JP2876182B2 - Joint foundation for temporary shutter - Google Patents

Joint foundation for temporary shutter

Info

Publication number
JP2876182B2
JP2876182B2 JP16283994A JP16283994A JP2876182B2 JP 2876182 B2 JP2876182 B2 JP 2876182B2 JP 16283994 A JP16283994 A JP 16283994A JP 16283994 A JP16283994 A JP 16283994A JP 2876182 B2 JP2876182 B2 JP 2876182B2
Authority
JP
Japan
Prior art keywords
base
foundation
temporary shutter
temporary
shutter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP16283994A
Other languages
Japanese (ja)
Other versions
JPH084007A (en
Inventor
州治 高瀬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP16283994A priority Critical patent/JP2876182B2/en
Publication of JPH084007A publication Critical patent/JPH084007A/en
Application granted granted Critical
Publication of JP2876182B2 publication Critical patent/JP2876182B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Operating, Guiding And Securing Of Roll- Type Closing Members (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、建築現場の仮囲いにお
ける出入口に設置する仮設シャッターを山留め工法に使
用中の杭体に固定する様にした仮設シャッター用ジョイ
ント基礎に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a temporary shutter joint base in which a temporary shutter installed at an entrance of a temporary enclosure at a construction site is fixed to a pile used in a mountain retaining method.

【0002】[0002]

【従来の技術】従来、建築現場の境界部に仮設する仮囲
いにおける出入口に仮設シャッターを設置する場合、大
型車輌、土木作業機材及び資材等の搬入出のために幅広
で背高の仮設シャッターを使用せねばならないが、かか
る仮設シャッターは非常に重く、而も一対の支柱上端部
間にシャッター本体を架設しているために重心が上方に
あってバランスが悪いため、仮設シャッターを支えるた
めのボリュームの大きい基礎の構築作業が必要に成り、
且つ仮設シャッターの倒壊等の事故が発生しない様に綿
密な構造計算も必要になって甚だ面倒であった。
2. Description of the Related Art Conventionally, when a temporary shutter is installed at a doorway of a temporary enclosure temporarily provided at a boundary of a building site, a wide and tall temporary shutter is used to carry in and out a large vehicle, civil engineering equipment and materials. Although it must be used, such a temporary shutter is very heavy, and since the shutter body is erected between the upper ends of a pair of columns, the center of gravity is at the top and the balance is poor, so the volume for supporting the temporary shutter is The construction work of a large foundation is necessary,
In addition, detailed structural calculations are required to prevent accidents such as the collapse of the temporary shutter, which is extremely troublesome.

【0003】又、建物基礎、地下構築物を構築するため
に1階床部よりやや広く敷地を掘削する総根切りを行っ
ており、かかる掘削時における掘削面の崩壊を防止する
ための山留め工法は、掘削前に掘削予定部の周囲部に多
数の杭体を所定間隔毎に打ち込み、その内側をパワーシ
ャベル等により全面的に掘削すると共に順次杭体間に横
矢板を嵌め込む様にして行っている。
Further, in order to construct a building foundation and an underground structure, a total excavation is performed to excavate a site slightly wider than the first floor, and a mountain retaining method for preventing collapse of an excavated surface during such excavation is known. Before the excavation, a large number of piles are driven into the periphery of the portion to be excavated at predetermined intervals, and the inside is entirely excavated with a power shovel or the like, and a horizontal sheet pile is sequentially inserted between the piles. I have.

【0004】しかし、最近の建物は敷地ぎりぎりに建て
ることが多いため、掘削部も当然敷地ぎりぎりになり、
その結果仮設シャッターのための大ボリュームの基礎を
構築するスペースが無く、対応に苦慮していた。
[0004] However, since recent buildings are often built just off the site, the excavation section is naturally also on the site,
As a result, there was no space to build a large-volume foundation for temporary shutters, and it was difficult to respond.

【0005】[0005]

【発明が解決しようとする課題】本発明は、山留めに使
用中の杭体に仮設シャッターを取り付けることによっ
て、建物が敷地境界線ぎりぎりの状況下でも仮設シャッ
ターを設置可能にした仮設シャッター用ジョイント基礎
を提供せんとするものである。
SUMMARY OF THE INVENTION The present invention relates to a temporary shutter joint base in which a temporary shutter is attached to a pile in use for a mountain retaining device so that the temporary shutter can be installed even when the building is very close to the site boundary line. Is to be provided.

【0006】[0006]

【課題を解決するための手段】本発明は、上記従来技術
に基づく、建築現場の仮囲いにおける出入口に設置する
仮設シャッターは、綿密な構造計算に基づく大ボリュー
ム基礎の構築作業が必要になるが、建物が敷地ぎりぎり
では仮設シャッターを設置することが非常に困難な課題
に鑑み、一対の土台梁上に載架固設したベース台により
ジョイント基礎を構成し、建築基礎、地下構築物のため
の掘削部における山留め用の多数の杭体の内、仮設シャ
ッターにおける一対の支柱との対応位置の隣接する一対
の杭体上端部間に一対の土台梁を並列架設すると共に、
ベース台におけるベース板上面に一体固設した支持脚部
上に仮設シャッターの支柱をボルト及びナットによる連
結手段により連結一体化することによって、地中深く打
ち込まれ、且つジョイント基礎を取り付けた杭体が仮設
シャッターの基礎杭体になって、敷地境界線と掘削部間
に余地が無くとも仮設シャッターを設置可能にして、上
記課題を解消せんとしたものである。
SUMMARY OF THE INVENTION According to the present invention, a temporary shutter to be installed at an entrance in a temporary enclosure of a building site based on the above-mentioned prior art requires a work of constructing a large-volume foundation based on detailed structural calculations. Considering the difficult task of installing temporary shutters when the building is at the very end of the site, a joint base is constructed with a base mounted on a pair of base beams and excavated for building foundations and underground structures Of a number of piles for mountain retaining in the part, a pair of foundation beams are laid in parallel between upper ends of a pair of piles adjacent to each other at positions corresponding to the pair of columns in the temporary shutter,
By connecting the support of the temporary shutter to the support legs integrally fixed to the upper surface of the base plate by the connection means using bolts and nuts, the pile body driven deep into the ground and attached with the joint foundation is formed. The object of the present invention is to solve the above-mentioned problem by providing a temporary shutter as a foundation pile of a temporary shutter so that the temporary shutter can be installed even if there is no room between the site boundary line and the excavation part.

【0007】[0007]

【実施例】以下本発明の一実施例を図面に基づいて説明
すると、1、1aは仮設シャッターS両側部の支柱L、La
を掘削部Aの山留めに使用中の杭体P、Pa…に固設する
ための一対のジョイント基礎であり、該ジョイント基礎
1、1aは夫々に隣接する一対の杭体P、Pa間に並列架設
する一対の土台梁2、2aと、該土台梁2、2a上に載架固
設して支柱L、La下端部を連結するベース台3により構
成され、仮設シャッターSの支柱L、Laとの対応位置の
2箇所における上記一対の杭体P、Paを一組にして基礎
杭体B、Baと成している。
DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the drawings.
Are fixed to the piles P, Pa... Used in the retaining of the excavation part A. The joint foundations 1 and 1a are arranged in parallel between the pair of adjacent piles P and Pa, respectively. It is composed of a pair of base beams 2, 2a to be erected, a base L mounted on and fixed to the base beams 2, 2a, and a base 3 connecting the lower ends of La. The pair of piles P and Pa at two locations corresponding to (1) and (2) form a foundation pile B and Ba.

【0008】尚、杭体P、Pa…はI型鋼で、フランジ
F、Faを杭体P、Pa…の配設方向に平行にして、而も掘
削部A底部より更に深く打ち込むと共に、上端部を地盤
面と略同一と成している。
The piles P, Pa... Are I-section steels. The flanges F, Fa are parallel to the direction in which the piles P, Pa. Is substantially the same as the ground surface.

【0009】先ず、土台梁2、2aについて説明すると、
4、4a…は各土台梁2、2aの構成要素の主要部となる一
対のみぞ形鋼であり、該みぞ形鋼4、4a…のウェブの長
手方向両端部にボルト孔5、5a…を縦方向直列に複数貫
設し、一方基礎杭体B、BaのフランジF、Faにボルト孔
5、5a…に対応するボルト孔H、Ha…を貫設し、かかる
みぞ形鋼4、4aを背合わせ状態に対設してその両端側で
フランジF、Faを挟着し、ボルト孔5、5a…、H、Ha…
に固定ボルト6、6a…を挿設すると共に、各固定ボルト
6、6a…の突端部に2個のナット7、7aを螺嵌して、基
礎杭体B、Ba間に土台梁2、2aを並列横架している。
First, the base beams 2, 2a will be described.
, 4a... Are a pair of grooved steels which are the main components of the base beams 2, 2a. Bolt holes 5, 5a... Are formed at both longitudinal ends of the webs of the grooved steels 4, 4a. A plurality of bolts H, Ha... Corresponding to the bolt holes 5, 5a... Are provided in the foundation pile B, the flanges F, Fa of the Ba, and the grooved steels 4, 4a. The flanges F, Fa are sandwiched at both ends of the back-to-back state, and the bolt holes 5, 5a,.
, And two nuts 7, 7a are screwed into the protruding ends of the fixing bolts 6, 6a, so that the base beams 2, 2a are interposed between the foundation piles B, Ba. Are laid in parallel.

【0010】8は各土台梁2、2aの縦方向に貫設したボ
ルト挿通部位であり、該ボルト挿通部位8は土台梁2、
2aの長手方向に長く形成し、本実施例においてはみぞ形
鋼4、4a間に形成されたみぞ形鋼4、4aの長手方向に長
い隙間部9をボルト挿通部位8と成している。
Reference numeral 8 denotes a bolt insertion portion penetrating in the longitudinal direction of each of the base beams 2, 2a.
In the present embodiment, a long gap portion 9 in the longitudinal direction of the grooved steel 4, 4 a formed between the grooved steel 4, 4 a forms a bolt insertion portion 8 in the present embodiment.

【0011】尚、各土台梁2、2aにおけるフランジF、
Faの外側面側のみぞ形鋼4の両端部に間隔保持板10、10
a を一体固設して、みぞ形鋼4、4a間のボルト挿通部位
8の間隔を拡幅している。
Incidentally, the flanges F in each of the base beams 2, 2a,
Spacing plates 10, 10 on both ends of the groove 4 on the outer side of Fa
a is integrally fixed to widen the interval between the bolt insertion portions 8 between the grooved steel bars 4 and 4a.

【0012】次に、ベース台3について説明すると、11
は矩形状のベース板であり、該ベース板11における各土
台梁2、2aのボルト挿通部位8との相当部位に所定間隔
毎にボルト孔12、12a …を貫設している。
Next, the base 3 will be described.
Is a rectangular base plate, and bolt holes 12, 12a,... Are provided at predetermined intervals in portions of the base plate 11 corresponding to the bolt insertion portions 8 of the base beams 2, 2a.

【0013】13、13a …は土台梁2、2aにベース台3を
固設する固定ボルトであり、各土台梁2、2a下部に配設
した1枚の座金板14を介してボルト挿通部位8に下方側
より固定ボルト13、13a …を挿設しボルト孔12、12a …
を貫通してベース板11より上方へ突出させ、かかる突端
部の夫々に座金15を介し2個のナット16、16a を螺嵌し
て、土台梁2、2a上にベース台3を載架固設している。
Reference numerals 13, 13a... Denote fixing bolts for fixing the base 3 to the base beams 2, 2a, and the bolt insertion portions 8 through one washer plate 14 disposed under each of the base beams 2, 2a. The fixing bolts 13, 13a ... are inserted from below into the bolt holes 12, 12a ...
Through the base plate 11 and project upward from the base plate 11. Two nuts 16 and 16a are screwed into the respective protruding ends via washers 15 to mount the base table 3 on the base beams 2 and 2a. Has been established.

【0014】17、17a …は土台梁2、2aに対するベース
台3の姿勢調節ボルトであり、ベース板11の四隅部近傍
の上方より姿勢調節ボルト17、17a …を垂直螺入して、
土台梁2、2aにおける内側のみぞ型鋼4a上面に姿勢調節
ボルト17、17a …の下端部が当接する様にしており、ベ
ース板11における姿勢調節ボルト17、17a …の螺入部位
にナット18、18a …を固設して、姿勢調節ボルト17、17
a …の回動によりその下端部をベース板11下面より出没
自在と成している。
Reference numerals 17, 17a... Are posture adjusting bolts of the base 3 with respect to the base beams 2, 2a. The posture adjusting bolts 17, 17a.
The lower ends of the posture adjusting bolts 17, 17a... Abut against the upper surface of the inner grooved steel 4a of the base beams 2, 2a. 18a… fixed and posture adjustment bolts 17, 17
By the rotation of a..., the lower end can be made to protrude and retract from the lower surface of the base plate 11.

【0015】19はベース板11の上面中央部に一体固設し
た支持脚部で、水平断面H形状の脚柱20上端部に矩形状
にして水平な連結板21を一体固設しており、連結板21に
ボルト孔22、22a …を貫設すると共に、各ボルト孔22、
22a …に挿設した連結ボルト23及びその突端部に螺嵌し
た2個のナット24、24a により支柱L、La下端部との連
結手段25を構成している。
Reference numeral 19 denotes a support leg integrally fixed at the center of the upper surface of the base plate 11, and a rectangular horizontal connecting plate 21 is integrally fixed to an upper end of a pillar 20 having an H-shaped horizontal cross section. The bolt holes 22, 22a,...
The connecting bolts 23 inserted in 22a and the two nuts 24, 24a screwed into the protruding ends of the connecting bolts 23 constitute connecting means 25 for connecting the support L and the lower end of La.

【0016】尚、図面中26、26a …はフランジF、Faの
外側面側のみぞ形鋼4に設けたリブ、27、27a …は連結
板21下部に設けたリブ、28、28a …は支持脚部19側部に
設けた三角板状のリブである。
In the drawings, 26, 26a are ribs provided on the grooved steel 4 only on the outer surface side of the flanges F, Fa, 27, 27a are ribs provided below the connecting plate 21, and 28, 28a are supporters. A triangular plate-shaped rib provided on the side of the leg 19.

【0017】次に本発明に係る仮設シャッター用ジョイ
ント基礎の取付け方法及び作用について説明すると、先
ず、建築基礎、地下構築物のための掘削部Aにおける山
留め用の杭体P、Pa…の内、仮設シャッターSの各支柱
L、Laの対応位置に配置された一対の基礎杭体B、Baの
上端周囲部の地盤を所定深さ掘削し、次にフランジF、
Faの外側面側のみぞ形鋼4のボルト孔5、5a…と、基礎
杭体B、BaのフランジF、Faのボルト孔H、Ha…を合致
させると共に、隣接する基礎杭体B、Baのウェブ間に合
致させる様にみぞ形鋼4を基礎杭体B、Baに添えて固定
ボルト6、6a…を挿通すると共に、内側のみぞ形鋼4aの
ボルト孔5、5a…に固定ボルト6、6a…を挿通する様に
内側のみぞ形鋼4aをセットした後、固定ボルト6、6a…
の突端部の夫々に2個のナット7、7aを螺嵌して、基礎
杭体B、Ba間に土台梁2、2aを並列横架する。
Next, a method and an operation of mounting the temporary shutter joint foundation according to the present invention will be described. First, the temporary foundations P, Pa... Excavating the ground around the upper end of the pair of foundation piles B and Ba located at the corresponding positions of the respective columns L and La of the shutter S to a predetermined depth, and then excavating the flange F,
The bolt holes 5, 5a... Of the grooved steel 4 on the outer surface side of Fa are aligned with the flanges F of the foundation piles B and Ba, the bolt holes H and Ha of Fa, and the adjacent foundation piles B and Ba are adjacent to each other. The grooved steel 4 is attached to the foundation piles B and Ba so that the fixing bolts 6, 6a... Are inserted so as to match with the webs, and the fixing bolts 6 are inserted into the bolt holes 5, 5a. , 6a ... are inserted, and after the inner grooved steel 4a is set, the fixing bolts 6, 6a ...
Two nuts 7 and 7a are screwed into each of the protruding end portions of the base piles B and Ba, and the base beams 2 and 2a are laid in parallel between the foundation piles B and Ba.

【0018】次に、ベース台3のベース板11を土台梁
2、2aに載架し、各土台梁2、2a下部に座金板14を配置
して、ボルト挿通部位8に下方側より固定ボルト13、13
a …を挿通してボルト孔12、12a …より上方へ突出さ
せ、固定ボルト13、13a …の各突端部に座金15を介して
2個のナット16、16a を螺嵌し、その時点でベース台3
が水平でない場合に姿勢調節ボルト17、17a …を適宜回
転させ下端部を突出させて、両方のジョイント基礎1、
1aにおけるベース台3を水平且つ同レベルにし、そして
各固定ボルト13、13a …に螺嵌したナット16、16a を完
全に締めつけて、土台梁2、2aとベース台3を堅固に一
体化する。
Next, the base plate 11 of the base 3 is mounted on the base beams 2 and 2a, and a washer plate 14 is disposed below each of the base beams 2 and 2a. 13, 13
a through the bolt holes 12, 12 a, and projecting upward from the bolt holes 12, 12 a, and two nuts 16, 16 a are screwed into the respective protruding ends of the fixing bolts 13, 13 a via the washer 15. Stand 3
Is not horizontal, the posture adjusting bolts 17, 17a are appropriately rotated to protrude the lower ends, and both joint bases 1,
The base table 3 in 1a is horizontal and at the same level, and the nuts 16, 16a screwed into the fixing bolts 13, 13a... Are completely tightened to firmly integrate the base beams 2, 2a and the base table 3.

【0019】そして、クレーン等により仮設シャッター
Sを吊り下げて、支柱L、Laをベース台3の支持脚部19
における連結板21上に配置し、各ボルト孔22、22a …に
連結ボルト23を挿通すると共に、該連結ボルト23の突端
部に2個のナット24、24a を螺嵌して、各支柱L、Laを
ベース台3に連結一体化し仮設シャッターSを設置す
る。
Then, the temporary shutter S is suspended by a crane or the like, and the columns L and La are supported by the support legs 19 of the base 3.
, The connecting bolt 23 is inserted into each of the bolt holes 22, 22a,..., And two nuts 24, 24a are screwed into the protruding ends of the connecting bolts 23, so that each of the columns L, La is connected and integrated with the base 3 and a temporary shutter S is installed.

【0020】尚、姿勢調節ボルト17、17a …によりベー
ス台3を水平にする具体的な調節方法は、内外方向へ支
柱L、Laが傾斜する様な場合、掘削部Aに対し内側の2
個と外側の2個を夫々一組にして調節し、左右方向へ支
柱L、Laが傾斜する様な場合、支持脚部19の一方側の2
個と他方側の2個を夫々一組にして調節する様にしてい
る。
The specific method of adjusting the horizontal position of the base table 3 by the posture adjusting bolts 17, 17a is as follows.
When the support L and La are inclined in the left and right direction, the two pieces on the one side of the support leg 19 are adjusted.
The two pieces on the other side and the two pieces on the other side are adjusted as a set.

【0021】最後に、基礎杭体B、Ba上端部側における
地盤の凹部に土砂を埋め戻したり、コンクリートを打設
する。
Finally, earth and sand are buried in the concave portion of the ground on the upper end side of the foundation pile B and Ba, or concrete is poured.

【0022】又、ボルト挿通部位8が横長であれば、土
台梁2、2aに対するベース台3の位置が調節出来るた
め、仮設シャッターSの幅と一致する様にジョイント基
礎1、1aにおけるベース台3をスライドさせ位置決めし
て、その間隔距離を調節可能にしている。
If the bolt insertion portion 8 is horizontally long, the position of the base 3 with respect to the base beams 2 and 2a can be adjusted. Therefore, the base 3 in the joint bases 1 and 1a is adjusted to match the width of the temporary shutter S. Are slid and positioned so that the distance between them can be adjusted.

【0023】[0023]

【発明の効果】要するに本発明は、掘削部Aの山留め用
の多数の杭体P、Pa…のうち仮設シャッターSの基礎杭
体B、Baを構成する隣接する一対の杭体P、Paの上端部
間に一対の土台梁2、2aを並列架設すると共に、該土台
梁2、2a上に、ベース板11上面に一体固設した支持脚部
19上部に仮設シャッターSの支柱L、La下端部との連結
手段25を設けたベース台3を載架固設したので、土台梁
2、2a、ベース台3等を介して杭体P、Pa…に仮設シャ
ッターSを取付けることになるため、掘削部Aが敷地ぎ
りぎりであっても仮設シャッターSを設置出来、而も地
中深く打ち込まれた杭体P、Pa…が支柱L、Laの基礎杭
体B、Baになるため、仮設シャッターS専用の基礎を別
途構築する作業を行わずに仮設シャッターSを堅牢に設
置出来る。
In summary, the present invention provides a method of forming a pair of adjacent piles P, Pa constituting the foundation piles B, Ba of the temporary shutter S out of a number of piles P, Pa. A pair of base beams 2, 2a are installed in parallel between the upper ends, and support legs are integrally fixed on the base plate 11, on the base beams 2, 2a.
19 Since the base 3 provided with the connecting means 25 for connecting the column L of the temporary shutter S and the lower end of La on the upper part of the temporary shutter S is mounted and fixed, the piles P, Pa are connected via the base beams 2, 2a, the base 3 and the like. Since the temporary shutter S is to be attached to the excavation part A, the temporary shutter S can be installed even if the excavation part A is just near the site, and the piles P, Pa, which are deeply driven into the ground, are the foundations of the columns L, La. Since the piles B and Ba are used, the temporary shutter S can be firmly installed without the need to separately construct a foundation dedicated to the temporary shutter S.

【0024】又、土台梁2、2aの縦方向にボルト挿通部
位8を貫設すると共に、該ボルト挿通部位8を土台梁
2、2aの長手方向に長く形成したので、土台梁2、2aに
対しベース台3が、固定ボルト13及びナット16、16a を
緩めた状態において横スライド可能になると共に、土台
梁2、2aに対しベース台3を適宜箇所で固定出来、よっ
て杭体P、Pa…の打ち込みピッチに誤差があったり、指
定寸法でなくてもジョイント基礎1、1a間を仮設シャッ
ターSの幅に対応して調節出来、又ボルト挿通部位8内
に挿通した固定ボルト13、13a …をベース板11のボルト
孔12、12a …より突出させると共にかかる突端部にナッ
ト16、16a を螺嵌したので、ジョイント基礎1、1aを夫
々土台梁2、2aとベース台3に分解可能で、土台梁2、
2aを基礎杭体B、Baに取付けた後、土台梁2、2aにベー
ス台3を取付けることが出来るため、土台梁2、2aの取
付け時の作業空間が広くなって、基礎杭体B、Baへの土
台梁2、2aの取付け作業を容易化出来る。
Further, since the bolt insertion portion 8 is penetrated in the longitudinal direction of the base beams 2 and 2a, and the bolt insertion portion 8 is formed long in the longitudinal direction of the base beams 2 and 2a, On the other hand, the base 3 can be slid laterally with the fixing bolts 13 and the nuts 16 and 16a loosened, and the base 3 can be fixed to the base beams 2 and 2a at appropriate places. Can be adjusted according to the width of the temporary shutter S even if there is an error in the driving pitch of the bolts or the dimensions are not specified, and the fixing bolts 13, 13a. Since the bolts 12 and 12a of the base plate 11 are protruded from the base plate 11 and the nuts 16 and 16a are screwed into the protruding ends thereof, the joint foundations 1 and 1a can be disassembled into base beams 2 and 2a and a base base 3, respectively. Beam 2,
After attaching 2a to the foundation piles B and Ba, the base 3 can be attached to the foundation beams 2 and 2a. Therefore, the work space for attaching the foundation beams 2 and 2a is increased, and the foundation pile B and The work of attaching the base beams 2, 2a to Ba can be facilitated.

【0025】又、一対のみぞ形鋼4、4aを背合わせ状態
で対設すると共に、該みぞ形鋼4、4a両端部で基礎杭体
B、BaのフランジF、Faを挟着固定して土台梁2、2aと
成したので、ジョイント基礎1、1aの構成部品を既存の
形鋼と成すと共に更に小型化出来るため、運搬時に取り
扱い易いと共に、保管時の省スペース化を図ることが出
来、又みぞ形鋼4、4a間をボルト挿通部位8としたの
で、ボルト挿通部位8はみぞ形鋼4、4aの長手方向に長
くなるため、上記と同様に土台梁2、2aに対するベース
台3の固定位置を調節出来る。
Also, a pair of grooved steel members 4, 4a are opposed to each other in a back-to-back state, and the flanges F, Fa of the foundation pile B, Ba are sandwiched and fixed at both ends of the grooved steel members 4, 4a. Since the base beams 2 and 2a are formed, the components of the joint foundations 1 and 1a can be formed with the existing shaped steel and further downsized, so that they can be easily handled during transportation and space saving during storage. Further, since the portion between the grooved steels 4 and 4a is the bolt insertion portion 8, the bolt insertion portion 8 becomes longer in the longitudinal direction of the grooved steels 4 and 4a. The fixed position can be adjusted.

【0026】又、姿勢調節ボルト17、17a …をベース板
11の四隅部近傍の上方より垂直螺入して、その下端部を
ベース板11下面より出没自在と成したので、基礎杭体
B、Baが垂直に打ち込まれていなかったり、打ち込み量
に誤差が有る場合、連結された仮設シャッターSの支柱
L、Laは当然垂直にならないが、傾斜側の姿勢調節ボル
ト17、17a …を適宜螺入して下端部をベース板11下面よ
り突出させることにより、土台梁2、2aに対しベース台
3が独自に傾斜するため、土台梁2、2aが水平でなくと
もベース台3を独立して水平状態にすることが出来、そ
れに伴い支柱L、Laも垂直状態に出来、而も固定ボルト
13、13a …及び各固定ボルト13、13a …に螺嵌するナッ
ト16、16a により土台梁2、2aに対しベース台3を傾斜
状態のまま堅固に一体化出来、よって垂直でない基礎杭
体B、Baにも対応して仮設シャッターSを設置出来る等
その実用的効果甚だ大なるものである。
Further, the posture adjusting bolts 17, 17a.
Vertically screwed from above near the four corners of 11 and the lower end was made to be able to protrude and retract from the lower surface of the base plate 11, so the foundation piles B and Ba were not driven vertically or there was an error in the amount of driving. If there is, the pillars L and La of the connected temporary shutter S naturally do not become vertical, but by appropriately screwing in the posture adjusting bolts 17, 17a on the inclined side and projecting the lower end portion from the lower surface of the base plate 11, Since the base 3 is tilted independently with respect to the base beams 2 and 2a, the base 3 can be independently leveled even if the base beams 2 and 2a are not horizontal. Ready to use
.. And the fixing bolts 13, 13 a, and the nuts 16, 16 a screwed into the fixing bolts 13, 13 a. The practical effect is extremely large, such as the provision of a temporary shutter S corresponding to Ba.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係るジョイント基礎の平面図である。FIG. 1 is a plan view of a joint foundation according to the present invention.

【図2】図1の正面図である。FIG. 2 is a front view of FIG.

【図3】ジョイント基礎の設置状態を示す断面図であ
る。
FIG. 3 is a sectional view showing an installation state of a joint foundation.

【図4】仮設シャッターの設置状態を示す平面図であ
る。
FIG. 4 is a plan view showing an installation state of a temporary shutter.

【図5】仮設シャッターの拡大側面図である。FIG. 5 is an enlarged side view of a temporary shutter.

【図6】図5の縮小正面図である。FIG. 6 is a reduced front view of FIG. 5;

【図7】仮設シャッターの支柱を垂直に調節した状態を
示す要部正面図である。
FIG. 7 is a main part front view showing a state in which a column of a temporary shutter is vertically adjusted.

【符号の説明】[Explanation of symbols]

2、2a 土台梁 3 ベース台 4、4a みぞ形鋼 8 ボルト挿通部位 11 ベース板 12、12a … ボルト孔 13、13a … 固定ボルト 16、16a ナット 17、17a … 姿勢調節ボルト 19 支持脚部 25 連結手段 A 掘削部 B、Ba 基礎杭体 F、Fa フランジ L、La 支柱 P、Pa… 杭体 S 仮設シャッター 2, 2a Base beam 3 Base 4, 4a Grooved section 8 Bolt insertion part 11 Base plate 12, 12a… Bolt hole 13, 13a… Fixing bolt 16, 16a Nut 17, 17a… Posture adjusting bolt 19 Support leg 25 Connection Means A Excavated part B, Ba foundation pile F, Fa flange L, La column P, Pa ... Pile S Temporary shutter

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 掘削部における山留め用の多数の杭体の
内、仮設シャッターの基礎杭体を構成する隣接する一対
の杭体の上端部間に一対の土台梁を並列架設すると共
に、該土台梁上に、ベース板上面に固設した支持脚部上
部に仮設シャッターの支柱下端部との連結手段を設けた
ベース台を載架固設したことを特徴とする仮設シャッタ
ー用ジョイント基礎。
1. A pair of foundation beams are installed in parallel between upper ends of a pair of adjacent piles constituting a foundation pile of a temporary shutter among a plurality of piles for retaining in an excavation part, and the foundation is mounted on the foundation. A joint base for a temporary shutter, wherein a base table provided with a connecting means for connecting to a lower end of a column of a temporary shutter is mounted and fixed on a support leg fixed on an upper surface of a base plate on a beam.
【請求項2】 土台梁の縦方向にボルト挿通部位を貫設
すると共に、該ボルト挿通部位を土台梁の長手方向に長
く形成し、ボルト挿通部位内に挿通した固定ボルトをベ
ース板のボルト孔より突出させると共に、かかる突端部
にナットを螺嵌したことを特徴とする請求項1の仮設シ
ャッター用ジョイント基礎。
2. A bolt insertion portion penetrating in the longitudinal direction of the base beam, and the bolt insertion portion is formed long in the longitudinal direction of the base beam, and a fixing bolt inserted into the bolt insertion portion is provided in a bolt hole of the base plate. 2. The joint base for a temporary shutter according to claim 1, wherein said joint base further protrudes and a nut is screwed onto said protruding end.
【請求項3】 一対のみぞ形鋼を背合わせ状態で対設す
ると共に、該みぞ形鋼両端側で基礎杭体のフランジを挟
着固定して土台梁と成し、みぞ形鋼間をボルト挿通部位
としたことを特徴とする請求項2の仮設シャッター用ジ
ョイント基礎。
3. A pair of grooved steel members are provided facing each other in a back-to-back state, a flange of a foundation pile body is sandwiched and fixed at both ends of the grooved steel members to form a base beam, and bolts are formed between the grooved steel members. 3. The joint base for a temporary shutter according to claim 2, wherein the joint base is an insertion portion.
【請求項4】 姿勢調節ボルトをベース板の四隅部近傍
の上方より垂直螺入して、その下端部をベース板下面よ
り出没自在と成したことを特徴とする請求項1、2又は
3の仮設シャッター用ジョイント基礎。
4. A base plate according to claim 1, wherein the posture adjusting bolt is vertically screwed in from above the vicinity of the four corners of the base plate, and the lower end thereof is allowed to protrude and retract from the lower surface of the base plate. Joint base for temporary shutter.
JP16283994A 1994-06-20 1994-06-20 Joint foundation for temporary shutter Expired - Lifetime JP2876182B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16283994A JP2876182B2 (en) 1994-06-20 1994-06-20 Joint foundation for temporary shutter

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16283994A JP2876182B2 (en) 1994-06-20 1994-06-20 Joint foundation for temporary shutter

Publications (2)

Publication Number Publication Date
JPH084007A JPH084007A (en) 1996-01-09
JP2876182B2 true JP2876182B2 (en) 1999-03-31

Family

ID=15762229

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16283994A Expired - Lifetime JP2876182B2 (en) 1994-06-20 1994-06-20 Joint foundation for temporary shutter

Country Status (1)

Country Link
JP (1) JP2876182B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0964464B1 (en) 1996-12-16 2010-08-25 Daikin Industries, Ltd. Binder for rechargeable battery with nonaqueous electrolyte and battery electrode depolarizing mix prepared using the same
WO2010092976A1 (en) 2009-02-12 2010-08-19 ダイキン工業株式会社 Positive electrode mixture slurry for lithium secondary batteries, and positive electrode and lithium secondary battery that use said slurry
CN105604068B (en) * 2016-01-15 2017-08-25 北京工业大学 Base pit engineering serration type prestressing force encloses purlin and its construction method
CN109914833A (en) * 2019-03-25 2019-06-21 五冶集团上海有限公司 A kind of pit earthwork excavation stage dust-proof shed erection method

Also Published As

Publication number Publication date
JPH084007A (en) 1996-01-09

Similar Documents

Publication Publication Date Title
US8966855B1 (en) Foundation system for modular system smart buildings
JP6831714B2 (en) Tower crane foundation and tower crane
JP3175586B2 (en) Column and pile connection method
JP2876182B2 (en) Joint foundation for temporary shutter
JP3491116B2 (en) Pillar and pile joints
JP2000265574A (en) High floor type steel frame footing beam method
JP4446544B2 (en) Basic structure of a house
JP3612600B2 (en) Unit anchor and structural steel foundation beam
CN213233482U (en) Deep foundation pit supporting structure with waterproof function
JPS6137692Y2 (en)
JP2014231702A (en) Column base fixing structure of steel frame column
JP3246321B2 (en) Column and pile joint structure
JP3611876B2 (en) Column base and foundation beam structure
JP2860491B2 (en) Solid foundation using steel frame
JPH09151463A (en) Column-integrated column base anchoring foundation structire and work execution method therefor
JP2577973B2 (en) How to build a building with a basement
JPH1193273A (en) Unit building
JP7365518B1 (en) Panel support material and formwork structure using it
JP2900840B2 (en) How to build underground structures
JPH0921238A (en) Entrance structure in building construction site
JP3086384B2 (en) Foundation structure and foundation construction method
JP2577642B2 (en) How to build underground structures
JPH01214619A (en) Construction method for subsurface structure
JP4204702B2 (en) Building method and building structure
JP2649682B2 (en) Underground structure