[0010]
【実施例】以下、本発明を図示の実施例について説明す
る。図1は本発明の方法によって構築される建築構築物
Aで、同建築構築物Aは地下構築物Bを有し、同地下構
築物Bは基礎K,柱C,梁G,床S,外壁Wより構成さ
れている。The present invention will be described below with reference to the illustrated embodiments. FIG. 1 shows a building structure A constructed by the method of the present invention. The building structure A has an underground structure B, and the underground structure B is composed of a foundation K, a pillar C, a beam G, a floor S, and an outer wall W. ing.
【0011】図2(イ)は工業化された建築部材によっ
て構築された地下建築物Bを示し、中空プレキャストコ
ンクリート柱(以下中空PC柱と称す)a、プレキャス
トコンクリート梁(以下PC梁と称す)b、プレキャス
トコンクリート小梁(以下PC小梁)c、床材d、より
構成されている。図2(ロ)は中空PC柱で、一階層に
相当する柱高さより梁成を短くし、柱頂部より上部床上
から定着長さ伸長した柱筋a1 と、下部現場打ちの柱と
接合される柱筋a1 が伸長し、柱断面の中心部が中空部
a2 となっている。FIG. 2A shows an underground building B constructed by industrialized building members. Hollow precast concrete columns (hereinafter referred to as hollow PC columns) a and precast concrete beams (hereinafter referred to as PC beams) b. , A precast concrete beam (hereinafter referred to as a PC beam) c and a floor material d. Figure 2 (b) is a hollow PC column. The beam height is made shorter than the column height corresponding to one floor, and the column reinforcement a 1 extending from the top of the column to the fixing floor extends from the top of the column and is joined to the lower cast-in-place column. The column rebar a 1 extends, and the central portion of the column cross section is a hollow portion a 2 .
【0012】前記地下構築物Bを施工するに当り、同地
下構築物を構築する外周地盤Dに山留壁1を築造して地
上地盤Dより現場打ちコンクリート杭3を造成し、同杭
3に上部構造物を支持する中間杭4を設置し、地下の一
次掘削を行う、図中5は一次掘削の根切底である。(図
3(イ)参照) 次いで一次掘削の根切底5に中空PC柱aを仮支持する
捨コンクリート6を設け、前記中間杭4を貫入して同中
間杭4に前記中空PC柱aを立設し、同中空PC柱a間
にPC梁bを架設し、同PC梁b間にPC小梁cを架設
するとともに型枠兼用床材dを架設し、同型枠に補強鉄
筋を配筋して、同床材と前記中空PC柱aの中空部a2
に亘って一体にコンクリートを打設し、トップスラブ7
を構築する。(図4参照) 更に基礎地盤まで掘削し、現場打コンクリート杭3上に
基礎Kを構築し、同基礎Kと前記杭3に前記中空PC柱
aを支持する下部柱9を構築して地下構築物を構築す
る。(図5参照) 図3(ロ)は本発明の他の実施例を示し、第1次掘削の
際に柱脚部を基礎上部まで掘削し、掘削部5′に捨コン
クリートを打設し、以後は前記実施例と同じ工程とする
こともできる。In constructing the underground structure B, a mountain retaining wall 1 is built on the outer ground D for constructing the underground structure B, a cast-in-place concrete pile 3 is formed from the ground ground D, and an upper structure is formed on the pile 3. An intermediate pile 4 for supporting an object is installed and underground primary excavation is performed. Reference numeral 5 in the figure denotes a root excavation bottom of the primary excavation. (See FIG. 3 (A)) Next, a waste concrete 6 for temporarily supporting the hollow PC pillars a is provided on the root excavation bottom 5 of the primary excavation, the intermediate pile 4 is penetrated, and the hollow PC pillars a are inserted in the intermediate pile 4. Standing up, a PC beam b is installed between the hollow PC columns a, a PC beam c is installed between the PC beams b, and a floor material d that also serves as a formwork is installed, and reinforcing reinforcing bars are laid in the formwork. Then, the same floor material and the hollow portion a 2 of the hollow PC pillar a
Top concrete slab 7
To build. (See FIG. 4) Further excavating to the foundation ground, constructing the foundation K on the cast-in-place concrete pile 3, and constructing the foundation K and the lower pillar 9 supporting the hollow PC pillar a on the pile 3 to construct an underground structure. To build. (Refer to FIG. 5) FIG. 3B shows another embodiment of the present invention, in which the column base is excavated to the upper part of the foundation during the first excavation, and the excavated portion 5 ′ is provided with waste concrete, After that, the same steps as those in the above-mentioned embodiment can be performed.
【0013】この場合は基礎部と中空PC柱との下部柱
9を省略することができ、現場作業が更に軽減され、作
業効率が向上する。なお図6は下部構造の詳細を示し、
10は前記杭3上に施工された基礎フーチング、12は
中空PC柱aの中空部コンクリートである。なお一階の
床には型枠兼用の床材dが用いられているが、例えば半
PC板に現場打コンクリートを打設する床工法やPC板
を用いてもよい。図中F2 は地下階床である。In this case, the lower column 9 of the foundation and the hollow PC column can be omitted, and the site work can be further reduced and the work efficiency can be improved. 6 shows the details of the lower structure,
Reference numeral 10 is a foundation footing constructed on the pile 3, and 12 is concrete in the hollow portion of the hollow PC column a. Although the floor material d that also serves as the formwork is used for the floor on the first floor, for example, a floor construction method in which cast-in-place concrete is cast on a half-PC board or a PC board may be used. In the figure, F 2 is the basement floor.
【0014】このように地下構築部は中空PC柱aとP
C梁bとPC小梁cと型枠兼用の床を用いることによっ
て工業化部材を用いて構築することができるので、専門
職の作業員を要せず、また地下の狭隘な場所での作業が
なくなる。In this way, the underground construction section is constructed of hollow PC columns a and P.
Since it can be constructed by using industrialized members by using C beam b, PC beam c, and floor that also serves as a formwork, it does not require a professional worker and can work in a narrow underground space. Disappear.
【0015】[0015]
【発明の効果】本発明によれば前記したように山留壁内
周下底部に施工した現場打コンクリート杭に地下構造物
を支持する中間杭を設置して一次掘削を行い、同中間杭
に中空PC柱の中空部を利用して立設し、同中空PC柱
間にPC梁を架設して、PC梁間に架設した型枠兼用床
材に補強鉄筋を配筋して床コンクリートを打設し、同打
設コンクリートを前記中空PC柱にその中空部を介して
一体化し、柱、床の一体化を図るものである。EFFECTS OF THE INVENTION According to the present invention, an intermediate pile for supporting an underground structure is installed on a cast-in-place concrete pile constructed on the bottom bottom of the inner circumference of the mountain retaining wall as described above, and primary excavation is performed to the intermediate pile. Standing up using the hollow part of hollow PC pillars, PC beams are erected between the hollow PC pillars, and reinforcement concrete bars are laid on the form and floor material erected between the PC beams, and floor concrete is placed. Then, the same poured concrete is integrated with the hollow PC column through the hollow portion to achieve integration of the column and floor.
【0016】更に本発明によれば柱,梁,小梁,型枠兼
用床材が工場生産のPC部材より構成され、現場に搬入
され、建方機械によって構築されるので型枠の組立,解
体,鉄筋の加工組立がなく作業が省力化され、作業性が
向上され、建設騒音により近隣に及ぼす建設公害が除去
されるものである。請求項2の発明は、前記中空PC柱
は一階層に相当する柱高さより梁成を短くし、柱頂部及
び柱下端部に柱筋を伸長して、上部躯体及び下部躯体と
を確実に接合することができ、また中空部に設けた空洞
部を介して地下構築物を支持する中間杭と剛強に接合し
うるものである。Further, according to the present invention, the pillar, the beam, the beam, and the floor material also used as the formwork are composed of PC members produced in the factory, and are brought into the field and constructed by the erection machine, so that the formwork is assembled and disassembled. The work is labor-saving because there is no rebar processing and assembly, workability is improved, and construction pollution that affects neighboring areas due to construction noise is eliminated. According to the invention of claim 2, the hollow PC column has a beam length shorter than a column height corresponding to one layer, and a column bar is extended to a column top portion and a column lower end portion to reliably join the upper frame and the lower frame. In addition, it can be rigidly joined to the intermediate pile supporting the underground structure through the hollow portion provided in the hollow portion.
【図1】本発明の方法によって構築された地下構築物の
縦断面図である。FIG. 1 is a vertical cross-sectional view of an underground structure constructed by the method of the present invention.
【図2】(イ)は本発明の方法によって構築された地下
構築物の斜視図、(ロ)は中空PC柱の斜視図である。FIG. 2A is a perspective view of an underground structure constructed by the method of the present invention, and FIG. 2B is a perspective view of a hollow PC column.
【図3】(イ)(ロ)は本発明の方法において山留壁及
び中間杭の設置及び掘削工程の各実施例を示す縦断面図
である。3 (a) and 3 (b) are vertical cross-sectional views showing respective examples of installation and excavation steps of the mountain retaining wall and the intermediate pile in the method of the present invention.
【図4】地下構築物の中空PC柱設置工程を示す縦断面
図である。FIG. 4 is a vertical cross-sectional view showing a hollow PC column installation step of an underground structure.
【図5】地下構築物の基礎及び構格の施工状況を示す縦
断面図である。FIG. 5 is a vertical cross-sectional view showing a foundation and a construction condition of a structure of an underground structure.
【図6】地下構築物の部分拡大縦断面図である。FIG. 6 is a partially enlarged vertical sectional view of an underground structure.
A 建築構築物 B 地下構築物 C 柱 D 地盤 F1 一階床 F2 二階床 G 梁 K 基礎 W 外壁 a 中空PC柱 a1 柱筋 a2 中空部 b PC梁 c PC小梁 d 床材 1 山留壁 2 根切底 3 現場打ちコンクリート杭 4 中間杭 5 一次掘削根切底 5′ 掘削部 6 捨コンクリート 7 トップスラブ 9 下部柱A Architectural structure B Underground structure C Column D Ground F 1 First floor F 2 Second floor G Beam K Foundation W Outer wall a Hollow PC column a 1 Column reinforcement a 2 Hollow part b PC beam c PC small beam d Floor material 1 Yamadome Wall 2 Root cut bottom 3 Cast-in-place concrete pile 4 Intermediate pile 5 Primary excavation Root cut bottom 5'Excavation section 6 Waste concrete 7 Top slab 9 Lower column
Claims (2)
盤に山留壁を築造し、現場打ちコンクリート杭を造成す
るとともに、同杭に地下構築物を支持する中間杭を設置
して地下の一次掘削を行い、次いで前記中間杭に中空プ
レキャストコンクリート柱を立設し、同プレキャストコ
ンクリート柱間にプレキャストコンクリート梁を架設し
たのち、同プレキャストコンクリート梁間に型枠兼用床
材を架設し、同型枠兼用床材に補強鉄筋を配筋して前記
中空プレキャストコンクリート柱の中空部と一体に床コ
ンクリートを打設するとともに基礎地盤まで掘削して基
礎を構築し、同基礎と前記中空プレキャストコンクリー
ト柱を支持する下部柱を構築することを特徴とする地下
構築物の構築方法。1. A primary excavation underground by constructing a mountain retaining wall on an outer peripheral ground where an underground structure should be constructed, forming a cast-in-place concrete pile, and installing an intermediate pile supporting the underground structure on the pile. Then, the hollow precast concrete columns are erected on the intermediate pile, and the precast concrete beams are erected between the precast concrete columns, and then the formwork / floor material is erected between the precast concrete beams. Reinforcement reinforcing bar is laid in and the floor concrete is placed integrally with the hollow part of the hollow precast concrete column, and the foundation is constructed by excavating to the foundation ground, and the lower column supporting the foundation and the hollow precast concrete column. A method for constructing an underground structure, characterized by:
一階層に相当する柱高さより梁成を短くし、柱頂部にお
いては上部躯体と接合する柱筋を伸長し、柱下端部にお
いては下部躯体と接合する柱筋を伸長してなり、柱断面
における中心部に設けた空洞部を介して前記中間杭と一
体にコンクリートを打設する請求項1記載の地下構築物
の構築方法。2. The hollow precast concrete column has a beam length shorter than a column height corresponding to one level, a column bar extending to the upper frame is extended at the column top, and a lower frame is connected to the column lower end. The method for constructing an underground structure according to claim 1, wherein the concrete reinforcement is formed integrally with the intermediate pile through a hollow portion formed by extending a column bar and provided in a central portion in a cross section of the column.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP7097011A JPH08291526A (en) | 1995-04-21 | 1995-04-21 | Construction method for underground structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP7097011A JPH08291526A (en) | 1995-04-21 | 1995-04-21 | Construction method for underground structure |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH08291526A true JPH08291526A (en) | 1996-11-05 |
Family
ID=14180391
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP7097011A Pending JPH08291526A (en) | 1995-04-21 | 1995-04-21 | Construction method for underground structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH08291526A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11336095A (en) * | 1998-05-26 | 1999-12-07 | Kajima Corp | Construction of base isolation building |
KR101255610B1 (en) * | 2010-12-03 | 2013-04-16 | 주식회사 포스코건설 | Structure construction method and structure of use it |
CN113529694A (en) * | 2021-06-29 | 2021-10-22 | 北京华城工程管理咨询有限公司 | Construction method for synchronously implementing underground reverse construction method and ground structure sequential construction |
CN115789340A (en) * | 2023-02-13 | 2023-03-14 | 中铁十八局集团有限公司 | In-situ protection structure for pipeline migration and modification digital construction and construction method |
-
1995
- 1995-04-21 JP JP7097011A patent/JPH08291526A/en active Pending
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11336095A (en) * | 1998-05-26 | 1999-12-07 | Kajima Corp | Construction of base isolation building |
KR101255610B1 (en) * | 2010-12-03 | 2013-04-16 | 주식회사 포스코건설 | Structure construction method and structure of use it |
CN113529694A (en) * | 2021-06-29 | 2021-10-22 | 北京华城工程管理咨询有限公司 | Construction method for synchronously implementing underground reverse construction method and ground structure sequential construction |
CN113529694B (en) * | 2021-06-29 | 2022-06-28 | 北京华城工程管理咨询有限公司 | Construction method for synchronously implementing underground reverse construction method and ground structure sequential construction |
CN115789340A (en) * | 2023-02-13 | 2023-03-14 | 中铁十八局集团有限公司 | In-situ protection structure for pipeline migration and modification digital construction and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH09242067A (en) | Building method for cast-in-place concrete pile | |
JPH08253946A (en) | Reverse placing method for concrete of underground structure under road | |
KR102286225B1 (en) | Method for constructing underground structure busing PC integrating method without support | |
RU2220258C1 (en) | Process of erection of multilevel underground structure ( variants ) | |
JP3760304B2 (en) | Building foundation construction method | |
JP6855296B2 (en) | Building foundation structure and its construction method | |
JPH08291526A (en) | Construction method for underground structure | |
JPH11172710A (en) | Method for constructing underground part of steel encased reinforced concrete building | |
JPH0684690B2 (en) | Building basement extension method | |
KR101077242B1 (en) | Construction method of basement structure using retaining wall and steel column | |
JP3109038B2 (en) | Underground skeleton structure and construction method | |
KR102583537B1 (en) | Top-down construction method for uneven-slope site | |
JPH10299003A (en) | Foundation work using precast concrete member | |
JP3809340B2 (en) | Reverse strike method | |
KR100694762B1 (en) | Method for constructing underground slabs and walls without preliminary wall-attached supports | |
JPS6217233A (en) | Foundation base column | |
JPH07103583B2 (en) | Construction method for large span underground structure | |
JPH0598653A (en) | Steel pipe concrete pillar in underground inverter construction method | |
JPH04366229A (en) | Temporary corresponding standard used for method of reverse driving construction | |
JP4045623B2 (en) | Construction method of reinforced concrete underground floor and underground structure constructed by this method | |
JPH0748848A (en) | Construction method for underground skeleton by inverted construction method | |
JP2023108327A (en) | Reconstruction method of building having underground structure | |
JPH06193084A (en) | Construction method for undeground structure | |
JP3238510B2 (en) | Construction method of preceding slab floor | |
JPH08105122A (en) | Underground and aboveground simultaneous execution method of structure |