JP2000160686A - Composite structure of reinforced concrete column and steel frame beam, and its execution - Google Patents

Composite structure of reinforced concrete column and steel frame beam, and its execution

Info

Publication number
JP2000160686A
JP2000160686A JP10333208A JP33320898A JP2000160686A JP 2000160686 A JP2000160686 A JP 2000160686A JP 10333208 A JP10333208 A JP 10333208A JP 33320898 A JP33320898 A JP 33320898A JP 2000160686 A JP2000160686 A JP 2000160686A
Authority
JP
Japan
Prior art keywords
reinforced concrete
steel
concrete column
column
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP10333208A
Other languages
Japanese (ja)
Other versions
JP3586121B2 (en
Inventor
Katsuyoshi Itagaki
勝善 板垣
Yoshihiro Fujita
佳宏 藤田
Katsuhisa Nishimura
勝尚 西村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP33320898A priority Critical patent/JP3586121B2/en
Publication of JP2000160686A publication Critical patent/JP2000160686A/en
Application granted granted Critical
Publication of JP3586121B2 publication Critical patent/JP3586121B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a composite structure of a reinforced concrete column and a steel frame beam and its execution method in which a welding quantity can be reduced and workability can be improved, and the fitting work of the steel frame beam to the reinforcing concrete column can be rationalized, and the construction works can be advanced without need to wait for completion of the reinforced concrete column and hence, the construction period can be shortened. SOLUTION: A columnar temporary erection member 3a to be embedded in a reinforced concrete column 1 is erected in a construction position of the reinforcing concrete column 1, while temporarily supporting a plurality of steel frame beams 5a, 5b, 5c crossing with each other on the reinforced concrete column 1, and connection members 7a, 7b are arranged between mutual steel frame beams 5a, 5b, 5c crossing with each other on the columnar temporary erection member 3a. The connection members 7a, 7b and the steel frame beams 5a, 5b, 5c are connected to each other by high tension bolts 13, 19 in order to mutually connect steel frame beams 5a, 5b, 5c.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、鉄筋コンクリート
柱と、H形鋼などの鉄骨梁との混合構造およびその施工
方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a mixed structure of a reinforced concrete column and a steel beam such as an H-section steel, and a method for constructing the mixed structure.

【0002】[0002]

【従来の技術】従来、鉄筋コンクリート柱と鉄骨梁との
仕口部においては、柱上で互いに直交する鉄骨梁同士を
溶接により接合したり、あるいはふさぎ板やダイヤフラ
ムを備えて柱コンクリートを拘束する仕口部材を溶接に
より予め作成し、柱上に載置したこの仕口部材に対して
直交する鉄骨梁を溶接接合することにより、柱と梁を結
合するようにしていた。仕口部材を用いた鉄骨梁の施工
を例にとって詳述すると、鉄骨材の製作工場で仕口部材
や鉄骨梁を別個に加工し溶接により組み立ててこれらを
現場に搬入し、現場では大型のクレーンなどを用いて鉄
筋コンクリート柱上に仕口部材を設置するとともに、さ
らに鉄骨梁を揚重して当該仕口部材に対し溶接接合する
ようにしていた。仕口部材についてはまた図7に示すよ
うに、先組みした柱用鉄筋と接合しておく場合もある。
この図示例にあっても、交差する梁部分同士が仕口部材
に対して溶接接合されている。
2. Description of the Related Art Conventionally, in a connection portion between a reinforced concrete column and a steel beam, a steel beam which is orthogonal to each other on the column is welded or provided with a covering plate or a diaphragm to restrain the column concrete. The mouth member was prepared in advance by welding, and the pillar and the beam were joined by welding a steel beam orthogonal to the connection member placed on the pillar. Taking the construction of steel beams using connection members as an example, in detail, the connection members and steel beams are separately processed in a steel frame manufacturing plant, assembled by welding, and then brought to the site. A connecting member is installed on a reinforced concrete column by using such a method, and a steel beam is further lifted and welded to the connecting member. As shown in FIG. 7, the connection member may be connected to a pre-assembled column reinforcing bar in some cases.
Also in the illustrated example, the crossing beam portions are welded to the connection member.

【0003】他方、鉄骨梁を鉄筋コンクリート柱に結合
する施工方法は、主に以下の2通りであった。コンク
リートを打設して鉄筋コンクリート柱を先行して構築
し、打設した柱コンクリートが十分に硬化した段階で柱
間に鉄骨梁を掛け渡していく。鉄骨梁を仮設支保工で
支えて梁の構築箇所に予め設置しておき、次いで鉄筋コ
ンクリート柱および上階床スラブの型枠を組み、その後
これら型枠にコンクリートを打設することで仕口部周り
へも一挙にコンクリートを充填する。いずれにあって
も、鉄筋コンクリート柱の構築を一階層ずつ進めていく
ものであった。
[0003] On the other hand, there are mainly two construction methods for connecting a steel beam to a reinforced concrete column. Concrete is cast and reinforced concrete columns are built in advance, and when the cast concrete is sufficiently hardened, steel beams are bridged between the columns. The steel beam is supported by temporary supports and installed in advance at the beam construction site, and then the reinforced concrete columns and the upper-floor slab formwork are assembled. Fill concrete at once. In each case, the construction of reinforced concrete columns was advanced one layer at a time.

【0004】[0004]

【発明が解決しようとする課題】上述したように従来の
鉄骨梁の施工にあっては、鉄骨梁同士の接合、あるいは
仕口部材の作成や交差する鉄骨梁の仕口部材への接合に
あたって、溶接を多用していた。このように、鉄骨梁を
用いる混合構造を構築するにあたっては従来溶接作業が
中心となっていて、この溶接接合では開先加工など手間
がかかり作業が煩雑であるとともに、コストもかかると
いう難点があった。また溶接接合部の溶接品質を確認す
るために溶接検査を実施する必要もあった。さらに現場
での溶接作業は熟練を要するとともに、また雨の日や風
の強い日には行うことができないため、工期が天候に左
右されるという課題もあった。
As described above, in the conventional construction of steel beams, when connecting steel beams, forming joint members, or joining intersecting steel beams to joint members, He used a lot of welding. As described above, the conventional welding work has been mainly used to construct a mixed structure using steel beams, and this welding connection has the disadvantage that the work is complicated, such as beveling, and the work is complicated, and the cost is high. Was. It was also necessary to carry out a welding inspection to confirm the welding quality of the welded joint. Furthermore, welding work on site requires skill and cannot be performed on a rainy day or a windy day, so that there is a problem that the construction period depends on the weather.

【0005】他方、鉄骨梁が接合される鉄筋コンクリー
ト柱の構築については、上記いずれの方法であっても柱
を一階層ずつ構築していくため、以下のような問題があ
った。すなわち、鉄骨梁を揚重するためのクレーンの使
用が、の方法では、同じ階層の複数の鉄筋コンクリー
ト柱それぞれで柱コンクリートが硬化するのを待った上
での使用となり、それぞれの鉄筋コンクリート柱の構築
完了時期に応じてクレーンを移動して揚重作業を行う必
要がある。またの方法でも、同じ階層の鉄骨梁をすべ
て仮設支保工上に載置した後は、柱および床スラブの型
枠工事やこれらへのコンクリート打設によりすべての鉄
筋コンクリート柱の構築が完了してその上の階層に工事
が移るまでは、クレーンを使用することがない。このよ
うに従来の鉄筋コンクリート柱の施工方法ではクレーン
の待機時間が長引く場合が多く、クレーンを高い稼働効
率で運用することが難しかった。
[0005] On the other hand, regarding the construction of a reinforced concrete column to which a steel beam is to be joined, there are the following problems since the columns are constructed one layer at a time by any of the above methods. In other words, the use of a crane to lift steel beams requires the use of a plurality of reinforced concrete columns on the same level, after the column concrete has hardened, and the completion of construction of each reinforced concrete column. It is necessary to move the crane according to the conditions and carry out the lifting work. Also, after all the steel beams of the same level are placed on the temporary support, the construction of all the reinforced concrete columns is completed by forming the columns and floor slabs and placing concrete in them. No crane will be used until construction moves to the upper level. As described above, in the conventional method of constructing a reinforced concrete column, the waiting time of the crane is often prolonged, and it has been difficult to operate the crane with high operation efficiency.

【0006】さらに、特にの方法では、先行して構築
した鉄筋コンクリート柱の上に鉄骨梁を載せて接合する
ので、搭載した梁とその直下の柱頂部との隙間へのコン
クリート充填作業が煩雑であるという問題もあった。
Furthermore, in the method of the present invention, since a steel beam is placed on a reinforced concrete column constructed in advance and joined, the work of filling concrete into the gap between the mounted beam and the column top immediately below it is complicated. There was also a problem.

【0007】そこで、本発明は係る従来の課題に鑑み
て、溶接作業量を削減できて施工性を改善できるととも
に、鉄筋コンクリート柱に対する鉄骨梁の取り付けの合
理化を図って、鉄筋コンクリート柱の構築完了を待つこ
となく構築作業を進めることができて、これらにより工
期短縮を達成できる鉄筋コンクリート柱と鉄骨梁の混合
構造およびその施工方法を提供することを目的とする。
In view of the above, the present invention can reduce the amount of welding work, improve workability, and rationalize the attachment of steel beams to reinforced concrete columns, and wait for the completion of the construction of reinforced concrete columns. It is an object of the present invention to provide a mixed structure of a reinforced concrete column and a steel beam and a method of constructing the same, whereby construction work can be carried out without any trouble and the construction period can be shortened.

【0008】[0008]

【課題を解決するための手段】上記課題を解決するため
に、請求項1に係る鉄筋コンクリート柱と鉄骨梁の混合
構造は、鉄筋コンクリート柱の構築箇所に、該鉄筋コン
クリート柱上で交差する複数の鉄骨梁を仮支持しつつ、
該鉄筋コンクリート柱内部に埋め込まれる柱状仮設部材
を設けるとともに、該柱状仮設部材上で互いに交差する
上記鉄骨梁相互間に接続部材を配設し、上記鉄骨梁同士
を接続するために、上記接続部材と上記鉄骨梁とを高力
ボルトで互いに接続したことを特徴とする。
In order to solve the above-mentioned problems, a mixed structure of a reinforced concrete column and a steel beam according to claim 1 comprises a plurality of steel beams crossing on a reinforced concrete column at a construction site of the reinforced concrete column. While temporarily supporting
Providing a columnar temporary member embedded inside the reinforced concrete column, arranging a connection member between the steel beam beams intersecting each other on the columnar temporary member, and connecting the steel member beams with each other. The steel beams are connected to each other by high-strength bolts.

【0009】このように鉄筋コンクリート柱の構築箇所
に設けられ、当該柱内部に埋め込まれる柱状仮設部材に
よって鉄骨梁を仮支持する構造であるから、別途仮設支
保工を設ける必要なく、かつまた柱コンクリートの硬化
による鉄筋コンクリート柱の構築完了を待つことなく、
当該柱状仮設部材を利用して鉄骨梁の建て方を先行する
ことができる。すなわち、鉄筋コンクリート柱の構築完
了に必要な型枠工事やコンクリート打設作業、並びにそ
の養生期間とは切り離して、クレーン等の揚重機器を利
用した鉄骨梁の建て方を、同階層だけでなく、柱状仮設
部材上に載置した鉄骨梁上にさらに柱状仮設部材を設置
することで上層階へも先行して進めていくことができ、
これにより一階層毎に進められる鉄筋コンクリート柱の
構築作業の進捗にかかわらず、鉄骨梁の建て方作業を短
い期間で先行して完了させることができ、工期短縮を図
ることができる。またこれに伴い、鉄骨梁を揚重するた
めの揚重機器を集中的に稼働させることができて、その
稼働効率を向上することができ、鉄骨梁の揚重作業完了
後は当該クレーンを自由に転用することもできる。
As described above, since the steel beam is temporarily supported by the columnar temporary member embedded in the reinforced concrete column and embedded in the column, there is no need to provide a temporary support, and the column concrete is not required. Without waiting for the completion of construction of reinforced concrete columns by hardening,
It is possible to precede how to build a steel beam using the columnar temporary member. In other words, apart from the formwork and concrete casting work required to complete the construction of reinforced concrete columns, and the curing period, the method of building steel beams using lifting equipment such as cranes, not only at the same level, By installing a columnar temporary member on the steel beam placed on the columnar temporary member, it is possible to proceed ahead to the upper floor,
Thus, regardless of the progress of the reinforced concrete column construction work progressing for each layer, the construction work of the steel beam can be completed in advance in a short period, and the construction period can be shortened. Along with this, lifting equipment for lifting steel beams can be intensively operated, and its operation efficiency can be improved. After completion of lifting work on steel beams, the crane can be freely operated. Can also be diverted to

【0010】また、鉄骨梁を仮支持して当該鉄骨梁の建
て方を先行できる柱状仮設部材を備えていることから、
鉄筋コンクリート柱を構築するためにコンクリートを打
設する際には、柱梁仕口部周りに一挙にコンクリートを
打ち込むことができ、当該仕口部周りのコンクリートの
充填性を改善でき、この面からも工期短縮を図ることが
できる。
[0010] Further, since the columnar temporary member is provided which can temporarily support the steel beam and precede the method of building the steel beam,
When laying concrete to construct a reinforced concrete column, concrete can be poured at once around the beam-to-column connection, and the concrete filling around the connection can be improved. The construction period can be shortened.

【0011】さらに、鉄骨梁同士を、接続部材を介して
高力ボルトで接続するようにしていて、これにより煩雑
でコストがかかるとともに熟練度が要求され、かつまた
天候にも左右される溶接作業を削減できて施工の省力
化、工期短縮を図ることができる。
Further, the steel beams are connected to each other by high-strength bolts via connecting members, which requires a complicated and costly technique, requires a high degree of skill, and is affected by the weather. Can be reduced, and labor saving and shortening of construction period can be achieved.

【0012】また請求項2に係る鉄筋コンクリート柱と
鉄骨梁の混合構造は、前記鉄骨梁に、前記鉄筋コンクリ
ート柱を取り囲んで帯状部材を設けたことを特徴とす
る。
Further, a mixed structure of a reinforced concrete column and a steel beam according to claim 2 is characterized in that a band-shaped member is provided on the steel beam so as to surround the reinforced concrete column.

【0013】この帯状部材によって鉄骨梁近傍の鉄筋コ
ンクリート柱の柱コンクリートを拘束することができ
て、従来の仕口部材を用いた構造と遜色のない強度の仕
口部を形成することができる。
The band-shaped member can restrain the column concrete of the reinforced concrete column in the vicinity of the steel beam, and can form a joint having a strength comparable to the structure using the conventional joint.

【0014】他方、請求項3に係る鉄筋コンクリート柱
と鉄骨梁の混合構造の施工方法は、まず、鉄筋コンクリ
ート柱の構築箇所に、該鉄筋コンクリート柱上で交差す
る複数の鉄骨梁を仮支持する柱状仮設部材を設け、次い
で、該柱状仮設部材上で互いに交差する上記鉄骨梁相互
間に接続部材を配設し、次いで、上記鉄骨梁同士を接続
するために、上記接続部材と上記鉄骨梁とを高力ボルト
で互いに接合して鉄骨建て方を先行し、その後、該鉄骨
建て方を完了した上記柱状仮設部材の周りに、柱用鉄筋
を配筋するとともにコンクリートを打設して鉄筋コンク
リート柱を構築するようにしたことを特徴とする。
According to a third aspect of the present invention, there is provided a method for constructing a mixed structure of a reinforced concrete column and a steel beam, wherein a temporary columnar member for temporarily supporting a plurality of steel beams intersecting on the reinforced concrete column at a construction site of the reinforced concrete column. Then, a connecting member is arranged between the steel beams intersecting each other on the columnar temporary member, and then, in order to connect the steel beams, the connecting member and the steel beams are subjected to high strength. A steel reinforced concrete column is constructed by joining together with bolts to precede the steel erection method, and then arranging a reinforcing bar for the column and placing concrete around the columnar temporary member having completed the steel erection method. It is characterized by the following.

【0015】このような施工方法にあっては、鉄筋コン
クリート柱の構築箇所に、鉄骨梁を仮支持する柱状仮設
部材を予め設置するようにしていて、これにより請求項
1と同様に、別途仮設支保工を設ける必要なく、かつま
た柱コンクリートの硬化による鉄筋コンクリート柱の構
築完了を待つことなく、当該柱状仮設部材を利用して鉄
骨梁の建て方を先行することができて、一階層毎に進め
られる鉄筋コンクリート柱の構築作業の進捗にかかわら
ず、鉄骨梁の建て方作業を上層階へ向かって先行して完
了させることができ、工期短縮を図ることができる。ま
たこれに伴い、請求項1と同様に、鉄骨梁を揚重するた
めの揚重機器の稼働効率を向上できる。
In this construction method, a temporary columnar member for temporarily supporting a steel beam is previously installed at a location where the reinforced concrete column is to be constructed. It is possible to precede the method of constructing a steel beam using the temporary column members without the need to provide a construction work and without waiting for the completion of the construction of the reinforced concrete column due to the hardening of the column concrete, and the process can be carried out one layer at a time. Regardless of the progress of the construction of the reinforced concrete columns, the construction work of the steel beams can be completed in advance toward the upper floor, and the construction period can be shortened. Accordingly, similarly to the first aspect, the operation efficiency of the lifting equipment for lifting the steel beam can be improved.

【0016】他方、鉄筋コンクリート柱の構築作業につ
いては、先行する鉄骨梁の建て方が完了したものから順
次、柱状仮設部材の周りに従来の方法によって施工する
ことができ、施工作業上、柱の構築と鉄骨梁の建て方と
が複雑に交錯することがなく、この面からも工期短縮を
図ることができる。
On the other hand, in the construction work of the reinforced concrete columns, the construction of the pillars can be sequentially carried out by the conventional method around the columnar temporary members, starting from the construction of the preceding steel beam is completed. The construction of the steel beam does not intersect complicatedly, and the construction period can be shortened from this aspect as well.

【0017】また、柱状仮設部材で鉄骨梁を仮支持して
当該鉄骨梁の建て方を先行するようにしていて、鉄筋コ
ンクリート柱を構築するためにコンクリートを打設する
際には請求項1と同様に、柱梁仕口部周りに一挙にコン
クリートを打ち込むことができ、工期短縮を図ることが
できる。
Further, the steel beam is temporarily supported by the columnar temporary member so as to precede the method of building the steel beam, and when the concrete is poured to construct the reinforced concrete column, it is the same as the first embodiment. In addition, concrete can be poured at once around the beam-column connection, and the construction period can be shortened.

【0018】さらに、鉄骨梁同士を、接続部材を介して
高力ボルトで接続するようにしていて、これにより請求
項1と同様に、施工の省力化、工期短縮を図ることがで
きる。
Furthermore, the steel beams are connected to each other by high-strength bolts via connecting members, thereby saving labor and shortening the construction period as in the first aspect.

【0019】[0019]

【発明の実施の形態】以下に本発明の好適な実施の形態
について、添付図面を参照しつつ詳細に説明する。図1
〜図4に示すように、鉄筋コンクリート柱1の構築箇所
には当該鉄筋コンクリート柱1相当の高さを有する柱状
仮設部材3aが立設される。図示例では、この柱状仮設
部材3aとしてH形鋼が示されている。この柱状仮設部
材3aは、鉄筋コンクリート柱1上で交差する複数の鉄
骨梁5a、5b、5cを仮支持できる強度を有し、かつ
最終的には鉄筋コンクリート柱1内部に埋め込まれるよ
うになっている。従ってこの柱状仮設部材3aとして
は、その上に載置される鉄骨梁5a、5b、5cを仮に
支持できる強度を備えていれば十分で、構造強度を増強
するような強度までは要求されず、かつまた鋼製に限ら
ず、コンクリート製やプラスチック製など材質も問われ
ない。さらに、平断面形状も円形や方形など、形態は問
われない。要するに、本実施形態の柱状仮設部材3a
は、いわゆるSRC構造を構成する部材とは異なる。ま
た、この柱状仮設部材3aは各階層の一本一本の鉄筋コ
ンクリート柱1それぞれに対して適用されるもので、従
って図示したように、ある階層の鉄骨梁5a、5b、5
cの直下並びにその直上に配置される。
Preferred embodiments of the present invention will be described below in detail with reference to the accompanying drawings. FIG.
As shown in FIG. 4, a temporary columnar member 3a having a height equivalent to that of the reinforced concrete column 1 is erected at the location where the reinforced concrete column 1 is constructed. In the illustrated example, an H-section steel is shown as the columnar temporary member 3a. The columnar temporary member 3a has a strength capable of temporarily supporting a plurality of steel beams 5a, 5b, 5c intersecting on the reinforced concrete column 1, and is finally embedded in the reinforced concrete column 1. Therefore, it is sufficient for the columnar temporary member 3a to have a strength capable of temporarily supporting the steel beams 5a, 5b, 5c placed thereon, and it is not required to have a strength that enhances the structural strength. Further, the material is not limited to steel, but may be concrete or plastic. Further, the shape of the flat cross section is not limited, such as circular or square. In short, the columnar temporary member 3a of the present embodiment
Are different from the members constituting the so-called SRC structure. The columnar temporary member 3a is applied to each reinforced concrete column 1 of each layer, and therefore, as shown in the figure, the steel beams 5a, 5b, 5
It is arranged immediately below and directly above c.

【0020】このように最終的には鉄筋コンクリート柱
1内部に埋設される柱状仮設部材3aの頂部には、当該
鉄筋コンクリート柱1の構築前の段階で当該柱状仮設部
材3aに仮支持させてH形鋼などの鉄骨梁5a、5b、
5cが載置される。図示例では、一方向の第1鉄骨梁5
aが梁貫通型の配置で柱状仮設部材3a上に載置される
とともに、この第1鉄骨梁5aと交差する第2鉄骨梁5
b、5cは当該第1鉄骨梁5aを挟む配置で柱状仮設部
材3a上に載置される。図示例にかかわらず、柱状仮設
部材直上で、縦横4本の鉄骨梁を互いに突き合わせる配
置であってもよいことはもちろんである。また図示例に
あっては、建物中央部であって鉄骨梁が縦横に交差する
箇所を示しているが、建物側面や隅部においてもそれら
に対応する配置で鉄骨梁が柱状仮設部材上に載置され
る。
As described above, the top of the columnar temporary member 3a finally buried inside the reinforced concrete column 1 is temporarily supported by the columnar temporary member 3a at the stage before the reinforced concrete column 1 is constructed, and the H-shaped steel is formed. Such as steel beams 5a, 5b,
5c is placed. In the illustrated example, the first steel beam 5
a is placed on the columnar temporary member 3a in a beam penetrating arrangement, and the second steel beam 5 intersecting with the first steel beam 5a
Reference numerals b and 5c are mounted on the columnar temporary member 3a so as to sandwich the first steel beam 5a. Regardless of the illustrated example, it is a matter of course that four vertical and horizontal steel beams may be arranged to abut each other immediately above the columnar temporary member. In the example shown in the drawing, the steel beams are placed on the columnar temporary members in the center of the building, where the steel beams intersect vertically and horizontally. Is placed.

【0021】このようにして柱状仮設部材3a上で交差
する鉄骨梁5a、5b、5c同士の接続構造と、またこ
れら鉄骨梁5a、5b、5cを柱状仮設部材3a上に仮
支持する構造について説明する。
The connection structure of the steel beams 5a, 5b, 5c intersecting on the columnar temporary member 3a and the structure of temporarily supporting the steel beams 5a, 5b, 5c on the columnar temporary member 3a will be described. I do.

【0022】第1鉄骨梁5aの直下に位置するH形鋼で
なる柱状仮設部材3aには、その上端部に後述する下ス
プライスプレート7aを取り付けるための一組の支持ブ
ラケット9aが設けられる。図示するようにこれら支持
ブラケット9aは断面L字形状に形成され、柱状仮設部
材3aのウエブ両面および一対のフランジに対しそれら
の一側面がボルト・ナット11aによりそれぞれ接合さ
れて、これら支持ブラケット9aの他側面が柱状仮設部
材の頂部とほぼ面一となるように配置される。
The columnar temporary member 3a made of H-shaped steel located immediately below the first steel beam 5a is provided with a set of support brackets 9a at the upper end thereof for attaching a lower splice plate 7a described later. As shown in the figure, these support brackets 9a are formed in an L-shaped cross section, and one side of each of them is joined to both sides of the web of the columnar temporary member 3a and a pair of flanges by bolts and nuts 11a, respectively. The other side surface is arranged so as to be substantially flush with the top of the columnar temporary member.

【0023】このようにして柱状仮設部材3aに取り付
けられた支持ブラケット9a上には、第1鉄骨梁5aを
挟んで配置される第2鉄骨梁5b、5cの配置方向に沿
って形成された接続部材としての下スプライスプレート
7aがボルト・ナット11aを介して取り付けられる。
図示例ではこの下スプライスプレート7aは、鉄筋コン
クリート柱1の柱芯と一致する柱状仮設部材3a位置で
幅広であって、当該柱芯位置から離れるに従って順次に
幅狭になる、ほぼ菱形形状に形成されている。この下ス
プライスプレート7aには、支持ブラケット9aとの接
合用のボルト孔に加えて、これに第1鉄骨梁5aおよび
第2鉄骨梁5b、5cを接続するための高力ボルト13
を挿通するボルト孔が適宜位置に形成されている。
On the support bracket 9a attached to the temporary columnar member 3a in this manner, the connection formed along the direction of disposition of the second steel beams 5b, 5c arranged with the first steel beam 5a interposed therebetween. A lower splice plate 7a as a member is attached via bolts and nuts 11a.
In the illustrated example, the lower splice plate 7a is formed in a substantially rhombic shape that is wide at the position of the columnar temporary member 3a coinciding with the column core of the reinforced concrete column 1 and gradually narrows as the distance from the column center position increases. ing. The lower splice plate 7a has high-strength bolts 13 for connecting the first steel beam 5a and the second steel beams 5b, 5c to the lower splice plate 7a in addition to the bolt holes for joining with the support bracket 9a.
Are formed at appropriate positions.

【0024】そしてこの下スプライスプレート7a上に
上記第1鉄骨梁5aおよび第2鉄骨梁5b、5cが載置
される。図示例にあってはさらに、第1鉄骨梁5aのウ
エブ両面には、第2鉄骨梁5b、5cが接続される位置
に当該第2鉄骨梁5b、5cのウエブに向かって突出さ
せて、一対の板状の接続用ブラケット15が予め溶接接
合されている。そしてこれら接続用ブラケット15およ
び第2鉄骨梁5b、5cのウエブにも、両者を高力ボル
ト17で接続するためのボルト孔が適宜位置に形成され
ている。
The first steel beam 5a and the second steel beams 5b, 5c are placed on the lower splice plate 7a. In the illustrated example, further, on both surfaces of the web of the first steel beam 5a, the two steel beams 5b, 5c are projected toward the web of the second steel beams 5b, 5c at positions where the second steel beams 5b, 5c are connected. Are connected in advance by welding. Bolt holes for connecting the connection bracket 15 and the second steel beams 5b and 5c with high-strength bolts 17 are formed at appropriate positions in the webs.

【0025】そしてまたさらに、互いに接続されるこれ
ら第1鉄骨梁5aおよび第2鉄骨梁5b、5c上には、
上記下スプライスプレート7aと同一形状で同一配置の
上スプライスプレート7bが載置され、これら上スプラ
イスプレート7bにも第1鉄骨梁5aおよび第2鉄骨梁
5b、5cを接続するための高力ボルト19を挿通する
ボルト孔が適宜位置に形成されている。第1鉄骨梁5a
および第2鉄骨梁5b、5cには、もちろん上・下スプ
ライスプレート7a、7bのボルト孔に対応するボルト
孔が形成されている。
Further still, on these first steel beam 5a and second steel beam 5b, 5c connected to each other,
An upper splice plate 7b having the same shape and the same arrangement as the lower splice plate 7a is placed, and a high-strength bolt 19 for connecting the first steel beam 5a and the second steel beam 5b, 5c also to the upper splice plate 7b. Are formed at appropriate positions. First steel beam 5a
Bolt holes corresponding to the bolt holes of the upper and lower splice plates 7a and 7b are formed in the second steel beams 5b and 5c.

【0026】そして、第1鉄骨梁5aおよび第2鉄骨梁
5b、5cとこれら間に配設した上・下スプライスプレ
ート7a、7bとをそれぞれ相互に高力ボルト13,1
9で接続するとともに、接続用ブラケット15を介して
第1鉄骨梁5aと第2鉄骨梁5b、5cとを高力ボルト
17で直接接続することにより、支持ブラケット9aを
介して柱状仮設部材3a上に鉄骨梁5a、5b、5cを
仮支持しつつ、鉄骨梁5a、5b、5c同士を当該柱状
仮設部材3a上で接続するようになっている。
Then, the first steel beam 5a and the second steel beam 5b, 5c and the upper and lower splice plates 7a, 7b disposed therebetween are connected to the high-strength bolts 13, 1 respectively.
9, the first steel beam 5a and the second steel beam 5b, 5c are directly connected to each other by the high-strength bolt 17 via the connection bracket 15, so that the first steel beam 5a and the second steel beam 5b, 5c are connected to the columnar temporary member 3a via the support bracket 9a. While temporarily supporting the steel beams 5a, 5b, 5c, the steel beams 5a, 5b, 5c are connected to each other on the columnar temporary member 3a.

【0027】図示例にあっては、上スプライスプレート
7b上にさらに一組の支持ブラケット9bを介して柱状
仮設部材3bの下端部を接合する様子が示されている。
このように上層階の鉄骨梁に対して同様の構成で柱状仮
設部材等を建て込んで仮支持を行うことにより、鉄骨梁
の建て方を、鉄筋コンクリート柱等のコンクリート打設
工事に先行させることができる。
In the illustrated example, the lower end of the columnar temporary member 3b is joined to the upper splice plate 7b via a pair of support brackets 9b.
In this way, by temporarily installing columnar temporary members etc. with the same configuration for the upper story steel beams and providing temporary support, it is possible to precede the method of building steel beams before concrete casting work such as reinforced concrete columns it can.

【0028】他方、柱状仮設部材3aに対しては、当該
柱状仮設部材3aが仮支持する鉄骨梁5a、5b、5c
の建て方が完了した後に、通常の施工方法で鉄筋コンク
リート柱1の構築が行われる。すなわち、鉄骨梁5a、
5b、5cの仮支持が完了した柱状仮設部材3aの周り
に、柱主筋21や剪断補強筋23などの柱用鉄筋を配筋
するとともに現場型枠を建て込み、その後型枠内部へと
コンクリートを打設することにより鉄筋コンクリート柱
1を構築することができる。
On the other hand, for the columnar temporary members 3a, the steel beams 5a, 5b, 5c temporarily supported by the columnar temporary members 3a are provided.
After the completion of the construction, the reinforced concrete columns 1 are constructed by a normal construction method. That is, the steel beam 5a,
Around the columnar temporary member 3a for which the temporary support of 5b and 5c has been completed, reinforcing bars for columns such as the column main reinforcement 21 and the shear reinforcement 23 are arranged and a formwork is erected, and then concrete is placed inside the formwork. By casting, the reinforced concrete column 1 can be constructed.

【0029】図5には、上記実施形態の鉄筋コンクリー
ト柱1と鉄骨梁5a、5b、5cの混合構造における応
力伝達の様子が示されている。図示するように、柱梁仕
口部においては、鉄骨梁5a、5b、5cと鉄筋コンク
リート柱1とを連結する関係で鉄筋コンクリート柱1内
部に埋設した柱状仮設部材3a、3bやスプライスプレ
ート7a、7b、さらには高力ボルト13,17,19
等が配設されているので、建物自重による長期荷重や、
地震などの短期荷重が作用した際、これら柱状仮設部材
3a、3bやスプライスプレート7a、7b等が有効な
支圧効果を発揮して、鉄骨梁5a、5b、5cから鉄筋
コンクリート柱1への応力伝達効果を高く確保すること
ができる。
FIG. 5 shows a state of stress transmission in the mixed structure of the reinforced concrete column 1 and the steel beams 5a, 5b, 5c of the above embodiment. As shown in the figure, at the beam-to-column connection, the columnar temporary members 3a, 3b and the splice plates 7a, 7b, which are embedded in the reinforced concrete column 1 in a relation of connecting the steel beams 5a, 5b, 5c and the reinforced concrete column 1, are provided. Furthermore, high strength bolts 13, 17, 19
Etc. are arranged, long-term load due to the building's own weight,
When a short-term load such as an earthquake is applied, the columnar temporary members 3a, 3b and the splice plates 7a, 7b exert an effective bearing effect, and transmit stress from the steel beams 5a, 5b, 5c to the reinforced concrete column 1. High effect can be secured.

【0030】以上のように構成される鉄筋コンクリート
柱と鉄骨梁の混合構造の施工手順について説明すると、
まず、鉄筋コンクリート柱1の構築箇所に柱状仮設部材
3aを建て込む。この建て込み作業では、上述したよう
に図示されない下階の柱状仮設部材で仮支持した鉄骨梁
上の上スプライスプレートにボルト・ナットで接合した
支持ブラケットを利用する。すなわち、支持ブラケット
にボルト・ナットを介して柱状仮設部材3aの下端部を
接合することにより、下階の鉄骨梁上に柱状仮設部材3
aを立設する。また、基礎コンクリート上に柱状仮設部
材を建て込む場合は図示しないが、当該基礎コンクリー
トに支持ブラケットを固定し、これに対して柱状仮設部
材を接合すればよい。
The construction procedure of the mixed structure of reinforced concrete columns and steel beams constructed as described above will be described.
First, a columnar temporary member 3a is erected at a location where the reinforced concrete column 1 is constructed. In this installation work, as described above, a support bracket joined by a bolt and a nut to an upper splice plate on a steel beam temporarily supported by a columnar temporary member (not shown) on the lower floor is used. That is, by joining the lower end of the columnar temporary member 3a to the support bracket via bolts and nuts, the columnar temporary member 3a is placed on the steel beam on the lower floor.
a is erected. Further, although not shown, when the columnar temporary member is erected on the foundation concrete, a support bracket may be fixed to the foundation concrete and the columnar temporary member may be joined thereto.

【0031】次いで、立設した柱状仮設部材3aの上端
部にボルト・ナット11aを介して支持ブラケット9a
を接合するとともに、この支持ブラケット9a上に、互
いに交差する上記第1鉄骨梁5aおよび第2鉄骨梁5
b、5c相互間にわたって、下スプライスプレート7a
をボルト・ナット13により接合する。その後、当該下
スプライスプレート7a上に第1鉄骨梁5aと第2鉄骨
梁5b、5cを載置する。この際、鉄骨梁5a、5b、
5cを単材として扱うことができるので、クローラーク
レーンなどの小型のクレーンを用いて鉄骨梁の吊り上げ
を行うことができる。
Next, a support bracket 9a is attached to the upper end of the standing columnar temporary member 3a via a bolt / nut 11a.
And the first steel beam 5a and the second steel beam 5 crossing each other on the support bracket 9a.
b, 5c, lower splice plate 7a
Are joined by bolts and nuts 13. Thereafter, the first steel beam 5a and the second steel beams 5b, 5c are placed on the lower splice plate 7a. At this time, the steel beams 5a, 5b,
Since 5c can be handled as a single material, the steel beam can be lifted using a small crane such as a crawler crane.

【0032】次いで、高力ボルト13によってこれら鉄
骨梁5a、5b、5cを下スプライスプレート7aに接
続するとともに、第1鉄骨梁5aに接合した接続用ブラ
ケット15に第2鉄骨梁5b、5cのウエブを高力ボル
ト17を介して接続する。そしてさらに、これら鉄骨梁
5a、5b、5c上に上スプライスプレート7bを載せ
て、これらを互いに高力ボルト19で接続する。これに
より、互いに交差する第1および第2鉄骨梁5a、5
b、5cが柱状仮設部材1a上に仮支持されて、当該箇
所の鉄骨建て方が完了する。
Next, the steel beams 5a, 5b, 5c are connected to the lower splice plate 7a by the high-strength bolts 13, and the webs of the second steel beams 5b, 5c are connected to the connecting bracket 15 joined to the first steel beam 5a. Are connected via a high-strength bolt 17. Further, the upper splice plate 7b is placed on the steel beams 5a, 5b, 5c, and these are connected to each other by the high-strength bolts 19. Thereby, the first and second steel beams 5a, 5
b and 5c are temporarily supported on the columnar temporary member 1a, and the method of building the steel frame at that location is completed.

【0033】上記手順による鉄骨建て方は、鉄筋コンク
リート柱の構築の進捗状況にかかわらず、それに先行さ
せて順次下層階から上層階へと施工を進めることができ
る。
Regarding the method of building a steel frame by the above procedure, regardless of the progress of the construction of the reinforced concrete columns, the construction can be sequentially advanced from the lower floor to the upper floor prior to the construction.

【0034】他方、鉄筋コンクリート柱1については詳
しくは図示しないけれども、柱状仮設部材3aの周りに
柱用鉄筋である柱主筋21や剪断補強筋23を配筋する
とともに、その外側を現場型枠で取り囲み、その内部へ
現場打ちコンクリートを打設して鉄筋コンクリート柱1
を構築する。この場合、柱型枠工事と並行して鉄骨梁5
a、5b、5c間にスラブ型枠を配置するようにすれ
ば、スラブから柱梁仕口部周り、並びに柱にわたって一
挙にコンクリートを流し込むことができて、コンクリー
ト打設作業の効率を向上できる。
On the other hand, although not shown in detail, the reinforced concrete column 1 is provided with a column main reinforcing member 21 and a shear reinforcing bar 23, which are column reinforcing bars, around the columnar temporary member 3a, and the outside thereof is surrounded by an on-site formwork. , Cast in-place concrete into the inside, and reinforced concrete column 1
To build. In this case, the steel beam 5
If the slab formwork is arranged between a, 5b, and 5c, concrete can be poured at once from the slab to around the beam-to-column connection, and over the columns, and the efficiency of concrete placing work can be improved.

【0035】以上説明したように、本実施形態に係る鉄
筋コンクリート柱1と鉄骨梁5a、5b、5cの混合構
造およびその施工方法にあっては、鉄筋コンクリート柱
1内部に埋め込まれる柱状仮設部材3aによって鉄骨梁
5a、5b、5cを仮支持するようにしたので、別途仮
設支保工を設ける必要なく、かつまた柱コンクリートの
硬化による鉄筋コンクリート柱1の構築完了を待つこと
なく、当該柱状仮設部材3aを利用して鉄骨梁5a、5
b、5cの建て方を先行して施工できる。すなわち、鉄
筋コンクリート柱1の構築完了に必要な型枠工事やコン
クリート打設作業、並びにその養生期間とは切り離し
て、クレーン等の揚重機器を利用した鉄骨梁5a、5
b、5cの建て方を、同階層だけでなく、柱状仮設部材
3a上に載置した鉄骨梁5a、5b、5c上にさらに柱
状仮設部材3bを設置することで上層階へも先行して進
めていくことができ、これにより一階層毎に進められる
鉄筋コンクリート柱の構築作業の進捗にかかわらず、鉄
骨梁の建て方作業を短い期間で先行して完了させること
ができ、工期短縮を図ることができる。またこれに伴
い、鉄骨梁を揚重するための揚重機器を集中的に稼働さ
せることができて、その稼働効率を向上することがで
き、鉄骨梁の揚重作業完了後は当該クレーンを自由に転
用することもできる。
As described above, in the mixed structure of the reinforced concrete column 1 and the steel beams 5a, 5b, 5c according to the present embodiment and the construction method thereof, the steel column is provided by the columnar temporary member 3a embedded inside the reinforced concrete column 1. Since the beams 5a, 5b and 5c are temporarily supported, the temporary temporary members 3a can be used without having to provide a separate temporary support and waiting for the completion of the construction of the reinforced concrete column 1 by hardening of the column concrete. Steel beams 5a, 5
b, 5c can be constructed in advance. That is, apart from the formwork and concrete casting work necessary for completing the construction of the reinforced concrete column 1 and the curing period, the steel beams 5a, 5a, 5c using lifting equipment such as cranes are used.
b, 5c can be built not only on the same level, but also on the upper story by installing the columnar temporary members 3b on the steel beams 5a, 5b, 5c placed on the columnar temporary members 3a. Therefore, regardless of the progress of the reinforced concrete column construction work progressing one layer at a time, the construction work of steel beams can be completed in advance in a short period of time, and the construction period can be shortened. it can. Along with this, lifting equipment for lifting steel beams can be intensively operated, and its operation efficiency can be improved. After completion of lifting work on steel beams, the crane can be freely operated. Can also be diverted to

【0036】また、鉄骨梁5a、5b、5cを仮支持し
て当該鉄骨梁5a、5b、5cの建て方を先行できる柱
状仮設部材3aを備えていることから、鉄筋コンクリー
ト柱1を構築するためにコンクリートを打設する際に
は、柱梁仕口部周りに一挙にコンクリートを打ち込むこ
とができ、当該仕口部周りのコンクリートの充填性を改
善でき、この面からも工期短縮を図ることができる。
Further, since the columnar temporary members 3a which temporarily support the steel beams 5a, 5b, 5c and can precede how to build the steel beams 5a, 5b, 5c are provided, it is necessary to construct the reinforced concrete column 1. When pouring concrete, concrete can be poured at once around the beam-column joint, the filling property of the concrete around the joint can be improved, and the construction period can be shortened from this aspect as well. .

【0037】さらに、鉄骨梁5a、5b、5c同士を、
スプライスプレート7a、7bや接続用ブラケット15
を介して高力ボルト13,19,17で接続するように
していて、これにより煩雑でコストがかかるとともに熟
練度が要求され、かつまた天候にも左右される溶接作業
を削減できて施工の省力化、工期短縮を図ることができ
る。
Further, the steel beams 5a, 5b, 5c are
Splice plates 7a and 7b and connection bracket 15
Are connected by high-strength bolts 13, 19, and 17, which requires complicated and costly work, requires a high degree of skill, and reduces welding work that is affected by the weather, thereby saving labor in construction. And shortening the construction period.

【0038】さらにまた、鉄筋コンクリート柱1の構築
作業については、先行する鉄骨梁5a、5b、5cの建
て方が完了したものから順次、柱状仮設部材3aの周り
に従来の方法によって施工することができ、施工作業
上、柱1の構築と鉄骨梁5a、5b、5cの建て方とが
複雑に交錯することがなく、この面からも工期短縮を図
ることができる。
Further, the construction work of the reinforced concrete column 1 can be carried out by a conventional method around the columnar temporary member 3a in order from the construction of the preceding steel beams 5a, 5b, 5c is completed. In the construction work, the construction of the column 1 and the construction of the steel beams 5a, 5b, 5c do not intersect in a complicated manner, and the construction period can be shortened from this aspect as well.

【0039】また本実施形態にあっては、柱状仮設部材
3a、3bとしてH形鋼を利用していて、当該H形鋼を
鉄筋コンクリート柱相当の高さに切断するとともにこれ
にボルト孔を形成するという簡単な加工で容易に現場に
適用することができる。また支持ブラケット9a、9b
やスプライスプレート7a、7bの形態も単純であり、
加工が容易で施工性に富む。さらに、スプライスプレー
ト7a、7bを柱芯で幅広な菱形形状に形成したので柱
梁仕口部周りへのスプライスプレート7a、7bの突出
が僅かであり、当該柱梁仕口部周りへのコンクリート打
設を妨げることがなく、コンクリートの充填性を確保で
きる。第1鉄骨梁5aと第2鉄骨梁5b、5c同士の接
続は主に、上・下スプライスプレート7a、7bとの高
力ボルト13,19による接続であり、これら第1・第
2鉄骨梁5a、5b、5c同士の直接的な接続は単純形
態の板状であって、第1鉄骨梁5aのウエブ両面に単に
溶接接合しただけの接続用ブラケット15で行えるの
で、この面でも容易な作業で鉄骨梁5a、5b、5c同
士を接続することができる。そして上述したように、鉄
骨梁5a、5b、5cや柱状仮設部材3a、3b、支持
ブラケット9a、9b、スプライスプレート7a、7
b、接続用ブラケット15を工場等で製作する際には、
鋼材を切断し、ボルト孔を形成するだけでよく、加工が
簡単で低コストに作成できるとともに、これら単材を工
場から現場へ積載、輸送、搬入することも容易であり、
この面からもコストを削減できる。
In the present embodiment, the H-shaped steel is used as the columnar temporary members 3a and 3b, and the H-shaped steel is cut to a height equivalent to a reinforced concrete column and a bolt hole is formed in the H-shaped steel. With such a simple process, it can be easily applied to the site. Also, support brackets 9a, 9b
And the form of the splice plates 7a and 7b is also simple,
Easy processing and excellent workability. Furthermore, since the splice plates 7a and 7b are formed in a wide rhombic shape with the pillar core, the splice plates 7a and 7b are slightly projected around the beam-column connection, and the concrete is cast around the beam-column connection. The filling of concrete can be ensured without hindering installation. The connection between the first steel beam 5a and the second steel beam 5b, 5c is mainly connection between the upper and lower splice plates 7a, 7b by high-strength bolts 13, 19, and the first and second steel beam 5a. , 5b, 5c is a simple plate-like connection and can be made by the connection bracket 15 which is simply welded to both surfaces of the web of the first steel beam 5a. The steel beams 5a, 5b, 5c can be connected to each other. As described above, the steel beams 5a, 5b, 5c, the columnar temporary members 3a, 3b, the support brackets 9a, 9b, and the splice plates 7a, 7
b, When manufacturing the connection bracket 15 at a factory or the like,
All you have to do is cut the steel material and form the bolt holes, and it is easy to process and can be made at low cost.
In this respect, costs can be reduced.

【0040】図6には、上記実施形態の変形例が示され
ている。この変形例では、第1鉄骨梁5aおよび第2鉄
骨梁5b、5c相互間にわたって鉄筋コンクリート柱1
の上端部および下端部を取り囲んで、柱梁仕口部の耐力
および靭性を高める帯状部材としてのバンドプレート2
5が接合されている。そしてこのバンドプレート25に
よって鉄骨梁近傍の鉄筋コンクリート柱1の柱コンクリ
ートを拘束することができ、従来の仕口部材を用いた構
造と遜色のない強度の柱梁仕口部を形成することができ
る。
FIG. 6 shows a modification of the above embodiment. In this modification, the reinforced concrete column 1 extends between the first steel beam 5a and the second steel beam 5b, 5c.
Plate 2 as a band-like member surrounding the upper end and the lower end of the joint to increase the strength and toughness of the beam-column connection
5 are joined. The band plate 25 can restrain the column concrete of the reinforced concrete column 1 in the vicinity of the steel beam, and can form a beam-column joint having a strength comparable to a structure using a conventional joint member.

【0041】[0041]

【発明の効果】以上説明したように請求項1に係る鉄筋
コンクリート柱と鉄骨梁の混合構造によれば、鉄筋コン
クリート柱の構築箇所に設けられ、当該柱内部に埋め込
まれる柱状仮設部材によって鉄骨梁を仮支持する構造で
あるので、別途仮設支保工を設ける必要なく、かつまた
柱コンクリートの硬化による鉄筋コンクリート柱の構築
完了を待つことなく、当該柱状仮設部材を利用して鉄骨
梁の建て方を先行することができる。すなわち、鉄筋コ
ンクリート柱の構築完了に必要な型枠工事やコンクリー
ト打設作業、並びにその養生期間とは切り離して、クレ
ーン等の揚重機器を利用した鉄骨梁の建て方を、同階層
だけでなく、柱状仮設部材上に載置した鉄骨梁上にさら
に柱状仮設部材を設置することで上層階へも先行して進
めていくことができ、これにより一階層毎に進められる
鉄筋コンクリート柱の構築作業の進捗にかかわらず、鉄
骨梁の建て方作業を短い期間で先行して完了させること
ができ、工期短縮を図ることができる。またこれに伴
い、鉄骨梁を揚重するための揚重機器を集中的に稼働さ
せることができて、その稼働効率を向上することがで
き、鉄骨梁の揚重作業完了後は当該クレーンを自由に転
用することもできる。
As described above, according to the mixed structure of the reinforced concrete columns and the steel beams according to the first aspect, the steel beams are temporarily provided by the columnar temporary members provided at the construction site of the reinforced concrete columns and embedded inside the columns. Since it is a structure to support, it is not necessary to provide a temporary support, and also, without waiting for the completion of the construction of the reinforced concrete column due to hardening of the column concrete, advance the method of building the steel beam using the columnar temporary member Can be. In other words, apart from the formwork and concrete casting work required to complete the construction of reinforced concrete columns, and the curing period, the method of building steel beams using lifting equipment such as cranes, not only at the same level, By installing a columnar temporary member on the steel beam placed on the columnar temporary member, it is possible to proceed ahead to the upper floors, thereby progressing the construction work of reinforced concrete columns that can be advanced one layer at a time Regardless of this, the construction work of the steel beam can be completed in advance in a short period, and the construction period can be shortened. Along with this, lifting equipment for lifting steel beams can be intensively operated, and its operation efficiency can be improved. After completion of lifting work on steel beams, the crane can be freely operated. Can also be diverted to

【0042】また、鉄骨梁を仮支持して当該鉄骨梁の建
て方を先行できる柱状仮設部材を備えていることから、
鉄筋コンクリート柱を構築するためにコンクリートを打
設する際には、柱梁仕口部周りに一挙にコンクリートを
打ち込むことができ、当該仕口部周りのコンクリートの
充填性を改善でき、この面からも工期短縮を図ることが
できる。
In addition, the provision of the columnar temporary member which can temporarily support the steel beam and precede the method of building the steel beam is provided.
When laying concrete to construct a reinforced concrete column, concrete can be poured at once around the beam-to-column connection, and the concrete filling around the connection can be improved. The construction period can be shortened.

【0043】さらに、鉄骨梁同士を、接続部材を介して
高力ボルトで接続するようにしていて、これにより煩雑
でコストがかかるとともに熟練度が要求され、かつまた
天候にも左右される溶接作業を削減できて施工の省力
化、工期短縮を図ることができる。
Further, the steel beams are connected to each other by high-strength bolts via connecting members, which makes the welding work complicated, costly, requires skill, and depends on the weather. Can be reduced, and labor saving and shortening of construction period can be achieved.

【0044】また請求項2に係る鉄筋コンクリート柱と
鉄骨梁の混合構造によれば、帯状部材によって鉄骨梁近
傍の鉄筋コンクリート柱の柱コンクリートを拘束するこ
とができて、従来の仕口部材を用いた構造と遜色のない
強度の仕口部を形成することができる。
Further, according to the mixed structure of the reinforced concrete columns and the steel beams according to the second aspect, the column concrete of the reinforced concrete columns in the vicinity of the steel beams can be restrained by the band-shaped members, and the structure using the conventional connection member can be obtained. It is possible to form a joint having a strength comparable to that of the first embodiment.

【0045】他方、請求項3に係る鉄筋コンクリート柱
と鉄骨梁の混合構造の施工方法によれば、まず鉄筋コン
クリート柱の構築箇所に、鉄骨梁を仮支持する柱状仮設
部材を予め設置するようにしたので、これにより請求項
1と同様に、別途仮設支保工を設ける必要なく、かつま
た柱コンクリートの硬化による鉄筋コンクリート柱の構
築完了を待つことなく、当該柱状仮設部材を利用して鉄
骨梁の建て方を先行することができて、一階層毎に進め
られる鉄筋コンクリート柱の構築作業の進捗にかかわら
ず、鉄骨梁の建て方作業を上層階へ向かって先行して完
了させることができ、工期短縮を図ることができる。ま
たこれに伴い、請求項1と同様に、鉄骨梁を揚重するた
めの揚重機器の稼働効率を向上できる。
On the other hand, according to the construction method of the mixed structure of the reinforced concrete columns and the steel beams according to the third aspect, first, the columnar temporary members for temporarily supporting the steel beams are installed in advance at the construction sites of the reinforced concrete columns. Therefore, in the same manner as in claim 1, it is not necessary to separately provide a temporary support, and also, without waiting for the completion of the construction of the reinforced concrete column due to the hardening of the column concrete, the method of constructing the steel beam using the columnar temporary member is used. Regardless of the progress of the reinforced concrete column construction work that can be performed at each level, the construction work of steel beams can be completed in advance toward the upper floor, shortening the construction period Can be. Accordingly, similarly to the first aspect, the operation efficiency of the lifting equipment for lifting the steel beam can be improved.

【0046】他方、鉄筋コンクリート柱の構築作業につ
いては、先行する鉄骨梁の建て方が完了したものから順
次、柱状仮設部材の周りに従来の方法によって施工する
ことができ、施工作業上、柱の構築と鉄骨梁の建て方と
が複雑に交錯することがなく、この面からも工期短縮を
図ることができる。
On the other hand, in the construction work of the reinforced concrete columns, the construction of the pillars can be sequentially carried out by the conventional method around the columnar temporary members, starting from the construction of the preceding steel beam is completed. The construction of the steel beam does not intersect complicatedly, and the construction period can be shortened from this aspect as well.

【0047】また、柱状仮設部材で鉄骨梁を仮支持して
当該鉄骨梁の建て方を先行するようにしていて、鉄筋コ
ンクリート柱を構築するためにコンクリートを打設する
際には請求項1と同様に、柱梁仕口部周りに一挙にコン
クリートを打ち込むことができ、工期短縮を図ることが
できる。
Further, the steel beam is temporarily supported by the columnar temporary member so as to precede the method of building the steel beam. When concrete is poured to construct a reinforced concrete column, it is the same as the first embodiment. In addition, concrete can be poured at once around the beam-column connection, and the construction period can be shortened.

【0048】さらに、鉄骨梁同士を、接続部材を介して
高力ボルトで接続するようにしていて、これにより請求
項1と同様に、施工の省力化、工期短縮を図ることがで
きる。
Further, the steel beams are connected to each other by a high-strength bolt via a connecting member, so that the construction can be labor-saving and the construction period can be shortened as in the first aspect.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の1実施例による柱−梁接合部構造を示
す正面図である。
FIG. 1 is a front view showing a column-beam joint structure according to an embodiment of the present invention.

【図2】本発明の1実施例による柱−梁接合部構造の組
立完了状態と組み付け状態を示す説明図である。
FIG. 2 is an explanatory view showing an assembled state and an assembled state of a column-beam joint structure according to one embodiment of the present invention.

【図3】本発明の1実施例による柱−梁接合部構造の主
要部を示す図である。(a)は同構造の正面断面図、
(b)は同構造の側面断面図である。
FIG. 3 is a view showing a main part of a column-beam joint structure according to an embodiment of the present invention. (A) is a front sectional view of the same structure,
(B) is a side sectional view of the same structure.

【図4】図3と同様の柱−梁接合部構造の主要部を示す
図である。(a)は図3に示すB断面による断面図、
(b)は図3に示すC断面による断面図である。
FIG. 4 is a view showing a main part of a column-beam joint structure similar to FIG. 3; (A) is a sectional view taken along the section B shown in FIG. 3,
FIG. 4B is a cross-sectional view taken along a cross section C shown in FIG. 3.

【図5】本発明の第1実施例による柱−梁接合部構造に
おける、梁から鉄筋コンクリート柱への応力の伝達を示
す説明図である。
FIG. 5 is an explanatory view showing transmission of stress from a beam to a reinforced concrete column in the column-beam joint structure according to the first embodiment of the present invention.

【図6】本発明の他の実施例による柱−梁接合部構造の
主要部を示す正面図である。
FIG. 6 is a front view showing a main part of a column-beam joint structure according to another embodiment of the present invention.

【図7】従来例での鉄筋コンクリート柱−鉄骨梁の接合
部構造を示す斜視図である。
FIG. 7 is a perspective view showing a joint structure between a reinforced concrete column and a steel beam in a conventional example.

【符号の説明】[Explanation of symbols]

1 鉄筋コンクリート柱 3a、3b 柱状仮設部材 5a、5b、5c、33 鉄骨梁 7a、7b スプライスプレート 9a、9b 支持ブラケット 11a、11b ボルト・ナット 13,17,19 高力ボルト 15 接続用ブラケット 21、35 柱主筋 23、37 剪断補強筋 25 バンドプレート 31 ふさぎ板 DESCRIPTION OF SYMBOLS 1 Reinforced concrete column 3a, 3b Temporary columnar member 5a, 5b, 5c, 33 Steel beam 7a, 7b Splice plate 9a, 9b Support bracket 11a, 11b Bolt and nut 13, 17, 19 High-strength bolt 15 Connection bracket 21, 35 Column Main reinforcement 23, 37 Shear reinforcement 25 Band plate 31 Cover plate

───────────────────────────────────────────────────── フロントページの続き (72)発明者 西村 勝尚 大阪府大阪市中央区北浜東4番33号 株式 会社大林組本店内 Fターム(参考) 2E125 AA04 AA14 AB01 AB12 AC04 AC07 AC15 AG03 AG12 BB02 BB22 BD01 BE05 CA05 EA33 ────────────────────────────────────────────────── ─── Continued on the front page (72) Katsuhisa Nishimura 4-33 Kitahama Higashi, Chuo-ku, Osaka-shi, Osaka F-term in Obayashi-gumi head office (reference) 2E125 AA04 AA14 AB01 AB12 AC04 AC07 AC15 AG03 AG12 BB02 BB22 BD01 BE05 CA05 EA33

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 鉄筋コンクリート柱の構築箇所に、該鉄
筋コンクリート柱上で交差する複数の鉄骨梁を仮支持し
つつ、該鉄筋コンクリート柱内部に埋め込まれる柱状仮
設部材を設けるとともに、該柱状仮設部材上で互いに交
差する上記鉄骨梁相互間に接続部材を配設し、上記鉄骨
梁同士を接続するために、上記接続部材と上記鉄骨梁と
を高力ボルトで互いに接続したことを特徴とする鉄筋コ
ンクリート柱と鉄骨梁の混合構造。
At a construction site of a reinforced concrete column, a plurality of steel beams intersecting on the reinforced concrete column are temporarily supported, and a columnar temporary member embedded inside the reinforced concrete column is provided. A connecting member is provided between the intersecting steel beams, and the connecting members and the steel beams are connected to each other by high-strength bolts to connect the steel beams to each other. Mixed structure of beams.
【請求項2】 前記鉄骨梁に、前記鉄筋コンクリート柱
を取り囲んで帯状部材を設けたことを特徴とする請求項
1に記載の鉄筋コンクリート柱と鉄骨梁の混合構造およ
びその施工方法。
2. A mixed structure of a reinforced concrete column and a steel beam according to claim 1, wherein a band-shaped member is provided around the reinforced concrete column on the steel beam.
【請求項3】 まず、鉄筋コンクリート柱の構築箇所
に、該鉄筋コンクリート柱上で交差する複数の鉄骨梁を
仮支持する柱状仮設部材を設け、次いで、該柱状仮設部
材上で互いに交差する上記鉄骨梁相互間に接続部材を配
設し、次いで、上記鉄骨梁同士を接続するために、上記
接続部材と上記鉄骨梁とを高力ボルトで互いに接合して
鉄骨建て方を先行し、その後、該鉄骨建て方を完了した
上記柱状仮設部材の周りに、柱用鉄筋を配筋するととも
にコンクリートを打設して鉄筋コンクリート柱を構築す
るようにしたことを特徴とする鉄筋コンクリート柱と鉄
骨梁の混合構造の施工方法。
3. A columnar temporary member for temporarily supporting a plurality of steel beams intersecting on the reinforced concrete column is provided at a location where the reinforced concrete column is constructed, and then the steel beam beams intersecting each other on the columnar temporary member are provided. A connecting member is disposed therebetween, and then, in order to connect the steel beams, the connecting member and the steel beams are joined to each other with high-strength bolts to precede the steel building method. A method of constructing a mixed structure of a reinforced concrete column and a steel beam, wherein a reinforcing steel for a column is laid around the columnar temporary member which has been completed, and concrete is cast to construct a reinforced concrete column. .
JP33320898A 1998-11-24 1998-11-24 Mixed structure of reinforced concrete column and steel beam and its construction method Expired - Fee Related JP3586121B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP33320898A JP3586121B2 (en) 1998-11-24 1998-11-24 Mixed structure of reinforced concrete column and steel beam and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP33320898A JP3586121B2 (en) 1998-11-24 1998-11-24 Mixed structure of reinforced concrete column and steel beam and its construction method

Publications (2)

Publication Number Publication Date
JP2000160686A true JP2000160686A (en) 2000-06-13
JP3586121B2 JP3586121B2 (en) 2004-11-10

Family

ID=18263535

Family Applications (1)

Application Number Title Priority Date Filing Date
JP33320898A Expired - Fee Related JP3586121B2 (en) 1998-11-24 1998-11-24 Mixed structure of reinforced concrete column and steel beam and its construction method

Country Status (1)

Country Link
JP (1) JP3586121B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007217984A (en) * 2006-02-17 2007-08-30 Okabe Co Ltd Column-beam joining structure
JP2010242390A (en) * 2009-04-07 2010-10-28 Toda Constr Co Ltd Joining method and structure of column-beam joint part having steel brace
US7975439B1 (en) * 2006-06-23 2011-07-12 Cude Herman E Bulk storage building
JP2011169063A (en) * 2010-02-22 2011-09-01 Maeda Corp Column-beam joint structure, and construction method of column-beam joint part

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007217984A (en) * 2006-02-17 2007-08-30 Okabe Co Ltd Column-beam joining structure
US7975439B1 (en) * 2006-06-23 2011-07-12 Cude Herman E Bulk storage building
JP2010242390A (en) * 2009-04-07 2010-10-28 Toda Constr Co Ltd Joining method and structure of column-beam joint part having steel brace
JP2011169063A (en) * 2010-02-22 2011-09-01 Maeda Corp Column-beam joint structure, and construction method of column-beam joint part

Also Published As

Publication number Publication date
JP3586121B2 (en) 2004-11-10

Similar Documents

Publication Publication Date Title
JP2010242390A (en) Joining method and structure of column-beam joint part having steel brace
KR100712354B1 (en) PC Integrating Construction Method of an Underground Parking Lot and PC Column-Beam Joint System for Long Span PC Beam therein
JP4490532B2 (en) Precast composite beam structure
JP2927402B2 (en) Column-beam joint structure of concrete building
JP4996370B2 (en) Frame assembly method and building frame
JP3586121B2 (en) Mixed structure of reinforced concrete column and steel beam and its construction method
JP2986751B2 (en) Seismic performance enhancement method for buildings and seismic blocks
JP2897663B2 (en) How to build underground structures
JPH0434161A (en) Centrifugally molded hollow pc concrete column and column construction method
JP2000160687A (en) Construction method for composite structure and precast concrete column
KR20200113901A (en) Method for constructing flat slab structure with drop panel
JP2972956B2 (en) Column and beam joining method and its structure
JPH0732706Y2 (en) Reinforcement structure of precast reinforced concrete columns and crossed steel frames for joining steel beams
JP2001146715A (en) Half precast floor slab and its joint structure
JP2614000B2 (en) Basics of steel frame
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JP3094198B2 (en) Precast reinforced concrete member and method of constructing structure using the same
JP2001193290A (en) Seismic isolation method for existing building
JPS6217233A (en) Foundation base column
JP2578671B2 (en) Column and beam construction method
JPH059975A (en) Constructing method of steel rigid-frame structure building
JP2023016370A (en) Construction method of structure
JP2967530B2 (en) Basement building construction method
JPH1113141A (en) Constructing method of composite structure
JPH03187436A (en) Supporting member for construction pillar of reinforced concrete building

Legal Events

Date Code Title Description
A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040805

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees