JP6974233B2 - Floor slab replacement method and floor slab replacement device - Google Patents

Floor slab replacement method and floor slab replacement device Download PDF

Info

Publication number
JP6974233B2
JP6974233B2 JP2018063780A JP2018063780A JP6974233B2 JP 6974233 B2 JP6974233 B2 JP 6974233B2 JP 2018063780 A JP2018063780 A JP 2018063780A JP 2018063780 A JP2018063780 A JP 2018063780A JP 6974233 B2 JP6974233 B2 JP 6974233B2
Authority
JP
Japan
Prior art keywords
floor slab
deck
existing
bridge axis
suspension device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2018063780A
Other languages
Japanese (ja)
Other versions
JP2019173435A (en
Inventor
祐輔 高井
名右衛門 宇野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IHI Infrastructure Systems Co Ltd
Original Assignee
IHI Infrastructure Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IHI Infrastructure Systems Co Ltd filed Critical IHI Infrastructure Systems Co Ltd
Priority to JP2018063780A priority Critical patent/JP6974233B2/en
Publication of JP2019173435A publication Critical patent/JP2019173435A/en
Application granted granted Critical
Publication of JP6974233B2 publication Critical patent/JP6974233B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、既設の床版を撤去して新たな床版を架設する床版取替方法及び床版取替装置に関するものである。 The present invention relates to a floor slab replacement method and a floor slab replacement device for removing an existing floor slab and installing a new floor slab.

従来、一般道や高速道路等の橋梁において、既設の床版が老朽化した場合は、当該床版を主桁上から撤去して新たな床版を再構築する床版取替施工が行われる。この場合、新たな床版は、工場で製作されたコンクリート製のプレキャスト床版を橋軸方向に複数枚配列して設置することにより構築される(例えば、特許文献1参照。)。 Conventionally, when an existing deck is deteriorated in a bridge such as a general road or a highway, the deck is replaced by removing the deck from the main girder and reconstructing a new deck. .. In this case, the new deck is constructed by arranging and installing a plurality of factory-made concrete precast decks in the direction of the bridge axis (see, for example, Patent Document 1).

以下、従来の床版取替方法について、図45乃至図51を参照して説明する。同図に示す橋梁では、図45に示すように道路の幅員方向に互いに間隔をおいて配置された複数の主桁2上に既設床版1が設置されており、各主桁2間には横桁及び対傾構3が設けられている。尚、本従来例では合成桁の場合を示す。 Hereinafter, the conventional floor slab replacement method will be described with reference to FIGS. 45 to 51. In the bridge shown in the figure, as shown in FIG. 45, existing floor slabs 1 are installed on a plurality of main girders 2 arranged at intervals in the width direction of the road, and between the main girders 2. A cross girder and an anti-tilt structure 3 are provided. In this conventional example, the case of a composite girder is shown.

まず、図46に示すように既設床版1の下方に足場Bを仮設する。次に、撤去する床版1を橋軸直角方向に切断するとともに、床版1を複数の切断位置で橋軸方向に切断する。この場合、合成桁橋では、床版コンクリートが主断面に含まれ、床版1と主桁2がスタッド(図示せず)によって強固に結合されているため、図47に示すように各主桁2の上フランジ両端部から100mm程度離れた位置Cで橋軸方向に切断する。 First, as shown in FIG. 46, a scaffold B is temporarily installed below the existing floor slab 1. Next, the deck 1 to be removed is cut in the direction perpendicular to the bridge axis, and the deck 1 is cut in the bridge axis direction at a plurality of cutting positions. In this case, in the synthetic girder bridge, the deck concrete is included in the main cross section, and the deck 1 and the main girder 2 are firmly connected by studs (not shown), so that each main girder is as shown in FIG. 47. Cut in the bridge axis direction at position C about 100 mm away from both ends of the upper flange of 2.

次に、切断された床版コンクリート1aを移動式クレーンによって吊り上げて撤去する。この場合、ジャッキを用いた周知の床版剥離装置(図示せず)によって床版コンクリート1aの切断部分を完全に分離する。その際、図48に示すように切断された床版コンクリート1aが主桁2上の床版コンクリート1bから分離して取り外される。 Next, the cut deck concrete 1a is lifted and removed by a mobile crane. In this case, the cut portion of the deck concrete 1a is completely separated by a well-known deck peeling device (not shown) using a jack. At that time, as shown in FIG. 48, the cut deck concrete 1a is separated from the deck concrete 1b on the main girder 2 and removed.

続いて、図49に示すように、主桁2上に残存する床版コンクリート1bを大型ブレーカまたはハンドブレーカ等の破砕機Dを用いて破砕した後、図50に示すように、主桁2、横桁及び対傾構3を補強する補強工Eを足場B内で行うとともに、主桁2の上フランジ上に新設床版と結合するための新たなスタッド(図示せず)を取り付ける。 Subsequently, as shown in FIG. 49, the deck concrete 1b remaining on the main girder 2 is crushed by using a crusher D such as a large breaker or a hand breaker, and then, as shown in FIG. 50, the main girder 2 and Reinforcing work E to reinforce the cross girder and anti-tilt structure 3 is performed in the scaffold B, and a new stud (not shown) for connecting to the new floor slab is attached on the upper flange of the main girder 2.

既設の床版1を撤去した後は、新設するプレキャスト床版4を橋軸方向に複数枚配列して設置する。この場合、図51に示すように既に設置されたプレキャスト床版4上にクレーン車Fを設置し、プレキャスト床版4を主桁2上に順次配列することにより新設床版を構築する。尚、撤去前の既設床版1上にクレーン車Fを設置し、床版取替を施工する場合もある。 After removing the existing floor slab 1, a plurality of newly installed precast floor slabs 4 are arranged and installed in the direction of the bridge axis. In this case, as shown in FIG. 51, the crane vehicle F is installed on the precast deck 4 already installed, and the precast deck 4 is sequentially arranged on the main girder 2 to construct a new deck. In some cases, the crane vehicle F may be installed on the existing floor slab 1 before removal to replace the floor slab.

特開2009−264040号公報Japanese Unexamined Patent Publication No. 2009-264040

しかしながら、前述のように既設床版の撤去及び新設床版の架設にクレーン車を用いる施工方法では、施工現場の上方に位置する交差道路や高圧電線によって上空制約がある場合や、供用中の隣接道路や近隣構造物により桁上でのクレーンの旋回や地上からのクレーン作業に制約がある場合、或いは既設橋梁の耐荷力が大型重機に対応していない場合には、大型のクレーン車を使用することができないという問題点があった。 However, as mentioned above, in the construction method using a mobile crane to remove the existing floor slab and erection of the new floor slab, there are cases where there are sky restrictions due to the crossing road or high-pressure electric wire located above the construction site, or the adjacent in service. Use a large mobile crane if there are restrictions on the turning of the crane on the girder or crane work from the ground due to roads or neighboring structures, or if the load capacity of the existing bridge is not compatible with large heavy machinery. There was a problem that it could not be done.

本発明は前記問題点に鑑みてなされたものであり、その目的とするところは、施工現場における上方または道路幅方向の作業スペースによる制約や既設橋梁の耐荷力による重量の制約を受けることがなく、クレーン車を用いずに効率よく作業を行うことのできる床版取替方法及び床版取替装置を提供することにある。 The present invention has been made in view of the above problems, and an object of the present invention is not restricted by a work space above or in the width direction of a road at a construction site or by weight due to the load bearing capacity of an existing bridge. It is an object of the present invention to provide a deck slab replacement method and a deck slab replacement device capable of efficiently performing work without using a mobile crane.

本発明は前記目的を達成するために、床版取替区間の既設床版を主桁上から撤去し、新たなプレキャスト床版を主桁上に設置する床版取替方法において、前記床版取替区間の既設床版を橋軸方向複数箇所で橋軸直角方向に切断し、既設床版上に敷設した軌条に沿って橋軸方向に移動可能な門型の吊り装置及び搬送台車を用い、切断された既設床版を吊り装置によって吊り上げて搬送台車に載置し、既設床版を載置した搬送台車を所定の場所まで搬送するとともに、次に既設床版を撤去する床版撤去位置の軌条を既設床版上から取り除き、吊り装置を橋軸方向の次の床版撤去位置に移動して既設床版の前記撤去を床版取替区間の橋軸方向一端から他端まで順次行うことにより、床版取替区間の既設床版を主桁上から撤去した後、前記既設床版が撤去された主桁上に敷設した軌条に沿って橋軸方向に移動可能な門型の吊り装置及び搬送台車を用い、新設用のプレキャスト床版を所定の場所で搬送台車に載置して吊り装置まで搬送し、搬送されたプレキャスト床版を吊り装置によって吊り上げて主桁上に設置し、次にプレキャスト床版を設置する床版設置位置の軌条を主桁上から取り除き、吊り装置を橋軸方向の次の床版設置位置に移動してプレキャスト床版の前記設置を床版取替区間の橋軸方向一端から他端まで順次行うことにより、床版取替区間に新たなプレキャスト床版を設置するようにしている。 The present invention is a floor slab replacement method in which an existing floor slab in a floor slab replacement section is removed from the main girder and a new precast floor slab is installed on the main girder in order to achieve the above object. The existing deck of the replacement section is cut at multiple points in the direction of the bridge axis in the direction perpendicular to the bridge axis, and a gate-shaped suspension device and a carrier that can move in the direction of the bridge axis along the rails laid on the existing deck are used. , The cut existing deck is lifted by a hanging device and placed on the transport trolley, the transport trolley on which the existing floor slab is placed is transported to a predetermined place, and then the existing deck is removed. Remove the rail from the existing deck, move the suspension device to the next deck removal position in the direction of the bridge axis, and perform the removal of the existing deck sequentially from one end to the other end of the deck replacement section in the bridge axis direction. As a result, after removing the existing deck in the deck replacement section from the main girder, a gate-shaped suspension that can move in the direction of the bridge axis along the rail laid on the main girder from which the existing deck was removed. Using the equipment and the transport trolley, the precast deck for new installation is placed on the transport trolley at a predetermined place and transported to the suspension device, and the transported precast deck is lifted by the suspension device and installed on the main girder. Next, remove the rail at the deck installation position where the precast deck is installed from the main girder, move the suspension device to the next deck installation position in the direction of the bridge axis, and replace the precast deck with the deck replacement section. A new precast deck is installed in the deck replacement section by sequentially performing from one end to the other end in the bridge axis direction.

また、本発明は前記目的を達成するために、床版取替区間の既設床版を主桁上から撤去し、新たなプレキャスト床版を主桁上に設置する床版取替装置において、前記既設床版上に敷設される軌条と、軌条に沿って橋軸方向に移動可能な門型の吊り装置及び搬送台車とを備え、橋軸方向複数箇所で橋軸直角方向に切断された床版取替区間の既設床版を吊り装置によって吊り上げるとともに、吊り上げた既設床版を搬送台車に載置し、既設床版を載置した搬送台車を所定の場所まで搬送するとともに、既設床版上から軌条が取り除かれた次の床版撤去位置に吊り装置を移動して既設床版の前記撤去を床版取替区間の橋軸方向一端から他端まで順次行うことにより、床版取替区間の既設床版を主桁上から撤去するように構成するとともに、前記既設床版が撤去された主桁上に敷設される軌条と、軌条に沿って橋軸方向に移動可能な門型の吊り装置及び搬送台車を備え、新設用のプレキャスト床版を所定の場所で搬送台車に載置して吊り装置まで搬送し、搬送されたプレキャスト床版を吊り装置によって吊り上げて主桁上に設置し、主桁上から軌条が取り除かれた次の床版設置位置に吊り装置を移動してプレキャスト床版の前記設置を床版取替区間の橋軸方向一端から他端まで順次行うことにより、床版取替区間に新たなプレキャスト床版を設置するように構成している。 Further, in order to achieve the above object, the present invention is a floor slab replacement device in which an existing floor slab in a floor slab replacement section is removed from the main girder and a new precast floor slab is installed on the main girder. A deck laid on an existing deck, a gate-shaped suspension device and a transport cart that can move in the direction of the bridge axis along the deck, and a deck cut in the direction perpendicular to the bridge axis at multiple points in the bridge axis direction. The existing floor slab in the replacement section is lifted by a lifting device, the lifted existing floor slab is placed on the transport trolley, the transport trolley on which the existing floor slab is placed is transported to a predetermined place, and from the existing floor slab. By moving the suspension device to the next deck removal position where the deck has been removed and performing the removal of the existing deck sequentially from one end to the other end in the bridge axis direction of the deck replacement section, the deck replacement section The existing deck is configured to be removed from the main girder, and the rail laid on the main girder from which the existing deck has been removed, and a gate-shaped suspension device that can move in the direction of the bridge axis along the rail. And equipped with a transport trolley, the precast deck for new installation is placed on the transport trolley at a predetermined place and transported to the suspension device, and the transported precast deck is lifted by the suspension device and installed on the main girder. Deck removal by moving the suspension device to the next deck installation position where the girder has been removed and performing the installation of the precast deck from one end to the other end in the bridge axis direction of the deck replacement section. It is configured to install a new precast deck in the replacement section.

これにより、橋軸方向に移動可能な門型の吊り装置及び搬送台車によって既設床版の撤去及び新たなプレキャスト床版の設置が行われることから、クレーン車を用いずに作業を行うことができる。 As a result, the existing deck can be removed and a new precast deck can be installed by using a gate-shaped suspension device and a transport cart that can move in the direction of the bridge axis, so that work can be performed without using a crane truck. ..

本発明によれば、クレーン車を用いずに床版の撤去作業及び新設作業を行うことができるので、施工現場の上方に位置する交差道路や高圧電線によって上空制約がある場合や、供用中の隣接道路や近隣構造物による道路幅方向の作業スペースに制約がある場合、或いは既設橋梁の耐荷力による重量の制約がある場合でも、これらの制約を受けることなく床版の取替施工を行うことができる。 According to the present invention, the floor slab can be removed and newly installed without using a crane vehicle. Even if there are restrictions on the work space in the width direction of the road due to adjacent roads or structures, or if there are restrictions on the weight due to the load capacity of the existing bridge, the deck replacement work should be carried out without these restrictions. Can be done.

本発明の一実施形態を示す床版取替装置の第1の吊り装置の側面図A side view of the first suspension device of the floor slab replacement device showing an embodiment of the present invention. 第1の吊り装置の平面図Top view of the first suspension device 第1の吊り装置の正面図Front view of the first suspension device 第1の吊り装置の正面図Front view of the first suspension device 第2の吊り装置の側面図Side view of the second suspension device 第2の吊り装置の平面図Top view of the second suspension device 第2の吊り装置の正面図Front view of the second suspension device 搬送台車の側面図Side view of the transport trolley 搬送台車の平面図Top view of the transport trolley 搬送台車の正面図Front view of the transport trolley 床版撤去工程を示す橋梁の側面図Side view of the bridge showing the deck removal process 床版撤去工程を示す橋梁の側面図Side view of the bridge showing the deck removal process 床版撤去工程を示す橋梁の側面図Side view of the bridge showing the deck removal process 床版撤去工程を示す橋梁の平面図Floor plan of the bridge showing the deck removal process 床版撤去工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the floor slab removal process 床版撤去工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the floor slab removal process 床版撤去工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the floor slab removal process 床版撤去工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the floor slab removal process 床版撤去工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the floor slab removal process 床版撤去工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the floor slab removal process 床版撤去工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the floor slab removal process 床版撤去工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the floor slab removal process 床版撤去工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the floor slab removal process 床版撤去工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the floor slab removal process 床版撤去工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the floor slab removal process 床版新設工程を示す橋梁の側面図Side view of the bridge showing the new floor slab construction process 床版新設工程を示す橋梁の側面図Side view of the bridge showing the new floor slab construction process 床版新設工程を示す橋梁の側面図Side view of the bridge showing the new floor slab construction process 床版新設工程を示す橋梁の側面図Side view of the bridge showing the new floor slab construction process 床版新設工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the new floor slab installation process 床版新設工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the new floor slab installation process 床版新設工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the new floor slab installation process 床版新設工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the new floor slab installation process 床版新設工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the new floor slab installation process 床版新設工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the new floor slab installation process 床版新設工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the new floor slab installation process 床版新設工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the new floor slab installation process 床版新設工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the new floor slab installation process 床版新設工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the new floor slab installation process 床版新設工程を示す床版取替装置の側面図Side view of the floor slab replacement device showing the new floor slab installation process 床版新設工程を示す橋梁の側面図Side view of the bridge showing the new floor slab construction process 床版新設工程を示す橋梁の平面図Floor plan of the bridge showing the new floor slab construction process 床版撤去工程を示すフローチャートFlow chart showing the floor slab removal process 床版新設工程を示すフローチャートFlow chart showing the new floor slab installation process 従来の床版取替工程を示す正面図Front view showing the conventional floor slab replacement process 床版取替工程を示す正面図Front view showing the floor slab replacement process 床版取替工程を示す正面図Front view showing the floor slab replacement process 床版取替工程を示す正面図Front view showing the floor slab replacement process 床版取替工程を示す正面図Front view showing the floor slab replacement process 床版取替工程を示す正面図Front view showing the floor slab replacement process 床版取替工程を示す正面図Front view showing the floor slab replacement process

図1乃至図44は本発明の一実施形態を示すもので、橋梁から既設の床版を撤去して新たな床版を架設する床版取替方法及び床版取替装置を示すものである。尚、図1、図5、図8、図15〜図25、図30〜図40は、床版取替装置を図2のA−A線矢視方向から見た側面図である。 1 to 44 show an embodiment of the present invention, and show a deck replacement method and a deck replacement device for removing an existing deck from a bridge and installing a new deck. .. 1, FIG. 5, FIG. 8, FIGS. 15 to 25, and FIGS. 30 to 40 are side views of the floor slab replacement device as viewed from the direction of arrow AA in FIG.

同図に示す橋梁10は、橋軸方向に間隔をおいて配置された複数の橋脚11と、橋脚11に支持された主桁12と、主桁12上に架設された既設床版13とからなり、本実施形態では、既設床版13を複数に切断して撤去し、新たなプレキャスト床版14に取り替える。 The bridge 10 shown in the figure is composed of a plurality of piers 11 arranged at intervals in the direction of the bridge axis, a main girder 12 supported by the pier 11, and an existing deck 13 erected on the main girder 12. Therefore, in the present embodiment, the existing floor slab 13 is cut into a plurality of pieces, removed, and replaced with a new precast floor slab 14.

本実施形態の床版取替装置は、既設床版13またはプレキャスト床版14の吊り上げ及び吊り降ろしを行う門型の第1及び第2の吊り装置20,30と、第1の吊り装置20と第2の吊り装置30との間で床版13,14の搬送を行う搬送台車40とを備え、第1の吊り装置20及び搬送台車40は軌条50に沿って橋軸方向に移動するようになっている。 The floor slab replacement device of the present embodiment includes the gate-type first and second hanging devices 20 and 30 for lifting and lowering the existing floor slab 13 or the precast floor slab 14, and the first lifting device 20. A transport trolley 40 for transporting the floor slabs 13 and 14 to and from the second suspension device 30 is provided, and the first suspension device 20 and the transport trolley 40 move in the bridge axis direction along the rail 50. It has become.

第1の吊り装置20は、橋軸方向に延びる左右一対の第1のフレーム21と、各第1のフレーム21の橋軸方向一端側及び他端側からそれぞれ下方に延びる左右一対の第2のフレーム22と、橋軸方向に延びる左右一対の第1のガイドレール23と、第1のガイドレール23に沿って橋軸方向に移動する環状の第2のガイドレール24と、第2のガイドレール24に沿って回動する吊り天秤25と、軌条50に係合して走行する複数の自走式の走行ユニット26とから構成されている。 The first suspension device 20 includes a pair of left and right first frames 21 extending in the bridge axis direction, and a pair of left and right second frames extending downward from one end side and the other end side of each first frame 21 in the bridge axis direction. The frame 22, a pair of left and right first guide rails 23 extending in the bridge axis direction, an annular second guide rail 24 moving in the bridge axis direction along the first guide rail 23, and a second guide rail. It is composed of a suspension balance 25 that rotates along 24 and a plurality of self-propelled traveling units 26 that travel by engaging with the rail 50.

各第1のフレーム21は、両端側が各第2のフレーム22よりも橋軸方向に長く延出した片持ち梁状に形成され、橋軸直角方向に延びる複数の横梁21aによって互いに連結されている。 Each first frame 21 is formed in a cantilever shape having both ends extending longer in the bridge axis direction than each second frame 22, and is connected to each other by a plurality of cross beams 21a extending in the direction perpendicular to the bridge axis. ..

各第2のフレーム22は、上端を第1のフレーム21に連結され、下端側を橋軸方向に延びる複数の横梁22aによって互いに連結されている。 The upper end of each second frame 22 is connected to the first frame 21, and the lower end side is connected to each other by a plurality of cross beams 22a extending in the bridge axis direction.

各第1のガイドレール23は、第1のフレーム21よりもやや長く形成され、各第1のガイドレール23の各横梁21aに固定されている。 Each first guide rail 23 is formed slightly longer than the first frame 21, and is fixed to each cross beam 21a of each first guide rail 23.

第2のガイドレール24は周方向4箇所をそれぞれ支持機構24aを介して各第1のガイドレール23に連結されており、各支持機構24aによって各第1のガイドレール23の一端側から他端側まで移動するようになっている。各支持機構24aとしては、例えば周知の電動トロリを用いることができる。 The second guide rail 24 is connected to each first guide rail 23 via a support mechanism 24a at four points in the circumferential direction, and each support mechanism 24a connects one end side to the other end of each first guide rail 23. It is designed to move to the side. As each support mechanism 24a, for example, a well-known electric trolley can be used.

吊り天秤25は水平方向に直線状に延びるように形成され、長手方向2箇所をそれぞれ支持機構25aを介して第2のガイドレール24に連結されており、各支持機構25aによって第2のガイドレール24の周方向に回動するようになっている。各支持機構25aとしては、例えば周知のギヤードトロリを用いることができる。また、吊り天秤25には複数の吊り下げ部材25bが互いに吊り天秤25の長手方向に間隔をおいて設けられ、各吊り下げ部材25bによって床版13,14を吊り下げるようになっている。各吊り下げ部材25bとしては、例えば周知の手動チェーンブロックを用いることができる。 The suspension balance 25 is formed so as to extend linearly in the horizontal direction, and two points in the longitudinal direction are connected to the second guide rail 24 via the support mechanism 25a, respectively, and the second guide rail is connected by each support mechanism 25a. It is designed to rotate in the circumferential direction of 24. As each support mechanism 25a, for example, a well-known geared trolley can be used. Further, the suspension balance 25 is provided with a plurality of suspension members 25b at intervals in the longitudinal direction of the suspension balance 25, and the floor slabs 13 and 14 are suspended by the suspension members 25b. As each suspension member 25b, for example, a well-known manual chain block can be used.

各走行ユニット26は、それぞれ各第2のフレーム22の下端に設けられている。走行ユニット26には前後一対の車輪26aが設けられ、各車輪26aは図示しないモータによって駆動されるようになっている。 Each traveling unit 26 is provided at the lower end of each second frame 22. The traveling unit 26 is provided with a pair of front and rear wheels 26a, and each wheel 26a is driven by a motor (not shown).

第2の吊り装置30は、橋軸方向に延びる左右一対の第1のフレーム31と、各第1のフレーム31の橋軸方向一端側及び他端側からそれぞれ下方に延びる左右一対の第2のフレーム32と、橋軸方向に延びる吊り天秤33とから構成されている。 The second suspension device 30 includes a pair of left and right first frames 31 extending in the bridge axis direction, and a pair of left and right second frames extending downward from one end side and the other end side of each first frame 31 in the bridge axis direction. It is composed of a frame 32 and a suspension balance 33 extending in the direction of the bridge axis.

各第1のフレーム31は、両端側がほぼ各第2のフレーム32の上端に位置するように形成され、橋軸直角方向に延びる複数の横梁31aによって互いに連結されている。 Each of the first frames 31 is formed so that both ends thereof are located substantially at the upper ends of the second frames 32, and is connected to each other by a plurality of cross beams 31a extending in the direction perpendicular to the bridge axis.

各第2のフレーム32は、上端を第1のフレーム31に連結され、下端側を橋軸方向に延びる複数の横梁32aによって互いに連結されている。 The upper end of each second frame 32 is connected to the first frame 31, and the lower end side is connected to each other by a plurality of cross beams 32a extending in the bridge axis direction.

吊り天秤33は水平方向に直線状に延びるように形成され、第1のフレーム31の各横梁31aに橋軸直角方向中央に位置するように固定されている。吊り天秤33には複数の吊り下げ部材33aが互いに吊り天秤33の長手方向に間隔をおいて設けられ、各吊り下げ部材33aによって床版13,14を吊り下げるようになっている。各吊り下げ部材33aとしては、例えば周知の手動チェーンブロックを用いることができる。 The suspension balance 33 is formed so as to extend linearly in the horizontal direction, and is fixed to each cross beam 31a of the first frame 31 so as to be located at the center in the direction perpendicular to the bridge axis. A plurality of suspension members 33a are provided on the suspension balance 33 at intervals in the longitudinal direction of the suspension balance 33, and the floor slabs 13 and 14 are suspended by the suspension members 33a. As each suspension member 33a, for example, a well-known manual chain block can be used.

搬送台車40は、橋軸方向に延びる左右一対の第1のフレーム41と、橋軸直角方向に延びる前後一対の第2のフレーム42と、軌条50に係合して走行する複数の自走式の走行ユニット43とから構成されている。 The transport carriage 40 is a plurality of self-propelled type traveling by engaging with a pair of left and right first frames 41 extending in the direction of the bridge axis, a pair of front and rear second frames 42 extending in the direction perpendicular to the bridge axis, and a rail 50. It is composed of the traveling unit 43 of the above.

各第1のフレーム41は、両端側が各第2のフレーム42よりも橋軸方向に長く延出するように形成され、互いに床版13,14の橋軸方向の長さLよりも短い間隔をおいて配置されている。 Each of the first frames 41 is formed so that both ends extend longer in the bridge axis direction than each second frame 42, and the intervals are shorter than the length L of the decks 13 and 14 in the bridge axis direction. It is placed in place.

各第2のフレーム42は、橋軸直角方向中央側が両端側よりも下方に位置するように屈曲しており、橋軸直角方向中央側に各第1のフレーム41が固定されている。 Each second frame 42 is bent so that the center side in the direction perpendicular to the bridge axis is located below both ends, and each first frame 41 is fixed to the center side in the direction perpendicular to the bridge axis.

各走行ユニット43は、それぞれ各第2のフレーム42の両端に設けられている。走行ユニット43には前後一対の車輪43aが設けられ、各車輪43aは図示しないモータによって駆動されるようになっている。 Each traveling unit 43 is provided at both ends of each second frame 42. The traveling unit 43 is provided with a pair of front and rear wheels 43a, and each wheel 43a is driven by a motor (not shown).

軌条50は、互いに橋軸直角方向に間隔をおいて配置されるレール51と、上端にレール51が固定された固定部材52とを有し、レール51及び固定部材52は既設床版13上または既設床版13が除去された主桁12上に互いに橋軸直角方向に間隔をおいて一対ずつ配置されるようになっている。軌条50は、床版13,14の橋軸方向の長さLの2倍の長さ2Lに形成されたレール51及び固定部材52が橋軸方向に連結されるようになっている。この場合、左右のレール51及び固定部材52は橋軸直角方向両端の主桁12と等しい間隔で配置され、左右の固定部材52は互いに複数の補強部材53を介して連結されている。また、軌条50を既設床版13が除去された主桁12上に設置する場合は、固定部材52と主桁12との間に床版13と等しい高さの枕木材54が配置される。 The rail 50 has a rail 51 arranged at right angles to each other in the direction perpendicular to the bridge axis, and a fixing member 52 to which the rail 51 is fixed at the upper end, and the rail 51 and the fixing member 52 are on the existing deck 13 or. A pair of existing floor slabs 13 are arranged on the main girder 12 from which the existing deck 13 has been removed at right angles to each other in the direction perpendicular to the bridge axis. The rail 50 is configured such that a rail 51 and a fixing member 52 formed in a length 2L that is twice the length L in the bridge axial direction of the decks 13 and 14 are connected in the bridge axial direction. In this case, the left and right rails 51 and the fixing members 52 are arranged at equal intervals with the main girders 12 at both ends in the direction perpendicular to the bridge axis, and the left and right fixing members 52 are connected to each other via a plurality of reinforcing members 53. Further, when the rail 50 is installed on the main girder 12 from which the existing floor slab 13 has been removed, a pillow wood 54 having a height equal to that of the floor slab 13 is arranged between the fixing member 52 and the main girder 12.

次に、本実施形態の床版取替装置を用いた床版取替方法について、図11乃至図42を参照して説明する。ここでは、図11に示すように橋梁10の床版取替区間Nにおける既設床版13を撤去して新たなプレキャスト床版14を新設する場合を示す。尚、本実施形態では、床版13と主桁12がスタッド(図示せず)によって結合された合成桁において既設床版13を撤去する場合を示す。 Next, a floor slab replacement method using the floor slab replacement device of the present embodiment will be described with reference to FIGS. 11 to 42. Here, as shown in FIG. 11, a case is shown in which the existing deck 13 in the deck replacement section N of the bridge 10 is removed and a new precast deck 14 is newly installed. In this embodiment, the case where the existing floor slab 13 is removed in the synthetic girder in which the floor slab 13 and the main girder 12 are connected by a stud (not shown) is shown.

まず、図12に示すように、撤去する床版13を切断後の橋軸方向の長さがLとなるように橋軸方向の複数の位置Cで橋軸直角方向に切断する。尚、床版13の橋軸方向の長さLは橋軸直角方向の長さWよりも十分に短いものとする。 First, as shown in FIG. 12, the deck 13 to be removed is cut in the direction perpendicular to the bridge axis at a plurality of positions C in the bridge axis direction so that the length in the bridge axis direction after cutting is L. It is assumed that the length L in the bridge axis direction of the deck 13 is sufficiently shorter than the length W in the direction perpendicular to the bridge axis.

次に、図13及び図14に示すように、橋軸直角方向に切断された既設床版13上に軌条50を敷設する。その際、床版取替区間Nの一端側の2枚の既設床版13を除いた位置から床版取替区間Nの他端側及び床版取替区間外の既設床版13上に亘って軌条50を敷設する。尚、床版取替区間外は既に床版取替施工が完了した新設床版上であってもよい。 Next, as shown in FIGS. 13 and 14, the rail 50 is laid on the existing deck 13 cut in the direction perpendicular to the bridge axis. At that time, from the position excluding the two existing floor slabs 13 on one end side of the floor slab replacement section N to the other end side of the floor slab replacement section N and on the existing floor slab 13 outside the floor slab replacement section. The rail 50 is laid. The area outside the floor slab replacement section may be on a newly installed floor slab for which the floor slab replacement work has already been completed.

続いて、図15に示すように、第1の吊り装置20、第2の吊り装置30及び搬送台車40を配置する。第1の吊り装置20は軌条50上を走行可能に配置され、床版取替区間Nの一端側に位置している。第2の吊り装置30は床版取替区間外の既設床版13上に配置され、各第2のフレーム32が軌条50の外側に位置するように設置される。搬送台車40は軌条50上を走行可能に配置され、第1の吊り装置20と第2の吊り装置30との間を往復移動するようになっている。 Subsequently, as shown in FIG. 15, the first suspension device 20, the second suspension device 30, and the transport carriage 40 are arranged. The first suspension device 20 is arranged so as to be able to travel on the rail 50, and is located on one end side of the deck replacement section N. The second suspension device 30 is arranged on the existing deck 13 outside the deck replacement section, and each second frame 32 is installed so as to be located outside the rail 50. The transport carriage 40 is arranged so as to be able to travel on the rail 50, and is adapted to reciprocate between the first suspension device 20 and the second suspension device 30.

次に、既設床版13を撤去する工程を説明する。まず、床版取替区間Nの最も一端側に位置する既設床版13と主桁12との間のコンクリートをスタッドごとワイヤーソー等を用いて切断する。 Next, the process of removing the existing floor slab 13 will be described. First, the concrete between the existing deck 13 located on the most end side of the deck replacement section N and the main girder 12 is cut together with the stud using a wire saw or the like.

続いて、図16に示すように、第1の吊り装置20の吊り天秤25を第1の吊り装置20の一端側に位置させるとともに、各吊り下げ部材25bを床版取替区間Nの最も一端側に位置する既設床版13にロープ25cを介して連結し、図17に示すように各吊り下げ部材25bによって既設床版13を吊り上げる。その際、吊り天秤25の向きは長手方向が橋軸直角方向となっている。また、搬送台車40は第1の吊り装置20の他端側に位置している。 Subsequently, as shown in FIG. 16, the suspension balance 25 of the first suspension device 20 is positioned on one end side of the first suspension device 20, and each suspension member 25b is placed at one end of the floor slab replacement section N. The existing floor slab 13 is connected to the existing floor slab 13 located on the side via a rope 25c, and the existing floor slab 13 is lifted by each hanging member 25b as shown in FIG. At that time, the direction of the suspension balance 25 is such that the longitudinal direction is perpendicular to the bridge axis. Further, the transport carriage 40 is located on the other end side of the first suspension device 20.

次に、図18に示すように、吊り天秤25及び既設床版13の長手方向の向きが橋軸直角方向となるように第1の吊り装置20の吊り天秤25を90度回転させ、図19に示すように第2のガイドレール24によって吊り天秤25及び既設床版13を第1の吊り装置20の他端側に移動する。 Next, as shown in FIG. 18, the suspension balance 25 of the first suspension device 20 is rotated 90 degrees so that the longitudinal orientation of the suspension balance 25 and the existing deck 13 is perpendicular to the bridge axis, and FIG. 19 As shown in the above, the suspension balance 25 and the existing deck 13 are moved to the other end side of the first suspension device 20 by the second guide rail 24.

この後、図20に示すように吊り天秤25から既設床版13を搬送台車40上に吊り降ろし、図21に示すように既設床版13を載せた搬送台車40を第2の吊り装置30まで移動する。 After that, as shown in FIG. 20, the existing floor slab 13 is suspended from the suspension balance 25 onto the transport trolley 40, and as shown in FIG. 21, the transport trolley 40 on which the existing floor slab 13 is mounted is moved to the second suspension device 30. Moving.

続いて、図22に示すように第2の吊り装置30の吊り天秤33の各吊り下げ部材33aによって既設床版13を吊り上げた後、搬送台車40を第1の吊り装置20の他端側まで移動する。その際、第1の吊り装置20を既設床版13の1つ分の長さLだけ床版取替区間Nの他端側に向かって移動するとともに、吊り天秤25を第1の吊り装置20の一端側まで移動する。 Subsequently, as shown in FIG. 22, after the existing floor slab 13 is lifted by each hanging member 33a of the hanging balance 33 of the second hanging device 30, the transport carriage 40 is moved to the other end side of the first hanging device 20. Moving. At that time, the first suspension device 20 is moved toward the other end side of the floor slab replacement section N by the length L of one of the existing floor slabs 13, and the suspension balance 25 is moved to the first suspension device 20. Move to one end side of.

次に、図23に示すように、第2の吊り装置30の内側に乗り入れた運搬車両60(トラック)に吊り天秤33から既設床版13を吊り降ろし、運搬車両60によって既設床版13を外部に搬出する。また、第1の吊り装置20の吊り天秤25を長手方向の向きが橋軸方向となるように90度回転させる。 Next, as shown in FIG. 23, the existing floor slab 13 is suspended from the suspension balance 33 on the transport vehicle 60 (truck) that has entered the inside of the second suspension device 30, and the existing floor slab 13 is externally mounted by the transport vehicle 60. Carry out to. Further, the suspension balance 25 of the first suspension device 20 is rotated by 90 degrees so that the direction in the longitudinal direction is the bridge axis direction.

この後、次の既設床版13と主桁12との間のコンクリートをスタッドごと前述と同様にワイヤーソー等を用いて切断し、図24に示すように第1の吊り装置20の各吊り下げ部材25bによって次の既設床版13を吊り上げる。前述と同様の工程により2枚目の既設床版13を撤去した後、図25に示すように第1の吊り装置20を既設床版13の1つ分の長さLだけ床版取替区間Nの他端側に向かって移動するとともに、軌条50のレール51及び固定部材52を1つ分だけ取り除く。即ち、既設床版13を2枚撤去するごとにレール51及び固定部材52を1つずつ取り除く工程を繰り返しながら第1の吊り装置20を順次移動させることにより、図26に示すように床版取替区間Nの既設床版13を全て撤去する。 After that, the concrete between the next existing floor slab 13 and the main girder 12 is cut together with the stud using a wire saw or the like in the same manner as described above, and each suspension of the first suspension device 20 is suspended as shown in FIG. 24. The next existing floor slab 13 is lifted by the member 25b. After removing the second existing floor slab 13 by the same process as described above, as shown in FIG. 25, the first suspension device 20 is used in the floor slab replacement section by the length L of one of the existing floor slabs 13. While moving toward the other end side of N, the rail 51 and the fixing member 52 of the rail 50 are removed by one. That is, as shown in FIG. 26, the first hanging device 20 is sequentially moved while repeating the step of removing the rail 51 and the fixing member 52 one by one every time two existing floor slabs 13 are removed. All the existing floor slabs 13 in the replacement section N are removed.

次に、既設床版13が全て撤去された床版取替区間Nの主桁12上に新たなプレキャスト床版14を設置する工程を説明する。プレキャスト床版14は、主桁12上に設置された際の橋軸方向の長さLが橋軸直角方向の長さWよりも短い長さに形成されている。
まず、図27に示すように主桁12上に枕木材54を設置し、図28及び図29に示すように枕木材54の上に軌条50を敷設する。その際、軌条50は新設するプレキャスト床版14の2枚分の長さ2Lだけ床版取替区間Nの一端側からスペースを空けて設置される。
Next, a process of installing a new precast deck 14 on the main girder 12 of the deck replacement section N from which all the existing deck 13 has been removed will be described. The precast deck 14 is formed so that the length L in the bridge axis direction when installed on the main girder 12 is shorter than the length W in the direction perpendicular to the bridge axis.
First, the pillow wood 54 is installed on the main girder 12 as shown in FIG. 27, and the rail 50 is laid on the pillow wood 54 as shown in FIGS. 28 and 29. At that time, the rail 50 is installed with a space from one end side of the floor slab replacement section N by the length of 2 L for two newly installed precast floor slabs 14.

続いて、図30に示すように、第1の吊り装置20、第2の吊り装置30及び搬送台車40を配置する。第1の吊り装置20は軌条50上を走行可能に配置され、床版取替区間Nの一端側に位置している。第2の吊り装置30は床版取替区間外の既設床版13上に配置され、各第2のフレーム32が軌条50の外側に位置するように設置される。搬送台車40は軌条50上を走行可能に配置され、第1の吊り装置20と第2の吊り装置30との間を移動するようになっている。 Subsequently, as shown in FIG. 30, the first suspension device 20, the second suspension device 30, and the transport carriage 40 are arranged. The first suspension device 20 is arranged so as to be able to travel on the rail 50, and is located on one end side of the deck replacement section N. The second suspension device 30 is arranged on the existing deck 13 outside the deck replacement section, and each second frame 32 is installed so as to be located outside the rail 50. The transport carriage 40 is arranged so as to be able to travel on the rail 50, and moves between the first suspension device 20 and the second suspension device 30.

次に、図31に示すように、第1の吊り装置20の吊り天秤25を第1の吊り装置20の他端側に位置させるとともに、第2の吊り装置30の内側に乗り入れた運搬車両60から吊り天秤33によってプレキャスト床版14を吊り上げる。 Next, as shown in FIG. 31, the transport vehicle 60 has the suspension balance 25 of the first suspension device 20 positioned on the other end side of the first suspension device 20 and has entered the inside of the second suspension device 30. The precast floor slab 14 is lifted by the hanging balance 33.

続いて、第2の吊り装置30から運搬車両60を退去させるとともに、図32に示すように、搬送台車40を第2の吊り装置30まで移動し、吊り天秤33からプレキャスト床版14を搬送台車40上に吊り降ろす。 Subsequently, the transport vehicle 60 is evacuated from the second suspension device 30, and the transport trolley 40 is moved to the second suspension device 30 as shown in FIG. 32, and the precast floor slab 14 is transferred from the suspension balance 33 to the transport trolley. Suspend on 40.

この後、図33に示すようにプレキャスト床版14を載せた搬送台車40を第2の吊り装置30から第1の吊り装置20の他端側まで移動し、第1の吊り装置20の吊り天秤25によって搬送台車40からプレキャスト床版14を吊り上げるとともに、プレキャスト床版14を吊り下げた吊り天秤25を第1の吊り装置20の一端側に移動する。また、第2の吊り装置30の内側に乗り入れた運搬車両60から吊り天秤33によって次のプレキャスト床版14を吊り上げる。 After that, as shown in FIG. 33, the transport trolley 40 on which the precast floor slab 14 is mounted is moved from the second suspension device 30 to the other end side of the first suspension device 20, and the suspension balance of the first suspension device 20. The precast floor slab 14 is lifted from the transport trolley 40 by the 25, and the suspension balance 25 on which the precast floor slab 14 is suspended is moved to one end side of the first lifting device 20. Further, the next precast deck 14 is lifted by the suspension balance 33 from the transport vehicle 60 that has entered the inside of the second suspension device 30.

次に、図34に示すように、吊り天秤25及びプレキャスト床版14の長手方向の向きが橋軸直角方向となるように第1の吊り装置20の吊り天秤25を90度回転させるとともに、搬送台車40を第1の吊り装置20から第2の吊り装置30まで移動する。 Next, as shown in FIG. 34, the suspension balance 25 of the first suspension device 20 is rotated 90 degrees and conveyed so that the longitudinal orientation of the suspension balance 25 and the precast deck 14 is the direction perpendicular to the bridge axis. The dolly 40 is moved from the first suspension device 20 to the second suspension device 30.

この後、図35に示すように、吊り天秤25からプレキャスト床版14を吊り降ろして床版取替区間Nの最も一端側の主桁12上に載置するとともに、第2の吊り装置30の吊り天秤33からプレキャスト床版14を搬送台車40上に吊り降ろす。また、第1の吊り装置20では、図36に示すようにプレキャスト床版14を吊り降ろした後の吊り天秤25を長手方向の向きが橋軸直角方向となるように90度回転させる。 After that, as shown in FIG. 35, the precast floor slab 14 is suspended from the suspension balance 25 and placed on the main girder 12 on the most end side of the floor slab replacement section N, and the second suspension device 30 is used. The precast floor slab 14 is hung from the suspension balance 33 onto the transport trolley 40. Further, in the first suspension device 20, as shown in FIG. 36, the suspension balance 25 after suspending the precast deck 14 is rotated by 90 degrees so that the direction in the longitudinal direction is perpendicular to the bridge axis.

続いて、図37に示すように、第1の吊り装置20を既設床版13の1つ分の長さLだけ床版取替区間Nの他端側に向かって移動するとともに、吊り天秤25を第1の吊り装置20の一端側まで移動し、次のプレキャスト床版14を載せた搬送台車40を第1の吊り装置20の他端側まで移動する。 Subsequently, as shown in FIG. 37, the first suspension device 20 is moved toward the other end side of the floor slab replacement section N by the length L of one of the existing floor slabs 13, and the suspension balance 25 is used. Is moved to one end side of the first suspension device 20, and the transport carriage 40 on which the next precast deck 14 is placed is moved to the other end side of the first suspension device 20.

この後、図38に示すように、第1の吊り装置20の吊り天秤25によって搬送台車40からプレキャスト床版14を吊り上げるとともに、プレキャスト床版14を吊り下げた吊り天秤25を第1の吊り装置20の一端側に移動する。また、第2の吊り装置30の内側に乗り入れた運搬車両60から吊り天秤33によって次のプレキャスト床版14を吊り上げる。 After that, as shown in FIG. 38, the precast deck 14 is lifted from the transport carriage 40 by the suspension balance 25 of the first suspension device 20, and the suspension balance 25 on which the precast deck 14 is suspended is lifted by the first suspension device. Move to one end side of 20. Further, the next precast deck 14 is lifted by the suspension balance 33 from the transport vehicle 60 that has entered the inside of the second suspension device 30.

次に、図39に示すように、吊り天秤25及びプレキャスト床版14の長手方向の向きが橋軸直角方向となるように第1の吊り装置20の吊り天秤25を90度回転させるとともに、吊り天秤25から2枚目のプレキャスト床版14を吊り降ろして主桁12上に載置する。また、第2の吊り装置30の吊り天秤33から次のプレキャスト床版14を搬送台車40上に吊り降ろす。 Next, as shown in FIG. 39, the suspension balance 25 of the first suspension device 20 is rotated 90 degrees and suspended so that the longitudinal orientation of the suspension balance 25 and the precast deck 14 is the direction perpendicular to the bridge axis. The second precast deck 14 is hung from the balance 25 and placed on the main girder 12. Further, the next precast deck 14 is suspended from the suspension balance 33 of the second suspension device 30 onto the transport carriage 40.

この後、図40に示すように第1の吊り装置20を既設床版13の1つ分の長さLだけ床版取替区間Nの他端側に向かって移動させるとともに、軌条50のレール51及び固定部材52を1つ分だけ取り除く。即ち、新たなプレキャスト床版14を2枚架設するごとにレール51及び固定部材52を1つずつ取り除く工程を繰り返しながら第1の吊り装置20を順次移動させることにより、図41及び図42に示すように床版取替区間Nの全体にプレキャスト床版14を新設する。 After that, as shown in FIG. 40, the first suspension device 20 is moved toward the other end side of the floor slab replacement section N by the length L of one of the existing floor slabs 13, and the rail of the rail 50. Remove only one 51 and one fixing member 52. That is, FIG. 41 and FIG. 42 show that the first suspension device 20 is sequentially moved while repeating the step of removing the rail 51 and the fixing member 52 one by one every time two new precast floor slabs 14 are erected. As described above, a precast floor slab 14 is newly installed in the entire floor slab replacement section N.

このように、本実施形態によれば、床版取替区間Nの既設床版13を橋軸方向の長さLが橋軸直角方向の長さWよりも短くなるように橋軸方向複数箇所で橋軸直角方向に切断し、既設床版13上を橋軸方向に移動可能な門型の第1の吊り装置20及び搬送台車40を用い、切断された既設床版13を第1の吊り装置20によって吊り上げるとともに、吊り上げた既設床版13を長手方向が橋軸方向となるように回転させて搬送台車40に載置し、既設床版13を載置した搬送台車40を所定の搬送場所まで搬送するとともに、第1の吊り装置20を次の床版撤去位置に移動して既設床版13の前記撤去を床版取替区間Nの橋軸方向一端から他端まで順次行うようにしたので、既設床版13をクレーン車によって吊り上げる必要がなく、しかも撤去する既設床版13を道路幅よりも小さい幅になる向きで搬送することができる。これにより、クレーン車を用いずに床版撤去作業を行うことができるので、施工現場の上方に位置する交差道路や高圧電線によって上空制約がある場合や、供用中の隣接道路や近隣構造物による道路幅方向の作業スペースに制約がある場合、或いは既設橋梁の耐荷力による重量の制約がある場合でも、これらの制約を受けることなく既設床版13の撤去を行うことができる。 As described above, according to the present embodiment, the existing deck 13 of the deck replacement section N is provided at a plurality of locations in the bridge axis direction so that the length L in the bridge axis direction is shorter than the length W in the direction perpendicular to the bridge axis. The cut existing deck 13 is first suspended by using a gate-shaped first suspension device 20 and a transport trolley 40 that can be cut in the direction perpendicular to the bridge axis and moved in the bridge axis direction on the existing deck 13. While being lifted by the device 20, the lifted existing deck 13 is rotated so that the longitudinal direction is the bridge axis direction and mounted on the transport trolley 40, and the transport trolley 40 on which the existing deck 13 is mounted is placed at a predetermined transport location. The first suspension device 20 was moved to the next deck removal position so that the existing deck 13 could be removed sequentially from one end to the other end of the deck replacement section N in the bridge axis direction. Therefore, it is not necessary to lift the existing deck 13 by a crane vehicle, and the existing deck 13 to be removed can be transported in a direction smaller than the road width. As a result, the deck removal work can be performed without using a crane vehicle, so if there are sky restrictions due to crossing roads or high-voltage electric wires located above the construction site, or if there are adjacent roads or nearby structures in service. Even if there are restrictions on the work space in the road width direction, or if there are restrictions on the weight due to the load capacity of the existing bridge, the existing floor slab 13 can be removed without these restrictions.

また、床版取替区間Nの既設床版13を撤去した後、既設床版13が撤去された主桁12上を橋軸方向に移動可能な前記第1の吊り装置20及び搬送台車40を用い、橋軸方向の長さLが橋軸直角方向の長さWよりも短くなるように形成された新設用のプレキャスト床版14を長手方向が橋軸方向となるように搬送台車40に載置して第1の吊り装置20まで搬送し、搬送されたプレキャスト床版14を第1の吊り装置20によって吊り上げるとともに、吊り上げたプレキャスト床版14を長手方向が橋軸直角方向となるように回転させて主桁12上に吊り降ろすことによってプレキャスト床版14を主桁上に設置し、第1の吊り装置20を次の床版設置位置に移動してプレキャスト床版14の前記設置を床版取替区間Nの橋軸方向一端から他端まで順次行うようにしたので、プレキャスト床版14をクレーン車によって吊り上げる必要がなく、しかも新設するプレキャスト床版14を道路幅よりも小さい幅になる向きで搬送することができる。これにより、クレーン車を用いずに床版設置作業を行うことができるので、前記床版撤去作業時と同様、施工現場の上方に位置する交差道路や高圧電線によって上空制約がある場合や、供用中の隣接道路や近隣構造物による道路幅方向の作業スペースに制約がある場合、或いは既設橋梁の耐荷力による重量の制約がある場合でも、これらの制約を受けることなくプレキャスト床版14の新設を行うことができる。 Further, after removing the existing deck 13 in the deck replacement section N, the first suspension device 20 and the transport trolley 40 that can move in the bridge axis direction on the main girder 12 from which the existing deck 13 has been removed are installed. A new precast deck 14 formed so that the length L in the bridge axis direction is shorter than the length W in the direction perpendicular to the bridge axis is mounted on the transport trolley 40 so that the longitudinal direction is the bridge axis direction. The precast deck 14 that has been placed and transported to the first suspension device 20 is lifted by the first suspension device 20, and the lifted precast deck 14 is rotated so that the longitudinal direction is perpendicular to the bridge axis. The precast deck 14 is installed on the main girder by suspending it on the main girder 12, and the first hanging device 20 is moved to the next deck installation position to install the precast deck 14 on the deck. Since the replacement section N is sequentially performed from one end to the other end in the bridge axis direction, it is not necessary to lift the precast deck 14 by a crane car, and the width of the newly installed precast deck 14 is smaller than the road width. Can be transported by. As a result, the floor slab installation work can be performed without using a crane car. Even if there are restrictions on the work space in the road width direction due to the adjacent roads and structures inside, or if there are restrictions on the weight due to the load capacity of the existing bridge, the precast deck 14 will be newly installed without these restrictions. It can be carried out.

更に、前記搬送場所に配置された門型の第2の吊り装置30を用い、搬送台車40から運搬車両60への既設床版13の積み替えと、運搬車両60から搬送台車40へのプレキャスト床版14の積み替えとを行うようにしたので、これらの積み替え作業もクレーン車を用いずに行うことができる。この場合、第1の吊り装置20によって床版の撤去作業または設置作業を行いながら、同時に第2の吊り装置30によって搬送台車40と運搬車両60との間での床版積み替え作業を行うことにより、床版取替施工全体の効率化を図ることができる。
また、第1及び第2の吊り装置20,30と搬送台車40を床版取替区間Nに設置した軌条50に沿って橋軸方向に移動させるようにしたので、第1及び第2の吊り装置20,30と搬送台車40を軌条50により常に安定して移動させることができ、特にトラック等の一般車両が走行できない床版撤去後の主桁12上での作業に極めて有利である。
Further, using the gate-shaped second suspension device 30 arranged at the transport location, the existing floor slab 13 is transshipped from the transport trolley 40 to the transport vehicle 60, and the precast deck slab from the transport vehicle 60 to the transport trolley 40. Since the transshipment of 14 is performed, these transshipment operations can also be performed without using a crane vehicle. In this case, the floor slab is removed or installed by the first suspension device 20, and at the same time, the floor slab is transshipped between the transport trolley 40 and the transport vehicle 60 by the second suspension device 30. , It is possible to improve the efficiency of the entire floor slab replacement work.
Further, since the first and second suspension devices 20 and 30 and the transport trolley 40 are moved in the direction of the bridge axis along the rail 50 installed in the deck replacement section N, the first and second suspension devices 20 and 30 are suspended. The devices 20 and 30 and the transport trolley 40 can always be stably moved by the rail 50, which is extremely advantageous for work on the main girder 12 after removing the floor slab where general vehicles such as trucks cannot travel.

更に、軌条50を一部ずつ除去しながら第1の吊り装置20を床版取替区間Nの橋軸方向一端側から他端側に順次移動させるようにしたので、撤去される既設床版13上またはプレキャスト床版14が設置される主桁12上に軌条50を設置して作業を行うことができ、軌条50を用いた作業を道路幅以下の範囲で行うことができる。 Further, since the first suspension device 20 is sequentially moved from one end side to the other end side in the bridge axis direction of the floor slab replacement section N while partially removing the rail 50, the existing floor slab 13 to be removed is removed. The rail 50 can be installed on the main girder 12 on which the precast floor slab 14 is installed, and the work using the rail 50 can be performed within the range of the road width or less.

尚、前記実施形態では、合成桁の既設床版13を撤去する場合を示したが、非合成桁橋を撤去する場合にも本発明を適用することができる。この場合、非合成桁橋は床版と主桁とを強固に結合するずれ止め部材がないため、前記実施形態のように床版13と主桁12との間のずれ止め部材を切断する工程は不要である。 In the above embodiment, the case where the existing floor slab 13 of the synthetic girder is removed is shown, but the present invention can also be applied to the case where the non-synthetic girder bridge is removed. In this case, since the non-synthetic girder bridge does not have a slip-preventing member that firmly connects the deck and the main girder, the step of cutting the slip-preventing member between the deck 13 and the main girder 12 as in the above embodiment. Is unnecessary.

また、前記実施形態では、橋軸方向の長さLの既設床版13またはプレキャスト床版14を複数枚(例えば2枚)撤去または設置するごとに長さ2Lのレール51及び固定部材52を1つずつ取り除くようにしたものを示したが、既設床版13またはプレキャスト床版14を1枚撤去または設置するごとに長さLのレール51及び固定部材52を1つずつ取り除くようにしてもよい。 Further, in the above embodiment, each time a plurality (for example, two) of existing floor slabs 13 or precast floor slabs 14 having a length L in the direction of the bridge axis are removed or installed, a rail 51 having a length of 2 L and a fixing member 52 are used. Although it is shown that the existing floor slab 13 or the precast floor slab 14 is removed one by one, the rail 51 and the fixing member 52 having a length L may be removed one by one every time one of the existing floor slabs 13 or the precast floor slab 14 is removed or installed. ..

10…橋梁、12…主桁、13…既設床版、14…プレキャスト床版、20…第1の吊り装置、30…第2の吊り装置、40…搬送台車、50…軌条、60…運搬車両。 10 ... Bridge, 12 ... Main girder, 13 ... Existing floor slab, 14 ... Precast floor slab, 20 ... First suspension device, 30 ... Second suspension device, 40 ... Transport trolley, 50 ... Rail, 60 ... Transport vehicle ..

Claims (7)

床版取替区間の既設床版を主桁上から撤去し、新たなプレキャスト床版を主桁上に設置する床版取替方法において、
前記床版取替区間の既設床版を橋軸方向複数箇所で橋軸直角方向に切断し、
既設床版上に敷設した軌条に沿って橋軸方向に移動可能な門型の吊り装置及び搬送台車を用い、
切断された既設床版を吊り装置によって吊り上げて搬送台車に載置し、
既設床版を載置した搬送台車を所定の場所まで搬送するとともに、
次に既設床版を撤去する床版撤去位置の軌条を既設床版上から取り除き、
吊り装置を橋軸方向の次の床版撤去位置に移動して既設床版の前記撤去を床版取替区間の橋軸方向一端から他端まで順次行うことにより、床版取替区間の既設床版を主桁上から撤去した後、
前記既設床版が撤去された主桁上に敷設した軌条に沿って橋軸方向に移動可能な門型の吊り装置及び搬送台車を用い、
新設用のプレキャスト床版を所定の場所で搬送台車に載置して吊り装置まで搬送し、
搬送されたプレキャスト床版を吊り装置によって吊り上げて主桁上に設置し、
次にプレキャスト床版を設置する床版設置位置の軌条を主桁上から取り除き、
吊り装置を橋軸方向の次の床版設置位置に移動してプレキャスト床版の前記設置を床版取替区間の橋軸方向一端から他端まで順次行うことにより、床版取替区間に新たなプレキャスト床版を設置する
ことを特徴とする床版取替方法。
In the floor slab replacement method, the existing floor slab in the floor slab replacement section is removed from the main girder and a new precast floor slab is installed on the main girder.
The existing deck in the floor slab replacement section is cut at multiple points in the bridge axis direction in the direction perpendicular to the bridge axis.
Using a gate-shaped suspension device and a transport trolley that can move in the direction of the bridge axis along the rails laid on the existing deck.
The cut existing floor slab is lifted by a lifting device and placed on a transport trolley.
In addition to transporting the transport trolley on which the existing floor slab is placed to the specified location,
Next, remove the rail at the floor slab removal position where the existing floor slab is removed from the existing floor slab.
By moving the suspension device to the next floor slab removal position in the bridge axis direction and sequentially removing the existing floor slab from one end to the other end in the bridge axis direction of the floor slab replacement section, the existing floor slab replacement section is already installed. After removing the deck from the main girder
Using a gate-shaped suspension device and a transport trolley that can move in the direction of the bridge axis along the rails laid on the main girder from which the existing floor slab has been removed.
Place the precast deck for new installation on the transport trolley at the designated place and transport it to the suspension device.
The transported precast deck is lifted by a hanging device and installed on the main girder.
Next, remove the rail of the floor slab installation position where the precast floor slab is installed from the main girder, and remove it.
By moving the suspension device to the next deck installation position in the bridge axis direction and sequentially installing the precast deck from one end to the other end in the bridge axis direction of the deck replacement section, a new deck replacement section will be created. A floor slab replacement method characterized by installing a variety of precast floor slabs.
前記床版取替区間の既設床版を切断する際、既設床版の橋軸方向の長さが橋軸直角方向の長さよりも短くなるように切断し、
前記吊り装置によって吊り上げた既設床版を長手方向が橋軸方向となるように水平方向に回転させて搬送台車に載置する
ことを特徴とする請求項1記載の床版取替方法。
When cutting the existing deck in the floor slab replacement section, the existing deck is cut so that the length in the bridge axis direction is shorter than the length in the direction perpendicular to the bridge axis.
The floor slab replacement method according to claim 1, wherein the existing floor slab lifted by the suspension device is rotated horizontally so that the longitudinal direction is the bridge axis direction and placed on a transport carriage.
前記新設用のプレキャスト床版を設置する際、橋軸方向の長さが橋軸直角方向の長さよりも短くなるように形成されたプレキャスト床版を長手方向が橋軸方向となるように搬送台車に載置して吊り装置まで搬送し、
前記吊り装置によって吊り上げたプレキャスト床版を長手方向が橋軸直角方向となるように水平方向に回転させて主桁上に設置する
ことを特徴とする請求項1または2記載の床版取替方法。
When installing the precast deck for new installation, the precast deck formed so that the length in the bridge axis direction is shorter than the length in the direction perpendicular to the bridge axis is transported so that the longitudinal direction is the bridge axis direction. Place it on the floor and transport it to the suspension device.
The floor slab replacement method according to claim 1 or 2, wherein the precast floor slab lifted by the suspension device is horizontally rotated so that the longitudinal direction is perpendicular to the bridge axis and installed on the main girder. ..
前記所定の場所に配置された他の門型の吊り装置を用い、搬送台車から運搬車両への既設床版の積み替えと、運搬車両から搬送台車へのプレキャスト床版の積み替えとを行う
ことを特徴とする請求項1、2または3記載の床版取替方法。
It is characterized by transshipping the existing floor slab from the transport vehicle to the transport vehicle and transshipping the precast floor slab from the transport vehicle to the transport vehicle by using another gate-type suspension device arranged at the predetermined location. The floor slab replacement method according to claim 1, 2 or 3.
床版取替区間の既設床版を主桁上から撤去し、新たなプレキャスト床版を主桁上に設置する床版取替装置において、
前記既設床版上に敷設される軌条と、
軌条に沿って橋軸方向に移動可能な門型の吊り装置及び搬送台車とを備え、
橋軸方向複数箇所で橋軸直角方向に切断された床版取替区間の既設床版を吊り装置によって吊り上げるとともに、
吊り上げた既設床版を搬送台車に載置し、
既設床版を載置した搬送台車を所定の場所まで搬送するとともに、
既設床版上から軌条が取り除かれた次の床版撤去位置に吊り装置を移動して既設床版の前記撤去を床版取替区間の橋軸方向一端から他端まで順次行うことにより、床版取替区間の既設床版を主桁上から撤去するように構成するとともに、
前記既設床版が撤去された主桁上に敷設される軌条と、
軌条に沿って橋軸方向に移動可能な門型の吊り装置及び搬送台車を備え、
新設用のプレキャスト床版を所定の場所で搬送台車に載置して吊り装置まで搬送し、
搬送されたプレキャスト床版を吊り装置によって吊り上げて主桁上に設置し、
主桁上から軌条が取り除かれた次の床版設置位置に吊り装置を移動してプレキャスト床版の前記設置を床版取替区間の橋軸方向一端から他端まで順次行うことにより、床版取替区間に新たなプレキャスト床版を設置するように構成した
ことを特徴とする床版取替装置。
In the floor slab replacement device that removes the existing floor slab in the floor slab replacement section from the main girder and installs a new precast floor slab on the main girder.
The rails laid on the existing floor slab and
Equipped with a gate-shaped suspension device and a transport cart that can move in the direction of the bridge axis along the rails.
The existing floor slab of the floor slab replacement section cut in the direction perpendicular to the bridge axis at multiple points in the bridge axis direction is lifted by a lifting device, and at the same time.
Place the lifted existing floor slab on the transport trolley and place it on the transport trolley.
In addition to transporting the transport trolley on which the existing floor slab is placed to the specified location,
By moving the suspension device to the next deck removal position where the rails have been removed from the existing deck, and performing the removal of the existing deck sequentially from one end to the other end in the bridge axis direction of the deck replacement section, the floor In addition to being configured to remove the existing floor slab in the plate replacement section from the main girder,
The rails laid on the main girder from which the existing floor slab was removed,
Equipped with a gate-shaped suspension device and a transport trolley that can move in the direction of the bridge axis along the rails.
Place the precast deck for new installation on the transport trolley at the designated place and transport it to the suspension device.
The transported precast deck is lifted by a hanging device and installed on the main girder.
By moving the suspension device to the next deck installation position where the rails have been removed from the main girder and performing the installation of the precast deck in sequence from one end to the other end in the bridge axis direction of the deck replacement section, the deck is installed. A deck replacement device characterized by being configured to install a new precast deck in the replacement section.
前記吊り装置は、吊り上げた既設床版またはプレキャスト床版を水平方向に回転可能に構成されている
ことを特徴とする請求項5記載の床版取替装置。
The floor slab replacement device according to claim 5, wherein the suspension device is configured so that the existing floor slab or precast floor slab that has been lifted can be rotated in the horizontal direction.
前記所定の場所に配置され、搬送台車から運搬車両への既設床版の積み替えと、運搬車両から搬送台車へのプレキャスト床版の積み替えとを行う他の門型の吊り装置を備えた
ことを特徴とする請求項5または6記載の床版取替装置。
It is characterized by being placed in the above-mentioned predetermined location and equipped with another gate-type suspension device that transships the existing floor slab from the transport vehicle to the transport vehicle and transships the precast deck from the transport vehicle to the transport vehicle. The floor slab replacement device according to claim 5 or 6.
JP2018063780A 2018-03-29 2018-03-29 Floor slab replacement method and floor slab replacement device Active JP6974233B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2018063780A JP6974233B2 (en) 2018-03-29 2018-03-29 Floor slab replacement method and floor slab replacement device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018063780A JP6974233B2 (en) 2018-03-29 2018-03-29 Floor slab replacement method and floor slab replacement device

Publications (2)

Publication Number Publication Date
JP2019173435A JP2019173435A (en) 2019-10-10
JP6974233B2 true JP6974233B2 (en) 2021-12-01

Family

ID=68168324

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018063780A Active JP6974233B2 (en) 2018-03-29 2018-03-29 Floor slab replacement method and floor slab replacement device

Country Status (1)

Country Link
JP (1) JP6974233B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7330411B2 (en) 2019-10-31 2023-08-21 株式会社大林組 Floor slab moving method and floor slab moving device
JP7421466B2 (en) 2020-11-05 2024-01-24 株式会社ピーエス三菱 Concrete slab replacement method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2578305B2 (en) * 1993-04-26 1997-02-05 株式会社ピー・エス Non-composite RC slab replacement method and self-propelled slab lifting device
JP3721166B2 (en) * 2003-02-03 2005-11-30 川田建設株式会社 Floor slab erection device
JP4143442B2 (en) * 2003-03-03 2008-09-03 株式会社野田自動車工業所 PC floor slab erection device and PC floor slab erection method using the device
JP6004353B2 (en) * 2014-11-18 2016-10-05 株式会社ピーエス三菱 Replacement method of concrete floor slab for elevated road

Also Published As

Publication number Publication date
JP2019173435A (en) 2019-10-10

Similar Documents

Publication Publication Date Title
JP6081117B2 (en) How to remove existing bridge and update existing bridge
JP6793542B2 (en) Floor slab erection method and floor slab erection equipment
KR101287455B1 (en) System and method for launching upper structure of bridege
JP2013174075A (en) Reconstruction technique for bridge girder
JP5823552B2 (en) Method and apparatus for erection of bridge deck
JP3954869B2 (en) Bridge girder replacement method
JP7193172B2 (en) Floor slab erection machine
JP2006265884A (en) Method of removing existing pier of viaduct
JP2014015808A (en) Method for constructing scaffold for rebuilding construction of bridge, and apparatus for constructing scaffold for construction
JP6974233B2 (en) Floor slab replacement method and floor slab replacement device
JP5890060B1 (en) Bridge dismantling method using erection girder
JP4134104B2 (en) Bridge removal method
JP5184248B2 (en) Construction method of level crossing
KR101160273B1 (en) Straddle carrier for bridge construction
KR101234090B1 (en) Method for changing girder of railway plate girder bridge
KR101077092B1 (en) Girder installation method using trolly without closing nor detouring existing road
JP2001098512A (en) Method for erecting and removing road striding bridge by frame with jack device
JP7020978B2 (en) How to remove the floor slab of synthetic girders
JP2007321476A (en) Bridge and its construction method
JP4339778B2 (en) How to remove a bridge
JP7324626B2 (en) Lifted load moving device, removal method of existing bridge, and installation method of bridge members
JP6682332B2 (en) Bridge removal method
JP6627177B2 (en) Construction method of vehicle-mounted lifter and pier
JP6678440B2 (en) Construction method of viaduct, installation method and removal method of container and support used for this
JPH11190008A (en) Rebuilding method for elevated bridge

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20201124

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20211027

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20211027

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20211104

R150 Certificate of patent or registration of utility model

Ref document number: 6974233

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150