JP6220659B2 - Position adjustment method of reaction force receiving member and top of column - Google Patents

Position adjustment method of reaction force receiving member and top of column Download PDF

Info

Publication number
JP6220659B2
JP6220659B2 JP2013251845A JP2013251845A JP6220659B2 JP 6220659 B2 JP6220659 B2 JP 6220659B2 JP 2013251845 A JP2013251845 A JP 2013251845A JP 2013251845 A JP2013251845 A JP 2013251845A JP 6220659 B2 JP6220659 B2 JP 6220659B2
Authority
JP
Japan
Prior art keywords
reaction force
receiving member
force receiving
top end
jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2013251845A
Other languages
Japanese (ja)
Other versions
JP2015108262A (en
Inventor
雅章 浦邉
雅章 浦邉
勝憲 鈴木
勝憲 鈴木
耕介 川戸
耕介 川戸
和也 飯塚
和也 飯塚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP2013251845A priority Critical patent/JP6220659B2/en
Publication of JP2015108262A publication Critical patent/JP2015108262A/en
Application granted granted Critical
Publication of JP6220659B2 publication Critical patent/JP6220659B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

本発明は、反力受部材及び構真柱の天端の位置調整工法に関する。   The present invention relates to a position adjusting method for a reaction force receiving member and a top end of a prism.

逆打工法においては、地上1階の床・梁コンクリート打設後、地下掘削を行い、地下1階の床・梁コクリートを打設し、順次地下2階、地下3階の順で、地下掘削や床・梁工事を行う。よって、上階の床・梁荷重を受けるための構真柱(鉄骨柱)を設けている。また、構真柱建て込み工法とは、場所打ち杭の杭体の中に上部構造の鉄骨支柱を挿入し、杭と上部の柱とを一体の構造物として施工する工法である。   In the reverse placement method, after placing the floor / beam concrete on the first floor above ground, excavating underground, placing the floor / beam cocrete on the first basement floor, and then excavating in the order of the second basement floor and then the third basement floor. And floor / beam construction. Therefore, a structural column (steel column) is provided to receive the floor / beam load on the upper floor. In addition, the structural column built-in construction method is a construction method in which a steel column having an upper structure is inserted into a pile body of a cast-in-place pile and the pile and the upper column are constructed as an integral structure.

そして、先行文献1〜先行文献4には、構真柱を建て込む際の構真柱の位置修正を高精度で行う技術が開示されている。   Prior art documents 1 to 4 disclose a technique for correcting the position of a structural pillar with high accuracy when the structural pillar is built.

ここで、構真柱は、0節の鉄骨柱および1階の梁鉄骨を設計通りに収めるために、構真柱天端の水平位置調整を行う必要がある。よって、非特許文献1には、逆打ち工事の基準床となる1階の床版(トップスラブ)の施工の際に、構真柱天端の廻りは捨てコンクリートを打設せずに箱抜きとし、捨てコンクリートをジャッキの反力受けとすることが開示されている。   Here, it is necessary to adjust the horizontal position of the top of the construction column so that the zero-section steel column and the first-stage beam steel frame can be accommodated as designed. Therefore, Non-Patent Document 1 states that when constructing the first floor slab (top slab), which is the standard floor for backlash construction, the area around the top of the construction pillar is thrown away and no box is placed without placing concrete. It is disclosed that discarded concrete is used as a reaction force of the jack.

しかし、このような仮設の作業床コンクリート(捨てコンクリート)を、構真柱天端の水平位置調整を行う際の反力受けとして利用する方法は、作業床コンクリートを打設し、更にコンクリートが乾燥し固化するまで、構真柱天端の水平位置調整を行うことができないため、地上階の鉄骨工事を先行して行うことができない。   However, the method of using such temporary work floor concrete (abandoned concrete) as a reaction force receiver when adjusting the horizontal position of the top of the structural pillar is to place work floor concrete and dry the concrete. Until it is solidified, it is not possible to adjust the horizontal position of the top of the column.

よって、構真柱の天端の位置調整を前倒しして実施することによる工期短縮が求められている。   Accordingly, there is a demand for shortening the work period by performing the position adjustment of the top end of the structural pillar forward.

特開平5−5312号公報Japanese Patent Laid-Open No. 5-5312 特開平6−26204号公報JP-A-6-26204 特開平7−109733号公報JP-A-7-109733 特開平10−280408号公報JP-A-10-280408

鴻池組技術研究報告 2010 「逆打ち工法による高層事務所ビルの施工」 21頁〜26頁Tsugaike Gumi Technology Research Report 2010 “Construction of high-rise office buildings by the back-striking method” pages 21-26

本発明では、構真柱の天端の位置調整を前倒しして実施可能とすることが課題である。   In the present invention, it is an object to make it possible to carry out the adjustment of the position of the top end of the stem pillar forward.

請求項1の発明は、建て込まれた構真柱の天端の周りに埋設され、中央部に形成された孔の内周面がジャッキ受面とされ、前記ジャッキ受面と前記天端との間にジャッキが設置されるコンクリート製の環状の反力受部材である。 The invention of claim 1 is embedded around the top end of the built-in column, and the inner peripheral surface of the hole formed in the center portion is a jack receiving surface, and the jack receiving surface, the top end, It is an annular reaction force receiving member made of concrete in which a jack is installed .

請求項1に記載の発明では、構真柱の天端の周りに埋設させたコンクリート製の環状の反力受部材は、中央部に形成された孔の内周面がジャッキ受面とされている。そして、このジャッキ受面と天端との間にジャッキを設置し、掘削後の構真柱の天端の位置調整の際のジャッキの反力受けとして用いる。よって、掘削後に、例えば仮設の作業床コンクリートを反力受けとする必要がないので、構真柱の天端の位置調整を前倒しして実施可能となる。 In the first aspect of the present invention, the annular reaction force receiving member made of concrete embedded around the top end of the stem column has a jack receiving surface on the inner peripheral surface of the hole formed in the central portion. Yes. And a jack is installed between this jack receiving surface and a top end, and it is used as a reaction force receiver of the jack at the time of position adjustment of the top end of the construction pillar after excavation. Therefore, after excavation, for example, it is not necessary to use a temporary work floor concrete as a reaction force receiver, so that the position adjustment of the top end of the structural pillar can be performed forward.

請求項2の発明は、建て込まれた構真柱の天端の周りに、内側にジャッキ受面が形成されたコンクリート製の環状の反力受部材を設置して、前記構真柱を埋め戻す埋戻工程と、埋め戻した埋戻材を掘削し、前記天端を露出させる掘削工程と、前記天端と前記反力受部材の前記ジャッキ受面との間にジャッキを設け、前記天端の位置調整を行う調整工程と、を備える構真柱の位置調整工法である。   The invention according to claim 2 is characterized in that an annular reaction force receiving member made of concrete having a jack receiving surface formed inside is installed around the top end of the built-up structural pillar to fill the structural pillar. A backfilling step, a drilling step of excavating the backfilled backfill material to expose the top end, and a jack provided between the top end and the jack receiving surface of the reaction force receiving member; And an adjustment process for adjusting the position of the end.

請求項2に記載の発明では、構真柱の天端の周りに埋設させたコンクリート製の環状の反力受部材を、掘削後の構真柱の天端の位置調整工程において、ジャッキの反力受けとして用いる。よって、掘削後に、例えば、仮設の作業床コンクリートを構築して反力受けとする必要がないので、構真柱の天端の位置調整を前倒しして実施可能となる。   In the invention according to claim 2, an annular reaction force receiving member made of concrete embedded around the top end of the stem column is used to adjust the position of the top of the stem column after excavation. Use as force receiver. Therefore, after excavation, for example, it is not necessary to construct a temporary work floor concrete to receive the reaction force, so that it is possible to carry out the adjustment of the position of the top end of the structural pillar forward.

本発明によれば、構真柱の天端の位置調整を前倒しして実施可能となる。   According to the present invention, the position adjustment of the top end of the true pillar can be carried out forward.

本発明の一実施形態の反力受部材を用いて構真柱の天端の位置調整作業を行っている状態の斜視図である。It is a perspective view of the state which is performing the position adjustment operation | work of the top end of a stem pillar using the reaction force receiving member of one Embodiment of this invention. 図1の反力受部材を用いて構真柱の天端の位置調整作業を行った後に、上部の鉄骨柱を接合した状態の斜視図である。It is a perspective view of the state where the upper steel column was joined after performing the position adjustment work of the top end of the stem column using the reaction force receiving member of FIG. 図1の反力受部材を作製している状態の斜視図である。It is a perspective view of the state which is producing the reaction force receiving member of FIG. 構真柱を建て込んで埋め戻すまでの工程の(A)〜(C)を示す工程図である。It is process drawing which shows (A)-(C) of the process until it builds a construction pillar and refills. 構真柱を建て込んで埋め戻すまでの工程の(D)〜(F)を示す工程図である。It is process drawing which shows (D)-(F) of the process until it builds a construction pillar and refills. 構真柱を建て込んで埋め戻すまでの工程の(G)〜(H)を示す工程図である。It is process drawing which shows (G)-(H) of the process until it builds a construction pillar and refills.

本発明の一実施形態に係る反力受部材と、反力受部材を用いた構真柱の天端の位置調整について説明する。   A reaction force receiving member according to an embodiment of the present invention and position adjustment of the top end of the true pillar using the reaction force receiving member will be described.

<反力受部材>
まず、反力受部材100について説明する。
<Reaction force receiving member>
First, the reaction force receiving member 100 will be described.

図1に示すように、反力受部材100は、平面視で略正方形状の外形とされ、中心部に略正六角形状の孔102が形成された環状のブロック材である。なお、この孔102の側面(内周面)が、後述するジャッキ200の反力を受けるジャッキ受面104である。   As shown in FIG. 1, the reaction force receiving member 100 is an annular block member having a substantially square outer shape in plan view and having a substantially regular hexagonal hole 102 formed in the center. A side surface (inner peripheral surface) of the hole 102 is a jack receiving surface 104 that receives a reaction force of the jack 200 described later.

本実施形態の反力受部材100は、鉄筋コンクリート製(プレキャスト)とされ、また、図3に示すように、鉄板152の上に木製の型枠150を組んでコンクリートを打設して作製されている。   The reaction force receiving member 100 of the present embodiment is made of reinforced concrete (precast), and is manufactured by assembling a wooden formwork 150 on an iron plate 152 and placing concrete as shown in FIG. Yes.

なお、本実施形態の反力受部材100には、吊フック(曲げ鉄筋)106を含む鉄筋(図示略)が配筋されている。なお、鉄筋は、反力受部材100を設置時に吊り下げる際に必要な強度や剛性を有する程度の最小限の配筋であればよい。   In addition, in the reaction force receiving member 100 of the present embodiment, reinforcing bars (not shown) including suspension hooks (bending reinforcing bars) 106 are arranged. The reinforcing bar may be a minimum reinforcing bar that has strength and rigidity required when the reaction force receiving member 100 is suspended during installation.

また、反力受部材100は、後述するようにジャッキ200の反力を受けることが可能な剛性と強度があればよく、また最終的には解体する。よって、反力受部材100には高い精度や品質は必要とされない。したがって、鉄板152の上に型枠150を組んでコンクリートを打設して作製することができる。また、別の工事で余ったコンクリートを使用することができる。   The reaction force receiving member 100 only needs to have rigidity and strength capable of receiving the reaction force of the jack 200 as will be described later, and is finally disassembled. Therefore, high accuracy and quality are not required for the reaction force receiving member 100. Therefore, it can be produced by assembling the formwork 150 on the iron plate 152 and placing concrete. In addition, the remaining concrete can be used in another construction.

<構真柱天端の位置調整>
つぎに、逆打工法における0節の鉄骨柱60(図2参照)および1階の梁鉄骨を設計通りに収めるための構真柱50の天端52の反力受部材100を用いた水平位置調整について説明する。
<Adjusting the position of the top of the structural stem>
Next, the horizontal position using the reaction force receiving member 100 at the top end 52 of the built-up column 50 for accommodating the zero-section steel column 60 (see FIG. 2) and the beam steel frame on the first floor as designed in the reverse driving method. The adjustment will be described.

なお、逆打工法においては、地上1階の床・梁コンクリート打設後、地下掘削を行い、地下1階の床・梁コクリートを打設し、順次地下2階、地下3階の順で、地下掘削や床・梁工事を行う。よって、上階の床・梁荷重を受けるための構真柱(鉄骨柱)20を設けている。   In the reverse placement method, after placing the floor / beam concrete on the first floor above ground, excavating underground, placing the floor / beam cocrete on the first floor underground, in order of the second floor underground and the third floor underground, Underground excavation and floor / beam construction. Therefore, a structural column (steel column) 20 is provided to receive the floor / beam load on the upper floor.

また、図4(A)〜図4(H)は構真柱を立て込んで埋め戻すまでの工程を模式的に順番に示す図である。   4 (A) to 4 (H) are diagrams schematically showing the steps from setting up the true pillar to backfilling.

図4(A)に示すように、表層ケーシング12を建て込み、杭穴10を図示していないアークドリルで掘削する。また、杭穴10の下端部を拡径し拡径部10Aを形成する。また、スライムクリーナー40でスライム処理(底浚い)を行う。   As shown in FIG. 4A, the surface casing 12 is built and the pile hole 10 is excavated with an arc drill (not shown). Moreover, the lower end part of the pile hole 10 is expanded in diameter, and 10A of enlarged diameter parts are formed. In addition, slime treatment (bottoming) is performed by the slime cleaner 40.

図4(B)示すように、杭穴10の下部に鉄筋籠14をクレーン42(図4(A)も参照)で吊り降ろし建て込む。図4(C)に示すように、杭穴10の上に構真柱50(図1参照)を建て込むための建込架台20を設置する。 As shown in FIG. 4 (B), the reinforcing bar 14 is suspended and built in the lower part of the pile hole 10 with a crane 42 (see also FIG. 4 (A)). As shown in FIG. 4 (C), the erection platform 20 for installing the construction pillar 50 (see FIG. 1) is installed on the pile hole 10.

図4(D)及び図4(E)に示すように、構真柱50を建込架台20に通し位置調整しながら杭穴10に建て込む。また、杭穴10にトレミー管46を建て込み、ポンプ車44(図4(D)を参照)で杭穴10の下端部にコンクリートCを打設する。そして、これらの作業の際に、反力受部材100を構真柱50と同数個、作製する(図3も参照)。なお、反力受部材100に使用するコンクリートは、杭穴10の下端部に打設するコンクリートCを流用してもよい。   As shown in FIG. 4D and FIG. 4E, the built-up pillar 50 is built in the pile hole 10 while adjusting the position through the built-in mount 20. Moreover, the tremy pipe | tube 46 is built in the pile hole 10, and concrete C is laid in the lower end part of the pile hole 10 with the pump truck 44 (refer FIG.4 (D)). Then, during these operations, the same number of reaction force receiving members 100 as the structural pillars 50 are produced (see also FIG. 3). In addition, the concrete used for the reaction force receiving member 100 may be diverted from the concrete C placed at the lower end of the pile hole 10.

図4(F)に示すように、バックホウ48を用いて土や土地砂等の埋戻材Mで杭穴10を埋め戻すと共に、クレーン42で建込架台20を撤去する。図4(G)及び図4(H)に示すように、クレーン42で表層ケーシング12を引き抜き(図4(G))撤去する(図4(H))。   As shown in FIG. 4F, the pile hole 10 is backfilled with a backfilling material M such as soil and land sand using a backhoe 48, and the erection platform 20 is removed with a crane 42. As shown in FIGS. 4G and 4H, the surface casing 12 is pulled out by the crane 42 (FIG. 4G) and removed (FIG. 4H).

このとき、図4(H)に示すように、反力受部材100を構真柱50の天端52の周りに配置して一緒に埋め戻す。なお、構真柱50毎にそれぞれ反力受部材100を設置して一緒に埋め戻す。   At this time, as shown in FIG. 4 (H), the reaction force receiving member 100 is disposed around the top end 52 of the stem 50 and backfilled together. In addition, the reaction force receiving member 100 is installed for each construction pillar 50 and backfilled together.

そして、図1に示すように、上階部分の鉄骨柱60(図2参照)を建てる際に、埋め戻した埋戻材Mや周囲の地盤R(図4(H)も参照)の土を掘削し、反力受部材100及び構真柱50の天端52を掘り出して露出させる。   Then, as shown in FIG. 1, when building the steel column 60 (see FIG. 2) of the upper floor portion, the backfill material M and the soil of the surrounding ground R (see also FIG. 4 (H)) are backfilled. Excavation is performed to dig out and expose the reaction force receiving member 100 and the top end 52 of the structural pillar 50.

掘り出して露出させた構真柱50の天端52と反力受部材100の孔102の側面であるジャッキ受面104との間にジャッキ200を設置し、ジャッキ200によって天端52の水平方向の位置調整を行う。   A jack 200 is installed between the top end 52 of the structural pillar 50 that has been dug and exposed and the jack receiving surface 104 that is the side surface of the hole 102 of the reaction force receiving member 100, and the jack 200 extends in the horizontal direction of the top end 52. Adjust the position.

図2に示すように、ジャッキ200によって構真柱50の天端52が水平方向の位置調整された状態で、天端52に上部の鉄骨柱60を溶接接合する。   As shown in FIG. 2, the upper steel column 60 is welded to the top end 52 in a state where the top end 52 of the stem column 50 is adjusted in the horizontal direction by the jack 200.

なお、この後、地下階の工事を行うために掘削する際に、例えば、既存地下躯体を解体する解体重機などによって、反力受部材100を解体する。   After that, when excavating for the construction of the underground floor, the reaction force receiving member 100 is disassembled by, for example, a weight dismantling machine that dismantles the existing underground enclosure.

<作用及び効果>
つぎに本実施形態の作用及び効果について説明する。
<Action and effect>
Next, the operation and effect of this embodiment will be described.

構真柱50の天端52の周りに埋設させたコンクリート製の環状の反力受部材100を、掘削後の構真柱50の天端52の位置調整において、ジャッキ200の反力受けとして用いている。   A concrete annular reaction force receiving member 100 embedded around the top end 52 of the structural pillar 50 is used as a reaction force receiver for the jack 200 in the position adjustment of the top end 52 of the structural pillar 50 after excavation. ing.

よって、掘削後に、例えば、仮設の作業床コンクリートを構築して反力受けとする必要がないので作業効率が向上する。また、構真柱50の天端52の位置調整を前倒して実施することができる(構真柱50天端52の周りに反力受部材100を埋設させない場合と比較して、天端52の位置調整を前倒して実施することが可能となる)。したがって、地上鉄骨工事を早期に開始できるので工期短縮が可能となる。   Therefore, after excavation, for example, it is not necessary to construct a temporary work floor concrete to receive the reaction force, so that work efficiency is improved. Further, the position adjustment of the top end 52 of the structural pillar 50 can be performed forward (compared to the case where the reaction force receiving member 100 is not embedded around the top end 52 of the structural pillar 50). It is possible to carry out position adjustment ahead of schedule). Therefore, the ground work can be started at an early stage, so that the work period can be shortened.

<その他>
尚、本発明は上記実施形態に限定されない。
<Others>
The present invention is not limited to the above embodiment.

例えば、上記実施形態では、反力受部材100は、平面視で略正方形状の外形とされ、中心部に略正六角形状の孔102が形成された環状のプレキャストであったが、これに限定されない。外形や孔はどのような形状であってもよい。また、鉄筋が配筋されていなくてもよい。要は、反力受部材は、ジャッキの反力を受けることが可能な剛性と強度とを有するジャッキ受面が内側に形成されていればよい。   For example, in the above-described embodiment, the reaction force receiving member 100 is an annular precast in which a substantially square outer shape is formed in a plan view and a substantially regular hexagonal hole 102 is formed in the center portion. Not. The outer shape and the hole may have any shape. Further, the reinforcing bars need not be arranged. In short, the reaction force receiving member only needs to have a jack receiving surface having rigidity and strength capable of receiving the reaction force of the jack inside.

また、上記実施形態では、図4(D)の工程の際に反力受部材100の作製を開始したが、これに限定されない。反力受部材100は、図4(H)で埋め戻すまでに作製が完了していればよい。また、構真柱50の建て込む前に反力受部材100を予め作製していてもよい。或いは、建設現場でなく、別の場所、例えば工場等で反力受部材100を作製して搬入してもよい。   Moreover, in the said embodiment, although production of the reaction force receiving member 100 was started in the process of FIG.4 (D), it is not limited to this. The reaction force receiving member 100 only needs to be completed before it is backfilled in FIG. Further, the reaction force receiving member 100 may be manufactured in advance before the construction column 50 is built. Alternatively, the reaction force receiving member 100 may be produced and loaded not at the construction site but at another place, for example, a factory.

更に、本発明の要旨を逸脱しない範囲において種々なる態様で実施し得ることは言うまでもない   Furthermore, it cannot be overemphasized that it can implement with a various aspect in the range which does not deviate from the summary of this invention.

50 構真柱
52 天端
100 反力受部材
104 ジャッキ受面
200 ジャッキ
50 Structural column 52 Top end 100 Reaction force receiving member 104 Jack receiving surface 200 Jack

Claims (2)

建て込まれた構真柱の天端の周りに埋設され、中央部に形成された孔の内周面がジャッキ受面とされ、前記ジャッキ受面と前記天端との間にジャッキが設置されるコンクリート製の環状の反力受部材。 The inner peripheral surface of the hole formed in the center portion is buried around the top end of the built-up structural pillar, and the jack is installed between the jack receiving surface and the top end. reaction force receiving member of the concrete ring that. 建て込まれた構真柱の天端の周りに、内側にジャッキ受面が形成されたコンクリート製の環状の反力受部材を設置して、前記構真柱を埋め戻す埋戻工程と、
埋め戻した埋戻材を掘削し、前記天端を露出させる掘削工程と、
前記天端と前記反力受部材の前記ジャッキ受面との間にジャッキを設け、前記天端の位置調整を行う調整工程と、
を備える構真柱の位置調整工法。
Around the top end of the built-up column, a concrete annular reaction force receiving member with a jack receiving surface formed inside is installed, and the backfilling step of backfilling the frame column
Excavating the backfill material, exposing the top edge, and
An adjustment step of adjusting the position of the top end by providing a jack between the top end and the jack receiving surface of the reaction force receiving member;
A construction method for adjusting the position of the true pillar.
JP2013251845A 2013-12-05 2013-12-05 Position adjustment method of reaction force receiving member and top of column Expired - Fee Related JP6220659B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013251845A JP6220659B2 (en) 2013-12-05 2013-12-05 Position adjustment method of reaction force receiving member and top of column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2013251845A JP6220659B2 (en) 2013-12-05 2013-12-05 Position adjustment method of reaction force receiving member and top of column

Publications (2)

Publication Number Publication Date
JP2015108262A JP2015108262A (en) 2015-06-11
JP6220659B2 true JP6220659B2 (en) 2017-10-25

Family

ID=53438799

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2013251845A Expired - Fee Related JP6220659B2 (en) 2013-12-05 2013-12-05 Position adjustment method of reaction force receiving member and top of column

Country Status (1)

Country Link
JP (1) JP6220659B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6645098B2 (en) * 2015-09-30 2020-02-12 株式会社大林組 Removal method of existing pile
JP7101077B2 (en) * 2018-08-09 2022-07-14 大成建設株式会社 How to build a column-beam frame

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08158387A (en) * 1994-12-09 1996-06-18 Ohbayashi Corp Constructing method of underground structure
JP3030377B2 (en) * 1995-02-01 2000-04-10 日特建設株式会社 Construction and repair equipment for trussed pillars
JP3890666B2 (en) * 1997-04-28 2007-03-07 株式会社大林組 Joining method and structure of the structural column and main body steel in the reverse driving method
JP2002356863A (en) * 2001-06-01 2002-12-13 Toda Constr Co Ltd First floor preconstruction method in reverse construction method
JP3779201B2 (en) * 2001-11-30 2006-05-24 戸田建設株式会社 Construction method of construction pillar and its holding jig
JP3682704B2 (en) * 2002-09-10 2005-08-10 株式会社竹中工務店 Built-in column construction method without casing
JP5337276B1 (en) * 2012-05-07 2013-11-06 鹿島建設株式会社 Seismic isolation device support unit for reverse driving method and construction method of seismic isolation structure using the same

Also Published As

Publication number Publication date
JP2015108262A (en) 2015-06-11

Similar Documents

Publication Publication Date Title
KR101014796B1 (en) Top-down underground construction method using prefabricated concrete column member as temporary bridge column
JP2008013926A (en) Existing building foundation reinforcing method
JP2009057680A (en) Structure and method for supporting covering plate
JP2015124587A (en) Construction method for new underground skeleton, accompanied by demolition of existing underground skeleton
JP2006207152A (en) Open caisson press-fitting method
JP5303381B2 (en) Demolition method for existing buildings
JP6220659B2 (en) Position adjustment method of reaction force receiving member and top of column
JP6228836B2 (en) Reverse winding method
JP2007308951A (en) Method of constructing outer peripheral column by inverted construction method
JP2018009336A (en) Underground space construction method
KR102082495B1 (en) Low part cast in place pile construction method
JP2012087561A (en) Construction method of outer peripheral column in inverted construction
JP4611108B2 (en) Integrated construction method of pile and column
JP2016223084A (en) Construction method of underground structure by inverted construction method
JP6006004B2 (en) Pile head space formation auxiliary tool, hollow ready-made pile provided with the same, pile head processing method using the hollow ready-made pile, and pile head space forming method
KR101128955B1 (en) The Construction Method of Pressing Underground Structure
JP4407716B2 (en) Construction method of earth retaining wall
JP5016521B2 (en) Earth anchor and its removal method
JP2011089320A (en) Method for constructing precast basement column
JP5027752B2 (en) Construction method of underground floor pillar and underground floor pillar
JP2018066220A (en) Reconstruction method of underground skeleton
KR101047257B1 (en) Construction method of earth wall using composite sheet pile
JP5140515B2 (en) Installation method of underground floor pillar and construction method of underground structure
JP4243069B2 (en) Construction method of earth retaining wall
JP6920039B2 (en) How to dismantle the existing underground skeleton

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20160927

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20170718

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20170719

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20170904

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20170926

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20171002

R150 Certificate of patent or registration of utility model

Ref document number: 6220659

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees