JP2900840B2 - How to build underground structures - Google Patents
How to build underground structuresInfo
- Publication number
- JP2900840B2 JP2900840B2 JP7146047A JP14604795A JP2900840B2 JP 2900840 B2 JP2900840 B2 JP 2900840B2 JP 7146047 A JP7146047 A JP 7146047A JP 14604795 A JP14604795 A JP 14604795A JP 2900840 B2 JP2900840 B2 JP 2900840B2
- Authority
- JP
- Japan
- Prior art keywords
- floor
- beams
- concrete
- strut
- pca
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は、逆打支柱に接続される
切梁を、床面を構成するコンクリート内に埋設するよう
にした地下構造物の構築法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing an underground structure in which a cutting beam connected to a striking column is buried in concrete constituting a floor surface.
【0002】[0002]
【従来の技術】近年、地下構造物を構築するにあたっ
て、地下部分に逆打支柱を打設した後に地面を掘削して
この逆打支柱を露出させ、露出した逆打支柱に順次梁を
接続して地下架構を構築するようにした逆打工法がある
(特開平5−5312号公報参照)。また、この逆打工
法では例えば特開平3−72119号公報(E02D
29/04)に開示されるようにフラットスラブ構造を
適用したものが提案されている。2. Description of the Related Art In recent years, when constructing an underground structure, a reverse strut is installed in an underground portion, and then the ground is excavated to expose the reverse strut, and a beam is sequentially connected to the exposed reverse strut. There is a reverse striking method in which an underground frame is constructed by using a conventional method (see Japanese Patent Laid-Open No. 5-5312). Also, in this reverse driving method, for example, Japanese Patent Application Laid-Open No. 3-72119 (E02D)
29/04) to which a flat slab structure is applied has been proposed.
【0003】前記フラットスラブ構造は、厚肉状のキャ
ピタル部分を介して比較的薄肉で平坦なコンクリート床
を逆打支柱で支持するようになっており、前記公報では
地下を掘削しつつ、掘削面を利用してキャピタル部分お
よびフラットスラブを地下階毎に構築するようになって
いる。このように逆打工法にフラットスラブ構造を適用
することにより、通常の柱梁のラーメン架構と比べて階
高を低く抑えることができるので、掘削土量を削減して
工期の短縮化やコスト削減を図ることができる。In the flat slab structure, a relatively thin and flat concrete floor is supported by a back strut via a thick-walled capital portion. The capital part and the flat slab are constructed for each basement floor. By applying a flat slab structure to the reverse striking method in this way, the floor height can be kept lower than that of a normal column-beam ramen frame, so the amount of excavated soil is reduced and the construction period is shortened and costs are reduced. Can be achieved.
【0004】しかし、フラットスラブを順次上階から構
築していく逆打工法の掘削においては、フラットスラブ
の構築が完了する度に当該フラットスラブの下に掘削重
機を搬入して掘削していくことになるが、フラットスラ
ブに覆われたその下の空間での作業では、当該フラット
スラブが掘削重機による作業の障害となり、円滑且つ効
率よく掘削することができないという問題があった。[0004] However, in the excavation of the reverse striking method in which the flat slab is sequentially constructed from the upper floor, every time the construction of the flat slab is completed, a heavy excavator is carried under the flat slab and excavated. However, in the work in the space under the flat slab, there is a problem that the flat slab hinders the work by the heavy excavator, and the excavation cannot be performed smoothly and efficiently.
【0005】そこで、地下階を順次掘削して行く段階
で、その都度、各地下階の床部分としてフラットスラブ
を構築するのではなく、逆打支柱には切梁を井桁状に架
設するようにし、地下部分の掘削を完了した後に前記切
梁を埋設するようにフラットスラブを構築する方法が既
に本出願人によって出願されている。このように切梁を
用いることにより、上方から下方に向かって順次掘削し
ていく掘削作業段階では、格子状に組込まれた切梁の升
目部分が大きく開口されるので、掘削重機を自由度高く
操作することができて、フラットスラブに覆われた空間
で掘削するのに比べて、円滑且つ高効率で作業すること
ができる。Therefore, at the stage of sequentially excavating the basement floor, instead of constructing a flat slab as the floor part of each basement floor, a beam is erected on the back strut in the form of a girder. A method of constructing a flat slab so as to bury the girder after completing excavation of an underground part has already been filed by the present applicant. By using the girder in this way, in the excavation work stage where the excavation is performed sequentially from the upper side to the lower side, the square portion of the girder incorporated girder is greatly opened, so that the excavating heavy equipment can be flexibly mounted. It can be operated and can work smoothly and efficiently compared to excavating in a space covered by a flat slab.
【0006】[0006]
【発明が解決しようとする課題】しかしながら、かかる
従来の地下構造物の構築法にあっては、上述したよう
に、切梁を架設しながら地下部分を掘削していき、地下
部分を全て掘削完了した後に、切梁を埋設するようにフ
ラットスラブを構築するようにしているので、掘削され
た地下部分を支える支保工としての機能も必要となる切
梁としては、所定の強度を確保できるように、ある程度
の切梁のせい、ひいては断面係数等に反映する部材寸法
の設定が要求されることとなる。そして、高いせいとす
る必要がある切梁を上下に交差させて井桁状に組み合わ
せて逆打支柱の縦横方向に配設してフラットスラブ内に
埋設しようとすると、どうしてもフラットスラブが厚肉
化してしまい、ひいては地下階の階高を十分にとること
ができなくなったり、また切梁を埋設するために床に打
設するコンクリート量が増大してしまうという課題があ
った。However, in such a conventional method for constructing an underground structure, as described above, the underground portion is excavated while erection beams are erected, and excavation of the entire underground portion is completed. After that, the flat slab is constructed to bury the girder, so as a girder that also needs a function as a shoring to support the excavated underground part, it is necessary to ensure the predetermined strength Therefore, it is required to set the member dimensions to be reflected on the cross-section modulus and the like due to a certain amount of the cutting beam. And, when crossing up and down the cross beams that need to be made high and combining them in a girder shape and arranging them in the vertical and horizontal directions of the back strut and trying to bury them in the flat slab, the flat slab thickens inevitably As a result, there has been a problem that the floor height of the basement floor cannot be sufficiently set, and the amount of concrete cast on the floor for burying the girder increases.
【0007】そこで、本発明はかかる従来の課題に鑑み
て、逆打支柱に対して縦横に配置する切梁の井桁状交差
部分の高さを低くできるように構成して、この切梁を埋
設する床の薄肉化を達成するようにした地下構造物の構
築法を提供することを目的とする。In view of the above-mentioned problems, the present invention is designed so that the height of the cross-shaped cross section of the cross beam arranged vertically and horizontally with respect to the reverse strut can be reduced, and this cross beam is buried. It is an object of the present invention to provide a method of constructing an underground structure capable of achieving a thinned floor.
【0008】[0008]
【課題を解決するための手段】かかる目的を達成するた
めに本発明は、支持ブラケットを有する逆打支柱を打設
した後、PCaキャピタル版を前記逆打支柱に対し適宜
間隔をもって遊嵌して前記支持ブラケットに支持させ、
次に、前記逆打支柱に対して縦横に配置される切梁を同
一高さレベルの平面内で井桁状に組み合わせて前記PC
aキャピタル版上に載置し、これら切梁の下側を覆って
敷設した床型枠にコンクリートを打設して、このコンク
リート内に前記切梁を埋設することを特徴とする。In order to achieve the above object, according to the present invention, after a reverse strut having a support bracket is cast, a PCa capital plate is loosely fitted to the reverse strut at appropriate intervals. Supported by the support bracket,
Next, the cutting beams arranged vertically and horizontally with respect to the reverse strut are combined in a cross-girder shape within a plane at the same height level to form the PC.
(a) Concrete is placed on a floor form laid on a capital plate and laid so as to cover the lower side of these cut beams, and the cut beams are embedded in the concrete.
【0009】[0009]
【作用】以上の構成により本発明の地下構造物の構築法
は、地面に逆打支柱を打設した後、地下部分を掘削しつ
つこの逆打支柱を露出し、この逆打支柱の支持ブラケッ
トに支持させたPCaキャピタル版上に切梁を井桁状に
組み合わせて載置する。このとき、縦横に配置される切
梁を、同一高さレベルの平面内で井桁状に組み合わせる
ように構成したため、切梁自体には、これを所要の部材
寸法で構成することができて所定の剛性・強度を確保し
つつ、切梁の井桁状交差部分の高さを切梁のせい相当の
高さまで低くすることができ、切梁をコンクリート内に
埋設して構築されるフラットスラブの肉厚を極力薄くす
ることができる。したがって、階高を大きくとることが
できるとともに、打設コンクリート量も削減することが
できる。そしてこのような切梁を架設することにより、
もちろんこの切梁によって掘削途中の土水圧や地震力を
受け止めさせることができる。そして、前記切梁を順次
架設しつつ下方に向かって地下躯体を構築完了した後、
前記切梁の下側に床型枠を敷設してコンクリートを打設
し、このコンクリート内に切梁を埋設することにより床
が構築される。According to the above construction, the method of constructing an underground structure according to the present invention is as follows. After the back strut is cast on the ground, the back strut is exposed while excavating the underground portion, and the support bracket of the strut is supported. The beams are combined and placed in a cross-girder shape on the PCa capital slab supported by. At this time, since the cutting beams arranged vertically and horizontally are configured to be combined in a cross-girder shape within a plane at the same height level, the cutting beams themselves can be configured with required member dimensions and can be provided in a predetermined shape. While maintaining rigidity and strength, the height of the girder-shaped intersection of the girder can be reduced to the height equivalent to the girder, and the thickness of the flat slab constructed by embedding the girder in concrete Can be made as thin as possible. Therefore, the floor height can be increased and the amount of cast concrete can be reduced. And by erection such a beam,
Of course, these cut beams can stop the earth pressure and seismic force during excavation. Then, after completing the construction of the underground skeleton downward while sequentially building the cutting beams,
The floor is constructed by laying a floor formwork under the cut beams and casting concrete, and burying the cut beams in the concrete.
【0010】また、前記切梁はPCaキャピタル版を介
して逆打支柱に組み付けられるが、このPCaキャピタ
ル版は逆打支柱に適宜間隔をもって遊嵌されるため、逆
打支柱が建て込み誤差によって正規位置から位置ずれし
ている場合にも、前記遊嵌部分によって逆打支柱の建て
込み誤差を吸収して、現場での加工作業を必要とするこ
となく切梁を正規位置に簡単に架設することができる。[0010] Further, the cutting beam is assembled to the upright strut via a PCa capital plate, but since this PCa capital plate is loosely fitted to the upright strut at an appropriate interval, the upright strut is improperly installed due to a mounting error. Even if the position is displaced from the position, the loose fitting portion absorbs the error of setting up the back strut and allows the girder to be easily erected at the proper position without the need for machining work on site. Can be.
【0011】[0011]
【実施例】以下、本発明の実施例を添付図面を参照して
詳細に説明する。図1から図3は本発明にかかる地下構
造物の構築法の一実施例を示し、図1は地下構造物を構
築する手順を順を追って示す工程図、図2は切梁の井桁
状組み合わせ部分を拡大して示す要部平面図、図3は図
2の側面図である。Embodiments of the present invention will be described below in detail with reference to the accompanying drawings. 1 to 3 show an embodiment of a method of constructing an underground structure according to the present invention. FIG. 1 is a process chart showing a procedure for constructing an underground structure in order. FIG. FIG. 3 is an enlarged plan view of a main part, and FIG. 3 is a side view of FIG.
【0012】本実施例は基本的には、支持ブラケット1
8を有する逆打支柱12を打設した後、PCaキャピタ
ル版22を逆打支柱12に対し適宜間隔をもって遊嵌し
て支持ブラケット18に支持させ、次に、逆打支柱12
に対して縦横に配置される切梁14を同一高さレベルの
平面内で井桁状に組み合わせてPCaキャピタル版22
上に載置し、これら切梁14の下側を覆って敷設した床
型枠にコンクリートを打設して、このコンクリート内に
切梁14を埋設するようになっている。In this embodiment, basically, a support bracket 1
8, the PCa capital plate 22 is loosely fitted to the reverse strut 12 at appropriate intervals and supported by the support bracket 18, and then the reverse strut 12 is cast.
Of the PCa capital plate 22 by combining the cut beams 14 arranged in the vertical and horizontal directions in a grid pattern in a plane of the same height level.
Concrete is cast on a floor form which is placed on the top and laid so as to cover the lower side of these beams 14, and the beams 14 are embedded in the concrete.
【0013】図1は逆打支柱12の打設工程および切梁
14の架設工程を順を追って示し、まず、削孔16内に
逆打支柱12を打設する(同図a参照)。尚、本実施例
では地下二階となる地下構造物を例にとって示し、前記
逆打支柱12には、予め地下二階の天井高さ位置(地下
一階の床高さ位置)の下側に支持ブラケット18が突設
されている。また、前記逆打支柱12の一般部分には鋼
管12aが用いられると共に、上端部には内面にリブが
突設されたリブ付鋼管12bが用いられる。そして、打
設された逆打支柱12の内部にコンクリート20を打設
する(同図b参照)。FIG. 1 shows, in order, the process of placing the reverse strut 12 and the process of erection of the cutting beam 14. First, the reverse strut 12 is driven into the bore 16 (see FIG. 1a). In this embodiment, an underground structure serving as the second basement is shown as an example, and the reverse strut 12 is provided with support brackets in advance below the ceiling height position of the second basement (floor height position of the first basement). 18 are protruded. A steel pipe 12a is used for a general portion of the reverse strut 12 and a ribbed steel pipe 12b having a rib protruding from an inner surface is used for an upper end portion. Then, concrete 20 is cast inside the installed reverse strut 12 (see FIG. 2B).
【0014】次に、前記逆打支柱12の上端部からPC
aキャピタル版22を吊込む(同図c参照)と共に、逆
打支柱12の上方に地上柱24を接続し、この地上柱2
4に一階梁の接合部材26を建込む(同図d参照)。前
記PCaキャピタル版22は正方形状の薄肉PCa版と
して形成され、その中央部分には逆打支柱12に適宜間
隙をもって遊嵌される円形状乃至正方形状の挿通穴22
a(図2参照)が形成される。また、前記接合部材26
はH形鋼を十字状に結合して形成され、前記地上柱24
の下端部にこの接合部材26を固定し(図1e参照)、
この接合部材26に一階梁28を接続する(同図f参
照)。Next, from the upper end of the reverse strut 12, PC
a While the capital plate 22 is suspended (see FIG. 3C), a ground column 24 is connected above the reverse strut 12 and
A joint member 26 of the first floor beam is erected in 4 (see FIG. 4D). The PCa capital plate 22 is formed as a square thin PCa plate, and has a circular or square insertion hole 22 that is loosely fitted to the reverse strut 12 with an appropriate gap in the center thereof.
a (see FIG. 2) is formed. Further, the joining member 26
Is formed by connecting H-section steels in a cross shape,
This joining member 26 is fixed to the lower end portion of (see FIG. 1e),
The first floor beam 28 is connected to the joining member 26 (see FIG. 5F).
【0015】次に、地下一階部分を掘削して前記PCa
キャピタル版22を吊下げつつ下降し(同図g参照)、
この地下一階部分の掘削が完了した後に、図3にも示す
ようにPCaキャピタル版22を支持ブラケット18に
載置すると共に、このPCaキャピタル版22の上側に
地下一階の切梁14を組立てる(同図h参照)。このと
き、前記切梁14は図2にも示すようにx方向に配置さ
れる第1切梁14aとy方向に配置される第2切梁14
bとで構成され、これら第1,第2切梁14a,14b
は逆打支柱12を囲むように井桁状に組込まれる。尚、
前記第1,第2切梁14a,14bは逆打支柱12のス
パン中央部分で分断されており、それぞれが井桁状に組
込まれる際に、突合わされる第1,第2切梁14a,1
4bどうしが互いに接続されるようになっている。その
後、地下二階部分を掘削して地下二階の床面部分にマッ
トスラブ32を構築する(図1i参照)。Next, the first basement is excavated and the PCa
The capital plate 22 is suspended and lowered (see FIG. G).
After the excavation of the first basement floor is completed, the PCa capital plate 22 is placed on the support bracket 18 as shown in FIG. 3, and the underground first floor cutting beam 14 is assembled above the PCa capital plate 22. (See FIG. H). At this time, as shown in FIG. 2, the cut beam 14 is composed of a first cut beam 14a arranged in the x direction and a second cut beam 14 arranged in the y direction.
b, and these first and second cut beams 14a, 14b
Are assembled in a girder shape so as to surround the reverse strut 12. still,
The first and second cut beams 14a, 14b are divided at the center of the span of the back strut 12, and when they are assembled in a cross-girder shape, the first and second cut beams 14a, 14a are joined.
4b are connected to each other. Then, the mat slab 32 is constructed on the second basement floor by excavating the second basement (see FIG. 1I).
【0016】また、前記マットスラブ32を構築した
後、前記逆打支柱12の外周に柱主筋70などの鉄筋を
配筋して下層階から順に鉄骨鉄筋コンクリート柱34を
構築する。このとき、地下二階部分の鉄骨鉄筋コンクリ
ート柱34の配筋および柱型枠をセットすると同時に、
図2に示すように前記切梁14の下側に床型枠としての
床スラブ36を隙間なく敷設し、前記柱型枠および前記
床スラブ36上にコンクリート36aを打設することに
より、地下二階部分の鉄骨鉄筋コンクリート柱34およ
び地下一階のフラットスラブ38が構築される。このと
き、前記床スラブ36にコンクリート36aを打設する
際に、このコンクリート36a内に前記切梁14を埋設
するようになっている。また、前記地下二階部分の鉄骨
鉄筋コンクリート柱34内に前記支持ブラケット18が
埋設される。そして、前記フラットスラブ38を構築し
た後、地下一階部分の鉄骨鉄筋コンクリート柱34を構
築するようになっている。なお、柱型枠としてPCa柱
型枠を用いる場合には、PCaキャピタル版22及び接
合部材26の搬入に先行させて逆打支柱12に遊嵌して
おけばよい。また、前記床スラブ36端部が前記PCa
キャピタル版22に支持される際、図2,図3に示すよ
うにPCaキャピタル版22の外周に係止具40を取り
付けておき、この係止具40に床スラブ36の端部を係
止させるようになっている。After the mat slab 32 is constructed, a reinforcing steel bar such as a column main bar 70 is arranged on the outer periphery of the back strut 12 to construct a steel reinforced concrete column 34 in order from the lower floor. At this time, at the same time as setting the reinforcement and the column formwork of the steel reinforced concrete columns 34 on the second basement level,
As shown in FIG. 2, a floor slab 36 as a floor form is laid without gaps below the cutting beam 14, and concrete 36 a is cast on the column form and the floor slab 36, thereby forming a second basement floor. A part of steel reinforced concrete column 34 and a flat slab 38 of the first basement floor are constructed. At this time, when the concrete 36a is cast on the floor slab 36, the cutting beam 14 is embedded in the concrete 36a. The support bracket 18 is buried in a steel reinforced concrete column 34 on the second basement floor. Then, after the flat slab 38 is constructed, the steel reinforced concrete columns 34 on the first basement floor are constructed. When the PCa column form is used as the column form, the PCa capital plate 22 and the joining member 26 may be loosely fitted to the reverse strut 12 prior to the carry-in. Also, the end of the floor slab 36 is the PCa
When supported by the capital plate 22, a locking member 40 is attached to the outer periphery of the PCa capital plate 22 as shown in FIGS. 2 and 3, and the end of the floor slab 36 is locked by the locking member 40. It has become.
【0017】ここで、前記切梁14が井桁状に組み合わ
される際、図2に示したようにx方向に配置される第1
切梁14aをy方向に配置される第2切梁14bの配置
部分で分断し、分断した第1切梁14aの端面を第2切
梁14bの側面に突合わせることにより、これら第1,
第2切梁14a,14bを同一高さレベルの平面内で結
合するようになっている。Here, when the cutting beams 14 are assembled in a cross-girder shape, the first beams 14 are arranged in the x direction as shown in FIG.
The first beam 14a is divided at the portion where the second beam 14b is arranged in the y direction, and the end face of the first beam 14a is joined to the side surface of the second beam 14b.
The second cutting beams 14a and 14b are connected in a plane at the same height level.
【0018】前記第1切梁14aが前記第2切梁14b
に結合される際、第2切梁14bの両側に突合わされた
第1切梁14a,14aの上下両面に跨がって一対の連
結板42,42を配置し、これら連結板42,42と第
1切梁14aとをボルト44,ナット44aを介して固
定する。また、第1切梁14aの先端部両側に溶接した
三角状のブラケット46,46を第2切梁14bの両側
に付当てて、これらブラケット46,46と第2切梁1
4bとをボルト48,ナット48aを介して固定してあ
る。尚、第1,第2切梁14a,14bの結合は図4に
示すように、ブラケット46,46を用いることなく連
結板42,42のみによって固定してもよい。また、前
記第1,第2切梁14a,14bは、断面矩形状の鋼管
の内部にコンクリートが充填されて形成される鋼管コン
クリートとして構成される。The first beam 14a is connected to the second beam 14b.
When the first and second connecting beams 42a and 42b are connected to each other, a pair of connecting plates 42 and 42 are arranged over the upper and lower surfaces of the first cutting beams 14a and 14a butted on both sides of the second cutting beam 14b. The first cutting beam 14a is fixed via bolts 44 and nuts 44a. Also, triangular brackets 46, 46 welded to both ends of the first cut beam 14a are applied to both sides of the second cut beam 14b, and these brackets 46, 46 and the second cut beam 1 are attached.
4b is fixed via bolts 48 and nuts 48a. Incidentally, the connection of the first and second cut beams 14a, 14b may be fixed by only the connecting plates 42, 42 without using the brackets 46, 46 as shown in FIG. The first and second cut beams 14a and 14b are formed as steel pipe concrete formed by filling concrete inside a steel pipe having a rectangular cross section.
【0019】以上の構成により本実施例の地下構造物の
構築法にあっては、逆打支柱12の支持ブラケット18
にPCaキャピタル版22を支持させると共に、このP
Caキャピタル版22の上側に第1,第2切梁14a,
14bを井桁状に組み合わせて載置し、これら切梁14
が架設されることにより、地下階の掘削途中の土水圧や
地震力をこれら切梁14によって支持することができ
る。このとき、これら井桁状に組み合わせた切梁14は
格子状となって升目部分が大きく上方に開放されてい
る。従って、掘削重機の操作性の自由度を十分に確保す
ることができ、掘削作業の能率化、延いては工期の短縮
化が達成される。In the construction method of the underground structure according to the present embodiment having the above configuration, the support bracket 18 of the reverse strut 12 is used.
To support the PCa capital plate 22,
On the upper side of the Ca capital plate 22, the first and second cutting beams 14a,
14b are combined and placed in a cross-girder shape.
Is installed, the seismic beam 14 can support soil pressure and seismic force during excavation of the basement floor. At this time, the cut beams 14 combined in a cross-girder form have a lattice shape, and the squares are largely open upward. Therefore, the operability of the heavy excavator can be sufficiently secured, and the efficiency of the excavation work can be increased, and the construction period can be shortened.
【0020】そして、PCaキャピタル版22上に架設
された前記切梁14の下側に床スラブ36を配置して、
この床スラブ36を床型枠としてコンクリート36aを
打設することにより、この切梁14をコンクリート36
a内に埋設した状態でフラットスラブ36が構築され
る。そして特に、本実施例では井桁状に組込まれる第
1,第2切梁14a,14bをそれらの交差部分で水平
方向に同一レベルで結合しているため、これら切梁14
a,14bは所要の部材寸法による所定の剛性・強度で
構成しつつ、これら切梁14a,14bの交差部分での
上下方向の配置スペースが、従来のように重ね合わせて
交差させる場合に比較して半分となって著しく低くする
ことができる。したがって、切梁14をコンクリート3
6a内に埋設して構築されるフラットスラブ38は、そ
の肉厚を極力薄くすることができ、階高を十分に確保す
ることができるとともに、フラットスラブ38のコンク
リート36a打設量を大幅に減少して工費削減を図るこ
とができる。Then, a floor slab 36 is arranged below the cutting beam 14 erected on the PCa capital plate 22,
By using the floor slab 36 as a floor form and placing concrete 36a, the cut beam 14 is
The flat slab 36 is constructed in a state of being buried in a. In particular, in the present embodiment, the first and second cut beams 14a and 14b to be assembled in a girder shape are connected at the same level in the horizontal direction at their intersections.
While a and 14b are formed with predetermined rigidity and strength according to the required member dimensions, the vertical arrangement space at the intersection of these cutting beams 14a and 14b is compared with a conventional case where they are overlapped and intersected. Can be significantly reduced by half. Therefore, the cutting beam 14 is
The flat slab 38 buried and embedded in the 6a can be made as thin as possible, and the floor height can be sufficiently secured, and the amount of the flat slab 38 cast into the concrete 36a is greatly reduced. The construction cost can be reduced.
【0021】また、本実施例では前記切梁14がPCa
キャピタル版22を介して逆打支柱12に組付けられる
が、このPCaキャピタル版22は中央部に形成された
挿通穴22aを介して逆打支柱12に適宜間隙をもって
遊嵌される。従って、逆打支柱12が建込み誤差をもっ
て正規位置から位置ずれしている場合にも、前記挿通穴
22によって逆打支柱12の建込み誤差を吸収して、切
梁14を正規位置に架設することが可能となる。このた
め、切梁14を現場で切断する等の加工を施す必要がな
く、切梁14の建込み作業が著しく簡単化される。In this embodiment, the beam 14 is made of PCa.
The PCa capital plate 22 is attached to the reverse strut 12 with an appropriate gap through an insertion hole 22a formed in the center portion. Therefore, even when the reverse strut 12 is displaced from the normal position due to the installation error, the insertion error of the reverse strut 12 is absorbed by the insertion hole 22, and the cutting beam 14 is erected at the normal position. It becomes possible. For this reason, there is no need to perform processing such as cutting the cutting beam 14 on site, and the work of installing the cutting beam 14 is significantly simplified.
【0022】図5は他の実施例を示し、前記実施例と同
一構成部分に同一符号を付して重複する説明を省略して
述べる。即ち、この実施例では連結板42を介して第
1,第2切梁14a,14bを互いに結合する際に、こ
の連結板42を第1,第2切梁14a,14bの上面の
みに配置し、この連結板42を、PCaキャピタル版2
2に埋設してその上面から突出させたアンカーボルト7
1およびナット71aで固定するようになっている。ま
た、PCaキャピタル版22の周縁部において第1,第
2切梁14a,14bの上面に断面U字状の押え材50
を配置し、この押え材50とPCaキャピタル版22と
の間をボルト52,ナット52aを介して締め付けるよ
うになっている。更に、前記PCaキャピタル版22に
床スラブ36を支持する場合に、PCaキャピタル版2
2の外周縁上面にアングル材54を突設し、このアング
ル材54に対して床スラブ36の端部上面をボルト5
6,ナット56aを介して固定してある。FIG. 5 shows another embodiment, in which the same components as those in the previous embodiment are denoted by the same reference numerals, and the description thereof will be omitted. That is, in this embodiment, when the first and second cut beams 14a and 14b are connected to each other via the connection plate 42, the connection plate 42 is arranged only on the upper surfaces of the first and second cut beams 14a and 14b. The connecting plate 42 is connected to the PCa capital plate 2
Anchor bolt 7 buried in and protruded from its upper surface
1 and a nut 71a. A pressing member 50 having a U-shaped cross section is provided on the upper surfaces of the first and second cut beams 14a and 14b at the periphery of the PCa capital plate 22.
Is arranged, and the space between the pressing member 50 and the PCa capital plate 22 is tightened via the bolt 52 and the nut 52a. Further, when supporting the floor slab 36 on the PCa capital plate 22, the PCa capital plate 2
An angle member 54 protrudes from the upper surface of the outer peripheral edge of the floor 2 and the upper surface of the end of the floor slab 36 is
6, it is fixed via a nut 56a.
【0023】更に、本実施例では前記切梁14をフラッ
トスラブ38内に埋設することにより、スラブ配筋量を
削減することができると共に、キャピタル部分の構築
に、逆打支柱12の支持ブラケット18で支持されるP
Caキャピタル版22を用いたことにより、型枠および
支保工の使用を省略でき、省仮設化,省力化および工期
短縮化を図ることができる。Further, in this embodiment, by embedding the cutting beam 14 in the flat slab 38, the amount of slab arrangement can be reduced, and the support bracket 18 of the reverse strut 12 can be used to construct the capital portion. P supported by
By using the Ca capital plate 22, it is possible to omit the use of the formwork and the shoring, and it is possible to save the temporary construction, the labor and the construction period.
【0024】ところで、上述した各実施例では地下二階
となる構造物を例にとって示したが、これに限ることな
く地下三階以上の地下階を備えた構造物にあっても本発
明を適用できることはいうまでもない。In each of the embodiments described above, the structure having the second basement floor is taken as an example. However, the present invention is not limited to this and can be applied to a structure having three or more basement floors. Needless to say.
【0025】[0025]
【発明の効果】以上説明したように本発明の地下構造物
の構築法にあっては、縦横に配置される切梁を、同一高
さレベルの平面内で井桁状に組み合わせるように構成し
たため、切梁自体には、これを所要の部材寸法で構成す
ることができて所定の剛性・強度を確保しつつ、切梁の
井桁状交差部分の高さを切梁のせい相当の高さまで低く
することができ、切梁をコンクリート内に埋設して構築
されるフラットスラブの肉厚を極力薄くすることができ
る。したがって、階高を大きくとることができるととも
に、床のコンクリート打設量を大幅に減少して工費削減
を図ることができる。As described above, in the method of constructing an underground structure according to the present invention, the cut beams arranged vertically and horizontally are combined in a cross-girder shape within a plane at the same height level. The girder itself can be configured with the required member dimensions, and while maintaining the required rigidity and strength, the height of the girder-shaped intersection of the girder is reduced to the height equivalent to the girder. The thickness of a flat slab constructed by embedding a cutting beam in concrete can be reduced as much as possible. Therefore, the floor height can be increased, and the amount of concrete placed on the floor can be significantly reduced, thereby reducing the construction cost.
【0026】また、前記切梁はPCaキャピタル版を介
して逆打支柱に組付けられるが、このPCaキャピタル
版は逆打支柱に適宜間隙をもって遊嵌されるため、逆打
支柱が建込み誤差によって正規位置から位置ずれしてい
る場合にも、前記遊嵌部分によって逆打支柱の建込み誤
差を吸収して、現場での加工作業を必要とすることなく
切梁を正規位置に簡単に架設できるという各種優れた効
果を奏する。Further, the cutting beam is assembled to the upright strut via a PCa capital plate. Since this PCa capital plate is loosely fitted to the upright strut with an appropriate gap, the upright strut may be mounted due to a mounting error. Even in the case where the position is deviated from the normal position, the loose fitting portion absorbs the error in setting up the back strut, so that the cutting beam can be easily installed at the normal position without the need for processing work on site. It has various excellent effects.
【図1】本発明の一実施例を示す地下構造物を構築する
手順の工程図である。FIG. 1 is a process chart of a procedure for constructing an underground structure showing one embodiment of the present invention.
【図2】本発明の一実施例を示す切梁の井桁状組み合わ
せ部分を拡大した要部平面図である。FIG. 2 is an enlarged plan view of a main part of a cross-girder combination part of a cutting beam showing one embodiment of the present invention.
【図3】図2の側面図である。FIG. 3 is a side view of FIG. 2;
【図4】本発明の他の実施例を示す切梁の井桁状組み合
わせ部分を拡大した要部平面図である。FIG. 4 is an enlarged plan view of a main part of a cross-girder combination portion of a cutting beam according to another embodiment of the present invention.
【図5】本発明の他の実施例を示す切梁の井桁状組み合
わせ部分を拡大した要部断面側面図である。FIG. 5 is a cross-sectional side view of an essential part of an enlarged cross-girder combination portion of a cutting beam showing another embodiment of the present invention.
12 逆打支柱 14 切梁 14a 第1切梁 14b 第2切
梁 18 支持ブラケット 22 PCaキ
ャピタル版 22a 挿通穴 36 床スラブ 36a コンクリート 38 フラット
スラブReference Signs List 12 reverse strut 14 cut beam 14a first cut beam 14b second cut beam 18 support bracket 22 PCa capital plate 22a insertion hole 36 floor slab 36a concrete 38 flat slab
フロントページの続き (72)発明者 後閑 章吉 東京都千代田区神田司町2丁目3番地 株式会社大林組東京本社内 (72)発明者 水田 幹夫 東京都千代田区神田司町2丁目3番地 株式会社大林組東京本社内 (56)参考文献 特開 平3−72119(JP,A) 特開 平7−90979(JP,A) 特開 平5−148837(JP,A) 特開 平8−239907(JP,A) (58)調査した分野(Int.Cl.6,DB名) E02D 29/045 E04B 1/35 E21D 13/00 Continued on the front page (72) Inventor Shokichi Gokan 2-3-3 Kandaji-cho, Chiyoda-ku, Tokyo Obayashi-gumi Tokyo Head Office (72) Inventor Mikio Mizuta 2-3-3 Kandaji-cho, Chiyoda-ku, Tokyo Obayashi-gumi Tokyo Co., Ltd. In-house (56) References JP-A-3-72119 (JP, A) JP-A-7-90979 (JP, A) JP-A-5-148837 (JP, A) JP-A 8-239907 (JP, A) (58) Fields investigated (Int. Cl. 6 , DB name) E02D 29/045 E04B 1/35 E21D 13/00
Claims (1)
した後、PCaキャピタル版を前記逆打支柱に対し適宜
間隔をもって遊嵌して前記支持ブラケットに支持させ、
次に、前記逆打支柱に対して縦横に配置される切梁を同
一高さレベルの平面内で井桁状に組み合わせて前記PC
aキャピタル版上に載置し、これら切梁の下側を覆って
敷設した床型枠にコンクリートを打設して、このコンク
リート内に前記切梁を埋設することを特徴とする地下構
造物の構築法。After a reverse strut having a support bracket is cast, a PCa capital plate is loosely fitted to the reverse strut at an appropriate interval to be supported by the support bracket,
Next, the cutting beams arranged vertically and horizontally with respect to the reverse strut are combined in a cross-girder shape within a plane at the same height level to form the PC.
a a concrete structure is placed on a capital plate, concrete is poured into a floor form laid so as to cover the lower side of these cut beams, and the cut beams are embedded in the concrete. Construction method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP7146047A JP2900840B2 (en) | 1995-06-13 | 1995-06-13 | How to build underground structures |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP7146047A JP2900840B2 (en) | 1995-06-13 | 1995-06-13 | How to build underground structures |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH08338035A JPH08338035A (en) | 1996-12-24 |
JP2900840B2 true JP2900840B2 (en) | 1999-06-02 |
Family
ID=15398906
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP7146047A Expired - Lifetime JP2900840B2 (en) | 1995-06-13 | 1995-06-13 | How to build underground structures |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2900840B2 (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100856723B1 (en) * | 2007-03-28 | 2008-09-04 | 박무용 | System and method for underground downward construction using cantilever type steel frame |
CN108005113A (en) * | 2017-11-22 | 2018-05-08 | 中冶京诚工程技术有限公司 | Comprehensive pipe rack system |
CN114482530A (en) * | 2021-12-06 | 2022-05-13 | 贵州建工集团第四建筑工程有限责任公司 | Sinking type pit well and inverted ridge one-time integral forming construction structure and method |
-
1995
- 1995-06-13 JP JP7146047A patent/JP2900840B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH08338035A (en) | 1996-12-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4069509B2 (en) | Construction method of reverse struts in the outer periphery of underground excavation space | |
JP2831909B2 (en) | Connection structure of steel columns, piles and foundation beams | |
JP2001349065A (en) | Underground base isolating construction method for existing building | |
KR100673475B1 (en) | A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof | |
JP2900840B2 (en) | How to build underground structures | |
KR100912574B1 (en) | Retaining wall system using strut assembly and excavating method using the same | |
JPH0220767A (en) | Earthquake-proofing method for existing building | |
JP2000265574A (en) | High floor type steel frame footing beam method | |
JP2959436B2 (en) | How to build underground structures | |
JP2897663B2 (en) | How to build underground structures | |
JP3109038B2 (en) | Underground skeleton structure and construction method | |
JP3135495B2 (en) | Construction method of avalanche and rock fall protection fence and avalanche and rock fall protection fence | |
KR20210098162A (en) | Under ground structure using column steel pipe wall and construction method thereof | |
JP2940451B2 (en) | How to build underground structures | |
KR20210017645A (en) | Underground structure using strut and method construturing the same | |
KR102523155B1 (en) | Connecting structure of middle girder and construction method thereof | |
JPS63280153A (en) | Underground inverted lining method | |
KR102718378B1 (en) | Floor support system for top-down mehtod without soil pressure | |
JP3246321B2 (en) | Column and pile joint structure | |
JP3636754B2 (en) | Solid foundation structure and its construction method | |
JP5989597B2 (en) | Temporary seismic structure and its construction method during construction of seismic isolation for existing frame | |
JP3612761B2 (en) | Construction method of underground structure | |
JP2000027291A (en) | Structure of steel framed building | |
JPH08326073A (en) | Method for constructing underground structure | |
JP3005885B2 (en) | How to build the foundation of a structure |