JP3399873B2 - How to build a dome structure - Google Patents

How to build a dome structure

Info

Publication number
JP3399873B2
JP3399873B2 JP10845299A JP10845299A JP3399873B2 JP 3399873 B2 JP3399873 B2 JP 3399873B2 JP 10845299 A JP10845299 A JP 10845299A JP 10845299 A JP10845299 A JP 10845299A JP 3399873 B2 JP3399873 B2 JP 3399873B2
Authority
JP
Japan
Prior art keywords
dome
dome roof
roof
side wall
peripheral side
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP10845299A
Other languages
Japanese (ja)
Other versions
JP2000297476A (en
Inventor
信彦 木村
克 中埜
Original Assignee
機動建設工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 機動建設工業株式会社 filed Critical 機動建設工業株式会社
Priority to JP10845299A priority Critical patent/JP3399873B2/en
Publication of JP2000297476A publication Critical patent/JP2000297476A/en
Application granted granted Critical
Publication of JP3399873B2 publication Critical patent/JP3399873B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、配水池となるタン
ク構造物など、ドーム状の屋根構造を有する建築構造物
を構築する方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a building structure having a dome-shaped roof structure, such as a tank structure serving as a water distribution reservoir.

【0002】[0002]

【従来の技術】ドーム構造物は、お椀を伏せたような球
曲面状のドーム屋根に特徴がある。ドーム屋根は、その
外周縁で支持されるだけで、中央側には柱などの支持構
造を持たないので、内部空間が広く使えて有効に利用で
きる。このようなドーム構造物は、内部に液体などを収
容するタンク構造物や倉庫などに有用である。
2. Description of the Related Art A dome structure is characterized by a spherical curved dome roof that looks like a bowl. The dome roof is supported only by the outer peripheral edge of the dome roof and does not have a support structure such as a pillar on the center side, so that the internal space can be used widely and can be effectively used. Such a dome structure is useful for a tank structure, a warehouse, or the like that stores a liquid or the like inside.

【0003】ドーム構造物の施工は、施工面に床版や周
側壁などを順次構築したあと、周側壁の上部にドーム屋
根を構築する。柱による支持構造のないドーム屋根を構
築するには、周側壁の内部空間にドーム屋根の位置まで
到達する支保工やドーム型枠を架設しておき、これらの
支保工や型枠を利用して、鉄筋の配設やコンクリートの
打設などのドーム屋根の構築作業を行うことになる。
In the construction of a dome structure, a floor slab, a peripheral side wall, etc. are sequentially constructed on the construction surface, and then a dome roof is constructed on the upper side of the peripheral side wall. In order to build a dome roof without pillar support structure, support structures and dome formwork that reach the position of the dome roof are installed in the inner space of the peripheral side wall, and these support structures and formwork are used. , Doing the construction work of the dome roof such as arranging reinforcing bars and placing concrete.

【0004】このようなドーム屋根の施工方法では、支
保工や型枠の架設作業が非常に大掛かりになり、作業時
間および作業コストがかかるという問題がある。しか
も、ドーム屋根の構築を全て地上から離れた上方空間で
行うため、技術的にも困難が多く、高所作業に伴う安全
性確保も面倒である。このような問題を解決するため、
ドーム屋根を地上で建造したあと、完成したドーム屋根
を周側壁の上方まで持ち上げてドーム構造物を構築する
方法が提案されている。ドーム屋根を地上で建造するの
であれば、大掛かりな支保工や型枠の架設作業は要ら
ず、能率的かつ安全に作業が行える。
In such a method for constructing a dome roof, there is a problem that the supporting work and the erection work of the formwork are extremely large-scale work, and the work time and work cost are required. Moreover, since the dome roof is constructed entirely in the upper space away from the ground, there are many technical difficulties and it is difficult to ensure safety when working in high places. In order to solve such problems,
A method of constructing a dome structure by constructing a dome roof on the ground and then lifting the completed dome roof above the peripheral side wall has been proposed. If the dome roof is constructed on the ground, large-scale support work and erection work of the formwork are not required, and the work can be performed efficiently and safely.

【0005】特開平11−6325号公報には、床版上
で構築されたドーム屋根を、側壁頂部に設置されたリフ
ティング架台により、ケーブルを介して側壁上方まで吊
り上げる方法が示されている。
Japanese Unexamined Patent Publication (Kokai) No. 11-6325 discloses a method of hoisting a dome roof constructed on a slab to the upper side of a side wall via a cable by a lifting mount installed on the top of the side wall.

【0006】[0006]

【発明が解決しようとする課題】前記先行技術では、ド
ーム屋根を、周側壁で支持されない独立した状態で構築
し、構築されたドーム屋根を単独で上方空間に持ち上げ
る作業を行う必要があるので、ドーム屋根の強度を十分
に高くしておかなければならない。そのために、ドーム
屋根を構成するコンクリートの厚みを増やしたり、内部
に多数の鉄筋を配設しておいたりする必要があり、施工
に時間がかかりコストも高くつくという問題がある。
In the above-mentioned prior art, it is necessary to construct the dome roof in an independent state where it is not supported by the peripheral side wall, and perform the work of lifting the constructed dome roof alone to the upper space. The dome roof must be strong enough. Therefore, it is necessary to increase the thickness of concrete forming the dome roof and dispose a large number of reinforcing bars inside, which causes a problem that construction takes time and costs are high.

【0007】ドーム屋根の強度を高めるために重量が増
えると、ドーム屋根を地上から上方空間に持ち上げる作
業も行い難くなる。前記したケーブルによる吊り下げ方
法では、太いケーブルを使用したり、ケーブルの本数を
増やしたりしなければならず、大規模な設備が必要で、
作業能率も低下する。しかも、ケーブル吊り下げ装置
を、周側壁の上部すなわち高所に設置しなければなら
ず、その作業にも時間とコストがかかる。重いドーム屋
根を支えるには、周側壁の厚みや強度も増やす必要があ
り、そのための手間とコストも増大する。
If the weight of the dome roof is increased to increase its strength, it becomes difficult to lift the dome roof from the ground to the upper space. In the suspension method using the cable described above, it is necessary to use a thick cable or to increase the number of cables, which requires a large-scale facility,
Work efficiency also decreases. In addition, the cable suspension device must be installed at the upper part of the peripheral side wall, that is, at a high place, and the work takes time and cost. In order to support a heavy dome roof, it is necessary to increase the thickness and strength of the peripheral side wall, which increases labor and cost.

【0008】しかも、ドーム屋根は、その構造上、自重
が増えすぎると却って構造強度が低下し、周側壁に加わ
る荷重も増えるので、施工後のドーム構造物の耐久性に
も悪影響を及ぼす。そこで、本発明の課題は、前記した
床版上で構築されたドーム屋根を上方空間に持ち上げる
作業を簡単かつ能率的に行えるようにして、ドーム構造
物の施工を容易することである。
In addition, the structure of the dome roof, if its own weight is excessively increased, rather reduces the structural strength and increases the load applied to the peripheral side walls, which adversely affects the durability of the dome structure after construction. Therefore, an object of the present invention is to facilitate the work of lifting the dome roof constructed on the floor slab to the upper space in a simple and efficient manner to facilitate the construction of the dome structure.

【0009】[0009]

【課題を解決するための手段】本発明にかかるドーム構
造物の構築方法は、床版と、床版に立設された周側壁
と、周側壁の上部に配置され周側壁の内側を覆うドーム
屋根とを有するドーム構造物を構築する方法であって、
以下の工程(a) 〜工程(c) を含む。床版上で、ドーム屋
根として、ドーム状をなす殻面部と、殻面部の外周に配
置された周環部と、周環部の円周方向に沿って配置され
たPC鋼材とを有し、PC鋼材を緊張させて固定するこ
とで円周方向のプレストレスが導入されたドーム屋根を
構築する工程(a) 。
A method of constructing a dome structure according to the present invention comprises a floor slab, a peripheral side wall standing on the floor slab, and a dome arranged above the peripheral side wall and covering the inside of the peripheral side wall. A method of constructing a dome structure having a roof,
The following steps (a) to (c) are included. On the floor slab, as a dome roof, has a dome-shaped shell surface portion, a peripheral ring portion arranged on the outer periphery of the shell surface portion, and a PC steel material arranged along the circumferential direction of the peripheral ring portion, Step (a) of constructing a dome roof with prestress in the circumferential direction by tensioning and fixing PC steel.

【0010】プレストレスが導入されたドーム屋根を、
床版の上方空間に持ち上げて支持する工程(b) 。持ち上
げられたドーム屋根の下方に周側壁を構築し、周側壁と
ドーム屋根とを結合する工程(c) 。 〔ドーム構造物〕通常の配水タンクや倉庫、競技場、集
会場、展示場その他のドーム状の空間を必要とする構造
物に適用できる。
Dome roof with prestress introduced
Step (b) of lifting and supporting in the space above the floor slab. Step (c) of constructing a peripheral side wall below the raised dome roof and connecting the peripheral side wall and the dome roof. [Dome structure] Applicable to ordinary water distribution tanks, warehouses, stadiums, meeting venues, exhibition halls, and other structures that require a dome-shaped space.

【0011】ドーム構造物は、床版と周側壁とドーム屋
根とを備えている。配水タンクなどの容器状構造物の場
合は、ほぼ密閉状の空間を構成する。目的によって、ド
ーム屋根や周側壁の一部に、人や物品の出入口となる開
口を設ける場合もある。 〔ドーム屋根の構築〕ドーム屋根の構造は、基本的に
は、通常のドーム構造物におけるドーム屋根と同様の形
状および構造を採用することができる。ドーム屋根を構
成する基本的な材料はコンクリートであるが、鋼材料や
木材、合成樹脂、ガラスなどを組み合わせて使用するこ
ともできる。
The dome structure comprises a floor slab, a peripheral side wall and a dome roof. In the case of a container-like structure such as a water distribution tank, a nearly sealed space is formed. Depending on the purpose, there may be a case where an opening serving as an entrance / exit for people or articles is provided in a part of the dome roof or the side wall. [Construction of Dome Roof] As for the structure of the dome roof, basically the same shape and structure as the dome roof in a normal dome structure can be adopted. The basic material forming the dome roof is concrete, but steel materials, wood, synthetic resins, glass, etc. can also be used in combination.

【0012】ドーム屋根は、いわゆる丸屋根を構成する
ドーム状の殻面部と、殻面部の外周に配置された周環部
と、周環部の円周方向に沿って配置されたPC鋼材とを
有する。殻面部は、通常、球面の一部を切り取った曲面
形状を有しているが、厳密な球面でなくても、実質的に
球面とみなせる形状や、球面以外の曲面形状であった
り、球面と球面以外の形状とを組み合わせたものであっ
てもよい。
The dome roof comprises a dome-shaped shell surface portion forming a so-called round roof, a peripheral ring portion arranged on the outer periphery of the shell surface portion, and a PC steel material arranged along the circumferential direction of the peripheral ring portion. Have. The shell surface portion usually has a curved surface shape obtained by cutting a part of a spherical surface, but even if it is not a strict spherical surface, it can be regarded as a substantially spherical surface, or a curved surface shape other than a spherical surface, or a spherical surface. It may be a combination of shapes other than spherical.

【0013】周環部に円周方向に沿って、プレストレス
コンクリート用の鋼材(以下、PC鋼材と呼ぶ)を配置
しておき、このPC鋼材に強い引張力を加えて緊張させ
た状態で固定する。その結果、殻面部に発生する応力
は、軸力しか作用しない状態になり、この軸力だけに対
応できる構造を有していればよいことになる。PC鋼材
は、ドーム屋根の周環部に埋め込まれてあってもよい
し、周環部の外周に巻回されていてもよい。導入するプ
レストレスの強さは、ドーム屋根の構造や要求強度など
の条件によっても異なるが、周環部には殻面部の自重と
積載荷重に対応する圧縮力を導入する。
A steel material for prestressed concrete (hereinafter referred to as PC steel material) is arranged along the circumferential direction in the circumferential ring portion and fixed in a state of being tensioned by applying a strong tensile force to the PC steel material. To do. As a result, the stress generated in the shell surface portion is in a state in which only the axial force acts, and it suffices that the structure has a structure capable of handling only this axial force. The PC steel material may be embedded in the circumferential ring portion of the dome roof, or may be wound around the outer circumference of the circumferential ring portion. The strength of the prestress to be introduced depends on the structure of the dome roof and the conditions such as the required strength, but a compressive force corresponding to the weight of the shell surface and the load is applied to the circumferential ring.

【0014】このようなプレストレス構造を採用するこ
とで、ドーム屋根の強度や耐久性が向上する。その結
果、ドーム屋根、特に殻面部の厚みを薄くできる。ま
た、ドーム屋根に配筋する鉄筋の本数を少なくしたり線
径を細くしたりできる。ドーム屋根の具体的な寸法は、
ドーム構造物全体の寸法によっても異なるが、通常は、
ドーム屋根の半径が10〜50m、殻面部の厚みは10
〜15cm程度に設定される。この厚みは、殻面部の構造
体の厚みで規定し、表面の仕上げに施工される化粧モル
タルや塗装などの厚みは含まない。
By adopting such a prestress structure, the strength and durability of the dome roof are improved. As a result, the thickness of the dome roof, especially the shell surface portion can be reduced. Also, the number of reinforcing bars arranged on the dome roof can be reduced and the wire diameter can be reduced. The specific dimensions of the dome roof are
Although it depends on the size of the entire dome structure,
The dome roof has a radius of 10 to 50 m and the shell surface has a thickness of 10
It is set to about 15 cm. This thickness is defined by the thickness of the structure of the shell surface portion, and does not include the thickness of decorative mortar or paint applied to finish the surface.

【0015】ドーム屋根は、現場打ちコンクリートで施
工することもできるし、プレキャストコンクリートパネ
ルを用いるPCパネル工法を採用することもできる。現
場打ちコンクリートの場合、ドーム屋根の形状に対応す
る型枠を設置し、必要に応じて鉄筋を配筋し、型枠内に
コンクリートを打設して形成される。PCパネル工法
は、ドーム屋根のうち殻面部の全体形状を複数枚のプレ
キャストパネルを組み合わせて構成する。プレキャスト
パネルは、殻面部の概略球面形状などを、円周方向に複
数枚の扇面に分割したもの、あるいは、円周方向に分割
するとともに径方向にも複数段に分割したものである。
The dome roof can be constructed of cast-in-place concrete or the PC panel construction method using precast concrete panels. In the case of cast-in-place concrete, it is formed by installing a formwork corresponding to the shape of the dome roof, arranging reinforcing bars as necessary, and placing concrete in the formwork. In the PC panel method, the entire shell surface of the dome roof is formed by combining a plurality of precast panels. The precast panel is one in which a roughly spherical shape of the shell surface portion is divided into a plurality of fan surfaces in the circumferential direction, or is divided in the circumferential direction and also in a plurality of steps in the radial direction.

【0016】各プレキャストパネルは、縦横に鉄筋が配
筋されたコンクリート板からなり、工場生産して施工現
場に搬入してもよいし、施工現場でパネル型枠にコンク
リートを打設して製造してもよい。ドーム屋根を構築す
る際に、後述するドーム屋根の持ち上げ作業に利用する
受金具などを取り付けておくことができる。受金具は周
環部に取り付けておくことが好ましい。 〔ドーム屋根の持ち上げ〕通常の土木建築技術における
重量物の持ち上げ技術が適用できる。クレーンやジャッ
キなどの持ち上げ装置が使用される。
Each precast panel is made of a concrete plate in which reinforcing bars are arranged in the vertical and horizontal directions, and may be produced at the factory and brought to the construction site. Alternatively, the precast panel is manufactured by placing concrete on the panel formwork. May be. When constructing the dome roof, it is possible to install a receiving metal fitting used for lifting work of the dome roof, which will be described later. It is preferable that the bracket be attached to the circumferential ring portion. [Dome roof lifting] The heavy object lifting technology in ordinary civil engineering and construction technology can be applied. Lifting devices such as cranes and jacks are used.

【0017】重いドーム屋根を確実かつ容易に所定の位
置まで持ち上げる方法として、以下の方法が採用でき
る。ドーム屋根の外周に沿って複数個所に、ドーム屋根
を支持し上下に昇降自在な荷重受台を有する架設ジャッ
キを配置する。架設ジャッキの配置場所は、床版の外側
あるいは内側で、周側壁の構築の邪魔にならない個所に
設定する。
The following method can be adopted as a method for reliably and easily lifting the heavy dome roof to a predetermined position. A plurality of erection jacks are provided along the outer circumference of the dome roof to support the dome roof and to have vertically movable load receiving stands. Place the erection jack on the outside or inside of the slab so that it does not interfere with the construction of the peripheral side wall.

【0018】架設ジャッキは、通常の油圧等で駆動され
る土木用のジャッキ装置が用いられる。ドーム屋根の重
量や構造に合わせて、架設ジャッキの使用数および配置
は適宜に設定される。但し、使用する架設ジャッキのう
ちの少なくとも一部、通常は半数だけでドーム屋根の重
量を支えられるように設定しておく。ドーム屋根には、
架設ジャッキの荷重受台が当接する位置に受金具を設け
ておくことができる。受金具は鋼材などで構成される。
複数個所の受金具でドーム屋根全体の荷重が支持できる
ように、受金具の形状配置を設定しておく。
As the erection jack, a jack device for civil engineering which is driven by ordinary hydraulic pressure is used. The number and layout of the erection jacks are set appropriately according to the weight and structure of the dome roof. However, the weight of the dome roof should be set so that only at least a part of the erection jacks used, usually half of them, can support the weight. On the dome roof,
A receiving metal fitting can be provided at a position where the load receiving base of the erection jack abuts. The bracket is made of steel or the like.
The shape of the bracket is set so that the load on the entire dome roof can be supported by the brackets at multiple locations.

【0019】作業工程としては、以下の工程(b-1)(b-2)
(b-3) を繰り返す。 工程(b-1) :複数個所の架設ジャッキのうちの一部の架
設ジャッキで、荷重受台を上昇させてドーム屋根を持ち
上げる。荷重受台を上昇させる架設ジャッキの個数は任
意に設定でき、荷重受台を上昇させない架設ジャッキが
少なくとも1個所残っていればよい。通常は、架設ジャ
ッキの総数の半分の架設ジャッキを使用する。この場
合、ドーム屋根の外周に配置された架設ジャッキを一つ
置きに使用すればよい。ドーム屋根を持ち上げる高さ
を、後述する支柱ブロックの1個分あるいは複数個分の
高さに設定する。
The working steps are as follows (b-1) (b-2)
Repeat (b-3). Step (b-1): With some of the erection jacks at a plurality of erection jacks, the load receiving base is raised to lift the dome roof. The number of erection jacks for raising the load pedestal can be set arbitrarily, and at least one erection jack that does not raise the load pedestal remains. Normally, half the total number of erection jacks is used. In this case, the erection jacks arranged on the outer circumference of the dome roof may be used alternately. The height at which the dome roof is lifted is set to the height for one or a plurality of pillar blocks described later.

【0020】工程(b-2) :荷重受台を上昇させていない
架設ジャッキで、荷重受台とドーム屋根との間に支柱ブ
ロックを挿入し、支柱ブロックをドーム屋根に固定す
る。支柱ブロックは、鋼板や鋼棒などの鋼材あるいは鋼
材の組立体からなり、支柱ブロック同士を上下に連結す
る連結構造を備えている。連結構造は、通常の支保工な
どと同様の連結構造が採用でき、ボルトによる締結構
造、嵌合構造などが挙げられる。ドーム屋根の受金具に
も支柱ブロックと同様の連結構造を備えておけば、ドー
ム屋根への支柱ブロックの固定が行い易い。
Step (b-2): An erection jack in which the load pedestal is not raised, and a pillar block is inserted between the load cradle and the dome roof, and the pillar block is fixed to the dome roof. The strut block is made of a steel material such as a steel plate or a steel rod, or an assembly of steel materials, and has a connecting structure for vertically connecting the strut blocks. As the connection structure, a connection structure similar to ordinary support work can be adopted, and examples include a fastening structure using bolts and a fitting structure. If the bracket for the dome roof is also provided with the same connecting structure as the pillar block, it is easy to fix the pillar block to the dome roof.

【0021】支柱ブロックは、各架設ジャッキ毎に1個
または複数個を挿入して、ドーム屋根と荷重受台との隙
間を埋める。複数個の支柱ブロックを挿入する場合に
は、上下に配置される支柱ブロック同士を連結固定して
おく。 工程(b-3) :荷重受台を上昇させた架設ジャッキで、荷
重受台を下降させてドーム屋根との間に間隙を設け、こ
の間隙に支柱ブロックを挿入し、支柱ブロックをドーム
屋根に固定する。荷重受台を下降させる架設ジャッキ
は、前工程で上昇させた全ての架設ジャッキであっても
よいし、そのうちの一部の架設ジャッキであってもよ
い。荷重受台を上昇させた架設ジャッキを複数組に分割
して、この工程を順番に行えば、最終的には全ての架設
ジャッキに対して、荷重受台とドーム屋根との間に支柱
ブロックが挿入されることになる。
One or a plurality of column blocks are inserted for each erection jack to fill the gap between the dome roof and the load receiving base. When inserting a plurality of pillar blocks, the pillar blocks arranged above and below are connected and fixed. Step (b-3): With the erection jack with the load pedestal raised, lower the load pedestal to make a gap with the dome roof, insert the pillar block into this gap, and place the pillar block on the dome roof. Fix it. The erection jack that lowers the load receiving base may be all the erection jacks that have been lifted in the previous step, or some of the erection jacks. If you divide the erection jack with the load pedestal raised into multiple sets and perform this process in order, finally, for all the erection jacks, the pillar blocks will be placed between the load pedestal and the dome roof. Will be inserted.

【0022】上記工程の結果、全ての架設ジャッキの上
に支柱ブロックを介してドーム屋根が支持される。ドー
ム屋根は、挿入された支柱ブロックの高さ分だけ持ち上
げられることになる。上記工程(b-1)(b-2)(b-3) を繰り
返せば、ドーム屋根を所望の高さまで持ち上げ、その状
態で安定に支持しておくことができる。この状態で、架
設ジャッキおよび支柱ブロックの内側に、周側壁を構築
できるスペースをあけておけば、ドーム屋根を支持した
ままで周側壁の構築ができる。 〔周側壁の構築〕通常のドーム構造物における周側壁の
構築技術が適用できる。
As a result of the above steps, the dome roof is supported on all the erection jacks via the pillar blocks. The dome roof will be lifted by the height of the inserted pillar block. By repeating the above steps (b-1) (b-2) (b-3), the dome roof can be lifted to a desired height and stably supported in that state. In this state, if a space where the peripheral side wall can be constructed is opened inside the erection jack and the pillar block, the peripheral side wall can be constructed while supporting the dome roof. [Construction of Peripheral Side Wall] A general technique for constructing a peripheral side wall in a dome structure can be applied.

【0023】施工現場に型枠を構築し、型枠内にコンク
リートを打設する現場施工が採用できる。予め製造され
たプレキャストパネルを組み立て、パネルの間隙に間詰
めコンクリートを打設して結合一体化させる方法も採用
できる。周側壁には、円周方向および軸線方向の片方あ
るいは両方にプレストレスを導入することができる。
It is possible to adopt the on-site construction in which the formwork is constructed on the construction site and concrete is poured into the formwork. It is also possible to adopt a method of assembling precast panels manufactured in advance and pouring space-filling concrete in the gaps between the panels to combine and integrate them. Prestress can be introduced into the circumferential side wall in one or both of the circumferential direction and the axial direction.

【0024】周側壁を構築したあと、周側壁とドーム屋
根とを結合一体化させる。具体的には、周側壁とドーム
屋根との間隙をコンクリート打設などで埋めればよい。
周側壁とドーム屋根とを連結する鉄筋を配筋しておくこ
とができる。周側壁とドーム屋根との間に垂直方向のプ
レストレスを導入することができる。具体的には、周側
壁とドーム屋根の少なくとも一部を貫通するPC鋼材を
配置し、PC鋼材に緊張力を加えた状態でPC鋼材の両
端を周側壁とドーム屋根との両方に固定すればよい。P
C鋼材の両端を、ドーム屋根と周側壁を挟んで床版とに
固定することもできる。
After the peripheral side wall is constructed, the peripheral side wall and the dome roof are combined and integrated. Specifically, the gap between the peripheral side wall and the dome roof may be filled with concrete or the like.
Reinforcing bars connecting the peripheral side wall and the dome roof can be arranged. Vertical prestress can be introduced between the peripheral side wall and the dome roof. Specifically, by arranging a PC steel material penetrating at least a part of the peripheral side wall and the dome roof, and fixing both ends of the PC steel material to both the peripheral side wall and the dome roof in a state where a tension force is applied to the PC steel material. Good. P
It is also possible to fix both ends of the C steel material to the slab sandwiching the dome roof and the peripheral side wall.

【0025】ドーム屋根が周側壁で支持されるようにな
れば、架設ジャッキおよび支柱ブロックなど、ドーム屋
根の支持構造を撤去することができる。周側壁やドーム
屋根などからなるドーム構造物には、外面にモルタル仕
上げを行ったり、配管や電気配線、作業者が昇るための
階段や手摺り、その他の必要な装置設備を設置したりす
る仕上げ作業が行われて、ドーム構造物の建築施工が完
了する。
When the dome roof is supported by the side wall, the supporting structure of the dome roof such as the erection jack and the pillar block can be removed. For the dome structure consisting of the side wall and the dome roof, finish the outer surface with mortar, install piping, electrical wiring, stairs and handrails for workers to climb, and other necessary equipment. Work is done and the construction of the dome structure is completed.

【0026】[0026]

【発明の実施形態】図1に概略構造を示すドーム構造物
を構築する方法を説明する。ドーム構造物は、円形状の
床版20と、床版20の上に床版20の外周に沿って立
設された円筒状の周側壁50と、周側壁50の上端に配
置され概略球面状をなすドーム屋根10とで構成されて
いる。 〔床版20の構築工程〕床版20は、基本的には通常の
ドーム構造物の場合と同様の工程で構築される。
DETAILED DESCRIPTION OF THE INVENTION A method for constructing a dome structure whose schematic structure is shown in FIG. 1 will be described. The dome structure includes a circular floor slab 20, a cylindrical peripheral side wall 50 standing on the floor slab 20 along the outer periphery of the floor slab 20, and a substantially spherical shape arranged at the upper end of the peripheral side wall 50. And the dome roof 10 forming the. [Construction process of floor slab 20] The floor slab 20 is basically constructed in the same process as in the case of a normal dome structure.

【0027】具体的には、図2に示すように、地面を少
し掘り下げ、型枠を設置し、必要に応じて鉄筋を配筋
し、コンクリートを打設して、床版20が形成される。
床版20の外周には、架設ジャッキ30を設置するため
の収容凹部22を形成しておく。図3に示すように、ド
ーム屋根10の外周に沿って等間隔で複数個所に配置さ
れる架設ジャッキ30のそれぞれに対して、床版20に
は収容凹部22が形成される。
Specifically, as shown in FIG. 2, the ground is dug down a little, a form is installed, reinforcing bars are reinforced if necessary, and concrete is poured to form a floor slab 20. .
A housing recess 22 for installing the erection jack 30 is formed on the outer periphery of the floor slab 20. As shown in FIG. 3, a housing recess 22 is formed in the floor slab 20 for each of the erection jacks 30 arranged at a plurality of positions at equal intervals along the outer periphery of the dome roof 10.

【0028】架設ジャッキ30は、その上端に上下に昇
降自在な荷重受台32を備えている。収容凹部22に収
容された架設ジャッキ30は、上端の荷重受台32が床
版20の上面と同じ位置か少し上方に配置される。荷重
受台32は油圧によって作動し、複数個所の架設ジャッ
キ30の作動を、別に設置された制御装置等で集中的に
制御できるようにしておく。 〔ドーム屋根10の構築工程〕床版20の上でドーム屋
根10が構築される。
The erection jack 30 has a load pedestal 32 at the upper end thereof, which is vertically movable. In the erection jack 30 accommodated in the accommodation recess 22, the load receiving base 32 at the upper end is arranged at the same position as the upper surface of the floor slab 20 or slightly above. The load receiving base 32 is operated by hydraulic pressure so that the operation of the erection jacks 30 at a plurality of locations can be centrally controlled by a separately installed control device or the like. [Dome Roof 10 Construction Process] The dome roof 10 is constructed on the floor slab 20.

【0029】ドーム屋根10は、球面の一部を切り取っ
た曲面状をなす殻面部12と、殻面部12の外周を取り
囲み、殻面部12の厚みよりも分厚い周環部14とを備
える。図3に示すように、平面円形状をなす殻面部12
は、円を周方向に分割した複数枚の概略扇形をなすプレ
キャストパネル12aで構成されている。各パネル12
aの境界と全てのパネル12aの先端が集まる頂点部分
には、間詰めコンクリート12bが打設されている。
The dome roof 10 is provided with a shell surface portion 12 which is a curved surface obtained by cutting off a part of a spherical surface, and a peripheral ring portion 14 which surrounds the outer periphery of the shell surface portion 12 and is thicker than the thickness of the shell surface portion 12. As shown in FIG. 3, the shell surface portion 12 having a plane circular shape.
Is composed of a plurality of substantially fan-shaped precast panels 12a obtained by dividing a circle in the circumferential direction. Each panel 12
Filling concrete 12b is poured at the boundary of a and the apex where all the tips of the panels 12a gather.

【0030】図2に示すように、周環部14は、下部1
4bと上部14aとに分割形成されている。これは、下
部14bをコンクリートで打設形成したあと、その上で
殻面部12を形成し、そのあとで、上部14aを形成し
て周環部14を完成しているためである。このような構
造を採用することで、殻面部12の形成が行い易く、殻
面部12の荷重を周環部14で確実に支持でき、ドーム
屋根10全体の構造強度も高まる。
As shown in FIG. 2, the circumferential ring portion 14 has a lower portion 1
4b and an upper part 14a are formed separately. This is because, after the lower portion 14b is cast and formed by concrete, the shell surface portion 12 is formed thereon, and then the upper portion 14a is formed to complete the circumferential ring portion 14. By adopting such a structure, the shell surface portion 12 can be easily formed, the load of the shell surface portion 12 can be reliably supported by the circumferential ring portion 14, and the structural strength of the entire dome roof 10 is increased.

【0031】図3に示すように、周環部14には、円周
方向に沿ってPC鋼材16が埋め込まれる。図2に示す
ように、PC鋼材16は上下に複数本配置されている。
このPC鋼材16は、周環部14のコンクリートが打設
され、養生が行われた後で、軸方向に強い引張力を加え
られて緊張状態にされ、いわゆるプレストレスが導入さ
れている。このプレストレスは、周環部14およびその
内側の殻面部12を中心側に押し縮める方向に作用し
て、殻面部12が外周側に拡がるように変形する力に対
向し、ドーム屋根10の構造強度あるいは耐久性を向上
させる。
As shown in FIG. 3, a PC steel material 16 is embedded in the circumferential ring portion 14 along the circumferential direction. As shown in FIG. 2, a plurality of PC steel materials 16 are arranged vertically.
The concrete of the peripheral ring portion 14 is cast into the PC steel material 16, and after curing, a strong tensile force is applied in the axial direction to bring the PC steel material 16 into a tension state, and so-called prestress is introduced. This prestress acts on the circumferential ring portion 14 and the shell surface portion 12 inside thereof in a direction of compressing the shell surface portion 12 toward the center side, and opposes the force of deforming the shell surface portion 12 so as to expand to the outer peripheral side, and the structure of the dome roof 10 Improves strength or durability.

【0032】上記したドーム屋根10の構築作業では、
床版20上でコンクリート打設用の型枠を設置したり、
そのための支保工や作業用の足場を設置したりする作業
が行われる。しかし、床版20すなわち地面に対するド
ーム屋根10の高さは、最大でも殻面部12の膨らみ程
度しかないので、支保工や足場あるいは型枠の高さも比
較的に低いものでよく、作業は容易であり、作業者の安
全性も確保し易い。
In the construction work of the dome roof 10 described above,
Installing a formwork for concrete placement on the floor slab 20,
For this purpose, support work and installation of scaffolds for work are performed. However, since the height of the slab 20 relative to the floor, that is, the height of the dome roof 10 with respect to the ground is only a bulge of the shell surface portion 12 at the maximum, the height of the support and scaffolding or the formwork may be relatively low, and the work is easy. Yes, it is easy to ensure worker safety.

【0033】また、床版20の上に、支保工や型枠を設
置する代わりに、構築されるドーム屋根10の下面形状
に沿う曲面状に砂や粘土を堆積させておけば、この堆積
物の曲面にしたがってコンクリートを打設してドーム屋
根10を構築することができる。ドーム屋根10の周環
部14の外周側面には、床版20の凹部22に設置され
た架設ジャッキ30の荷重受台32が当接する受金具3
4が外向きに張り出して取り付けられている。 〔ドーム屋根10の持ち上げ工程〕図4〜図8には、ド
ーム屋根10の持ち上げ工程を段階的に示している。
If sand or clay is deposited on the floor slab 20 in a curved shape along the lower surface shape of the dome roof 10 to be constructed instead of installing supports and forms, this deposit will be deposited. The dome roof 10 can be constructed by placing concrete according to the curved surface of. On the outer peripheral side surface of the peripheral ring portion 14 of the dome roof 10, the load receiving bracket 32 of the erection jack 30 installed in the recess 22 of the floor slab 20 abuts.
4 is attached so as to project outward. [Dome Roof 10 Lifting Process] FIGS. 4 to 8 show the dome roof 10 lifting process in stages.

【0034】前記図2に示すように、ドーム屋根10が
複数個所の架設ジャッキ30で支持された状態から作業
が始まる。図4に示すように、複数個所の架設ジャッキ
30のうち、円周方向で一つ置きに配置された架設ジャ
ッキ30で、荷重受台32を上昇させる。図3に示す配
置形態の場合、6個所の架設ジャッキ30のうち、一つ
置きの3個所の架設ジャッキ30aで荷重受台32を上
昇させ、残りの3個所の架設ジャッキ30bは作動させ
ない。このような架設ジャッキ30の作動は、予め決め
られたプログラムにしたがって、各架設ジャッキ30に
供給する油圧配管の制御バルブや油圧ポンプなどを制御
することで行われる。同時に上昇させる複数の架設ジャ
ッキ30の作動が連動するように駆動用の油圧配管系を
互いに連結しておく。
As shown in FIG. 2, the work starts when the dome roof 10 is supported by the erection jacks 30 at a plurality of locations. As shown in FIG. 4, among the erection jacks 30 at a plurality of positions, the erection jacks 30 arranged at every other in the circumferential direction raise the load receiving base 32. In the case of the arrangement form shown in FIG. 3, of the installation jacks 30 at six locations, the load receiving base 32 is raised by the installation jacks 30a at every other three locations, and the installation jacks 30b at the remaining three locations are not operated. Such an operation of the erection jack 30 is performed by controlling a control valve of a hydraulic pipe or a hydraulic pump that is supplied to each erection jack 30 according to a predetermined program. The hydraulic piping systems for driving are connected to each other so that the operations of the plurality of erection jacks 30 that are simultaneously raised are interlocked.

【0035】受金具34を介して荷重受台32に支持さ
れたドーム10は、上方に持ち上げられる。複数の架設
ジャッキ30の作動量をバランスさせて制御すること
で、屋根ドーム10を水平状態のままで所定の距離だけ
確実に持ち上げることができる。荷重受台32を上昇さ
せなかった架設ジャッキ30bの個所では、荷重受台3
2と受金具34との間に隙間があく。
The dome 10 supported by the load receiving base 32 via the receiving metal fitting 34 is lifted upward. By balancing and controlling the operation amounts of the plurality of erection jacks 30, the roof dome 10 can be reliably lifted by a predetermined distance in a horizontal state. At the location of the erection jack 30b where the load cradle 32 has not been raised, the load cradle 3
There is a gap between 2 and the receiving bracket 34.

【0036】図5に示すように、架設ジャッキ30bの
荷重受台32と受金具34との隙間に、支柱ブロック3
6を挿入する。支柱ブロック36は、鋼材を組立接合し
て作製されており、上下方向に大きな耐荷重力を有して
いる。支柱ブロック36同士は、ボルト連結などの締結
手段で、上下に連結自在になっている。受金具34にも
支柱ブロック36と同様の連結構造を備えており、この
連結構造を使って支柱ブロック36を受金具34に固定
する。
As shown in FIG. 5, the support block 3 is provided in the gap between the load receiving base 32 and the receiving metal fitting 34 of the erection jack 30b.
Insert 6. The pillar block 36 is made by assembling and joining steel materials, and has a large load bearing force in the vertical direction. The pillar blocks 36 are vertically connectable by fastening means such as bolt connection. The receiving metal fitting 34 is also provided with the same connecting structure as the supporting pillar block 36, and the supporting pillar block 36 is fixed to the receiving metal fitting 34 using this connecting structure.

【0037】図6に示すように、架設ジャッキ30aで
上昇させていた荷重受台32を元の位置まで下降させ
る。屋根ブロック10は支柱ブロック36を介して架設
ジャッキ30bの荷重受台32で支持されている。架設
ジャッキ30aの荷重受台32とドーム屋根10の受金
具34との間には隙間があく。図7に示すように、架設
ジャッキ30aの荷重受台32と受金具34の間に支柱
ブロック36を挿入し、支柱ブロック36を受金具34
に固定する。
As shown in FIG. 6, the load receiving base 32, which has been raised by the erection jack 30a, is lowered to its original position. The roof block 10 is supported by a load receiving base 32 of the erection jack 30b via a pillar block 36. There is a gap between the load receiving base 32 of the erection jack 30a and the receiving metal fitting 34 of the dome roof 10. As shown in FIG. 7, a support block 36 is inserted between the load receiving base 32 and the receiving metal fitting 34 of the erection jack 30 a and the supporting pillar block 36 is attached to the receiving metal fitting 34.
Fixed to.

【0038】この状態で、全ての架設ジャッキ30a、
30bの荷重受台32は同じ高さ位置にあり、全ての荷
重受台32と受金具34との間には1個の支柱ブロック
36が配置されることになる。ドーム屋根10は、支柱
ブロック36の1個分だけ上方に持ち上げられたことに
なる。次に、図8に示すように、再び1群の架設ジャッ
キ30aを伸ばすと、ドーム屋根10が持ち上げられる
とともに、残りの架設ジャッキ30bの個所では、支柱
ブロック36は受金具34とともに上方に持ち上げら
れ、荷重受台32との間に隙間があく。この状態は、支
柱ブロック36が1個づつ存在する以外は、前記した図
4の状態と同じである。
In this state, all the erection jacks 30a,
The load receiving bases 32 of 30b are at the same height position, and one column block 36 is arranged between all the load receiving bases 32 and the metal fittings 34. The dome roof 10 is lifted up by one column block 36. Next, as shown in FIG. 8, when the group of erection jacks 30a is extended again, the dome roof 10 is lifted up, and at the rest of the erection jacks 30b, the support block 36 is lifted up together with the bracket 34. , There is a gap between the load receiving table 32 and the load receiving table 32. This state is the same as the state of FIG. 4 described above, except that one column block 36 is provided.

【0039】その後、図4〜図7と同様の操作を行え
ば、全ての架設ジャッキ30a、30bと受金具34の
間に2個づつの支柱ブロック36が配置され、ドーム屋
根10は支柱ブロック36の2個分だけ上方に持ち上げ
られる。このような作業を順次繰り返すことで、ドーム
屋根10と架設ジャッキ30との間に任意の個数の支柱
ブロック36を挿入することができ、ドーム屋根10を
所望の高さまで持ち上げることができる。ドーム屋根1
0の位置が高くなっても、支柱ブロック36の挿入作業
は常に架設ジャッキ30の位置で行えばよいので、作業
は容易で効率的に行え、作業者の安全も確保し易い。
After that, if the same operation as in FIGS. 4 to 7 is performed, two column blocks 36 are arranged between all the erection jacks 30a and 30b and the receiving metal fitting 34, and the dome roof 10 has the column blocks 36. Can be lifted up by 2 pieces. By repeating such operations in sequence, an arbitrary number of pillar blocks 36 can be inserted between the dome roof 10 and the erection jack 30, and the dome roof 10 can be lifted to a desired height. Dome roof 1
Even if the position of 0 is high, the work of inserting the column block 36 may be always performed at the position of the erection jack 30, so the work can be performed easily and efficiently, and the safety of the worker can be easily ensured.

【0040】図1に示すように、ドーム屋根10を、そ
の下方に周側壁50が構築できる位置まで持ち上げる。 〔周側壁50の構築工程〕ドーム屋根10が所定の高さ
位置に持ち上げられて支持された状態で、ドーム屋根1
0の下方空間で周側壁50を構築する。構築作業は、通
常のドーム構造物における周側壁50の構築と同様に行
える。
As shown in FIG. 1, the dome roof 10 is lifted to a position below which the peripheral side wall 50 can be constructed. [Construction Process of Peripheral Side Wall 50] With the dome roof 10 being lifted and supported at a predetermined height position, the dome roof 1
The peripheral side wall 50 is constructed in the space below 0. The construction work can be performed in the same manner as the construction of the peripheral side wall 50 in a normal dome structure.

【0041】図1の実施形態では、予め作製された矩形
状のプレキャストパネル52を、床版20とドーム屋根
10との間に立てて円周状に配置したあと、パネル52
同士の隙間に間詰めコンクリートを打設して複数枚のパ
ネル52を一体接合して周側壁50を構築する。周側壁
50を構築する際には、周側壁50の内部に円周方向に
沿ってPC鋼材を埋め込み、PC鋼材に前記同様のプレ
ストレスを導入することで、周側壁50の構造強度を向
上させることができる。前記したパネル52として、予
めPC鋼材が埋め込まれたものを用いることができる。
In the embodiment shown in FIG. 1, a prefabricated rectangular precast panel 52 is erected between the floor slab 20 and the dome roof 10 and circumferentially arranged.
Filling concrete in the gaps between them to form a peripheral side wall 50 by integrally joining a plurality of panels 52. When constructing the peripheral side wall 50, the structural strength of the peripheral side wall 50 is improved by embedding PC steel material inside the peripheral side wall 50 along the circumferential direction and introducing the same prestress to the PC steel material. be able to. As the panel 52 described above, a panel in which PC steel material is embedded in advance can be used.

【0042】周側壁50が構築されたあと、周側壁50
とドーム屋根10との間もコンクリートを打設するなど
して一体接合すれば、ドーム構造物の基本的な構造体部
分が完成する。周側壁50とドーム屋根10の周環部1
4との間にもプレストレスを導入することで、周側壁5
0と周環部14すなわちドーム屋根10との一体性を高
めることができる。具体的には、図1に示すように、周
側壁50と周環部14とを上下方向に貫通するPC鋼材
54を配置し、PC鋼材54に引張力を加えて固定すれ
ばよい。
After the peripheral side wall 50 is constructed, the peripheral side wall 50 is
The basic structure portion of the dome structure is completed if the dome roof 10 and the dome roof 10 are integrally joined by pouring concrete. Circumferential side wall 50 and circumferential ring portion 1 of dome roof 10
By introducing pre-stress between 4 and 5,
0 and the circumferential ring portion 14, that is, the dome roof 10 can be more integrated. Specifically, as shown in FIG. 1, a PC steel material 54 that penetrates the peripheral side wall 50 and the peripheral ring portion 14 in the vertical direction may be arranged, and a tensile force may be applied to the PC steel material 54 to fix the PC steel material 54.

【0043】ドーム屋根10を支持していた支柱ブロッ
ク36および架設ジャッキ30は、ドーム屋根10と周
側壁50とが一体接合されたあとで撤去すればよい。ド
ーム屋根10の外周に取り付けられていた受金具34も
必要がなくなれば撤去してしまう。ドーム構造物の内部
あるいは外面には、仕上げ用のモルタルを塗工したり、
配管や作業用の階段、手摺りなどを設置したりする仕上
げ作業を行って、ドーム構造物が完成する。
The support block 36 and the erection jack 30 supporting the dome roof 10 may be removed after the dome roof 10 and the peripheral side wall 50 are integrally joined. The receiving metal fitting 34 attached to the outer periphery of the dome roof 10 is also removed when it is no longer necessary. The inner or outer surface of the dome structure is coated with mortar for finishing,
Finishing work such as installing piping, stairs for work, and handrails is completed to complete the dome structure.

【0044】[0044]

【発明の効果】本発明にかかるドーム構造物の構築方法
は、円周方向のプレストレスが導入されたドーム屋根を
用いるので、比較的に厚みが薄く軽量のドーム屋根でも
十分な構造強度を有するものとなり、ドーム屋根を床版
の上方空間に持ち上げて支持しておく作業が容易かつ能
率的に行える。ドーム屋根の構築は地上で行えるので、
ドーム屋根の構築作業も容易であり、作業者の安全性も
確保し易い。
The method of constructing a dome structure according to the present invention uses a dome roof to which a prestress in the circumferential direction is introduced, and therefore a dome roof having a relatively thin thickness and a sufficient weight has a sufficient structural strength. As a result, the work of lifting and supporting the dome roof in the space above the floor slab can be performed easily and efficiently. Since the dome roof can be constructed on the ground,
Construction work of the dome roof is easy, and it is easy to ensure the safety of the worker.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の実施形態を表し、地上におけるドーム
屋根の構築状態を示す断面図
FIG. 1 is a cross-sectional view showing an embodiment of the present invention and showing a construction state of a dome roof on the ground.

【図2】ドーム屋根の構造を示す平面図FIG. 2 is a plan view showing the structure of a dome roof.

【図3】ドーム屋根の持ち上げ作業の第1段階を示す模
式的工程図
FIG. 3 is a schematic process diagram showing a first stage of a dome roof lifting operation.

【図4】ドーム屋根の持ち上げ作業の第2段階を示す模
式的工程図
FIG. 4 is a schematic process diagram showing the second stage of the dome roof lifting work.

【図5】ドーム屋根の持ち上げ作業の第3段階を示す模
式的工程図
FIG. 5 is a schematic process diagram showing the third stage of the dome roof lifting work.

【図6】ドーム屋根の持ち上げ作業の第4段階を示す模
式的工程図
FIG. 6 is a schematic process diagram showing a fourth stage of lifting work of the dome roof.

【図7】ドーム屋根の持ち上げ作業の第5段階を示す模
式的工程図
FIG. 7 is a schematic process diagram showing a fifth step of lifting the dome roof.

【図8】周側壁の構築作業を示す一部切欠正面図FIG. 8 is a partially cutaway front view showing the construction work of the peripheral side wall.

【符号の説明】[Explanation of symbols]

10 ドーム屋根 12 殻面部 14 周環部 16 PC鋼材 20 床版 22 収容凹部 30 架設ジャッキ 32 荷重受台 34 受金具 10 Dome roof 12 Shell surface 14 Circumference 16 PC steel 20 floor slab 22 Storage recess 30 erection jack 32 load cradle 34 Bracket

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 平6−57955(JP,A) 特開 平5−287815(JP,A) 特開 平11−6325(JP,A) 特開 平7−4110(JP,A) 特開 平10−45391(JP,A) 特公 昭58−56778(JP,B1) (58)調査した分野(Int.Cl.7,DB名) E04B 1/35 E04G 21/14 E04H 7/18 302 E04H 7/20 ─────────────────────────────────────────────────── --- Continuation of the front page (56) References JP-A-6-57955 (JP, A) JP-A-5-287815 (JP, A) JP-A-11-6325 (JP, A) JP-A-7- 4110 (JP, A) JP-A-10-45391 (JP, A) JP-B-58-56778 (JP, B1) (58) Fields investigated (Int.Cl. 7 , DB name) E04B 1/35 E04G 21 / 14 E04H 7/18 302 E04H 7/20

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】床版と、床版に立設された周側壁と、周側
壁の上部に配置され周側壁の内側を覆うドーム屋根とを
有するドーム構造物を構築する方法であって、 前記床版上で、前記ドーム屋根として、ドーム状をなす
殻面部と、殻面部の外周に配置された周環部と、周環部
の円周方向に沿って配置されたPC鋼材とを有し、PC
鋼材を緊張させて固定することで円周方向のプレストレ
スが導入されたドーム屋根を構築する工程(a) と、 前記プレストレスが導入されたドーム屋根を、床版の上
方空間に持ち上げて支持する工程(b) と、 前記持ち上げられたドーム屋根の下方に周側壁を構築
し、周側壁とドーム屋根とを結合する工程(c) と を含み、 前記工程(b) が、ドーム屋根の外周に沿って複数個所
に、ドーム屋根を支持し上下に昇降自在な荷重受台を有
する架設ジャッキを配置し、 複数個所の架設ジャッキのうちの一部の架設ジャッキ
で、荷重受台を上昇させてドーム屋根を持ち上げる工程
(b-1) と、 荷重受台を上昇させていない架設ジャッキで、荷重受台
とドーム屋根との間に支柱ブロックを挿入し、支柱ブロ
ックをドーム屋根に固定する工程(b-2) と、 前記荷重受台を上昇させた架設ジャッキで、荷重受台を
下降させてドーム屋根との間に間隙を設け、この間隙に
支柱ブロックを挿入し、支柱ブロックをドーム屋根に固
定する工程(b-3) とを繰り返す ドーム構造物の構築方法。
1. A method for constructing a dome structure having a floor slab, a peripheral side wall provided upright on the floor slab, and a dome roof arranged above the peripheral side wall and covering the inside of the peripheral side wall, the method comprising: On the floor slab, the dome roof has a dome-shaped shell surface portion, a peripheral ring portion arranged on the outer periphery of the shell surface portion, and a PC steel material arranged along the circumferential direction of the peripheral ring portion. , PC
Step (a) of constructing a dome roof in which circumferential prestress is introduced by tensioning and fixing the steel material, and supporting the dome roof in which the prestress is introduced by lifting it to the space above the floor slab a step of (b), to construct the peripheral side wall below the dome roof lifted, seen including a step (c) coupling the peripheral side wall and the dome roof, wherein step (b), the dome roof Multiple locations along the perimeter
In addition, there is a load stand that supports the dome roof and can move up and down freely.
Arrange the erection jacks, and install some of the erection jacks at multiple locations.
The process of raising the load pedestal and lifting the dome roof
(b-1) and the erection jack that does not raise the load cradle
Insert the pillar block between the roof and the dome roof, and
The load cradle with the step (b-2) of fixing the rack to the dome roof and the erection jack that raises the load cradle.
Lower it to create a gap between it and the dome roof.
Insert the pillar block and secure it to the dome roof.
A method for constructing a dome structure , which repeats the step (b-3) of determining .
【請求項2】前記工程(a) が、プレキャストコンクリー
トパネルを組み立ててドーム屋根の殻面部を構築する 請求項1に記載のドーム構造物の構築方法。
2. The method for constructing a dome structure according to claim 1, wherein the step (a) constructs a shell surface portion of a dome roof by assembling a precast concrete panel.
【請求項3】前記工程(c) が、周側壁とドーム屋根の周
環部とを垂直方向に貫通するPC鋼材を配置し、PC鋼
材を緊張させて固定し、周側壁とドーム屋根に垂直方向
のプレストレスを導入する請求項1〜の何れかに記載
のドーム構造物の構築方法。
3. The step (c) comprises arranging a PC steel material vertically penetrating the peripheral side wall and the peripheral annulus of the dome roof, tensioning and fixing the PC steel material, and vertically arranging the peripheral side wall and the dome roof. method for constructing a dome structure according to any one of claims 1-2 for introducing the direction of prestressing.
【請求項4】前記ドーム構造物が、PCタンクである請
求項1〜の何れかに記載のドーム構造物の構築方法。
Wherein said dome structure is, how to build the dome structure according to any one of claims 1 to 3 which is a PC tank.
JP10845299A 1999-04-15 1999-04-15 How to build a dome structure Expired - Fee Related JP3399873B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10845299A JP3399873B2 (en) 1999-04-15 1999-04-15 How to build a dome structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10845299A JP3399873B2 (en) 1999-04-15 1999-04-15 How to build a dome structure

Publications (2)

Publication Number Publication Date
JP2000297476A JP2000297476A (en) 2000-10-24
JP3399873B2 true JP3399873B2 (en) 2003-04-21

Family

ID=14485146

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10845299A Expired - Fee Related JP3399873B2 (en) 1999-04-15 1999-04-15 How to build a dome structure

Country Status (1)

Country Link
JP (1) JP3399873B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105046001A (en) * 2015-07-21 2015-11-11 上海海勃膜结构有限公司 Whole construction process simulation analysis method for prestressed suspended cable membrane dome structure

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102995909A (en) * 2012-11-14 2013-03-27 中冶天工集团有限公司 Space latticed shell coordinate rotation assembly method
CN105649206A (en) * 2016-01-05 2016-06-08 江苏沪宁钢机股份有限公司 Single-layer latticed shell steel structure roof and installation method thereof
CN106437171A (en) * 2016-07-18 2017-02-22 广州建筑股份有限公司 Multi-span continuous steel latticed shell accumulative sliding construction method
JP6902189B2 (en) * 2017-04-14 2021-07-14 株式会社大林組 PC liquid barrier
CN110230393B (en) * 2019-06-18 2024-04-05 中建三局第二建设工程有限责任公司 Large concrete tank dome climbing high formwork support system and installation method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105046001A (en) * 2015-07-21 2015-11-11 上海海勃膜结构有限公司 Whole construction process simulation analysis method for prestressed suspended cable membrane dome structure
CN105046001B (en) * 2015-07-21 2018-02-27 上海海勃膜结构股份有限公司 The construction overall process analogue simulation analysis method of prestressing force string guy film dome structure

Also Published As

Publication number Publication date
JP2000297476A (en) 2000-10-24

Similar Documents

Publication Publication Date Title
EP3752691B1 (en) Apparatus and method for slipforming a shaft
US3239990A (en) Multi-storey buildings
US20040134152A1 (en) Method and apparatus for precast and framed block element construction
US10829927B2 (en) Vertical slip form construction system with multi-function platform, and method of constructing a building therewith
JP3399873B2 (en) How to build a dome structure
JP2639361B2 (en) Construction method of steel pipe / concrete composite structure pier
JP2897663B2 (en) How to build underground structures
JP4027170B2 (en) External scaffold device and construction method of external scaffold device
JPS61109827A (en) Construction of basement
JP3445419B2 (en) Double slab construction method
JPH03125755A (en) Constructing method for cylindrical multistoried structure
JPH0470424A (en) Lift-down underground building body construction
JPH10237886A (en) Method for constructing underground tank
JPS63312437A (en) Construction of underground structure
JP2000160686A (en) Composite structure of reinforced concrete column and steel frame beam, and its execution
JP2696486B2 (en) Building construction method
JPH0230854A (en) Method for reconstructing multistoried building
JP2761528B2 (en) How to build structures
JPH0849301A (en) Building with basement
JP3499019B2 (en) Basement building unit and method for forming basement retaining wall
Nagy The lift‐form method
JPH0673793A (en) Multistoried building and constructing method thereof
JPH03107038A (en) Constructing method for structure
JPH0571226A (en) Temporarily set structure of complete weather type
JPH03107036A (en) Constructing method for structure

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees