JPH03107038A - Constructing method for structure - Google Patents

Constructing method for structure

Info

Publication number
JPH03107038A
JPH03107038A JP24249089A JP24249089A JPH03107038A JP H03107038 A JPH03107038 A JP H03107038A JP 24249089 A JP24249089 A JP 24249089A JP 24249089 A JP24249089 A JP 24249089A JP H03107038 A JPH03107038 A JP H03107038A
Authority
JP
Japan
Prior art keywords
construction
work
constructed
formwork
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP24249089A
Other languages
Japanese (ja)
Other versions
JP2761527B2 (en
Inventor
Koji Kondo
弘司 近藤
Tomoaki Ichikawa
智章 市川
Junichiro Maeda
純一郎 前田
Nobuhiro Okuyama
信博 奥山
Tadashi Okano
正 岡野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP1242490A priority Critical patent/JP2761527B2/en
Publication of JPH03107038A publication Critical patent/JPH03107038A/en
Application granted granted Critical
Publication of JP2761527B2 publication Critical patent/JP2761527B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To improve the productivity of constructing work by constructing a structure along core parts constructed for fixed layers from its highest part on the ground, and pushing up a constructed part using a weight lifting means in a state where it attains a fixed height and can stand for itself, and repeating these works. CONSTITUTION:A core part 1 is constructed using an automatically rising formwork consisting of a provisional part, a formwork part, a jack and a bracket, and a jack 12 is also installed at a position where a pillar 13 of a building is vertically set. After the advanced construction of the core part 1 for two layers, beams 14 and pillars 13 for three layers are simultaneously constructed from the highest part of the building, and a pillar bottom formwork and a pillar formwork are arranged on the above constructed part, and concrete is deposited for the pillar 13 and a slab 24. At a stage where the concrete becomes so hard that the pillar can stand for itself, the jack 12 is extended to push up one layer of a structural body, and the constructing work for lower floors is continued in order, and these works are repeated. Thus the productivity of the constructing work can be improved.

Description

【発明の詳細な説明】 「産業上の利用分野」 この発明は、建築・土木構造物の構築方法に係り、特に
、構築作業の生産性向上を図りうる構造物の構築方法に
関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method of constructing an architectural/civil engineering structure, and particularly to a method of constructing a structure that can improve the productivity of construction work.

「従来の技術およびその課題」 建築・土木構造物の構築作業は、他の技術分野に比較し
てその生産性向上の程度が大変遅れており、近年の労働
者不足の現象とあいまって構造物の構築作業の生産性向
上の達或は大きな課題となっている。
"Conventional technologies and their issues" The productivity of construction work for architectural and civil engineering structures has lagged far behind that of other technical fields, and combined with the recent labor shortage phenomenon, Improving the productivity of construction work has become a major challenge.

構造物の構築作業の生産性向上を阻害する要因の一つと
しては、建築・土木構造物の作業工桟の特殊性がある。
One of the factors that hinders the improvement of productivity in construction work of structures is the peculiarity of the construction workpieces of architectural and civil engineering structures.

例えば、一般に複数階の建築物を構築する場合は、最下
階から順に上方に向って施工され、従って、構築作業は
常にその時点で構築が終了した部分の最上階で行なわれ
ることとなる。
For example, when constructing a multi-story building, construction is generally carried out from the bottom floor upwards, and therefore construction work is always performed on the top floor of the part that has been completed at that point.

このため、降雨、強風時等には作業員が危険な状態にさ
らされ、あるいは作業を中止せざるを得なくなることで
、作業の進行状況が天候に大きく左右される結果となる
For this reason, in times of rain or strong winds, workers are exposed to dangerous conditions or are forced to stop work, resulting in the progress of work being greatly influenced by the weather.

また、型枠等の仮設材や仮設機械も、作業の進行に伴っ
て順次上階に盛り替えたりあるいは積層する必要があり
、最終的な解体撤去も含めて多くの手間や時間を必要と
すると共に、その作業自体危険性を伴う場合も多い。当
然、資材も作業の進行に伴って順次上階に運搬する必要
があり、その運搬作業に多くの手間や時間がかかると共
に、その管理も煩雑なものとなる。
In addition, temporary materials such as formwork and temporary machinery need to be moved or stacked on top of each other as the work progresses, which requires a lot of effort and time, including the final disassembly and removal. In addition, the work itself is often dangerous. Naturally, it is necessary to transport materials to the upper floors one after another as the work progresses, and the transport work requires a lot of effort and time, and its management becomes complicated.

さらに、生産性向上のために構築作業の機械化を図ろう
とする場合、前述のような作業現場の変化に対応しうる
機械の存在を必要とするが、一般に使用されている溶接
ロボット等の自動化機械は可搬性や作業状況の変化に対
する柔軟な対応といった面でその適用に問題が多い。従
って、機械化推進のためには各施工現場専用の機械を用
いるか、あるいは高度な機能を付加することで汎用性を
確保した機械を用いるしかなく、いずれにしてもコスト
高を招いて現実的でない。
Furthermore, when attempting to mechanize construction work to improve productivity, it is necessary to have machines that can respond to changes in the work site as described above, but automated machines such as commonly used welding robots are necessary. However, there are many problems in its application in terms of portability and flexible response to changes in work conditions. Therefore, in order to promote mechanization, there is no choice but to use specialized machinery for each construction site, or to use machines that have been added with advanced functions to ensure versatility, which is impractical due to high costs. .

近年、このような課題を解決することを目的として、1
階部分で構造物をその最上部から構築し、順次ジャッキ
アップしつり下階部分へと構築を進める、いわゆるジャ
ッキアップ工法と呼ばれる工法が提案されている。この
工法によれば、構築物の構築作業を常時一定位置で行う
ことができ、機材搬送の手間等を大幅に削減できて構造
物の構築作業の生産性向上を図ることができる。しかし
ながら、構造物をジャッキアップする関係上、構築作業
中はこの構造物と地盤との間は縁が切れた状態にあり、
地震力等の水平力が作用した場合に水平移動あるいは転
倒のおそれがあるため、現実の適用が困難である。
In recent years, with the aim of solving such issues, 1
A construction method called the jack-up construction method has been proposed, in which a structure is built from the top of the floor and then jacked up one by one to proceed with construction to the lower floors. According to this construction method, the construction work of the structure can be always performed at a fixed position, and the time and effort of transporting equipment can be significantly reduced, thereby improving the productivity of the construction work of the structure. However, because the structure is being jacked up, there is a disconnect between the structure and the ground during construction.
Actual application is difficult because there is a risk of horizontal movement or overturning when horizontal force such as earthquake force is applied.

この発明は前記事情に鑑みてなされたものであり、構築
作業の生産性向上を図ることができ、しかも構築作業中
でも水平力に対する対応を為しうる構造物の構築方法の
提供を目的としている。
This invention has been made in view of the above circumstances, and aims to provide a method for constructing a structure that can improve the productivity of construction work and can also cope with horizontal forces even during construction work.

「課題を解決するための手段」 そこでこの発明は、構造物のコア部をその下部から上部
に向って所定層分だけ構築すると共に、このコア部に沿
って地上で構造物をその最上部から構築し、構築した部
分がコア部の構築高さ以下の所定高さに達しかつ自立可
能となった状態でこの構築部分を揚重手段により上方に
押し上げ、さらに押し上げられた構築部分の下部につな
げて地上でこの構築部分の直下を構築する工程と前記押
し上げ工程とを順次繰り返すことで構造物全体の構築を
完成することを特徴とする構造物の構築方法により、前
記課題を解決せんとしている。
``Means for Solving the Problems'' Therefore, the present invention is to construct a core part of a structure by a predetermined number of layers from the bottom to the top, and to build the structure on the ground from the top along this core part. When the constructed part reaches a predetermined height below the construction height of the core part and becomes self-supporting, this constructed part is pushed upward by a lifting means and connected to the lower part of the constructed part that has been further pushed up. The above-mentioned problem is solved by a structure construction method characterized in that the construction of the entire structure is completed by sequentially repeating the step of constructing directly below the construction part on the ground and the pushing up step.

「実施例」 以下、この発明の実施例について図面を参照して説明す
る。
"Embodiments" Hereinafter, embodiments of the present invention will be described with reference to the drawings.

第1図ないし第15図は、この発明の構造物の構築方法
を多層建築物の構築方法に適用したー実施例を示す図で
ある。以下、工程順に説明する。
1 to 15 are diagrams showing an embodiment in which the method for constructing a structure of the present invention is applied to a method for constructing a multi-story building. The steps will be explained below in order.

(i)コア部構築 第2図に示すように、建築物の中央部に設けられたコア
部1を、建築物の他の部分に先行して構築を開始する。
(i) Construction of Core Section As shown in FIG. 2, construction of the core section 1 provided at the center of the building is started prior to the construction of the other parts of the building.

コア部1の構築高さは任意であるが、1層分程度である
と後述する構築中の水平力に対する躯体の支持が弱くな
り、一方、あまり多層に亙って先行して構築したのでは
本工法の利点゛である工期短縮の効果が薄くなる。従っ
て、2層分程度を先行して構築することが好ましい。な
お、コア部lの下端は地盤G,中に埋設しておく。
The construction height of the core part 1 is arbitrary, but if it is about one layer, the support of the frame against the horizontal force during construction, which will be described later, will be weakened, and on the other hand, if too many layers are constructed in advance. The advantage of this construction method, which is to shorten the construction period, is diminished. Therefore, it is preferable to construct approximately two layers in advance. Note that the lower end of the core portion I is buried in the ground G.

コア部lの構築方法は任意であり、従来より周知のよう
に、鉄筋を四角簡状に組み上げてその内外を型枠で包囲
し、この型枠内にコンクリートを打設して鉄筋コンクリ
ート造のコア部1を構築してもよい。本実施例では、第
8図ないし第9図に示すような自動上昇型枠2を使用し
てコア部1を構築する。
The construction method for the core part l is arbitrary, and as is well known in the past, reinforcing bars are assembled into a rectangular shape, the inside and outside of the reinforcing bars are surrounded by formwork, and concrete is poured into this formwork to form a reinforced concrete core. Part 1 may be constructed. In this embodiment, the core section 1 is constructed using a self-rising formwork 2 as shown in FIGS. 8 and 9.

この自動上昇型枠2は、略垂直方向に立設された仮設支
柱3と、この支柱3に沿って移動自在に取り付けられた
型枠部4と、この型枠部4上部に配設されたジャソキ5
と、このジャッキ5上部に配設され、前記支柱3に沿っ
て移動自在とされたブラケット6とから概略構戊されて
いる。
This self-rising formwork 2 includes a temporary support 3 erected in a substantially vertical direction, a formwork part 4 movably attached along this support 3, and a formwork part 4 disposed above the formwork part 4. Jasoki 5
and a bracket 6 disposed above the jack 5 and movable along the support column 3.

また、型枠部4は、前記ジャッキ5下方に位置するフレ
ーム7と、このフレーム7の下部前後(第8図において
左右)からそれぞれ下方に延出され、フレーム7に回動
自在に支持された1対のヨーク8、8と、これらヨーク
8、8の相対向する面にそれぞれ設けられた堰板9、9
と、相対向するヨーク8、8に向って突設された脱型用
ジャソキto,toと、これら脱型用ジャッキ10,1
0間に回動自在に連結されたロッド1lとから構戊され
ている。
Further, the formwork part 4 extends downward from the frame 7 located below the jack 5 and from the lower front and rear (left and right in FIG. 8) of the lower part of the frame 7, and is rotatably supported by the frame 7. A pair of yokes 8, 8 and weir plates 9, 9 provided on opposing surfaces of these yokes 8, 8, respectively.
, demolding jacks to, to protruding toward the opposing yokes 8, 8, and these demolding jacks 10, 1.
The rod 1l is rotatably connected between the two ends.

なお、これらジャッキ5とフレーム7、ジャッキ5とブ
ラケット6、ブラケット6と支柱3、フレーム7と支柱
3はそれぞれボルト等により連結、固定可能とされてい
る。また、前記堰板9、9間の距離は、これらが互いに
平行に配置された状態で構築すべきコア部lの壁厚に等
しくなるように設定されている。
Incidentally, the jack 5 and the frame 7, the jack 5 and the bracket 6, the bracket 6 and the support column 3, and the frame 7 and the support column 3 can be connected and fixed with bolts or the like, respectively. Further, the distance between the weir plates 9, 9 is set to be equal to the wall thickness of the core portion l to be constructed with these weir plates 9 disposed parallel to each other.

以上のような構戊の自動上昇型枠2を用いてコア部lを
構築するには、フレーム7を支柱3に固定すると共にブ
ラケット6を支柱3に対して移動自在な状態とし、次い
でジャッキ5を伸長させることでブラケット6のみを上
昇させた後、逆にブラケット6を支柱3に固定すると共
にフレーム7を支柱3に対して移動自在な状態とし、今
度はジャッキ5を短縮させることでフレーム7、すなわ
ち型枠部4全体を上昇させて堰板9、9間にコンクリー
ト打設用の間隙を形戊する。そして、これら堰板9、9
間に鉄筋を配設した後にコンクリートを打設し、コンク
リートの硬化を待って前述した型枠部4上昇工程を行い
、これらコンクリート打設工程及び型枠部4上昇工程を
繰り返すことで、下部から上部に向ってコア部lを構築
するのである。そして、2層分のコア部1の構築が終了
したら、その上端を塞ぐようにコア内スラブ31を構築
する。
In order to construct the core part l using the self-rising formwork 2 having the structure described above, the frame 7 is fixed to the pillar 3 and the bracket 6 is made movable relative to the pillar 3, and then the jack 5 is After raising only the bracket 6 by extending it, conversely fix the bracket 6 to the column 3 and make the frame 7 movable relative to the column 3, and then shorten the jack 5 to raise the frame 7. That is, the entire formwork portion 4 is raised to form a gap for concrete pouring between the weir plates 9, 9. And these weir plates 9, 9
After placing reinforcing bars in between, concrete is poured, and after waiting for the concrete to harden, the above-mentioned formwork part 4 raising process is performed, and by repeating these concrete pouring process and formwork part 4 raising process, The core portion l is constructed toward the top. After the construction of the core portion 1 for two layers is completed, the in-core slab 31 is constructed so as to close the upper end thereof.

また、後述する躯体構築作業に先行して、第3図に示す
ように、建築物の柱が立設される箇所の地面にもジャッ
キ(揚重手段N2、l2、・・・を設置する。これらジ
ャッキ12、・・・は、後述する建築物の躯体上昇工程
時に使用されるものであり、最下階構築の際には建築物
の躯体のほぼ全体を押し上げるだけの能力を必要とする
。但し、10階建程度の建築物であれば、tooot程
度の荷重を発生できれば十分であり、周知の油圧ジャッ
キ等が好適に適用可能である。
In addition, prior to the frame construction work to be described later, as shown in FIG. 3, jacks (lifting means N2, l2, . . . ) are also installed on the ground where the pillars of the building are to be erected. These jacks 12, . . . are used during the process of raising the building frame, which will be described later, and require the ability to lift up almost the entire building frame when building the lowest floor. However, in the case of a building of about 10 stories, it is sufficient to generate a load of about 100 ft, and a well-known hydraulic jack or the like can be suitably applied.

さらに、第3図に示すように、スラブ型枠23及びコア
スラブ型枠32を設置する。
Furthermore, as shown in FIG. 3, a slab formwork 23 and a core slab formwork 32 are installed.

このスラブ型枠23は、第16図ないし第18図に示す
ように、同一階に位置する梁11,・・・で囲繞される
平面内に配置される矩形板状のデッキプレート51と、
このデッキプレート51上に配設されてスラブ24下面
に埋殺される同様に矩形板状の波状板52とからなり、
このスラブ型枠23は、仮設梁53、53を介して地下
部2底面から支柱54、・・・により支持されている。
As shown in FIGS. 16 to 18, this slab formwork 23 includes a rectangular plate-shaped deck plate 51 arranged in a plane surrounded by beams 11, . . . located on the same floor;
It consists of a similarly rectangular plate-shaped wavy plate 52 arranged on this deck plate 51 and buried in the lower surface of the slab 24,
This slab formwork 23 is supported by columns 54, . . . from the bottom of the underground section 2 via temporary beams 53, 53.

なお、本実施例では、スラブ24の構築工程は後述する
柱及び梁構築工程に遅れて行なわれるため、スラブ型枠
23は地面から2層分だけ上方に離間されて配置されて
いる。同様に、コアスラブ型枠32も支柱33、・・・
を介して建築物の塔屋(第14図ないし第15図参照)
の突出高さだけ上方に離間されて配置されている。
In this embodiment, since the step of constructing the slab 24 is carried out later than the step of constructing columns and beams, which will be described later, the slab formwork 23 is placed two layers above the ground. Similarly, the core slab formwork 32 also has supports 33,...
through the tower of the building (see Figures 14 and 15)
are spaced apart upwardly by a protrusion height.

(ii)躯体構築開始 2層分程度のコア部1を先行して構築したら、第4図に
示すように、このコア部lに沿って建築物の最上部から
柱、梁等の躯体の構築作業を開始する。なお、本実施例
の建築物はいわゆるセンタ−コア構造と呼ばれる構造を
採用しており、平面視した状態でコア部1が建築物の略
中央に位置している。但し、片コア構造であっても本実
施例に準じて行なえることは言うまでもない。
(ii) Start of frame construction After constructing the core part 1 for about two layers in advance, construct the frame such as columns and beams from the top of the building along this core part 1, as shown in Figure 4. Start working. The building of this embodiment employs a so-called center core structure, and the core portion 1 is located approximately at the center of the building when viewed from above. However, it goes without saying that even a single core structure can be used in accordance with this embodiment.

建築物の躯体を構成すj柱、梁としては、鉄骨造、鉄筋
コンクリート造、あるいは鉄骨鉄筋コンクリート造等周
知の柱、梁から任意に選択可能であるが、本実施例では
柱13は鉄筋コンクリート造、梁14は鉄骨造とされて
いる。
The pillars and beams that make up the building frame can be arbitrarily selected from well-known columns and beams such as steel-frame construction, reinforced concrete construction, or steel-frame reinforced concrete construction, but in this example, the column 13 is constructed of reinforced concrete construction, 14 is said to be of steel frame construction.

すなわち、第10図ないし第l2図に示すように、垂直
方向に延在する主筋l5、15、・・・及びこれら主筋
15、・・・の外周に巻回された帯筋l6、・・・が四
角柱状のコンクリートl7内に埋設されて柱l3が構或
され、一方、梁l4はH型鋼から構成されている。この
ため、柱l3と梁l4との交叉部である仕口部には特殊
な仕口部材18が配設されている。
That is, as shown in FIGS. 10 to 12, main reinforcements l5, 15, . . . extending in the vertical direction, and tie reinforcements l6, . is buried in a square column-shaped concrete l7 to form a column l3, while a beam l4 is made of H-beam steel. For this reason, a special joint member 18 is provided at the joint section where the pillar l3 and the beam l4 intersect.

この仕口部材18は、第10図に示すように、梁l4と
同一の断面形状を有するH型鋼が平面視十字状に交叉し
た形状に形戎された取付部材19と、前記柱l3と同一
幅に形威されて取付部材l9の中央部を囲繞する角筒状
の端面箱20と、端面箱20の上面または下面を塞ぐ矩
形板状の住用底型枠2lから概略構戎されている。この
柱用底型枠21には、前記主筋l5、・・・に対応する
位置に貫通孔22、・・・が穿設されている。
As shown in FIG. 10, this joint member 18 includes a mounting member 19 formed of H-beam steel having the same cross-sectional shape as the beam l4 and crossed in a cross shape in a plan view, and a mounting member 19 that is the same as the pillar l3. It is roughly constructed from a rectangular cylindrical end box 20 that surrounds the center of the mounting member 19 with its width, and a rectangular plate-shaped housing bottom form 2l that closes the top or bottom surface of the end box 20. . Through holes 22, . . . are bored in the column bottom form 21 at positions corresponding to the main reinforcing bars 15, .

従って、取付部材l9の四方から梁14、・・・が接合
されると共に、住用底型枠21の貫通孔22、・・・に
主筋l5、・・・が挿通されて固定され、さらに端面箱
20内にコンクリートl7が打設されることで、柱13
と梁14との接合が行なわれる。
Therefore, the beams 14, . . . are joined from all sides of the mounting member 19, and the main reinforcing bars 15, . By pouring concrete l7 into the box 20, the pillar 13
and the beam 14 are joined.

さて、前述の基礎工事が終了したら、第10図に示すよ
うに、地面に設置されたジャッキl2、・・・の上面に
前記住用底型枠2lを載置し、さらにその上に前記仕口
部材l8を載置する。そして、ジャッキ12、・・・上
に仕口部材18、・・・が配設されたら、これら仕口部
材18、・・・間を前記梁14、・・で連結する。
Now, after the above-mentioned foundation work is completed, as shown in Fig. 10, the residential bottom formwork 2l is placed on top of the jack l2,... installed on the ground, and then the Place the joint member l8. Then, after the joint members 18, . . . are disposed on the jacks 12, . . ., these joint members 18, .

また、最初の構築作業においては、後述するジャッキl
2、・・・による押し上げ工程を省く目的で、3層分の
梁l4、14及びこの間に位置する柱l3を同時に構築
する。すなわち、屋上を構成する梁l4と、最上階及び
その下の階を構成する梁14、14である。従って、ジ
ャッキl2、・・・直上に配設された梁l4、・・・及
び仕口部材l8、・・・から・1層分ないし2層分だけ
上方に離間した位置に更に梁l4、・・・及び仕口部材
l8、・・・を配設する。
Also, during the initial construction work, use the jack l described later.
For the purpose of omitting the push-up process by 2, . That is, the beam 14 constitutes the roof, and the beams 14, 14 constitute the top floor and the floors below it. Therefore, there is a beam l4 placed directly above the jack l2,...and a beam l4, placed one or two layers upward from the joint member l8,... . . . and a joint member l8, . . . are arranged.

これら梁l4、・・・及び仕口部材l8、・・・は支柱
34、・・・により支持すればよい。また、前記コア部
1に接する部分には、このコア部1を囲繞するように梁
(図示略)を環状に架設しておく。
The beams l4, . . . and the joint members l8, . . . may be supported by the supports 34, . In addition, a beam (not shown) is installed in a ring shape in a portion in contact with the core portion 1 so as to surround the core portion 1 .

そして、これら上下方向に並設された仕口部材18、l
8間にl層分より若干長目に切断された主筋15、・・
・を配設し、その上下を前記社用底型枠2l、21に固
定する。さらに、主筋l5、・・・の外周に帯筋l6、
・・・を巻回してから、この周囲に柱用型枠26、・・
・を配設する。これと同時に、仮設構台23、・・・上
にスラブ24用の鉄筋27、・・・を配設する。この状
態で、柱13及びスラブ24のコンクリートを打設し、
所定の強度が発現した段階で柱用型枠26、・・・の脱
型を行う。なお、柱■3のコンクリート打設は、例えば
第11図ないし第12図に示すように、上階の柱13に
柱用型枠26、・・・内に連通ずる貫通孔28を設けて
おり、この貫通孔28を介して打設するような方法が挙
げられる。
These shishaguchi members 18, l arranged in parallel in the vertical direction
Main reinforcement 15 cut slightly longer than 1 layer between 8...
- are arranged and their upper and lower parts are fixed to the company bottom formworks 2l and 21. Furthermore, on the outer periphery of the main reinforcement l5,...
... and then wrap the column formwork 26 around it.
・Deploy. At the same time, reinforcing bars 27, . . . for the slab 24 are placed on the temporary pedestal 23, . In this state, concrete for pillars 13 and slabs 24 is poured,
At the stage when a predetermined strength has been developed, the column formwork 26, . . . is demolded. In addition, for concrete pouring of column 3, for example, as shown in Figs. 11 and 12, a through hole 28 is provided in the column 13 on the upper floor that communicates with the column formwork 26. , a method of pouring through the through hole 28 can be mentioned.

一方、第4図に示すように、コア部lの上端部たる塔屋
35の側壁部も同時に構築する。この塔屋35の構築に
は前述した自動上昇型枠は使用し難いので、通常の塔屋
施工のように筒状の鉄筋を組んでその内外を型枠で囲繞
してからコンクリートを打設するような構築方法が採ら
れる。この場合、塔屋35と既に構築されているコア部
lとの間は縁切り状態としておく。
On the other hand, as shown in FIG. 4, the side wall portion of the tower 35, which is the upper end of the core portion l, is also constructed at the same time. Since it is difficult to use the above-mentioned automatic climbing formwork to construct this tower 35, it is difficult to use the above-mentioned automatic climbing formwork, so it is difficult to use the above-mentioned automatic climbing formwork, so it is necessary to assemble cylindrical reinforcing bars and surround the inside and outside with formwork, and then pour concrete, as in normal tower construction. construction method is adopted. In this case, a separation is made between the tower house 35 and the already constructed core part l.

(iii)躯体押し上げ 住13、・・・が自立司能な状態まで硬化した段階で、
第6図に示すように、建築物の躯体を1層分上方に押し
上げる。
(iii) When the building frame has been hardened to the point where it can function independently,
As shown in Figure 6, the building frame is pushed up one layer.

まず、第5図に示すように、ジャッキ12、・・・を若
干伸長させてから前記塔屋35を既に構築された建築物
の躯体に連結する。
First, as shown in FIG. 5, the jacks 12, . . . are slightly extended, and then the tower 35 is connected to the frame of the already constructed building.

この後、第13図(イ)に示すように、ジャノ牛l2、
・・・をさらに所定長さ伸長させる。次に、同図(口)
に示すように、梁14、・・・と地而との間に支持材3
6、・・・を挿入し、さらに、同図(ハ)に示すように
、ジャッキl2、・・・を元の位置に短縮してこのジャ
ッキl2、・・・と仕口部材18との間に補助材37、
・・・を挿入する。そして、以上の工程を繰り返して、
同図(二)に示すように躯体をl層分押し上げた段階で
、同図(ホ)に示すようにジャッキ6、・・・を元の位
置に短縮して補助材37、・・・を全て取り除く。
After this, as shown in Figure 13 (a), Jano beef l2,
... is further extended by a predetermined length. Next, the same figure (mouth)
As shown in FIG.
6,... and then shorten the jacks l2,... to their original positions as shown in FIG. Auxiliary material 37,
Insert... Then repeat the above process,
At the stage when the building frame has been pushed up by one layer as shown in Figure (2), the jacks 6, ... are shortened to their original positions and the auxiliary members 37, ... are moved up, as shown in Figure (E). Remove everything.

なお、前記スラブ型枠23、・・・は支柱25、・・を
介して地面に支持されているので、建築物の躯体の押し
上げに伴い型枠の脱型は自動的に行なわれる。
Incidentally, since the slab formwork 23, . . . is supported on the ground via the supports 25, .

(工V)構築作業継続 建築物の躯体上昇工程が終了したら、前述の工程により
、第6図に示すように、既に構築された部分の直下階に
相当する柱13、梁14及びスラブ24構築作業を行う
。そして、柱13、梁14及びスラブ24構築作業が終
了したら、前述のようにジャッキl2、・・・を用いて
躯体を押し上げ、さらにこれら工程を繰り返して、第1
図ないし第7図に示すように、順次下階へと建築物の構
築作業を継続する。
(Construction V) Continuation of construction work Once the process of raising the building frame is completed, as shown in Figure 6, the columns 13, beams 14 and slab 24 corresponding to the floor immediately below the already constructed part are constructed. Do the work. When the construction of the columns 13, beams 14, and slabs 24 is completed, the structure is pushed up using jacks l2, . . . as described above, and these steps are repeated.
As shown in Figures 7 to 7, construction work continues on the lower floors one after another.

このようにして、建築物の躯体部分は主に地上1階にお
いて構築され、構築が終了した部分については順次上方
に押し上げられてゆくので、外壁工事、設備工事、仕上
工事は地上2階以上の上階において作業階を決定して行
えばよい。
In this way, the framework of the building is constructed mainly on the first floor above ground, and the parts that have been constructed are successively pushed upwards, so exterior wall work, equipment work, and finishing work are carried out on the second floor above ground. All you have to do is decide on the work floor on the upper floor.

例えば、階段を鉄骨造とするならば、この階段取付工事
は地上2階において行えばよい。一方、階段を鉄筋コン
クリート造とする場合、前述のスラブ24の場合と同様
に地面に底型枠だけ配置しておけば、躯体の押し上げ工
程時に自動的に脱型が行なわれて好ましい。
For example, if the stairs are made of steel, the stairs installation work may be performed on the second floor above ground. On the other hand, when the staircase is made of reinforced concrete, it is preferable to place only the bottom form on the ground, as in the case of the slab 24 described above, so that the form can be automatically removed during the process of pushing up the building frame.

このように、地上2階においてスラブ24、外壁、階段
の構築作業を行い、地上3階において間仕切壁、窓、電
気、設備作業を行い、地上4階において天井、電気、設
備作業を行い、地上5階において床等の仕上作業を行う
といったように、順次上階に移動するに従って建築物の
構築作業の工程が進行するようにすれば、各階の作業を
並行して行うことができ、大変能率的である。また、各
階における作業を固定化することで、資材、人材の配置
も明確化され、その管理も容易なものとなる。
In this way, construction work on the slab 24, exterior walls, and stairs was carried out on the second floor above ground, partition wall, window, electrical, and equipment work was carried out on the third floor above ground, and ceiling, electrical, and equipment work was carried out on the fourth floor above ground. If the process of building construction work progresses as one moves up to the upper floors, such as completing floor finishing work on the 5th floor, work on each floor can be done in parallel, resulting in great efficiency. It is true. Furthermore, by fixing the work on each floor, the allocation of materials and personnel becomes clearer, and management becomes easier.

なお、これら各階への資材の搬送は、前記コア部1内に
仮設リフトを設けて、この仮設リフトにより順次行えば
よい。特に、本実施例では、重量を有する鉄骨、鉄筋等
は地面に吊り降ろせばよく、従って、仮設リフトも小規
模なもので済む。さらに、一般の建築物の構築作業であ
れば、前述のように各階における作業工程を定めて作業
を行えば5階程度まででほとんどの作業は完了するため
、仮設リフトを設置すべき階数も少なくて済む。
Note that a temporary lift may be provided in the core section 1 and the materials may be transported to each floor sequentially by this temporary lift. In particular, in this embodiment, heavy steel frames, reinforcing bars, etc. can be suspended to the ground, and therefore only a small temporary lift can be used. Furthermore, in construction work for general buildings, if the work schedule for each floor is determined as described above, most of the work can be completed up to the 5th floor, so the number of floors where temporary lifts need to be installed is small. It's done.

そして、以上のような工程を繰り返すことで建築物の躯
体構築作業を地上1階部分まで完了し、型枠等の仮設機
材を撤去すると共に、前述した電気、設備、仕上作業が
完了した時点で、第14図ないし第15図に示すような
建築物40の構築作業が完了する。
By repeating the above process, the building frame construction work is completed up to the first floor above ground, temporary equipment such as formwork is removed, and the electricity, equipment, and finishing work described above is completed. , the construction work of the building 40 as shown in FIGS. 14 and 15 is completed.

このように、本実施例では、建築物40の躯体構築作業
を地上1階で行うと共に、建築物40の最上部から構築
を開始して、構築が終了した部分から順次ジャッキ12
、・・・を用いて躯体を押し上げることで順次下階へと
建築物40の構築作業を進めているので、躯体構築以外
の作業も含めて各作業を常時一定位置で行うことができ
る。しかも、各作業を行う位置を地上1階等の低位置に
固定しているため、型枠等の仮設材や仮設機械等の盛り
替え、積層、更には解体撤去等の手間がかからず、作業
の生産性向上に大きく寄与できる。そして、このように
して各作業を一定位置で行えることから、例えば、溶接
ロボット等を地上l階に常設して溶接作業の自動化を図
ることができ、各作業への自動化機械導入を現実のもの
とすることができる。
As described above, in this embodiment, the work of constructing the frame of the building 40 is carried out on the first floor above ground, and the construction is started from the top of the building 40, and the jacks 12 are sequentially installed from the completed part.
, . . . are used to push up the building frame, and the construction work of the building 40 is progressed sequentially to the lower floors. Therefore, each work, including work other than building the frame, can be performed at a constant position at all times. Moreover, since each work is performed at a low location such as the first floor above ground, there is no need to rearrange, stack, or even dismantle and remove temporary materials such as formwork and temporary machinery. It can greatly contribute to improving work productivity. Since each work can be performed in a fixed position in this way, for example, welding robots can be permanently installed on the first floor above ground to automate welding work, making it a reality to introduce automated machines to each work. It can be done.

また、従来のように作業員が最上階にまで登らずに地上
に近い位置において作業することができ、その安全性確
保も容易なものとなる。
Additionally, workers can work from a position close to the ground without having to climb to the top floor as in the past, making it easier to ensure safety.

さらに、本実施例では作業位置を固定することができる
ため、建築物40の構築作業全体を通して資材搬入工程
を一定のものとすることができ、手間、時間の削減が図
れると共に、管理が容易なものとなる。特に、本実施例
では、躯体構築作業を地上1階で行っているので、鉄骨
、鉄筋等の資材搬入は搬送用のトラックから水平移動す
れば足り、従来のように鉄骨等の大重量の部材を上階に
揚重する必要がないため、クレーン付トラックのクレー
ン程度で鉄骨等の搬入作業が十分可能である。
Furthermore, in this embodiment, since the work position can be fixed, the material delivery process can be kept constant throughout the construction work of the building 40, reducing labor and time, and making management easier. Become something. In particular, in this example, the frame construction work is carried out on the first floor above the ground, so materials such as steel frames and reinforcing bars can be brought in by horizontal movement from transport trucks, unlike conventional construction of heavy parts such as steel frames. Since there is no need to lift the steel frames to the upper floor, it is possible to transport the steel frames etc. using a crane equipped with a truck.

しかも、本実施例では建築物40の最上部から構築を開
始しているので、屋上の防水工事や塔屋の構築等手間の
かかる部分の工事が余裕をもって施工できる。
Moreover, in this embodiment, construction starts from the top of the building 40, so that time-consuming work such as rooftop waterproofing and construction of a tower can be completed with plenty of time.

そして、本実施例では、建築物40の躯体構築に先立っ
てコア部l構築を行っており、躯体構築作業中や躯体押
し上げ作業中に地震力等の水平力が作用しても、コア部
1の存在により構築中の躯体が地盤に支持され、建築物
40の水平移動や転倒のおそれがなくて安全な施工が可
能となる。しかも、塔屋35と躯体とを連結した後は、
構築作業を行う地」二部分は建築物の屋上部で覆われる
ので、天候に左右されずに作業を行える、という利点も
ある。
In this embodiment, the core part l is constructed prior to constructing the frame of the building 40, and even if a horizontal force such as an earthquake force acts during the frame construction work or the work of pushing up the frame, the core part l Due to the presence of the structure, the frame under construction is supported by the ground, and there is no fear of horizontal movement or overturning of the building 40, allowing safe construction. Moreover, after connecting the tower house 35 and the frame,
The area where construction work will be carried out is covered by the roof of the building, which has the advantage of allowing work to be carried out regardless of the weather.

なお、この発明の構造物の構築方法は、その細部が前記
実施例に限定されず、種々の変形例が可能である。一例
として、前記実施例では柱が鉄筋コンクリート造、梁が
鉄骨造であったが、これに限定されず、例えば梁が鉄筋
コンクリート造であってもよい。この場合、前述したス
ラブ24や階段のように地上1階に梁の底型枠を設けて
おけば、躯体押し上げ工程により自動的に脱型が行なわ
れて好ましい。
Note that the structure construction method of the present invention is not limited to the details of the above embodiments, and various modifications are possible. As an example, in the above embodiment, the columns are made of reinforced concrete and the beams are made of steel, but the present invention is not limited to this, and the beams may be made of reinforced concrete, for example. In this case, it is preferable to provide a bottom formwork for the beam on the first floor above ground, as in the case of the slab 24 and stairs described above, so that the molding can be automatically removed by the process of pushing up the frame.

「発明の効果」 以上詳細に説叫したように、この発明は、構造物のコア
部をその下部から上部に向って所定層分だけ構築すると
共に、このコア部に沿って地上で構造物をその最上部か
ら構築し、構築した部分がコア部の構築高さより低い所
定高さに達しかつ自立可能となった状態でこの構築部分
を揚重手段により上方に押し上げ、さらに押し上げられ
た構築部分の下部につなげて地上でこの構築部分の直下
を構築する工程と前記押し上げ工程とを順次繰り返すこ
とで構造物全体の構築を完成することを特徴とする構造
物の構築方法であるので、構造物の構築作業以外の作業
も含めて各作業を常時一定位置で行うことができる。
``Effects of the Invention'' As described in detail above, the present invention constructs the core part of a structure by a predetermined number of layers from the bottom to the top, and builds the structure on the ground along this core part. The constructed part is constructed from the top, and when the constructed part reaches a predetermined height lower than the construction height of the core part and becomes self-supporting, this constructed part is pushed upward by a lifting means, and the constructed part that has been pushed up further is This method of constructing a structure is characterized in that the construction of the entire structure is completed by sequentially repeating the step of connecting it to the lower part and constructing directly below this construction part on the ground, and the pushing up step. All work, including work other than construction work, can be performed in a fixed position at all times.

しかも、構造物の構築作業を地上で行っているため、型
枠等の仮設材や仮設機械等の盛り替え、積層、更には解
体撤去等の手間がかからず、作業の生産性向上に大きく
寄与できる。さらに、作業位置が固定できることで、各
作業位置に自動化機械を常設する等することで、作業の
自動化を図りうる。また、従来のように作業員が最上階
にまで登らずに地上に近い位置において作業することが
でき、その安全性確保も容易なものとなる。
Moreover, since the construction work of the structure is carried out on the ground, there is no need to replace, stack, or even dismantle and remove temporary materials such as formwork and temporary equipment, which greatly improves work productivity. I can contribute. Furthermore, since the working position can be fixed, the work can be automated by permanently installing an automated machine at each working position. Additionally, workers can work from a position close to the ground without having to climb to the top floor as in the past, making it easier to ensure safety.

さらに、作業位置の固定化により構造物の構築作業全体
を通して資材搬入工程を一定のものとすることができ、
手間、時間の削減が図れると共に、管理が容易なものと
なる。特に、この発明では、構造物の構築作業を地上で
行っているので、鉄骨、鉄筋等の資材搬入はトラック等
からクレーン等で水平移動すれば足り、従来のように鉄
骨等の大重量の部材を上階に揚重する必要がないため、
クレーン付トラックのクレーン程度で資材搬入作業が十
分可能である。
Furthermore, by fixing the working position, the material delivery process can be kept constant throughout the construction work of the structure.
This saves time and effort, and makes management easier. In particular, in this invention, since the construction work of the structure is carried out on the ground, materials such as steel frames and reinforcing bars can be brought in by horizontally moving them from trucks etc. using cranes etc. Because there is no need to lift it to the upper floor,
It is possible to carry in materials with a truck equipped with a crane.

しかも、この発明では構造物の最上部から構築を開始し
ているので、屋上の防水工事等手間のかかる部分の工事
が余裕をもって施工できる。
Furthermore, since construction starts from the top of the structure in this invention, time-consuming work such as rooftop waterproofing can be carried out with plenty of time.

そして、この発明では、構造物の躯体構築に先立ってコ
ア部構築を行っており、躯体構築作業中や躯体押し上げ
作業中に地震力等の水平力が作用しても、コア部の存在
により構築中の躯体が地盤に支持され、構造物の水平移
動や転倒のおそれがなくて安全な施工が可能となる。し
かも、構造物の最上部から構築を開始するので、構築作
業を行う地上部分はこの構造物の屋上部により覆われ、
天候を気にせずに構築作業を行うことができる、という
利点もある。
In this invention, the core part is constructed before constructing the frame of the structure, and even if horizontal forces such as seismic force act during the construction of the frame or during the work of pushing up the frame, the presence of the core allows the structure to be constructed. The inner frame is supported by the ground, allowing safe construction without the risk of horizontal movement or overturning of the structure. Moreover, since construction starts from the top of the structure, the above-ground part where construction work is performed is covered by the roof of the structure.
Another advantage is that construction work can be carried out without worrying about the weather.

【図面の簡単な説明】[Brief explanation of drawings]

第1図ないし第15図は、この発明の一実施例である構
造物の構築方法を説明するための図であり、第1図は構
築途中の状態を示す断面図、第2図ないし第7図は工程
の順序を示す断面図、第8図は自動上昇型枠を示す正面
図、第9図は同平面図、第lO図はジャッキ上への仕口
部材の配置方法を示す斜視図、第11図は鉄筋の配設方
法を示す斜視図、第12図は柱用型枠の配置状態を示す
斜視図、第131iは躯体上昇工程を示す断面図、第1
4図は本実施例により構築された建築物の正面図、第■
5図は同平面図、第l6図ないし第18図は仮設構台を
取り出して示した図であって、第16図は平面図、第1
7図は第16図のA−A′線に沿う矢視断面図、第18
図は第16図のB−B’線に沿う矢視断面図である。 l・・・・・・コア部、2・・・・・・自動上昇型枠、
4・・・・・・型枠部、 l 2・・・・・・ジャッキ( 揚重手段 )、 l 3・・・・・・柱、 1 4・・・・・・梁、 24・・・・・・スラブ、 35・・・・・・塔屋、 4 O・・・・・・建築物。
1 to 15 are diagrams for explaining a method of constructing a structure according to an embodiment of the present invention, in which FIG. 1 is a sectional view showing a state in the middle of construction, and The figure is a sectional view showing the order of the process, FIG. 8 is a front view showing the automatic lifting formwork, FIG. 9 is a plan view thereof, and FIG. FIG. 11 is a perspective view showing the method of arranging reinforcing bars, FIG.
Figure 4 is a front view of the building constructed according to this example, and
Figure 5 is a plan view of the same, Figures 16 to 18 are diagrams showing the temporary gantry taken out, Figure 16 is a plan view,
Figure 7 is a sectional view taken along line A-A' in Figure 16, and Figure 18
The figure is a sectional view taken along line BB' in FIG. 16. l...Core part, 2...Automatic rising formwork,
4... Formwork part, l 2... Jack (lifting means), l 3... Column, 1 4... Beam, 24... ...Slab, 35...Tower, 4 O...Building.

Claims (1)

【特許請求の範囲】[Claims] 構造物のコア部をその下部から上部に向って所定層分だ
け構築すると共に、このコア部に沿って地上で構造物を
その最上部から構築し、構築した部分がコア部の構築高
さ以下の所定高さに達しかつ自立可能となった状態でこ
の構築部分を揚重手段により上方に押し上げ、さらに押
し上げられた構築部分の下部につなげて地上でこの構築
部分の直下を構築する工程と前記押し上げ工程とを順次
繰り返すことで構造物全体の構築を完成することを特徴
とする構造物の構築方法。
The core part of the structure is constructed from the bottom to the top by a predetermined number of layers, and the structure is constructed on the ground along this core part from the top, so that the constructed part is below the construction height of the core part. a step of pushing this construction part upward by a lifting means when it has reached a predetermined height and is able to stand on its own, and connecting it to the lower part of the construction part that has been pushed up further to construct directly below this construction part on the ground; A method for constructing a structure, characterized in that the construction of the entire structure is completed by sequentially repeating the pushing-up process.
JP1242490A 1989-09-19 1989-09-19 How to build structures Expired - Lifetime JP2761527B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1242490A JP2761527B2 (en) 1989-09-19 1989-09-19 How to build structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1242490A JP2761527B2 (en) 1989-09-19 1989-09-19 How to build structures

Publications (2)

Publication Number Publication Date
JPH03107038A true JPH03107038A (en) 1991-05-07
JP2761527B2 JP2761527B2 (en) 1998-06-04

Family

ID=17089862

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1242490A Expired - Lifetime JP2761527B2 (en) 1989-09-19 1989-09-19 How to build structures

Country Status (1)

Country Link
JP (1) JP2761527B2 (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5027652A (en) * 1973-05-08 1975-03-20

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5027652A (en) * 1973-05-08 1975-03-20

Also Published As

Publication number Publication date
JP2761527B2 (en) 1998-06-04

Similar Documents

Publication Publication Date Title
EP2852724B1 (en) High rise building elevation concept
CN104594204A (en) Construction supporting system for hill type U beam of viaduct of urban light rail and construction method
KR100694493B1 (en) Downward construction method capable of using bracket support type temporary structure as working table
US10829927B2 (en) Vertical slip form construction system with multi-function platform, and method of constructing a building therewith
RU2558065C2 (en) Partially prefabricated building and method of its erection
CN111608270A (en) Prefabricated through long column concrete assembled frame structure and construction method thereof
JPH03107038A (en) Constructing method for structure
US3435583A (en) Method of forming buildings
JPH08270081A (en) Construction method of frame structure
JP2761528B2 (en) How to build structures
JP2761526B2 (en) How to build structures
JP3445419B2 (en) Double slab construction method
CN109680811B (en) Prefabricated steel column node connection structure for assembled building and construction method thereof
RU2087650C1 (en) House-building combine
JP3234442B2 (en) Building and scrap type building method
JP2777516B2 (en) Construction method of high-rise structure
JPH03107036A (en) Constructing method for structure
JPH0932295A (en) Construction method for concrete structure
RU2026941C1 (en) Method of the building erection by means of hoisting
SU1048093A1 (en) Method of erecting multistorey building by floor-rising technique
JP2696486B2 (en) Building construction method
WO2023148635A1 (en) Arrangement and process for the construction of a steel plant and related steel plant
JPH0437893B2 (en)
JPH04319172A (en) Skeleton building construction workbench
JPH03197734A (en) Lift up method by replacement of scaffold body