JP2017119953A - Building method using reverse out method - Google Patents

Building method using reverse out method Download PDF

Info

Publication number
JP2017119953A
JP2017119953A JP2015255833A JP2015255833A JP2017119953A JP 2017119953 A JP2017119953 A JP 2017119953A JP 2015255833 A JP2015255833 A JP 2015255833A JP 2015255833 A JP2015255833 A JP 2015255833A JP 2017119953 A JP2017119953 A JP 2017119953A
Authority
JP
Japan
Prior art keywords
floor
temporary opening
building
construction
temporary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2015255833A
Other languages
Japanese (ja)
Other versions
JP6654428B2 (en
Inventor
正信 ▲徳▼久
正信 ▲徳▼久
Masanobu Tokuhisa
茂 原野
Shigeru Harano
茂 原野
真二 立花
Shinji Tachibana
真二 立花
国光 森
Kunimitsu Mori
国光 森
憲一 森口
Kenichi Moriguchi
憲一 森口
秀幸 渡邊
Hideyuki Watanabe
秀幸 渡邊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP2015255833A priority Critical patent/JP6654428B2/en
Publication of JP2017119953A publication Critical patent/JP2017119953A/en
Application granted granted Critical
Publication of JP6654428B2 publication Critical patent/JP6654428B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a technology capable of efficiently constructing an underground building part while sufficiently providing a process shortening effect using a simultaneous construction of a building part and a ground building part.SOLUTION: Relating to a building method using a reverse out method, a temporary opening part A which extends over a plurality of post spans S is formed at a floor part 11A which is on an upper floor side than a bottom floor in a portion constructed by the reverse out method in a building B, and under a condition where the temporary opening part A is being formed, a construction work at a floor just under the floor where the temporary opening part A is formed is carried out.SELECTED DRAWING: Figure 2

Description

本発明は、逆打ち工法を用いた建築方法に関する。   The present invention relates to a construction method using a reverse driving method.

逆打ち工法は、まず、地下建物部の構築部位の外周に山留め壁を形成し、地下建物部の本設柱を構真柱として地盤中に打ち込んだ後、地盤の掘削作業と、構真柱に支持させながら梁や床部を構築する躯体構築作業とを繰り返し、上階側の建物躯体にて山留め壁を支保しながら地下建物部を下階側に向かって順に構築する工法である。
この逆打ち工法を用いれば、地下の切梁の省略が可能となり、更に、地上建物部の荷重も構真柱に支持させて地下建物部と地上建物部とを同時に施工することにより、全体工期を大幅に短縮することが可能となる。
In the reverse driving method, first, a retaining wall is formed on the outer periphery of the construction part of the underground building, and after the main pillar of the underground building is driven into the ground as a construction pillar, the excavation work of the ground and the construction pillar It is a construction method that constructs the underground building part in order toward the lower floor side while supporting the mountain retaining wall in the building frame on the upper floor side by repeating the frame construction work for building the beam and the floor part while supporting it.
By using this reverse driving method, it is possible to omit the underground beam, and the entire construction period can be achieved by simultaneously constructing the underground building part and the above ground building part while supporting the load of the above ground building part on the construction pillar. Can be greatly shortened.

このような逆打ち工法を用いる場合、先に構築した上階側の床部と下階側の床部の構築部位との間の高さ制限の中で掘削作業等を行うことになる。しかしながら、例えば、掘削する地盤が岩盤等の硬質地盤で、通常の掘削機では相当に時間がかかる場合など、高さ制限を越える高さの作業空間を必要とする大型の掘削機の使用が望ましいこともある。   When such a reverse driving method is used, excavation work or the like is performed in a height restriction between the previously constructed upper floor portion and the lower floor portion. However, for example, when the ground to be excavated is hard ground such as rock, and it takes a long time with a normal excavator, it is desirable to use a large excavator that requires a working space whose height exceeds the height limit. Sometimes.

そこで、地下建物部において、複数の柱スパンに亘る平面視の中央部以外の外周部を逆打ち工法で構築する部分とし、当該外周部のみを逆打ち工法にて構築することで、構築した外周部にて山留め壁を支えながら、中央部に地上まで開放された大きな空間を形成するようにした建築方法が提案されている(下記特許文献1参照)。この建築方法では、地下建物部の中央部は、外周部を形成した後で上階側に向かって順打ち工法にて構築することになる。   Therefore, in the underground building part, the outer peripheral part other than the central part in plan view over a plurality of column spans is the part constructed by the reverse hammering method, and the outer circumference constructed by constructing only the outer peripheral part by the reverse hammering method. A construction method has been proposed in which a large space that is open to the ground is formed in the central portion while supporting the mountain retaining wall at the portion (see Patent Document 1 below). In this construction method, the central part of the underground building part is constructed by the forward construction method toward the upper floor side after forming the outer peripheral part.

特開2012−107430号公報JP 2012-107430 A

特許文献1記載の技術では、地下建物部を構築する際、中央部の大きな空間を利用して大型の掘削機等を使用することができるので、地盤が岩盤等の硬質地盤であっても掘削作業を効率的に実施することができる。
しかしながら、地下建物部の中央部以外の外周部を逆打ち工法で構築する部分とし、地下建物部の中央部は外周部を形成した後で順打ち工法にて構築するので、地下建物部と地上建物部の同時施工を実施する場合に、地上建物部の中央部側を適切に支持することができない。
そのため、この特許文献1記載の技術では、地上建物部の構築作業が制限されることになり、地下建物部と地上建物部の同時施工による工期短縮効果が不十分になる問題がある。
In the technology described in Patent Document 1, when constructing an underground building, a large excavator can be used using a large space in the center, so excavation is possible even when the ground is hard ground such as rock. Work can be performed efficiently.
However, since the outer peripheral part other than the central part of the underground building part is a part to be constructed by the reverse driving method, and the central part of the underground building part is constructed by the forward construction method after forming the outer peripheral part, the underground building part and the ground When carrying out the simultaneous construction of the building part, the center part side of the ground building part cannot be properly supported.
Therefore, in the technique described in Patent Document 1, the construction work of the above-ground building part is restricted, and there is a problem that the construction period shortening effect by the simultaneous construction of the underground building part and the above-ground building part becomes insufficient.

この実情に鑑み、本発明の主たる課題は、地下建物部と地上建物部の同時施工による工期短縮効果は十分に得られながら、地下建物部を効率的に構築することのできる技術を提供する点にある。   In view of this situation, the main problem of the present invention is to provide a technique capable of efficiently constructing an underground building part while sufficiently obtaining the work period shortening effect by simultaneous construction of the underground building part and the above ground building part. It is in.

本発明の第1特徴構成は、逆打ち工法を用いた建築方法において、
建物における逆打ち工法にて構築する部分中の最下階よりも上階側の床部に複数の柱スパンに亘る仮設開口部を形成しておき、
当該仮設開口部を残したままで仮設開口部を形成した階の直下階の構築作業を実施する点にある。
The first characteristic configuration of the present invention is a construction method using a reverse driving method,
A temporary opening spanning a plurality of column spans is formed on the floor portion on the upper floor side from the lowermost floor in the part to be constructed by the reverse driving method in the building,
The construction work is performed on the floor immediately below the floor on which the temporary opening is formed while leaving the temporary opening.

上記構成によれば、逆打ち工法にて構築する部分中の床部に複数の柱スパンに亘る仮設開口部を形成するので、逆打ち工法にて構築する部分の構真柱に地上建物部を支持させる状態で地下建物部と地上建物部の同時施工を適切に実施できながら、仮設開口部の直下階において当該仮設開口部の上下に亘る大きな空間を形成することができる。そして、この仮設開口部の上下に亘る大きな空間を利用し、大型の掘削機等を使用するなどして仮設開口部の直下階の構築作業を効率的に実施することができる。
したがって、地下建物部と地上建物部の同時施工による工期短縮効果は十分に得られながら、地下建物部を効率的に構築することができる。
According to the above configuration, a temporary opening spanning a plurality of column spans is formed in the floor portion in the portion constructed by the reverse driving method, so the ground building portion is formed on the structural pillar of the portion constructed by the reverse driving method. While the simultaneous construction of the underground building portion and the ground building portion can be appropriately performed in the state of supporting, a large space extending above and below the temporary opening portion can be formed on the floor immediately below the temporary opening portion. And the construction work of the floor immediately under the temporary opening can be efficiently carried out by using a large space extending above and below the temporary opening and using a large excavator or the like.
Therefore, it is possible to efficiently construct the underground building part while the effect of shortening the work period by the simultaneous construction of the underground building part and the ground building part is sufficiently obtained.

本発明の第2特徴構成は、前記仮設開口部を形成せずに床部を構築した階よりも下階側の床部に前記仮設開口部を形成する点にある。   The second characteristic configuration of the present invention resides in that the temporary opening is formed in the floor portion on the lower floor side than the floor on which the floor portion is constructed without forming the temporary opening portion.

上記構成によれば、前記仮設開口部を床部に形成した階の上階側には、このような仮設開口部を床部に形成していない階が存在することになる。そのため、この仮設開口部の存在しない上階側の床部を地上建物部の構築作業の作業床にして、地上建物部の構築作業を効率的に実施することができる。したがって、地下建物部と地上建物部の同時施工による工期短縮効果を一層向上させることができる。   According to the said structure, the floor which does not form such a temporary opening in a floor exists in the upper floor side of the floor which formed the said temporary opening in the floor. Therefore, the construction work of the above-mentioned ground building part can be carried out efficiently by using the floor part on the upper floor side where the temporary opening is not present as the work floor of the construction work of the above ground building part. Therefore, the construction period shortening effect by simultaneous construction of the underground building part and the ground building part can be further improved.

本発明の第3特徴構成は、前記仮設開口部を、内部に構真柱が位置する状態で形成し、
前記仮設開口部の内部に位置する前記構真柱に支持させる状態で、前記仮設開口部の相対向する縁辺部間に切梁を亘らせる点にある。
According to a third characteristic configuration of the present invention, the temporary opening is formed in a state where the construction pillar is located inside,
In the state where it is supported by the stem column located inside the temporary opening, a cut beam is extended between the opposing edges of the temporary opening.

上記構成によれば、仮設開口部内の縁辺部間に切梁を亘らせることで、仮設開口部の形成に伴う地下建物部の剛性低下分を補い、山留壁に対する支保力を適切に確保することができる。しかも、仮設開口部の内部に位置する本設柱である頑強な構真柱に切梁を支持させるので、別途の仮設支柱等の支持体を不要にし、安全で効率的な切梁構造にすることができる。   According to the above-mentioned configuration, by making the beam between the edges in the temporary opening, it compensates for the decrease in rigidity of the underground building part due to the formation of the temporary opening, and appropriately secures the support force for the mountain retaining wall. can do. In addition, since the beam is supported by a strong structural pillar, which is a permanent column located inside the temporary opening, a separate support member such as a temporary column is not required, and a safe and efficient beam structure is provided. be able to.

本発明の第4特徴構成は、前記切梁を、複数本の梁材が並ぶ集中切梁として構成し、前記仮設開口部の内部に位置する前記構真柱を複数本の梁材で挟む状態で当該構真柱に支持させるとともに、
当該集中切梁を、前記仮設開口部の縁辺部側の構真柱とスラブとの接続部位に形成されたキャピタル部分で反力を受ける状態に設置する点にある。
According to a fourth characteristic configuration of the present invention, the cut beam is configured as a concentrated cut beam in which a plurality of beam members are arranged, and the frame column located inside the temporary opening is sandwiched between the plurality of beam members. And supporting the construction pillar,
The concentrated cutting beam is installed in a state in which a reaction force is received at a capital portion formed at a connection portion between the erection column and the slab on the edge side of the temporary opening.

上記構成によれば、仮設開口部に設ける切梁を、複数本の梁が並ぶ高剛性の集中切梁とするので、1つの切梁(集中切梁)にて仮設開口部の縁辺部間に大きな突っ張り力を作用させることができる。そのため、切梁の設置間隔を広げることが可能となり、仮設開口部の上下に亘る空間を利用した下階側の構築作業の際に切梁が邪魔になるのを抑制することができる。
また、この切梁は、仮設開口部の内部に位置する構真柱を複数本の梁材で挟む状態で当該構真柱に支持させるので、構真柱に偏荷重がかかり難く、構真柱にて切梁をバランスよく支持することができるとともに、構真柱を挟む複数本の梁材によって切梁と構真柱との相対姿勢(支持姿勢)を適切に保持することができる。
According to the above configuration, the cut beam provided in the temporary opening is a high-rigidity concentrated cut beam in which a plurality of beams are arranged. Therefore, one cut beam (concentrated cut beam) is interposed between the edges of the temporary opening. A large tension force can be applied. Therefore, it becomes possible to widen the installation interval of the cut beams, and it is possible to suppress the cut beams from interfering during the construction work on the lower floor side using the space above and below the temporary opening.
In addition, the beam is supported by the beam in a state where the beam is positioned between a plurality of beam members, so that an eccentric load is not easily applied to the beam. The beam can be supported in a well-balanced manner, and the relative posture (support posture) between the beam and the structural pillar can be appropriately maintained by a plurality of beam members sandwiching the structural column.

建物の施工状況を示す縦断面図Vertical section showing the construction status of the building 建物の施工状況を示す縦断面図Vertical section showing the construction status of the building 仮設開口部を形成した階の要部の水平断面図Horizontal sectional view of the main part of the floor where the temporary opening is formed 集中切梁の設置状況を示す拡大縦断面図Enlarged longitudinal section showing the installation situation of concentrated beams

本発明に係る逆打ち工法を用いた建築方法の実施形態を図面に基づいて説明する。
本建築方法は、図1中において点線で表示した地下建物部10と地上建物部20を上下に備えた建物Bを建築する場合に好適に適用できる。この場合には、下方に向かって順に構築する逆打ち工法を用いて地下建物部10を構築し、これに併行して、地上建物部20を上方に向かって順に構築することができる。
そして、本建築方法は、逆打ち工法にて地下建物部10を構築する際に、図2、図3に示すように、逆打ち工法にて構築する部分中の最下階よりも上階側の床スラブ(床部の一例)11Aに複数の柱スパンS(柱の間隔、以下、単にスパンと称する)に亘る仮設開口部Aを形成することで、地下建物部10の構築作業を効率的に実施することができる。
以下、まず、当該建築方法の概要を説明し、その後、仮設開口部Aの詳細について説明を加える。
An embodiment of a construction method using a reverse driving method according to the present invention will be described with reference to the drawings.
This construction method can be suitably applied when building a building B provided with the underground building part 10 and the ground building part 20 indicated by dotted lines in FIG. In this case, the underground building part 10 can be constructed by using the reverse driving method constructed sequentially in the downward direction, and the ground building part 20 can be constructed in the upward direction in parallel.
And when this construction method constructs the underground building part 10 by the reverse driving method, as shown in FIG. 2 and FIG. 3, it is an upper floor side from the lowest floor in the part constructed by the reverse driving method. The floor building slab (an example of the floor) 11A is formed with temporary openings A that span a plurality of column spans S (column spacing, hereinafter simply referred to as spans), thereby efficiently constructing the underground building 10 Can be implemented.
Hereinafter, the outline of the construction method will be described first, and then the details of the temporary opening A will be described.

(建築方法の概要について)
図1は、当該建築方法の施工初期の状況を示し、同図1に示すように、まず、地盤Gの掘削作業に先立ち、敷地外周側に山留め壁Kを造築するとともに、地下建物部10における逆打ち工法で構築する部分(本例では全部)の本設柱を、逆打ち工法用の構真柱12として地盤中の所定位置に建て込む。構真柱12は、例えば、事前に造築した場所打ちコンクリート杭等からなる構真台柱Jの上部に貫入させて構真台柱Jに支持させる。
(About the outline of the building method)
FIG. 1 shows an initial construction state of the construction method. As shown in FIG. 1, first, prior to excavation work of the ground G, a retaining wall K is constructed on the outer periphery side of the site, and an underground building 10 The main pillars of the part (all in this example) constructed by the reverse driving method are built at predetermined positions in the ground as the construction pillars 12 for the reverse driving method. The structural pillar 12 is supported by the structural pillar J by penetrating into the upper part of the structural pillar J made of cast-in-place concrete piles or the like built in advance.

構真柱12の構造としては、SRC造(鉄骨鉄筋コンクリート造)、RC造(鉄筋コンクリート造)、S造(鉄骨造)等の各種の構造のものであってもよい。例えば、構真柱12をSRC造(鉄骨鉄筋コンクリート造)とする場合には、クロスH鋼やH鋼等の鉄骨部分を構真柱部分とし、地下躯体の構築作業において残りのコンクリート部分を構築して仕上げることができる。   The structure of the structural pillar 12 may have various structures such as SRC (steel reinforced concrete), RC (steel reinforced), S (steel). For example, when the structural pillar 12 is made of SRC (steel reinforced concrete), a steel part such as cross H steel or H steel is used as the structural pillar part, and the remaining concrete part is constructed in the construction work of the underground frame. Can be finished.

次に、少なくとも1階の梁と床スラブ11Aからなる1階の建物躯体(地下躯体)11を構築できるラインまで地盤Gを掘削し(一次掘削)、先に建て込んだ構真柱12に支持させる状態で1階の建物躯体11(図中実線で表示した建物躯体11)を構築する。1階の建物躯体11中の床スラブ11Aは地上建物部20を構築するための作業床に活用する。   Next, the ground G is excavated (primary excavation) to the line where the first-floor building frame (underground frame) 11 composed of at least the first-floor beams and the floor slab 11A can be constructed, and supported by the built-in column 12 previously built. In this state, the first-floor building frame 11 (the building frame 11 indicated by a solid line in the figure) is constructed. The floor slab 11 </ b> A in the building frame 11 on the first floor is used as a work floor for constructing the ground building portion 20.

図2は、当該建築方法の施工中期の状況を示し、同図に示すように、地盤の掘削作業と地下該当階の建物躯体11の構築作業とを、上階側の床スラブ11Aで山留め壁Kを内側から支保しながら下方に向かって順に実施するとともに、この地下建物部10の構築作業に併行し、地上建物部20の柱21を構真柱に支持させながら、地上建物部20の構築作業を上方に向かって順に実施する。そして、最終的に、地下建物部10は最下階下の基礎13(図1参照)を構築し、地上建物部20は最上階を構築する。
このようにして、本建築方法では、地下建物部10と地上建物部20の同時施工による工期短縮を図り、図1中において点線で表示した建物Bを短工期で構築する。
FIG. 2 shows the state of construction in the middle of the construction method. As shown in the figure, the excavation work of the ground and the construction work of the building frame 11 of the corresponding underground floor are carried out by the floor slab 11A on the upper floor side. While supporting K from the inside in order toward the bottom, in parallel with the construction work of the underground building part 10, the pillar 21 of the ground building part 20 is supported by the construction pillar while the ground building part 20 is constructed. Work in order upwards. And finally, the underground building part 10 constructs the foundation 13 (see FIG. 1) on the lowest floor, and the ground building part 20 constructs the top floor.
Thus, in this construction method, the construction period is shortened by simultaneous construction of the underground building part 10 and the ground building part 20, and the building B indicated by the dotted line in FIG. 1 is constructed in a short construction period.

(仮設開口部について)
図2、図3に示すように、本建築方法では、地下3階部分の地盤Gが岩盤等の硬質地盤であるのに対応して、逆打ち工法による地下建物部10の構築作業の途中において、逆打ち工法で構築する部分中の地下2階の床スラブ11Aに複数のスパンSに亘る仮設開口部(換言すれば、1スパンを超える仮設開口部)Aを形成する。
このように大型の仮設開口部Aを地下2階の床スラブ11Aに形成することで、この大型の仮設開口部Aの上下に亘る大空間を地下に形成し、削岩機等の大型の重機を使用して地下3階部分の硬質地盤を掘削し、地下建物部10の構築作業を効率的に実施する。
この仮設開口部Aは、直下階の掘削作業が完了する等の建築中の適宜の時点で床スラブ11Aを構築して閉塞する。
(About the temporary opening)
As shown in FIG. 2 and FIG. 3, in this construction method, in response to the ground G on the third basement floor being a hard ground such as a bedrock, in the middle of the construction work of the underground building part 10 by the reverse driving method. Then, temporary openings (in other words, temporary openings exceeding one span) A extending over a plurality of spans S are formed in the floor slab 11A on the second basement floor in the portion constructed by the reverse driving method.
In this way, by forming the large temporary opening A in the floor slab 11A on the second floor underground, a large space extending above and below the large temporary opening A is formed underground, and a large heavy machine such as a rock drill or the like. Is used to excavate the hard ground on the third floor of the basement to efficiently construct the underground building 10.
The temporary opening A constructs and closes the floor slab 11A at an appropriate time during construction such as the completion of excavation work immediately below the floor.

なお、本例では、仮設開口部Aを形成した地下2階の床スラブ11Aの上階側である地下1階の床スラブ11Aと1階の床スラブ11Aには仮設開口部Aを形成せず、地下工事部分への搬入動線や搬出動線(図示省略)は別途形成しているが、地下工事の施工計画に応じて、これらの床スラブ11Aにも適宜に仮設開口部Aを形成することができる。   In this example, the temporary opening A is not formed in the floor slab 11A on the first basement, which is the upper floor side of the floor slab 11A on the second basement where the temporary opening A is formed, and the floor slab 11A on the first floor. In addition, although the carry-in flow line and the carry-out flow line (not shown) to the underground construction part are separately formed, temporary openings A are appropriately formed in these floor slabs 11A according to the construction plan of the underground work. be able to.

この仮設開口部Aは、図2及び図3に示すように、地下建物部10における平面視で山留め壁Kから離れた部位に形成する。本例では、山留め壁Kが地下建物部10の四方に存在することに対して、地下建物部10の中央部に仮設開口部Aを形成する。このように大型の仮設開口部Aを地下建物部10の中央部に形成することで、地下建物部10の外周部にて周囲の山留め壁Kを内側から支保する。   As shown in FIGS. 2 and 3, the temporary opening A is formed at a site away from the retaining wall K in the plan view of the underground building 10. In this example, the temporary retaining portion A is formed at the center of the underground building portion 10 in contrast to the mountain retaining walls K being present on all sides of the underground building portion 10. Thus, by forming the large temporary opening A at the center of the underground building 10, the surrounding mountain retaining wall K is supported from the inside at the outer periphery of the underground building 10.

仮設開口部Aの具体的な大きさや形状は各種のものを採用できるが、地下建物部10の外周部の幅が、少なくとも山留め壁Kの支保を効果的に行える所定幅を有するように、地下建物部10の平面形状に応じて適切に設定する。
本例では、仮設開口部Aは、地下建物部10の平面形状が長方形状であることに対して、長辺方向を同一に揃えた略相似形の長方形状に設定しており、具体的には、地下建物部10の長辺方向(図2、図3中の左右幅方向)に沿う長さL1が約6スパンで、地下建物部10の短辺方向(図2中の奥行き方向、図3中の上下方向)に沿う長さL2が約3スパンとなる大きさの長方形状に設定する。
Various specific sizes and shapes of the temporary opening A can be employed, but the width of the outer peripheral portion of the underground building 10 is at least a predetermined width that can effectively support the retaining wall K. It is set appropriately according to the planar shape of the building part 10.
In this example, the temporary opening A is set to a substantially similar rectangular shape in which the long side direction is the same, whereas the planar shape of the underground building 10 is rectangular. The length L1 along the long side direction of the underground building part 10 (left and right width direction in FIGS. 2 and 3) is about 6 spans, and the short side direction of the underground building part 10 (depth direction in FIG. 3 is set to a rectangular shape having a length L2 along the vertical direction of 3) of about 3 spans.

仮設開口部Aの相対向する縁辺部a1間には、突っ張り力を発現するジャッキ等(図示省略)を適宜に備えた切梁30を亘らせる。本例では、切梁30は、仮設開口部Aの短辺方向に沿う姿勢で、仮設開口部Aにおける相対向する長辺側の縁辺部a1間に設定間隔毎で複数亘らせることで、仮設開口部Aによる剛性低下が大きな床スラブ11Aの短辺方向を適切に補強する。
なお、切梁30は、仮設開口部Aにおける相対向する長辺側の縁辺部a1間に代えて、又は、これに追加して、仮設開口部Aにおける相対向する短辺側の縁辺部a1間に亘らせてもよい。
A cutting beam 30 appropriately provided with a jack or the like (not shown) that develops a tension force is placed between the opposing edges a1 of the temporary opening A. In this example, the cut beam 30 is in a posture along the short side direction of the temporary opening A, and a plurality of the beams 30 are provided at every set interval between the opposing long side edges a1 in the temporary opening A. The short side direction of the floor slab 11A having a large rigidity reduction due to the temporary opening A is appropriately reinforced.
In addition, it replaces between the edge part a1 of the long side which opposes in the temporary opening part A in addition to this, or the cutting beam 30 is edge part a1 of the short side of the temporary opening part A which opposes. It may be in between.

仮設開口部Aを形成する地下2階の床スラブ11Aは、図2、図3に示すように、下階側の構真柱12が接続される柱頭部位にキャピタル部分11aを一体形成して梁を省略したフラットスラブ構造を採用している。このキャピタル部分11aは、床スラブ11Aの該当部位を下方側に拡厚して構成することができる。なお、地下1階の床スラブ11Aも同様のフラットスラブ構造で構成する。
そして、各切梁30は、このフラットスラブ構造に対応して、図3に示すように、仮設開口部Aの縁辺部a1のうち、床スラブ11Aのキャピタル部分11aの外周端面部に当て付けて当該フラットスラブ構造のキャピタル部分11aで反力を受ける状態に設置する。
このようにすることで、床スラブ11Aにおける切梁30の反力を受ける部分の補強を省略又は簡略化することができる。
As shown in FIG. 2 and FIG. 3, the floor slab 11A on the second basement floor forming the temporary opening A is formed by integrally forming a capital portion 11a at a stigma portion to which a lower pillar side construction column 12 is connected. The flat slab structure which omits is adopted. The capital portion 11a can be formed by expanding the corresponding portion of the floor slab 11A downward. In addition, the floor slab 11A on the first basement floor is configured with the same flat slab structure.
And each cut beam 30 is applied to the outer peripheral end surface portion of the capital portion 11a of the floor slab 11A in the edge portion a1 of the temporary opening A, as shown in FIG. 3, corresponding to the flat slab structure. It installs in the state which receives reaction force in the capital part 11a of the said flat slab structure.
By doing in this way, reinforcement of the part which receives the reaction force of the cut beam 30 in the floor slab 11A can be omitted or simplified.

各切梁30は、仮設開口部Aの内部で立設する構真柱12に支持させる。具体的には、各切梁30は、仮設開口部Aの内部で間隔を空けて立設する複数本(本例では2本)の構真柱12に長手方向の中間部分の複数箇所を支持させる。このようにすることで、切梁30を支持する別途の仮設支柱等を不要にしながら、本設柱である構真柱12にて姿勢保持に有利な中間二点以上の支持点で適切に支持することができる。   Each beam 30 is supported by a structural pillar 12 standing upright inside the temporary opening A. Specifically, each cut beam 30 supports a plurality of intermediate pillars in the longitudinal direction on a plurality (two in this example) of the construction pillars 12 standing at intervals inside the temporary opening A. Let By doing so, it is possible to appropriately support at two or more support points that are advantageous for maintaining the posture with the construction pillar 12 that is a permanent pillar, while eliminating the need for a separate temporary support column that supports the cut beam 30. can do.

複数の切梁30の設置間隔は、1スパン毎でなく、複数スパン(1スパンを超える長さの一例)毎に設定する。このように切梁30の設置間隔を設定して切梁30どうしの間隔を広く確保することで、仮設開口部Aの上下に亘る作業空間を利用した下階側の構築作業の際に切梁30が邪魔になるのを抑制する。   The interval between the plurality of cut beams 30 is set not for each span but for each of a plurality of spans (an example of a length exceeding one span). In this way, by setting the installation interval of the cut beams 30 to ensure a wide interval between the cut beams 30, the cut beam is used in the construction work on the lower floor side using the work space extending above and below the temporary opening A. Suppresses 30 from getting in the way.

本例では、上述のように切梁30の設置間隔を広く確保することに対応して、図3、図4に示すように、切梁30を頑強な集中切梁として構成する。
具体的には、H型鋼等の鋼材からなる二本の梁材31を、切梁30の幅方向から構真柱12を挟む状態に間隔を空けて並べ、当該二本の梁材31を鋼材製等の組付材32にて適所で組み付けることにより、切梁30を集中切梁として構成する。
In this example, as shown in FIGS. 3 and 4, the cutting beam 30 is configured as a robust concentrated cutting beam in response to securing a wide installation interval of the cutting beam 30 as described above.
Specifically, two beam members 31 made of a steel material such as H-shaped steel are arranged in a state where the structural pillar 12 is sandwiched from the width direction of the cut beam 30, and the two beam members 31 are arranged as a steel material. The cut beam 30 is configured as a concentrated cut beam by assembling at an appropriate position with an assembling material 32 such as a product.

本例では、組付材32として、例えば、切梁30の長さ方向の適所で両梁材31に亘らせるH型鋼製等の横架材32Aと、当該横架材32Aと両梁材31とで区画される開口部に配設されるブレース32Bを使用する。横架材32Aは、切梁30の長さ方向の両端箇所と、切梁30の長さ方向の中間箇所とに設ける。切梁30の長さ方向の中間箇所では、構真柱12を長さ方向から挟む状態で構真柱12の二箇所に設けるとともに、構真柱12どうしの間、及び、構真柱12と切梁30の長さ方向の両端箇所との間にも設ける。   In this example, as the assembling material 32, for example, a horizontal member 32A made of H-shaped steel or the like that extends over both beam members 31 at an appropriate position in the length direction of the cut beam 30, and the horizontal member 32A and both beams A brace 32 </ b> B disposed in an opening partitioned by the material 31 is used. The horizontal members 32 </ b> A are provided at both end portions in the length direction of the cut beam 30 and intermediate portions in the length direction of the cut beam 30. At the intermediate position in the longitudinal direction of the cut beam 30, the structural pillar 12 is provided at two positions with the structural pillar 12 sandwiched from the longitudinal direction, and between the structural pillars 12 and between the structural pillar 12 and It is also provided between both ends in the length direction of the cut beam 30.

そして、各切梁30は、構真柱12を挟む状態に配置した両梁材31の下面側を、構真柱12の外周面から突出させた鋼材製の支持ブラケット33にて下方側から受け止める状態で、適切な高さにて構真柱12に支持させる。なお、支持ブラケット33は、ボルトや溶接等の適宜の固定手段で構真柱12に固定することができる。   Each beam 30 receives the lower surface side of both beam members 31 arranged in a state of sandwiching the structural pillar 12 from below with a steel support bracket 33 projecting from the outer peripheral surface of the structural pillar 12. In the state, it is supported on the stem pillar 12 at an appropriate height. The support bracket 33 can be fixed to the structural pillar 12 by an appropriate fixing means such as a bolt or welding.

このような切梁30の設置構造によれば、二本の梁材31が幅方向で構真柱12の両側に分かれて配置されるので、構真柱12に偏荷重がかからず、構真柱12にて切梁30をバランスよく支持することができる。しかも、この支持状態では、二本の梁材31にて切梁30の幅方向から構真柱12を挟み、更に、横架材32Aにて切梁30の長さ方向から構真柱12を挟む状態にあるので、切梁30と構真柱12との相対姿勢(支持姿勢)を適切に保持し、切梁30を安定的に支持することができる。   According to such an installation structure of the beam 30, the two beam members 31 are arranged separately on both sides of the structural pillar 12 in the width direction. The beam 30 can be supported in a balanced manner by the true pillar 12. In addition, in this supported state, the frame pillar 12 is sandwiched between the two beam members 31 from the width direction of the cut beam 30, and further, the frame column 12 is moved from the length direction of the beam 30 by the horizontal member 32 </ b> A. Since it is in the sandwiched state, the relative posture (supporting posture) between the beam 30 and the structural pillar 12 can be appropriately maintained, and the beam 30 can be stably supported.

〔別実施形態〕
(1)仮設開口部Aを形成する箇所は、前述の実施形態で示した地下建物部10の床スラブ11Aの中央部に限らず、施工計画等に応じて適宜に変更することができる。また、仮設開口部Aの個数や仮設開口部Aを形成する階も、施工計画等に応じて適宜に変更することができる。
[Another embodiment]
(1) The location where the temporary opening A is formed is not limited to the central portion of the floor slab 11A of the underground building 10 shown in the above-described embodiment, but can be changed as appropriate according to the construction plan and the like. Moreover, the number of the temporary openings A and the floor on which the temporary openings A are formed can be changed as appropriate according to the construction plan and the like.

(2)切梁30の具体的構造は、前述の実施形態で示した複数本の梁材31を組み付けた集中切梁に限らず、1本の梁材31で構成してもよく、施工計画等に応じて各種の構造を適宜に採用することができる。   (2) The specific structure of the cutting beam 30 is not limited to the concentrated cutting beam in which the plurality of beam members 31 shown in the above-described embodiment are assembled, and may be configured by a single beam member 31. Various structures can be appropriately employed depending on the above.

A 仮設開口部
a1 縁辺部
11A 床部(床スラブ)
11a キャピタル部分
12 構真柱
30 切梁
31 梁材
A Temporary opening a1 Edge 11A Floor (floor slab)
11a Capital portion 12 True pillar 30 Cut beam 31 Beam material

Claims (4)

逆打ち工法を用いた建築方法であって、
建物における逆打ち工法にて構築する部分中の最下階よりも上階側の床部に複数の柱スパンに亘る仮設開口部を形成しておき、
当該仮設開口部を形成した状態のままで仮設開口部を形成した階の直下階の構築作業を実施する逆打ち工法を用いた建築方法。
It is a construction method that uses the reverse hammering method,
A temporary opening spanning a plurality of column spans is formed on the floor portion on the upper floor side from the lowermost floor in the part to be constructed by the reverse driving method in the building,
A construction method using a reverse driving method in which construction work is performed on the floor immediately below the floor on which the temporary opening is formed while the temporary opening is formed.
前記仮設開口部を形成せずに床部を構築した階よりも下階側の床部に前記仮設開口部を形成する請求項1記載の逆打ち工法を用いた建築方法。   The construction method using the reverse driving method according to claim 1, wherein the temporary opening is formed in a floor portion on a lower floor side than a floor on which a floor portion is constructed without forming the temporary opening portion. 前記仮設開口部を、内部に構真柱が位置する状態で形成し、
前記仮設開口部の内部に位置する前記構真柱に支持させる状態で、前記仮設開口部の相対向する縁辺部間に切梁を亘らせる請求項1又は2記載の逆打ち工法を用いた建築方法。
The temporary opening is formed in a state where the construction pillar is located inside,
3. The reverse driving method according to claim 1, wherein a cutting beam is extended between opposite edges of the temporary opening in a state of being supported by the frame pillar located inside the temporary opening. Building method.
前記切梁を、複数本の梁材が並ぶ集中切梁として構成し、前記仮設開口部の内部に位置する前記構真柱を複数本の梁材で挟む状態で当該構真柱に支持させるとともに、
当該集中切梁を、前記仮設開口部の縁辺部側の構真柱とスラブとの接続部位に形成されたキャピタル部分で反力を受ける状態に設置する請求項3記載の逆打ち工法を用いた建築方法。
The cut beam is configured as a concentrated cut beam in which a plurality of beam members are arranged, and the structured column located inside the temporary opening is supported by the structured column while being sandwiched by the plurality of beam materials. ,
The reverse driving method according to claim 3, wherein the concentrated cutting beam is installed in a state of receiving a reaction force at a capital portion formed at a connection portion between a slab and a built-up column on an edge side of the temporary opening. Building method.
JP2015255833A 2015-12-28 2015-12-28 Building method using reverse construction method Active JP6654428B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015255833A JP6654428B2 (en) 2015-12-28 2015-12-28 Building method using reverse construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015255833A JP6654428B2 (en) 2015-12-28 2015-12-28 Building method using reverse construction method

Publications (2)

Publication Number Publication Date
JP2017119953A true JP2017119953A (en) 2017-07-06
JP6654428B2 JP6654428B2 (en) 2020-02-26

Family

ID=59272695

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015255833A Active JP6654428B2 (en) 2015-12-28 2015-12-28 Building method using reverse construction method

Country Status (1)

Country Link
JP (1) JP6654428B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111636483A (en) * 2020-05-08 2020-09-08 中铁隧道集团二处有限公司 Waterproof device for reverse construction concrete structure gap and construction method
CN115324106A (en) * 2022-08-19 2022-11-11 中建三局第三建设工程有限责任公司 Construction method for optimizing intermittent stop points of synchronous reverse construction technology
JP7510328B2 (en) 2020-10-19 2024-07-03 株式会社竹中工務店 Construction Method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0372119A (en) * 1989-08-11 1991-03-27 Takenaka Komuten Co Ltd Constructing method for underground construction provided with column having capital using reverse-driving method
JPH05140957A (en) * 1991-11-21 1993-06-08 Fujita Corp Constructing method for basement of building
JPH05255943A (en) * 1991-09-13 1993-10-05 Takenaka Komuten Co Ltd Construction method for underground skeleton by slide down system
JP2012107430A (en) * 2010-11-17 2012-06-07 Shimizu Corp Construction method of underground structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0372119A (en) * 1989-08-11 1991-03-27 Takenaka Komuten Co Ltd Constructing method for underground construction provided with column having capital using reverse-driving method
JPH05255943A (en) * 1991-09-13 1993-10-05 Takenaka Komuten Co Ltd Construction method for underground skeleton by slide down system
JPH05140957A (en) * 1991-11-21 1993-06-08 Fujita Corp Constructing method for basement of building
JP2012107430A (en) * 2010-11-17 2012-06-07 Shimizu Corp Construction method of underground structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111636483A (en) * 2020-05-08 2020-09-08 中铁隧道集团二处有限公司 Waterproof device for reverse construction concrete structure gap and construction method
JP7510328B2 (en) 2020-10-19 2024-07-03 株式会社竹中工務店 Construction Method
CN115324106A (en) * 2022-08-19 2022-11-11 中建三局第三建设工程有限责任公司 Construction method for optimizing intermittent stop points of synchronous reverse construction technology
CN115324106B (en) * 2022-08-19 2023-08-18 中建三局第三建设工程有限责任公司 Construction method for optimizing intermittent stopping point of synchronous reverse construction technology

Also Published As

Publication number Publication date
JP6654428B2 (en) 2020-02-26

Similar Documents

Publication Publication Date Title
KR101205783B1 (en) The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously
JP6103667B1 (en) Construction method of underground structure
JP2008013926A (en) Existing building foundation reinforcing method
JP2013256793A (en) Construction method for underground structure, and underground structure
JP2017096063A (en) Earth retaining excavation method and skeleton construction method
KR20170048879A (en) Reinforcement of foundation
JP6654428B2 (en) Building method using reverse construction method
JP6329357B2 (en) Building structure
JP6143068B2 (en) Underground structure of building
JP2016089481A (en) Extension method for underground facility
KR20130021952A (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
JP5457276B2 (en) Underground pillar construction
JP2011246910A (en) Construction method of underground structure
JP6228836B2 (en) Reverse winding method
JP6693115B2 (en) Underground construction method
JP2020070701A (en) Underground structure, building and method for constructing underground structure
JP2020125630A (en) Building construction method
JP6710999B2 (en) Temporary receiving method for existing structures
KR101707376B1 (en) Structure for constructing underground structure using composite beams and the construction method thereof
JP7230313B2 (en) Basement structure and construction method of basement
JP6827256B2 (en) How to rebuild the building
JP6220659B2 (en) Position adjustment method of reaction force receiving member and top of column
JP6937205B2 (en) How to build an underground structure
JP6938198B2 (en) Construction method
JP6774774B2 (en) Pile foundation structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180925

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20190614

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190626

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190808

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20200106

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20200130

R150 Certificate of patent or registration of utility model

Ref document number: 6654428

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150