JPH05140957A - Constructing method for basement of building - Google Patents

Constructing method for basement of building

Info

Publication number
JPH05140957A
JPH05140957A JP3305982A JP30598291A JPH05140957A JP H05140957 A JPH05140957 A JP H05140957A JP 3305982 A JP3305982 A JP 3305982A JP 30598291 A JP30598291 A JP 30598291A JP H05140957 A JPH05140957 A JP H05140957A
Authority
JP
Japan
Prior art keywords
floor
ground
building
construction
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP3305982A
Other languages
Japanese (ja)
Other versions
JP2769941B2 (en
Inventor
Hiroshi Nojima
博 野島
Takashi Takimoto
隆 滝本
Seiichi Shibayama
誠一 柴山
Takahiro Maru
隆宏 丸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP3305982A priority Critical patent/JP2769941B2/en
Publication of JPH05140957A publication Critical patent/JPH05140957A/en
Application granted granted Critical
Publication of JP2769941B2 publication Critical patent/JP2769941B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To construct the basement of a building through automated processes by the inverse construction method, which presents good easiness and accuracy in works, allows saving the labor, and prevents producing of pollution. CONSTITUTION:The top of the ground 5 is used as concrete form and as timbering, and a floor surface structure S consisting of a beam 7 and floor slab 6 is constructed where a hoist rail 9 for running of a working machine is laid on the undersurface. The floor surface structure S is allowed to work as a horizontal structural surface bearing the soil pressure. and the ground under this floor surface structure S is excavated with a working machine of ceiling running type which is suspended at the hoist rail 9 as freely to travel. Further a floor surface structure S' working also as a soil pressure horizontal bearing structural surface for the lower floor is constructed, and then the basement structure of the building is constructed, and this cycle of processes is repeated.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は逆打工法による建築物地
下部の構築方法に係るものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an underground portion of a building by a reverse driving method.

【0002】[0002]

【従来の技術】図13乃至図15は従来の逆打ち工法の
工程を示し、止水、土留め用のシートパイルaを打込
み、アースドリルによる穿孔部に仮支柱bを挿入したの
ち、根巻きコンクリートを打設し、山砂cを埋戻し、第
1次掘削dを施し、地下2階床より少し下まで深礎eを
掘削し、地下鉄骨柱fの長さ分だけ仮支柱を切断する。
(図13参照)次いで地下1階の鉄骨柱及び梁hを構築
し、1階床梁コンクリートiを打設し、鉄骨柱にブラケ
ツトを取付け、H鋼の切梁兼逆打ち用ステージガーダj
を設置し、第2次掘削kを深礎底部まで施す。次いで地
下1階梁l及び側柱を構築する。(第14図参照)次い
で地下1階床梁コンクリートmを打設し、以下地下2階
床梁コンクリート打設まで前記の工程を反覆し、最終掘
削nを底盤まで施し、最下階と基礎tを構築し、前記地
下躯体工事と平行して地上階鉄骨建方を行なう。(図1
5参照)なお前記従来例においては、地下構造として鉄
骨鉄筋コンクリート造の例を示しているが鉄筋コンクリ
ート造として仮支柱のみ配設する場合もある。
2. Description of the Related Art FIGS. 13 to 15 show steps of a conventional reverse driving method, in which a sheet pile a for waterproofing and earth retaining is driven in, a temporary support b is inserted into a perforated portion by an earth drill, and then a neck wrapping is performed. Concrete is poured, mountain sand c is backfilled, the first excavation d is performed, the deep foundation e is excavated to slightly below the second basement floor, and the temporary columns are cut by the length of the subway bone column f. ..
(Refer to FIG. 13) Next, a steel frame column and beam h on the first basement floor are constructed, a floor floor beam concrete i is placed, a bracket is attached to the steel frame column, and an H steel cutting beam and reverse stage girder j
Is installed and the second excavation k is performed to the bottom of the deep foundation. Next, the first basement beam 1 and side pillars are constructed. (Refer to FIG. 14) Next, the concrete floor m of the first floor is placed, the above steps are repeated up to the concrete placement of the floor girder of the second floor, and the final excavation n is performed to the bottom plate. And construct a steel frame on the ground floor in parallel with the underground structure work. (Fig. 1
In the above-mentioned conventional example, an example of the steel frame reinforced concrete structure is shown as the underground structure, but in some cases only temporary columns are arranged as the reinforced concrete structure.

【0003】[0003]

【発明が解決しようとする課題】前記従来の逆打工法は
作業者にとっては非常に厳しい作業空間となるため機械
による自動又は半自動の施工の導入を考えると次のよう
な問題点がある。 イ)地下の掘削を自動機械で行う方法では掘削機械が非
常に大型となり、土木工事のようなケーソン内の工事と
は違って従来の建築工事における逆打ち工法のように仮
支柱が林立した場所での施工は掘削機械の機動性に欠け
るので不適当である。 ロ)従来の掘削機械(ユンボ・ドーザーショベル・クラ
ムシエル等)ではオペレターにより操作されるもので自
動化がしにくい。 ハ)建物周囲の土留の壁の土圧を支持するための切り梁
兼用逆打ち用ステージの設置は、狭隘な空間で重量物を
取り扱うために非常に困難であり、作業空間としても支
障となる。 ニ)仮支柱又は土留め壁に付着した土は人が一つ一つか
き落している。 ホ)地下階は太物鉄筋の配筋が多く大量の長尺重量物の
搬送の効率的方法が乏しい。 ヘ)掘削機械の動力は内燃機械のものが多く排気ガス対
策が容易でない。
The above-mentioned conventional reverse-placing method has a very strict working space for the operator, and therefore has the following problems when considering the introduction of automatic or semi-automatic construction by a machine. B) In the method of underground excavation using an automatic machine, the excavator becomes very large, and unlike the construction inside the caisson such as civil engineering work, a place where temporary columns are forested like the reverse construction method in conventional construction work. It is not suitable for construction because of lack of mobility of the excavating machine. B) Conventional excavators (Yumbo, Dozer Shovel, Clam Ciel, etc.) are operated by an operator and are difficult to automate. C) It is very difficult to install a reverse beam stage that also serves as a cutting beam to support the earth pressure of the retaining wall around the building, because it is very difficult to handle heavy objects in a narrow space, and it will be an obstacle as a working space. .. D) People have scraped off the soil adhering to the temporary columns or retaining walls one by one. E) On the basement floor, there are many thick reinforcing bars, and there are few efficient methods for conveying large amounts of long heavy objects. F) The power of excavating machines is mostly internal combustion machines, and it is not easy to take measures against exhaust gas.

【0004】本発明は前記従来技術の有する問題点に鑑
みて提案されたもので、その目的とする処は、作業性が
優れ、施工精度が向上し、省力化と作業環境を改善し公
害の発生を防止する逆打工法による建築物地下部の自動
化された構築方法を提供する点にある。
The present invention has been proposed in view of the problems of the above-mentioned prior art, and the purpose thereof is to provide excellent workability, improved construction accuracy, labor saving and improved work environment, thereby reducing pollution. The point is to provide an automated construction method of the underground part of the building by the reverse driving method to prevent the occurrence.

【0005】[0005]

【課題を解決するための手段】前記の目的を達成するた
め、本発明に係る建築物地下部の構築方法によれば、逆
打ち工法による建築物の地下部の構築方法において、地
盤頂部を型枠及び支保工として使用して下面に作業機械
走行用レールを設置した梁と床版とからなる頂部床面構
造体を構築するとともに、同床面構造体に土圧支持水平
構面を兼用せしめ、次いで前記レールに走行自在に懸吊
された天井走行型の作業機械によって、前記床面構造体
下部の地盤を掘削して、下階の土圧水平支持構面を兼用
する床面構造体を構築するとともに、建物地下構造体を
構築し、以下前記の工程を反覆して複数階の構築を行う
ものである。
In order to achieve the above object, according to the method of constructing an underground portion of a building according to the present invention, in the method of constructing an underground portion of a building by a reverse construction method, Construct a top floor structure consisting of beams and floor slabs with rails for running work machines on the bottom surface used as a frame and supporting work, and also use the floor structure as a horizontal surface for earth pressure support. Then, by using an overhead traveling type working machine suspended so that it can travel freely on the rails, the ground at the bottom of the floor structure is excavated, and a floor structure that also serves as an earth pressure horizontal support structure on the lower floor is formed. Along with the construction, a building underground structure is constructed, and then the above steps are repeated to construct a plurality of floors.

【0006】[0006]

【作用】本発明によれば前記したように、地盤頂部を型
枠及び支保工として利用し、下面に作業機械走行用レー
ルを設置した梁と床版からなる頂部床面構造体を構築
し、同構造体によって土圧を支持し、同構造体の下部を
掘削して下階の床面構造体を構築する。
According to the present invention, as described above, the top of the ground is used as a formwork and supporting structure, and a top floor structure including a beam and a floor slab on which a rail for running a working machine is installed on the lower surface is constructed. Earth pressure is supported by the structure, and the lower part of the structure is excavated to construct the floor structure on the lower floor.

【0007】この際、前記床面構造体下面のレールが地
盤の掘削以前に設置されるので、同レールに走行自在に
懸架される天井走行型の作業機械の使用が可能となり、
高精度の掘削建物地下構造体の構築が可能となり、掘削
土の搬出が効率的に行なわれ、前記作業機械を電気的に
駆動することによって、地下の作業環境が改善されて公
害の発生を防止しうるものである。
At this time, since the rail on the lower surface of the floor structure is installed before excavation of the ground, it becomes possible to use an overhead traveling type working machine suspended freely on the rail,
It becomes possible to construct an underground structure of a highly accurate excavated building, the excavated soil is efficiently carried out, and the work machine is electrically driven to improve the underground work environment and prevent pollution. It is possible.

【0008】[0008]

【実施例】以下本発明を図示の実施例について説明す
る。地下工事に先立って、地下構築物の外周面に山留工
事を必要深さまで施工する(図1参照)。次に建物の自
重を支持地盤へ伝達する杭2を構築し、同杭2の上部に
施工中の建物自重を支えるH型鋼等による構真柱3を立
設する。
The present invention will be described below with reference to the illustrated embodiments. Prior to underground construction, mountain retaining work will be performed on the outer peripheral surface of the underground structure to the required depth (see Fig. 1). Next, the pile 2 that transmits the weight of the building to the supporting ground is constructed, and on the upper part of the pile 2, the true pillar 3 made of H-shaped steel or the like that supports the weight of the building under construction is erected.

【0009】以上はいずれも従来工法によって施工さ
れ、地上躯体と地下逆打工法における鉛直荷重支持用の
工事が完了する。なお5は施工場所の地盤である。次に
図2及び図11並に図12において、前記基礎部分の工
事を完了して平地となった敷地の地盤5を従来土工機械
又は後記する作業機械により建物1階部分の床版6、梁
7、鉄骨柱脚8及び梁下に装架されるホイストレール9
を設置するのに必要な空間を掘削する。この時掘削地盤
の表面はコンクリート用型枠及びレール設置用床面とし
ては凹凸が大きいので、捨てコンクリート10を必要な
部分に打設し精度を保持する。また梁7部分の垂直面に
は高強度コンクリート板等による型枠11を設置する。
更にホイストレール9の上部は空間となるので前記同様
のコンクリート板等の型枠12を設置して同空間を封塞
する。ホイストレール9及びそのアンカー15と梁7、
床版6の各鉄筋13,14とを同時に設置しコンクリー
トCの打設を行い1階部分の床面構造体Sの施工を完了
する。図12中、pの範囲は梁7の底面の型枠としての
捨コンクリート、qの範囲は同じく高強度コンクリート
板等による型枠を表わす。
All of the above are carried out by the conventional construction method, and the construction for supporting the vertical load in the above-ground frame and the underground reverse construction method is completed. In addition, 5 is the ground of the construction site. 2 and 11, as well as in FIG. 12, the ground 5 of the site, which has become a flat land after the construction of the foundation portion is completed, is converted into a floor slab 6 and a beam on the first floor of the building by a conventional earthworking machine or a working machine described later. 7, steel column base 8 and hoist rail 9 mounted under the beam
Excavate the space needed to set up. At this time, since the surface of the excavated ground has large irregularities for the concrete formwork and the floor surface for rail installation, the waste concrete 10 is placed in a necessary portion to maintain accuracy. Further, a mold 11 made of high-strength concrete plate or the like is installed on the vertical surface of the beam 7.
Further, since the upper part of the hoist rail 9 becomes a space, a mold 12 such as a concrete plate as described above is installed to close the space. Hoist rail 9 and its anchor 15 and beam 7,
The reinforcing bars 13 and 14 of the floor slab 6 are installed at the same time, concrete C is placed, and the construction of the floor structure S on the first floor is completed. In FIG. 12, the range of p represents waste concrete as a formwork on the bottom surface of the beam 7, and the range of q represents a formwork made of high-strength concrete plate or the like.

【0010】次に図3に示すように地上部分の工事を行
う。柱脚8の上に地上構造の柱16を接合し、本出願人
の提案に係る特願平3−43381号(発明の名称「建
築物の構築方法」)の構築方法により、最終的に最上階
の構造体となる仮設ステージKの下面に配設されたホイ
ストレール17に走行自在に懸架された各種作業機械1
8によって地上構造の梁19、及び地下作業用仮設フレ
ーム20を構築する。更にこの仮設フレーム20で一連
の作業を行う、ホイスト21、クラムシエル22、ベル
トコンベヤー23等の排土機器の設置も作業機械18が
行う。以上説明したように地上部分の構築は前記仮設ス
テージKを順次上昇させながら、工事を進行させる。
(図4参照) 地下部分工事は図4のように1階の床面構造体Sの一部
分に地下工事用開口部24を設け、先ずクラムシエル2
2等により地盤5を掘削し、クラムシエル22を巻き上
げホイストを21′の位置に走行させクラムシエルを2
2′に示すように開放してホツパー25に掘削土5を排
出する。この排土をベルトコンベアー23でトラツク2
6に積載し、場外へ運搬する。この作業を繰り返えし行
い図5のように地下地盤掘削機27が入る大きさまで地
盤5が掘削排土されると、仮設フレーム20に補完レー
ル28を介し、ベースマシン29に装着した掘削機27
を懸架し、開口部24の直上より降下させ図6のように
1階床面構造体Sの梁下に予め装架されているホイスト
レール9に補完レール28を嵌合し、同補完レール28
よりホイストレール9にベースマシン29上の掘削機2
7を走行し、水平方向地盤5を掘削する。
Next, as shown in FIG. 3, construction of the above-ground portion is performed. The pillar 16 of the ground structure is joined onto the pillar base 8, and finally the best construction is made by the construction method of Japanese Patent Application No. 3-43381 (the title of the invention "construction method of building") proposed by the applicant. Various working machines 1 suspended movably on a hoist rail 17 arranged on the lower surface of a temporary stage K which is a structure of the floor
8 constructs a beam 19 having a ground structure and a temporary frame 20 for underground work. Further, the work machine 18 also installs earth discharging equipment such as a hoist 21, a clam shell 22, a belt conveyor 23, and the like for performing a series of operations with the temporary frame 20. As described above, in the construction of the above-ground portion, the construction is advanced while the temporary stage K is sequentially raised.
(Refer to FIG. 4) As for the subsurface construction, as shown in FIG. 4, an opening 24 for the underground construction is provided in a part of the floor structure S on the first floor, and first the clam shell 2 is used.
The ground 5 is excavated by 2 etc., the clam shell 22 is wound up, the hoist is moved to the position of 21 ', and the clam shell 2 is moved.
The excavated soil 5 is discharged to the hopper 25 by opening it as indicated by 2 '. The belt 2 conveys this soil to the truck 2
It is loaded on No.6 and transported to the outside. When this operation is repeated and the ground 5 is excavated and discharged to a size where the underground ground excavator 27 can be inserted as shown in FIG. 5, the excavator mounted on the base machine 29 via the complementary rail 28 on the temporary frame 20. 27
6 and is lowered from directly above the opening 24, and the complementary rail 28 is fitted to the hoist rail 9 which is pre-mounted under the beam of the first floor floor structure S as shown in FIG.
More hoist rail 9 excavator 2 on base machine 29
7 is run and the horizontal ground 5 is excavated.

【0011】前記補完レール28は本出願人の提案に係
る特願平3−161414号(発明の名称「建築工事に
おける資材搬送装置」)に開示された方法により任意の
階でレール、トロリー線、信号線等を接合し図9におけ
る地下1階天井のホイストレール9及びその下階の地下
2階天井のホイストレール34更に下階へ行っても夫々
必要な階で補完レール28を嵌合し、図示せめ係止具に
より錠止固定し掘削機27を任意の階で走行及び作業が
できるようになっている。なお29は各種作業を行うベ
ースマシンでホイストレール9に走行自在に懸架されそ
の先端に掘削機27がつけられている。この先端部材を
交換することにより各種作業を行わせることができる。
このベースマシン29はホイストレール9に沿って走行
して、X,Y方向のコントロールを行い、更に、ベース
マシン29自身の腕により、X,Y,Zの3方向を精度
よくコントロールするので、各種作業を高精度で施工す
ることができる。
The complementary rail 28 is a rail, a trolley wire, on any floor, according to the method disclosed in Japanese Patent Application No. 3-161414 (the title of the invention "material conveying device in construction work") proposed by the present applicant. When connecting the signal lines and the like to the hoist rail 9 on the ceiling on the first basement floor in FIG. 9 and the hoist rail 34 on the ceiling on the second basement floor on the lower floor in FIG. The excavator 27 is locked and fixed by a locking tool (not shown) so that the excavator 27 can run and work on any floor. Reference numeral 29 is a base machine for performing various operations, which is suspended freely on the hoist rail 9 and has an excavator 27 attached to its tip. Various works can be performed by exchanging the tip member.
This base machine 29 runs along the hoist rail 9 to control in the X and Y directions, and the arm of the base machine 29 itself controls the three directions of X, Y and Z with high accuracy. Work can be performed with high precision.

【0012】水平方向の掘削は図7、図8に示すように
掘削機27はベースマシン29の作動により地盤5を掘
削して掘削土砂31を下部に堆積させる。同土砂31の
水平方向の搬送は土砂運搬車32によって行い、1階の
床面構造体Sの開口部24の直下のクラムシエル22で
掘削土砂31を吊り上げ可能な位置へ搬送する。このよ
うに掘削機27により掘削された掘削土砂31を、これ
を土砂運搬車32によりクラムシエル22で掴持できる
所まで集積してクラムシエル22で垂直方向の吊り出し
を行い、ホツパー25とベルトコンベヤー23でダンプ
トラツク26に積載し場外へ搬出する一連の作業を繰り
返して一層分の掘削を行う。このように比較的機械自重
が小さく精度を必要とする掘削機27を天井吊りの構造
とし、重量の大きい単純な往復運動による前記土砂31
運搬は地盤5上を土砂運搬車32が走行する方式で夫々
を分離して、建物構造の建設時、仮設用荷重のための構
造変更を軽減又は不要とすることができるようにし、経
済的に大きく貢献する。
In the horizontal excavation, as shown in FIGS. 7 and 8, the excavator 27 excavates the ground 5 by the operation of the base machine 29 and deposits the excavated earth 31 on the lower part. The earth and sand 31 is conveyed in the horizontal direction by the earth and sand carrier 32, and the excavated earth and sand 31 is conveyed to a position where the excavated earth and sand 31 can be lifted by the clam shell 22 just below the opening 24 of the floor structure S on the first floor. The excavated earth and sand 31 thus excavated by the excavator 27 is accumulated by the earth and sand carrier 32 to a place where the clam shell 22 can grab it, and vertically suspended by the clam shell 22, and then the hopper 25 and the belt conveyor 23. The excavation for one layer is performed by repeating a series of operations of loading the dump truck 26 and carrying it out of the site. As described above, the excavator 27, which has a relatively small machine weight and requires precision, has a structure of suspending from the ceiling, and the earth and sand 31 due to a simple heavy reciprocating motion is used.
As for transportation, the method of traveling of the earth and sand carrier 32 on the ground 5 separates each one, so that it is possible to reduce or eliminate structural changes due to a temporary load when constructing a building structure, and economically. Make a big contribution.

【0013】同時に天井吊りの掘削機27及び土砂運搬
車32を電動化することにより、作業環境の改善と騒音
対策上有効である。地下掘削中は建物上部構造の自重、
その他荷重は構真柱3が支持し敷地外の水圧及び湧水は
地中連続壁1が安全に支持し湧水を押えている。また、
掘削による地中連続壁1への土圧の影響は1階にすでに
床面構造体Sが完成しているので、この床面構造体Sに
荷重が伝達され、地中連続壁1の荷重スパンは地下1階
の階高分のみとなり経済的に安全性の確保ができる。
At the same time, by electrifying the ceiling-mounted excavator 27 and the earth and sand carrier 32, it is effective for improving the working environment and noise countermeasures. During underground excavation, the weight of the superstructure of the building,
Other loads are supported by the structure columns 3, and water pressure and spring water outside the site are safely supported by the underground continuous wall 1 to suppress the spring water. Also,
The influence of earth pressure on the underground continuous wall 1 due to excavation is that the floor surface structure S has already been completed on the first floor, so the load is transmitted to this floor surface structure S and the load span of the underground continuous wall 1 Is only for the height of the first basement floor, and economical safety can be ensured.

【0014】次に地下1階の床面構造体S′の構築は前
記1階の床面構造体Sの構築に準じて行うもので、その
作業は1階床構造Sの下のホイストレール9に走行自在
に懸架されたベースマシン29の先端に各種作業機械3
3を着脱し、マシニングセセンター的な機能を活用して
図11,12に示すとおり構築する。即ち地盤5をコン
クリート用型枠と支保工の代用をさせるための同地盤5
の掘削、排土、ホイストレール34の設置し、捨てコン
クリート10の打設、均らし、作業セメント系型枠11
の設置、鉄筋13,14の配筋、コンクリートCの打
設、均らし作業を行う。
Next, the construction of the floor surface structure S'of the first basement is carried out in accordance with the construction of the floor surface structure S of the first floor, and the work is performed under the hoist rail 9 under the first floor structure S. Various work machines 3 are attached to the tip of the base machine 29 that is suspended freely on the ground.
3 is attached and detached, and it is constructed as shown in FIGS. That is, the ground 5 is used as a substitute for concrete formwork and support work.
Excavation, earth removal, installation of hoist rail 34, placing and leveling of discarded concrete 10, work cement-based formwork 11
Installation, reinforcement bar 13, 14 reinforcement, concrete C placement, and leveling work.

【0015】更に天井、壁、床等の内装工事建築設備の
工事も各種作業機械33により行う。更にまた下階の工
事は前記したように、補完レール28が任意の階で係止
具により錠止固定できるので、地下1階と全く同じ方法
で一層づつ固めながら下階へと構築し、図10のように
杭2に建物の基礎35と最下階を構築して構造体が完成
する。次に、土工事用のクラムシエル22、ベルトコン
ベヤー23等の不要になった機器類を撤去する。あとは
仕上げ工事と前記床面構造体S、S′の開口部24の補
修を行い、仮設フレーム20及びこれに設置された補完
レール28、ホイスト21等を撤去して工事を完了す
る。
Further, interior work such as ceilings, walls, floors, and the like, construction work for construction equipment is also performed by various work machines 33. Furthermore, as mentioned above, the construction of the lower floor is possible because the complementary rail 28 can be locked and fixed on any floor by a locking tool, so that the lower rail can be constructed by hardening it one by one in exactly the same way as the first basement floor. The foundation 35 and the lowest floor of the building are constructed on the pile 2 as shown in 10, and the structure is completed. Next, unnecessary equipment such as the clam shell 22 for earthwork and the belt conveyor 23 is removed. After that, finishing work and repair of the openings 24 of the floor structures S and S'are carried out, and the temporary frame 20, the complementary rail 28 and the hoist 21 installed therein are removed, and the work is completed.

【0016】以上のように、地盤を支保工にして掘削前
に床面構造体Sとしての土圧支持用水平構面を活用し、
水平作業用ホイストレール9,34を床面構造体Sと同
時に取付け、これを地盤の掘削から使用することにより
狭隘な空間での重量物取扱い作業を安全、高精度で行う
ことが可能となる。前記実施例に示す方法においては床
版梁のコンクリート打設時の支保工(前記切り梁兼用逆
打ちステージ)を省略するために床版、梁の夫々の必要
高さ毎に地盤の掘削を行い必要レベルまで捨てコンクリ
ート打ちを打設し、凹凸面の整形が必要な部分のみセメ
ント系打込み型枠を設置してコンクリート鋳型を形成
し、そこに鉄筋を配筋してコンクリート打設することに
よって前記課題ハ)の切り梁兼用逆打ち用ステージを省
略し地下掘削後の土圧と支持させるようにしたものであ
る。
As described above, the earth support structure is used to support the earth pressure support horizontal structure as the floor structure S before excavation.
By attaching the horizontal work hoist rails 9 and 34 at the same time as the floor surface structure S and using the hoist rails from the ground excavation, it is possible to safely and accurately perform heavy object handling work in a narrow space. In the method shown in the above-mentioned embodiment, the ground excavation is performed for each required height of the floor slab and the beam in order to omit the support work (the above-mentioned reverse beam-cutting stage for beam cutting) when placing the concrete on the floor slab. By discarding concrete up to the required level, placing a cement-based driving form only on the part where irregularities need to be shaped to form a concrete mold, and arranging rebar there The problem is that the reverse beaming stage that also serves as a beam is omitted and it is supported by the earth pressure after underground excavation.

【0017】また前記コンクリート部の下面に水平作業
用ホイストレールを設置し、同レールに走行自在に懸架
された作業機械が前記コンクリート床面下の地盤の掘削
を即座に行うことが可能になる。またこの天井走行式の
作業機械は支持している鉄筋コンクリート構造体が建物
本来の保有耐力を超過しない程度の比較的軽量の機能と
し、ホイストレール上走行の利点をいかし、互いに直交
するX,Y,Z軸方向のコントロールの精度を向上さ
せ、狭隘な仮支柱の林立する空間での地盤の掘削を可能
とする。各種の作業機械は電力を動力源として電動化す
ることができる。これにより前記課題イ)ト)及びロ)
の掘削機能を解決するものである。
Further, a hoist rail for horizontal work is installed on the lower surface of the concrete portion, and a work machine suspended freely on the rail can immediately excavate the ground under the concrete floor surface. In addition, this overhead traveling work machine has a relatively lightweight function such that the reinforced concrete structure that it supports does not exceed the inherent strength of the building, and takes advantage of traveling on the hoist rails. The accuracy of control in the Z-axis direction is improved, enabling the excavation of the ground in a narrow forested space of temporary columns. Various work machines can be electrified using electric power as a power source. As a result, the above problems a) g) and b)
Is to solve the excavation function of.

【0018】更に天井吊り機械としては、仮支柱、土留
め壁等に付着した土を掃除する大型回転ブラシ機械鉄筋
の搬送及び組立をする機械、コンクリートの搬送打設均
らし作業をする機械設備機器の設置、配管、配線を設置
する機械仕上材料を搬送仕上げをする機械等一連の建設
作業が可能なインテリジエントな各種機械を必要に応じ
て走行させ作業を行うことによって前記課題ニ)ホ)を
解決することができる。
Further, as a ceiling hanging machine, a large rotating brush machine for cleaning soil adhering to temporary columns, earth retaining walls, etc. A machine for transporting and assembling rebar, a machine and equipment for transporting and leveling concrete. Installation, piping, wiring installation, finishing, transporting and finishing finishing materials, etc. By running various intelligent machines that can perform a series of construction work as necessary, the above problems d) e) Can be resolved.

【0019】更に各種の掘削機械並びに作業機械は水平
作業用ホイストレールにより決められたコースのみを単
純に往復する機械とすることによりケーブルよりの電力
供給が可能となる。また、土砂運搬車により前記課題
ロ)の搬送機能と、ト)の公害発生の問題を解決でき
る。更にまた掘削土の垂直搬送はレーザー又は超音波等
による深度センサーにより水平搬送された掘削土の盛り
上げ高さを検知し自動的にコントロールできるクラムシ
エルにより地上のトラツクに積み込むこれにより前記課
題へ)の機械化を計る。又、伸縮式のバケツトコンベヤ
ーにより搬出深度の増加対応させることも可能である。
Further, various excavating machines and working machines can be supplied with electric power from a cable by simply reciprocating only a course determined by a horizontal hoist rail. Also, the earth and sand carrier can solve the above-mentioned problem (b) of the transport function and (g) the problem of occurrence of pollution. In addition, vertical transportation of excavated soil is detected by a depth sensor such as laser or ultrasonic wave, and the height of excavated soil that has been horizontally transported can be detected and automatically controlled and loaded onto a track on the ground by a clam shell. Measure It is also possible to increase the carry-out depth by using a telescopic bucket conveyor.

【0020】以上の各手段の組み合わせにより、逆打ち
工法の機械化施工の実現が可能となる。
By combining the above means, it is possible to realize the mechanized construction of the reverse construction method.

【0021】[0021]

【発明の効果】本発明によれば逆打ち工法による建築物
地下部の構築方法において、地盤を型枠及び支保工とし
て使用して、型枠支保工を省略し下面に水平作業用ホイ
ストレールを設置した梁と床版とからなる床面構造体を
構築するとともに、同床面構造体に土圧支持水平構面を
兼用せしめることによって、土圧支持用切梁を不要なら
しめ、切梁の盛り替え、支持位置の変更がなくなり、土
圧に対する安全性が向上し、更に中間に切梁がないた
め、空間の有効利用が可能になり、更に仮設材の設置、
片付けのための作業がなくなり、また前記床面構造体の
型枠脱型、片付けが不要になり、作業性が向上される。
According to the present invention, in the method for constructing the underground part of the building by the upside down construction method, the ground is used as the formwork and the support work, the formwork support work is omitted, and the horizontal hoist rail is provided on the lower surface. By constructing a floor structure consisting of installed beams and floor slabs, and by making the same floor structure also serve as a horizontal structure for earth pressure support, a truss for earth pressure support becomes unnecessary, Since there is no need to refill or change the support position, the safety against earth pressure is improved, and since there is no beam in the middle, it is possible to effectively use the space, and also to install temporary materials,
Work for tidying up is eliminated, and mold demolding and tidying up of the floor structure are not necessary, and workability is improved.

【0022】また前記走行用レール走行自在に懸架され
た天井走行機械を使用することによって、施工精度の向
上が図られ、また精度を要する地盤の掘削と重量物運搬
の土砂の水平搬送とを別系統にすることによって、床面
構造体の耐力保持と掘削精度の向上を図ることができ、
更に掘削地盤面を走行する土砂運搬車の動力を電力とす
ることによって、操作性を向上し、排気ガス、騒音の発
生を防止しうるものである。
Further, by using the overhead traveling machine suspended so that the traveling rail can travel freely, the construction accuracy can be improved, and the excavation of the ground which requires the accuracy and the horizontal transportation of the earth and sand for the heavy load transportation are separately performed. By making it a system, it is possible to maintain the yield strength of the floor structure and improve the excavation accuracy,
Further, by using the power of the earth and sand carrier traveling on the excavated ground surface as electric power, operability can be improved and generation of exhaust gas and noise can be prevented.

【0023】本発明によれば現在人力で行なわれている
逆打ち工法を大きく変更することなく、機械化施工が可
能となり、省力化が図られ、作業環境が改善され、安全
性が確保されるものである。
According to the present invention, mechanized construction can be carried out without largely changing the reverse striking method which is currently performed manually, labor is saved, the working environment is improved, and safety is ensured. Is.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る建築物地下部の構築方法の一実施
例の杭部の施工状況を示す縦断面図である。
FIG. 1 is a vertical cross-sectional view showing a construction state of a pile portion of an embodiment of a method for constructing a building underground portion according to the present invention.

【図2】本発明の方法における1階部分の施工完了状況
を示す縦断面図である。
FIG. 2 is a vertical cross-sectional view showing a construction completion situation of the first floor portion in the method of the present invention.

【図3】本発明の方法における地上部躯体の状況と地下
工事用仮設機材の関係を示す縦断面図である。
FIG. 3 is a vertical cross-sectional view showing the relationship between the condition of the above-ground structure and the temporary equipment for underground construction in the method of the present invention.

【図4】本発明の方法における地上部躯体の施工状況と
地下部分排土工事の状況とを示す縦断面図である。
FIG. 4 is a vertical cross-sectional view showing the construction status of the above-ground structure and the underground excavation work according to the method of the present invention.

【図5】本発明の方法における地下部分掘削用機械の搬
入状況を示す縦断面図である。
FIG. 5 is a vertical cross-sectional view showing a loading state of an underground excavating machine according to the method of the present invention.

【図6】本発明の方法における地下部分掘削工事を説明
する縦断面図である。
FIG. 6 is a vertical cross-sectional view for explaining underground excavation work in the method of the present invention.

【図7】本発明の方法における地下部分の掘削と掘削土
砂の水平搬送と垂直方向の排土とトラツクへの積込み状
況を示す縦断面図である。
FIG. 7 is a vertical cross-sectional view showing excavation of an underground portion, horizontal transportation of excavated soil, vertical discharge of soil, and loading on a truck in the method of the present invention.

【図8】本発明の方法における土砂の水平搬送機械の稼
動状態を示す縦断面図である。
FIG. 8 is a vertical cross-sectional view showing an operating state of the horizontal earth-sand transporting machine according to the method of the present invention.

【図9】本発明の方法における地下部分の一連の工事を
説明する縦断面図である。
FIG. 9 is a vertical cross-sectional view for explaining a series of construction work of the underground portion in the method of the present invention.

【図10】本発明の方法における地下工事がほぼ完了し
た状態を示す縦断面図である。
FIG. 10 is a vertical cross-sectional view showing a state in which underground construction according to the method of the present invention is almost completed.

【図11】本発明の方法における床面構造体の作業機械
走行用レールの施工状況を示す縦断面図である。
FIG. 11 is a vertical cross-sectional view showing a construction situation of a rail for working machine traveling of a floor structure in the method of the present invention.

【図12】図11の矢視イ−イ図である。12 is a view taken along the line EE in FIG.

【図13】従来の逆打ち工法の実施状況を示す縦断面図
である。
FIG. 13 is a vertical cross-sectional view showing a state of implementation of a conventional upside-down construction method.

【図14】図13の次工程を示す縦断面図である。FIG. 14 is a vertical cross-sectional view showing the next step of FIG.

【図15】図14の次工程を示す縦断面図である。FIG. 15 is a vertical cross-sectional view showing the next step of FIG.

【符号の説明】[Explanation of symbols]

S 床面構造体 1 地中連続壁 3 構真柱 5 地盤 6 床版 7 梁 9 ホイストレール 16 柱 18 作業機械 21 ホイスト 22 クラムシエル 23 ベルトコンベヤー 24 開口部 25 ホツパー 26 ダンプトラツク S Floor surface structure 1 Underground continuous wall 3 Structure true pillar 5 Ground 6 Floor slab 7 Beam 9 Hoist rail 16 Pillar 18 Working machine 21 Hoist 22 Clam shell 23 Belt conveyor 24 Opening 25 Hopper 26 Dump truck

───────────────────────────────────────────────────── フロントページの続き (72)発明者 丸 隆宏 東京都渋谷区千駄ケ谷四丁目6番15号 株 式会社フジタ内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Takahiro Maru 4-6-15 Sendagaya, Shibuya-ku, Tokyo Fujita Co., Ltd.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 逆打ち工法による建築物の地下部の構築
方法において、地盤頂部を型枠及び支保工として使用し
て下面に作業機械走行用レールを設置した梁と床版とか
らなる頂部床面構造体を構築するとともに、同床面構造
体に土圧支持水平構面を兼用せしめ、次いで前記レール
に走行自在に懸吊された天井走行型の作業機械によっ
て、前記床面構造体下部の地盤を掘削して、下階の土圧
水平支持構面を兼用する床面構造体を構築するととも
に、建物地下構造体を構築し、以下前記の工程を反覆し
て複数階の構築を行うことを特徴とする建築物地下部の
構築方法。
1. A method for constructing a basement of a building by a reverse construction method, in which a top floor composed of a beam and a floor slab, the top of the ground being used as a formwork and supporting work, and a rail for running a working machine being installed on the lower surface. While constructing a surface structure, the floor structure also serves as a horizontal structure for earth pressure support, and then by an overhead traveling type working machine suspended movably on the rail, the lower part of the floor structure is Excavating the ground to construct a floor structure that also serves as a horizontal support structure for the earth pressure on the lower floor, construct a substructure of the building, and repeat the above steps to construct multiple floors. A method of constructing an underground part of a building characterized by.
JP3305982A 1991-11-21 1991-11-21 How to build the basement of the building Expired - Fee Related JP2769941B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3305982A JP2769941B2 (en) 1991-11-21 1991-11-21 How to build the basement of the building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3305982A JP2769941B2 (en) 1991-11-21 1991-11-21 How to build the basement of the building

Publications (2)

Publication Number Publication Date
JPH05140957A true JPH05140957A (en) 1993-06-08
JP2769941B2 JP2769941B2 (en) 1998-06-25

Family

ID=17951646

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3305982A Expired - Fee Related JP2769941B2 (en) 1991-11-21 1991-11-21 How to build the basement of the building

Country Status (1)

Country Link
JP (1) JP2769941B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017119953A (en) * 2015-12-28 2017-07-06 株式会社竹中工務店 Building method using reverse out method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100939916B1 (en) 2009-07-14 2010-02-03 나석주 Construction method of train platform base pile

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61109827A (en) * 1984-10-31 1986-05-28 Takenaka Komuten Co Ltd Construction of basement
JPH03100225A (en) * 1989-09-14 1991-04-25 Taisei Corp Inverted hitting construction using multifunction working floor and the same floor

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61109827A (en) * 1984-10-31 1986-05-28 Takenaka Komuten Co Ltd Construction of basement
JPH03100225A (en) * 1989-09-14 1991-04-25 Taisei Corp Inverted hitting construction using multifunction working floor and the same floor

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017119953A (en) * 2015-12-28 2017-07-06 株式会社竹中工務店 Building method using reverse out method

Also Published As

Publication number Publication date
JP2769941B2 (en) 1998-06-25

Similar Documents

Publication Publication Date Title
US5112161A (en) Method for excavating and constructing monolithic continuous straight or circular structural walls and a machine for realizing such a method
JP4853429B2 (en) Support structure of lining board, method of supporting lining board
JP2019120115A (en) Method of constructing tunnel lining structure
JP6043006B1 (en) Construction method of underground structure
CN110106915A (en) One kind exempts from that support is inverse to make underground engineering construction method and underground construction structure
JP3356048B2 (en) Construction method of elevated structure using building girder
CN111287194A (en) Recyclable foundation pit supporting structure using inclined steel sheet piles and supporting method thereof
JP2769941B2 (en) How to build the basement of the building
JPH07127374A (en) Method for constructing tunnel
CN114961336A (en) Protective demolition construction method for basement pile foundation next to existing subway line
CN211737163U (en) Subway station support system for receiving double-line shield in advance
JP3910135B2 (en) Building construction method and beam member used therefor
CN111456143A (en) Open excavation construction equipment for comprehensive pipe gallery and construction method thereof
JPH08253947A (en) Installation method for form-support in reverse placing method of concrete
CN209523201U (en) The structure of form concrete between a kind of subway station fender post
JPH05255943A (en) Construction method for underground skeleton by slide down system
CN114875925B (en) Construction method of oversized deep foundation pit of subway tunnel adjacent to sea-filling stratum
KR100777777B1 (en) Earthwork temporary ramp using mainsteel structure
JP5167578B2 (en) Construction method for underground structures
JPH07331997A (en) Constructing method of rock cavern
JPH0971923A (en) Construction method of inclined cable way equipment
JP3236092B2 (en) Steel frame reinforced concrete reverse driving method
JP2001090478A (en) Open shield machine
CN115897600A (en) Construction method for newly-built foundation pit close to existing subway station deep foundation pit proximity area
CN115369916A (en) Underground building construction method

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees