JP3345395B2 - Elevator tower construction method - Google Patents
Elevator tower construction methodInfo
- Publication number
- JP3345395B2 JP3345395B2 JP2000282431A JP2000282431A JP3345395B2 JP 3345395 B2 JP3345395 B2 JP 3345395B2 JP 2000282431 A JP2000282431 A JP 2000282431A JP 2000282431 A JP2000282431 A JP 2000282431A JP 3345395 B2 JP3345395 B2 JP 3345395B2
- Authority
- JP
- Japan
- Prior art keywords
- elevator shaft
- elevator
- shaft
- lifting
- tower
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0266—Enlarging
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
Description
【0001】[0001]
【発明の属する技術分野】本発明は、建造物の完成後又
は建造過程でエレベータ塔を施工する方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an elevator tower after completing a building or during the construction process.
【0002】[0002]
【従来の技術】従来、昇降設備の付加されていない鉄筋
の集合住宅にあっては、各階の住戸の玄関どうしを共用
フロアを介して向合せとし、上記共用フロアの上階と下
階の間を方向の異なる上,下の階段で結ぶとともに、こ
の階段の中間部位に踊場を設けて構成されるものが一般
的である。上記踊場には手摺を設け、この手摺を介して
外方を臨めるようにしている。従来では、このような集
合住宅に昇降設備を増設する場合には、階段部分を、は
つり作業により除去した上で、エレベータシャフトを下
層より上層に向かって徐々に建造し、その内部に昇降籠
等の昇降設備を収納し、エレベータシャフトの内,外装
を仕上げることによりエレベータ塔を増設するようにし
ている。2. Description of the Related Art Conventionally, in a reinforced apartment house to which no elevating equipment is added, entrances of dwelling units on each floor are faced to each other via a shared floor, and a space between the upper floor and the lower floor of the shared floor is used. Are connected by upper and lower stairs having different directions, and a landing is provided at an intermediate portion of the stairs. A handrail is provided at the landing, and the outside can be seen through the handrail. Conventionally, when increasing and lowering equipment is added to such an apartment house, after removing the stairs by hanging work, the elevator shaft is gradually built from the lower layer to the upper layer, and the elevator basket etc. The elevator tower is expanded by storing the elevator equipment and finishing the interior and exterior of the elevator shaft.
【0003】[0003]
【発明が解決しようとする課題】しかしながら、上記従
来のようなエレベータ塔の増設施工方法では、階段部分
を撤去しなければならないので、住戸を全く使用できな
いか、あるいは増設完了までに使用すべき仮設階段を取
付けなければならないので、住民に不便な生活を強いる
場合があったり、仮設階段の増設コストが高くなったり
していた。また、現場にて柱,梁等を組立てて、下層よ
り上層に向かって徐々にエレベータシャフトを構築した
後、このエレベータシャフトの内部に昇降籠等の昇降設
備を収容してエレベータシャフト内,外装工事を行うよ
うにしているので、エレベータ塔の建造のために長期間
を要するだけでなく、この長期間に渡って立入り禁止の
広い安全スペースを確保しなければならなかった。However, in the above-described conventional method of expanding an elevator tower, the stairs must be removed, so that no dwelling units can be used, or a temporary building to be used until the expansion is completed. Since the stairs must be installed, the residents may be inconvenienced in living, and the cost of adding temporary stairs is high. Also, after assembling columns, beams, etc. at the site, gradually constructing the elevator shaft from the lower layer to the upper layer, the elevator shaft is housed inside the elevator shaft, and elevator equipment such as elevator cages is housed. Therefore, the construction of the elevator tower not only takes a long time, but also has to secure a large safe space where no entry is allowed over this long time.
【0004】本発明はこのような問題を解決するために
なされたもので、階段部分を撤去する必要がなく、短期
間でエレベータ塔を施工でき、施工コストを抑えること
ができる方法を提供するものである。The present invention has been made to solve such a problem, and it is an object of the present invention to provide a method in which an elevator tower can be constructed in a short period of time without having to remove a stair portion, and the construction cost can be reduced. It is.
【0005】[0005]
【課題を解決するための手段】この発明に係るエレベー
タ塔の施工方法は、建造物の各階に対応する出入口を有
する筒状のエレベータシャフトをあらかじめ製作して、
建造物の完成後又は建造過程でこのエレベータシャフト
を垂直に建込んで固定し、上記エレベータシャフトの出
入口を上記各階に連通させたエレベータ塔の施工方法で
あって、エレベータシャフトの上端側の両側部と下部側
の両側部に、それぞれ横方向に突出する突出部を設け
て、この突出部にワイヤの下端を接続し、このワイヤが
エレベータシャフトの外側に接触しないようにワイヤの
上端を保持して上記エレベータシャフトを吊るようにし
た。また、上記エレベータシャフトの出入口を各階をつ
なぐ階段の踊場に連通させるようにした。また、上記エ
レベータシャフトを建込む前に、エレベータシャフトに
昇降籠のガイドレール,昇降籠,巻上機等の昇降設備を
あらかじめ組込んでおくようにした。 また、上記それぞ
れ横方向に突出する各突出部の先端間の長さと同程度の
吊りビームを用いてワイヤの上端を保持することでワイ
ヤがエレベータシャフトに接触しないようにエレベータ
シャフトを吊るようにした。 According to the method for constructing an elevator tower according to the present invention, a tubular elevator shaft having an entrance corresponding to each floor of a building is manufactured in advance.
After the completion of the building or during the construction process, this elevator shaft is vertically erected and fixed, and the elevator tower construction method in which the entrance and exit of the elevator shaft are connected to each floor above
There are both upper and lower sides of the elevator shaft
Protruding parts are provided on both sides of
And connect the lower end of the wire to this protrusion,
Be careful not to touch the outside of the elevator shaft.
Holding the upper end was so that hanging the elevator shaft. Further, the entrance of the elevator shaft is communicated with the landing of the stairs connecting each floor. Before the elevator shaft is built, elevator equipment such as a guide rail of a lifting cage, a lifting cage, and a hoist are previously incorporated into the elevator shaft . Also, each of the above
The same length as the distance between the tips of the protrusions
Use the hanging beam to hold the top of the wire
The elevator shaft so that it does not touch the elevator shaft.
The shaft was suspended.
【0006】[0006]
【発明の実施の形態】以下、この発明の実施の形態を図
に基づいて説明する。図1ないし図3は実施の形態によ
るエレベータ塔の施工方法を説明するための簡略構成図
であり、各図において、1は昇降設備の付加されていな
い鉄筋の集合住宅などの建造物であって、これは各階の
住戸1a,1bの玄関1m,1m同志を共用フロア1n
を介して向合せとし、上,下の共用フロア1n,1n間
を方向の異なる上,下の階段1c,1cで結ぶととも
に、この階段1c,1cの中間部位に踊場1dを設けて
構成される。上記踊場1dには手摺1eが設けられ、こ
の手摺1eを介して外方を臨めるようになっている。本
実施の形態では、上記手摺1eの前部外方の予定位置A
にエレベータシャフト2を建込むものである。このエレ
ベータシャフト2は、あらかじめ工場等で製作されるも
のである。Embodiments of the present invention will be described below with reference to the drawings. 1 to 3 are simplified structural diagrams for explaining a method of constructing an elevator tower according to an embodiment. In each of the drawings, reference numeral 1 denotes a building such as a reinforced apartment house to which no lifting equipment is added. , This is the entrance 1m of each dwelling unit 1a, 1b, 1m comrades are shared floor 1n
The upper and lower common floors 1n, 1n are connected by upper and lower stairs 1c, 1c having different directions, and a landing 1d is provided at an intermediate portion between the stairs 1c, 1c. . A handrail 1e is provided in the landing 1d, and the outside can be seen through the handrail 1e. In the present embodiment, a scheduled position A outside the front part of the handrail 1e.
The elevator shaft 2 is built in the vehicle. The elevator shaft 2 is manufactured in advance at a factory or the like.
【0007】本実施の形態で建込むエレベータシャフト
2の構成を図4に示す。図4において、70は昇降籠、
60は昇降籠70のガイドレール、61はガイドレール
60を取付けるためのボード、62はエレベータシャフ
ト2のシャフトフレーム620を構成するH形鋼などの
主柱、63は外装ボード、64は各階毎の出入口、2a
は通路作成用のキャンティ梁である。エレベータシャフ
ト2の製作は、図5(a)に示すように、まず、4本の
主柱62をH形鋼等の横柱62aで接続し、さらには、
側部を補強横梁やブレース等(図示せず)で補強して、
四角柱状のシャフトフレーム620を製作する。次に、
図5(b)に示すように、シャフトフレーム620の内
側に、出入口64側を除いてボード31を貼り、上記ガ
イドレール60、昇降籠70、巻上機80等の昇降設備
を組み付ける。その後、図5(c)に示すように、シャ
フトフレーム620の外側に、出入口64側を除いて、
外装ボード63を貼付けて外装仕上げを行ない、さら
に、キャンティ梁2aを取付ける。これにより、内部に
あらかじめ昇降設備が組み付けられ、建造物1の各階に
対応する出入口64を有し、かつ、キャンティ梁2aが
あらかじめ取付けられた四角筒状のエレベータシャフト
2,即ち、本実施の形態による方法で建込まれ、エレベ
ータ塔を構築するエレベータシャフト2が製作される。
尚、上記ガイドレール60は、ブラケット等を介して上
記横柱62aに取付けることもある。また、ガイドレー
ル60取付用の専用の横柱を別に設けるようにして当該
横柱にガイドレール60を取付けることもある。FIG. 4 shows the structure of the elevator shaft 2 built in the present embodiment. In FIG. 4, 70 is a lifting basket,
Reference numeral 60 denotes a guide rail of the elevator cage 70, 61 denotes a board for attaching the guide rail 60, 62 denotes a main pillar such as an H-shaped steel constituting a shaft frame 620 of the elevator shaft 2, 63 denotes an exterior board, and 64 denotes a board for each floor. Doorway, 2a
Is a Chianti beam for making a passage. As shown in FIG. 5A, the elevator shaft 2 is manufactured by first connecting four main columns 62 with horizontal columns 62a such as H-section steel.
Reinforce the sides with reinforcing beams, braces, etc. (not shown)
A square pillar-shaped shaft frame 620 is manufactured. next,
As shown in FIG. 5B, the board 31 is attached to the inside of the shaft frame 620 except for the entrance 64 side, and ascending and descending equipment such as the guide rail 60, the elevator cage 70, and the hoist 80 are assembled. After that, as shown in FIG. 5C, outside the shaft frame 620, except for the entrance 64 side,
The exterior board 63 is attached to finish the exterior, and further, the chianti beam 2a is attached. As a result, the elevator equipment is preliminarily installed inside the elevator shaft 2, and the elevator shaft 2, which has the entrance 64 corresponding to each floor of the building 1 and has the cantilever beam 2a attached thereto in advance, that is, the present embodiment. And an elevator shaft 2 for constructing an elevator tower is manufactured.
The guide rail 60 may be attached to the horizontal column 62a via a bracket or the like. Further, the guide rail 60 may be attached to the horizontal column by separately providing a dedicated horizontal column for mounting the guide rail 60.
【0008】上記エレベータシャフト2は図2に示すよ
うに現場にてエレベータシャフト2の建込み予定位置A
に建込まれる。この場合、エレベータシャフト2の建込
み予定位置Aの地面3は、図6に示すように掘削され
て、この掘削穴3sに基礎ユニット30Aが配置されて
エレベータ塔の基礎30が構築され、この基礎30に対
してエレベータシャフト2を建込むことにより、図3に
示すようにエレベータ塔を増設できる。上記基礎30の
構築手順を図6に基づいて詳説する。まず、図6のの
ようにエレベータシャフト2の建込み予定位置Aの地面
3を掘削して、この掘削穴3sの底に捨てコンクリート
30aを打設する。この捨てコンクリート30aの上
に、製作しておいた底盤鉄筋30bを搬入して据え付け
る。そして、製作しておいた基礎ユニット30Aを搬入
して、図6ののように、捨てコンクリート30a及び
底盤鉄筋30bに据え付けて、レベル調整を行なう。上
記基礎ユニット30Aは、4本の柱材30cをコンクリ
ート枠30dで囲って筒状に形成されたものであり、4
本の柱材30cの上部には、エレベータシャフト2の下
端側との接合部31が設けられている。そして、図6の
のように、底盤鉄筋30bの部分にコンクリートを打
設して底版コンクリート30eを形成することにより、
捨てコンクリート30a上に基礎ユニット30Aを一体
化させた後に、基礎ユニット30Aの上部側に設けられ
た接合部31が露出するよう上記掘削穴3s内に土30
f等を埋め戻すことにより、エレベータ塔の基礎30を
構築する。よって、後述のように、エレベータシャフト
2の下端側を基礎ユニット30Aに接合する場合におい
て、基礎ユニット30Aの接合部31が地上に露出して
いることから、基礎ユニット30Aに対するエレベータ
シャフト2の接合作業を簡単に行なうことができるよう
になる。尚、上記では、捨てコンクリート30aの上
に、基礎ユニット30A,底盤鉄筋30b,底版コンク
リート30eから成る基礎体を現場で構築するようにし
たが、基礎ユニット30A,底盤鉄筋30b,底版コン
クリート30eから成る基礎体をあらかじめ工場などで
製作しておいて、このプレキャストによる基礎体を現場
に搬入し、掘削穴3sの底に捨てコンクリート30aを
設けた後、搬入した上記基礎体を、この掘削穴3sに配
置して、上記のように埋め戻すことにより基礎30を構
築するようにしてもよい。この場合、基礎施工における
現場作業を少なくできる。[0008] As shown in FIG. 2, the elevator shaft 2 is to be erected at a site A where the elevator shaft 2 is to be erected.
It is built in In this case, the ground 3 at the planned installation position A of the elevator shaft 2 is excavated as shown in FIG. 6, the foundation unit 30A is arranged in the excavation hole 3s, and the elevator tower foundation 30 is constructed. By building the elevator shaft 2 with respect to 30, the number of elevator towers can be increased as shown in FIG. The procedure for constructing the foundation 30 will be described in detail with reference to FIG. First, as shown in FIG. 6, the ground 3 at the planned installation position A of the elevator shaft 2 is excavated, and discarded concrete 30a is poured into the bottom of the excavation hole 3s. The manufactured bottom reinforcement 30b is carried in and installed on the discarded concrete 30a. Then, the manufactured basic unit 30A is carried in, and as shown in FIG. 6, installed on the discarded concrete 30a and the bottom reinforcement 30b, and the level is adjusted. The base unit 30A is formed in a cylindrical shape by surrounding four pillars 30c with a concrete frame 30d.
A joint 31 with the lower end of the elevator shaft 2 is provided at the upper part of the pillar 30c. Then, as shown in FIG. 6, the concrete is poured into the portion of the bottom reinforcement 30 b to form the bottom slab concrete 30 e,
After integrating the foundation unit 30A on the discarded concrete 30a, the soil 30 is inserted into the excavation hole 3s so that the joint 31 provided on the upper side of the foundation unit 30A is exposed.
By backfilling f etc., the foundation 30 of the elevator tower is constructed. Therefore, as described later, when the lower end side of the elevator shaft 2 is joined to the base unit 30A, since the joining portion 31 of the base unit 30A is exposed to the ground, the work of joining the elevator shaft 2 to the base unit 30A is performed. Can be easily performed. In the above description, the foundation composed of the foundation unit 30A, the bottom reinforcement 30b and the bottom slab concrete 30e is constructed on site on the waste concrete 30a. However, the foundation unit 30A, the bottom reinforcement 30b and the bottom slab concrete 30e are constructed. The foundation is manufactured in advance in a factory or the like, and the precast foundation is carried into the site, a concrete 30a is disposed at the bottom of the excavation hole 3s, and the carried foundation is put into the excavation hole 3s. The foundation 30 may be constructed by arranging and backfilling as described above. In this case, the on-site work in the foundation construction can be reduced.
【0009】建込みの施工の概略は、後述の図8で説明
する方法で、エレベータシャフト2の下端に設けた接合
部32と基礎ユニット30Aの接合部31を高力ボルト
接合33等により接合してエレベータシャフト2を基礎
ユニット30Aに接続し、キャンティ梁2aの先端を踊
場1dの先端に、図外の手段で結合し、さらに、上記出
入口64毎に、各出入口64の下側の両側に設けられる
一対のキャンティ梁2a,2a間(即ち、各階に対応し
て図3の紙面方向に2本設けられるキャンティ梁2a,
2a間)にスラブ等の床材を取付けてエレベータシャフ
ト2の出入口64と建造物1との連通路を形成し、キャ
ンティ梁2aの側部を側壁で被うことで完成する。ま
た、建込み前には、図2に示すように踊場1dの先端側
を垂直養生パネル6で被った上で、手摺1eを解体撤去
してから、同じ位置に仮手摺7を取り付けておくものと
する。従って、図3に示す如く、エレベータシャフト2
を建込んだ後、仮手摺7を撤去すれば踊場1dとキャン
ティ梁2aとの連通が可能となる。ここで、エレベータ
シャフト2にはあらかじめガイドレール60,昇降籠7
0,巻上機80等の昇降設備が組付けられているので、
エレベータシャフト2の建込み後に、これら昇降設備を
搬入して組付ける必要はない。このため、エレベータシ
ャフト2の建込み後に、昇降籠70などをクレーンで吊
ってエレベータシャフト2の上方から入れる必要が無く
なるので、現場での施工手間,コストが減り、施工期間
も短縮することができる。The outline of the construction work is as follows: a joint 32 provided at the lower end of the elevator shaft 2 and a joint 31 of the base unit 30A are joined by a high-strength bolt joint 33 or the like by a method described later with reference to FIG. The elevator shaft 2 is connected to the base unit 30A, and the tip of the cantilever 2a is connected to the tip of the landing 1d by means not shown in the figure. 3 (that is, two cantilever beams 2a, 2a provided in the direction of the paper surface of FIG. 3 corresponding to each floor).
2a), a floor material such as a slab is attached to form a communication passage between the entrance and exit 64 of the elevator shaft 2 and the building 1, and the side portion of the chianti beam 2a is covered with a side wall to complete the process. Before the building, as shown in FIG. 2, the leading side of the landing 1d is covered with the vertical curing panel 6, the handrail 1e is dismantled and removed, and the temporary handrail 7 is attached at the same position. And Therefore, as shown in FIG.
After the building, the temporary handrail 7 is removed to allow communication between the landing 1d and the chianti beam 2a. Here, the elevator shaft 2 has a guide rail 60 and a lifting basket 7 in advance.
0, since hoisting equipment such as hoisting machine 80 is installed,
After the elevator shaft 2 is installed, it is not necessary to carry in these elevator facilities and assemble them. For this reason, after the elevator shaft 2 is installed, it is not necessary to suspend the elevator basket 70 and the like from above the elevator shaft 2 by using a crane, so that it is possible to reduce the construction labor and cost on site, and to shorten the construction period. .
【0010】尚、建込み前に、キャンティ梁2a間に上
記スラブ等の床材をあらかじめ取付けておいてから建込
むようにしてもよい。[0010] Before the building, the floor material such as the slab may be attached between the cantilever beams 2a before the building.
【0011】つぎに、図7(尚、図7(b)は正面図、
図7(a)は左側面図、図7(c)の右側面図である)
を用いてエレベータシャフト2の建込み時におけるエレ
ベータシャフト2の吊り方を説明する。まず、工場にお
いて、上述したようなエレベータシャフト2を製作し、
これをトラック等で現場に搬送し、現場において前,後
に位置された架台10a,10bの上にこのエレベータ
シャフト2を図7(b)に示すように横置きする。な
お、キャンティ梁2aは工場でエレベータシャフト2に
あらかじめ取付けておくので、エレベータシャフト2を
建込んだ後に現場で取付ける必要がない。従って、足場
などを組んで溶接等する必要がないので、現場での施工
手間,コストが減り、施工期間も短縮することができ
る。また、足場を利用した危険な作業を行う必要も無く
なる。尚、図7では、キャンティ梁2aが設けられた側
が地面3側を向くようにエレベータシャフト2を横置き
した状態から建起こす例を示しているが、キャンティ梁
2aが設けられた側が、上側あるいは横側を向くように
横置きした状態から建起こすようにしてもよい。FIG. 7 (FIG. 7 (b) is a front view,
7A is a left side view, and FIG. 7C is a right side view.
The method of suspending the elevator shaft 2 when the elevator shaft 2 is installed will be described with reference to FIG. First, in a factory, the elevator shaft 2 as described above is manufactured.
The elevator shaft 2 is transported to a site by a truck or the like, and the elevator shaft 2 is placed horizontally on the gantry 10a, 10b located at the front and rear of the site as shown in FIG. 7 (b). Since the cantilever 2a is previously attached to the elevator shaft 2 at the factory, there is no need to attach it at the site after the elevator shaft 2 is built. Therefore, since it is not necessary to form a scaffold or the like and perform welding or the like, it is possible to reduce labor and cost for construction on site and shorten the construction period. Moreover, it is not necessary to perform dangerous work using the scaffold. FIG. 7 shows an example in which the elevator shaft 2 is erected from a state in which the elevator shaft 2 is placed horizontally so that the side on which the cantilever beam 2a is provided faces the ground 3 side. You may make it erect from the state where it laid sideways so that it might turn to the side.
【0012】但し、キャンティ梁2aが搬送に邪魔とな
るときは、キャンティ梁2aを現場で組付けてエレベー
タシャフト2を構成してから建込むようにしてもよい。However, when the cantilever beam 2a hinders the transportation, the cantilever beam 2a may be assembled on site to construct the elevator shaft 2, and then installed.
【0013】図7(b),(a)に示すように、11は
エレベータシャフト2の頂部に取付けられた長枠より成
る頂部吊上げ部であり、キャンティ梁2aの突出方向と
直角方向に延長する如く取付けられ、その両端にはエレ
ベータシャフト2の側部よりも一定寸法突出し、この突
出部12の先端に、2本の頂部吊りワイヤ13a,13
aの下端が接続され、頂部吊りワイヤ13a,13aの
上端は、頂部吊りビーム14の両端に接続される。この
頂部吊りビーム14は頂部吊上げ部11と同程度の長さ
となっており、その両端は、左,右の電動チェーンブロ
ック15a,15aのワイヤ16a,16aに接続され
る。また、図7(b),(c)に示すように、エレベー
タシャフト2の背面側のやや下部側には、幅方向に延長
する長枠より成る下部吊上げ部17が固定される。この
下部吊上げ部17の両端はエレベータシャフト2の側部
よりも一定寸法突出し、この突出部18,18の先端
に、2本の下部吊りワイヤ19a,19aの下端が接続
され、下部吊りワイヤ19a,19aの上端は、下部吊
上げ部17と同程度の長さの下部吊りビーム20の両端
に接続される。この下部吊りビーム20の両端は、中央
の電動チェーンブロック21のワイヤ22に接続され
る。上記電動チェーンブロック15a,15a,21は
吊上げ材23に共通に取付けられ、この吊上げ材23は
図外のクレーンに、ワイヤ24を介して吊上げられる。
なお、頂部吊上げ部11の取付け位置は、キャンティ梁
2aの荷重を考慮して頂部の中央よりやや下寄りに位置
されて、エレベータシャフト2の建込み時の垂直バラン
スが取れるようにしている。また、25は電動チェーン
ブロックの電源ユニットである。As shown in FIGS. 7 (b) and 7 (a), reference numeral 11 denotes a top lifting portion formed of a long frame attached to the top of the elevator shaft 2, and extends in a direction perpendicular to the direction in which the chianti beam 2a projects. At both ends thereof, a predetermined dimension protrudes from the side of the elevator shaft 2, and two top suspension wires 13 a, 13 a
The lower end of a is connected, and the upper ends of the top suspension wires 13a, 13a are connected to both ends of the top suspension beam 14. The top suspension beam 14 has approximately the same length as the top suspension section 11, and both ends thereof are connected to wires 16a, 16a of the left and right electric chain blocks 15a, 15a. As shown in FIGS. 7B and 7C, a lower lifting portion 17 formed of a long frame extending in the width direction is fixed to a slightly lower portion on the back side of the elevator shaft 2. Both ends of the lower lifting portion 17 project from the side portion of the elevator shaft 2 by a certain distance, and the lower ends of two lower hanging wires 19a, 19a are connected to the tips of the projections 18, 18, respectively. The upper end of 19 a is connected to both ends of a lower suspension beam 20 having a length similar to that of the lower lifting section 17. Both ends of the lower suspension beam 20 are connected to wires 22 of a central electric chain block 21. The electric chain blocks 15a, 15a, and 21 are commonly attached to a lifting member 23, and the lifting member 23 is lifted by a crane (not shown) via a wire 24.
The mounting position of the top lifting section 11 is positioned slightly below the center of the top in consideration of the load of the cantilever 2a so that the elevator shaft 2 can be balanced vertically when installed. Reference numeral 25 denotes a power supply unit of the electric chain block.
【0014】以上の構成によれば、施工現場において、
図8(a)〜(c)に示すように、垂直養生パネル6を
除去した後、図外のクレーンでワイヤ24を介して吊上
げ材23を一定の高さに保持した状態で、電動チェーン
ブロック15a,15aでワイヤ16a,16aを巻上
げ、電動チェーンブロック21のワイヤ22を巻下げて
行くことにより、エレベータシャフト2を水平状態から
徐々に垂直状態に立てる。従って、吊上げに際して、エ
レベータシャフト2の頂部側の両側部と下部側の両側部
に、それぞれ横方向に突出する吊上げ部11,17を設
けて、この吊上げ部11,17の突出部12,18に吊
りワイヤ13a,19aの下端を接続して吊上げるよう
にしているので、エレベータシャフト2の姿勢を安定さ
せた状態で建込むことができる。また、吊りワイヤ13
a,19aがそれぞれ吊りビーム14,吊りビーム20
を介して、エレベータシャフト2に接続されているの
で、吊りワイヤ13a,19aがエレベータシャフト2
の外側に接触せず、エレベータシャフト2の外装ボード
63等の仕上げ材を痛めることがない。なお、エレベー
タシャフト2の上部側の吊り上げ機構において、吊りビ
ーム14を1本のワイヤと1つの電動チェーンブロック
で吊り上げるようにしてもよく、この場合でも、エレベ
ータシャフト2の外装ボード63等の仕上げ材を痛める
ことがない。ついで、図2,3に示すようにエレベータ
シャフト2の下側の回りに仮囲いパネル34を立ててガ
ードした状態で、図8(c)〜(f)に示すように、基
礎ユニット30Aの接合部31とエレベータシャフト2
の下端に設けられた接合部32とを合致させ、エレベー
タシャフト2の垂直度調整を行った後、高力ボルト接合
33等により、エレベータシャフト2を基礎30に接続
し、その回りを外壁仕上げ工事により塞ぐ。また、キャ
ンティ梁2aの先端を踊場1dの先端に対接させて、両
者を図外の固定手段で接合し、キャンティ梁2a間に床
材を取付け、かつキャンティ梁2aの両側を側壁で塞ぐ
とともに、エレベータシャフト2の内部の昇降機械をセ
ッティングすることで、エレベータシャフト2の増設が
行える。また、エレベータシャフト2の増設完了後に、
吊上げ部11,17を撤去し、撤去した部分に外装仕上
げを行うようにして外観を整えるようにしてもよい。以
上によりエレベータ塔の施工が完了する。According to the above configuration, at the construction site,
As shown in FIGS. 8A to 8C, after removing the vertical curing panel 6, the electric chain hoist 23 is held in a state in which the lifting material 23 is held at a certain height via the wire 24 by a crane (not shown). The elevator shaft 2 is gradually raised from a horizontal state to a vertical state by winding up the wires 16a, 16a with the wires 15a, and lowering the wire 22 of the electric chain block 21 with the wires 15a, 15a. Therefore, at the time of lifting, the lifting portions 11 and 17 projecting in the lateral direction are provided on both sides on the top side and both sides on the lower side of the elevator shaft 2, respectively, and the projections 12 and 18 of the lifting portions 11 and 17 are provided. Since the lower ends of the suspension wires 13a and 19a are connected to be lifted, the elevator shaft 2 can be built in a stable state. In addition, the suspension wire 13
a and 19a are the suspension beam 14 and the suspension beam 20, respectively.
Are connected to the elevator shaft 2 via the elevator shaft 2 so that the suspension wires 13a and 19a
Does not contact the outside of the elevator shaft 2 and does not damage the finishing material such as the exterior board 63 of the elevator shaft 2. In the lifting mechanism on the upper side of the elevator shaft 2, the suspension beam 14 may be lifted by one wire and one electric chain block. Even in this case, the finishing material such as the exterior board 63 of the elevator shaft 2 may be used. Does not hurt. Next, as shown in FIGS. 8 (c) to 8 (f), the temporary enclosure panel 34 is erected around the lower side of the elevator shaft 2 and guarded, as shown in FIGS. Part 31 and elevator shaft 2
After adjusting the verticality of the elevator shaft 2 with the joint 32 provided at the lower end of the elevator shaft, the elevator shaft 2 is connected to the foundation 30 by a high-strength bolted joint 33 or the like, and the surrounding area is subjected to exterior wall finishing work. Close by. Also, the tip of the cantilever 2a is brought into contact with the tip of the landing 1d, and the two are joined by a fixing means (not shown), a floor material is attached between the cantilever 2a, and both sides of the cantilever 2a are closed with side walls. By setting the lifting machine inside the elevator shaft 2, the elevator shaft 2 can be added. Also, after the completion of the extension of the elevator shaft 2,
The lifting portions 11 and 17 may be removed, and the exterior of the removed portion may be finished to improve the appearance. Thus, the construction of the elevator tower is completed.
【0015】なお、本発明は、図9に示すように、廊下
40が横並びの住戸41の前に設けられた集合住宅等の
建造物42の側部に階段43が設けられる場合にあって
は、階段43の隣りにエレベータシャフト2を建込ん
で、共通フロア44の床45側にエレベータシャフト2
から突出するキャンティ梁2aの先端を接続しても、あ
るいはエレベータシャフト2のキャンティ梁2aを廊下
40に直接接続しても、あるいは階段43の中央に設け
られる踊場43aにキャンティ梁2aの先端を接続して
もよい。As shown in FIG. 9, the present invention is applied to a case where a stairway 43 is provided on a side of a building 42 such as an apartment house provided in front of a dwelling unit 41 in which a corridor 40 is arranged side by side. , The elevator shaft 2 is built next to the stairs 43, and the elevator shaft 2 is placed on the floor 45 side of the common floor 44.
The tip of the cantilever 2a projecting from the stairs is connected, or the cantilever 2a of the elevator shaft 2 is directly connected to the corridor 40, or the tip of the cantilever 2a is connected to the landing 43a provided at the center of the stairs 43. May be.
【0016】また、図10に示すように、吊りビーム1
4,吊りビーム20を用いずに、吊上げ部11,17を
それぞれ2本のワイヤと1つの電動チェーンブロックで
吊り上げるようにしてもよく、この場合でも、エレベー
タシャフト2の姿勢を安定させた状態で建込むことがで
き、また、エレベータシャフト2の外装ボード63等の
仕上げ材を痛めることがない。Also, as shown in FIG.
4, the lifting portions 11 and 17 may be lifted by two wires and one electric chain block, respectively, without using the lifting beam 20. Even in this case, the posture of the elevator shaft 2 is stabilized. It can be erected and does not damage finishing materials such as the exterior board 63 of the elevator shaft 2.
【0017】尚、上記では、エレベータシャフト2側に
取付けたキャンティ梁2a,2a間にスラブ等の床材を
取付けて、連通路を構成したが、図11に示すように、
キャンティ梁2a,2a間に床材を取付けてエレベータ
シャフト2側通路2Xを形成するとともに、建造物1の
各階より跳ね出しスラブ2b等の床材を設けて建造物側
通路2Yを構成するようにし、これらエレベータシャフ
ト側通路2Xと建造物側通路2Yとにより連通路2Zを
構成するようにしてもよい。この場合、エレベータシャ
フト側通路2Xと建造物側通路2Yの接続部分には、例
えば、エキスパンジョイントを介装することにより、エ
レベータシャフト2と建造物1とを構造上分離するよう
にする。2cは跳ね出しスラブ2b保持用のアングルブ
ラケットである。これによれば、エレベータシャフト側
通路2Xと建造物側通路2Yを軽微なスラブで構築で
き、スラブ等の床材によるエレベータシャフト2の応力
負担が軽減される。また、建造物1側の跳ね出しスラブ
2bを、仮設の足場として利用できるといった効果が得
られる。尚、エレベータシャフト側通路2Xや建造物側
通路2Yを構成するスラブは、プレキャストコンクリー
ト板、デッキと一体化させたコンクリート板、鋼板など
の金属板、その他の単体あるいは複合体による床パネル
等を用いることができる。また、跳ね出しスラブ2b,
アングルブラケット2cは、工場などであらかじめ製作
し、現場に搬入して、エレベータシャフト2の建込み後
に取付ける。In the above description, a communication path is formed by attaching a floor material such as a slab between the cantilever beams 2a, 2a attached to the elevator shaft 2 side. However, as shown in FIG.
A floor material is attached between the cantilever beams 2a, 2a to form a passage 2X on the elevator shaft 2 side, and a floor material such as a slab 2b projecting from each floor of the building 1 is provided to form a building side passage 2Y. The communication passage 2Z may be configured by the elevator shaft side passage 2X and the building side passage 2Y. In this case, the elevator shaft 2 and the building 1 are structurally separated from each other by, for example, interposing an expand joint at a connecting portion between the elevator shaft side passage 2X and the building side passage 2Y. 2c is an angle bracket for holding the projecting slab 2b. According to this, the elevator shaft-side passage 2X and the building-side passage 2Y can be constructed with a small slab, and the stress load on the elevator shaft 2 due to the floor material such as the slab is reduced. Further, an effect is obtained that the projecting slab 2b on the building 1 side can be used as a temporary scaffold. As the slabs constituting the elevator shaft side passage 2X and the building side passage 2Y, a precast concrete plate, a concrete plate integrated with a deck, a metal plate such as a steel plate, and other floor panels made of a single body or a composite body are used. be able to. In addition, the spring slab 2b,
The angle bracket 2c is manufactured in advance at a factory or the like, carried into the site, and attached after the elevator shaft 2 is installed.
【0018】また、上記では、あらかじめ昇降設備を組
み込んだエレベータシャフト2を現場に搬入して建込む
ようにしたが、エレベータシャフトと昇降設備を別々に
現場に搬入し、エレベータシャフトを建込む前に、昇降
設備を組み込んだエレベータシャフト2を建込むように
してもよい。Further, in the above description, the elevator shaft 2 in which the elevating and lowering equipment is previously incorporated is carried into the site and built therein. However, the elevator shaft and the elevating and lowering equipment are separately carried into the site and before the elevator shaft is built. Alternatively, the elevator shaft 2 incorporating the elevating equipment may be built.
【0019】尚、昇降籠70や巻上機80などの昇降設
備は工場等でエレベータシャフトに組み込んでおいてか
ら現場に運搬すると損傷するおそれがあるので、ガイド
レール60等の損傷することの少ない昇降設備だけを工
場等でエレベータシャフトに組み込んでおくようにし、
これを現場に運搬して、他の昇降籠70や巻上機80な
どの昇降設備は現場で組み付けるようにしてもよい。こ
のようにすれば、少なくともガイドレール60が先付け
されているので、現場でのガイドレール取付け作業を省
け、また、ガイドレール60を工場等で取付けるので、
ガイドレール60の取付精度を良くできる。また、昇降
籠70や巻上機80などの昇降設備を損傷するおそれが
少なくなる。また、ガイドレール60があらかじめ組み
込まれたエレベータシャフトを建込んだ後に、昇降籠7
0や巻上機80などの昇降設備を当該エレベータシャフ
トに取付けるようにすれば、現場でのガイドレール取付
け作業を省け、ガイドレール60の取付精度を良くでき
るとともに、エレベータシャフトの建込み時の重量が軽
減し、建込み作業がやりやすくなる。The lifting equipment such as the lifting cage 70 and the hoisting machine 80 may be damaged if it is installed in an elevator shaft at a factory or the like and then transported to the site, so that the guide rail 60 and the like are less likely to be damaged. Only lift equipment should be incorporated into the elevator shaft at factories, etc.
This may be transported to the site, and other lifting equipment such as the lifting cage 70 and the hoisting machine 80 may be assembled at the site. In this way, since at least the guide rails 60 are pre-attached, the work of mounting the guide rails on site is omitted, and the guide rails 60 are mounted at a factory or the like.
The mounting accuracy of the guide rail 60 can be improved. In addition, there is less possibility that the lifting equipment such as the lifting basket 70 and the hoisting machine 80 will be damaged. Further, after the elevator shaft in which the guide rail 60 is incorporated in advance is built, the elevator basket 7 is installed.
If the elevator equipment such as the hoisting machine 0 and the hoist 80 is mounted on the elevator shaft, the work of mounting the guide rails on site can be omitted, the mounting accuracy of the guide rails 60 can be improved, and the weight of the elevator shaft at the time of installation can be improved. Is reduced, and the installation work becomes easier.
【0020】また、エレベータシャフト2の高さが高過
ぎて、搬送上もしくは吊上げ重量の関係で分割せざる得
ない場合や、エレベータ塔設置場所に建起こし用のスペ
ースが十分にない場合には、上記エレベータシャフト2
をあらかじめ分割して製作して、これら分割された複数
の分割エレベータシャフトを現場に搬入して組立てるよ
うにしてエレベータ塔を構築してもよい。例えば、エレ
ベータシャフト2を2分割した分割エレベータシャフト
2を予め工場等で製作して、これらを現場に搬入して組
立てる方法について、図12(a)〜(f)に基づいて
説明する。尚、図12においては、キャンティ梁2aの
図示を省略している。まず、基礎30を施工し、エレベ
ータシャフト2の下側部分を構成する分割エレベータシ
ャフト2Aの下端の接合部32を基礎30の基礎ユニッ
ト30Aの接合部31に合致させて高力ボルト接合等に
より接合して分割エレベータシャフト2Aを建込む。次
に、建込んだ分割エレベータシャフト2A内に昇降籠7
0を入れて、昇降籠70の重量をガイドレール60にあ
ずける。その後、エレベータシャフト2の上側部分を構
成する分割エレベータシャフト2Bを分割エレベータシ
ャフト2Aの上に連結接合する。そして、分割エレベー
タシャフト2Aと基礎30との接合部分35の周り及び
分割エレベータシャフト2Aと分割エレベータシャフト
2Bとの連結接合部分36の周りを外装仕上げ工事によ
り仕上げることで、分割エレベータシャフト2A,2B
により構成されたエレベータシャフト2によるエレベー
タ塔が完成する。尚、図12では、2分割の場合を説明
したが、分割数はいくつでもよい。また、最下側部分を
構成する分割エレベータシャフト内に昇降籠70を組み
込んだ状態でこの最下側部分の分割エレベータシャフト
を建込むようにしてもよいが、この場合、昇降籠70の
仮受けのための装置が必要となる。従って、上記のよう
に、最下側部分を構成する分割エレベータシャフトを建
込んだ後にこの分割エレベータシャフト内に昇降籠70
を入れて昇降籠70の重量を当該分割エレベータシャフ
ト内のガイドレール60にあずけるようにした方が仮受
けのための装置が不要となり、コストを低減できて、作
業も容易になるので好ましい。In the case where the height of the elevator shaft 2 is too high and it is necessary to divide the elevator shaft 2 in terms of transportation or lifting weight, or when there is not enough space for erection at the installation site of the elevator tower, The above elevator shaft 2
May be divided in advance and the divided elevator shafts may be carried to the site and assembled to construct an elevator tower. For example, a method of manufacturing an elevator shaft 2 in which the elevator shaft 2 is divided into two parts in advance at a factory or the like, and carrying them into the site and assembling them will be described with reference to FIGS. In FIG. 12, the illustration of the chianti beam 2a is omitted. First, the foundation 30 is constructed, and the joining portion 32 at the lower end of the divided elevator shaft 2A constituting the lower portion of the elevator shaft 2 is matched with the joining portion 31 of the foundation unit 30A of the foundation 30, and joined by high-strength bolt joining or the like. To build the divided elevator shaft 2A. Next, the elevator basket 7 is placed in the built divided elevator shaft 2A.
0 is inserted, and the weight of the lifting basket 70 is given to the guide rail 60. Thereafter, the divided elevator shaft 2B constituting the upper part of the elevator shaft 2 is connected and joined on the divided elevator shaft 2A. Then, around the joint 35 between the divided elevator shaft 2A and the foundation 30 and around the joint 36 between the divided elevator shaft 2A and the divided elevator shaft 2B by exterior finishing work, the divided elevator shafts 2A and 2B are finished.
The elevator tower with the elevator shaft 2 constituted by the above is completed. Although FIG. 12 illustrates the case of two divisions, the number of divisions may be any number. In addition, while the elevator cage 70 is installed in the divided elevator shaft constituting the lowermost part, the divided elevator shaft of the lowermost part may be erected, but in this case, the temporary elevator cage 70 is temporarily mounted. Device is required. Therefore, as described above, after the divided elevator shaft constituting the lowermost portion is erected, the elevator cage 70 is placed in the divided elevator shaft.
It is preferable that the weight of the elevator cage 70 be put into the guide rail 60 in the divided elevator shaft so that a device for temporary receiving becomes unnecessary, the cost can be reduced, and the work becomes easier.
【0021】[0021]
【発明の効果】以上説明したように、この発明によれ
ば、階段部分を撤去する必要がなく、短期間でエレベー
タ塔を施工できるようになり、施工コストを抑えること
ができ、また、エレベータシャフトの外装仕上げ材を痛
めることなく、エレベータシャフトを建込むことがで
き、また、エレベータシャフトの建て起こしから正規の
位置への取付けまでを、ワイヤでエレベータシャフトを
吊り上げた状態のままで行えるようになる。なお、上記
効果に加え、請求項3に係る発明によれば、現場での施
工手間,コストを減らすことができる。 As described above, according to the present invention, it is not necessary to remove the stairs, the elevator tower can be constructed in a short time, the construction cost can be reduced , and the elevator shaft can be reduced. Hurt the exterior finishing material
Elevator shaft can be built without turning
From the erecting of the elevator shaft
Elevator shaft with wire until installation in position
It becomes so that can remain in the lifting state. In addition to the above effects, according to the third aspect of the invention, it is possible to reduce the labor and cost for construction on site .
【図1】 この発明の実施の形態による方法でエレベー
タ塔を増設する集合住宅の平面図である。FIG. 1 is a plan view of an apartment house in which an elevator tower is added by a method according to an embodiment of the present invention.
【図2】 集合住宅と実施の形態による方法で増設する
エレベータ塔の位置関係を示す図である。FIG. 2 is a diagram illustrating a positional relationship between an apartment house and an elevator tower that is added by the method according to the embodiment;
【図3】 集合住宅と実施の形態による方法で増設され
たエレベータ塔とを示す図である。FIG. 3 is a diagram showing an apartment house and an elevator tower added by the method according to the embodiment;
【図4】 エレベータシャフトの斜視図である。FIG. 4 is a perspective view of an elevator shaft.
【図5】 エレベータシャフトの製作工程を説明する図
である。FIG. 5 is a diagram illustrating a manufacturing process of the elevator shaft.
【図6】 エレベータ塔の基礎の施工工程を説明する図
である。FIG. 6 is a diagram illustrating a construction process of an elevator tower foundation.
【図7】 エレベータシャフトの吊上げ前の状態を示す
図である。FIG. 7 is a diagram showing a state before the elevator shaft is lifted.
【図8】 エレベータシャフトの吊上げ、建込みの工程
を示す図である。FIG. 8 is a diagram showing a process of lifting and setting up the elevator shaft.
【図9】 この発明の他の実施の形態を示す図である。FIG. 9 is a diagram showing another embodiment of the present invention.
【図10】 この発明の他の実施の形態を示す図であ
る。FIG. 10 is a diagram showing another embodiment of the present invention.
【図11】 この発明の他の実施の形態を示す図であ
る。FIG. 11 is a diagram showing another embodiment of the present invention.
【図12】 分割エレベータシャフトによるエレベータ
塔の施工工程を説明する図である。FIG. 12 is a diagram illustrating a construction process of an elevator tower using a divided elevator shaft.
1 建造物、2 エレベータシャフト、2A,2B 分
割エレベータシャフト、2a キャンティ梁、2X エ
レベータシャフト側通路、2Y 建造物側通路、2Z
連通路、3 地面、3s 掘削穴、11,17 吊上げ
部、12,18 突出部、14,20 吊りビーム、1
5a,21 電動チェーンブロック、13a,16a,
19a,22 ワイヤ、30 基礎、30A 基礎ユニ
ット、31 接合部。DESCRIPTION OF SYMBOLS 1 Building, 2 elevator shaft, 2A, 2B split elevator shaft, 2a Chianti beam, 2X elevator shaft side passage, 2Y building side passage, 2Z
Communication passage, 3 ground, 3s excavation hole, 11,17 lifting part, 12,18 projecting part, 14,20 suspension beam,
5a, 21 Electric chain block, 13a, 16a,
19a, 22 wires, 30 foundations, 30A foundation unit, 31 joints.
フロントページの続き (72)発明者 藤原 健 東京都新宿区津久戸町2番1号 株式会 社熊谷組 東京本社内 (72)発明者 羽野 弘規 東京都新宿区津久戸町2番1号 株式会 社熊谷組 東京本社内 (72)発明者 木下 克彦 東京都新宿区津久戸町2番1号 株式会 社熊谷組 東京本社内 (72)発明者 永野 雅則 東京都新宿区津久戸町2番1号 株式会 社熊谷組 東京本社内 (72)発明者 飯利 昌人 東京都新宿区津久戸町2番1号 株式会 社熊谷組 東京本社内 (56)参考文献 特開 平8−282944(JP,A) 特開 昭58−172180(JP,A) 特開 昭61−188381(JP,A) 特開 平9−315724(JP,A) 特開 平11−159153(JP,A) 特開 平8−217359(JP,A) 特開 平5−310381(JP,A) 特開 平10−25072(JP,A) 特開 平8−143245(JP,A) 実開 平7−23776(JP,U) (58)調査した分野(Int.Cl.7,DB名) B66B 7/00 - 7/12 Continued on the front page (72) Inventor Ken Fujiwara 2-1 Tsukudo-cho, Shinjuku-ku, Tokyo Co., Ltd. Kumagaya Gumi Tokyo Head Office (72) Inventor Hironori Hano 2-1 Tsukudo-cho, Shinjuku-ku, Tokyo Co., Ltd. Kumagaya Co., Ltd. Gumi Tokyo Headquarters (72) Katsuhiko Kinoshita, Inventor 2-1 Tsukudocho, Shinjuku-ku, Tokyo Kumagaya Gumi Tokyo Headquarters (72) Inventor Masanori Nagano 2-1 Tsukudocho, Shinjuku-ku, Tokyo Co., Ltd. Gumi Tokyo Head Office (72) Inventor Masato Imari 2-1 Tsukudo-cho, Shinjuku-ku, Tokyo Kumagaya Gumi Tokyo Head Office (56) References JP-A-8-282944 (JP, A) JP Akira 58-172180 (JP, A) JP-A-61-188381 (JP, A) JP-A-9-315724 (JP, A) JP-A-11-159153 (JP, A) JP-A-8-217359 (JP, A A) JP-A-5-310381 (JP, A) JP-A-10-25072 (JP, A) JP-A-8-143245 (JP, A) JP-A-7-23776 (JP, U) (58) Survey Minutes (Int.Cl. 7, DB name) B66B 7/00 - 7/12
Claims (4)
筒状のエレベータシャフトをあらかじめ製作して、建造
物の完成後又は建造過程でこのエレベータシャフトを垂
直に建込んで固定し、上記エレベータシャフトの出入口
を上記各階に連通させたエレベータ塔の施工方法であっ
て、エレベータシャフトの上端側の両側部と下部側の両
側部に、それぞれ横方向に突出する突出部を設けて、こ
の突出部にワイヤの下端を接続し、このワイヤがエレベ
ータシャフトの外側に接触しないようにワイヤの上端を
保持して上記エレベータシャフトを吊るようにしたこと
を特徴とするエレベータ塔の施工方法。1. A cylindrical elevator shaft having an entrance corresponding to each floor of a building is manufactured in advance, and the elevator shaft is vertically erected and fixed after completion of the building or during the building process. The construction method of the elevator tower with the entrance of
The upper and lower sides of the elevator shaft.
Provide side projections on each side,
Connect the lower end of the wire to the protrusion of
The upper end of the wire so that it does not touch the outside of the
A method for constructing an elevator tower, wherein the elevator shaft is suspended while being held .
各階をつなぐ階段の踊場に連通させたことを特徴とする
請求項1に記載のエレベータ塔の施工方法。2. The method according to claim 1, wherein an entrance of the elevator shaft communicates with a landing of a stair connecting the floors.
上記エレベータシャフトに昇降籠のガイドレール,昇降
籠,巻上機等の昇降設備をあらかじめ組込んでおくよう
にしたことを特徴とする請求項1又は請求項2に記載の
エレベータ塔の施工方法。 3. Before the elevator shaft is installed,
3. The method for constructing an elevator tower according to claim 1 or 2, wherein the elevator shaft is provided with in advance lifting equipment such as a guide rail of the lifting cage, a lifting cage, and a hoist.
の先端間の長さと同程度の吊りビームを用いてワイヤの
上端を保持することでワイヤがエレベータシャフトに接
触しないようにエレベータシャフトを吊ることを特徴と
する請求項1ないし請求項3のいずれかに記載のエレベ
ータ塔の施工方法。 4. Each projecting portion projecting in the lateral direction.
Of the wire using a suspension beam of the same length as
Holding the upper end allows the wire to contact the elevator shaft.
It is characterized by hanging the elevator shaft so that it does not touch
The elevator according to any one of claims 1 to 3,
Construction method of data tower.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000282431A JP3345395B2 (en) | 1999-12-20 | 2000-09-18 | Elevator tower construction method |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP11-361667 | 1999-12-20 | ||
JP36166799 | 1999-12-20 | ||
JP2000282431A JP3345395B2 (en) | 1999-12-20 | 2000-09-18 | Elevator tower construction method |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002219319A Division JP2003137483A (en) | 1999-12-20 | 2002-07-29 | Construction method of elevator tower |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2001240340A JP2001240340A (en) | 2001-09-04 |
JP3345395B2 true JP3345395B2 (en) | 2002-11-18 |
Family
ID=26581305
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000282431A Expired - Fee Related JP3345395B2 (en) | 1999-12-20 | 2000-09-18 | Elevator tower construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3345395B2 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003013615A (en) * | 2001-07-03 | 2003-01-15 | Chikashi Soda | Method for setting elevator to apartment house |
CN101759079B (en) * | 2009-12-30 | 2012-05-30 | 山西四建集团有限公司 | Method for integrally assembling and installing steel structure elevator derrick on the ground |
-
2000
- 2000-09-18 JP JP2000282431A patent/JP3345395B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2001240340A (en) | 2001-09-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP7542522B2 (en) | Method for constructing a multi-storey structure, facade and building | |
KR20220154087A (en) | construction method | |
JP3569861B2 (en) | Construction method of stairs and staircase, staircase support device, and staircase structure | |
US7219474B2 (en) | Load bearing building panel | |
JP3196043B2 (en) | Construction method of stairs and staircase, construction method of stairs, and stair members | |
JP3345395B2 (en) | Elevator tower construction method | |
JP3078931B2 (en) | Climbing stage method and chimney construction method for tubular structures | |
JP2003137483A (en) | Construction method of elevator tower | |
JP2874576B2 (en) | Moving scaffold for retaining wall construction | |
JP2683878B2 (en) | Precast staircase structure | |
AU2019316713B2 (en) | Method of erecting a multi-storey structure and facade | |
JP3234442B2 (en) | Building and scrap type building method | |
JPH09235849A (en) | External staircase | |
JP2002087730A (en) | Work execution method for elevator tower, and elevator shaft | |
JP3944870B2 (en) | Method for constructing staircase with staircase and unit staircase used in this construction method | |
JP2650606B2 (en) | Stairs outside PC | |
JP2002087729A (en) | Work execution method for elevator tower | |
JP2761527B2 (en) | How to build structures | |
JP2023008012A (en) | Method of constructing additional elevator shaft for mid-rise residential building | |
JP2761528B2 (en) | How to build structures | |
AU2002234421B2 (en) | A load bearing building panel | |
JPH0849301A (en) | Building with basement | |
JP2761526B2 (en) | How to build structures | |
JPH1113141A (en) | Constructing method of composite structure | |
FI79587C (en) | Method and apparatus for performing edge suspension on a hollow plate. |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20020820 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 3345395 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080830 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080830 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090830 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100830 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100830 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110830 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110830 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120830 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120830 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130830 Year of fee payment: 11 |
|
LAPS | Cancellation because of no payment of annual fees |