JP7020978B2 - How to remove the floor slab of synthetic girders - Google Patents

How to remove the floor slab of synthetic girders Download PDF

Info

Publication number
JP7020978B2
JP7020978B2 JP2018063783A JP2018063783A JP7020978B2 JP 7020978 B2 JP7020978 B2 JP 7020978B2 JP 2018063783 A JP2018063783 A JP 2018063783A JP 2018063783 A JP2018063783 A JP 2018063783A JP 7020978 B2 JP7020978 B2 JP 7020978B2
Authority
JP
Japan
Prior art keywords
floor slab
deck
bridge axis
cut
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2018063783A
Other languages
Japanese (ja)
Other versions
JP2019173436A (en
Inventor
祐輔 高井
名右衛門 宇野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IHI Infrastructure Systems Co Ltd
Original Assignee
IHI Infrastructure Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IHI Infrastructure Systems Co Ltd filed Critical IHI Infrastructure Systems Co Ltd
Priority to JP2018063783A priority Critical patent/JP7020978B2/en
Publication of JP2019173436A publication Critical patent/JP2019173436A/en
Application granted granted Critical
Publication of JP7020978B2 publication Critical patent/JP7020978B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

本発明は、合成桁からなる既設の橋梁から床版を撤去して新たな床版を架設するための合成桁の床版撤去方法に関するものである。 The present invention relates to a method for removing a floor slab of a synthetic girder for removing a floor slab from an existing bridge made of a synthetic girder and constructing a new floor slab.

従来、一般道、高速道路等の橋梁の多くには、主桁上にコンクリートを打設してなる床版を設置した合成桁が用いられている。合成桁は、主桁の上面に複数のずれ止め部材としてのスタッドを設け、スタッドを埋め込んだ状態で床版のコンクリートを打設することにより、スタッドによって主桁と床版とを結合している。 Conventionally, many bridges such as general roads and highways use synthetic girders in which a floor slab made by placing concrete on the main girder is installed. In the synthetic girder, a plurality of studs as slip prevention members are provided on the upper surface of the main girder, and the concrete of the floor slab is placed with the studs embedded, so that the main girder and the floor slab are connected by the studs. ..

また、床版が老朽化した場合は、既設の床版を撤去して新たな床版を再構築する床版取替施工が行われる(例えば、特許文献1参照)。図42乃至図45は、従来の床版取替施工における床版撤去方法を示すものである。 When the floor slab becomes old, the floor slab is replaced by removing the existing floor slab and reconstructing a new floor slab (see, for example, Patent Document 1). 42 to 45 show a floor slab removal method in the conventional floor slab replacement construction.

従来の床版撤去方法では、まず、合成桁1において、撤去する床版2を橋軸直角方向に切断するとともに、図42に示すように主桁3上に一部のコンクリート4を残して床版2を橋軸直角方向の複数の切断位置Cで橋軸方向に切断する。次に、図43に示すように、主桁3上のコンクリート4以外をクレーン等で吊り上げて撤去する。この後、図44に示すように、主桁3上に残存したコンクリート4を大型ブレーカやハンドブレーカ等の破砕機5により破砕し、破砕作業で発生したコンクリート屑の撤去及び収集を行う。そして、図45に示すように、スタッド3aの切断及び撤去を行い、残存コンクリート屑を除去した後、主桁3の表面仕上げを行う。 In the conventional floor slab removal method, first, in the composite girder 1, the floor slab 2 to be removed is cut in the direction perpendicular to the bridge axis, and as shown in FIG. 42, a part of concrete 4 is left on the main girder 3 to make a floor. The plate 2 is cut in the bridge axis direction at a plurality of cutting positions C in the direction perpendicular to the bridge axis. Next, as shown in FIG. 43, the concrete other than the concrete 4 on the main girder 3 is lifted by a crane or the like and removed. After that, as shown in FIG. 44, the concrete 4 remaining on the main girder 3 is crushed by a crusher 5 such as a large breaker or a hand breaker, and the concrete debris generated in the crushing operation is removed and collected. Then, as shown in FIG. 45, the stud 3a is cut and removed, the residual concrete debris is removed, and then the surface of the main girder 3 is finished.

特開2016-121458号公報Japanese Unexamined Patent Publication No. 2016-12148

しかしながら、従来の床版撤去方法では、主桁3上の床版2を橋軸方向の複数箇所で切断し、橋軸直角方向に多数に分割された床版2を個々に撤去する必要があるため、床版2の切断及び撤去作業に長時間を要する。また、主桁3上の残存コンクリート4の破砕作業により、コンクリート屑が多く発生し、その収集作業に多大な手間を要するとともに、鉄筋やスタッド間のコンクリートを除去する必要があり、コンクリート屑の撤去及び収集にも長時間を要する。このため、施工期間中の交通規制時間が長くなり、通行量の多い道路橋での交通への影響が大きくなるという問題点があった。また、コンクリート4の破砕作業による騒音、振動、粉塵の発生が著しく、市街地での作業に適さないという問題点もあった。 However, in the conventional floor slab removal method, it is necessary to cut the floor slab 2 on the main girder 3 at a plurality of points in the bridge axis direction and individually remove the floor slab 2 divided into a large number in the direction perpendicular to the bridge axis. Therefore, it takes a long time to cut and remove the floor slab 2. In addition, the crushing work of the residual concrete 4 on the main girder 3 generates a large amount of concrete debris, which requires a great deal of time and effort for collecting the debris, and it is necessary to remove the concrete between the reinforcing bars and the studs. And it takes a long time to collect. For this reason, there is a problem that the traffic regulation time during the construction period becomes long, and the influence on the traffic on the high-traffic road bridge becomes large. In addition, there is a problem that noise, vibration, and dust are remarkably generated by the crushing work of the concrete 4, and it is not suitable for work in an urban area.

本発明は前記問題点に鑑みてなされたものであり、その目的とするところは、床版の切断及び撤去作業の効率化を図ることができるとともに、主桁上に残存したコンクリートの除去作業を軽減することのできる合成桁の床版撤去方法を提供することにある。 The present invention has been made in view of the above problems, and an object thereof is to improve the efficiency of the work of cutting and removing the floor slab and to remove the concrete remaining on the main girder. The purpose is to provide a method for removing the floor slab of the synthetic girder that can be mitigated.

本発明は前記目的を達成するために、主桁上にコンクリート製の床版が設置され、主桁の上面に設けられたずれ止め部材によって主桁と床版が結合された合成桁から床版を撤去する合成桁の床版撤去方法において、床版撤去区間の床版を橋軸方向の複数箇所で橋軸直角方向に切断する第1の切断工程と、主桁と床版との間のコンクリートをずれ止め部材ごとワイヤーソーで橋軸方向に所定長さだけ切断する第2の切断工程と、第2の切断工程で切断された床版を吊り上げて撤去する撤去工程とを含み、第1の切断工程は、湿式のコンクリートカッターによって既設床版のコンクリートを上面から所定深さまで切断した後、残りのコンクリートを乾式のコンクリートカッターによって下面まで切断するようにし、第2の切断工程と撤去工程とを床版撤去区間の橋軸方向一端から他端まで繰り返し行うようにしている。 In the present invention, in order to achieve the above object, a concrete floor slab is installed on the main girder, and a floor slab is formed from a synthetic girder in which the main girder and the floor slab are connected by a slip prevention member provided on the upper surface of the main girder. In the method of removing the deck of the synthetic girder, the first cutting step of cutting the deck in the deck removal section at a plurality of points in the direction of the bridge axis in the direction perpendicular to the bridge axis, and between the main girder and the deck. The first includes a second cutting step of cutting the concrete together with the slip-preventing member together with a wire saw by a predetermined length in the direction of the bridge axis, and a removal step of lifting and removing the deck cut in the second cutting step. In the cutting process, after cutting the existing deck concrete from the upper surface to a predetermined depth with a wet concrete cutter, the remaining concrete is cut to the lower surface with a dry concrete cutter, and the second cutting step and the removing step are performed. Is repeated from one end to the other end in the bridge axis direction of the deck removal section.

これにより、床版撤去区間の床版が橋軸方向の複数箇所で橋軸直角方向に切断された後、主桁と床版との間のコンクリートを橋軸方向に所定長さだけ切断された床版が撤去されることから、橋軸方向に所定長さずつ分割した床版を橋軸直角方向に分割せずに全幅のまま撤去することができる。また、主桁と床版との間のコンクリートがずれ止め部材ごとワイヤーソーで切断されることから、主桁上に残存するコンクリート量が極めて少なくなる。更に、第1の切断工程と撤去工程とが床版撤去区間の橋軸方向一端から他端まで繰り返し行われることから、主桁から切り離される前の床版上で床版撤去作業を行うことが可能となる。また、第1の切断工程において、湿式のコンクリートカッターによって既設床版のコンクリートが上面から所定深さまで切断された後、残りのコンクリートが乾式のコンクリートカッターによって下面まで切断されることから、湿式と乾式を併用した切断が行われる。 As a result, after the deck in the deck removal section was cut in the direction perpendicular to the bridge axis at multiple points in the bridge axis direction, the concrete between the main girder and the deck was cut by a predetermined length in the bridge axis direction. Since the deck is removed, the deck divided by a predetermined length in the bridge axis direction can be removed with the full width without dividing in the direction perpendicular to the bridge axis. Further, since the concrete between the main girder and the floor slab is cut by the wire saw together with the slip prevention member, the amount of concrete remaining on the main girder is extremely small. Further, since the first cutting step and the removing step are repeated from one end to the other end in the bridge axis direction of the deck removing section, the deck removing work can be performed on the deck before being separated from the main girder. It will be possible. Further, in the first cutting step, after the concrete of the existing floor slab is cut from the upper surface to a predetermined depth by the wet concrete cutter, the remaining concrete is cut to the lower surface by the dry concrete cutter. The cutting is performed in combination with.

本発明によれば、橋軸方向に所定長さずつ分割した既設床版を橋軸直角方向に分割せずに全幅のまま撤去することができるので、従来のように床版を橋軸直角方向に複数に分割して撤去する必要がなく、撤去する床版の分割数を大幅に少なくすることができる。これにより、床版の切断及び撤去作業を効率よく行うことができ、施工期間を短縮することができる。また、主桁上に残存するコンクリート量を極めて少なくすることができるので、主桁上のコンクリート除去作業を大幅に軽減することができる。更に、主桁から切り離される前の床版上で床版撤去作業を行うことができるので、例えば床版を撤去及び搬送するための装置を床版上を移動させながら床版撤去作業を行うことができる。また、第1の切断工程においては、湿式と乾式を併用した切断により、桁下への汚水の落下を防止しつつ低コストに既設床版のコンクリートを切断することができる。即ち、湿式切断は冷却に使用した水の処理が必要であるが、乾式よりも低コストであるという利点があり、他方、乾式は汚水を発生させないが、切削粉を回収するための大型バキューム装置を必要とする分コストが高くなるとともに最大深長が湿式よりも小さいため、既設床版の厚さ方向の大部分を湿式で切断し、残りの僅かな部分を乾式で切断することにより、切断コストを抑えるとともに、汚水対策も講じることができる。 According to the present invention, the existing deck divided by a predetermined length in the bridge axis direction can be removed without being divided in the direction perpendicular to the bridge axis, and the deck can be removed in the direction perpendicular to the bridge axis as in the conventional case. It is not necessary to divide it into multiple parts and remove it, and the number of divisions of the deck to be removed can be significantly reduced. As a result, the floor slab can be cut and removed efficiently, and the construction period can be shortened. Further, since the amount of concrete remaining on the main girder can be extremely reduced, the concrete removal work on the main girder can be significantly reduced. Further, since the floor slab can be removed on the floor slab before it is separated from the main girder, for example, the floor slab removal work should be performed while moving the device for removing and transporting the floor slab on the floor slab. Can be done. Further, in the first cutting step, the existing floor slab concrete can be cut at low cost while preventing the sewage from falling under the girder by cutting using both the wet type and the dry type. That is, wet cutting requires treatment of the water used for cooling, but has the advantage of being cheaper than the dry type, while the dry type does not generate sewage, but is a large vacuum device for recovering cutting powder. Since the cost is higher and the maximum depth is smaller than the wet type, the cutting cost is increased by cutting most of the existing deck in the thickness direction with the wet type and the remaining small part with the dry type. It is possible to take measures against sewage as well as suppress the problem.

本発明の一実施形態を示す主桁及び床版の斜視図Perspective view of main girder and floor slab showing one embodiment of the present invention 第1の切断工程を示す主桁及び床版の平面図Top view of main girder and deck showing the first cutting step 第1の切断工程を示す主桁及び床版の正面断面図Front sectional view of main girder and deck showing the first cutting step 第1の切断工程を示す床版の正面断面図Front sectional view of the floor slab showing the first cutting step 第1の切断工程を示す床版の正面断面図Front sectional view of the floor slab showing the first cutting step 第2の切断工程を示す主桁及び床版の平面図Top view of main girder and deck showing the second cutting step 第2の切断工程を示す主桁及び床版の正面断面図Front sectional view of main girder and deck showing the second cutting step 第2の切断工程を示す主桁及び床版の正面断面図Front sectional view of main girder and deck showing the second cutting step 第2の切断工程を示す主桁及び床版の平面断面図Planar sectional view of main girder and deck showing the second cutting step 第2の切断工程を示す主桁及び床版の平面断面図Planar sectional view of main girder and deck showing the second cutting step 第2の切断工程を示す主桁及び床版の側面断面図Side sectional view of main girder and deck showing the second cutting step 第2の切断工程を示す主桁及び床版の側面断面図Side sectional view of main girder and deck showing the second cutting step 撤去工程を示す主桁及び床版の側面断面図Side sectional view of main girder and deck showing the removal process 撤去工程を示す主桁及び床版の側面断面図Side sectional view of main girder and deck showing the removal process 撤去工程を示す主桁及び床版の分解斜視図An exploded perspective view of the main girder and deck showing the removal process 床版撤去装置の第1の吊り装置の側面図Side view of the first suspension device of the deck removal device 第1の吊り装置の平面図Top view of the first suspension device 第1の吊り装置の正面図Front view of the first suspension device 第1の吊り装置の正面図Front view of the first suspension device 第2の吊り装置の側面図Side view of the second suspension device 第2の吊り装置の平面図Top view of the second suspension device 第2の吊り装置の正面図Front view of the second suspension device 搬送台車の側面図Side view of the transport trolley 搬送台車の平面図Top view of the transport trolley 搬送台車の正面図Front view of the transport trolley 床版撤去工程を示す橋梁の側面図Side view of the bridge showing the deck removal process 床版撤去工程を示す橋梁の側面図Side view of the bridge showing the deck removal process 床版撤去工程を示す橋梁の側面図Side view of the bridge showing the deck removal process 床版撤去工程を示す橋梁の平面図Floor plan of the bridge showing the deck removal process 床版撤去工程を示す床版撤去装置の側面図Side view of the floor slab removal device showing the floor slab removal process 床版撤去工程を示す床版撤去装置の側面図Side view of the floor slab removal device showing the floor slab removal process 床版撤去工程を示す床版撤去装置の側面図Side view of the floor slab removal device showing the floor slab removal process 床版撤去工程を示す床版撤去装置の側面図Side view of the floor slab removal device showing the floor slab removal process 床版撤去工程を示す床版撤去装置の側面図Side view of the floor slab removal device showing the floor slab removal process 床版撤去工程を示す床版撤去装置の側面図Side view of the floor slab removal device showing the floor slab removal process 床版撤去工程を示す床版撤去装置の側面図Side view of the floor slab removal device showing the floor slab removal process 床版撤去工程を示す床版撤去装置の側面図Side view of the floor slab removal device showing the floor slab removal process 床版撤去工程を示す床版撤去装置の側面図Side view of the floor slab removal device showing the floor slab removal process 床版撤去工程を示す床版撤去装置の側面図Side view of the floor slab removal device showing the floor slab removal process 床版撤去工程を示す床版撤去装置の側面図Side view of the floor slab removal device showing the floor slab removal process 床版撤去工程を示すフローチャートFlow chart showing the floor slab removal process 従来の床版撤去工程を示す正面図Front view showing the conventional floor slab removal process 床版撤去工程を示す正面図Front view showing the floor slab removal process 床版撤去工程を示す正面図Front view showing the floor slab removal process 床版撤去工程を示す正面図Front view showing the floor slab removal process

図1乃至図41は本発明の一実施形態を示すもので、橋梁から既設の床版を撤去する床版撤去方法を示すものである。 1 to 41 show an embodiment of the present invention, and show a method for removing an existing deck from a bridge.

同図に示す橋梁10は、橋軸方向に間隔をおいて配置された複数の橋脚11と、橋脚11に支持された主桁12と、主桁12上に架設された既設床版13とからなる。 The bridge 10 shown in the figure is composed of a plurality of piers 11 arranged at intervals in the direction of the bridge axis, a main girder 12 supported by the pier 11, and an existing floor slab 13 erected on the main girder 12. Become.

主桁12は、ウエブ12aの上端及び下端にそれぞれ上フランジ12b及び下フランジ12cを有する鋼桁からなり、互いに橋軸直角方向に間隔をおいて複数列(例えば3列)に配置されている。また、上フランジ12bの上面には、主桁12と床版13とを結合するための複数のずれ止め部材としてのジベル12dが設けられている。ジベル12dは、上下方向に延びる金属製の棒状部材によって形成され、上端に他の部分よりも外径の大きい頭部を有する、いわゆるスタッドジベルからなる。このジベル12dは、橋軸直角方向に複数本(例えば3本)ずつ設けられるとともに、主桁12の長手方向一端側から他端側に亘って橋軸方向に間隔をおいて配列されている。尚、本実施形態で示すジベル12dは一例であり、ずれ止め部材としては他の形状のものが用いられる場合もある。 The main girder 12 is made of a steel girder having an upper flange 12b and a lower flange 12c at the upper end and the lower end of the web 12a, respectively, and is arranged in a plurality of rows (for example, three rows) at intervals in the direction perpendicular to the bridge axis. Further, on the upper surface of the upper flange 12b, a gibber 12d as a plurality of slip prevention members for connecting the main girder 12 and the floor slab 13 is provided. The gibber 12d is made of a so-called stud gibber, which is formed by a metal rod-shaped member extending in the vertical direction and has a head having a head having a larger outer diameter than other portions at the upper end. A plurality of (for example, three) gibber 12d are provided in the direction perpendicular to the bridge axis, and the girders 12 are arranged at intervals in the bridge axis direction from one end side to the other end side in the longitudinal direction of the main girder 12. The gibber 12d shown in this embodiment is an example, and a member having another shape may be used as the slip prevention member.

床版13は、各主桁12の上フランジ12b上に図示しない型枠によって打設されたコンクリートにより形成され、その幅方向両側には壁高欄13aが一体に形成されている。床版13においては、各ジベル12dを埋め込んだ状態でコンクリートを打設することにより、各ジベル12dによって主桁12と床版13が結合されている。また、床版13の下面側には、各主桁12の上フランジ12b上にそれぞれ位置するハンチ13bが設けられ、各ハンチ13bは下方に向かって突出するように形成されている。この場合、ハンチ13bの側面は上フランジ12bの両側から床版13の下面まで傾斜面をなすように形成されている。 The deck 13 is formed of concrete cast on the upper flange 12b of each main girder 12 by a formwork (not shown), and wall railings 13a are integrally formed on both sides in the width direction thereof. In the deck 13, the main girder 12 and the deck 13 are connected by each gibber 12d by placing concrete with each gibber 12d embedded therein. Further, on the lower surface side of the floor slab 13, haunches 13b located on the upper flanges 12b of each main girder 12 are provided, and each haunch 13b is formed so as to project downward. In this case, the side surface of the haunch 13b is formed so as to form an inclined surface from both sides of the upper flange 12b to the lower surface of the deck 13.

次に、本実施形態における床版撤去方法について説明する。本実施形態の床版撤去方法は、既設床版13を橋軸直角方向に切断する第1の切断工程と、既設床版13と主桁12との間のコンクリートをスタッドごとワイヤーソーで切断する第2の切断工程と、第2の切断工程で切断された既設床版13を吊り上げて撤去する撤去工程とを含み、第2の切断工程と撤去工程とを床版撤去区間Nの一端から他端まで繰り返し行うことにより、既設床版13を主桁12上から撤去する。尚、前記撤去工程には、図16乃至図24に示す床版撤去装置が用いられるが、床版撤去装置の詳細な構成については後述する。 Next, the floor slab removal method in the present embodiment will be described. In the floor slab removal method of the present embodiment, the first cutting step of cutting the existing deck 13 in the direction perpendicular to the bridge axis and the concrete between the existing deck 13 and the main girder 12 are cut together with the stud with a wire saw. The second cutting step and the removing step of lifting and removing the existing deck 13 cut in the second cutting step are included, and the second cutting step and the removing step are performed from one end of the deck removing section N. The existing floor slab 13 is removed from the main girder 12 by repeating the process to the end. The floor slab removing device shown in FIGS. 16 to 24 is used in the removing step, and the detailed configuration of the floor slab removing device will be described later.

まず、第1の切断工程では、図2に示すように、既設床版13を切断後の橋軸方向の長さがLとなるように橋軸方向の複数の位置Cで橋軸直角方向に切断する。尚、床版13の橋軸方向の長さLは橋軸直角方向の長さWよりも十分に短いものとする。この場合、壁高欄13aを含まない部分(路面部分のほぼ全福に亘る床版)を第1の切断範囲C1 とし、壁高欄13aを含む他の部分を第2の切断範囲C2 として、各切断範囲C1 ,C2 ごとに以下のように切断する。 First, in the first cutting step, as shown in FIG. 2, the existing floor slab 13 is formed in the direction perpendicular to the bridge axis at a plurality of positions C in the bridge axis direction so that the length in the bridge axis direction after cutting is L. Disconnect. It is assumed that the length L in the bridge axis direction of the deck 13 is sufficiently shorter than the length W in the direction perpendicular to the bridge axis. In this case, the portion not including the wall height column 13a (the floor slab covering almost the entire road surface) is set as the first cutting range C1, and the other part including the wall height column 13a is set as the second cutting range C2. Cut as follows for each range C1 and C2.

第1の切断範囲C1 では、図4に示すように、まず湿式のコンクリートカッター70によって既設床版13のコンクリートを上面から所定深さT1 (例えば150mm)まで切断した後、図5に示すように残りの所定深さT2 (例えば20mm)のコンクリートを乾式(無水)のコンクリートカッター71によって下面まで切断する。その際、既設床版13の下面にスポンジ等の養生部材72を切断位置Cに沿って取り付けておくことにより、乾式の切断によってコンクリートが下面まで切断された際、切削粉が橋桁下方に飛散しないようにする。また、第2の切断範囲C2 はワイヤーソーによって切断する。 In the first cutting range C1, as shown in FIG. 4, the concrete of the existing deck 13 is first cut from the upper surface to a predetermined depth T1 (for example, 150 mm) by a wet concrete cutter 70, and then as shown in FIG. The remaining concrete having a predetermined depth T2 (for example, 20 mm) is cut to the lower surface by a dry (anhydrous) concrete cutter 71. At that time, by attaching a curing member 72 such as a sponge to the lower surface of the existing floor slab 13 along the cutting position C, the cutting powder does not scatter below the bridge girder when the concrete is cut to the lower surface by dry cutting. To do so. The second cutting range C2 is cut with a wire saw.

次に、第2の切断工程では、まず、図6及び図7に示すように既設床版13にワイヤーソー用の複数の貫通孔13cを穿設する。各貫通孔13cは、例えば周知のコアドリルでコンクリートを削孔することにより、主桁12の幅方向(橋軸直角方向)両側に位置するように主桁12ごとに2つずつ設けられる。この場合、貫通孔13cは、橋軸直角方向の各切断位置C間の既設床版13のうち、床版撤去区間Nの一端側(図中右側)から3番目の既設床版13に設けられるとともに、5番目以降の既設床版13に切断位置C間の既設床版13の1つおきに設けられる。 Next, in the second cutting step, first, as shown in FIGS. 6 and 7, a plurality of through holes 13c for a wire saw are formed in the existing deck 13. Two through holes 13c are provided for each main girder 12 so as to be located on both sides of the main girder 12 in the width direction (direction perpendicular to the bridge axis), for example, by drilling concrete with a well-known core drill. In this case, the through hole 13c is provided in the existing deck 13 which is the third from one end side (right side in the figure) of the deck removal section N among the existing decks 13 between the cutting positions C in the direction perpendicular to the bridge axis. At the same time, every other existing floor slab 13 between the cutting positions C is provided on the fifth and subsequent existing floor slabs 13.

続いて、床版撤去区間Nの一端側から1番目及び2番目の既設床版13をワイヤーソー80によって以下のように主桁12から切り離す。ワイヤーソー80は駆動装置81から環状に延出し、切断対象物に巻き掛けたワイヤーソー80を駆動装置81によって高速で回転させながら牽引することにより切断対象物を切断する周知の構成からなる。この場合、駆動装置81は、後述する軌条50を跨いで既設床版13上に設置可能に形成されている。 Subsequently, the first and second existing floor slabs 13 from one end side of the floor slab removal section N are separated from the main girder 12 by a wire saw 80 as follows. The wire saw 80 extends from the drive device 81 in an annular shape, and has a well-known configuration for cutting the object to be cut by pulling the wire saw 80 wound around the object to be cut while rotating the wire saw 80 at high speed by the drive device 81. In this case, the drive device 81 is formed so as to be able to be installed on the existing floor slab 13 across the rail 50 described later.

即ち、図9に示すように、3番目の既設床版13の上面にワイヤーソー80の駆動装置81を配置し、駆動装置81から延出するワイヤーソー80を既設床版13の下面側に貫通孔13cを介して通すとともに、図9及び図11に示すように、1番目の既設床版13の橋軸方向一端側の端面にワイヤーソー80を主桁12の上フランジ12bの幅方向両側から掛け渡す。続いて、駆動装置81を駆動し、図10及び図12に示すように、1番目及び2番目の既設床版13と主桁12の上フランジ12bとの間のコンクリート(ハンチ13b)をワイヤーソー80で橋軸方向に切断する。この場合、図示したように主桁12ごとに配置された3台のワイヤーソー80及び駆動装置81を用いてもよいし、1台のワイヤーソー80及び駆動装置81で各主桁12の位置の切断を順次行うようにしてもよい。 That is, as shown in FIG. 9, the drive device 81 of the wire saw 80 is arranged on the upper surface of the third existing floor slab 13, and the wire saw 80 extending from the drive device 81 penetrates the lower surface side of the existing floor slab 13. While passing through the hole 13c, as shown in FIGS. 9 and 11, a wire saw 80 is attached to the end surface of the first existing deck 13 on one end side in the bridge axial direction from both sides in the width direction of the upper flange 12b of the main girder 12. Hand over. Subsequently, the drive device 81 is driven, and as shown in FIGS. 10 and 12, the concrete (haunch 13b) between the first and second existing floor slabs 13 and the upper flange 12b of the main girder 12 is wire sawed. Cut in the direction of the bridge axis at 80. In this case, as shown in the figure, three wire saws 80 and a drive device 81 arranged for each main girder 12 may be used, or one wire saw 80 and a drive device 81 may be used at the positions of the main girders 12. The cutting may be performed sequentially.

次に、図13に示すように1番目の既設床版13を吊り上げて撤去した後、図14に示すように2番目の既設床版13を吊り上げて撤去する。 Next, as shown in FIG. 13, the first existing floor slab 13 is lifted and removed, and then the second existing floor slab 13 is lifted and removed as shown in FIG.

この後、ワイヤーソー80の駆動装置81を5番目の既設床版13に移動し、前記第2の切断工程と前記撤去工程とを繰り返し行うことにより、床版撤去区間Nの全ての既設床版13を撤去する。既設床版13が撤去された主桁12は、上フランジ2bの上面に残存する僅かなコンクリート(ハンチ13b)及びスタッド13dの一部を除去した後、上フランジ2bの表面仕上げを行う。 After that, the drive device 81 of the wire saw 80 is moved to the fifth existing floor slab 13, and the second cutting step and the removal step are repeated to perform all the existing floor slabs in the floor slab removal section N. Remove 13 The main girder 12 from which the existing floor slab 13 has been removed is subjected to surface finishing of the upper flange 2b after removing a small amount of concrete (haunch 13b) remaining on the upper surface of the upper flange 2b and a part of the stud 13d.

ここで、床版13上に設置される床版撤去装置を用いて既設床版13を撤去する床版撤去工程を図16乃至図41に基づいて説明する。尚、図16、図20、図23、図30~図40は、床版撤去装置を図17のA-A線矢視方向から見た側面図である。 Here, a floor slab removing step of removing the existing floor slab 13 by using the floor slab removing device installed on the floor slab 13 will be described with reference to FIGS. 16 to 41. 16, FIG. 20, FIG. 23, and FIGS. 30 to 40 are side views of the floor slab removing device as viewed from the direction of arrow AA in FIG.

同図に示す床版撤去装置は、既設床版13の吊り上げ及び吊り降ろしを行う門型の第1及び第2の吊り装置20,30と、第1の吊り装置20と第2の吊り装置30との間で床版13の搬送を行う搬送台車40とを備え、第1の吊り装置20及び搬送台車40は軌条50に沿って橋軸方向に移動するようになっている。 The floor slab removing device shown in the figure is a gate-type first and second lifting devices 20 and 30 for lifting and lowering the existing floor slab 13, and a first lifting device 20 and a second lifting device 30. A transport trolley 40 for transporting the floor slab 13 is provided between the first suspension device 20 and the transport trolley 40 so as to move in the bridge axis direction along the rail 50.

第1の吊り装置20は、橋軸方向に延びる左右一対の第1のフレーム21と、各第1のフレーム21の橋軸方向一端側及び他端側からそれぞれ下方に延びる左右一対の第2のフレーム22と、橋軸方向に延びる左右一対の第1のガイドレール23と、第1のガイドレール23に沿って橋軸方向に移動する環状の第2のガイドレール24と、第2のガイドレール24に沿って回動する吊り天秤25と、軌条50に係合して走行する複数の自走式の走行ユニット26とから構成されている。 The first suspension device 20 includes a pair of left and right first frames 21 extending in the bridge axis direction, and a pair of left and right second frames extending downward from one end side and the other end side of each first frame 21 in the bridge axis direction. The frame 22, a pair of left and right first guide rails 23 extending in the bridge axis direction, an annular second guide rail 24 moving in the bridge axis direction along the first guide rail 23, and a second guide rail. It is composed of a suspension balance 25 that rotates along 24 and a plurality of self-propelled traveling units 26 that travel by engaging with the rail 50.

各第1のフレーム21は、両端側が各第2のフレーム22よりも橋軸方向に長く延出した片持ち梁状に形成され、橋軸直角方向に延びる複数の横梁21aによって互いに連結されている。 Each first frame 21 is formed in a cantilever shape having both ends extending longer in the bridge axis direction than each second frame 22, and is connected to each other by a plurality of cross beams 21a extending in the direction perpendicular to the bridge axis. ..

各第2のフレーム22は、上端を第1のフレーム21に連結され、下端側を橋軸方向に延びる複数の横梁22aによって互いに連結されている。 The upper end of each second frame 22 is connected to the first frame 21, and the lower end side is connected to each other by a plurality of cross beams 22a extending in the bridge axis direction.

各第1のガイドレール23は、第1のフレーム21よりもやや長く形成され、各第1のガイドレール23の各横梁21aに固定されている。 Each first guide rail 23 is formed slightly longer than the first frame 21, and is fixed to each cross beam 21a of each first guide rail 23.

第2のガイドレール24は周方向4箇所をそれぞれ支持機構24aを介して各第1のガイドレール23に連結されており、各支持機構24aによって各第1のガイドレール23の一端側から他端側まで移動するようになっている。各支持機構24aとしては、例えば周知の電動トロリを用いることができる。 The second guide rail 24 is connected to each first guide rail 23 via a support mechanism 24a at four points in the circumferential direction, and each support mechanism 24a connects one end side to the other end of each first guide rail 23. It is designed to move to the side. As each support mechanism 24a, for example, a well-known electric trolley can be used.

吊り天秤25は水平方向に直線状に延びるように形成され、長手方向2箇所をそれぞれ支持機構25aを介して第2のガイドレール24に連結されており、各支持機構25aによって第2のガイドレール24の周方向に回動するようになっている。各支持機構25aとしては、例えば周知のギヤードトロリを用いることができる。また、吊り天秤25には複数の吊り下げ部材25bが互いに吊り天秤25の長手方向に間隔をおいて設けられ、各吊り下げ部材25bによって床版13を吊り下げるようになっている。各吊り下げ部材25bとしては、例えば周知の手動チェーンブロックを用いることができる。 The suspension balance 25 is formed so as to extend linearly in the horizontal direction, and two points in the longitudinal direction are connected to the second guide rail 24 via the support mechanism 25a, respectively, and the second guide rail is connected by each support mechanism 25a. It is designed to rotate in the circumferential direction of 24. As each support mechanism 25a, for example, a well-known geared trolley can be used. Further, the suspension balance 25 is provided with a plurality of suspension members 25b at intervals in the longitudinal direction of the suspension balance 25, and the floor slab 13 is suspended by each suspension member 25b. As each suspension member 25b, for example, a well-known manual chain block can be used.

各走行ユニット26は、それぞれ各第2のフレーム22の下端に設けられている。走行ユニット26には前後一対の車輪26aが設けられ、各車輪26aは図示しないモータによって駆動されるようになっている。 Each traveling unit 26 is provided at the lower end of each second frame 22. The traveling unit 26 is provided with a pair of front and rear wheels 26a, and each wheel 26a is driven by a motor (not shown).

第2の吊り装置30は、橋軸方向に延びる左右一対の第1のフレーム31と、各第1のフレーム31の橋軸方向一端側及び他端側からそれぞれ下方に延びる左右一対の第2のフレーム32と、橋軸方向に延びる吊り天秤33とから構成されている。 The second suspension device 30 includes a pair of left and right first frames 31 extending in the bridge axis direction, and a pair of left and right second frames extending downward from one end side and the other end side of each first frame 31 in the bridge axis direction. It is composed of a frame 32 and a suspension balance 33 extending in the direction of the bridge axis.

各第1のフレーム31は、両端側がほぼ各第2のフレーム32の上端に位置するように形成され、橋軸直角方向に延びる複数の横梁31aによって互いに連結されている。 Each of the first frames 31 is formed so that both ends thereof are located substantially at the upper ends of the second frames 32, and is connected to each other by a plurality of cross beams 31a extending in the direction perpendicular to the bridge axis.

各第2のフレーム32は、上端を第1のフレーム31に連結され、下端側を橋軸方向に延びる複数の横梁32aによって互いに連結されている。 The upper end of each second frame 32 is connected to the first frame 31, and the lower end side is connected to each other by a plurality of cross beams 32a extending in the bridge axis direction.

吊り天秤33は水平方向に直線状に延びるように形成され、第1のフレーム31の各横梁31aに橋軸直角方向中央に位置するように固定されている。吊り天秤33には複数の吊り下げ部材33aが互いに吊り天秤33の長手方向に間隔をおいて設けられ、各吊り下げ部材33aによって床版13を吊り下げるようになっている。各吊り下げ部材33aとしては、例えば周知の手動チェーンブロックを用いることができる。 The suspension balance 33 is formed so as to extend linearly in the horizontal direction, and is fixed to each cross beam 31a of the first frame 31 so as to be located at the center in the direction perpendicular to the bridge axis. A plurality of suspension members 33a are provided on the suspension balance 33 at intervals in the longitudinal direction of the suspension balance 33, and the floor slab 13 is suspended by each suspension member 33a. As each suspension member 33a, for example, a well-known manual chain block can be used.

搬送台車40は、橋軸方向に延びる左右一対の第1のフレーム41と、橋軸直角方向に延びる前後一対の第2のフレーム42と、軌条50に係合して走行する複数の自走式の走行ユニット43とから構成されている。 The transport trolley 40 is a plurality of self-propelled type traveling by engaging with a pair of left and right first frames 41 extending in the direction of the bridge axis, a pair of front and rear second frames 42 extending in the direction perpendicular to the bridge axis, and a rail 50. It is composed of the traveling unit 43 of the above.

各第1のフレーム41は、両端側が各第2のフレーム42よりも橋軸方向に長く延出するように形成され、互いに床版13の橋軸方向の長さLよりも短い間隔をおいて配置されている。 Each first frame 41 is formed so that both ends extend longer in the bridge axis direction than each second frame 42, and are spaced apart from each other by a length shorter than the bridge axis length L of the deck 13. Have been placed.

各第2のフレーム42は、橋軸直角方向中央側が両端側よりも下方に位置するように屈曲しており、橋軸直角方向中央側に各第1のフレーム41が固定されている。 Each second frame 42 is bent so that the center side in the direction perpendicular to the bridge axis is located below both ends, and each first frame 41 is fixed to the center side in the direction perpendicular to the bridge axis.

各走行ユニット43は、それぞれ各第2のフレーム42の両端に設けられている。走行ユニット43には前後一対の車輪43aが設けられ、各車輪43aは図示しないモータによって駆動されるようになっている。 Each traveling unit 43 is provided at both ends of each second frame 42. The traveling unit 43 is provided with a pair of front and rear wheels 43a, and each wheel 43a is driven by a motor (not shown).

軌条50は、互いに橋軸直角方向に間隔をおいて配置されるレール51と、上端にレール51が固定された固定部材52とを有し、レール51及び固定部材52は既設床版13上または既設床版13が除去された主桁12上に互いに橋軸直角方向に間隔をおいて一対ずつ配置されるようになっている。軌条50は、床版13の橋軸方向の長さLの2倍の長さ2Lに形成されたレール51及び固定部材52が橋軸方向に連結されるようになっている。この場合、左右のレール51及び固定部材52は橋軸直角方向両端の主桁12と等しい間隔で配置され、左右の固定部材52は互いに複数の補強部材53を介して連結されている。また、軌条50を既設床版13が除去された主桁12上に設置する場合は、固定部材52と主桁12との間に床版13と等しい高さの枕木材54が配置される。 The rail 50 has a rail 51 arranged at right angles to each other in the direction perpendicular to the bridge axis, and a fixing member 52 to which the rail 51 is fixed at the upper end, and the rail 51 and the fixing member 52 are on the existing deck 13 or. A pair of existing floor slabs 13 are arranged on the main girder 12 from which the existing deck 13 has been removed at right angles to each other in the direction perpendicular to the bridge axis. The rail 50 is configured such that a rail 51 and a fixing member 52 formed in a length 2L that is twice the length L in the bridge axial direction of the deck 13 are connected in the bridge axial direction. In this case, the left and right rails 51 and the fixing members 52 are arranged at equal intervals with the main girders 12 at both ends in the direction perpendicular to the bridge axis, and the left and right fixing members 52 are connected to each other via a plurality of reinforcing members 53. Further, when the rail 50 is installed on the main girder 12 from which the existing floor slab 13 has been removed, a pillow wood 54 having a height equal to that of the floor slab 13 is arranged between the fixing member 52 and the main girder 12.

次に、前記床版撤去装置を用いた床版撤去工程について、図26乃至図40を参照して説明する。 Next, the floor slab removing step using the floor slab removing device will be described with reference to FIGS. 26 to 40.

まず、図27に示すように、前記第1の切断工程によって既設床版13を橋軸方向の複数の位置Cで橋軸直角方向に切断する。この場合、床版13の橋軸方向の長さLは橋軸直角方向の長さWよりも十分に短いものとする。 First, as shown in FIG. 27, the existing deck 13 is cut at a plurality of positions C in the bridge axis direction in the direction perpendicular to the bridge axis by the first cutting step. In this case, the length L in the bridge axis direction of the deck 13 is sufficiently shorter than the length W in the direction perpendicular to the bridge axis.

次に、図28及び図29に示すように、橋軸直角方向に切断された既設床版13上に軌条50を敷設する。その際、床版撤去区間Nの一端側の2枚の既設床版13を除いた位置から床版撤去区間Nの他端側及び床版撤去区間外の既設床版13上に亘って軌条50を敷設する。尚、床版撤去区間外は既に床版取替施工が完了した新設床版上であってもよい。 Next, as shown in FIGS. 28 and 29, the rail 50 is laid on the existing deck 13 cut in the direction perpendicular to the bridge axis. At that time, the rail 50 extends from the position excluding the two existing decks 13 on one end side of the deck removal section N to the other end side of the deck removal section N and on the existing deck 13 outside the deck removal section. To lay. The area outside the floor slab removal section may be on a newly installed floor slab for which the floor slab replacement work has already been completed.

続いて、図30に示すように、第1の吊り装置20、第2の吊り装置30及び搬送台車40を配置する。第1の吊り装置20は軌条50上を走行可能に配置され、床版撤去区間Nの一端側に位置している。第2の吊り装置30は床版撤去区間外の既設床版13上に配置され、各第2のフレーム32が軌条50の外側に位置するように設置される。搬送台車40は軌条50上を走行可能に配置され、第1の吊り装置20と第2の吊り装置30との間を往復移動するようになっている。 Subsequently, as shown in FIG. 30, the first suspension device 20, the second suspension device 30, and the transport carriage 40 are arranged. The first suspension device 20 is arranged so as to be able to travel on the rail 50, and is located on one end side of the deck removal section N. The second suspension device 30 is arranged on the existing deck 13 outside the deck removal section, and each second frame 32 is installed so as to be located outside the rail 50. The transport carriage 40 is arranged so as to be able to travel on the rail 50, and reciprocates between the first suspension device 20 and the second suspension device 30.

次に、前記第2の切断工程によって床版撤去区間Nの一端側の既設床版13と主桁12との間のコンクリートを切断する。 Next, the concrete between the existing deck 13 and the main girder 12 on one end side of the deck removal section N is cut by the second cutting step.

続いて、図31に示すように、第1の吊り装置20の吊り天秤25を第1の吊り装置20の一端側に位置させるとともに、各吊り下げ部材25bを床版撤去区間Nの最も一端側に位置する既設床版13にロープ25cを介して連結し、図32に示すように各吊り下げ部材25bによって既設床版13を吊り上げる。その際、吊り天秤25の向きは長手方向が橋軸直角方向となっている。また、搬送台車40は第1の吊り装置20の他端側に位置している。 Subsequently, as shown in FIG. 31, the suspension balance 25 of the first suspension device 20 is positioned on one end side of the first suspension device 20, and each suspension member 25b is placed on the most end side of the deck removal section N. The existing floor slab 13 is connected to the existing floor slab 13 located in the above via a rope 25c, and the existing floor slab 13 is lifted by each hanging member 25b as shown in FIG. 32. At that time, the direction of the suspension balance 25 is such that the longitudinal direction is perpendicular to the bridge axis. Further, the transport carriage 40 is located on the other end side of the first suspension device 20.

次に、図33に示すように、吊り天秤25及び既設床版13の長手方向の向きが橋軸直角方向となるように第1の吊り装置20の吊り天秤25を90度回転させ、図34に示すように第2のガイドレール24によって吊り天秤25及び既設床版13を第1の吊り装置20の他端側に移動する。 Next, as shown in FIG. 33, the suspension balance 25 of the first suspension device 20 is rotated 90 degrees so that the longitudinal orientation of the suspension balance 25 and the existing deck 13 is perpendicular to the bridge axis, and FIG. 34 As shown in the above, the suspension balance 25 and the existing deck 13 are moved to the other end side of the first suspension device 20 by the second guide rail 24.

この後、図35に示すように吊り天秤25から既設床版13を搬送台車40上に吊り降ろし、図36に示すように既設床版13を載せた搬送台車40を第2の吊り装置30まで移動する。 After that, as shown in FIG. 35, the existing floor slab 13 is suspended from the suspension balance 25 onto the transport trolley 40, and as shown in FIG. 36, the transport trolley 40 on which the existing floor slab 13 is mounted is moved to the second suspension device 30. Moving.

続いて、図37に示すように第2の吊り装置30の吊り天秤33の各吊り下げ部材33aによって既設床版13を吊り上げた後、搬送台車40を第1の吊り装置20の他端側まで移動する。その際、第1の吊り装置20を既設床版13の1つ分の長さLだけ床版撤去区間Nの他端側に向かって移動するとともに、吊り天秤25を第1の吊り装置20の一端側まで移動する。 Subsequently, as shown in FIG. 37, after the existing floor slab 13 is lifted by each hanging member 33a of the suspension balance 33 of the second suspension device 30, the transport carriage 40 is moved to the other end side of the first suspension device 20. Moving. At that time, the first suspension device 20 is moved toward the other end side of the floor slab removal section N by the length L of one of the existing floor slabs 13, and the suspension balance 25 is moved to the other end side of the floor slab removal section N, and the suspension balance 25 is moved to the first suspension device 20. Move to one end side.

次に、図38に示すように、第2の吊り装置30の内側に乗り入れた運搬車両60(トラック)に吊り天秤33から既設床版13を吊り降ろし、運搬車両60によって既設床版13を外部に搬出する。また、第1の吊り装置20の吊り天秤25を長手方向の向きが橋軸方向となるように90度回転させる。 Next, as shown in FIG. 38, the existing floor slab 13 is suspended from the suspension balance 33 on the transport vehicle 60 (truck) that has entered the inside of the second suspension device 30, and the existing floor slab 13 is externally mounted by the transport vehicle 60. Carry out to. Further, the suspension balance 25 of the first suspension device 20 is rotated by 90 degrees so that the direction in the longitudinal direction is the bridge axis direction.

この後、次の既設床版13と主桁12との間のコンクリートをスタッドごと前述と同様に切断し、図39に示すように第1の吊り装置20の各吊り下げ部材25bによって次の既設床版13を吊り上げる。前述と同様の工程により2枚目の既設床版13を撤去した後、図40に示すように第1の吊り装置20を既設床版13の1つ分の長さLだけ床版撤去区間Nの他端側に向かって移動するとともに、軌条50のレール51及び固定部材52を1つ分だけ取り除く。即ち、既設床版13を2枚撤去するごとにレール51及び固定部材52を1つずつ取り除く工程を繰り返しながら第1の吊り装置20を順次移動させることにより、床版撤去区間Nの既設床版13を全て撤去する。 After that, the concrete between the next existing floor slab 13 and the main girder 12 is cut together with the studs in the same manner as described above, and as shown in FIG. Lift the floor slab 13. After removing the second existing floor slab 13 by the same process as described above, as shown in FIG. 40, the first suspension device 20 is attached to the floor slab removal section N by the length L of one of the existing floor slabs 13. While moving toward the other end side of the rail 50, the rail 51 and the fixing member 52 of the rail 50 are removed by one. That is, by sequentially moving the first suspension device 20 while repeating the process of removing the rail 51 and the fixing member 52 one by one every time two existing floor slabs 13 are removed, the existing floor slab in the floor slab removal section N is moved. Remove all 13's.

そして、既設床版13が全て撤去された床版撤去区間Nの主桁12上には、新たな床版が設置される。 Then, a new floor slab is installed on the main girder 12 of the floor slab removal section N from which all the existing floor slab 13 has been removed.

このように、本実施形態の床版撤去方法によれば、床版撤去区間Nの既設床版13を橋軸方向の複数箇所で橋軸直角方向に切断した後、主桁12の上フランジ12bと既設床版13との間のコンクリートを橋軸方向に所定長さだけ切断し、切断された既設床版13を吊り上げて撤去するようにしたので、橋軸方向に所定長さLずつ分割した既設床版13を橋軸直角方向に分割せずに全幅のまま撤去することができる。即ち、既設床版13を従来のように橋軸直角方向に複数に分割する必要がないので、撤去する既設床版13の分割数を大幅に少なくすることができる。これにより、既設床版13の切断及び撤去作業を効率よく行うことができ、施工期間を短縮することができる。 As described above, according to the deck removing method of the present embodiment, after cutting the existing deck 13 of the deck removing section N at a plurality of points in the bridge axis direction in the direction perpendicular to the bridge axis, the upper flange 12b of the main girder 12 The concrete between the and the existing deck 13 was cut by a predetermined length in the direction of the bridge axis, and the cut existing deck 13 was lifted and removed. The existing deck 13 can be removed with its full width without dividing it in the direction perpendicular to the bridge axis. That is, since it is not necessary to divide the existing floor slab 13 into a plurality of parts in the direction perpendicular to the bridge axis as in the conventional case, the number of divisions of the existing floor slab 13 to be removed can be significantly reduced. As a result, the existing floor slab 13 can be efficiently cut and removed, and the construction period can be shortened.

また、主桁12の上フランジ12bと既設床版13との間のコンクリートをスタッド12dごとワイヤーソー80で切断するようにしたので、主桁12上に残存するコンクリート量を極めて少なくすることができ、主桁12上のコンクリート除去作業を大幅に軽減することができる。 Further, since the concrete between the upper flange 12b of the main girder 12 and the existing floor slab 13 is cut with the wire saw 80 together with the stud 12d, the amount of concrete remaining on the main girder 12 can be extremely reduced. , The concrete removal work on the main girder 12 can be significantly reduced.

この場合、切断しようとする既設床版13に対して橋軸方向他の位置に配置される他の既設床版13上にワイヤーソー80の駆動装置81を配置し、駆動装置81から延出するワイヤーソー80を他の既設床版13に穿設した貫通孔13cを介して既設床版13の下面側に通すとともに、切断しようとする既設床版13の橋軸方向一端側の端面にワイヤーソー80を主桁12の上フランジ12bの幅方向両側から掛け渡し、切断しようとする既設床版13と主桁12の上フランジ12bとの間のコンクリート(ハンチ13b)をワイヤーソー80で橋軸方向に切断するようにしたので、切断しようとする既設床版13と主桁12とを他の既設床版13上に配置された駆動装置81から延出するワイヤーソー80によって確実に切り離すことができる。 In this case, the drive device 81 of the wire saw 80 is arranged on another existing deck 13 arranged at another position in the bridge axis direction with respect to the existing deck 13 to be cut, and extends from the drive device 81. The wire saw 80 is passed through the lower surface side of the existing deck 13 through the through hole 13c drilled in the other existing deck 13, and the wire saw is placed on the end surface of the existing deck 13 to be cut on one end side in the bridge axis direction. 80 is hung from both sides of the upper flange 12b of the main girder 12 in the width direction, and the concrete (haunch 13b) between the existing deck 13 to be cut and the upper flange 12b of the main girder 12 is crossed in the bridge axis direction with a wire saw 80. The existing floor slab 13 and the main girder 12 to be cut can be reliably separated by the wire saw 80 extending from the drive device 81 arranged on the other existing floor slab 13. ..

また、主桁12の上フランジ12bと既設床版13との間のコンクリートを橋軸方向に所定長さLだけ切断する第2の切断工程と、切断された既設床版13を吊り上げて撤去する撤去工程とを床版撤去区間Nの橋軸方向一端から他端まで繰り返し行うようにしたので、主桁12から切り離される前の既設床版13上に第1の吊り装置20及び搬送台車40を配置して作業することができ、第1の吊り装置20及び搬送台車40を軌条50に沿って既設床版13上を移動させながら床版撤去作業を行うことができる。即ち、床版撤去区間Nの全ての既設床版13と主桁12との間を先に切断してしまうと、主桁12と切り離された不安定な既設床版13上では作業ができなくなるが、本実施形態では主桁12と切り離される前の既設床版13上を第1の吊り装置20の作業場として利用することができる。 Further, a second cutting step of cutting the concrete between the upper flange 12b of the main girder 12 and the existing deck 13 by a predetermined length L in the direction of the bridge axis, and lifting and removing the cut existing deck 13. Since the removal process is repeated from one end to the other end of the deck removal section N in the bridge axis direction, the first suspension device 20 and the transport trolley 40 are mounted on the existing deck 13 before being separated from the main girder 12. The work can be arranged and the work can be performed, and the floor slab removal work can be performed while moving the first suspension device 20 and the transport trolley 40 on the existing floor slab 13 along the rail 50. That is, if the space between all the existing floor slabs 13 and the main girder 12 in the floor slab removal section N is cut first, work cannot be performed on the unstable existing floor slab 13 separated from the main girder 12. However, in the present embodiment, the existing floor slab 13 before being separated from the main girder 12 can be used as a work place for the first suspension device 20.

更に、第1の切断工程において、既設床版13を橋軸方向複数の切断位置Cで互いに間隔Lをおいて切断する際、湿式のコンクリートカッター70によって既設床版13のコンクリートを上面から所定深さT1 まで切断した後、残りの所定深さT2 のコンクリートを無水式のコンクリートカッター71によって既設床版13の下面まで切断するようにしたので、湿式と乾式を併用した切断により、桁下への汚水の落下を防止しつつ低コストに既設床版13のコンクリートを切断することができる。即ち、湿式切断は冷却に使用した水の処理が必要であるが、乾式よりも低コストであるという利点があり、他方、乾式は汚水を発生させないが、切削粉を回収するための大型バキューム装置を必要とする分コストが高くなるとともに最大深長が湿式よりも小さいため、本実施形態のように、既設床版13の厚さ方向の大部分を湿式で切断し、残りの僅かな部分を乾式で切断することにより、切断コストを抑えるとともに、汚水対策も講じることができる。 Further, in the first cutting step, when the existing deck 13 is cut at a plurality of cutting positions C in the bridge axis direction at intervals L from each other, the concrete of the existing deck 13 is cut from the upper surface to a predetermined depth by a wet concrete cutter 70. After cutting to T1, the remaining concrete with a predetermined depth T2 was cut to the lower surface of the existing deck 13 with an anhydrous concrete cutter 71. It is possible to cut the concrete of the existing floor slab 13 at low cost while preventing the fall of sewage. That is, wet cutting requires treatment of the water used for cooling, but has the advantage of being cheaper than the dry type, while the dry type does not generate sewage, but is a large vacuum device for recovering cutting powder. Since the cost is high and the maximum depth is smaller than that of the wet type, most of the existing floor slab 13 in the thickness direction is cut by the wet type and the remaining small part is dry type as in the present embodiment. By cutting with, it is possible to reduce the cutting cost and take measures against sewage.

この場合、既設床版13の下面に養生部材72を切断位置Cに沿って取り付けておくようにしたので、乾式の切断によってコンクリートが下面まで切断された際、切削粉が橋桁下方に飛散することがない。また、前工程の湿式の切断時に発生した水や雨水が床版134上に残存していた場合でも、養生部材72によって橋桁下方への水の落下を防止することもできる。 In this case, since the curing member 72 is attached to the lower surface of the existing floor slab 13 along the cutting position C, cutting powder is scattered below the bridge girder when the concrete is cut to the lower surface by dry cutting. There is no. Further, even if water or rainwater generated during the wet cutting in the previous step remains on the deck 134, the curing member 72 can prevent the water from falling below the bridge girder.

更に、床版撤去区間Nの既設床版13を橋軸方向の長さLが橋軸直角方向の長さWよりも短くなるように橋軸方向複数箇所で橋軸直角方向に切断し、既設床版13上を橋軸方向に移動可能な門型の第1の吊り装置20及び搬送台車40を用い、切断された既設床版13を第1の吊り装置20によって吊り上げるとともに、吊り上げた既設床版13を長手方向が橋軸方向となるように回転させて搬送台車40に載置し、既設床版13を載置した搬送台車40を所定の搬送場所まで搬送するとともに、第1の吊り装置20を次の床版撤去位置に移動して既設床版13の前記撤去を床版撤去区間Nの橋軸方向一端から他端まで順次行うようにしたので、既設床版13をクレーン車によって吊り上げる必要がなく、しかも撤去する既設床版13を道路幅よりも小さい幅になる向きで搬送することができる。これにより、クレーン車を用いずに床版撤去作業を行うことができるので、施工現場の上方に位置する交差道路や高圧電線によって上空制約がある場合や、供用中の隣接道路や近隣構造物による道路幅方向の作業スペースに制約がある場合、或いは既設橋梁の耐荷力による重量の制約がある場合でも、これらの制約を受けることなく既設床版13の撤去を行うことができる。 Further, the existing deck 13 of the deck removal section N is cut at a plurality of points in the bridge axis direction in the direction perpendicular to the bridge axis so that the length L in the bridge axis direction is shorter than the length W in the direction perpendicular to the bridge axis. Using a gate-shaped first suspension device 20 and a transport trolley 40 that can move on the deck 13 in the direction of the bridge axis, the cut existing deck 13 is lifted by the first suspension device 20, and the existing floor is lifted. The plate 13 is rotated so that the longitudinal direction is the bridge axis direction and mounted on the transport trolley 40, and the transport trolley 40 on which the existing floor slab 13 is mounted is transported to a predetermined transport location and the first suspension device. Since 20 is moved to the next deck removal position and the removal of the existing deck 13 is sequentially performed from one end to the other end in the bridge axis direction of the deck removal section N, the existing deck 13 is lifted by a crane car. It is not necessary, and the existing deck 13 to be removed can be transported in a direction smaller than the road width. As a result, the deck removal work can be performed without using a crane vehicle, so if there are sky restrictions due to crossing roads or high-voltage electric wires located above the construction site, or if there are adjacent roads or nearby structures in service. Even if there are restrictions on the work space in the road width direction, or if there are restrictions on the weight due to the load capacity of the existing bridge, the existing floor slab 13 can be removed without these restrictions.

尚、前記実施形態では、橋軸方向の長さLの既設床版13を複数枚(例えば2枚)撤去するごとに長さ2Lのレール51及び固定部材52を1つずつ取り除くようにしたものを示したが、既設床版13を1枚撤去するごとに長さLのレール51及び固定部材52を1つずつ取り除くようにしてもよい。 In the above embodiment, each time a plurality (for example, two) of existing floor slabs 13 having a length L in the direction of the bridge axis are removed, one rail 51 having a length of 2 L and one fixing member 52 are removed. However, each time the existing floor slab 13 is removed, the rail 51 and the fixing member 52 having a length L may be removed one by one.

10…橋梁、12…主桁、12d…スタッド、13…既設床版、13c…貫通孔、20…第1の吊り装置、30…第2の吊り装置、40…搬送台車、50…軌条、60…運搬車両、70,71…コンクリートカッター、80…ワイヤーソー、81…駆動装置。 10 ... Bridge, 12 ... Main girder, 12d ... Stud, 13 ... Existing floor slab, 13c ... Through hole, 20 ... First suspension device, 30 ... Second suspension device, 40 ... Transport trolley, 50 ... Rail, 60 ... transport vehicle, 70, 71 ... concrete cutter, 80 ... wire saw, 81 ... drive device.

Claims (5)

主桁上にコンクリート製の床版が設置され、主桁の上面に設けられたずれ止め部材によって主桁と床版が結合された合成桁から床版を撤去する合成桁の床版撤去方法において、
床版撤去区間の床版を橋軸方向の複数箇所で橋軸直角方向に切断する第1の切断工程と、
主桁と床版との間のコンクリートをずれ止め部材ごとワイヤーソーで橋軸方向に所定長さだけ切断する第2の切断工程と、
第2の切断工程で切断された床版を吊り上げて撤去する撤去工程とを含み、
第1の切断工程は、湿式のコンクリートカッターによって既設床版のコンクリートを上面から所定深さまで切断した後、残りのコンクリートを乾式のコンクリートカッターによって下面まで切断するようにし、
第2の切断工程と撤去工程とを床版撤去区間の橋軸方向一端から他端まで繰り返し行う
ことを特徴とする合成桁の床版撤去方法。
In the method of removing the floor slab of a synthetic girder in which a concrete floor slab is installed on the main girder and the floor slab is removed from the synthetic girder in which the main girder and the floor slab are combined by a slip stopper provided on the upper surface of the main girder. ,
The first cutting step of cutting the deck in the deck removal section in the direction perpendicular to the bridge axis at multiple points in the bridge axis direction,
A second cutting step in which the concrete between the main girder and the floor slab is cut by a predetermined length in the bridge axis direction with a wire saw together with the slip prevention member.
Including the removal step of lifting and removing the floor slab cut in the second cutting step.
In the first cutting step, the concrete of the existing deck is cut from the upper surface to a predetermined depth by a wet concrete cutter, and then the remaining concrete is cut to the lower surface by a dry concrete cutter.
A method for removing a floor slab of a synthetic girder, which comprises repeating a second cutting step and a removal step from one end to the other end in the bridge axis direction of the floor slab removal section.
前記第2の切断工程は、切断しようとする床版に対して橋軸方向他の位置に配置される他の床版上にワイヤーソーの駆動装置を配置し、駆動装置から延出するワイヤーソーを他の床版に穿設した貫通孔を介して床版の下面側に通すとともに、切断しようとする床版にワイヤーソーを主桁の幅方向両側から掛け渡し、切断しようとする床版と主桁との間のコンクリートをワイヤーソーで橋軸方向に切断する
ことを特徴とする請求項1記載の合成桁の床版撤去方法。
In the second cutting step, the drive device of the wire saw is arranged on another deck arranged at another position in the bridge axial direction with respect to the deck to be cut, and the wire saw extends from the drive device. Is passed through the through hole drilled in another deck slab to the lower surface side of the deck, and the wire saw is hung from both sides in the width direction of the main girder to the deck to be cut, and the deck to be cut. The method for removing a deck of a synthetic girder according to claim 1, wherein the concrete between the main girder and the main girder is cut in the direction of the bridge axis with a wire saw.
前記撤去工程は、床版上に敷設される軌条に沿って橋軸方向に移動可能な門型の吊り装置及び搬送台車を用い、前記第2の切断工程で切断された床版を吊り装置によって吊り上げて搬送台車に載置し、床版を載置した搬送台車を所定の場所まで搬送するとともに、吊り装置を橋軸方向に所定距離だけ移動し、次に撤去しようとする床版上の軌条を除去する
ことを特徴とする請求項1または2記載の合成桁の床版撤去方法。
In the removal step, a gate-shaped suspension device and a transport trolley that can move in the direction of the bridge axis along the rail laid on the deck are used, and the deck cut in the second cutting step is lifted by the suspension device. The rail on the floor slab to be lifted and placed on the transport trolley, the transport trolley on which the deck is placed is transported to a predetermined location, the suspension device is moved by a predetermined distance in the direction of the bridge axis, and then the rail is to be removed. The method for removing a floor slab of a synthetic girder according to claim 1 or 2, wherein the method is to remove the rail.
前記第1の切断工程は、床版を橋軸方向の長さが橋軸直角方向の長さよりも短くなるように切断し、
前記撤去工程は、前記吊り装置によって吊り上げた床版を長手方向が橋軸方向となるように水平方向に回転させて搬送台車に載置する
ことを特徴とする請求項3記載の合成桁の床版撤去方法。
In the first cutting step, the deck is cut so that the length in the direction of the bridge axis is shorter than the length in the direction perpendicular to the bridge axis.
The floor of the synthetic girder according to claim 3, wherein the removing step is to rotate the deck lifted by the lifting device in the horizontal direction so that the longitudinal direction is the bridge axis direction and place it on the transport carriage. How to remove the plate.
前記所定の場所に配置された他の門型の吊り装置を用いて搬送台車から運搬車両への床版の積み替えを行う
ことを特徴とする請求項3または4記載の合成桁の床版撤去方法。
The method for removing a floor slab of a synthetic girder according to claim 3 or 4, wherein the floor slab is transshipped from a transport trolley to a transport vehicle using another gate-type suspension device arranged at the predetermined location. ..
JP2018063783A 2018-03-29 2018-03-29 How to remove the floor slab of synthetic girders Active JP7020978B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2018063783A JP7020978B2 (en) 2018-03-29 2018-03-29 How to remove the floor slab of synthetic girders

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018063783A JP7020978B2 (en) 2018-03-29 2018-03-29 How to remove the floor slab of synthetic girders

Publications (2)

Publication Number Publication Date
JP2019173436A JP2019173436A (en) 2019-10-10
JP7020978B2 true JP7020978B2 (en) 2022-02-16

Family

ID=68168287

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018063783A Active JP7020978B2 (en) 2018-03-29 2018-03-29 How to remove the floor slab of synthetic girders

Country Status (1)

Country Link
JP (1) JP7020978B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114214976B (en) * 2022-01-27 2023-07-07 中铁二十二局集团第三工程有限公司 Concrete bridge flange dismantling construction method and cantilever device

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004232426A (en) 2003-02-03 2004-08-19 Kawada Construction Co Ltd Floor panel laying apparatus
JP2017203299A (en) 2016-05-12 2017-11-16 首都高速道路株式会社 Cutting device and floor slab cutting method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0643682B2 (en) * 1989-05-02 1994-06-08 ショーボンド建設株式会社 Bridge floor slab removal method
JP2578305B2 (en) * 1993-04-26 1997-02-05 株式会社ピー・エス Non-composite RC slab replacement method and self-propelled slab lifting device
JPH08151607A (en) * 1994-11-30 1996-06-11 Kajima Corp Method of carrying precast block for bridge

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004232426A (en) 2003-02-03 2004-08-19 Kawada Construction Co Ltd Floor panel laying apparatus
JP2017203299A (en) 2016-05-12 2017-11-16 首都高速道路株式会社 Cutting device and floor slab cutting method

Also Published As

Publication number Publication date
JP2019173436A (en) 2019-10-10

Similar Documents

Publication Publication Date Title
JP6793542B2 (en) Floor slab erection method and floor slab erection equipment
JP6081117B2 (en) How to remove existing bridge and update existing bridge
JP4403579B2 (en) Removal method of existing pier of overpass
CN101781878B (en) Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof
JPH11131427A (en) Floor board replacing machine for concrete bridge
JP3954869B2 (en) Bridge girder replacement method
JP3579897B1 (en) Construction method of split bridge type traffic route and split bridge type traffic route
KR100891961B1 (en) The construction infrastructure the use road the martial art as a matter of bridge of the bridge which is old in the railroad or the railroad respects the induction event a method of construction which shifts the bridge and the system
CN106976157A (en) A kind of post stretching precast beam pedestal for being applicable different length and cross sectional shape
JP7020978B2 (en) How to remove the floor slab of synthetic girders
RU2495184C1 (en) Method to disassemble bridge span and device for realisation of this method
JP6974233B2 (en) Floor slab replacement method and floor slab replacement device
KR20050108867A (en) A method for changing plate-girder bridge of railway bridge into slab bridge by using temporary construction bents.
KR101270947B1 (en) Deck repairing construction method of bridge using precast concrete slab
KR20060082970A (en) Crane for replacement of a girdir of a railway bridge and method for replacement of the girdir using the same
CN111705682A (en) Construction method and equipment for removing and rebuilding superstructure of widened bridge across electrified railway
JP3996818B2 (en) Work truck for tunnel widening work
CN205501840U (en) A braced system for construction of overpass cast -in -situ box girder
JP7409952B2 (en) Viaduct construction method and viaduct construction equipment
KR100699022B1 (en) A railroad bridge repair method used low and longer girder
JP7453837B2 (en) Reinforcement structure and reinforcement construction method for concrete structures
JP6395056B2 (en) How to make precast concrete slabs
JP2005232922A (en) Track concrete slab board of tramcar and its construction method
JP4098581B2 (en) Overpass bridge construction method
JP7003376B2 (en) Construction method of structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20201124

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20211027

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20211102

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20211227

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220126

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220203

R150 Certificate of patent or registration of utility model

Ref document number: 7020978

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150