CN108005113A - A kind of pipe gallery system - Google Patents

A kind of pipe gallery system Download PDF

Info

Publication number
CN108005113A
CN108005113A CN201711170179.5A CN201711170179A CN108005113A CN 108005113 A CN108005113 A CN 108005113A CN 201711170179 A CN201711170179 A CN 201711170179A CN 108005113 A CN108005113 A CN 108005113A
Authority
CN
China
Prior art keywords
pipe gallery
standard paragraphs
gallery system
node section
piping lane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711170179.5A
Other languages
Chinese (zh)
Inventor
陈思
王瑀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Capital Engineering and Research Incorporation Ltd
Zhongye Jingcheng Engineering Technology Co Ltd
Original Assignee
Zhongye Jingcheng Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongye Jingcheng Engineering Technology Co Ltd filed Critical Zhongye Jingcheng Engineering Technology Co Ltd
Priority to CN201711170179.5A priority Critical patent/CN108005113A/en
Publication of CN108005113A publication Critical patent/CN108005113A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Abstract

The present invention provides a kind of pipe gallery system, pipe gallery system includes:Standard paragraphs, the piping lane wall of standard paragraphs is steel structure;Node section, each node section connect at least one standard paragraphs, and the piping lane wall of node section is precast reinforced concrete structure or monolithic reinforced concrete structure.The pipe gallery system cost of the present invention is relatively low, is conducive to large-scale promotion, and the manufacture and installation requirement at node are relatively low.

Description

A kind of pipe gallery system
Technical field
The present invention relates to municipal works technical field, especially a kind of pipe gallery system.
Background technology
Current pipe gallery system, more using following two structure types:
The first is precast reinforced concrete structure, and piping lane standard paragraphs and piping lane node section are using assembled steel reinforced mixed Xtah Crude Clay structure, this structure is more demanding for mould and die accuracy, and prefabricated cost is higher, and large-scale promotion is restricted;
It is for second steel construction, piping lane standard paragraphs and piping lane node section use steel construction, the assembled at piping lane node Manufacture is higher with installation requirement, at node section of jurisdiction need to be turned, the measure such as reducing, therefore section of jurisdiction radius is more, assembly compared with For complexity, it is bolted a little also more, phenomena such as being easy to leak, and section of jurisdiction production required precision is higher.
The content of the invention
The object of the present invention is to provide a kind of pipe gallery system, its construction cost is relatively low, manufacture and installation at node It is it is required that relatively low.
To reach above-mentioned purpose, the present invention proposes a kind of pipe gallery system, it includes:Standard paragraphs, the standard paragraphs Piping lane wall is steel structure;Node section, each node section connect at least one standard paragraphs, the piping lane of the node section Wall is precast reinforced concrete structure or monolithic reinforced concrete structure.
Pipe gallery system as described above, wherein, pipeline is equipped with the standard paragraphs, use is connected with the node section In the fixing bracket and sliding support that support the pipeline.
Pipe gallery system as described above, wherein, the fixing bracket and the sliding support by pre-embedded steel slab with The piping lane wall connection of the node section.
Pipe gallery system as described above, wherein, it is equipped with pipeline valve, the pipeline valve and institute in the node section State pipeline connection.
Pipe gallery system as described above, wherein, the piping lane wall of the standard paragraphs is steel corrugated pipe structure.
Pipe gallery system as described above, wherein, the piping lane wall of the standard paragraphs is connected successively by multiple steel corrugated pipes Composition is connect, is bolted between adjacent two steel corrugated pipes.
Pipe gallery system as described above, wherein, the section configuration of the standard paragraphs is rectangle.
Pipe gallery system as described above, wherein, there is inspection space in the standard paragraphs.
Pipe gallery system as described above, wherein, the piping lane wall of the node section is monolithic reinforced concrete structure, institute The one end for stating the close node section of standard paragraphs is embedded in the piping lane wall of the node section.
Pipe gallery system as described above, wherein, the standard paragraphs are multiple, and the node section is multiple, the section Point section is alternately arranged with the standard paragraphs, or the node section is located at the crossover location of at least three standard paragraphs.
The characteristics of pipe gallery system of the present invention and advantage are:
1st, pipe gallery system of the invention, the piping lane wall of standard paragraphs use steel structure, and the piping lane wall of node section uses Precast reinforced concrete structure or monolithic reinforced concrete structure, with standard paragraphs in the prior art and node section using assembling Formula reinforced concrete structure is compared, and cost is relatively low, is conducive to large-scale promotion, is adopted with standard paragraphs in the prior art and node section Compared with steel construction, the manufacture at node of the invention and installation requirement are relatively low, without splicing steel tunnel segment, reduce section of jurisdiction installation And required precision;
2nd, the pipe gallery system in the present invention, fixing bracket and sliding support is connected in node section, due to node The piping lane wall of section uses precast reinforced concrete structure or monolithic reinforced concrete structure, can bear fixing bracket and slide branch The relatively high thrust that frame transmission comes, optimizes structure stress, and the piping lane wall of node section uses steel construction in the prior art, steel construction by In itself thin wall flexible design feature, it is more sensitive to bear thrust for bottom, fixing bracket and sliding support transmission can not be born The relatively high thrust come;
3rd, the pipe gallery system in the present invention, pipeline valve is arranged in node section, can reduce the piping lane of standard paragraphs Cross dimensions, standard paragraphs space layout is compacter, only need to consider pipeline itself installation requirement, and the prior art pacifies pipeline valve In standard paragraphs, piping lane standard paragraphs cross dimensions is larger.
Brief description of the drawings
The following drawings is only intended to, in doing schematic illustration and explanation to the present invention, not delimit the scope of the invention.Wherein:
Fig. 1 is the schematic diagram of one embodiment of the pipe gallery system of the present invention;
Fig. 2 is the schematic diagram of second embodiment of the pipe gallery system of the present invention;
Fig. 3 is the schematic diagram of the 3rd embodiment of the pipe gallery system of the present invention.
Main element label declaration:
1st, standard paragraphs;2nd, node section.
Embodiment
In order to which the technical features, objects and effects of the present invention are more clearly understood, now control illustrates this hair Bright embodiment.
As shown in Figure 1, Figure 2, Figure 3 shows, the present invention provides a kind of pipe gallery system, its standard for including being connected and connecting Section 1 and node section 2, the piping lane wall of standard paragraphs 1 is steel structure, and each node section 2 connects at least one standard paragraphs 1, node section 2 Piping lane wall be precast reinforced concrete structure (alternatively referred to as prefabricated reinforced concrete structure) or cast-in-situ steel reinforced concrete knot Structure.
The pipe gallery system of the present invention, the piping lane wall of standard paragraphs 1 use steel structure, and the piping lane wall of node section 2 uses Precast reinforced concrete structure or monolithic reinforced concrete structure, it is equal with the piping lane wall of standard paragraphs in the prior art and node section Compared using precast reinforced concrete structure, cost is relatively low, is conducive to large-scale promotion, with standard paragraphs in the prior art and section The piping lane wall of point section is compared using steel construction, and the manufacture at node of the invention and installation requirement are relatively low, without splicing steel Section of jurisdiction, reduces section of jurisdiction installation and required precision.
As shown in Figure 1, Figure 2, Figure 3 shows, further, standard paragraphs 1 are multiple that node section 2 is multiple, node section 2 and standard paragraphs 1 It is alternately arranged, or node section 2 is located at the crossover location of at least three standard paragraphs 1.For example, node section 2 can be two-way node, Node section 2 is connected between two standard paragraphs 1, and node section 2 can also be threeway node, and node section 2 is positioned at three standard paragraphs 1 At crossover location, and it is connected respectively with three standard paragraphs 1, node section 2 can also be four-way node, and node section 2 is positioned at four marks At the crossover location of quasi- section 1, and it is connected respectively with four standard paragraphs 1.
Further, the piping lane wall of node section 2 is monolithic reinforced concrete structure, standard paragraphs 1 (i.e. steel structure) it is close Cast inner membrance of the one end of node section 2 as monolithic reinforced concrete structure, is embedded in the piping lane wall of node section 2, that is, is constructing When, using one end of steel structure as concreting inner membrance, poured together.
Further, pipeline is equipped with the standard paragraphs 1 of pipe gallery system, is connected with the node section 2 of pipe gallery system For supporting the fixing bracket and sliding support of pipeline, fixing bracket and sliding support can not only support pipeline, moreover it is possible to resistance pipe The thrust of line, can especially resist the relatively high thrust of the particular pressure such as heating power pipeline and Large Diameter Pipeline pipeline.
Since the piping lane wall of node section 2 uses precast reinforced concrete structure or monolithic reinforced concrete structure, can hold The relatively high thrust come by fixing bracket and sliding support transmission, optimizes structure stress;And the piping lane wall of node section in the prior art Using steel construction, it is more sensitive that steel construction due to itself thin wall flexible design feature, for bottom bears thrust, can not bear to fix The relatively high thrust that stent and sliding support transmission come.
Further, fixing bracket and sliding support pass through pre-embedded steel slab and the piping lane of the node section 2 of pipe gallery system Wall connects, such as fixing bracket and sliding support are welded with pre-embedded steel slab.
Further, pipeline valve is equipped with the node section 2 of pipe gallery system, pipeline valve is connected with pipeline.Pass through Pipeline valve is arranged in node section 2, the piping lane cross dimensions of standard paragraphs 1 can be reduced, 1 space layout of standard paragraphs is compacter, It need to only consider pipeline itself installation requirement, and pipeline valve is installed in standard paragraphs by the prior art, piping lane standard paragraphs section ruler It is very little larger.
Further, the piping lane wall of the standard paragraphs 1 of pipe gallery system is steel corrugated pipe structure.For example, pipe gallery system The piping lane wall of the standard paragraphs 1 of system is sequentially connected by multiple steel corrugated pipes to be formed, and is passed through between adjacent two steel corrugated pipes It is bolted.If the piping lane wall of node section 2 uses monolithic reinforced concrete structure, construction when, using Steel Corrugated Pipes for Making steel pipe as Concreting inner membrance, is poured together, and steel corrugated pipe is not extracted after pouring molding.
Further, the piping lane wall of standard paragraphs 1 is sequentially connected by multiple steel corrugated pipes is formed, adjacent two steel ripples It is bolted between line pipe.
Further, the section configuration of the standard paragraphs 1 of pipe gallery system is rectangle, and scetion utilization is high, and the prior art Steel piping lane, the section configurations of standard paragraphs is pipeline overhead lifting shape, circle, semicircle or pyriform etc., and scetion utilization is lower than rectangle.
Further, there is inspection space in the standard paragraphs 1 of pipe gallery system.
The structure of the above-mentioned pipe gallery system of the present invention applies also for pipe-line system, and pipe-line system is farmland irrigating tube The large scale pipeline system such as road system or water conservancy transport pipe system, or between underground pedestrian crossing channel system, the underground space Interface channel system, underground antiaircraft tunnel system or the transport underground interface channel system such as culvert system.Refer to Fig. 1, figure 2nd, shown in Fig. 3, i.e. pipe-line system also includes standard paragraphs and the node section for being connected and connecting, each node section connection at least one A standard paragraphs, the duct wall of standard paragraphs is steel structure, and the duct wall of node section is precast reinforced concrete structure or cast-in-place Reinforced concrete structure.
The foregoing is merely the schematical embodiment of the present invention, the scope of the present invention is not limited to.It is any Those skilled in the art, the equivalent variations made on the premise of the design of the present invention and principle is not departed from and modification, should all Belong to the scope of protection of the invention.And it should be noted that the present invention each part be not limited in above-mentioned entirety should With, each technical characteristic described in specification of the invention can according to be actually needed selection one individually use or select it is multinomial Combine use, and therefore, the present invention covers the other combinations related with this case inventive point and concrete application in the nature of things.

Claims (10)

1. a kind of pipe gallery system, it is characterised in that the pipe gallery system includes:
Standard paragraphs, the piping lane wall of the standard paragraphs is steel structure;
Node section, each node section connect at least one standard paragraphs, and the piping lane wall of the node section is assembled steel Tendon concrete structure or monolithic reinforced concrete structure.
2. pipe gallery system as claimed in claim 1, it is characterised in that be equipped with pipeline, the node in the standard paragraphs The fixing bracket and sliding support for supporting the pipeline are connected with section.
3. pipe gallery system as claimed in claim 2, it is characterised in that the fixing bracket and the sliding support pass through Pre-embedded steel slab is connected with the piping lane wall of the node section.
4. pipe gallery system as claimed in claim 2, it is characterised in that pipeline valve is equipped with the node section, it is described Pipeline valve is connected with the pipeline.
5. pipe gallery system as claimed in claim 1, it is characterised in that the piping lane wall of the standard paragraphs is steel corrugated pipe Structure.
6. pipe gallery system as claimed in claim 5, it is characterised in that the piping lane wall of the standard paragraphs is by multiple steel ripples Line pipe is sequentially connected composition, is bolted between adjacent two steel corrugated pipes.
7. pipe gallery system as claimed in claim 1, it is characterised in that the section configuration of the standard paragraphs is rectangle.
8. pipe gallery system as claimed in claim 1, it is characterised in that there is inspection space in the standard paragraphs.
9. such as claim 1 to 8 any one of them pipe gallery system, it is characterised in that the piping lane wall of the node section is Monolithic reinforced concrete structure, one end of the close node section of the standard paragraphs are embedded in the piping lane wall of the node section.
10. such as claim 1 to 8 any one of them pipe gallery system, it is characterised in that the standard paragraphs are multiple, institute Node section is stated to be multiple, the node section is alternately arranged with the standard paragraphs, or the node section is located at least three marks At the crossover location of quasi- section.
CN201711170179.5A 2017-11-22 2017-11-22 A kind of pipe gallery system Pending CN108005113A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711170179.5A CN108005113A (en) 2017-11-22 2017-11-22 A kind of pipe gallery system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711170179.5A CN108005113A (en) 2017-11-22 2017-11-22 A kind of pipe gallery system

Publications (1)

Publication Number Publication Date
CN108005113A true CN108005113A (en) 2018-05-08

Family

ID=62053184

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711170179.5A Pending CN108005113A (en) 2017-11-22 2017-11-22 A kind of pipe gallery system

Country Status (1)

Country Link
CN (1) CN108005113A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08338035A (en) * 1995-06-13 1996-12-24 Ohbayashi Corp Construction method of underground structure
CN103775100A (en) * 2014-02-26 2014-05-07 华瀚管道系统科技有限公司 Prefabricated assembled urban comprehensive pipe gallery
CN105113543A (en) * 2015-09-22 2015-12-02 赵洪志 Assembled and combined cabin concrete structure of shallow-buried 0815-type underground comprehensive pipe gallery
CN205296222U (en) * 2016-01-12 2016-06-08 上海市城市建设设计研究总院 Two sides enlarge arrangement structure of utility tunnel pipeline branch mouth
CN205557566U (en) * 2016-02-29 2016-09-07 衡水益通管业股份有限公司 City underground steel construction utility tunnel
CN106759481A (en) * 2017-01-05 2017-05-31 周彩华 Guan Suicanggou formulas communication station
WO2017107372A1 (en) * 2015-12-21 2017-06-29 南京联众建设工程技术有限公司 Urban underground comprehensive steel pipe gallery
CN107268679A (en) * 2017-08-03 2017-10-20 中冶京诚工程技术有限公司 Remain silent section steel tubulation corridor and concrete cast-in-situ section connection structure
CN107313455A (en) * 2017-09-05 2017-11-03 北京建工土木工程有限公司 Cast-in-place single storehouse pipe gallery node and construction method with prefabricated combination
CN208009470U (en) * 2017-11-22 2018-10-26 中冶京诚工程技术有限公司 A kind of pipe gallery system

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08338035A (en) * 1995-06-13 1996-12-24 Ohbayashi Corp Construction method of underground structure
CN103775100A (en) * 2014-02-26 2014-05-07 华瀚管道系统科技有限公司 Prefabricated assembled urban comprehensive pipe gallery
CN105113543A (en) * 2015-09-22 2015-12-02 赵洪志 Assembled and combined cabin concrete structure of shallow-buried 0815-type underground comprehensive pipe gallery
WO2017107372A1 (en) * 2015-12-21 2017-06-29 南京联众建设工程技术有限公司 Urban underground comprehensive steel pipe gallery
CN205296222U (en) * 2016-01-12 2016-06-08 上海市城市建设设计研究总院 Two sides enlarge arrangement structure of utility tunnel pipeline branch mouth
CN205557566U (en) * 2016-02-29 2016-09-07 衡水益通管业股份有限公司 City underground steel construction utility tunnel
CN106759481A (en) * 2017-01-05 2017-05-31 周彩华 Guan Suicanggou formulas communication station
CN107268679A (en) * 2017-08-03 2017-10-20 中冶京诚工程技术有限公司 Remain silent section steel tubulation corridor and concrete cast-in-situ section connection structure
CN107313455A (en) * 2017-09-05 2017-11-03 北京建工土木工程有限公司 Cast-in-place single storehouse pipe gallery node and construction method with prefabricated combination
CN208009470U (en) * 2017-11-22 2018-10-26 中冶京诚工程技术有限公司 A kind of pipe gallery system

Similar Documents

Publication Publication Date Title
US10648152B2 (en) Box-type pipeline with circumferential obtuse angle connection
CN103643966B (en) A kind of assembling tunnel lining segment
WO2017071110A1 (en) Assembled-type underground pipe gallery
WO2018113488A1 (en) Pipe jacking and freezing system and construction method thereof
WO2017107372A1 (en) Urban underground comprehensive steel pipe gallery
CN106381885B (en) A kind of Underground Steel pipe gallery with skeleton
WO2017071113A1 (en) Cement-soil mixing pile protected underground pipe gallery
CN110029599A (en) Prefabricated culvert steel connecting structure and construction method
CN106351258A (en) All-prefabricated split steel concrete combined utility tunnel
CN103015310B (en) Sectional type concrete filled steel tube pier adopting non tension and shear limiting and construction method thereof
WO2008025200A1 (en) A prestressed concrete pipe unit with a steel socket and a steel spigot and a concrete pipe formed of such concrete pipe units
CN201954135U (en) Modular glass fiber reinforced plastics pipeline
CN103362517A (en) Assembled jacking pipe
CN208009470U (en) A kind of pipe gallery system
WO2017071111A1 (en) Underground pipe gallery protection structure
CN108005113A (en) A kind of pipe gallery system
CN107965324B (en) Assembled underpass tunnel
CN209816916U (en) Flexible pipe gallery prefabricated part
CN207846241U (en) Whole assembly overlapping box culvert
CN102207229B (en) Modular glass steel pipeline and method for repairing underground broken pipeline by using same
CN205804404U (en) A kind of novel prefabricated box culvert for pipe gallery
CN202989763U (en) Sectional type concrete filled steel tube pier adopting non-pulling resistant and non-shearing resistant limitation
CN112726667A (en) Semi-rigid assembly type comprehensive pipe gallery and construction method thereof
CN108724446A (en) A kind of pre-stress glass fibre reinforced plastic inner lining concrete push pipe and its preparation process
CN105971013A (en) Split mounting type comprehensive pipe rack

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180508