JPH0849301A - Building with basement - Google Patents

Building with basement

Info

Publication number
JPH0849301A
JPH0849301A JP6187056A JP18705694A JPH0849301A JP H0849301 A JPH0849301 A JP H0849301A JP 6187056 A JP6187056 A JP 6187056A JP 18705694 A JP18705694 A JP 18705694A JP H0849301 A JPH0849301 A JP H0849301A
Authority
JP
Japan
Prior art keywords
building
basement
building unit
floor
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6187056A
Other languages
Japanese (ja)
Inventor
Katsuyuki Chihara
勝幸 千原
Masahiro Inayama
正弘 稲山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Misawa Homes Co Ltd
Original Assignee
Misawa Homes Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Misawa Homes Co Ltd filed Critical Misawa Homes Co Ltd
Priority to JP6187056A priority Critical patent/JPH0849301A/en
Publication of JPH0849301A publication Critical patent/JPH0849301A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To facilitate the erection works at the construction site, by forming a basemant with a building unit placed on a mat foundation and mounting the first and the second floor building units on the building unit for the basement and joining them. CONSTITUTION:Sheath pipes are buried in a mat foundation and a connection plate 4 is placed on the upper face of the mat foundation 2. Respective building units 6 in a basement are lifted on the mat foundation and installed thereon by a crane and the soil generated on excavating the vertical hole is filled back and the ground is retained by an earth-retaining external wall 11 fitted to the building units 6 for basement. Then the first and second floor building units 15, 16 are installed on the building unit 6 for basement by a crane to form a building 17 on the ground consisted of the first and second building units 15, 16. In this way, the construction period and cost can be reduced.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、地下室を備えた建物に
関し、例えば戸建て住宅、集合住宅等に利用できるもの
である。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a building having a basement, and can be used, for example, in a detached house, an apartment house or the like.

【0002】[0002]

【背景技術】建物の地下室は、従来、一般的に現場打ち
コンクリートや、特開昭57−235号等に示されてい
るようにプレキャストコンクリートによるパネルの組合
せによって作られていた。
2. Description of the Related Art Conventionally, a basement of a building is generally made of cast-in-place concrete or a combination of panels made of precast concrete as disclosed in JP-A-57-235.

【0003】[0003]

【発明が解決しようとする課題】地上建物には、軸組み
工法によるもの、パネル工法によるもの、ユニット工法
によるもの等があり、それぞれの工法に基づいて建てら
れている。ここで、地下室付き建物を建てる場合、地下
室を作るための工法と、地上建物を作る工法とが異なる
と、建設現場において、地下室と地上建物とで異なる工
法の作業を行わなければならなくなり、作業が複雑化
し、また、困難化する。
The above-ground buildings include those by the frame construction method, those by the panel construction method, those by the unit construction method, etc., and they are built based on each construction method. Here, when building a building with a basement, if the construction method for making the basement and the construction method for the above-ground building are different, it will be necessary to perform different work methods for the basement and above-ground building at the construction site. Becomes complicated and difficult.

【0004】本発明の目的は、地下室と地上建物とで工
法が同じになり、このため、建設現場作業の容易化を達
成できるようになる地下室付き建物を提供するところに
ある。
An object of the present invention is to provide a building with a basement in which the construction method is the same for the basement and the above-ground building, so that the construction site work can be facilitated.

【0005】[0005]

【課題を解決するための手段】本発明に係る地下室付き
建物は、地下室と、この地下室の上部の地上建物とが建
物ユニットによって構成されていることを特徴とするも
のである。
The building with a basement according to the present invention is characterized in that the basement and the aboveground building above the basement are constructed by building units.

【0006】地下室は、1個の建物ユニットによるもの
でもよく、2個以上の建物ユニットによるものでもよ
い。また、地上建物は1階だけのものでもよく、2階建
て以上のものでもよい。
The basement may consist of one building unit or two or more building units. Further, the above-ground building may have only one floor or two or more floors.

【0007】地上建物が1階用建物ユニットと2階用建
物ユニットとを含んで構成されている場合には、地下室
用建物ユニットと1階用建物ユニット、および1階用建
物ユニットと2階用建物ユニットは同じ接合構造で接合
される。
When the above-ground building is configured to include the first floor building unit and the second floor building unit, the basement building unit and the first floor building unit, and the first floor building unit and the second floor building unit. Building units are joined with the same joining structure.

【0008】この接合構造は、ボルトで上下の建物ユニ
ットを接合するものでもよく、或いは、接合金物等で接
合するものでもよい。
This joining structure may be one in which the upper and lower building units are joined by bolts, or one that is joined by a joining metal or the like.

【0009】地下室用建物ユニットと地上建物用建物ユ
ニットが共に水平方向に隣接配置された複数個ある場合
には、複数個の地下室用建物ユニット同士、および複数
個の地上建物用建物ユニット同士の接合構造は同じとさ
れる。
When there are a plurality of basement building units and a plurality of aboveground building units horizontally adjacent to each other, a plurality of basement building units are joined together and a plurality of aboveground building units are joined together. The structures are the same.

【0010】この接合構造は、水平方向に隣接する建物
ユニット間に架け渡された接合部材と、この接合部材で
間隔が規定され、水平方向に隣接する建物ユニットに挿
入されたピンとを含んで構成されたものでもよく、或い
は、接合金物等でこれらの建物ユニット同士を接合する
ものでもよい。前記ピンは1個の建物ユニットについて
1本でもよく、複数本でもよい。
This joining structure includes a joining member bridged between horizontally adjacent building units, and a pin whose spacing is defined by the joining member and which is inserted into a horizontally adjacent building unit. The building units may be joined together, or these building units may be joined together with a joining metal or the like. The number of the pins may be one or plural for one building unit.

【0011】地下室用建物ユニットには、土留め外壁材
が取り付けられ、この外壁材で地下室周囲が土留めされ
てもよい。また、地下室用建物ユニットを擁壁で囲まれ
た空間内に配置し、この擁壁で土留めするようにしても
よい。擁壁は、例えば、現場打ちコンクリートによるも
のやプレキャストコンクリートによるものでよく、ま
た、これらを組み合わせたものでもよい。
An earth retaining outer wall material may be attached to the building unit for the basement, and the periphery of the basement may be retained by this outer wall material. Further, the basement building unit may be arranged in a space surrounded by a retaining wall and earth retaining may be performed by the retaining wall. The retaining wall may be made of cast-in-place concrete, precast concrete, or a combination thereof.

【0012】地下室用建物ユニットはプレキャストコン
クリートによる基礎上に載置してもよく、また、現場打
ちコンクリートによるべた基礎上に載置してもよい。
The basement building unit may be mounted on a foundation made of precast concrete or on a solid foundation made of cast-in-place concrete.

【0013】[0013]

【作用】本発明では、地下室と地上建物は建物ユニット
によるユニット工法で作られ、その工法は同じであるた
め、工場で予め製造された建物ユニットを建設現場にお
いてクレーンで順次吊り込む作業を行うことにより、地
下室およびその上の地上建物を作ることができ、建設現
場で異種の工法作業を行わなくてよいため、作業の容易
化を図ることができ、工期の短縮、コストダウン等を達
成できる。
In the present invention, the basement and the above-ground building are made by the unit construction method using the building units, and the construction method is the same, so that the building units pre-manufactured in the factory are sequentially suspended by the crane at the construction site. As a result, the basement and the above-ground building can be formed, and since it is not necessary to perform work of different construction methods at the construction site, the work can be facilitated, the construction period can be shortened, and the cost can be reduced.

【0014】また、地下室用建物ユニットと1階用建物
ユニット、および1階用建物ユニットと2階用建物ユニ
ットが同じ接合構造で接合され、複数個の地下室用建物
ユニット同士、複数個の地上建物用建物ユニット同士が
同じ接合構造で接合されていると、これらの接合作業は
同じになるため、同じ作業を繰り返すことによって地下
室付き建物を建てることができ、作業の単純化による容
易化を達成できる。
Further, the basement building unit and the first-floor building unit, and the first-floor building unit and the second-floor building unit are joined by the same joining structure, and a plurality of basement building units are connected to each other and a plurality of above-ground buildings. If the building units are joined with the same joining structure, the joining work will be the same, so you can build a building with a basement by repeating the same work, and you can achieve the simplification of the work .

【0015】[0015]

【実施例】以下に本発明の実施例を図面に基づいて説明
する。
Embodiments of the present invention will be described below with reference to the drawings.

【0016】図1のAにおいて、建設現場の敷地内に縦
穴1を掘削し、縦穴1の底部に栗石の敷設、捨てコンク
リートの打設を行った後、図1のBに示す通り、コンク
リートの打設でべた基礎2を形成する。このべた基礎2
には、地下室用建物ユニットの設置位置にシース管3を
埋設する。また、図3に示す通り、べた基礎2の上面に
は、地下室用建物ユニット同士の接合部と対応する位置
にプレート状の接合部材4を載置する。この接合部材4
には上方へ突出したピン5が固定されており、このピン
は本実施例では1個の地下室用建物ユニットについて大
小2本ある。図3で示された接合部材4は、2個の地下
室用建物ユニットを接合するためのものであるため、こ
の接合部材4には大小2本のピン5は2組設けられてい
る。
In FIG. 1A, a vertical hole 1 is excavated in the site of the construction site, and after laying rubble stones and pouring waste concrete at the bottom of the vertical hole 1, as shown in FIG. Form solid foundation 2 by casting. This solid foundation 2
At this position, the sheath tube 3 is buried at the installation position of the basement building unit. Further, as shown in FIG. 3, a plate-shaped joining member 4 is placed on the upper surface of the solid foundation 2 at a position corresponding to the joining portion between the basement building units. This joining member 4
A pin 5 protruding upward is fixed to each of the two, and in this embodiment, there are two pins, one large and two small, for each basement building unit. Since the joining member 4 shown in FIG. 3 is for joining two basement building units, the joining member 4 is provided with two sets of two large and small pins 5.

【0017】この後、図1のCに示す通り、予め工場で
生産された地下室用建物ユニット6をクレーン7でべた
基礎2上に吊り込む作業を行う。地下室用建物ユニット
6は、四隅の4本の柱8と、これらの柱8の上端間、下
端間に架設された各4本の上梁9、下梁10とを有する
骨組みを備えている(この骨組みの構造は後述する1階
用,2階用建物ユニットについても同様である)。地下
室用建物ユニット6の外面には工場で予め土留め外壁材
11が取り付けられており、この外壁材11は例えば軽
量気泡コンクリート(ALC)からなる。
Thereafter, as shown in FIG. 1C, a work for suspending the basement building unit 6 produced in the factory in advance on the solid foundation 2 by the crane 7 is performed. The basement building unit 6 includes a framework having four pillars 8 at four corners, and four upper beams 9 and lower beams 10 provided between upper ends and lower ends of the columns 8 ( The structure of this frame is the same for the building units for the first and second floors described below). The earth retaining outer wall material 11 is attached to the outer surface of the basement building unit 6 in advance at the factory, and the outer wall material 11 is made of lightweight cellular concrete (ALC), for example.

【0018】各地下室用建物ユニット6がクレーン7で
吊り上げられたとき、図3の通り、柱8と下梁10とを
結合する仕口金物12にはアンカー部材13が下向きに
ねじ込み固定され、このアンカー部材13をグラウト材
が充填されたシース管3内に挿入しながら各地下室用建
物ユニット6はべた基礎2上に降ろされる。この降ろし
作業時に、仕口金物12の底面に形成された孔14に接
合部材4のピン5が挿入される。
When each basement building unit 6 is hoisted by the crane 7, as shown in FIG. 3, an anchor member 13 is screwed downwardly and fixed to a fitting 12 that joins the pillar 8 and the lower beam 10. Each basement building unit 6 is lowered onto the solid foundation 2 while inserting the anchor member 13 into the sheath tube 3 filled with grout material. During this unloading operation, the pin 5 of the joining member 4 is inserted into the hole 14 formed in the bottom surface of the joint fitting 12.

【0019】以上の作業により、シース管3内のグラウ
ト材が硬化すると、各地下室用建物ユニット6はべた基
礎2に固定されることになり、また、各地下室用建物ユ
ニット6毎に接合部材4に設けられたピン5は、その間
の間隔が接合部材4で規定されていて移動不能になって
いるため、これらのピン5が挿入された孔14を有して
いて水平方向に隣接している地下室用建物ユニット6同
士は、これらの接合部材4とピン5とで水平方向に接合
されることになる。
When the grout material in the sheath pipe 3 is hardened by the above-mentioned work, each basement building unit 6 is fixed to the solid foundation 2, and the joining member 4 is attached to each basement building unit 6. Since the pins 5 provided in the above are immovable because the distance between them is defined by the joining member 4, they have holes 14 into which these pins 5 are inserted and are adjacent in the horizontal direction. The basement building units 6 are horizontally joined by the joining members 4 and the pins 5.

【0020】この後、図2にAで示す通り、前記縦穴1
の掘削時に生じた土を埋め戻し、地下室用建物ユニット
6に取り付けた土留め外壁材11で土留めする。即ち、
建物ユニット6で形成される地下室の周囲の土はこの外
壁材11で土留めされることになり、このため、この実
施例では縦穴1の内側面に現場打ちコンクリート等によ
る擁壁を形成する必要はない。
Thereafter, as shown by A in FIG. 2, the vertical hole 1
The soil generated at the time of excavation is backfilled, and the soil is retained by the earth retaining wall material 11 attached to the basement building unit 6. That is,
The soil around the basement formed by the building unit 6 will be retained by this outer wall material 11. Therefore, in this embodiment, it is necessary to form a retaining wall made of cast-in-place concrete or the like on the inner surface of the vertical hole 1. There is no.

【0021】なお、この実施例の地下室用建物ユニット
6は上部が地上に突出しており、このため、地下室は半
地下室となっているが、建物ユニット6の全体を地中に
入れてもよい。
The basement building unit 6 of this embodiment has an upper part projecting above the ground. Therefore, the basement is a semi-basement, but the entire building unit 6 may be placed in the ground.

【0022】この後、図2のBで示す通り、地下室用建
物ユニット6の上に1階用建物ユニット15、さらにそ
の上に2階用建物ユニット16をそれぞれクレーンで吊
り込み、これらの建物ユニット15,16で地上建物1
7を形成する。1階用建物ユニット15の吊り込み作業
を行う前には、水平方向に隣接する地下室用建物ユニッ
ト6の上部に図4で示したプレート状の接合部材18
を、また、2階用建物ユニット16の吊り込み作業を行
う前には、水平方向に隣接した1階建物ユニット15の
上部に同様の接合部材18をそれぞれ架け渡して配置す
る(図4は、前後、左右に各4個隣接配置された地下室
用と1階用の建物ユニットの部分を示している)。接合
部材18には孔19が形成され、この孔19には、地下
室用建物ユニット6(或いは1階用建物ユニット15)
の柱8と上梁9とを結合する仕口金物20の上面に立設
されたピン21が挿入され、ピン21の先端は1階用建
物ユニット15(或いは2階用建物ユニット16)の柱
8と下梁10とを接合する仕口金物12の底面に形成さ
れている図示しない孔に挿入される。
After that, as shown in FIG. 2B, the building unit 15 for the first floor is hung on the building unit 6 for the basement, and the building unit 16 for the second floor is further hung on the building unit 15 for the first floor. 15 and 16 above ground building 1
Form 7. Before suspending the first-floor building unit 15, the plate-shaped joining member 18 shown in FIG. 4 is provided on the upper part of the horizontally adjacent basement building unit 6.
In addition, before carrying out the work of suspending the second-floor building unit 16, similar joint members 18 are arranged so as to bridge the upper part of the horizontally adjacent first-floor building unit 15 (FIG. 4, Shown are the building units for the basement and the first floor, each of which has four adjacent units on the front, back, left, and right). A hole 19 is formed in the joining member 18, and the basement building unit 6 (or the first floor building unit 15) is formed in the hole 19.
The pin 21 standing on the upper surface of the fitting 20 for connecting the pillar 8 and the upper beam 9 is inserted, and the tip of the pin 21 is the pillar of the building unit 15 for the first floor (or the building unit 16 for the second floor). 8 and the lower beam 10 are inserted into a hole (not shown) formed in the bottom surface of the joint fitting 12.

【0023】孔19は、接合部材18が架け渡される水
平方向に隣接した建物ユニットと対応した個数分あり、
本実施例では、1個の建物ユニットについてピン21は
大小2本あるため、1個の建物ユニットに対する孔19
の個数は2個となっている。
There are as many holes 19 as there are horizontally adjacent building units on which the joining members 18 are bridged,
In this embodiment, since there are two large and small pins 21 for one building unit, a hole 19 for one building unit is provided.
Is two.

【0024】各建物ユニット6(或いは15)のピン2
1が接合部材18の各孔19に挿入され、かつ、その先
端が各建物ユニット15(或いは16)の仕口金物12
に形成された孔に挿入されると、ピン19同士の間隔は
接合部材18で規定されるため、その上で水平方向に隣
接している建物ユニット15(或いは16)は、接合部
材18とピン19とで水平方向に接合されたことにな
り、これらの建物ユニットは水平方向に位置決め連結さ
れる。
Pin 2 of each building unit 6 (or 15)
1 is inserted into each hole 19 of the joining member 18, and the tip thereof is the fitting 12 of each building unit 15 (or 16).
When it is inserted into the hole formed in, the space between the pins 19 is defined by the joining member 18, so that the building units 15 (or 16) that are horizontally adjacent to each other on the joining member 18 and the pin 19 are horizontal. This means that the building units are horizontally joined at 19, and these building units are horizontally positioned and connected.

【0025】図4に示されている通り、地下室用建物ユ
ニット6の上に接合部材18を介して1階用建物ユニッ
ト15を載置した後、1階用建物ユニット15の仕口金
物12の孔22、接合部材18の孔23、地下室用建物
ユニット6の仕口金物20の孔24にボルト25を貫通
挿入し、ボルト25の先端にナット26を螺合して締め
付ける。この作業は、上下に並んでいる建物ユニット
6,15毎に行い、これにより上下の建物ユニット同士
はボルト25、ナット26で接合される。
As shown in FIG. 4, after the first-floor building unit 15 is placed on the basement building unit 6 via the joining member 18, the fitting 12 of the first-floor building unit 15 is placed. A bolt 25 is inserted through the hole 22, the hole 23 of the joining member 18, and the hole 24 of the fitting 20 of the basement building unit 6, and a nut 26 is screwed into the tip of the bolt 25 and tightened. This work is performed for each of the building units 6 and 15 which are arranged vertically, so that the upper and lower building units are joined by the bolts 25 and the nuts 26.

【0026】このボルト25、ナット26による接合作
業は、1階用建物ユニット15と2階用建物ユニット1
6についても行う。即ち、地下室用建物ユニット6と1
階用建物ユニット15、および1階用建物ユニット15
と2階用建物ユニット16は同じ接合構造で接合され
る。
The joining work using the bolts 25 and the nuts 26 is performed by the building unit 15 for the first floor and the building unit 1 for the second floor.
Repeat for 6. That is, basement building units 6 and 1
Building unit 15 for the first floor and building unit 15 for the first floor
And the second floor building unit 16 are joined by the same joining structure.

【0027】以上の作業後、2階用建物ユニット6の上
部には例えば屋根パネルを組み合わせて屋根が形成され
る。建物ユニット6,15,16には、工場で予め壁材
や床材、天井材等が取り付けられているため、建設現場
でこれらの建物ユニットの水平方向および上下方向の接
続部分についての仕上げ作業等を行うことにより、建物
ユニット6で地下室、建物ユニット15,16で地上建
物がそれぞれ構成された地下室付き建物が完成する。
After the above work, a roof is formed on the upper part of the second-floor building unit 6 by combining roof panels, for example. Since wall materials, floor materials, ceiling materials, etc. are pre-installed in the building units 6, 15 and 16 at the factory, finishing work etc. on the horizontal and vertical connection parts of these building units at the construction site. As a result, the building unit 6 completes a basement building, and the building units 15 and 16 form a building with a basement, which is a ground building.

【0028】以上の実施例によれば、地下室は建物ユニ
ット6によるユニット工法で、また、地上建物は建物ユ
ニット15,16によるユニット工法でそれぞれ構成さ
れ、これらの工法は同じであるため、地下室から地上の
最上階までの建築作業を工場で予め生産された建物ユニ
ットのクレーンによる吊り込み作業で行えるようにな
り、地下室と地上建物を異種の工法で建てる場合と異な
り、地下室と地上建物とで異なる建築作業を行う必要が
ないため、建設現場作業を容易化でき、工期の短縮化と
コストダウンを図ることができる。
According to the above embodiments, the basement is constructed by the unit construction method using the building unit 6, and the aboveground building is constructed by the unit construction method using the building units 15 and 16, respectively. Since these construction methods are the same, It is now possible to perform construction work up to the top floor above the ground by suspending a building unit pre-produced at the factory using a crane, and unlike the case where the basement and the ground building are constructed by different construction methods, the basement and the ground building are different Since it is not necessary to perform construction work, construction site work can be facilitated, and the construction period and cost can be reduced.

【0029】また、水平方向に隣接する地下室用建物ユ
ニット6同士、1階用建物ユニット15同士、2階用建
物ユニット16同士は、接合部材4,18、ピン5,2
1による同じ接合構造で水平方向に接合されているた
め、これらを接合する作業は地下室から地上の最上階ま
で同じ作業となり、クレーン等による同一作業を繰り返
せばよいため、作業の単純化を実現できて建築現場作業
を容易化できる。
The basement building units 6 adjacent to each other in the horizontal direction, the first-floor building units 15 and the second-floor building units 16 are joined to each other by the joining members 4, 18 and the pins 5, 2.
Since they are horizontally joined with the same joining structure according to 1, the work of joining these is the same work from the basement to the top floor on the ground, and the same work can be repeated with a crane, etc., so the work can be simplified. Construction site work can be facilitated.

【0030】また、上下に並んだ地下室用建物ユニット
6と1階用建物ユニット15、および1階用建物ユニッ
ト15と2階用建物ユニット16はボルト25、ナット
26による同じ構造で上下に接合されているため、これ
らの建物ユニット同士を同じ作業の繰り返しによって接
合でき、この作業の容易化も達成できる。
The basement building unit 6 and the first-floor building unit 15 and the first-floor building unit 15 and the second-floor building unit 16 which are vertically arranged are joined together by bolts 25 and nuts 26 in the same structure. Therefore, these building units can be joined by repeating the same work, and the work can be facilitated.

【0031】図5は、地下室用建物ユニット6の基礎の
別実施例を示す。この基礎27の立上部28はプレキャ
ストコンクリートで形成されており、工場で生産された
複数の立上部28を所定位置に配置した後、現場打ちコ
ンクリートで基礎底盤29を形成する。立上部28には
グラウト材30を充填したシース管3が埋設されてお
り、基礎27の完成後、地下室用建物ユニット6のアン
カー部材13がシース管3内に挿入される。
FIG. 5 shows another embodiment of the foundation of the basement building unit 6. The rising portion 28 of the foundation 27 is formed of precast concrete, and after arranging a plurality of rising portions 28 produced in the factory at predetermined positions, the foundation bottom plate 29 is formed of cast-in-place concrete. The sheath pipe 3 filled with the grout material 30 is embedded in the rising portion 28, and after the foundation 27 is completed, the anchor member 13 of the basement building unit 6 is inserted into the sheath pipe 3.

【0032】図6、図7の基礎31は図5の実施例と同
様に、プレキャストコンクリート製の立上部32と、現
場打ちコンクリートによる基礎底盤33とから形成され
ているが、立上部32の下部には立上部32内に埋設さ
れた配筋材34が突出している。図6の通り、この配筋
材34を縦穴1に打設した捨てコンクート上に載せて各
立上部32を所定位置に配置した後、図7で示した基礎
底盤33のコンクリートを打つ。これによると、配筋材
34によって立上部32と基礎底盤33が強固、確実に
一体化されることになる。
The foundation 31 shown in FIGS. 6 and 7 is formed of a precast concrete rising portion 32 and a foundation bottom plate 33 made of cast-in-place concrete as in the embodiment shown in FIG. A bar arrangement material 34 embedded in the upright portion 32 projects from the. As shown in FIG. 6, the reinforcing bar 34 is placed on the discarded concrete placed in the vertical hole 1 to place the respective rising parts 32 at predetermined positions, and then the concrete of the foundation bottom plate 33 shown in FIG. 7 is poured. According to this, the standing member 32 and the foundation bottom plate 33 are firmly and surely integrated by the reinforcing bar 34.

【0033】地下室用建物ユニット6の基礎は、以上の
実施例のように、一部をプレキャストコンクリート製と
してもよく、また、基礎全体をプレキャストコンクリー
ト製としてもよい。このように、基礎の少なくとも一部
をプレキャストコンクリートで形成することにより、建
設現場での基礎施工作業を短時間で行え、作業を簡単化
できる。
A part of the foundation of the basement building unit 6 may be made of precast concrete as in the above embodiments, or the entire foundation may be made of precast concrete. Thus, by forming at least a part of the foundation with precast concrete, the foundation construction work at the construction site can be performed in a short time, and the work can be simplified.

【0034】図8、図9の実施例では、べた基礎35の
終端部に土留めのための擁壁36を形成している。この
擁壁36は現場打ちコンクリートによるもの、或いはプ
レキャストコンクリートパネルによるものである。この
ような擁壁36で囲まれた空間内に地下室用建物ユニッ
ト6がクレーンで吊り込まれ、更に、その上に図9の通
り1階用建物ユニット15が吊り込まれる。
In the embodiment shown in FIGS. 8 and 9, a retaining wall 36 for retaining soil is formed at the end of the solid foundation 35. The retaining wall 36 is made of cast-in-place concrete or precast concrete panels. The basement building unit 6 is suspended by a crane in the space surrounded by the retaining wall 36, and the first-floor building unit 15 is suspended thereon as shown in FIG.

【0035】この実施例によれば、地下室用建物ユニッ
ト6を工場から建設現場にトラックで運ぶとき、建物ユ
ニット6に大重量の土留め外壁材を取り付けておかなく
てよいため、トラック運搬作業および建設現場でのクレ
ーン吊り込み作業を容易に行え、また、土留め外壁材に
よって建物ユニット6の重心が建物ユニット6の中央か
ら大きく偏る事態が生ずるのを無くすことができるた
め、クレーン吊り込み作業時等において建物ユニット6
を容易に取り扱えるようになる。
According to this embodiment, when the basement building unit 6 is transported from the factory to the construction site by truck, it is not necessary to attach a heavy earth retaining wall material to the building unit 6, so that the truck transport work and During the crane hoisting work, the crane hoisting work at the construction site can be performed easily, and the situation that the center of gravity of the building unit 6 is largely deviated from the center of the building unit 6 due to the earth retaining outer wall material can be prevented. Building unit 6 in etc.
Can be easily handled.

【0036】以上説明した各実施例は地下1階、地上2
階の建物の場合であったが、本発明は地下2階以上や、
地上3階以上の建物にも利用できる。
Each of the embodiments described above has a basement floor and two above ground.
Although it was the case of the building on the first floor, the present invention is the second floor and above,
It can also be used for buildings over 3 floors above ground.

【0037】また、前記各実施例では、地下室用建物ユ
ニットと基礎との結合は、基礎に設けたシース管にグラ
ウト材を充填し、この中に地下室用建物ユニットのアン
カー部材を挿入することにより行われていたが、この結
合構造はこれに限定されず、例えば、基礎にアンカーボ
ルトを立設し、このアンカーボルトで地下室用建物ユニ
ットを基礎に結合するようにしてもよい。
Further, in each of the above-mentioned embodiments, the basement building unit and the foundation are connected by filling a sheath tube provided in the base with grout material and inserting an anchor member of the basement building unit into the sheath tube. Although this has been done, this connecting structure is not limited to this. For example, an anchor bolt may be erected on the foundation and the building unit for basement may be connected to the foundation by this anchor bolt.

【0038】また、前記各実施例では全部の1階用建物
ユニットの下部に地下室用建物ユニットが配置されてい
たが、一部の1階用建物ユニットの下部だけに地下室用
建物ユニットが配置されていてもよく、地下室用建物ユ
ニットの個数は1個でもよい。
Further, in each of the above-mentioned embodiments, the basement building units are arranged at the bottom of all the first-floor building units, but the basement building units are arranged only at the bottom of some of the first-floor building units. The number of basement building units may be one.

【0039】[0039]

【発明の効果】本発明によれば、地下室と、この地下室
の上部の地上建物は共に建物ユニットで構成され、地下
室および地上建物はユニット工法で作られるため、これ
らを異種の工法で作る場合と比べ、建設現場作業を容易
化でき、工期の短縮やコストダウンを達成できる。
According to the present invention, the basement and the ground building above the basement are both constructed by building units, and the basement and the ground building are made by a unit construction method. In comparison, the construction site work can be facilitated, and the construction period and cost can be reduced.

【図面の簡単な説明】[Brief description of drawings]

【図1】第一実施例に係る地下室付き建物の建設現場作
業を示した工程図である。
FIG. 1 is a process diagram showing construction site work of a building with a basement according to the first embodiment.

【図2】図1の続きの工程を示した図である。FIG. 2 is a diagram showing a step following that of FIG.

【図3】地下室用建物ユニットと基礎との結合、および
地下室用建物ユニット同士の接合の構造を示した分解斜
視図である。
FIG. 3 is an exploded perspective view showing a structure in which a building unit for a basement and a foundation are coupled and a structure for building units for a basement is joined.

【図4】水平方向および上下方向に並んだ建物ユニット
同士の接合構造を示した分解斜視図である。
FIG. 4 is an exploded perspective view showing a joint structure of building units arranged in a horizontal direction and a vertical direction.

【図5】第二実施例に係る地下室付き建物の基礎部分を
示す縦断面図である。
FIG. 5 is a vertical cross-sectional view showing a foundation portion of a building with a basement according to a second embodiment.

【図6】第三実施例に係る地下室付き建物の基礎施工作
業を示す図で、現場打ちコンクリートによる基礎底盤形
成前を示す斜視図である。
FIG. 6 is a diagram showing a foundation construction work of a building with a basement according to the third embodiment, and is a perspective view showing a foundation floor plate before being formed by cast-in-place concrete.

【図7】図6の基礎底盤形成後を示す縦断面図である。FIG. 7 is a vertical cross-sectional view showing the state after the foundation bottom plate of FIG. 6 is formed.

【図8】擁壁で土留めした第4実施例に係る地下室付き
建物の地下室用建物ユニット設置前を示す縦断面図であ
る。
FIG. 8 is a vertical cross-sectional view showing a building with a basement according to a fourth embodiment, which is earth-retained with a retaining wall, before installation of a building unit for basement.

【図9】図8の地下室用建物ユニットおよび1階用建物
ユニットの設置後を示す縦断面図である。
9 is a vertical cross-sectional view showing the basement building unit and the first-floor building unit of FIG. 8 after installation.

【符号の説明】[Explanation of symbols]

1 地下室用縦穴 2,35 べた基礎 3 シース管 4,18 接合部材 5,21 ピン 6 地下室用建物ユニット 7 クレーン 11 土留め外壁材 13 アンカー部材 15 1階用建物ユニット 16 2階用建物ユニット 17 地上建物 27,31 基礎 28,32 立上部 29,33 基礎底盤 36 擁壁 1 Vertical hole for basement 2,35 Solid foundation 3 Sheath pipe 4,18 Joining member 5,21 Pin 6 Building unit for basement 7 Crane 11 Outer wall material for earth retaining 13 Anchor member 15 Building unit for 1st floor 16 Building unit for 2nd floor 17 Ground Building 27,31 Foundation 28,32 Upright 29,33 Foundation bottom 36 Retaining wall

Claims (8)

【特許請求の範囲】[Claims] 【請求項1】 地下室と、この地下室の上部の地上建物
とを備え、これらの地下室と地上建物とが建物ユニット
によって構成されていることを特徴とする地下室付き建
物。
1. A building with a basement, comprising a basement and an above-ground building above the basement, the basement and the above-ground building being constituted by a building unit.
【請求項2】 請求項1に記載の地下室付き建物におい
て、前記地上建物は1階用建物ユニットと2階用建物ユ
ニットを含んで構成され、前記地下室用建物ユニットと
前記1階用建物ユニット、およびこの1階用建物ユニッ
トと前記2階用建物ユニットは同じ接合構造で接合され
ていることを特徴とする地下室付き建物。
2. The building with a basement according to claim 1, wherein the above-ground building includes a first floor building unit and a second floor building unit, and the basement building unit and the first floor building unit, A building with a basement, wherein the building unit for the first floor and the building unit for the second floor are joined by the same joining structure.
【請求項3】 請求項2に記載の地下室付き建物におい
て、前記接合構造は、ボルトで上下の建物ユニットを接
合するものであることを特徴とする地下室付き建物。
3. The building with a basement according to claim 2, wherein the joint structure joins the upper and lower building units with bolts.
【請求項4】 請求項1〜3のいずれかに記載の地下室
付き建物において、前記地下室用建物ユニットと前記地
上建物用建物ユニットは共に水平方向に隣接配置された
複数個あり、複数個の前記地下室用建物ユニット同士、
および複数個の前記地上建物用建物ユニット同士の接合
構造は同じであることを特徴とする地下室付き建物。
4. The building with a basement according to any one of claims 1 to 3, wherein the basement building unit and the above-ground building unit are both horizontally adjacent to each other. Building units for basements,
And a building with a basement, wherein a plurality of the above-mentioned building units for ground building have the same joint structure.
【請求項5】 請求項4に記載の地下室付き建物におい
て、前記接合構造は、水平方向に隣接する建物ユニット
間に架け渡された接合部材と、この接合部材で間隔が規
定され、前記水平方向に隣接する建物ユニットに挿入さ
れたピンとを含んで構成されていることを特徴とする地
下室付き建物。
5. The building with a basement according to claim 4, wherein the joint structure has a joint member bridged between horizontally adjacent building units, and a gap is defined by the joint member. A building with a basement, which is configured to include a pin inserted in a building unit adjacent to.
【請求項6】 請求項1〜5のいずれかに記載の地下室
付き建物において、前記地下室用建物ユニットには土留
め外壁材が取り付けられ、この外壁材により地下室周囲
が土留めされていることを特徴とする地下室付き建物。
6. The building with a basement according to any one of claims 1 to 5, wherein a soil retaining outer wall material is attached to the basement building unit, and the periphery of the basement is retained by the outer wall material. Characteristic building with basement.
【請求項7】 請求項1〜5のいずれかに記載の地下室
付き建物において、前記地下室用建物ユニットは擁壁で
囲まれた空間内に配置されていることを特徴とする地下
室付き建物。
7. The building with a basement according to any one of claims 1 to 5, wherein the basement building unit is arranged in a space surrounded by a retaining wall.
【請求項8】 請求項1〜7のいずれかに記載の地下室
付き建物において、前記地下室用建物ユニットは少なく
とも一部がプレキャストコンクリートで形成された基礎
上に載置されていることを特徴とする地下室付き建物。
8. The building with a basement according to any one of claims 1 to 7, wherein the basement building unit is placed on a foundation formed at least partially of precast concrete. Building with basement.
JP6187056A 1994-08-09 1994-08-09 Building with basement Pending JPH0849301A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6187056A JPH0849301A (en) 1994-08-09 1994-08-09 Building with basement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6187056A JPH0849301A (en) 1994-08-09 1994-08-09 Building with basement

Publications (1)

Publication Number Publication Date
JPH0849301A true JPH0849301A (en) 1996-02-20

Family

ID=16199404

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6187056A Pending JPH0849301A (en) 1994-08-09 1994-08-09 Building with basement

Country Status (1)

Country Link
JP (1) JPH0849301A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20210016169A (en) * 2019-08-01 2021-02-15 효성중공업 주식회사 Steel pit structure for elevator

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20210016169A (en) * 2019-08-01 2021-02-15 효성중공업 주식회사 Steel pit structure for elevator

Similar Documents

Publication Publication Date Title
JP3644605B2 (en) Reverse driving method of underground structure under road surface.
KR101107567B1 (en) For top down methode of rc structure, the connecting devices between beam structure and vertical steel material, the supporting structures of exclusive use, and the construction method using these devices
US7219474B2 (en) Load bearing building panel
KR102595835B1 (en) Seismic retrofit system using foundation integrated PC panel
KR100462236B1 (en) panel for external underground wall of building, structure and construction method using the same
JPH0684690B2 (en) Building basement extension method
JPS6137692Y2 (en)
JP2897663B2 (en) How to build underground structures
JPH0849301A (en) Building with basement
KR20210090100A (en) In a building where the underground structure is a wall structure, the shortened construction type top down construction method and structure that enables early ground frame start using temporary transfer structures
JP2876182B2 (en) Joint foundation for temporary shutter
JP2577973B2 (en) How to build a building with a basement
JPH08291529A (en) Underground floor construction method
JP2894217B2 (en) Building structural frame
JP3086384B2 (en) Foundation structure and foundation construction method
JP4589506B2 (en) Pre-installation method of large steel columns for constructing buildings with superstructure structure by the reverse driving method
JP3345395B2 (en) Elevator tower construction method
JP3176803B2 (en) Basement structure
JP2959436B2 (en) How to build underground structures
JP3499019B2 (en) Basement building unit and method for forming basement retaining wall
KR200266585Y1 (en) panel for external underground wall of building and external underground wall- structure using the same
JP2023038130A (en) Skeleton construction method
JP2839985B2 (en) Reverse construction method for structures
JPH08177068A (en) Construction of underground structure
KR20220094841A (en) Middle connecting structure of steel pilar and construction method thereof

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20020326