JP2002332691A - Joint construction between column and beam - Google Patents

Joint construction between column and beam

Info

Publication number
JP2002332691A
JP2002332691A JP2001139213A JP2001139213A JP2002332691A JP 2002332691 A JP2002332691 A JP 2002332691A JP 2001139213 A JP2001139213 A JP 2001139213A JP 2001139213 A JP2001139213 A JP 2001139213A JP 2002332691 A JP2002332691 A JP 2002332691A
Authority
JP
Japan
Prior art keywords
joint
steel
column
steel pipe
steel frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2001139213A
Other languages
Japanese (ja)
Inventor
Yasushi Samori
康司 佐守
Takumi Kimura
匠 木村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2001139213A priority Critical patent/JP2002332691A/en
Publication of JP2002332691A publication Critical patent/JP2002332691A/en
Withdrawn legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a joint construction between a column and a beam with which the main reinforcement can be arranged even to a position of a column joint of the steel frame. SOLUTION: A steel frame 2 at a joint portion where a second joint reinforcing bar 5b is welded to a lower flange 7 is placed to a coaxial shape at the top end of a steel pipe 4 erected on a pile footing 11, and the same work is performed for other adjacent columns. A steel beam 8 is elected on a bracket 2a opposite to the neighboring joint of the steel frame 8, after welding an end portion of the second joint reinforcing bar 5a to the upper flange 6 of the joint steel frame 2, the unit of the first joint reinforcing bar 3a is inserted from the above to the joint 10, and concrete 9 is filled up to the top of the upper flange 6. A stop formwork 15 is provided around the position of placing an upper steel pipe 13 at the upper portion of the steel beam 8, and a floor slab 18 is formed. Upon completion of one floor, a new steel pipe 4 is placed at the upper portion of the joint of the steel frame in a coaxial shape with the steel pipe 4, and an air gap 17 between the lower end portion and the stop formwork 15 is adhered with concrete.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は建物の構造に係わ
り、柱と鉄骨梁との接合部の仕口部構造に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a structure of a building, and more particularly to a connection structure of a joint between a column and a steel beam.

【0002】[0002]

【従来の技術】図4に従来の柱と梁の仕口部構造を示
す。符号51は充填コンクリート鋼管柱、52は仕口部
鉄骨、53は接合鉄筋、54は鋼管を示している。仕口
部鉄骨52の上下に連設された鋼管54内にはコンクリ
ート55が充填され、充填コンクリート鋼管柱51が形
成されているとともに、複数の接合鉄筋53が、前記仕
口部鉄骨52を挿通して、上下に連設された前記鋼管5
4内に挿入するように、前記鋼管54内の内周に沿って
鉛直方向に配設されている。
2. Description of the Related Art FIG. 4 shows a conventional column and beam connection structure. Reference numeral 51 denotes a filled concrete steel pipe column, reference numeral 52 denotes a connection portion steel frame, reference numeral 53 denotes a joint reinforcing bar, and reference numeral 54 denotes a steel pipe. Concrete 55 is filled in steel pipes 54 provided vertically above and below the connection part steel frame 52 to form a filled concrete steel pipe column 51, and a plurality of connecting reinforcing bars 53 are inserted through the connection part steel frame 52. And the steel pipes 5 connected vertically
4 so as to be inserted into the inside of the steel pipe 54 in the vertical direction along the inner periphery of the steel pipe 54.

【0003】[0003]

【発明が解決しようとする課題】しかし、前記仕口部5
6には前記仕口部鉄骨52が配設されることにより、該
仕口部56の水平断面の一部が塞がれてしまうため、前
記仕口部56を挿通することが可能な前記接合鉄筋53
の配設位置が限定されるとともに、一般的に鉄筋の配設
間隔には制約があるため、前記充填コンクリート鋼管柱
51を構成する鋼管54内に、配設することが可能な前
記接合鉄筋53の本数も限られることとなる。このた
め、前記仕口部鉄骨52と前記充填コンクリート鋼管柱
51の接合強度を高めることを目的に、前記接合鉄筋5
3の本数を増設したい場合には、該接合鉄筋53の配設
位置を確保するため、前記充填コンクリート鋼管柱51
の径を大きくとる等の対策を講じている。
However, the connection 5
6 is provided with the connection part steel frame 52, so that a part of the horizontal cross section of the connection part 56 is closed, so that the connection capable of inserting the connection part 56 is provided. Reinforcing bar 53
The arrangement position of the reinforcing bars is limited, and the arrangement interval of the reinforcing bars is generally limited. Therefore, the joining reinforcing bars 53 that can be arranged in the steel pipes 54 constituting the filled concrete steel pipe columns 51 are provided. Will also be limited. Therefore, in order to increase the joint strength between the connection portion steel frame 52 and the filled concrete steel pipe column 51, the joint rebar 5
When it is desired to increase the number of the steel pipe columns 3, the filled concrete steel pipe columns 51
Take measures such as increasing the diameter of

【0004】上記事情に鑑み、本発明は前記柱の仕口部
における断面の総ての位置で、接合鉄筋を配設すること
が可能な、柱と梁の仕口部構造を提供することを目的と
している。
In view of the above circumstances, the present invention provides a connection structure between a column and a beam, in which joint rebars can be arranged at all positions of the cross section of the connection portion of the column. The purpose is.

【0005】[0005]

【課題を解決するための手段】請求項1記載の柱と梁の
仕口部構造は、仕口部に配した梁接合用のブラケットを
有する仕口部鉄骨と、該仕口部鉄骨の上下に連設された
鋼管と、前記仕口部を挿通してその両端部が上下の前記
鋼管内に挿入される複数の第1の接合鉄筋と、前記鋼管
と前記仕口部の内部に充填されるコンクリートと、を備
える柱と梁の仕口部構造において、仕口部鉄骨の上部フ
ランジおよび下部フランジには、複数の第2の接合鉄筋
の端部が接合されて、上下の鋼管内の鉛直軸方向にそれ
ぞれ挿通されていることを特徴としている。
According to a first aspect of the present invention, there is provided a column and beam connection structure comprising: a connection portion steel frame having a beam joining bracket disposed in the connection portion; And a plurality of first joining rebars, both ends of which are inserted into the upper and lower steel pipes by penetrating the connection part, and filled inside the steel pipe and the connection part. In the joint structure of a column and a beam, the ends of a plurality of second joint reinforcing bars are joined to an upper flange and a lower flange of the joint portion, thereby forming a vertical joint in the upper and lower steel pipes. It is characterized by being inserted in the axial direction.

【0006】請求項2記載の柱と梁の仕口部構造は、前
記第2の接合鉄筋は、上部フランジ及び下部フランジに
接合させるのに代わって、上部フランジ及び下部フラン
ジに設けられた孔を貫通して、前記仕口部鉄骨の上下に
連接された鋼管内で鉛直軸方向に通じて設けられている
ことを特徴としている。
According to a second aspect of the invention, there is provided a connection structure between a column and a beam, wherein the second joint reinforcing bar is provided with holes provided in an upper flange and a lower flange instead of being joined to the upper flange and the lower flange. It is characterized by being provided so as to penetrate and extend in the vertical axis direction in a steel pipe connected vertically above and below the connection portion steel frame.

【0007】請求項3記載の柱と梁の仕口部構造は、前
記柱が鉄筋コンクリートよりなる柱であることを特徴と
している。
[0007] A third aspect of the present invention is characterized in that the column is a column made of reinforced concrete.

【0008】[0008]

【発明の実施の形態】図1に、本発明に係る柱と梁の仕
口部構造の詳細を示す。符号1は充填コンクリート鋼管
柱、2は仕口部鉄骨、3aは第1の接合鉄筋、4は鋼
管、5a、5bは第2の接合鉄筋を示している。図1よ
り明らかなように、充填コンクリート鋼管柱1を構成す
る鋼管4の内部には、鉛直軸方向であり、かつ内周に沿
って間隔をあけて配設された第1の接合鉄筋3aが仕口
部鉄骨2の間隙を挿通し、上下に連設されている鋼管4
内にそれぞれ突き出ているとともに、仕口部鉄骨2に一
方の端部が溶接された第2の接合鉄筋5a、5bも、他
方の端部が該仕口部鉄骨2の上下に連設されている鋼管
4内にそれぞれ突き出ている。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 shows details of a column and beam connection structure according to the present invention. Reference numeral 1 denotes a filled concrete steel pipe column, reference numeral 2 denotes a connection portion steel frame, reference numeral 3a denotes a first joint reinforcing bar, reference numeral 4 denotes a steel pipe, and reference numerals 5a and 5b denote second joint reinforcing bars. As is clear from FIG. 1, inside the steel pipe 4 constituting the filled concrete steel pipe column 1, there are provided first joining reinforcing bars 3a extending in the vertical axis direction and arranged at intervals along the inner periphery. Steel pipes 4 inserted vertically through the gap of the steel frame 2
The second joint rebars 5a and 5b, each of which protrudes inward and whose one end is welded to the joint steel frame 2, have the other end connected vertically above and below the joint steel frame 2. Projecting into the steel pipes 4 which are located.

【0009】前記充填コンクリート鋼管柱1は、前記鋼
管4の中空部にコンクリート9を打設することによりな
る充填コンクリート造の柱であり、該充填コンクリート
鋼管柱1の仕口部10には、仕口部鉄骨2と、複数の第
1の接合鉄筋3aが配設されている。
The filled concrete steel pipe column 1 is a filled concrete column made by placing concrete 9 in the hollow portion of the steel pipe 4. A mouth steel frame 2 and a plurality of first joint reinforcing bars 3a are provided.

【0010】前記仕口部鉄骨2は、十字型を形成し、そ
の四方の端部に鉄骨梁を接合するブラケット2aと、前
記鋼管4と略同径で該ブラケット2aの十字型の中心部
を覆うように設けられる鋼管部2bと、を備えている
(図1(b)参照)。該ブラケット2aの上部フランジ
6上であってウェブと同軸の位置には、第2の接合鉄筋
5aの下端部、また下部フランジ7上であって前記第2
の接合鉄筋5aと同軸の位置には、第2の接合鉄筋5b
の上端部が溶接により固着されており、第2の接合鉄筋
5a、5bはそれぞれ鉛直軸方向に同軸状で前記鋼管4
の内部に上方または下方に通じて設けられている。この
ように、該第2の接合鉄筋5a、5bは各々前記仕口部
鉄骨2の上下に位置しながら、前記ブラケット2aのウ
ェブを介して同軸状でかつ連続性を持つ形状を確保する
こととなる。
The connection part steel frame 2 is formed in a cross shape, and a bracket 2a for joining steel beams to four ends thereof, and a center portion of the cross shape of the bracket 2a having substantially the same diameter as the steel pipe 4 are formed. And a steel pipe portion 2b provided so as to cover (see FIG. 1B). At the position on the upper flange 6 of the bracket 2a and coaxial with the web, the lower end of the second joint reinforcing bar 5a and the lower flange 7 on the second flange 5a
The second joint reinforcing bar 5b is positioned coaxially with the joint reinforcing bar 5a.
The upper ends of the steel pipes 4a and 5b are coaxially formed in the vertical axis direction.
Are provided to communicate with the inside upward or downward. In this way, the second joint reinforcing bars 5a and 5b are positioned above and below the connection portion steel frame 2, respectively, and secure a coaxial and continuous shape through the web of the bracket 2a. Become.

【0011】なお、前記鋼管4への配筋の設計上、前記
第2の接合鉄筋5a、5bの配設位置が、前記上部フラ
ンジ6、及び下部フランジ7上であるが、前記ブラケッ
ト2aのウェブと同軸上でない場合には、前記第2の接
合鉄筋5a、5bと同軸状であって、該上部フランジ6
と下部フランジ7の間に鉄筋や鋼板等を溶接により固着
させることで、前記第2の接合鉄筋5a、5bの連続性
を確保する。もしくは、前記上部フランジ6、および下
部フランジ7の第2の接合鉄筋5a、5bの設置位置に
孔を設け、高さ方向の位置決め、及び脱落防止の機能を
有する突起を設けた第1の接合鉄筋3aを挿入する等の
工夫を行い、前記仕口部10に配置する接合鉄筋の連続
性を確保する。
Although the second joint reinforcing bars 5a and 5b are arranged on the upper flange 6 and the lower flange 7 in terms of the arrangement of the reinforcing bars on the steel pipe 4, the web of the bracket 2a is provided. When the upper flange 6 is not coaxial with the second joint reinforcing bars 5a and 5b,
The continuity of the second joint reinforcing bars 5a and 5b is secured by fixing a reinforcing bar, a steel plate or the like between the lower flange 7 and the lower flange 7 by welding. Alternatively, a hole is provided in the upper flange 6 and the lower flange 7 at a position where the second joint reinforcing bars 5a and 5b are installed, and a first joint reinforcing bar provided with a projection having functions of positioning in the height direction and preventing falling off. By devising, for example, inserting 3a, continuity of the joint reinforcing bars arranged in the connection part 10 is ensured.

【0012】一方、複数の該第1の接合鉄筋3aは、2
本の補助筋3bにより前記鋼管4の内部に収まる程度の
径を有する円筒状にユニット化された状態で、前記仕口
部10に配設されている。図1(b)に示すように、こ
れら第1の接合鉄筋3aと第2の接合鉄筋5a、5bと
は、周方向に等間隔をあけて配置されることとなる。
On the other hand, the plurality of first joint reinforcing bars 3a
It is arranged in the connection part 10 in a state where it is unitized into a cylindrical shape having a diameter enough to fit inside the steel pipe 4 by the auxiliary muscle 3b. As shown in FIG. 1B, the first joint reinforcing bars 3a and the second joint reinforcing bars 5a and 5b are arranged at equal intervals in the circumferential direction.

【0013】このとき、該第1の接合鉄筋3aに取り付
けられた前記補助筋3bの1本は、ユニット化された前
記第1の接合鉄筋3aを前記仕口部10に建て込む際
に、該補助筋3bを前記仕口部鉄骨2の上部フランジ6
に載置することにより、前記第1の接合鉄筋3aの高さ
位置を確保できるような位置に取り付けられている。こ
のように、前記補助筋3bは、該第1の接合鉄筋3aの
ユニット形状の確保と建て込み時の高さ方向の位置の確
保の2つの機能を持たせることを目的に、2本設置する
ものである。
At this time, when one of the auxiliary reinforcing bars 3b attached to the first connecting reinforcing bar 3a is to be built into the connection portion 10 when the unitized first connecting reinforcing bar 3a is installed, The auxiliary bar 3b is connected to the upper flange 6 of the connection part steel frame 2.
Is mounted at a position where the height position of the first joint reinforcing bar 3a can be secured. As described above, two auxiliary reinforcing bars 3b are provided for the purpose of having two functions of securing the unit shape of the first joining reinforcing bar 3a and securing the position in the height direction at the time of erection. Things.

【0014】また、該第1の接合鉄筋3aをユニット化
する際には、第1の接合鉄筋3aが前記仕口部鉄骨2を
挿通できるよう、前記鋼管4の水平断面を一部塞ぐこと
となる前記該仕口部鉄骨2の前記ブラケット2aの配設
位置をあらかじめ避けるような位置に配置した上で、該
第1の接合鉄筋3aをユニット化する。これにより、該
第1の接合鉄筋3aの一方の端部は、前記仕口部鉄骨2
の下部に設けられている鋼管4の内部に、また該第1の
接合鉄筋3aの他方の端部は、前記仕口部鉄骨2の上部
に新たに設けられる鋼管4の内部に挿入されることとな
る。
When the first joint reinforcing bar 3a is unitized, a part of the horizontal section of the steel pipe 4 is closed so that the first joint reinforcing bar 3a can pass through the connection portion steel frame 2. The first joint reinforcing bar 3a is unitized after the bracket 2a of the connection portion steel frame 2 is disposed at a position where it is to be avoided in advance. Thereby, one end of the first joint reinforcing bar 3a is connected to the connection portion steel frame 2.
And the other end of the first joint reinforcing bar 3a is inserted into a steel pipe 4 newly provided on the upper part of the connection portion steel frame 2. Becomes

【0015】次に、本発明の施工方法の一例を示す。前
記鋼管4を杭基礎11の上に建て込んだ後(図2(a)
参照)、あらかじめ天地を逆にして配置した仕口部鉄骨
2の下部フランジ7に前記第2の接合鉄筋5bを溶接に
より接合させた前記仕口部鉄骨2(図2(b)参照)を
該鋼管4の上端に同軸状になるよう、天地を戻して載置
する(図2(c)参照)。また、隣接する他の充填コン
クリート鋼管柱1の建設予定位置に対しても同様に、前
記鋼管4及び前記仕口部鉄骨2を設置する。この後、隣
接する前記仕口部鉄骨2のそれぞれ対向するブラケット
2aにスプライズプレートを用いたボルト及びナットの
締結により鉄骨梁8を架設する(図2(d)参照)。
Next, an example of the construction method of the present invention will be described. After the steel pipe 4 is built on the pile foundation 11 (FIG. 2 (a)
2), the second connection reinforcing bar 5b is welded to the lower flange 7 of the connection portion steel frame 2 which is arranged upside down in advance and welded (see FIG. 2 (b)). The top and the bottom are placed back so that they are coaxial with the upper end of the steel pipe 4 (see FIG. 2C). In addition, the steel pipe 4 and the connection part steel frame 2 are similarly installed at the position where the other filled concrete steel pipe column 1 is to be constructed. Thereafter, the steel beams 8 are erected on the brackets 2a of the joints 2 adjacent to each other by fastening bolts and nuts using splice plates (see FIG. 2D).

【0016】この後、前記仕口部鉄骨2の上部フランジ
6に対して、下部フランジ7に溶接した前記第2の接合
鉄筋5bと同軸となるように前記第2の接合鉄筋5aの
端部を溶接した後(図2(f)参照)、前記補助筋3b
を用いて仮組みした前記該第1の接合鉄筋3aのユニッ
ト(図2(e)参照)を、ユニットの前記補助筋3bが
前記仕口部鉄骨2の上部フランジ6に載置されるよう
に、前記仕口部鉄骨2の上方より前記仕口部10の中に
挿入する(図2(g)参照)。この状態で、前記仕口部
鉄骨2の上方よりコンクリート9を打設し、前記鋼管4
の中空部が充填されることにより前記充填コンクリート
鋼管柱1が形成される。さらに、前記コンクリート9が
前記仕口部鉄骨2の上部フランジ6の天端まで充填され
ることにより、前記該第1の接合鉄筋3aの下半、前記
仕口部鉄骨2、および前記充填コンクリート鋼管柱1が
一体的に固着されることとなる(図2(h)参照)。
Thereafter, the end of the second joint reinforcing bar 5a is coaxial with the upper flange 6 of the connection portion steel frame 2 so as to be coaxial with the second joint reinforcing bar 5b welded to the lower flange 7. After welding (see FIG. 2 (f)), the auxiliary muscle 3b
The unit (see FIG. 2 (e)) of the first joint reinforcing bar 3a temporarily assembled by using the auxiliary reinforcing bar 3b of the unit is mounted on the upper flange 6 of the connection portion steel frame 2. Then, it is inserted into the connection part 10 from above the connection part steel frame 2 (see FIG. 2 (g)). In this state, concrete 9 is poured from above the connection part steel frame 2 and the steel pipe 4
Is filled to form the filled concrete steel pipe column 1. Further, the concrete 9 is filled up to the top end of the upper flange 6 of the connection portion steel frame 2, so that the lower half of the first joint reinforcing bar 3 a, the connection portion steel frame 2, and the filled concrete steel pipe The column 1 is integrally fixed (see FIG. 2 (h)).

【0017】一方、先に仮設した前記鉄骨梁8の上部に
は床型枠(図示せず)を設置し、スラブ配筋14を施す
とともに、前記仕口部鉄骨2の上部で、今後の作業にお
いて新たな鋼管鋼管4を載置する位置の周囲に止め型枠
15を設けた上で、場所打ちコンクリート16を打設
し、床スラブ18を形成する(図1(a)参照)。
On the other hand, a floor form (not shown) is installed on the upper part of the steel beam 8 which has been temporarily provided, slab reinforcements 14 are provided, and future work is performed on the upper part of the connection part steel frame 2. In FIG. 1, after a stop formwork 15 is provided around the position where the new steel pipe 4 is placed, cast-in-place concrete 16 is cast to form a floor slab 18 (see FIG. 1A).

【0018】このように、1フロアを終了させた後、前
記仕口部鉄骨2の上部フランジ6より突出した前記第1
の接合鉄筋3a、および前記第2の接合鉄筋5aを内包
し、かつ前記仕口部鉄骨2の下部に設けられた前記鋼管
4と同軸状になるように、前記仕口部鉄骨2の上部に新
たに鋼管4を載置する。この後、該鋼管4に対して十分
な位置決めを行った上で、その下端部と床スラブ18の
形成時に用いた前記止め型枠15との空隙17をコンク
リートにより固着しておく。以降は、上述したものと同
様な作業を繰り返すことにより、次フロアを施工してい
く。
As described above, after one floor is completed, the first projecting portion projecting from the upper flange 6 of the connection portion steel frame 2 is obtained.
And the upper part of the connection part steel frame 2 so as to be coaxial with the steel pipe 4 provided at the lower part of the connection part steel frame 2. A new steel pipe 4 is placed. Thereafter, after sufficient positioning with respect to the steel pipe 4, a gap 17 between the lower end portion thereof and the stop form 15 used for forming the floor slab 18 is fixed by concrete. Thereafter, the next floor is constructed by repeating the same operations as those described above.

【0019】なお、本実施例では柱として充填コンクリ
ート鋼管柱1を採用したが、鉄筋コンクリート柱19で
あっても良い。この場合には、前記第1の接合鉄筋3
a、および前記第2の接合鉄筋5a、5bは柱の全長に
わたって連続している必要がある。このため、基礎11
および前記鉄筋コンクリート柱19を接続するように設
けられた鉄筋12と、前記第1の接合鉄筋3aの下端部
及び前記第2の接合鉄筋5bは、重ね継ぎ手を形成させ
る必要がある(図3参照)。
In this embodiment, the filled concrete steel column 1 is used as the column, but a reinforced concrete column 19 may be used. In this case, the first joint reinforcing bar 3
a and the second joint reinforcing bars 5a and 5b need to be continuous over the entire length of the column. Therefore, the basics 11
It is necessary to form a lap joint between the reinforcing bar 12 provided to connect the reinforced concrete columns 19, the lower end of the first connecting reinforcing bar 3a, and the second connecting reinforcing bar 5b (see FIG. 3). .

【0020】また、前記仕口部鉄骨2の下部に位置する
前記鋼管4に設けた前記第1の接合鉄筋3aの上端部及
び前記第2の接合鉄筋5aと、前記仕口部鉄骨2の上部
に位置する前記鋼管4に設けられた前記第1の接合鉄筋
3aの下端部及び前記第2の接合鉄筋5bとの間にも、
重ね継ぎ手を形成させる必要がある。
Further, the upper end of the first joint reinforcing bar 3a and the second joint reinforcing bar 5a provided on the steel pipe 4 located below the joint steel frame 2, and the upper part of the joint steel frame 2 Between the lower end of the first joint reinforcing bar 3a provided in the steel pipe 4 and the second joint reinforcing bar 5b.
It is necessary to form a lap joint.

【0021】さらに、施工段階では、前記鉄筋コンクリ
ート柱19にコンクリート9を打設する際の柱型枠20
を用いて前記仕口部鉄骨2を仮支持する方法もあるが、
鉄筋コンクリート柱19内に、あらかじめ前記仕口部鉄
骨2を仮支持可能な部材長を有する捨て鋼管を内装し、
これにより仮支持する等の方法により施工を行ってもよ
い。
Further, in the construction stage, a column form 20 for placing concrete 9 on the reinforced concrete column 19 is used.
There is also a method of temporarily supporting the connection part steel frame 2 using
In a reinforced concrete column 19, a discarded steel pipe having a member length capable of temporarily supporting the connection part steel frame 2 is previously provided,
This may be performed by a method such as temporary support.

【0022】上述の構成によれば、前記仕口部10にお
いて前記仕口部鉄骨2の建て込み位置にも第2の接合鉄
筋5a、5を配設することができるため、前記仕口部鉄
骨2を挿通する前記第1の接合鉄筋3aの本数を増やす
必要はなく、さらに該第1の接合鉄筋3aの増設を目的
として、前記充填コンクリート鋼管柱1の径を大きく取
る必要はないため、コスト高を回避することができる。
According to the above-described structure, the second joint reinforcing bars 5a and 5 can be disposed in the joint 10 at the position where the joint steel 2 is erected. It is not necessary to increase the number of the first joint reinforcing bars 3a through which the second concrete bar 2 is inserted, and it is not necessary to increase the diameter of the filled concrete steel tubular column 1 for the purpose of increasing the first joint reinforcing bars 3a. High can be avoided.

【0023】また、前記仕口部鉄骨2の上フランジ6お
よび下部フランジ7に、直接第2の接合鉄筋5a、5b
を溶接固定するため、現場で対応できる簡略な構造かつ
簡単な作業で、前記充填コンクリート鋼管柱1の曲げ耐
力を増すことができるとともに、前記仕口部10とのせ
ん断伝達においても効果的な外力の作用に強い仕口部構
造とすることができる。
The upper and lower flanges 6 and 7 of the connection part steel frame 2 are directly connected to second joint reinforcing bars 5a and 5b.
, The bending strength of the filled concrete steel tubular column 1 can be increased by a simple structure and simple work that can be performed on site, and an effective external force is also effective in shear transmission with the connection portion 10. The structure of the connection part can be made strong against the action of

【0024】[0024]

【発明の効果】請求項1の柱と梁の仕口部構造によれ
ば、仕口部に配した梁接合用のブラケットを有する仕口
部鉄骨と、該仕口部鉄骨の上下に連設された鋼管と、前
記仕口部を挿通してその両端部が上下の前記鋼管内に挿
入される複数の第1の接合鉄筋と、前記鋼管と前記仕口
部の内部に充填されるコンクリートと、を備える柱と梁
の仕口部構造において、仕口部鉄骨の上部フランジおよ
び下部フランジには、複数の第2の接合鉄筋の端部が接
合されて、上下の鋼管内の鉛直軸方向にそれぞれ挿通さ
れていることから、簡略な装備で柱の曲げ耐力を増すこ
とができるとともに、仕口部のせん断伝達においても効
果的な外力の作用に強い仕口部構造とすることができる
だけでなく、前記鉄骨梁の建て込み位置にも鉄筋を配設
することができるため、仕口部を貫通する第1の鉄筋の
本数を増やす必要がなく、さらに仕口部を貫通する第1
の鉄筋の増設を目的に前記柱の径を大きく取る必要がな
いため、コスト高を回避することができる。
According to the first aspect of the present invention, there is provided a joint between a column and a beam, and a joint having a beam-joining bracket disposed at the joint, and a vertically extending joint above and below the joint. Steel pipe, a plurality of first joining rebars whose both ends are inserted into the upper and lower steel pipes through the connection part, and concrete filled into the steel pipe and the connection part. In the joint structure of a column and a beam, the ends of a plurality of second joint reinforcing bars are joined to the upper flange and the lower flange of the joint steel frame, and the ends are connected in the vertical axis direction in the upper and lower steel pipes. Since each is inserted, not only can the bending strength of the column be increased with simple equipment, but also the joint structure that is strong against the effect of external force even in the shear transfer of the joint can be made. In addition, it is possible to dispose a reinforcing bar also at the position where the steel beam is erected. , There is no need to increase the number of first reinforcing bars penetrating the Joint portion, first to further penetrate the Joint portion
Since it is not necessary to increase the diameter of the column for the purpose of increasing the reinforcing bar, cost can be avoided.

【0025】請求項2の柱と梁の仕口部構造によれば、
前記第2の接合鉄筋は、上部フランジ及び下部フランジ
に接合させるのに代わって、上部フランジ及び下部フラ
ンジに設けられた孔を貫通して、前記仕口部鉄骨の上下
に連接された鋼管内で鉛直軸方向に通じて設けられてい
ることから、上記と同様に簡略な装備で柱の曲げ耐力を
増すことができるとともに、仕口部のせん断伝達におい
ても効果的な外力の作用に強い仕口部構造とすることが
できる
According to the joint structure of the pillar and the beam of the second aspect,
Instead of joining the second joint reinforcing bar to the upper flange and the lower flange, the second joint reinforcing bar passes through holes provided in the upper flange and the lower flange, and is formed in a steel pipe connected vertically above and below the connection portion steel frame. Since the connection is provided in the vertical axis direction, the bending resistance of the column can be increased with the simple equipment as described above, and the connection is strong against the effect of external force even in the shear transmission of the connection. Can be part structure

【0026】請求項3の柱と梁の仕口部構造によれば、
前記柱は鉄筋コンクリートよりなる柱であることから、
上記と同様に簡略かつ合理的な構造で施工性に優れ、施
工の簡略化、省力化、工費削減を図ることができる。
According to a third aspect of the present invention, there is provided a connection structure between a pillar and a beam.
Since the pillar is a pillar made of reinforced concrete,
Similar to the above, it has a simple and rational structure and is excellent in workability, and simplification of work, labor saving, and reduction of construction cost can be achieved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係る柱と梁の仕口部構造の詳細を示す
ものである。
FIG. 1 shows details of a connection structure between a pillar and a beam according to the present invention.

【図2】本発明に係る柱と梁の仕口部構造の施工手順を
示すものである。
FIG. 2 is a view showing a construction procedure of a connection structure between a pillar and a beam according to the present invention.

【図3】本発明に係る鉄筋コンクリート造の柱と梁の仕
口部構造の詳細を示すものである。
FIG. 3 shows details of a reinforced concrete column / beam connection structure according to the present invention.

【図4】従来の柱と梁の仕口部構造の詳細を示すもので
ある。
FIG. 4 shows details of a conventional column and beam connection structure.

【符号の説明】[Explanation of symbols]

1 充填コンクリート鋼管柱 2 仕口部鉄骨 2a ブラケット 2b 鋼管部 3a 第1の接合鉄筋 3b 補助筋 4 鋼管 5a 第2の接合鉄筋 5b 第2の接合鉄筋 6 上部フランジ 7 下部フランジ 8 鉄骨梁 9 コンクリート 10 仕口部 11 杭基礎 12 鉄筋 13 上部鋼管 14 スラブ配筋 15 止め型枠 16 場所打ちコンクリート 17 空隙 18 床スラブ 19 鉄筋コンクリート柱 20 柱型枠 51 柱 52 仕口部鉄骨 53 鉄筋 54 鋼管 55 コンクリート 56 仕口部 DESCRIPTION OF SYMBOLS 1 Filled concrete steel pipe column 2 Steel part of connection part 2a Bracket 2b Steel pipe part 3a 1st joint reinforcement 3b Auxiliary reinforcement 4 Steel pipe 5a 2nd joint reinforcement 5b 2nd joint reinforcement 6 Upper flange 7 Lower flange 8 Steel beam 9 Concrete 10 Connection part 11 Pile foundation 12 Reinforcement 13 Upper steel pipe 14 Slab reinforcement 15 Stopping form 16 Cast-in-place concrete 17 Air gap 18 Floor slab 19 Reinforced concrete column 20 Column formwork 51 Column 52 Connection part steel frame 53 Reinforcing steel 54 Steel pipe 55 Concrete 56 Mouth

フロントページの続き Fターム(参考) 2E125 AA04 AA14 AA45 AA57 AA72 AB01 AB11 AB17 AC04 AC07 AC16 AE04 AE07 AF03 AG10 AG12 AG28 BB01 BB22 BD01 BE05 BE08 BF01 CA05 Continued on the front page F term (reference) 2E125 AA04 AA14 AA45 AA57 AA72 AB01 AB11 AB17 AC04 AC07 AC16 AE04 AE07 AF03 AG10 AG12 AG28 BB01 BB22 BD01 BE05 BE08 BF01 CA05

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 仕口部に配した梁接合用のブラケットを
有する仕口部鉄骨と、該仕口部鉄骨の上下に連設された
鋼管と、前記仕口部を挿通してその両端部が上下の前記
鋼管内に挿入される複数の第1の接合鉄筋と、前記鋼管
と前記仕口部の内部に充填されるコンクリートと、を備
える柱と梁の仕口部構造において、仕口部鉄骨の上部フ
ランジ及び下部フランジには、複数の第2の接合鉄筋の
端部が接合されて、それら第2の接合鉄筋は上下の鋼管
内で鉛直軸方向にそれぞれ上方または下方に通じて設け
られていることを特徴とする柱と梁の仕口部構造。
1. A steel joint having a beam-joining bracket disposed at a joint, a steel pipe connected vertically above and below the steel joint, and both ends of the steel pipe inserted through the joint. In a column and beam connection structure comprising: a plurality of first joint reinforcing bars inserted into the upper and lower steel pipes; and concrete filled into the connection between the steel pipe and the connection, Ends of a plurality of second joint reinforcing bars are joined to the upper flange and the lower flange of the steel frame, and the second joint reinforcing bars are provided in the upper and lower steel pipes so as to extend upward or downward in the vertical axis direction, respectively. The structure of the connection between the pillar and the beam, characterized in that
【請求項2】 請求項1記載の柱と梁の仕口部構造にお
いて、前記第2の接合鉄筋は、上部フランジ及び下部フ
ランジに接合させるのに代わって、上部フランジ及び下
部フランジに設けられた孔を貫通して、前記仕口部鉄骨
の上下に連接された鋼管内で鉛直軸方向に通じて設けら
れていることを特徴とする柱と梁の仕口部構造。
2. The column and beam connection structure according to claim 1, wherein the second reinforcing bar is provided on the upper flange and the lower flange instead of being bonded to the upper flange and the lower flange. A joint structure of a column and a beam, wherein the joint structure is provided in a steel pipe vertically penetrating through a hole and connected vertically to the joint steel frame.
【請求項3】 請求項1、2記載の柱と梁の仕口構造に
おいて、前記柱は鉄筋コンクリートよりなる柱であるこ
とを特徴とする柱と梁の仕口部構造。
3. The joint structure between a column and a beam according to claim 1, wherein the column is a column made of reinforced concrete.
JP2001139213A 2001-05-09 2001-05-09 Joint construction between column and beam Withdrawn JP2002332691A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001139213A JP2002332691A (en) 2001-05-09 2001-05-09 Joint construction between column and beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001139213A JP2002332691A (en) 2001-05-09 2001-05-09 Joint construction between column and beam

Publications (1)

Publication Number Publication Date
JP2002332691A true JP2002332691A (en) 2002-11-22

Family

ID=18986022

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001139213A Withdrawn JP2002332691A (en) 2001-05-09 2001-05-09 Joint construction between column and beam

Country Status (1)

Country Link
JP (1) JP2002332691A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1298945C (en) * 2004-02-13 2007-02-07 哈尔滨工业大学 Unshored self supporting cast-in-situ concrete structure
WO2008133460A1 (en) * 2007-04-26 2008-11-06 M.C.S.Tech Composite concrete column and construction method using the same
CN102505846A (en) * 2011-11-21 2012-06-20 中国建筑第八工程局有限公司 Steel pipe column bearing table girder connection construction method
CN103628571A (en) * 2013-12-09 2014-03-12 广州市第一建筑工程有限公司 Beam-column joint for reverse construction method and construction method
JP2016075131A (en) * 2014-10-09 2016-05-12 清水建設株式会社 Composite structure
JP2019011675A (en) * 2018-09-25 2019-01-24 清水建設株式会社 Composite structure

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1298945C (en) * 2004-02-13 2007-02-07 哈尔滨工业大学 Unshored self supporting cast-in-situ concrete structure
WO2008133460A1 (en) * 2007-04-26 2008-11-06 M.C.S.Tech Composite concrete column and construction method using the same
CN102505846A (en) * 2011-11-21 2012-06-20 中国建筑第八工程局有限公司 Steel pipe column bearing table girder connection construction method
CN102505846B (en) * 2011-11-21 2013-10-30 中国建筑第八工程局有限公司 Steel pipe column bearing table girder connection construction method
CN103628571A (en) * 2013-12-09 2014-03-12 广州市第一建筑工程有限公司 Beam-column joint for reverse construction method and construction method
JP2016075131A (en) * 2014-10-09 2016-05-12 清水建設株式会社 Composite structure
JP2019011675A (en) * 2018-09-25 2019-01-24 清水建設株式会社 Composite structure

Similar Documents

Publication Publication Date Title
KR200381303Y1 (en) Form system for joint between retaining wall and slab of basement floor
KR100631363B1 (en) Panel zone system of y shape tied column reinforced with high tension bolts
JP2001123534A (en) Construction of composite precast beam
JP2002332691A (en) Joint construction between column and beam
JP2001173097A (en) Structure of precast composite beam
JP7213154B2 (en) Top slab construction method for shaft and top slab structure
JP2003206569A (en) Connection structure of complex structure building
JP2004263501A (en) Beam-column joint structural body
JP2769937B2 (en) Steel tube concrete column in underground reverse driving method
JP3586121B2 (en) Mixed structure of reinforced concrete column and steel beam and its construction method
KR20210004289A (en) Transfer Structure Construction Method Using U-shaped Steel Girder
JP2002364072A (en) Beam for hybrid-structure frame
JP2645329B2 (en) Pillar construction method
JPH08319695A (en) Underground beam reinforcement assembly and underground beam construction method
JPH1150538A (en) Building and method for constructing the same
JP2003193564A (en) Column-beam structural body, its construction method, and connection metal fitting
JPS6217233A (en) Foundation base column
JPH01203537A (en) Src precast beam and junction structure of column and beam
JPH08239807A (en) Composite column base structure
JP2004197347A (en) Construction method of cross girder-integrated concrete floor slab
JP2984626B2 (en) PC pillar construction method and its PC pillar
JP3608086B2 (en) Column / beam joint structure
JP2893406B2 (en) Precast concrete beam-column joining method
JPH02167937A (en) Connecting work of steel plate-concrete structure
JPH116162A (en) Construction method for reinforced concrete underground external wall

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20080805