KR101270947B1 - Deck repairing construction method of bridge using precast concrete slab - Google Patents

Deck repairing construction method of bridge using precast concrete slab Download PDF

Info

Publication number
KR101270947B1
KR101270947B1 KR1020110036517A KR20110036517A KR101270947B1 KR 101270947 B1 KR101270947 B1 KR 101270947B1 KR 1020110036517 A KR1020110036517 A KR 1020110036517A KR 20110036517 A KR20110036517 A KR 20110036517A KR 101270947 B1 KR101270947 B1 KR 101270947B1
Authority
KR
South Korea
Prior art keywords
bottom plate
precast
girder
bridge
upper side
Prior art date
Application number
KR1020110036517A
Other languages
Korean (ko)
Other versions
KR20120118884A (en
Inventor
김근택
Original Assignee
김근택
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김근택 filed Critical 김근택
Priority to KR1020110036517A priority Critical patent/KR101270947B1/en
Publication of KR20120118884A publication Critical patent/KR20120118884A/en
Application granted granted Critical
Publication of KR101270947B1 publication Critical patent/KR101270947B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법에 관한것으로써, 더욱 상세하게는 바닥판을 철거한 후 거더의 상측면에 프리캐스트 바닥판을 설치하는 동시에 프리캐스트 바닥판의 최외곽에 방호벽 또는 방음벽용 철근 설치를 병행하고, 상기 프리캐스트 바닥판과 거더를 합성시키는 시점에 상기 방호벽 또는 방음벽 형성을 위한 콘크리트 타설을 병행함과 아울러 상기 바닥판 철거와 동시에 거더의 상측면에 연결수단을 설치하면서 프리캐스트 바닥판을 설치하도록 함으로써, 노후 교량의 바닥판 교체공사를 신속하게 할 수 있어서 공사기간을 단축할 수 있고 이로인해 공사비용을 줄일 수 있는 프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법에 관한 것이다.The present invention relates to a bridge plate replacement construction method using a precast deck, and more particularly, after the bottom plate is removed, the precast deck is installed on the upper side of the girder, and at the same time, Installation of reinforcing walls or sound barriers on the outer side and at the time of synthesizing the precast deck and the girder, parallel installation of concrete for forming the barriers or the sound barrier, and at the same time the top plate of the girder is removed. By installing the precast deck while installing the means, it is possible to quickly replace the deck of old bridges, which can shorten the construction period and thereby reduce the cost of construction. It relates to a plate replacement construction method.

Description

프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법{Deck repairing construction method of bridge using precast concrete slab}Deck repairing construction method of bridge using precast concrete slab}

본 발명은 프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법에 관한것으로써, 더욱 상세하게는 바닥판을 철거한 후 거더의 상측면에 프리캐스트 바닥판을 설치하는 동시에 프리캐스트 바닥판의 최외곽에 방호벽 또는 방음벽용 철근 설치를 병행하고, 상기 프리캐스트 바닥판과 거더를 합성시키는 시점에 상기 방호벽 또는 방음벽 형성을 위한 콘크리트 타설을 병행함과 아울러 상기 바닥판 철거와 동시에 거더의 상측면에 연결수단을 설치하면서 프리캐스트 바닥판을 설치하도록 한 프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법에 관한 것이다.The present invention relates to a bridge plate replacement construction method using a precast deck, and more particularly, after the bottom plate is removed, the precast deck is installed on the upper side of the girder, and at the same time, Installation of reinforcing walls or sound barriers on the outer side and at the time of synthesizing the precast deck and the girder, parallel installation of concrete for forming the barriers or the sound barrier, and at the same time the top plate of the girder is removed. It relates to a bridge plate replacement construction method using a precast floor plate to install a precast floor plate while installing the means.

일반적으로, 교량은 하천,계곡,호수 및 도로 등을 건널 수 있도록 가로질러 걸쳐놓은 고가 구조물로서, 통상 강합성 교량의 구조는 지면상에 일정간격을 두고 설치되는 복수개의 교각과, 상기 각 인접된 교각의 상단에 일정간격을 두고 수평방향으로 병렬 배치되는 거더(Girder)와, 상기 거더의 처짐 보강을 위해 각 인접된 거더 간에 일정간격을 두고 직교방향으로 연결되는 크로스빔과, 상기 거더의 상부에 배치되는 바닥판으로 이루어진다.In general, bridges are expensive structures that span across rivers, valleys, lakes, and roads. Typically, a composite bridge has a plurality of bridges installed at regular intervals on the ground, and the adjacent bridges. Girders arranged in parallel in the horizontal direction at regular intervals at the top of the piers, crossbeams connected at right angles at regular intervals between adjacent girders to reinforce the deflection of the girders, and on top of the girders It consists of a bottom plate placed.

상기 거더의 상부에 바닥판을 시공하고자 할 경우에는, 상기 거더의 상부에 거푸집 및 작업발판을 설치한 후, 콘크리트를 현장 타설하여 바닥판을 양생하게 되며, 이후 상기 거푸집 등을 제거하게 된다.When the bottom plate is to be installed on the upper part of the girder, after installing the formwork and the working scaffold on the upper part of the girder, the concrete is cast on-site to cure the bottom plate, and then the formwork is removed.

또한, 상기 바닥판이 양생된 후에는 바닥판의 최외곽에 철근을 설치한 후, 콘크리트를 타설하여 방호벽 또는 방음벽을 설치하게 된다.In addition, after the bottom plate is cured, the reinforcing bar is installed at the outermost side of the bottom plate, and then concrete is installed to install a protective wall or a soundproof wall.

그리고, 상기한 교량이 노후되어 교량의 전체구간 또는 특정구간의 바닥판을 교체하고자 할 경우, 상기 거더는 존치시키고 상기 바닥판과, 방호벽 또는 방음벽을 철거한 후 교체 시공하게 된다.In addition, when the bridge is deteriorated to replace the bottom plate of the entire section or a specific section of the bridge, the girder is left and replaced after removing the bottom plate, the protective wall or the soundproof wall.

즉, 교량의 전체구간 또는 특정구간의 바닥판과 방호벽 또는 방음벽을 철거한 후, 상기 바닥판이 철거된 거더의 상측면에 거푸집 및 작업발판을 설치한다.That is, after removing the bottom plate and the protective wall or soundproof wall of the entire section or a specific section of the bridge, the formwork and the working scaffold is installed on the upper side of the girder from which the bottom plate is removed.

이후, 콘크리트를 현장 타설하여 상기 바닥판을 양생시킨다.Thereafter, concrete is cast in place to cure the bottom plate.

상기 바닥판이 완전히 양생되고 나면, 상기 바닥판의 최외곽에 방호벽 또는 방음벽용 철근을 설치 조립한 후, 콘크리트를 타설하여 방호벽 또는 방음벽을 형성하게 된다.After the bottom plate is completely cured, after installing the reinforcing bar or sound barrier reinforcing bar in the outermost of the bottom plate, the concrete is poured to form a barrier or sound barrier.

그러나, 상기 종래의 바닥판 교체 시공방법은, 바닥판을 철거한 후 거더의 상측면에 거푸집 및 작업발판을 설치하여 콘크리트를 타설하고, 바닥판이 완전히 양생되고 나면 방호벽 또는 방음벽용 철근을 설치한 후 콘크리트를 재차 타설하여 방호벽 또는 방음벽을 형성하기 때문에, 상기 바닥판 교체 공사기간이 많이 소요됨은 물론 공사비용도 증가하는 문제가 있었다.However, in the conventional method for replacing the bottom plate, after installing the formwork and the working scaffold on the upper side of the girder after the bottom plate is removed, and after the bottom plate is completely cured, after installing the reinforcing bar or soundproof wall rebar Since the concrete is laid again to form a protective wall or a soundproof wall, there is a problem in that the construction cost of the floor plate replacement is increased and the construction cost is increased.

상기한 종래의 문제점을 해결하기 위한 본 발명의 목적은 바닥판을 철거한 후 거더의 상측면에 프리캐스트 바닥판을 설치하는 동시에 프리캐스트 바닥판의 최외곽에 방호벽 또는 방음벽용 철근 설치를 병행하고, 상기 프리캐스트 바닥판과 거더를 합성시키는 시점에 상기 방호벽 또는 방음벽 형성을 위한 콘크리트 타설을 병행함과 아울러 상기 바닥판 철거와 동시에 거더의 상측면에 연결수단을 설치하면서 프리캐스트 바닥판을 설치하도록 함으로써, 노후 교량의 바닥판 교체공사를 신속하게 할 수 있어서 공사기간을 단축할 수 있고 이로인해 공사비용을 줄일 수 있는 프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법을 제공하는데 있다.An object of the present invention for solving the above problems is to install a precast bottom plate on the upper side of the girder after the bottom plate is removed, and at the same time to install a reinforcing bar or sound barrier for the outermost of the precast bottom plate At the time of synthesizing the precast deck and the girder, the concrete wall for forming the protective wall or the soundproof wall is installed in parallel, and the precast deck is installed while installing the connecting means on the upper side of the girder at the same time as the demolition of the deck. By doing so, it is possible to quickly replace the floor plate replacement work of the aging bridge to shorten the construction period and thereby to provide a construction method for replacing the floor plate of the bridge using a precast floor plate that can reduce the construction cost.

상기한 목적을 달성하기 위한 본 발명은, 교량의 거더 상측에 설치된 바닥판을 교체하기 위한 교량의 바닥판 교체 시공 방법에 있어서, 상기 거더의 상측에 설치된 바닥판을 철거하되, 바닥판의 최외곽에 설치되어 있는 방호벽 또는 방음벽까지 모두 철거하는 바닥판 철거단계와, 상기 바닥판이 철거된 상기 거더 상측의 면을 정리하는 면 정리단계와, 상기 거더의 상측면에 프리캐스트 바닥판과의 합성을 위한 연결수단을 설치하는 연결수단 설치단계와, 상기 연결수단이 설치된 거더의 상측면에 프리캐스트 바닥판을 안착 설치함과 동시에 프리캐스트 바닥판의 최외곽에 방호벽 또는 방음벽을 설치하기 위한 철근을 설치하는 프리캐스트 바닥판 및 철근 설치 병행단계와, 상기 프리캐스트 바닥판과 상기 거더를 합성시킴과 동시에 상기 철근 설치 부위에 방호벽 또는 방음벽을 형성하도록 콘크리트를 타설하는 콘크리트 타설단계를 포함하여 이루어진 것을 특징으로 한다.The present invention for achieving the above object, in the bridge plate replacement construction method of the bridge for replacing the bottom plate installed on the upper side of the girder, the bottom plate installed on the upper side of the girder, but the outermost of the bottom plate A bottom plate demolition step for removing all of the barriers or soundproof walls installed on the floor; and a surface arranging step for arranging the upper surface of the girder from which the bottom plate is removed; and for synthesizing with the precast floor plate on the upper side of the girder. Installing the connecting means for installing the connecting means, and installing the precast bottom plate on the upper side of the girder in which the connecting means is installed, and at the same time to install a reinforcing bar or soundproof wall in the outermost of the precast bottom plate Precast floor plate and rebar installation parallel step, the precast floor plate and the girder at the same time the rebar installation site It characterized in that it comprises a concrete pouring step of placing concrete to form a protective wall or soundproof wall.

본 발명은, 바닥판을 철거한 후 거더의 상측면에 프리캐스트 바닥판을 설치하는 동시에 프리캐스트 바닥판의 최외곽에 방호벽 또는 방음벽용 철근 설치를 병행하고, 상기 프리캐스트 바닥판과 거더를 합성시키는 시점에 상기 방호벽 또는 방음벽 형성을 위한 콘크리트 타설을 병행함으로써, 노후 교량의 바닥판 교체공사를 신속하게 할 수 있어서 공사기간을 단축할 수 있고 이로인해 공사비용을 줄일 수 있다.The present invention is to remove the bottom plate and to install the precast bottom plate on the upper side of the girder and at the same time to install the reinforcing bar or sound barrier wall at the outermost side of the precast bottom plate, and synthesize the precast bottom plate and the girder By simultaneously placing the concrete for forming the protective wall or the soundproof wall at the point of time, it is possible to quickly replace the floor plate of the aging bridge, thereby shortening the construction period and thereby reducing the construction cost.

또한, 상기 바닥판 철거 작업이 진행되는 도중에 상기 거더의 상측면에 연결수단을 설치하면서 프리캐스트 바닥판을 설치할 수 있고 이와 동시에 방호벽 또는 방음벽용 철근 설치를 병행할 수 있도록 함으로써, 바닥판 교체공사를 더욱 신속하게 하여 공사기간을 더욱 단축할 수 있다.In addition, while the bottom plate removal work is in progress, it is possible to install a precast floor plate while installing a connecting means on the upper side of the girder, and at the same time to install a reinforcing bar or sound barrier wall reinforcement, so that the bottom plate replacement construction By making it faster, the construction period can be further shortened.

그리고, 콘크리트 타설단계의 전단계인 상기 프리캐스트 바닥판 및 철근 설치 병행단계에서 이미 철근조립이 완료되고, 상기 콘크리트 타설단계에서는 프리캐스트 바닥판과 거더의 합성을 위한 콘크리트 타설과 방호벽 또는 방음벽 형성을 위한 콘크리트 타설만 하면됨으로써, 공사기간을 더욱 단축시킬 수 있다.In addition, reinforcement is already completed in the precast deck and rebar installation parallel stage, which is a preliminary stage of the concrete pouring stage, and in the concrete pouring stage, concrete casting and a barrier or soundproof wall for the synthesis of the precast deck and the girder are performed. By simply pouring concrete, the construction period can be further shortened.

도 1은 본 발명에 따른 프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법을 나타내는 블록도,
도 2는 본 발명에 따른 프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법으로 시공하는 과정을 나타내는 도면,
도 3은 본 발명에 따른 프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법에서 바닥판 철거단계를 나타내는 사시도,
도 4는 본 발명에 따른 프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법에서 면 정리단계를 나타내는 사시도,
도 5는 본 발명에 따른 프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법에서 연결수단 설치단계를 나타내는 사시도,
도 6은 본 발명에 따른 프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법에서 프리캐스트 바닥판 및 철근 설치 병행단계를 나타내는 사시도,
도 7은 도 6의 다른 실시예로서 바닥판의 철거와 동시에 프리캐스트 바닥판 및 철근 설치를 병행하는 경우를 나타내는 사시도,
도 8은 본 발명에 따른 프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법에서 콘크리트 타설단계를 나타내는 사시도,
도 9는 도 8의 콘크리트 타설단계 이후 프리캐스트 바닥판의 상측면에 콘크리트 또는 아스팔트 포장하는 경우를 나타내는 사시도,
도 10은 교량의 거더 상측면에 프리캐스트 바닥판을 설치하는 경우를 나타내는 사시도,
도 11은 거더의 종류에 따른 각 교량의 형태를 나타내는 도면이다.
1 is a block diagram showing a method for replacing the bottom plate of a bridge using a precast deck according to the present invention,
2 is a view showing a process of construction by the method of replacing the base plate of the bridge using a precast deck according to the present invention,
Figure 3 is a perspective view showing the step of removing the bottom plate in the construction method for replacing the bottom plate of the bridge using the precast bottom plate according to the present invention,
Figure 4 is a perspective view showing the surface cleaning step in the construction method for replacing the floor plate of the bridge using a precast floor plate according to the present invention,
5 is a perspective view showing the installation step of the connecting means in the bottom plate replacement construction method of the bridge using the precast bottom plate according to the present invention,
Figure 6 is a perspective view showing a parallel step of precast floor plate and reinforcing bar in the construction method of the bridge replacement plate using the precast floor plate according to the present invention,
FIG. 7 is a perspective view illustrating a case in which a precast bottom plate and reinforcing bar are installed at the same time as removal of the bottom plate as another embodiment of FIG. 6; FIG.
8 is a perspective view showing the concrete pouring step in the construction method for replacing the floor plate of the bridge using the precast deck according to the present invention,
9 is a perspective view showing a case of concrete or asphalt pavement on the upper side of the precast deck after the concrete pouring step of FIG.
10 is a perspective view showing a case where a precast bottom plate is provided on the upper side of the girder of the bridge;
11 is a view showing the shape of each bridge according to the type of girder.

이하, 본 발명을 첨부된 도면을 참조하여 상세히 설명하면 다음과 같다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.

도시된 바와 같이, 본 발명에 따른 프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법은, 교량(1)의 거더(2) 상측에 설치된 바닥판(5)을 프리캐스트 바닥판(20)으로 교체하기 위한 시공방법으로서, 노후 교량 뿐만 아니라 신설 교량의 경우에도 바닥판(5)의 노후 또는 파손 등으로 인해 교체가 필요할 때 시공하는 방법이다.As shown, the method for replacing the bottom plate of the bridge using the precast bottom plate according to the present invention, the bottom plate 5 provided on the upper side of the girder 2 of the bridge (1) to the precast bottom plate 20 As a construction method for replacing, it is a method for construction when replacement is required due to the aging or damage of the bottom plate 5, as well as the old bridges, new bridges.

일반적인 교량(1)은, 도 11과 같이, 거더(2)의 종류에 따라 강 거더 교량(플레이트 거더교, 강박스 거더교, 개구제형 강박스 거더교)과, PSC(Prestressed Concrete Girder) 거더 교량으로 구분되며, 상기 거더(2)의 상측면에는 바닥판(5)이 시공되고, 상기 바닥판(5)의 최외곽에는 방호벽(6) 또는 방음벽(미도시)이 시공된다.The general bridge 1 is divided into a steel girder bridge (plate girder bridge, steel box girder bridge, opening type steel box girder bridge) and PSC (Prestressed Concrete Girder) girder bridge as shown in FIG. The bottom plate 5 is constructed on the upper side of the girder 2, and the outer wall of the bottom plate 5 is provided with a protective wall 6 or a soundproof wall (not shown).

상기 바닥판(5)의 경우, 상기 거더(2)의 상측면에 거푸집 및 작업발판을 설치한 후 콘크리트를 현장 타설하여 시공하게 된다.In the case of the bottom plate (5), after installing the formwork and the working scaffold on the upper side of the girder (2) is to be installed by placing the site in the field.

아울러, 상기 바닥판(5)의 상측면에는 추가로 아스팔트 또는 콘크리트 포장을 진행할 수도 있다.In addition, the upper side surface of the bottom plate 5 may further proceed with asphalt or concrete pavement.

이하, 본 발명에서는 PSC 거더 교량의 바닥판(5)을 교체 시공하는 방법에 대해서 일예로 설명하기로 한다. 물론 다른 거더 교량에도 동일한 방법으로 시공할 수 있다.Hereinafter, in the present invention, a method for replacing the bottom plate 5 of the PSC girder bridge will be described as an example. Of course, other girder bridges can be constructed in the same way.

본 발명에 따른 프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법은, 바닥판 철거단계(S1)와, 면 정리단계(S2)와, 연결수단 설치단계(S3)와, 프리캐스트 바닥판 및 철근 설치 병행단계(S4)와, 콘크리트 타설단계(S5)를 포함하여 이루어진다.The bridge plate replacement construction method using the precast floor plate according to the present invention, the bottom plate removal step (S1), surface arrangement step (S2), connecting means installation step (S3), precast floor plate and Rebar installation parallel step (S4), and concrete placing step (S5) is made.

가. 바닥판 철거단계(S1),end. Bottom plate removal step (S1),

상기 바닥판 철거단계(S1)는, 도 3과 같이, 상기 교량(1)의 거더(2) 상측에 설치된 바닥판(5)을 철거하는 단계이다.The bottom plate dismantling step (S1) is a step of dismantling the bottom plate 5 installed above the girder 2 of the bridge 1 as shown in FIG. 3.

이때, 상기 바닥판(5)의 최외곽에 방호벽(6) 또는 방음벽(미도시)이 설치되어 있는 경우에는 상기 방호벽(6) 도는 방음벽까지 모두 철거하게 된다.In this case, when the protective wall 6 or the soundproof wall (not shown) is installed at the outermost part of the bottom plate 5, all of the protective wall 6 or the soundproof wall is removed.

또한, 상기 바닥판(5) 철거시에는 도 3과 같이 소단위로 바닥판(5)을 커팅 분할하여 철거하게 된다.
In addition, when the bottom plate 5 is dismantled, the bottom plate 5 is cut and divided into small units as shown in FIG. 3.

나. 면 정리단계(S2),I. Clean up phase (S2),

상기 면 정리단계(S2)는, 도 4와 같이, 상기 바닥판(5)이 철거된 상기 거더(2) 상측의 면을 정리하는 단계이다.The surface rearranging step S2 is a step of arranging the upper surface of the girder 2 on which the bottom plate 5 is removed, as shown in FIG. 4.

즉, 상기 바닥판(5)이 철거된 거더(2)의 상측면에 요철이 발생하지 않도록 면을 정리함으로써, 상기 거더(2)의 상측면에 프리캐스트 바닥판(20)을 용이하게 설치할 수 있을 뿐만 아니라, 상기 거더(2)의 상측면에 프리캐스트 바닥판(20) 합성용 연결수단(10)도 용이하게 설치할 수 있다.
That is, by arranging the surface so that unevenness does not occur on the upper side of the girder 2 on which the bottom plate 5 is removed, the precast bottom plate 20 can be easily installed on the upper side of the girder 2. In addition, the connecting means 10 for synthesizing the precast bottom plate 20 may be easily installed on the upper side of the girder 2.

다. 연결수단 설치단계(S3),All. Connecting means installation step (S3),

상기 연결수단 설치단계(S3)는, 도 5와 같이, 상기 면 정리단계(S2)를 거쳐 상기 거더(2) 상측면의 면 정리가 완료되면, 상기 거더(2)의 상측면에 프리캐스트 바닥판(20)과의 합성을 위한 연결수단(10)을 설치하는 단계이다.The connecting means installation step (S3), as shown in Figure 5, when the surface clearance of the upper side of the girder 2 through the surface clearance step (S2) is completed, the precast bottom on the upper side of the girder (2) It is a step of installing the connecting means 10 for synthesis with the plate 20.

상기 연결수단(10)으로는, PSC 거더 교량(1)의 경우 상기 거더(2)의 상측면에 매입 설치되는 앙카볼트이고, 강 거더 교량의 경우 상기 거더(2)의 상측면에 용접하여 설치되는 스터드볼트 이다.
The connecting means 10 is an anchor bolt installed in the upper side of the girder 2 in the case of the PSC girder bridge 1, and welded to the upper side of the girder 2 in the case of the steel girder bridge. It is a stud bolt.

라. 프리캐스트 바닥판 및 철근 설치 병행단계(S4),la. Precast deck and rebar installation parallel step (S4),

상기 프리캐스트 바닥판 및 철근 설치 병행단계(S4)는, 도 6과 같이, 상기 연결수단 설치단계(S3)를 거쳐 상기 연결수단(10)이 설치된 거더(2)의 상측면에 프리캐스트 바닥판(20)을 안착 설치함과 동시에 프리캐스트 바닥판(20)의 최외곽에 방호벽(40) 또는 방음벽을 설치하기 위한 철근(30) 설치를 병행하는 단계이다.The precast bottom plate and the rebar installation parallel step (S4), as shown in Figure 6, through the connecting means installation step (S3), the precast bottom plate on the upper side of the girder 2, the connection means 10 is installed At the same time as the seat 20 is installed and installed at the same time the installation of the reinforcing bar 30 for installing the protective wall 40 or the soundproof wall in the outermost of the precast bottom plate 20.

여기서, 상기 프리캐스트 바닥판 및 철근 설치 병행단계(S4)는, 상기 거더(2)의 상측면에 프리캐스트 바닥판(20)의 설치가 완료되는 시점에 상기 방호벽(40) 또는 방음벽용 철근(30) 설치도 완료되는 단계이다.Here, the precast bottom plate and the rebar installation parallel step (S4), when the installation of the precast bottom plate 20 on the upper side of the girder 2 is completed, the barrier 40 or the soundproof wall rebar ( 30) Installation is also completed.

먼저, 도 10을 참조하여 상기 거더(2)의 상측면에 프리캐스트 바닥판(20)을 설치하는 방법에 대해서 설명하면, 상기 교량(1) 위에 제1크레인차량(3a)을 배치하여 제1크레인차량(3a)의 작업반경내에 프리캐스트 바닥판(20)을 설치한 후, 상기 제1크레인차량(3a)의 작업반경을 벗어난 구간은 상기에서 먼저 설치된 프리캐스트 바닥판(20) 위에 상기 제1크레인차량(3a) 보다 소형인 제2크레인차량(3b)을 진입시켜 일정간격씩 이동하면서 거더(2)의 상측면에 프리캐스트 바닥판(20)을 설치하게 된다.First, a method of installing the precast bottom plate 20 on the upper side of the girder 2 will be described with reference to FIG. 10. The first crane vehicle 3a is disposed on the bridge 1 to provide a first method. After the precast bottom plate 20 is installed within the working radius of the crane vehicle 3a, the section outside the working radius of the first crane vehicle 3a is first placed on the precast bottom plate 20 installed above. The pre-cracker plate 20 is installed on the upper side of the girder 2 while entering the second crane vehicle 3b which is smaller than the one crane vehicle 3a and moving at regular intervals.

좀더 상세히 설명하면, 상기 교량(1) 위에 제1크레인차량(3a)을 진입시키되, 상기 바닥판 교체 공사구간에 최대한 인접되게 상기 제1크레인차량(3a)을 진입시켜 배치하게 되고, 상기 제1크레인차량(3a)이 배치된 위치에는 별도의 운반차량을 통해 프리캐스트 바닥판(20)이 공급된다.In more detail, the first crane vehicle (3a) is entered on the bridge (1), the first crane vehicle (3a) is entered to be arranged as close as possible to the bottom plate replacement construction section, the first The precast bottom plate 20 is supplied to a position where the crane vehicle 3a is disposed through a separate transport vehicle.

이후, 상기 제1크레인차량(3a)은 운반차량을 통해 공급된 프리캐스트 바닥판(20)을 상기 거더(2)의 상측면에 안착 설치하게 되며, 이때 제1크레인차량(3a)으로 작업할 수 있는 반경까지 프리캐스트 바닥판(20)을 설치한다.Subsequently, the first crane vehicle 3a is installed on the upper side of the girder 2 to install the precast bottom plate 20 supplied through the transport vehicle, and at this time, the first crane vehicle 3a to work with the first crane vehicle 3a. Install the precast bottom plate 20 to a radius that can be.

여기서, 상기 제1크레인차량(3a)으로는 가급적 대형 크레인을 사용해야 한번에 작업할 수 있는 작업반경이 커지게 되므로 효율적이다.Here, the first crane vehicle (3a) is efficient because the work radius that can be worked at a time when the large crane should be used as possible increases.

상기 제1크레인차량(3a)을 통한 프리캐스트 바닥판(20) 설치가 완료되면, 상기 제1크레인차량(3a)의 작업반경을 벗어난 구간은 상기 제1크레인차량(3a) 보다 소형인 제2크레인차량(3b)을 이용하여 거더(2)의 상측면에 설치하게 되는데, 즉, 상기에서 제1크레인차량(3a)을 통해 먼저 설치된 프리캐스트 바닥판(20)은 아직 거더(2)와 합성되기 전이므로 상기 대형인 제1크레인차량(3a)은 프리캐스트 바닥판(20) 위로 진입하지 못한다.When the installation of the precast bottom plate 20 through the first crane vehicle 3a is completed, a section outside the working radius of the first crane vehicle 3a is smaller than the first crane vehicle 3a. It is installed on the upper side of the girder 2 by using the crane vehicle 3b, that is, the precast bottom plate 20 installed first through the first crane vehicle 3a is still composited with the girder 2. Since the large first crane vehicle 3a does not enter the precast bottom plate 20 because it is before.

따라서, 제1크레인차량(3a) 보다 상대적으로 소형인 제2크레인차량(3b)을 상기 거더(2)와 합성되기 전인 프리캐스트 바닥판(20) 위로 진입시켜, 나머지 바닥판 교체 구간내의 거더(2) 상측면에 프리캐스트 바닥판(20)을 설치하게 되는 것이다.Accordingly, the second crane vehicle 3b, which is relatively smaller than the first crane vehicle 3a, enters the precast sole plate 20 before being combined with the girder 2, and thus the girder in the remaining sole plate replacement section ( 2) Precast base plate 20 is to be installed on the upper side.

한편, 상기 제2크레인차량(3b)은 상기 프리캐스트 바닥판(20) 위로 진입하여 거더(2)의 상측면에 프리캐스트 바닥판(20)을 안착 설치하게 되는데, 이때 한번에 모두 설치할 수 없으므로 일정간격씩 이동하면서 프리캐스트 바닥판(20)을 설치하게 된다.On the other hand, the second crane vehicle 3b enters the precast bottom plate 20 and installs the precast bottom plate 20 on the upper side of the girder 2. The precast bottom plate 20 is installed while moving at intervals.

그리고, 상기 거더(2)와 합성되기 전인 프리캐스트 바닥판(20) 위에서 일정간격씩 전진하면서 이동하는 상기 제2크레인차량(3b) 위치까지 프리캐스트 바닥판(20)을 공급할 수 있도록, 상기 프리캐스트 바닥판(20) 위에는 레일(4)이 설치되고, 상기 레일(4)에는 상기 교량(1) 위의 제1크레인차량(3a)을 통해 공급받은 프리캐스트 바닥판(20)을 상기 제2크레인차량(3b) 위치까지 운반하는 대차(4a)가 설치된다.The precast bottom plate 20 may be supplied to a position of the second crane vehicle 3b moving forward by a predetermined interval on the precast bottom plate 20 before being combined with the girder 2. A rail 4 is installed on the cast bottom plate 20, and the precast bottom plate 20 supplied through the first crane vehicle 3a on the bridge 1 is mounted on the rail 4. The trolley | bogie 4a which conveys to the crane vehicle 3b position is provided.

즉, 상기 제2크레인차량(3b)이 프리캐스트 바닥판(20) 위에서 계속 일정간격씩 전진하면서 나머지 구간에 프리캐스트 바닥판(20)을 설치하게 되므로 상기 제2크레인차량(3b)이 위치한 곳까지 프리캐스트 바닥판(20)을 지속적으로 공급해줘야 작업이 가능하고 작업효율도 높일수 있다.That is, since the second crane vehicle 3b continues to advance on the precast bottom plate 20 at predetermined intervals and installs the precast bottom plate 20 in the remaining section, where the second crane vehicle 3b is located. Until you can continue to supply the precast floor plate 20 is possible to increase the work efficiency.

따라서, 본 발명에서는, 상기 프리캐스트 바닥판(20) 위에 양측에 레일(4)을 설치하고 상기 각 레일(4)에는 전동모터로 구동되는 대차(4a)를 각각 설치한 것이며, 상기 대차(4a)는 레일(4)을 타고 다니면서 상기 제1크레인차량(3a) 위치에서부터 상기 제2크레인차량(3b) 위치까지 왕복하게 된다.Therefore, in the present invention, the rails 4 are provided on both sides of the precast bottom plate 20, and the rails 4 are provided with trolleys 4a driven by electric motors, respectively. ) Is reciprocated from the position of the first crane vehicle 3a to the position of the second crane vehicle 3b while riding on the rail 4.

이때, 상기 제1크레인차량(3a)은 운반차량을 통해 공급된 프리캐스트 바닥판(20)을 상기 대차(4a) 위에 실게 되고, 상기 대차(4a)는 프리캐스트 바닥판(20)을 상기 제2크레인차량(3b) 위치까지 운반하여 제2크레인차량(3b)에 공급하게 된다.At this time, the first crane vehicle 3a loads the precast bottom plate 20 supplied through the transport vehicle on the trolley 4a, and the trolley 4a loads the precast bottom plate 20 on the first wheel. The second crane vehicle 3b is transported to the second crane vehicle 3b and supplied to the second crane vehicle 3b.

그리고, 상기 방호벽(40) 또는 방음벽용 철근(30) 설치 방법을 설명하면, 상기 프리캐스트 바닥판(20)은 별도의 장소에서 미리 제작되어 바닥판 교체 공사구간으로 공급되어 지는데, 이때 상기 프리캐스트 바닥판(20)의 최외곽에는 방호벽(40) 또는 방음벽용 철근(30)을 용이하게 설치할 수 있도록 베이스 철근(30a)이 미리 설치된 상태로 공급된다.In addition, the method for installing the barrier 40 or the soundproof wall reinforcing bar 30 will be described. The precast floor plate 20 is prefabricated in a separate place and supplied to the floorboard replacement construction section. In the outermost portion of the bottom plate 20, the base reinforcing bar 30a is supplied in a pre-installed state so that the protective wall 40 or the soundproof wall reinforcing bar 30 can be easily installed.

따라서, 작업자는 상기 제1크레인차량(3a) 또는 제2크레인차량(3b)을 통해 상기 거더(2)의 상측면에 프리캐스트 바닥판(20)이 안착 설치됨과 동시에 상기 프리캐스트 바닥판(20)의 최외곽에 기설치된 베이스 철근(30a)에 방호벽(40) 또는 방음벽용 철근(30)을 조립함으로써, 상기 프리캐스트 바닥판(20) 설치와, 방호벽(40) 또는 방음벽용 철근(30) 설치를 동시에 병행할 수 있으며, 이로인해 바닥판 교체공사를 신속하게 할 수 있어서 공사기간을 단축할 수 있고 공사비용도 줄일 수 있는 것이다.Therefore, the worker is mounted on the upper side of the girder 2 via the first crane vehicle 3a or the second crane vehicle 3b, and at the same time, the precast bottom plate 20 is installed. By prefabricating the protection wall 40 or the soundproof wall reinforcing bar 30 to the base reinforcing bar (30a) pre-installed in the outermost of the), the installation of the precast bottom plate 20, the barrier 40 or the soundproof wall rebar (30) The installation can be done at the same time, and thus the floor plate replacement work can be performed quickly, which can shorten the construction period and reduce the construction cost.

그리고, 본 발명에서는, 상기 바닥판 철거단계(S1)를 통해 바닥판(5) 철거 작업을 모두 완료한 후에 상기 면 정리단계(S2)와, 연결수단 설치단계(S3)와, 프리캐스트 바닥판 및 철근 설치 병행단계(S4)를 진행할 수도 있지만, 상기 바닥판 교체공사를 더욱 신속하게 하여 공사기간을 더욱 단축할 수 있도록, 도 7과 같이, 상기 바닥판 철거단계(S1)를 통해 상기 바닥판(5) 철거 작업이 진행되는 도중에 상기 거더(2)의 상측면에 프리캐스트 바닥판(20)을 설치할 수 있다.And, in the present invention, after completing the demolition work of the bottom plate 5 through the bottom plate demolition step (S1), the surface cleaning step (S2), the connecting means installation step (S3) and the precast floor plate And rebar installation parallel step (S4) may proceed, but to make the bottom plate replacement work more quickly to further shorten the construction period, as shown in Figure 7, the bottom plate through the demolition step (S1) (5) The precast bottom plate 20 may be installed on the upper side of the girder 2 while the demolition work is in progress.

즉, 상기 바닥판 철거단계(S1)에서 바닥판(5)이 먼저 철거된 거더(2)의 상측면에 상기 면 정리단계(S2)와, 연결수단 설치단계(S3)와, 프리캐스트 바닥판 및 철근 설치 병행단계(S4)를 병행할 수 있는 것이다.That is, in the bottom plate dismantling step (S1), the surface rearranging step (S2), the connecting means installation step (S3) and the precast bottom plate on the upper side of the girder 2, the bottom plate (5) is first removed And can be parallel to the rebar installation parallel step (S4).

다시말해, 도 7과 같이, 바닥판(5) 철거 작업과, 프리캐스트 바닥판(20) 및 철근(30) 설치 작업을 동시에 병행할 수 있는 것이다.
In other words, as shown in Fig. 7, the demolition work of the bottom plate 5 and the installation work of the precast bottom plate 20 and the reinforcing bar 30 can be performed at the same time.

마. 콘크리트 타설단계(S5),hemp. Concrete pouring step (S5),

상기 콘크리트 타설단계(S5)는, 도 8과 같이, 상기 프리캐스트 바닥판(20)과 상기 거더(2)를 합성시킴과 동시에 상기 프리캐스트 바닥판(20) 최외곽의 철근(30) 설치 부위에 방호벽(40) 또는 방음벽을 형성하도록 콘크리트를 타설하는 단계이다.In the concrete placing step (S5), as shown in Figure 8, the precast bottom plate 20 and the girder (2) at the same time as the precast bottom plate 20 outermost reinforcing bar 30 installation site Placing concrete to form a barrier 40 or a sound barrier in the.

즉, 종래에는 상기 거더의 상측면에 콘크리트를 현장 타설하여 바닥판이 양생된 후에 방호벽 또는 방음벽용 철근조립을 시작하지만, 본 발명에서는 전단계인 상기 프리캐스트 바닥판 및 철근 설치 병행단계(S4)에서 이미 철근(30) 조립이 완료되고, 상기 콘크리트 타설단계(S5)에서는 프리캐스트 바닥판(20)과 거더(2)의 합성을 위한 콘크리트 타설과 방호벽(40) 또는 방음벽 형성을 위한 콘크리트 타설만 하면되므로 공사기간을 더욱 단축시킬 수 있는 것이다.That is, in the prior art, the concrete is placed on the upper side of the girder after the bottom plate is cured to start the reinforcement for the protective wall or soundproof wall, but in the present invention, the precast floor plate and the rebar installation parallel step (S4) Assembly of the reinforcing bar 30 is completed, and in the concrete pouring step (S5), only the concrete pouring for the synthesis of the precast deck 20 and the girder 2 and the concrete 40 for the formation of the protective wall 40 or the soundproof wall, The construction period can be further shortened.

그리고, 상기 콘크리트 타설단계(S5)를 거친 후에는, 도 9와 같이, 상기 프리캐스트 바닥판(20)의 상측면에 일정두께의 아스팔트 또는 콘크리트 포장(50)을 실시하게 됨으로써, 바닥판 교체 시공이 완료되게 된다.And, after the concrete pouring step (S5), as shown in Figure 9, by performing an asphalt or concrete pavement 50 of a predetermined thickness on the upper side of the precast bottom plate 20, the bottom plate replacement construction Will be completed.

한편, 상기 프리캐스트 바닥판(20)과 거더(2)의 합성전에, 상기 거더(2)의 상측에 설치된 복수개의 프리캐스트 바닥판(20)에 프리스트레스를 먼저 도입하는 것이 바람직하다.On the other hand, before the synthesis of the precast bottom plate 20 and the girder 2, it is preferable to first introduce prestress into the plurality of precast bottom plates 20 provided on the upper side of the girder 2.

1: 교량 2: 거더
5: 바닥판 6: 방호벽
10: 연결수단 20: 프리캐스트 바닥판
30: 철근 30a: 베이스 철근
40: 방호벽
S1: 바닥판 철거단계 S2: 면 정리단계
S3: 연결수단 설치단계
S4: 프리캐스트 바닥판 및 철근 설치 병행단계
S5: 콘크리트 타설단계
1: bridge 2: girder
5: bottom plate 6: firewall
10: connecting means 20: precast bottom plate
30: rebar 30a: base rebar
40: firewall
S1: Demolition of Slab
S3: installation step of connecting means
S4: Parallel installation of precast deck and rebar
S5: Concrete pouring step

Claims (5)

교량(1)의 거더(2) 상측에 설치된 바닥판(5)을 교체하기 위한 교량의 바닥판 교체 시공 방법에 있어서,
상기 거더(2)의 상측에 설치된 바닥판(5)을 철거하되, 바닥판(5)의 최외곽에 설치되어 있는 방호벽(6) 또는 방음벽까지 모두 철거하는 바닥판 철거단계(S1)와,
상기 바닥판(5)이 철거된 상기 거더(2) 상측의 면을 정리하는 면 정리단계(S2)와,
상기 거더(2)의 상측면에 프리캐스트 바닥판(20)과의 합성을 위한 연결수단(10)을 설치하는 연결수단 설치단계(S3)와,
상기 연결수단(10)이 설치된 거더(2)의 상측면에 프리캐스트 바닥판(20)을 안착 설치함과 동시에 프리캐스트 바닥판(20)의 최외곽에 방호벽(40) 또는 방음벽을 설치하기 위한 철근(30)을 설치하는 프리캐스트 바닥판 및 철근 설치 병행단계(S4)와,
상기 프리캐스트 바닥판(20)과 상기 거더(2)를 합성시킴과 동시에 상기 철근(30) 설치 부위에 방호벽(40) 또는 방음벽을 형성하도록 콘크리트를 타설하는 콘크리트 타설단계(S5)를 포함하여 이루어지되,
상기 프리캐스트 바닥판 및 철근 설치 병행단계(S4)에서 상기 프리캐스트 바닥판(20) 설치시에는, 상기 교량(1) 위에 제1크레인차량(3a)을 배치하여 제1크레인차량(3a)의 작업반경내에 프리캐스트 바닥판(20)을 설치한 후, 상기 제1크레인차량(3a)의 작업반경을 벗어난 구간은 상기에서 먼저 설치된 프리캐스트 바닥판(20) 위에 상기 제1크레인차량(3a) 보다 소형인 제2크레인차량(3b)을 진입시켜 일정간격씩 이동하면서 거더(2)의 상측면에 프리캐스트 바닥판(20)을 설치하며,
상기 프리캐스트 바닥판(20) 위에서 일정간격씩 이동하는 상기 제2크레인차량(3b) 위치까지 프리캐스트 바닥판(20)을 공급할 수 있도록, 상기 프리캐스트 바닥판(20) 위에는 레일(4)이 설치되고, 상기 레일(4)에는 상기 교량(1) 위의 제1크레인차량(3a)을 통해 공급받은 프리캐스트 바닥판(20)을 상기 제2크레인차량(3b) 위치까지 운반하는 대차(4a)가 설치되는 것을 특징으로 하는 프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법.
In the bridge plate replacement construction method of the bridge for replacing the bottom plate 5 installed on the upper side of the girder 2 of the bridge (1),
A bottom plate demolition step (S1) of dismantling the bottom plate 5 installed on the upper side of the girder 2, but removing all of the protection wall 6 or the soundproof wall installed at the outermost part of the bottom plate 5;
A surface rearranging step (S2) for arranging the upper surface of the girder 2 on which the bottom plate 5 is removed;
Connection means installation step (S3) for installing the connection means 10 for the synthesis with the precast bottom plate 20 on the upper side of the girder (2),
In order to install the precast bottom plate 20 on the upper side of the girder 2 in which the connecting means 10 is installed, and to install the protective wall 40 or the soundproof wall at the outermost side of the precast bottom plate 20. Precast deck and rebar installation parallel step (S4) for installing the reinforcing bar 30,
Including the concrete cast step (S5) to the concrete to form a protective wall (40) or a soundproof wall on the reinforcing bar 30 installation site while synthesizing the precast bottom plate 20 and the girder (2). Understand,
When the precast bottom plate 20 is installed in the precast bottom plate and reinforcing bar installation step S4, the first crane vehicle 3a is disposed on the bridge 1 to form the first crane vehicle 3a. After the precast bottom plate 20 is installed in the working radius, a section outside the working radius of the first crane vehicle 3a is placed on the first crane vehicle 3a on the precast bottom plate 20 installed above. The precast bottom plate 20 is installed on the upper side of the girder 2 while entering a smaller second crane vehicle 3b and moving at regular intervals.
On the precast bottom plate 20, a rail 4 is provided on the precast bottom plate 20 so that the precast bottom plate 20 can be supplied to the position of the second crane vehicle 3b moving at predetermined intervals on the precast bottom plate 20. The rail 4 is provided with a trolley 4a for carrying the precast bottom plate 20 supplied through the first crane vehicle 3a on the bridge 1 to the position of the second crane vehicle 3b. Construction method for replacing the floor plate of the bridge using a precast floor plate, characterized in that is installed.
제 1 항에 있어서,
상기 바닥판 철거단계(S1)를 통해 상기 바닥판(5) 철거 작업이 진행되는 도중에 상기 바닥판(5)이 먼저 철거된 거더(2)의 상측면에는 상기 면 정리단계(S2)와 연결수단 설치단계(S3)와 프리캐스트 바닥판 및 철근 설치 병행단계(S4)를 병행하는 것을 특징으로 하는 프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법.
The method of claim 1,
Connecting means and the surface arrangement step (S2) on the upper side of the girder (2) where the bottom plate (5) is first dismantled during the demolition operation of the bottom plate (5) through the bottom plate removal step (S1) Construction method for replacing the floor plate of the bridge using a precast floor plate, characterized in that parallel to the installation step (S3) and the precast floor plate and rebar installation parallel step (S4).
제 1 항에 있어서,
상기 프리캐스트 바닥판 및 철근 설치 병행단계(S4)는, 상기 거더(2)의 상측면에 프리캐스트 바닥판(20)의 설치가 완료되는 시점에 상기 방호벽(40) 또는 방음벽용 철근(30) 설치도 완료되는 단계인 것을 특징으로 하는 프리캐스트 바닥판을 이용한 교량의 바닥판 교체 시공 방법.
The method of claim 1,
The precast bottom plate and the reinforcing bar installation step (S4), at the time when the installation of the precast bottom plate 20 on the upper side of the girder 2, the barrier 40 or the sound barrier wall (30) Installation method of the bridge bottom plate replacement using the precast bottom plate, characterized in that the installation step is completed.
삭제delete 삭제delete
KR1020110036517A 2011-04-20 2011-04-20 Deck repairing construction method of bridge using precast concrete slab KR101270947B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110036517A KR101270947B1 (en) 2011-04-20 2011-04-20 Deck repairing construction method of bridge using precast concrete slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110036517A KR101270947B1 (en) 2011-04-20 2011-04-20 Deck repairing construction method of bridge using precast concrete slab

Publications (2)

Publication Number Publication Date
KR20120118884A KR20120118884A (en) 2012-10-30
KR101270947B1 true KR101270947B1 (en) 2013-06-11

Family

ID=47286220

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110036517A KR101270947B1 (en) 2011-04-20 2011-04-20 Deck repairing construction method of bridge using precast concrete slab

Country Status (1)

Country Link
KR (1) KR101270947B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102618251B1 (en) 2023-07-25 2023-12-27 (주) 대현이엔씨 Bridge Deck Replacement Construction Method
KR102705907B1 (en) 2023-09-26 2024-09-11 (주)지승씨앤아이 Repair and partial replacement method of bridge deck with arched modules for punching shear failure reinforcement

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104110002B (en) * 2014-07-10 2017-09-19 中铁大桥局武汉桥梁特种技术有限公司 A kind of method for changing steel truss girder bridge floorings
CN105714700B (en) * 2016-04-29 2018-03-02 长安大学 Concrete slab surface consolidation system and reinforcement means
CN106320192B (en) * 2016-10-27 2018-10-09 武汉理工大学 A kind of beam section replacing and reinforcing method for large span concrete continuous beam bridge

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010045640A (en) * 1999-11-05 2001-06-05 장승필 Precast Reinforced Concrete Slab, Composite Continuous Bridge Having Such Slab, and Constructing Method thereof
KR20060117642A (en) * 2005-05-13 2006-11-17 주식회사 효성엘비데크 Construction method of slab for bridge without support bar

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010045640A (en) * 1999-11-05 2001-06-05 장승필 Precast Reinforced Concrete Slab, Composite Continuous Bridge Having Such Slab, and Constructing Method thereof
KR20060117642A (en) * 2005-05-13 2006-11-17 주식회사 효성엘비데크 Construction method of slab for bridge without support bar

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102618251B1 (en) 2023-07-25 2023-12-27 (주) 대현이엔씨 Bridge Deck Replacement Construction Method
KR102705907B1 (en) 2023-09-26 2024-09-11 (주)지승씨앤아이 Repair and partial replacement method of bridge deck with arched modules for punching shear failure reinforcement

Also Published As

Publication number Publication date
KR20120118884A (en) 2012-10-30

Similar Documents

Publication Publication Date Title
JP5847483B2 (en) Bridge wall railing method
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
JP2015151768A5 (en)
KR101270947B1 (en) Deck repairing construction method of bridge using precast concrete slab
JP2013036206A (en) Structure for joining precast barrier curbs to each other
KR101118257B1 (en) Deck for concrete slab construction
JP6889010B2 (en) Bridge construction method
JP4477467B2 (en) Bridge structure and its replacement method
KR100603901B1 (en) Girder bridge construction make use of a part existing girder and that execution method
JP2017053117A (en) Renewal method for existing road, and renewed road
KR101258841B1 (en) Precast concrete slab construction method of bridge
CN105926820B (en) Construction method for precast beam steel support plate resistance mesh combined floor
KR100758878B1 (en) Method for repairing bridge using integrated girder-concrete slab assembly
JP7134133B2 (en) Bridge railing construction method
KR20200139572A (en) Bridge upper structure with rrecast slab
KR200240457Y1 (en) Frame for substitu ting steel girder of a railway bridge for concrete slab
KR100729844B1 (en) Repair work of railroad bridge and that structure
JP7239356B2 (en) Concrete slab replacement method for highway bridges
JP7021386B1 (en) How to replace the wall rail
JP7153475B2 (en) Floor slab renewal method and girder bridge structure
CN108979133A (en) A kind of close rib building roof mold and application method
JP2024151537A (en) Bridges and their construction methods
JP2009243075A (en) Prestressed concrete mold form, foundation structure of building using the prestressed concrete mold form, and method of constructing the foundation structure
KR101156013B1 (en) Method of constructing bride deck using precast concrete deck and bridge superstructure thereof
KR100629905B1 (en) Reinforcement method for existing bridges and bridges production it

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20160524

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170524

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20180704

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20190503

Year of fee payment: 7