JP4490532B2 - Precast composite beam structure - Google Patents
Precast composite beam structure Download PDFInfo
- Publication number
- JP4490532B2 JP4490532B2 JP35707599A JP35707599A JP4490532B2 JP 4490532 B2 JP4490532 B2 JP 4490532B2 JP 35707599 A JP35707599 A JP 35707599A JP 35707599 A JP35707599 A JP 35707599A JP 4490532 B2 JP4490532 B2 JP 4490532B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- steel
- composite beam
- precast composite
- precast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Rod-Shaped Construction Members (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、構造物のプレキャスト合成梁の構造の改良に関するものである。
【0002】
【従来の技術とその課題】
従来、コンクリート建築物の構築にあたっては、柱梁接合部の簡素化と設計自由度の拡大を目的として、柱は鉄骨鉄筋コンクリート造(SRC造)を用い、梁は端部と中央部とで構造の異なる合成梁を用いて、これらを結合して建築物を構築する複合構造が採用されている。
【0003】
例えば図16、17に示された特許番号第2629503号に記載のものはコンクリート梁51内部にPC鋼材53及び主筋56が配置され、プレストレスが導入されてプレキャスト化されたコンクリート梁51と鋼管コンクリート造柱52は、ガセットプレート62とブラケット54のウェブ、ダイアフラム55とブラケット54が結合されることによって組み立てられる構造である。
【0004】
この構造ではコンクリート梁51の端部に配設するブラケット54(H形鋼)の天端がコンクリート梁51の天端面に連続して配設されるため、ブラケット54のフランジとスラブコンクリートとの付着強度を確保することが難しく、フランジ天端にスタッドを溶植して一体性を確保している。
【0005】
また図18に示す特開平10−96294号に記載のものは、プレキャストコンクリートの梁74の端部に鉄骨のH形鋼71を埋め込むと共に主筋72をH形鋼71のフランジの内側に配筋し、フランジの外側にフープ筋73が巻かれている。梁の端部のH形鋼71をコンクリート充填鋼管柱76に接合した後、梁のプレキャストコンクリート74とコンクリート充填鋼管柱76との間の隙間は、スラブの打設と同時に現場でコンクリートを打設して一体の柱梁結合構造としたものである。この工法では梁の主筋72とH形鋼71のフランジは溶接されておらず、フランジ内側のコンクリートの付着のみで応力を伝達するためにH形鋼71の必要長さを長くする必要があり、コストの面で高価なものとなる。
【0006】
本発明は、これらの問題を解決するプレキャスト合成梁の構造を提供することを目的とする。
【0007】
【課題を解決するための手段】
本発明は、鋼管の内部にコンクリートが充填された鋼管コンクリート造の柱の間を結合し、前記柱との結合部端部がH形鋼を配設した鉄骨コンクリート造、中央部は鉄筋コンクリート造のプレキャストコンクリートで形成されたプレキャスト合成梁の構造において、前記鉄筋コンクリートの鉄筋は、H形鋼のフランジ端部近傍に配置され、プレキャスト合成梁の軸方向に伸びる第一梁主筋一段筋と、H形鋼のフランジ中央部近傍に配置され、プレキャスト合成梁の軸方向に伸びる第二梁主筋一段筋とを備え、前記第一梁主筋一段筋は、H形鋼の上下のフランジ端部近傍に配置された第一梁主筋一段筋の端部を結合しフープ状に形成され、前記第二梁主筋一段筋は、その端部がH形鋼の他方のフランジ部に向けて折れ曲げられて前記上下のフランジ間でX字形状になるように形成され、プレキャスト合成梁の鉄筋コンクリート造から鉄骨コンクリート造に切替わる部分のピッチが他の部分のピッチより細かく配置された複数のスタラップを備える。
【0009】
【発明の作用および効果】
本発明では、鋼管の内部にコンクリートが充填された鋼管コンクリート造の柱の間を結合するプレキャストコンクリートで形成されたプレキャスト合成梁の構造であって、柱との結合部にはH形鋼を配設した鉄骨コンクリート造を採用し、中央部は、鉄筋コンクリート造とした構造である。
【0010】
中央部を構成する鉄筋は、第一及び第二梁主筋一段筋と梁主筋二段筋とスタラップより構成されている。第一梁主筋一段筋はプレキャスト合成梁の両端に備えられたH形鋼のフランジ端部近傍に配置され、かつプレキャスト合成梁の軸方向に配置されており、上下に位置した第一梁主筋一段筋の端部を結合しフープ状に構成される。
【0011】
また第二梁主筋一段筋は、H形鋼の上側のフランジ中央部近傍に位置する鉄筋が下側のフランジに向けて、下側のフランジ中央部近傍に位置する鉄筋が上側のフランジに向けて折り曲げられるので、第二梁主筋一段筋は上側と下側の第二梁主筋一段筋によってH形鋼の上下フランジ間でX字を形成することになる。よってH形鋼との定着長さを長くすることができ、外力による曲げに抵抗するのみでなく、せん断に対しても抵抗することが可能となる。
【0012】
さらにこのような構成とすることによって、その製作は鉄筋を折り曲げることによってのみで対応することができ、現場にて溶接等のための火気を用いることがないので安全で、施工が容易になる。
【0013】
さらに第一梁主筋一段筋はH形鋼のフランジ端部近傍に配置され、フランジ部に固定されないので、フランジ幅を狭くすることができ、コンクリート打設時のH形鋼フランジ裏側へのコンクリートの充填性が改良される。
【0015】
【発明の実施の形態】
以下、本発明の実施形態を添付図面に基づいて説明する。
【0016】
図1から図5は本実施形態の構成図を示している。
【0017】
図1に示すように建築物の主要部は鉛直方向に立設された柱2と、柱2の間に掛け渡されて床を形成するための基礎部材となるプレキャスト合成梁1が結合されることによって構築される。
【0018】
柱2は鋼管2bの内部に充填コンクリート2aを充填して形成されるコンクリート充填鋼管造を用いて造られる。また柱2のプレキャスト合成梁1との結合位置には、2つのダイアフラム13が、プレキャスト合成梁1を上下方向から挟みこむように柱2の軸に対して略垂直に取付けられる。
【0019】
鋼管2bはダイアフラム13を介してそれぞれ突き合わされて結合され、充填コンクリート2aが注入される型枠として機能する。
【0020】
さらに2つのダイアフラム13の間のプレキャスト合成梁の中心軸近傍に渡ってガセットプレート9が配置され、このガセットプレート9は柱2に軸方向に沿って柱2の面と突き当てられ、結合している。
【0021】
なおダイアフラム13の中央部には、図2に示すように柱2内に充填コンクリート2aを隙間なく行き渡らせるための打設孔13aおよび空気抜き孔13bが設けられている。
【0022】
ガセットプレート9にはプレキャスト合成梁1との結合に使用されるボルト用の穴が上下方向に2列穿孔されている。
【0023】
柱2に結合されるプレキャスト合成梁1は予め工場または工事現場で製作される。
【0024】
プレキャスト合成梁1の構成について詳しく説明すると、図1と図3に示すように、柱2に突き当てられるH形鋼8がプレキャスト合成梁1の両端に備えられる。H形鋼8は2つのダイアフラム13にそれぞれ突き当てられ固定される2枚のフランジ8aと、ガセットプレート9とボルト止めされるウェブ8bとから構成される。ウェブ8bには柱2のガセットプレート9とボルト止めされるための穴が上下方向に2列穿孔されている。また上下のフランジ8a端を結合するバンドプレート12がフランジ8aの外力による変形を抑止するために設けられる。
【0025】
また、図4に示すようにフープ状の第一梁主筋一段筋3が2本配置され、第一梁主筋一段筋3はH形鋼8の上下2枚のフランジ8a間の長さとほぼ同等の幅を有する。第一梁主筋一段筋3の軸方向寸法は、相対する2本の柱2のガセットプレート9の近傍に位置する程の長さである。
【0026】
また第一梁主筋一段筋3の内側には、図5に示すように第二梁主筋一段筋4が上下計4本配置される。第二梁主筋一段筋4は、図1に示すようにその両端部を上部に配置された第二梁主筋一段筋4は下に曲げられ、下部に配置された第二梁主筋一段筋4は上に曲げられて上下の第二梁主筋一段筋が重なるようにX字を形成し、H形鋼8の2枚のフランジ8aの間に位置する(図1および4に示す)。
【0027】
第一梁主筋一段筋3が形成するフープ内には同じくフープ状の梁主筋二段筋5が配置される。梁主筋二段筋5はH形鋼8の上下フランジ8aの内側に溶植されるスタッド11の外側に近接して備えられることになる。
【0028】
上下の第一梁主筋一段筋3と第二梁主筋一段筋4の外周を取り囲むように四角状のスタラップ7が合成梁1の軸方向に複数配設されている。スタラップ7はガセットプレート9とウェブ8bの結合部まで覆うように配置される。スタラップ7の配置のピッチは第二梁主筋一段筋が形成するX字の付近に位置するスタラップ7のピッチがその他の位置のピッチよりも細かく配設されている。
【0029】
なお合成梁1の端部にはスタラップ7をガセットプレート9の周囲まで覆うように配置するためのスタラップ7を支持する添え筋6が第一梁主筋一段筋3の内側から柱2側に伸びている。
【0030】
このようにプレキャスト合成梁1の配筋が行われ、次に型枠を設置し、コンクリートを型枠内に打設してプレキャスト合成梁1が完成する。このときコンクリートの打設がスタラップ7及び第一梁主筋一段筋3の上部を残して、また軸方向には第一梁主筋一段筋3全体に打設される程度(ウェブ8bとガセットプレート9のボルト締結に支障がないように合成梁1の端部付近のスタラップ7がコンクリートに触れずに残る程度)に行われるように、型枠は形成される。
【0031】
次にプレキャスト合成梁1と柱2の結合方法について図6から図15を用いて説明する。
【0032】
図6では柱2として既設された鋼管2b’の上端部に別の鋼管2bを設置して継手ボルト等によって固定する。このとき既に新設の鋼管2bにはガセットプレート9とダイアフラム13が組み付けられている。
【0033】
図7、8では、工場等で事前に製作されたプレキャスト合成梁1を新設の鋼管2bに連結する。このとき、プレキャスト合成梁1のウェブ8bと柱2のガセットプレート9とに設けられた穴を貫通するボルト10によってウェブ8bとガセットプレート9とは締結される。さらにフランジ8aはダイアフラム13に突き当てられ、結合される。
【0034】
図9から図11では、プレキャスト合成梁1の両端部と柱2に型枠を組み立て、プレキャスト合成梁1全体に渡ってプレキャスト床版16を据え付ける。なおプレキャスト床版16の代わりに床スラブ型枠を組み立ててもよい。
【0035】
図12から図14でプレキャスト合成梁1の端部及び床スラブに後打ちコンクリート13を打設する。このとき床スラブとプレキャスト合成梁製作時にコンクリート打設されずにプレキャスト合成梁1から露出されていたスタラップ7の上部が同時にコンクリート打設される。
【0036】
図15で、鋼管2bの内部に充填コンクリート2aを充填して柱2を形成し、一連の作業を終了する。
【0037】
以上の作業を繰り返し行うことによって、建築物に所望の階数の床面を形成することができる。
【0038】
これまで説明してきたように本発明のプレキャスト合成梁1は、フープ状の第一梁主筋一段筋3をH形鋼8の外側に配置し、第二梁主筋一段筋をH形鋼8の上下のフランジ8b間でX字を形成するように折り曲げ、コンクリート打設することで、柱2と結合される。
【0039】
このような構成により、プレキャスト合成梁1と柱2との結合部に作用するせん断力は主としてガセットプレート9とウェブ8bの接合部によって支持され、一方、結合部に作用する曲げ荷重は主として第一梁主筋一段筋3、第二梁主筋一段筋4と梁主筋二段筋5およびH形鋼8のフランジ8aによって支持されるが、第二梁主筋一段筋4がX字形状となっており、H形鋼8との定着長さを長くとることができるので、曲げ荷重に対する性能を向上できる。さらにはX字形状の第二梁主筋一段筋4によるせん断力に対する性能向上も期待できる。
【0040】
またそのプレキャスト合成梁1の施工現場においては、その構造上曲げ加工を施すのみで製造可能であり、溶接等の火気を用いる必要がなく、安全で施工が容易となる。
【0041】
コンクリート打設時には、第一梁主筋一段筋3をH形鋼8のフランジ8aに固定しないため、フランジ幅を狭くすることができ、フランジ8a裏などのコンクリートの充填が難しい箇所にも充填ができるので、コンクリートの充填性を向上することができる。
【0042】
また第一及び第二梁主筋一段筋3、4の外周に設けられたスタラップ7は鉄筋コンクリート造の中央部と、鉄筋コンクリート造から鉄骨コンクリート造に変化する領域ではそのピッチが異なっており、構造の変化する領域のピッチは中央部のピッチよりも細かい構成としたので、合成梁1に大きなせん断力が作用した場合でも、構造変化領域において円滑に力を伝達することができる。
【0043】
さらに梁主筋二段筋5はH形鋼8のフランジ部8aに設けられたスタッド11に近接して設けたので、合成梁1に外力が作用した場合にフープ状の梁主筋二段筋5に作用する応力をコンクリートを介してH形鋼8のフランジ部8aに伝達することができる。
【0044】
以上の構成により、プレキャスト合成梁1から柱2に円滑に力を伝達し、構造変化領域における耐力及び剛性を効果的に高めることができ、また梁せいは小さくなることにより、合成梁が軽くなり、広い室内空間を確保できる。
【0045】
またプレキャスト合成梁の上部スタラップを床スラブのコンクリート打設時に床スラブと同時にコンクリート打設することによって、床スラブとプレキャスト合成梁との一体性を確保することが可能となる。
【図面の簡単な説明】
【図1】本発明の実施の形態を示し、図2のA−A線に沿う断面図である。
【図2】同じく図1のB−B線に沿う断面図である。
【図3】同じく図1のC−C線に沿う断面図である。
【図4】同じく図1のD−D線に沿う断面図である。
【図5】同じく図1のE−E線に沿う断面図である。
【図6】同じく建築工程を示す断面図である(プレキャスト合成梁設置前)。
【図7】同じく建築工程を示す断面図である(プレキャスト合成梁設置状態)。
【図8】同じく建築工程を示す断面図である(プレキャスト合成梁接合完了状態)。
【図9】同じく建築工程を示す断面図である(プレキャスト合成梁端部型枠設置状態)。
【図10】同じく図9のF−F線に沿う断面図である。
【図11】同じく図9のG−G線に沿う断面図である。
【図12】同じく建築工程を示す断面図である(プレキャスト合成梁後打ちコンクリート打設状態)。
【図13】同じく図12のH−H線に沿う断面図である。
【図14】同じく図12のI−I線に沿う断面図である。
【図15】同じく建築工程を示す断面図である(柱内充填コンクリート充填状態)。
【図16】従来例のコンクリート梁と柱の接合部を示す図である。
【図17】同じくコンクリート梁の製作例を示す図である。
【図18】同じく従来例を示す図である。
【符号の説明】
1 プレキャスト合成梁
2 柱
2a 充填コンクリート
2b 鋼管
3 第一梁主筋一段筋
4 第二梁主筋一段筋
5 梁主筋二段筋
6 添え筋
7 スタラップ
8 H形鋼
8a フランジ
8b ウェブ
9 ガセットプレート
10 ボルト
11 スタッド
12 バンドプレート
13 ダイアフラム
13a 打設孔
13b 空気抜き孔
14 後打ちコンクリート
15 プレキャストコンクリート
16 プレキャスト床版[0001]
BACKGROUND OF THE INVENTION
The present invention relates to an improvement in the structure of a precast composite beam of a structure.
[0002]
[Prior art and its problems]
Conventionally, in the construction of concrete buildings, for the purpose of simplifying the beam-column joint and increasing the degree of design freedom, steel columns and steel reinforced concrete structures (SRC structures) are used for the columns, and the beams are structured at the end and center. A composite structure in which different composite beams are used to construct a building by combining them is employed.
[0003]
For example, the one described in Japanese Patent No. 2629503 shown in FIGS. 16 and 17 is a
[0004]
In this structure, since the top end of the bracket 54 (H-shaped steel) provided at the end of the
[0005]
Further, in the one described in Japanese Patent Laid-Open No. 10-96294 shown in FIG. 18, a steel frame H-
[0006]
It is an object of the present invention to provide a precast composite beam structure that solves these problems.
[0007]
[Means for Solving the Problems]
The present invention connects steel pipe concrete columns filled with concrete inside the steel pipe, and the ends of the joints with the columns are steel-concrete structures in which H-shaped steel is arranged, and the central part is a reinforced concrete structure. In the structure of the precast composite beam formed of precast concrete, the reinforcing bar of the reinforced concrete is disposed in the vicinity of the flange end of the H-shaped steel, and the first beam main reinforcing bar one-stage reinforcing bar extends in the axial direction of the precast composite beam, And a second beam main reinforcement first step extending in the axial direction of the precast composite beam, the first beam main reinforcement first step being arranged in the vicinity of the upper and lower flange ends of the H-shaped steel. It is formed on the hoop and joining the ends of the first beam main reinforcement single stage muscle, the second beam main reinforcement one stage muscle, its ends of the upper and lower Te bending piece Gerare toward the other flange portion of the H-shaped steel Hula Is formed so as to be X-shape between di-, comprising a plurality of Sturup pitch is finer disposed than the pitch of other portions of the steel skeleton concrete structure in switched portion from the reinforced concrete precast composite beam.
[0009]
Operation and effect of the invention
In the present invention, the structure is a precast composite beam formed of precast concrete that joins between steel pipe concrete columns filled with concrete inside the steel pipe, and H-shaped steel is arranged at the joint with the column. The installed steel concrete structure is adopted, and the central part is a reinforced concrete structure.
[0010]
The reinforcing bar constituting the central part is composed of the first and second beam main bars, the beam main bars and the stirrup. The first beam main reinforcement is arranged near the flange end of the H-shaped steel provided at both ends of the precast composite beam, and is arranged in the axial direction of the precast composite beam. Combining the ends of the muscles, it is configured in a hoop shape.
[0011]
In the second beam main reinforcement, the rebar located near the center of the upper flange of the H-shaped steel is directed toward the lower flange, and the rebar located near the center of the lower flange is directed toward the upper flange. Since it is bent, the second beam main reinforcement first-stage reinforcement forms an X-shape between the upper and lower flanges of the H-section steel by the upper and lower second beam main reinforcement first-stage reinforcement. Therefore, the fixing length with the H-shaped steel can be increased, and it is possible not only to resist bending by an external force but also to resist shearing.
[0012]
Further, by adopting such a configuration, the production can be dealt with only by bending the reinforcing bars, and it is safe and easy to construct since no fire for welding or the like is used on site.
[0013]
Furthermore, the first beam main reinforcement is arranged near the flange end of the H-section steel and is not fixed to the flange. Therefore, the flange width can be reduced, and the concrete on the back side of the H-section steel flange during concrete placement Fillability is improved.
[0015]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the accompanying drawings.
[0016]
1 to 5 show a configuration diagram of the present embodiment.
[0017]
As shown in FIG. 1, the main part of the building is connected to a
[0018]
The
[0019]
The
[0020]
Further, a
[0021]
In addition, the center part of the
[0022]
The
[0023]
The precast
[0024]
The configuration of the precast
[0025]
In addition, as shown in FIG. 4, two hoop-shaped first beam main reinforcing
[0026]
Further, as shown in FIG. 5, four first and second second beam main reinforcing
[0027]
In the hoop formed by the first beam main bar first-
[0028]
A plurality of
[0029]
Note that a
[0030]
In this way, the precast
[0031]
Next, a method for connecting the precast
[0032]
In FIG. 6, another
[0033]
7 and 8, the precast
[0034]
9 to 11, a formwork is assembled to both ends of the precast
[0035]
12 to 14, post-cast concrete 13 is placed on the end of the precast
[0036]
In FIG. 15, the concrete 2a is filled into the
[0037]
By repeatedly performing the above operations, a floor with a desired number of floors can be formed on the building.
[0038]
As described above, in the precast
[0039]
With such a configuration, the shearing force acting on the joint between the precast
[0040]
Further, at the construction site of the precast
[0041]
At the time of concrete placement, the first beam main reinforcing
[0042]
In addition, the
[0043]
Further, since the beam main reinforcing bar second reinforcing
[0044]
With the above configuration, the force can be smoothly transmitted from the precast
[0045]
In addition, by placing the upper slap of the precast composite beam at the same time as the floor slab when the floor slab is concreted, it is possible to ensure the integrity of the floor slab and the precast composite beam.
[Brief description of the drawings]
FIG. 1 shows an embodiment of the present invention and is a cross-sectional view taken along line AA in FIG.
2 is a cross-sectional view taken along the line BB in FIG.
3 is a cross-sectional view taken along the line CC of FIG.
4 is a cross-sectional view taken along line DD in FIG.
5 is a cross-sectional view taken along line EE in FIG.
FIG. 6 is a sectional view showing the construction process (before the precast composite beam is installed).
FIG. 7 is a cross-sectional view showing the construction process (precast composite beam installation state).
FIG. 8 is a cross-sectional view showing the construction process (precast composite beam joining completed state).
FIG. 9 is a cross-sectional view showing the construction process (precast composite beam end formwork installation state).
10 is a cross-sectional view taken along line FF in FIG.
11 is a cross-sectional view taken along line GG in FIG.
FIG. 12 is a cross-sectional view showing the construction process (precast composite beam post-cast concrete placement state).
13 is a cross-sectional view taken along line HH in FIG.
14 is a cross-sectional view taken along the line II of FIG.
FIG. 15 is a cross-sectional view showing the construction process (filled concrete in a column).
FIG. 16 is a view showing a joint portion between a concrete beam and a column in a conventional example.
FIG. 17 is a view similarly showing a manufacturing example of a concrete beam.
FIG. 18 is a diagram similarly showing a conventional example.
[Explanation of symbols]
DESCRIPTION OF
Claims (1)
前記鉄筋コンクリートの鉄筋は、
H形鋼のフランジ端部近傍に配置され、プレキャスト合成梁の軸方向に伸びる第一梁主筋一段筋と、
H形鋼のフランジ中央部近傍に配置され、プレキャスト合成梁の軸方向に伸びる第二梁主筋一段筋とを備え、
前記第一梁主筋一段筋は、H形鋼の上下のフランジ端部近傍に配置された第一梁主筋一段筋の端部を結合しフープ状に形成され、
前記第二梁主筋一段筋は、その端部がH形鋼の他方のフランジ部に向けて折れ曲げられて前記上下のフランジ間でX字形状になるように形成され、
プレキャスト合成梁の鉄筋コンクリート造から鉄骨コンクリート造に切替わる部分のピッチが他の部分のピッチより細かく配置された複数のスタラップを備えたことを特徴とするプレキャスト合成梁の構造。Steel pipe concrete columns filled with concrete inside the steel pipe are joined together, and the end of the joint with the pillar is steel-framed concrete with H-shaped steel, and the central part is made of reinforced concrete precast concrete In the structure of the precast composite beam,
The reinforced concrete rebar is
The first beam main reinforcement is arranged near the flange end of the H-shaped steel and extends in the axial direction of the precast composite beam;
It is arranged near the center of the flange of the H-shaped steel, and comprises a second beam main reinforcing bar and a first reinforcing bar extending in the axial direction of the precast composite beam,
The first beam main reinforcement first stage reinforcement is formed in a hoop shape by joining the ends of the first beam main reinforcement first stage reinforcement arranged near the upper and lower flange ends of the H-section steel,
Said second beam main reinforcement one stage muscle, its ends are formed to be X-shaped Te folded piece Gerare between said upper and lower flanges toward the other flange portion of the H-shaped steel,
A structure of a precast composite beam comprising a plurality of stirrups in which a pitch of a portion of the precast composite beam switching from a reinforced concrete structure to a steel concrete structure is arranged more finely than a pitch of other portions.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP35707599A JP4490532B2 (en) | 1999-12-16 | 1999-12-16 | Precast composite beam structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP35707599A JP4490532B2 (en) | 1999-12-16 | 1999-12-16 | Precast composite beam structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2001173097A JP2001173097A (en) | 2001-06-26 |
JP4490532B2 true JP4490532B2 (en) | 2010-06-30 |
Family
ID=18452263
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP35707599A Expired - Fee Related JP4490532B2 (en) | 1999-12-16 | 1999-12-16 | Precast composite beam structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4490532B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103967128A (en) * | 2014-05-23 | 2014-08-06 | 东北石油大学 | Combination column and combination beam frame with internally-arranged high-strength concrete core columns and construction method thereof |
CN103967129A (en) * | 2014-05-23 | 2014-08-06 | 东北石油大学 | Combination column and combination beam frame with internally-arranged pipe high-strength concrete core columns and construction method thereof |
CN103967127A (en) * | 2014-05-23 | 2014-08-06 | 东北石油大学 | Special strong combination column and combination beam frame with internally-arranged core columns and construction method thereof |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6121772B2 (en) * | 2013-03-28 | 2017-04-26 | 株式会社フジタ | Hybrid beam |
KR101509179B1 (en) * | 2014-02-17 | 2015-04-14 | 주식회사 아이에스중공업 | Welding beam for composition with concrete slab and column-beam joint structure using this beam |
CN104818801A (en) * | 2015-05-08 | 2015-08-05 | 重庆欧冠钢结构有限公司 | Pre-fabricated section steel reinforced concrete beam and pillar and manufacturing method |
CN104895246A (en) * | 2015-06-09 | 2015-09-09 | 南京长江都市建筑设计股份有限公司 | Thin-walled section steel skeleton structure in concrete beam |
CN110331816A (en) * | 2019-07-11 | 2019-10-15 | 江西建工第二建筑有限责任公司 | A kind of cast-in-place combination beam construction of assembled |
CN115370008B (en) * | 2022-08-02 | 2023-08-18 | 深圳市柏涛蓝森国际建筑设计有限公司 | Connection structure of steel pipe concrete column-reinforced concrete beam |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0549927U (en) * | 1991-12-09 | 1993-07-02 | 戸田建設株式会社 | Precast beams |
JPH1096294A (en) * | 1996-09-24 | 1998-04-14 | Kawasaki Steel Corp | Steel frame and reinforced concrete beam |
-
1999
- 1999-12-16 JP JP35707599A patent/JP4490532B2/en not_active Expired - Fee Related
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0549927U (en) * | 1991-12-09 | 1993-07-02 | 戸田建設株式会社 | Precast beams |
JPH1096294A (en) * | 1996-09-24 | 1998-04-14 | Kawasaki Steel Corp | Steel frame and reinforced concrete beam |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103967128A (en) * | 2014-05-23 | 2014-08-06 | 东北石油大学 | Combination column and combination beam frame with internally-arranged high-strength concrete core columns and construction method thereof |
CN103967129A (en) * | 2014-05-23 | 2014-08-06 | 东北石油大学 | Combination column and combination beam frame with internally-arranged pipe high-strength concrete core columns and construction method thereof |
CN103967127A (en) * | 2014-05-23 | 2014-08-06 | 东北石油大学 | Special strong combination column and combination beam frame with internally-arranged core columns and construction method thereof |
CN103967128B (en) * | 2014-05-23 | 2016-03-09 | 东北石油大学 | The coupled column assembled beam frame of built-in high-strength concrete stem stem and construction method thereof |
CN103967129B (en) * | 2014-05-23 | 2016-06-01 | 东北石油大学 | The coupled column assembled beam frame of built-in pipe high-strength concrete stem stem and constructional method thereof |
Also Published As
Publication number | Publication date |
---|---|
JP2001173097A (en) | 2001-06-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100971736B1 (en) | Shear reinforcement with dual anchorage function each up and down | |
JP4490532B2 (en) | Precast composite beam structure | |
JP2001123534A (en) | Construction of composite precast beam | |
JP2010242390A (en) | Joining method and structure of column-beam joint part having steel brace | |
KR102104382B1 (en) | Steel beam, composite column, and joint structure of the same | |
KR100343960B1 (en) | Steel concrete structure | |
JP2010261270A (en) | Composite structure and method for constructing composite structure building | |
JP2005188102A (en) | Structure of building and construction method | |
KR101017800B1 (en) | Reinforcement structure for connection of cold formed plate column and steel beam | |
GB2131849A (en) | Structural framework | |
KR200383489Y1 (en) | System for constructing composite reinforced concrete girders and beams using FRP | |
KR100578641B1 (en) | Steel-Concrete Hybrid Column, Hybrid Structure System Using the Same, and Construction Method Thereof | |
JPH08135018A (en) | Mixed structure of reinforced concrete column and steel skeleton beam | |
JP2002332691A (en) | Joint construction between column and beam | |
JPH08151648A (en) | Joint structure for column beam of steel structure | |
JP2000073448A (en) | Connection method and structure for precast concrete beam and column | |
JP2645329B2 (en) | Pillar construction method | |
JP7476836B2 (en) | Composite structure and construction method | |
JP2000160686A (en) | Composite structure of reinforced concrete column and steel frame beam, and its execution | |
JPH0732706Y2 (en) | Reinforcement structure of precast reinforced concrete columns and crossed steel frames for joining steel beams | |
KR200166886Y1 (en) | Steel concrete structure | |
JPH08239807A (en) | Composite column base structure | |
KR100579543B1 (en) | System for constructing composite reinforced concrete girders and beams using FRP | |
JPH06104993B2 (en) | Construction method of steel pipe precast concrete columns | |
JPS603844Y2 (en) | reinforced concrete structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20061010 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20080123 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20090804 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20091005 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20100316 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20100402 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130409 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 Ref document number: 4490532 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130409 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20160409 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |