JP2024151537A - Bridges and their construction methods - Google Patents

Bridges and their construction methods Download PDF

Info

Publication number
JP2024151537A
JP2024151537A JP2023064963A JP2023064963A JP2024151537A JP 2024151537 A JP2024151537 A JP 2024151537A JP 2023064963 A JP2023064963 A JP 2023064963A JP 2023064963 A JP2023064963 A JP 2023064963A JP 2024151537 A JP2024151537 A JP 2024151537A
Authority
JP
Japan
Prior art keywords
precast
bridge
bridge axis
substructure
vertical beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2023064963A
Other languages
Japanese (ja)
Inventor
達斗 堀内
Tatsuto Horiuchi
潔 桐川
Kiyoshi Kirikawa
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ps Construction Co Ltd
Original Assignee
Ps Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ps Construction Co Ltd filed Critical Ps Construction Co Ltd
Priority to JP2023064963A priority Critical patent/JP2024151537A/en
Publication of JP2024151537A publication Critical patent/JP2024151537A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

To provide a bridge and its construction method capable of reducing a burden on a lower structure such as a bridge pier and shortening a construction period.SOLUTION: A bridge 1 comprises a substructure transverse beam 4 supported on the upper parts of each lower structure 3a, 3a in the direction perpendicular to the bridge-axis, vertical girder parts LB, LB composed of one or a plurality of hollow rectangular parallelepiped precast vertical girder members 6, 6 directed in the bridge-axis direction supported on the substructure transverse beam 4 through bearing members 5, and precast slab 7 installed between vertical girder parts LB, LB adjacent to each other at an interval in the direction perpendicular to the bridge axis, and prestress is introduced by a post-tensioning system over the whole width in the direction perpendicular to the bridge axis of a superstructure 8 by PC steel materials 9, 9... inserted in the direction perpendicular to the bridge axis of the superstructure 8 comprising the precast vertical girder members 6, 6 and the precast slab 7.SELECTED DRAWING: Figure 3

Description

本発明は、高架道路等を含む橋梁を架け替え又は新たに構築する橋梁及びその構築方法に関する。 The present invention relates to a bridge and a method for constructing a new bridge, including an elevated road, or to replace the existing bridge.

近年、コンクリート製の橋梁は、経年劣化に加え、車両の大型化による使用環境の悪化や凍結防止剤散布の影響等による老朽化が問題となっており、橋梁の架け替え工事による大規模更新工事が進められている。 In recent years, concrete bridges have been facing problems with deterioration due to age, as well as the worsening environment caused by larger vehicles and the effects of antifreeze spraying, and large-scale renovation work is underway to replace bridges.

特に、RC中空床版橋は、死荷重の軽減等を目的として、橋脚等の下部構造体に支持された床版の内部に空隙部を設けているため、凍結防止剤による塩害や凍害に加え、空隙部を設けたことでかぶりが十分に確保し難いこともあり、重交通や浸透水の影響で上面部に変状が生じやすくなっており、上面部に変状を来した場合、床版全体を更新する必要がある。 In particular, RC hollow deck bridges have gaps inside the deck that are supported by substructures such as piers in order to reduce dead loads, making them susceptible to salt and frost damage from antifreeze agents, and because the gaps make it difficult to ensure sufficient cover, the upper surface is prone to deformation due to heavy traffic and seepage water. If deformation occurs in the upper surface, the entire deck must be replaced.

また、RC中空床版橋は、高架橋の標準構造として数多く採用されており、今後、多くの更新工事が必要になると思われる。 In addition, RC hollow deck bridges are widely used as the standard structure for viaducts, and it is expected that many renewal works will be required in the future.

従来、このようなRC中空床版橋等の橋梁の架け替え方法としては、支保工又はガーダーを用いて既設の上部工を撤去した後、撤去した部分に新たに中空床版や鋼鈑桁橋を構築する工法が一般に用いられている。 Conventionally, the most common method for replacing bridges such as RC hollow deck bridges has been to remove the existing superstructure using shoring or girders, and then build a new hollow deck or steel girder bridge in the removed area.

また、その他の工法としては、既設上部工を撤去した後、橋脚または橋台等の下部構造体上に橋軸直角方向に向けたプレキャスト横梁を設置し、そのプレキャスト横梁上に中空直方体状の複数のプレキャスト縦桁部材を橋軸直角方向に並べて敷設して中空床版を構築する方法も開発されている(例えば、特許文献1を参照)。 Another construction method that has been developed is to remove the existing superstructure, then install precast cross beams perpendicular to the bridge axis on the substructure such as piers or abutments, and then lay multiple hollow rectangular precast vertical beam members on the precast cross beams in a direction perpendicular to the bridge axis to construct a hollow deck (see, for example, Patent Document 1).

また、この種の橋梁の架け替えにおいては、床版等の既設上部工の撤去に伴い通行規制が行われることから、通行規制による社会的損失を最小限に抑えるため、短期間で取替えを行うことが可能な工法が求められている。 In addition, when replacing this type of bridge, traffic restrictions are imposed due to the removal of the existing superstructure, such as the deck, so there is a demand for a construction method that allows replacement in a short period of time to minimize the social losses caused by traffic restrictions.

特開2009-256873号公報JP 2009-256873 A

しかしながら、上述の特許文献1に示す如き従来技術では、橋脚または橋台等の下部構造体上に設置したプレキャスト横梁上に複数のプレキャスト縦桁部材を橋軸直角方向に並べて敷設することから、上部工全体の重量が増加し、それを支持する下部構造体の耐力不足が懸念される。 However, in the conventional technology shown in Patent Document 1 mentioned above, multiple precast vertical beam members are laid in a line perpendicular to the bridge axis on precast cross beams installed on substructures such as piers or abutments, which increases the weight of the entire superstructure and raises concerns about the insufficient strength of the substructures that support it.

また、従来の技術では、既設上部工を撤去した後でなければプレキャスト横梁を設置することができず、既設上部工の撤去からプレキャスト横桁の設置を経て新たな床版部が形成されるまでのすべての期間において通行規制を行わなくてはならず、通行規制による社会的損失が大きくなるという問題があった。 Furthermore, with conventional technology, precast cross beams could only be installed after the existing superstructure had been removed, meaning that traffic restrictions had to be implemented throughout the entire period from the removal of the existing superstructure through the installation of the precast cross beams to the formation of the new deck, resulting in significant social losses due to the traffic restrictions.

そこで、本発明は、このような従来の問題に鑑み、橋脚等の下部構造体の負担を軽減でき、且つ、工期の短縮を図ることができる橋梁及びその構築方法の提供を目的としてなされたものである。 In view of these conventional problems, the present invention was made with the aim of providing a bridge and a method for constructing the same that can reduce the burden on substructures such as bridge piers and shorten the construction period.

上述の如き従来の問題を解決するための請求項1に記載の発明の特徴は、橋軸方向に間隔をおいて立設された下部構造体間に上部工が架設されてなる橋梁において、前記各下部構造体の上部に橋軸直角方向に向けて支持された下部工横梁と、該下部工横梁上に支承部材を介して支持された橋軸方向に向けた一又は複数の中空直方体状のプレキャスト縦桁部材からなる縦桁部と、橋軸直角方向で間隔をおいて隣り合う前記縦桁部間に架設されたプレキャスト版とを備えるとともに、前記下部工横梁上の間隔をおいて隣り合う前記縦桁部と前記プレキャスト版に囲まれた部分がコンクリートで充填されてなる横梁部が形成され、前記プレキャスト縦桁部材と前記プレキャスト版とからなる床版部の橋軸直角方向全幅に亘って挿通されたPC鋼材と、前記横梁部の橋軸直角方向全幅に亘って挿通されたPC鋼材とにより前記縦桁部、前記プレキャスト版及び前記横桁部からなる構造体の橋軸直角方向全幅に亘ってポストテンション方式によりプレストレスが導入されていることにある。 The feature of the invention described in claim 1 for solving the above-mentioned conventional problems is that in a bridge in which a superstructure is erected between substructures erected at intervals in the bridge axis direction, the bridge comprises a substructure cross beam supported on the upper part of each substructure in a direction perpendicular to the bridge axis, a vertical beam section made of one or more hollow rectangular parallelepiped precast vertical beam members facing in the bridge axis direction and supported on the substructure cross beams via bearing members, and a precast plate erected between adjacent vertical beam sections at intervals in the direction perpendicular to the bridge axis, and The cross beam is formed by filling the area surrounded by the adjacent vertical beams and the precast plate with concrete at a distance above the cross beam, and prestress is introduced by the post-tensioning method across the entire width of the structure consisting of the vertical beams, the precast plate, and the cross beam, in the direction perpendicular to the bridge axis, by the PC steel inserted across the entire width of the deck section consisting of the precast vertical beam members and the precast plate, and the PC steel inserted across the entire width of the cross beam in the direction perpendicular to the bridge axis.

請求項2に記載の発明の特徴は、請求項1の構成に加え、前記下部工横梁は、前記下部構造体の上端より所定の高さ分だけ低い位置に支持されていることにある。 The invention described in claim 2 is characterized in that, in addition to the configuration of claim 1, the substructure cross beam is supported at a position a predetermined height lower than the upper end of the substructure.

請求項3に記載の発明の特徴は、請求項1又は2の構成に加え、前記プレキャスト版には橋軸方向に向けたPC鋼材によりプレテンション方式によるプレストレスが導入されていることにある。 The invention described in claim 3 is characterized in that, in addition to the configuration of claim 1 or 2, prestress is introduced to the precast slab by the pretensioning method using PC steel members oriented in the bridge axis direction.

請求項4に記載の発明の特徴は、橋軸方向に間隔をおいて立設された下部構造体間に上部工が架設されてなる橋梁の構築方法において、前記各下部構造体の上部に橋軸直角方向に向けた下部工横梁を支持させ、該下部工横梁上に支承部材を介して橋軸方向に向けた一又は複数の中空直方体状のプレキャスト縦桁部材を支持させて縦桁部を形成し、しかる後、橋軸直角方向で間隔をおいて隣り合う前記縦桁部間にプレキャスト版を架設し、前記下部工横梁上の間隔をおいて隣り合う前記縦桁部と前記プレキャスト版に囲まれた部分にコンクリートを打設して横梁部を形成し、前記プレキャスト縦桁部材と前記プレキャスト版とからなる床版部の橋軸直角方向全幅に亘ってPC鋼材を挿通させるとともに、前記横梁部の橋軸直角方向全幅に亘ってPC鋼材を挿通させ、該PC鋼材により前記縦桁部、前記プレキャスト版及び前記横桁部からなる構造体の橋軸直角方向全幅に亘ってポストテンション方式によりプレストレスを導入することにある。 The invention described in claim 4 is characterized in that in a method of constructing a bridge in which a superstructure is erected between substructures erected at intervals in the bridge axis direction, a substructure cross beam facing perpendicular to the bridge axis is supported on the upper part of each substructure, and one or more hollow rectangular parallelepiped precast vertical beam members facing the bridge axis direction are supported on the substructure cross beams via bearing members to form vertical beam sections, after which precast panels are erected between adjacent vertical beam sections at intervals in the bridge axis direction, and adjacent vertical beam members are supported at intervals on the substructure cross beams. Concrete is poured into the area surrounded by the interlocking vertical beams and the precast slab to form the cross beams, and PC steel is inserted through the entire width of the deck section consisting of the precast vertical beams and the precast slab in the direction perpendicular to the bridge axis, and PC steel is inserted through the entire width of the cross beam in the direction perpendicular to the bridge axis, and the PC steel introduces prestress by post-tensioning across the entire width of the structure consisting of the vertical beams, the precast slab, and the cross beam in the direction perpendicular to the bridge axis.

請求項5に記載の発明の特徴は、橋軸方向に間隔をおいて立設された下部構造体間に架設された既設上部工を新たな上部工に架け替えて構築する橋梁の構築方法において、既設上部工を支持する前記下部構造体の上端より所定の距離だけ低い位置に橋軸直角方向に向けた下部工横梁を予め構築しておき、前記既設上部工を撤去した後、前記下部工横梁の前記下部構造体上端部を挟んだ両側にそれぞれ支承部材を介して橋軸方向に向けた一又は複数の中空直方体状のプレキャスト縦桁部材を支持させて縦桁部を形成し、しかる後、前記下部構造体上端部を挟んで間隔をおいて隣り合う前記縦桁部間にプレキャスト版を架設し、前記下部工横梁上の間隔をおいて隣り合う前記縦桁部と前記プレキャスト版に囲まれた部分にコンクリートを打設して横梁部を形成し、前記プレキャスト縦桁部材と前記プレキャスト版とからなる床版部の橋軸直角方向全幅に亘ってPC鋼材を挿通させるとともに、前記横梁部の橋軸直角方向全幅に亘ってPC鋼材を挿通させ、該PC鋼材により前記縦桁部、前記プレキャスト版及び前記横桁部からなる構造体の橋軸直角方向全幅に亘ってポストテンション方式によりプレストレスを導入することにある。 The invention described in claim 5 is characterized in that, in a bridge construction method in which an existing superstructure erected between substructures erected at intervals in the bridge axis direction is replaced with a new superstructure, a substructure cross beam facing perpendicular to the bridge axis is constructed in advance at a position a predetermined distance lower than the upper end of the substructure supporting the existing superstructure, and after removing the existing superstructure, one or more hollow rectangular parallelepiped precast vertical beam members facing in the bridge axis direction are supported via bearing members on both sides of the upper end of the substructure of the substructure to form a vertical beam portion, and then the upper end of the substructure is sandwiched between the substructure and the horizontal beam, forming a vertical beam portion. A precast plate is erected between the adjacent vertical beams, concrete is poured into the area surrounded by the adjacent vertical beams and the precast plate at a distance on the substructure cross beam to form a cross beam, PC steel is inserted through the entire width of the deck section consisting of the precast vertical beam member and the precast plate in the direction perpendicular to the bridge axis, and PC steel is inserted through the entire width of the cross beam in the direction perpendicular to the bridge axis, and prestress is introduced by the post-tensioning method using the PC steel across the entire width of the structure consisting of the vertical beams, the precast plate, and the cross beam in the direction perpendicular to the bridge axis.

さらに、請求項6に記載の発明の特徴は、請求項4又は5の構成に加え、前記支承部材上に設置された桁受板材の橋軸直角方向両端部を、仮支承部材を介して前記下部工横梁に支持させた状態で、前記桁受板材上に複数の前記プレキャスト縦桁部材を橋軸直角方向に並べて設置し、前記PC鋼材により前記縦桁部、前記プレキャスト版及び前記横桁部からなる構造体の橋軸直角方向全幅に亘ってポストテンション方式によりプレストレスを導入した後、前記仮支承部材を撤去することにある。 Furthermore, the invention described in claim 6 is characterized in that, in addition to the configuration of claim 4 or 5, both ends of the girder support plate material installed on the support member perpendicular to the bridge axis are supported by the substructure cross beam via temporary support members, and multiple precast vertical beam members are installed in a line perpendicular to the bridge axis on the girder support plate material, and prestress is introduced by the post-tensioning method using the PC steel material across the entire width perpendicular to the bridge axis of the structure consisting of the vertical beam section, the precast plate, and the cross beam section, and then the temporary support members are removed.

請求項7に記載の発明の特徴は、請求項4又は5の構成に加え、前記プレキャスト版には橋軸方向に向けたPC鋼材によりプレテンション方式によるプレストレスが導入されていることにある。 The invention described in claim 7 is characterized in that, in addition to the configuration of claim 4 or 5, prestress is introduced to the precast slab by the pretensioning method using PC steel members oriented in the bridge axis direction.

本発明に係る橋梁は、請求項1に記載の構成を具備することによって、上部工全体の重量を軽減し、橋脚や橋台等の下部構造体の負担軽減を図ることができる。 By being provided with the configuration described in claim 1, the bridge of the present invention can reduce the weight of the entire superstructure and the burden on the substructure such as piers and abutments.

また、本発明において、請求項2に記載の構成を具備することによって、下部構造体の上端よりプレキャスト縦桁部材を支持する位置が下がる分、プレキャスト縦桁部材の桁高を大きくとることができる。また、既存の上部工を供用に供したまま、改修工事に着手することができ、工期の短縮を図り、通行規制による社会的損失を軽減することができる。 In addition, in the present invention, by providing the configuration described in claim 2, the position where the precast vertical beam members are supported is lower than the upper end of the lower structure, and the girder height of the precast vertical beam members can be increased accordingly. In addition, renovation work can be started while the existing superstructure remains in service, shortening the construction period and reducing social losses due to traffic restrictions.

また、本発明において、請求項3に記載の構成を具備することによって、プレキャスト縦桁部材間に架設されたプレキャスト床版の強度を高め、高強度の上部工を構築することができる。 In addition, in the present invention, by providing the configuration described in claim 3, the strength of the precast deck installed between the precast stringer members can be increased, and a high-strength superstructure can be constructed.

本発明に係る橋梁の構築方法は、請求項4に記載の構成を具備することによって、上部工全体の重量を軽減し、橋脚や橋台等の下部構造体の負担軽減を図ることができる The bridge construction method according to the present invention, by incorporating the configuration described in claim 4, can reduce the weight of the entire superstructure and reduce the burden on the substructure such as piers and abutments.

また、本発明において、請求項5に記載の構成を具備することによって、既存の上部工を供用に供したまま、改修工事に着手することができ、工期の短縮を図り、通行規制による社会的損失を軽減することができる。 In addition, by providing the configuration described in claim 5 of the present invention, it is possible to begin repair work while keeping the existing superstructure in service, shortening the construction period and reducing social losses due to traffic restrictions.

さらに、本発明において、請求項6に記載の構成を具備することによって、一の支承部材で複数のプレキャスト縦桁部材を支持させることができる。 Furthermore, in the present invention, by providing the configuration described in claim 6, it is possible to support multiple precast stringer members with one support member.

さらにまた、本発明において、請求項7に記載の構成を具備することによって、プレキャスト縦桁部材間に架設されたプレキャスト床版の強度を高め、高強度の上部工を構築することができる。 Furthermore, in the present invention, by providing the configuration described in claim 7, the strength of the precast deck installed between the precast stringer members can be increased, and a high-strength superstructure can be constructed.

本発明に係る橋梁の一例を示す側面図である。FIG. 1 is a side view showing an example of a bridge according to the present invention. 図1中のA-A線矢視断面図である。2 is a cross-sectional view taken along line AA in FIG. 1. 同上の上部工を支持する構造部分を示す拡大A-A線矢視断面図である。This is an enlarged cross-sectional view taken along line A-A, showing the structural portion supporting the above-mentioned superstructure. 同上の上部工を支持する構造部分を示す拡大B-B線矢視断面図である。This is an enlarged cross-sectional view along line B-B showing the structural portion supporting the above-mentioned superstructure. (a)は同上のプレキャスト縦桁部材の端部を示す平面図、(b)は同端部の側面図、(c)は同C-C線矢視断面図である。1A is a plan view showing the end of the precast vertical beam member of the same, FIG. 1B is a side view of the same end, and FIG. 1C is a cross-sectional view taken along line CC of the same. (a)は同上のプレキャスト版を示す平面図、(b)は同側面図、(c)は同断面図である。1A is a plan view of the precast slab shown in FIG. 1A, FIG. 1B is a side view of the same, and FIG. 同上のプレキャスト版間の接合部分を示す平面図である。FIG. 2 is a plan view showing the joint between the precast slabs. 本発明に係る橋梁の構築方法の手順を示す拡大断面図であって、(a)は既存の上部工が設置された状態の図、(b)は下部工横梁を構築した状態を示す図、(c)は支承部材を設置した状態を示す図である。FIG. 1 is an enlarged cross-sectional view showing the steps of the bridge construction method according to the present invention, in which (a) shows the state after the existing superstructure has been installed, (b) shows the state after the substructure cross beam has been constructed, and (c) shows the state after the support member has been installed. (d)は同上のプレキャスト縦桁部材を設置した状態を示す図、(e)は同プレキャスト版を架設した状態を示す図、(f)は同下部工横梁上の両プレキャスト縦桁部材とプレキャスト版に囲まれた部分にコンクリートを打設した状態を示す図である。(d) is a diagram showing the above-mentioned precast vertical beam members after installation, (e) is a diagram showing the same precast plate after it has been erected, and (f) is a diagram showing the state in which concrete has been poured into the area surrounded by both precast vertical beam members and the precast plate on the same substructure cross beam. (g)は同上の上部工の全幅に亘ってプレストレスを導入した状態を示す図、(h)は完成した橋梁を示す図である。4(g) shows the state in which prestress has been introduced across the entire width of the superstructure, and FIG. 4(h) shows the completed bridge.

次に、本発明に係る橋梁及びその構築方法の実施態様を図1~図10に示した実施例に基づいて説明する。尚、図中符号1は橋梁、符号2は地盤である。 Next, an embodiment of a bridge and a method for constructing the bridge according to the present invention will be described based on the examples shown in Figures 1 to 10. In the figures, reference numeral 1 denotes a bridge and reference numeral 2 denotes the ground.

橋梁1は、橋軸方向に間隔をおいて立設された橋脚等の下部構造体3と、下部構造体3の上部に支持された橋軸直角方向に向けた下部工横梁4と、下部工横梁4上に橋軸直角方向に間隔をおいて配置された支承部材5と、各支承部材5を介して設置された一又は複数のプレキャスト縦桁部材6,6からなる縦桁部LB,LBと、橋軸直角方向に間隔をおいて隣り合う縦桁部LB,LB間に架設されたプレキャスト版7とを備え、下部工横梁4上の隣り合う縦桁部LB,LBとプレキャスト版7に囲まれた部分がコンクリート23で充填されてなる横梁部WBが形成され、プレキャスト縦桁部材6,6及びプレキャスト版7とからなる上部工8(床版部)の橋軸直角方向に挿通させたPC鋼材9,9…と、横梁部WBの橋軸直角方向全幅に亘って挿通させたPC鋼材9,9…により縦桁部LB,LB、プレキャスト版7及び横桁部WBからなる構造体8(以下、上部工8という)の橋軸直角方向全幅に亘ってポストテンション方式によりプレストレスが導入されている。 The bridge 1 comprises a substructure 3 such as a pier erected at intervals in the bridge axis direction, a substructure cross beam 4 oriented perpendicular to the bridge axis and supported on the upper part of the substructure 3, support members 5 arranged at intervals in the direction perpendicular to the bridge axis on the substructure cross beam 4, vertical beam sections LB, LB consisting of one or more precast vertical beam members 6, 6 installed via each support member 5, and a precast plate 7 erected between adjacent vertical beam sections LB, LB at intervals in the direction perpendicular to the bridge axis. The area surrounded by the slab 7 is filled with concrete 23 to form the cross beam section WB, and prestress is introduced by the post-tensioning method across the entire width of the structure 8 (hereafter referred to as the superstructure 8) consisting of the vertical beam sections LB, LB, precast slab 7, and cross beam section WB in the direction perpendicular to the bridge axis using PC steel members 9, 9... inserted perpendicular to the bridge axis into the superstructure 8 (deck section) consisting of the precast vertical beam members 6, 6 and precast slab 7, and PC steel members 9, 9... inserted across the entire width of the cross beam section WB in the direction perpendicular to the bridge axis.

ここで、下部構造体3とは、地盤2に立設され、上部工8を支持する構造体であって、橋梁1の両端部が支持される橋台、両橋台間にあって上部工8の下面を支持する橋脚及び橋脚を構成する複数の脚体3a,3aや分岐した部分等とを含むものとする。 Here, the substructure 3 is a structure erected on the ground 2 and supporting the superstructure 8, and includes the abutments on which both ends of the bridge 1 are supported, the piers located between the abutments and supporting the underside of the superstructure 8, and the multiple legs 3a, 3a and branched parts that make up the piers.

橋脚3は、図1、図2に示すように、橋軸直角方向に間隔をおいてフーチング3bに支持された複数(本実施例では一対)の脚体3a,3aを備え、下部工横梁4が両脚体3a,3aに跨って支持されている。 As shown in Figures 1 and 2, the pier 3 has multiple legs 3a, 3a (a pair in this embodiment) supported by a footing 3b at intervals perpendicular to the bridge axis, and the substructure cross beam 4 is supported across both legs 3a, 3a.

下部工横梁4は、鉄筋コンクリート造又はプレストレストコンクリート造の直方体状に形成され、各脚体3a,3aに支持されている。 The substructure cross beam 4 is made of reinforced concrete or prestressed concrete and is rectangular, and is supported by each leg 3a, 3a.

この下部工横梁4は、橋梁1の橋軸直角方向幅と略同じ長さを有し、脚体3a,3aに支持されて脚体3a,3aの両外側部及び脚体3a,3a間に少なくとも設置される一又は複数のプレキャスト縦桁部材6,6が設置可能な分の幅が確保されている。 This substructure cross beam 4 has a length approximately equal to the width of the bridge 1 perpendicular to the bridge axis, and is wide enough to accommodate one or more precast vertical beam members 6, 6 that are supported by the legs 3a, 3a and installed at least on both outer sides of the legs 3a, 3a and between the legs 3a, 3a.

支承部材5は、例えば、ゴム材と鋼板とが交互に積層されてなる積層ゴム支承等によって構成され、下端が下部工横梁4の上面部にボルト止め等によって固定されるとともに、上端部に鋼板等からなる桁受板材10が固定されている。 The support member 5 is, for example, a laminated rubber support made of alternating layers of rubber material and steel plates, and its lower end is fixed to the upper surface of the substructure cross beam 4 by bolts or the like, and a girder support plate material 10 made of a steel plate or the like is fixed to its upper end.

桁受板材10は、複数のプレキャスト縦桁部材6,6(本実施例では一対)が載置可能な幅、即ち、橋軸直角方向に並べられた複数のプレキャスト縦桁部材6,6の幅の合計と略同じ又はそれ以上の幅を有するとともに、構築される上部工8を支持するに足る剛性を確保できる厚みを有する矩形板状に形成されている。 The girder support plate material 10 is formed in a rectangular plate shape with a width that allows multiple precast vertical beam members 6, 6 (a pair in this embodiment) to be placed on it, i.e., a width that is approximately the same as or greater than the total width of the multiple precast vertical beam members 6, 6 arranged perpendicular to the bridge axis, and a thickness that ensures sufficient rigidity to support the superstructure 8 to be constructed.

また、桁受板材10には、特に図示しないが、橋軸直角方向に間隔をおいて板状の固定板が突設され、固定板にプレキャスト縦桁部材6,6をボルト締め等によって固定できるようになっている。 In addition, although not shown, plate-shaped fixing plates protrude from the girder support plate material 10 at intervals in the direction perpendicular to the bridge axis, and the precast vertical beam members 6, 6 can be fixed to the fixing plates by bolting or the like.

プレキャスト縦桁部材6,6は、図5に示すように、長手方向の両端部及び必要に応じて中間部に充実した隔壁部6b,6bを備え、この隔壁部6b,6b間に中空部6aが形成され、鉄筋コンクリート造の中空直方体状を成している。 As shown in FIG. 5, the precast vertical beam members 6, 6 have solid partition walls 6b, 6b at both longitudinal ends and, if necessary, in the middle, with a hollow section 6a formed between the partition walls 6b, 6b, forming a hollow rectangular parallelepiped of reinforced concrete construction.

また、プレキャスト縦桁部材6,6は、長手方向に向けて埋設された複数のPC鋼材(図示せず)によってプレテンション方式によるプレストレスが導入されている。 In addition, prestress is introduced into the precast vertical beam members 6, 6 by a pretensioning method using multiple PC steel members (not shown) embedded in the longitudinal direction.

このプレキャスト縦桁部材6,6は、標準的なスラブ用プレストレストコンクリート橋げた(JIS A 5373)に準拠して形成されているが、下部工横梁4を下部構造体3である脚体3a,3aの上端より所定の高さh分だけ低い位置に支持させたことにより、同じ高さに床版を形成する場合、標準的なスラブ用プレストレストコンクリート橋げたよりも高さを高く形成でき、その分、耐荷力の増加を図ることができるようになっている。 These precast vertical beam members 6, 6 are formed in accordance with standard prestressed concrete bridge girders for slabs (JIS A 5373), but by supporting the substructure cross beams 4 at a position a certain height h lower than the upper ends of the legs 3a, 3a, which are the substructure 3, when forming a deck at the same height, the height can be formed higher than that of a standard prestressed concrete bridge girders for slabs, thereby increasing the load-bearing capacity.

また、プレキャスト縦桁部材6,6は、橋軸方向に間隔をおいて立設された複数の下部構造体3間に跨って架設される長さを有し、両端部及び中間の一又は複数個所が支承部材5を介して下部構造体3に支持されるようになっている。 The precast vertical beam members 6, 6 are long enough to span multiple substructures 3 erected at intervals in the bridge axis direction, and both ends and one or more intermediate points are supported by the substructures 3 via support members 5.

また、プレキャスト縦桁部材6,6は、各縦桁部LB,LBを構成するプレキャスト縦桁部材6,6のプレキャスト版7側の側面上部に長手方向に連続するプレキャスト版受部12が一体に突設され、プレキャスト版受部12にプレキャスト版7の側縁部が支持され、各縦桁部LB,LB間にプレキャスト版7が架設されるようになっている。 The precast vertical beam members 6, 6 are provided with a precast plate support 12 that is continuous in the longitudinal direction and protrudes integrally from the upper side of the precast vertical beam members 6, 6 that constitute each vertical beam section LB, LB, on the precast plate 7 side. The precast plate support 12 supports the side edge of the precast plate 7, and the precast plate 7 is erected between each vertical beam section LB, LB.

プレキャスト版受部12は、プレキャスト縦桁部材6,6の上面からプレキャスト版7側部の厚み分だけ低い位置に突設され、プレキャスト版7がプレキャスト縦桁部材6,6間に架設された際、プレキャスト版7の上面と、プレキャスト梁部材の上面とが同一高さになるようになっている。 The precast plate support 12 protrudes from the top surface of the precast vertical beam members 6, 6 at a position lower than the thickness of the side of the precast plate 7, so that when the precast plate 7 is erected between the precast vertical beam members 6, 6, the top surface of the precast plate 7 and the top surface of the precast beam member are at the same height.

尚、プレキャスト縦桁部材6,6には、上部に長手方向に間隔をおいて橋軸直角方向に貫通した多数のPC挿通孔13,13…が形成され、プレキャスト版7が両プレキャスト縦桁部材6,6間に架設された際にプレキャスト版7に形成されたPC挿通孔14,14…と連通するようになっている。 The precast vertical beam members 6, 6 have numerous PC insertion holes 13, 13... formed at the top at intervals in the longitudinal direction, penetrating perpendicular to the bridge axis, which are connected to the PC insertion holes 14, 14... formed in the precast slab 7 when the precast slab 7 is erected between the two precast vertical beam members 6, 6.

また、プレキャスト縦桁部材6,6の各隔壁部6b,6b…、即ち、プレキャスト縦桁部材6の支承部材5を介して下部工横梁4に支持される部分には、高さ方向に間隔をおいて複数のPC挿通孔15,15…が形成されている。 In addition, in each bulkhead portion 6b, 6b... of the precast vertical beam members 6, 6, i.e., in the portion supported by the substructure cross beam 4 via the support member 5 of the precast vertical beam member 6, a plurality of PC insertion holes 15, 15... are formed at intervals in the height direction.

プレキャスト版7は、図6に示すように、コンクリート造の平板状に形成され、両側部下面にプレキャスト版受部12に支持される被支持用凸状部7a,7aが一体に突設されている。 As shown in FIG. 6, the precast slab 7 is made of concrete and is formed into a flat plate shape, with supported convex portions 7a, 7a that are supported by the precast slab receiving portion 12 and protrude integrally from the underside of both sides.

このプレキャスト版7には、図6(c)に示すように、橋軸方向に向けた複数のPC鋼材17,17…が緊張した状態で埋設され、橋軸方向にプレテンション方式によりプレストレスが導入されている。 As shown in Figure 6 (c), multiple PC steel members 17, 17... are embedded in the precast slab 7 in a tensile state in the bridge axis direction, and prestress is introduced in the bridge axis direction by the pretensioning method.

また、プレキャスト版7には、橋軸直角方向に貫通した多数のPC挿通孔14,14…が橋軸方向に間隔をおいて形成され、プレキャスト縦桁部材6,6のPC挿通孔13,13…と連続し、両PC挿通孔13,14を跨いでPC鋼材9,9…がプレキャスト縦桁部材6,6とプレキャスト版7とによって構成される部分(床版部)の橋軸直角方向全幅に亘って挿通されるようになっている。 In addition, the precast slab 7 has numerous PC insertion holes 14, 14... that penetrate perpendicular to the bridge axis and are spaced apart in the bridge axis direction, and are connected to the PC insertion holes 13, 13... of the precast vertical beam members 6, 6, so that the PC steel members 9, 9... are inserted across both PC insertion holes 13, 14 over the entire width of the part (deck section) formed by the precast vertical beam members 6, 6 and the precast slab 7 in the direction perpendicular to the bridge axis.

尚、プレキャスト版7の橋軸方向両端部には、端面より継手用鉄筋16,16が突出し、図7に示すように、橋軸直角方向で隣り合うプレキャスト版7間に重ね継手が形成され、端面間にコンクリートが打設されることにより、橋軸直角方向で隣り合うプレキャスト版7間が接続されている。 In addition, joint reinforcing bars 16, 16 protrude from the end faces at both ends of the precast slab 7 in the bridge axis direction, and as shown in Figure 7, lap joints are formed between adjacent precast slabs 7 in the direction perpendicular to the bridge axis, and concrete is poured between the end faces to connect adjacent precast slabs 7 in the direction perpendicular to the bridge axis.

次に、上述した橋梁1の構築方法について図8~図9に基づいて説明する。尚、本実施例では、橋軸方向に間隔をおいて立設された下部構造体3間に架設された既存上部工20を新たな上部工8に架け替えて構築する場合を例に説明し、上述の実施例と同様の構成には同一符号を付して説明する。また、図中符号2は地盤、符号20は既存の上部工(以下、既存上部工20という)である。 Next, the construction method of the above-mentioned bridge 1 will be explained with reference to Figures 8 and 9. In this embodiment, an example will be explained in which an existing superstructure 20 erected between substructures 3 erected at intervals in the bridge axis direction is replaced with a new superstructure 8, and the same components as in the above-mentioned embodiment will be described with the same reference numerals. In the figures, reference numeral 2 denotes the ground, and reference numeral 20 denotes the existing superstructure (hereinafter referred to as the existing superstructure 20).

既存の橋梁は、橋軸方向に間隔をおいて立設された複数の下部構造体3と、複数の下部構造体3間に架設された既存上部工20とを備え、既存上部工20が橋脚等の下部構造体3上に設置された既存支承体21,21を介して各下部構造体3に支持されている。 The existing bridge comprises multiple substructures 3 erected at intervals in the bridge axis direction and an existing superstructure 20 erected between the multiple substructures 3, and the existing superstructure 20 is supported by each substructure 3 via existing supports 21, 21 installed on the substructures 3 such as piers.

既存上部工20は、例えば、図8(a)に示すように、内部に中空部を有する中空床版部材によって構成され、中空床版部材が複数の下部構造体3に亘って架設されている。 The existing superstructure 20 is, for example, as shown in FIG. 8(a), composed of a hollow deck member having a hollow portion inside, and the hollow deck member is erected across multiple substructures 3.

この橋梁の既存上部工20を架け替えて新たなに橋梁1を構築するには、まず、図8(b)に示すように、既存上部工20を供用した状態で、既存上部工20を支持する下部構造体3の上端より所定の高さhだけ低い位置に橋軸直角方向に向けた下部工横梁4を構築する。 To replace the existing superstructure 20 of this bridge and build a new bridge 1, first, as shown in Figure 8 (b), while leaving the existing superstructure 20 in service, construct a substructure cross beam 4 oriented perpendicular to the bridge axis at a position a specified height h lower than the upper end of the substructure 3 that supports the existing superstructure 20.

具体的には、特に図示しないが、橋脚等の下部構造体3の周囲に足場を設置して下部工横梁4の形状に合わせて型枠を設置し、型枠内に鉄筋を配置する。尚、鉄筋は、下部構造体3と一体化させることが望ましい。 Specifically, although not shown, scaffolding is set up around the substructure 3 such as a pier, formwork is set up to match the shape of the substructure cross beam 4, and reinforcing bars are placed inside the formwork. It is preferable to integrate the reinforcing bars with the substructure 3.

そして、型枠内に場所打ちによってコンクリートを打設し、コンクリートを養生・硬化させて下部工横梁4を構築する。 Then, concrete is poured into the formwork by casting in place, and the concrete is cured and hardened to construct the substructure cross beam 4.

その際、下部工横梁4を下部構造体3の上端より所定の高さh分だけ低い位置に構築することによって、下部工横梁4の構築に要する期間、即ち、足場設置、型枠設置、鉄筋配置、コンクリート打設、コンクリート養生・硬化及び脱型の一連の各作業を行う間、既存上部工20を供用でき、通行規制等の社会的損失を最小限に抑えることができる。 In this case, by constructing the substructure cross beam 4 at a position a predetermined height h lower than the upper end of the substructure 3, the existing superstructure 20 can be used during the period required to construct the substructure cross beam 4, i.e., during the series of tasks of setting up scaffolding, setting up formwork, arranging rebar, pouring concrete, curing and hardening the concrete, and stripping the form, and social losses such as traffic restrictions can be minimized.

次に、下部工横梁4が構築されたら、図8(c)に示すように、既存上部工20の供用を停止し、既存上部工20を所定の間隔に分割した後、ガーダーやクレーン(図示せず)を用いて分割した部分毎に既存上部工20を撤去する。 Next, once the substructure cross beam 4 has been constructed, the existing superstructure 20 is taken out of service, as shown in FIG. 8(c), and the existing superstructure 20 is divided into predetermined intervals, after which each divided section of the existing superstructure 20 is removed using girders and a crane (not shown).

次に、図9(d)に示すように、下部構造体3である脚体3a,3aを挟んで下部工横梁4の両側、即ち、下部工横梁4上の両脚体3a,3aの外側及び脚体3a,3a間に支承部材5を取り付けるとともに、支承部材5の上端に桁受板材10を固定し、桁受板材10の橋軸直角方向両端部を、仮支承部材22,22を介して下部工横梁4に支持させる。 Next, as shown in FIG. 9(d), support members 5 are attached to both sides of the substructure cross beam 4, sandwiching the legs 3a, 3a of the lower structure 3, i.e., to the outside of the legs 3a, 3a on the substructure cross beam 4 and between the legs 3a, 3a. The girder support plate material 10 is fixed to the upper end of the support member 5, and both ends of the girder support plate material 10 perpendicular to the bridge axis are supported by the substructure cross beam 4 via temporary support members 22, 22.

そして、桁受板材10上に2本のプレキャスト縦桁部材6,6を橋軸直角方向に並べて設置して縦桁部LB,LBを形成し、各プレキャスト縦桁部材6,6の所定の位置を桁受板材10に固定する。 Then, two precast vertical beam members 6, 6 are placed on the girder support plate material 10 in a line perpendicular to the bridge axis to form the vertical beam sections LB, LB, and the predetermined positions of each precast vertical beam member 6, 6 are fixed to the girder support plate material 10.

尚、縦桁部LB,LBを構成するプレキャスト縦桁部材6,6の内、プレキャスト版7側に配置されるものには、そのプレキャスト版7側の側面上部にプレキャスト版受部12を備えたものを用いる。 In addition, among the precast vertical beam members 6, 6 that make up the vertical beam sections LB, LB, the one that is placed on the precast slab 7 side is equipped with a precast slab support part 12 on the upper side on the precast slab 7 side.

尚、この状態では、縦桁部LB,LB間が互いに支持されていないが、桁受板材10の橋軸直角方向両端部が仮支承部材22,22を介して下部工横梁4に支持されていることで、プレキャスト縦桁部材6,6が安定した状態で各下部構造体3に支持される。 In this state, the vertical beam sections LB, LB are not supported by each other, but both ends of the girder support plate material 10 perpendicular to the bridge axis are supported by the substructure cross beams 4 via temporary support members 22, 22, so that the precast vertical beam members 6, 6 are supported by each substructure 3 in a stable state.

次に、図9(e)に示すように、橋軸直角方向に間隔をおいて隣り合う縦桁部LB,LB間にプレキャスト版7を架設し、複数のプレキャスト版7を橋軸方向に敷設する。 Next, as shown in FIG. 9(e), precast slabs 7 are erected between adjacent vertical beam sections LB, LB spaced apart perpendicular to the bridge axis, and multiple precast slabs 7 are laid in the bridge axis direction.

その際、図7に示すように、橋軸方向に連なるプレキャスト版7間には、各プレキャスト版7の端面より突出した継手用鉄筋16,16が重複した状態で配置されて重ね継手が形成され、プレキャスト版7間にモルタルやコンクリートが打設されて連結される。 As shown in Figure 7, joint reinforcing bars 16, 16 protruding from the end faces of each precast slab 7 are placed in an overlapping state between the precast slabs 7 connected in the bridge axis direction to form lap joints, and mortar or concrete is poured between the precast slabs 7 to connect them.

また、特に図示しないが、橋軸直角方向で連続するプレキャスト縦桁部材6,6及びプレキャスト版7のPC挿通孔13,13…間をシースの接続により連通させる。 Although not specifically shown, the PC insertion holes 13, 13 of the precast vertical beam members 6, 6 and the precast slabs 7, which are continuous in the direction perpendicular to the bridge axis, are connected by sheaths.

次に、図9(f)に示すように、下部工横梁4上の縦桁部LB,LB(プレキャスト縦桁部材6,6)及びプレキャスト版7に囲まれた部分を閉鎖するように型枠を設置し、型枠内に必要に応じて鉄筋やシースを配置し、しかる後、場所打ちによってコンクリート23を打設して横桁部WBを形成する。 Next, as shown in FIG. 9(f), a formwork is installed to close the area surrounded by the vertical beams LB, LB (precast vertical beam members 6, 6) on the substructure cross beam 4 and the precast slab 7, reinforcing bars and sheaths are placed inside the formwork as necessary, and then concrete 23 is poured in place to form the horizontal beams WB.

また、互いに隣接して設置されたプレキャスト縦桁部材6,6間の隙間やプレキャスト縦桁部材6,6とプレキャスト版7との隙間にモルタル等の充填材を充填する。 In addition, the gaps between the adjacent precast vertical beam members 6, 6 and the gaps between the precast vertical beam members 6, 6 and the precast slab 7 are filled with a filler such as mortar.

そして、図10(g)に示すように、プレキャスト縦桁部材6,6とプレキャスト版7とからなる床版部の橋軸直角方向全幅に亘ってPC鋼材9,9…を挿通させるとともに、横梁部WBの橋軸直角方向全幅に亘ってPC鋼材9,9…を挿通させ、このPC鋼材9,9…を緊張させた状態でその両端を縦桁部LB,LB、プレキャスト版7及び横桁部WBからなる構造体(上部工8)の両側部に定着させ、上部工8の橋軸直角方向全幅に亘ってポストテンション方式によるプレストレスを導入する。 Then, as shown in FIG. 10(g), PC steel members 9, 9... are inserted across the entire width of the deck section, consisting of the precast vertical beam members 6, 6 and the precast slab 7, perpendicular to the bridge axis, and PC steel members 9, 9... are inserted across the entire width of the cross beam section WB, perpendicular to the bridge axis. With these PC steel members 9, 9... under tension, both ends are fixed to both sides of the structure (superstructure 8) consisting of the vertical beam sections LB, LB, the precast slab 7 and the cross beam section WB, and prestress is introduced by the post-tensioning method across the entire width of the superstructure 8, perpendicular to the bridge axis.

プレストレス導入後には、図10(h)に示すように、仮支承部材22,22を撤去して上部工8を支承部材5のみで支持させ、必要に応じて側壁24,24等を設置して橋梁1の構築が完了する。 After the prestress is introduced, as shown in Figure 10 (h), the temporary support members 22, 22 are removed and the superstructure 8 is supported only by the support members 5, and side walls 24, 24, etc. are installed as necessary to complete the construction of the bridge 1.

尚、上述の実施例では、既存の上部工20を新たな上部工8に架け替える場合について説明したが、下部構造体3を構築した後、下部工横梁4の構築し、その後図8(c)~図10(h)に示す手順と同様に作業を進めることによって新たに橋梁1を構築することができる。 In the above embodiment, the case where the existing superstructure 20 is replaced with a new superstructure 8 has been described, but after constructing the substructure 3, the substructure cross beams 4 can be constructed, and then a new bridge 1 can be constructed by carrying out the work in the same manner as shown in Figures 8(c) to 10(h).

その際、下部工横梁4は、必ずしも下部構造体3(脚体3a,3a)の上端より所定の高さh分だけ低い位置に支持させる必要はなく、下部構造体3の上端部に跨って下部構造体3の上面と下部工横梁4の上面とが同一平面となるように構築してもよく、下部構造体3に架設された状態に下部工横梁4を形成してもよい。 In this case, the substructure cross beam 4 does not necessarily need to be supported at a position a certain height h lower than the upper end of the substructure 3 (legs 3a, 3a). It may be constructed so that the upper surface of the substructure 3 and the upper surface of the substructure cross beam 4 are flush with each other across the upper end of the substructure 3, or the substructure cross beam 4 may be formed in a state where it is erected on the substructure 3.

1 橋梁
2 地盤
3 下部構造体
4 下部工横梁
5 支承部材
6 プレキャスト縦桁部材
7 プレキャスト版
8 上部工
9 PC鋼材
10 桁受板材
11 固定板
12 プレキャスト版受部
13~15 PC挿通孔
16 継手用鉄筋
17 PC鋼材
20 既存上部工
21 既存支承体
22 仮支承部材
23 コンクリート
24 側壁
LB 縦桁部
WB 横桁部
Reference Signs List 1 Bridge 2 Ground 3 Substructure 4 Substructure cross beam 5 Support member 6 Precast vertical beam member 7 Precast slab 8 Superstructure 9 PC steel 10 Girder support plate material 11 Fixed plate 12 Precast slab support part 13-15 PC insertion hole 16 Joint reinforcing bar 17 PC steel 20 Existing superstructure 21 Existing support body 22 Temporary support member 23 Concrete 24 Side wall LB Vertical beam part WB Horizontal beam part

Claims (7)

橋軸方向に間隔をおいて立設された下部構造体間に上部工が架設されてなる橋梁において、
前記各下部構造体の上部に橋軸直角方向に向けて支持された下部工横梁と、
該下部工横梁上に支承部材を介して支持された橋軸方向に向けた一又は複数の中空直方体状のプレキャスト縦桁部材からなる縦桁部と、
橋軸直角方向で間隔をおいて隣り合う前記縦桁部間に架設されたプレキャスト版とを備えるとともに、
前記下部工横梁上の間隔をおいて隣り合う前記縦桁部と前記プレキャスト版に囲まれた部分がコンクリートで充填されてなる横梁部が形成され、
前記プレキャスト縦桁部材と前記プレキャスト版とからなる床版部の橋軸直角方向全幅に亘って挿通されたPC鋼材と、前記横梁部の橋軸直角方向全幅に亘って挿通されたPC鋼材とにより前記縦桁部、前記プレキャスト版及び前記横桁部からなる構造体の橋軸直角方向全幅に亘ってポストテンション方式によりプレストレスが導入されていることを特徴としてなる橋梁。
In a bridge in which a superstructure is erected between substructures spaced apart in the bridge axis direction,
A substructure cross beam supported on the upper part of each of the substructures in a direction perpendicular to the bridge axis;
A vertical beam portion made of one or more hollow rectangular parallelepiped precast vertical beam members oriented in the bridge axis direction and supported on the substructure cross beam via bearing members;
A precast plate is installed between adjacent vertical beam portions spaced apart in a direction perpendicular to the bridge axis,
A cross beam portion is formed by filling a portion surrounded by the adjacent vertical beam portions and the precast plate with concrete on the substructure cross beam,
A bridge characterized in that prestress is introduced by the post-tensioning method across the entire width perpendicular to the bridge axis of the structure consisting of the vertical beam members, the precast plate and the horizontal beam members, by PC steel members inserted across the entire width perpendicular to the bridge axis of the deck section consisting of the precast vertical beam members and the precast plate, and PC steel members inserted across the entire width perpendicular to the bridge axis of the horizontal beam members.
前記下部工横梁は、前記下部構造体の上端より所定の高さ分だけ低い位置に支持されている請求項1に記載の橋梁。 The bridge according to claim 1, in which the substructure cross beam is supported at a position a predetermined height lower than the upper end of the substructure. 前記プレキャスト版には橋軸方向に向けたPC鋼材によりプレテンション方式によるプレストレスが導入されている請求項1又は2に記載の橋梁。 A bridge as described in claim 1 or 2, in which prestress is introduced to the precast slab by pretensioning using PC steel members oriented in the bridge axis direction. 橋軸方向に間隔をおいて立設された下部構造体間に上部工が架設されてなる橋梁の構築方法において、
前記各下部構造体の上部に橋軸直角方向に向けた下部工横梁を支持させ、
該下部工横梁上に支承部材を介して橋軸方向に向けた一又は複数の中空直方体状のプレキャスト縦桁部材を支持させて縦桁部を形成し、
しかる後、橋軸直角方向で間隔をおいて隣り合う前記縦桁部間にプレキャスト版を架設し、
前記下部工横梁上の間隔をおいて隣り合う前記縦桁部と前記プレキャスト版に囲まれた部分にコンクリートを打設して横梁部を形成し、
前記プレキャスト縦桁部材と前記プレキャスト版とからなる床版部の橋軸直角方向全幅に亘ってPC鋼材を挿通させるとともに、前記横梁部の橋軸直角方向全幅に亘ってPC鋼材を挿通させ、
該PC鋼材により前記縦桁部、前記プレキャスト版及び前記横桁部からなる構造体の橋軸直角方向全幅に亘ってポストテンション方式によりプレストレスを導入することを特徴としてなる橋梁の構築方法。
A method for constructing a bridge in which a superstructure is erected between substructures spaced apart in the bridge axis direction, comprising:
A substructure cross beam perpendicular to the bridge axis is supported on the upper part of each of the substructures,
One or more hollow rectangular parallelepiped precast vertical beam members oriented in the bridge axis direction are supported on the substructure cross beam via bearing members to form a vertical beam portion;
Then, a precast plate is erected between adjacent vertical beams spaced apart in the direction perpendicular to the bridge axis,
Pour concrete into a portion surrounded by the adjacent vertical beam portions and the precast slabs at an interval on the substructure horizontal beam to form a horizontal beam portion;
The PC steel is inserted along the entire width of the deck section consisting of the precast vertical beam member and the precast slab in the direction perpendicular to the bridge axis, and the PC steel is inserted along the entire width of the cross beam section in the direction perpendicular to the bridge axis,
A bridge construction method characterized in that prestress is introduced by the post-tensioning method using the PC steel material across the entire width perpendicular to the bridge axis of the structure consisting of the vertical beam section, the precast plate, and the horizontal beam section.
橋軸方向に間隔をおいて立設された下部構造体間に架設された既設上部工を新たな上部工に架け替えて構築する橋梁の構築方法において、
既設上部工を支持する前記下部構造体の上端より所定の距離だけ低い位置に橋軸直角方向に向けた下部工横梁を予め構築しておき、
前記既設上部工を撤去した後、
前記下部工横梁の前記下部構造体上端部を挟んだ両側にそれぞれ支承部材を介して橋軸方向に向けた一又は複数の中空直方体状のプレキャスト縦桁部材を支持させて縦桁部を形成し、
しかる後、前記下部構造体上端部を挟んで間隔をおいて隣り合う前記縦桁部間にプレキャスト版を架設し、
前記下部工横梁上の間隔をおいて隣り合う前記縦桁部と前記プレキャスト版に囲まれた部分にコンクリートを打設して横梁部を形成し、
前記プレキャスト縦桁部材と前記プレキャスト版とからなる床版部の橋軸直角方向全幅に亘ってPC鋼材を挿通させるとともに、前記横梁部の橋軸直角方向全幅に亘ってPC鋼材を挿通させ、
該PC鋼材により前記縦桁部、前記プレキャスト版及び前記横桁部からなる構造体の橋軸直角方向全幅に亘ってポストテンション方式によりプレストレスを導入することを特徴としてなる橋梁の構築方法。
A bridge construction method in which an existing superstructure is replaced with a new superstructure between substructures erected at intervals in the bridge axis direction,
A substructure cross beam is constructed in advance at a position a predetermined distance lower than the upper end of the substructure supporting the existing superstructure, and is oriented perpendicular to the bridge axis.
After removing the existing superstructure,
A vertical beam portion is formed by supporting one or more hollow rectangular parallelepiped precast vertical beam members oriented in the bridge axis direction via bearing members on both sides of the upper end portion of the lower structure of the substructure cross beam,
Thereafter, a precast plate is erected between the adjacent vertical beam portions with a gap therebetween, sandwiching the upper end portion of the lower structure therebetween;
Pour concrete into a portion surrounded by the adjacent vertical beam portions and the precast slabs at an interval on the substructure horizontal beam to form a horizontal beam portion;
The PC steel is inserted along the entire width of the deck section consisting of the precast vertical beam member and the precast slab in the direction perpendicular to the bridge axis, and the PC steel is inserted along the entire width of the cross beam section in the direction perpendicular to the bridge axis,
A bridge construction method characterized in that prestress is introduced by the post-tensioning method using the PC steel material across the entire width perpendicular to the bridge axis of the structure consisting of the vertical beam section, the precast plate, and the horizontal beam section.
前記支承部材上に設置された桁受板材の橋軸直角方向両端部を、仮支承部材を介して前記下部工横梁に支持させた状態で、前記桁受板材上に複数の前記プレキャスト縦桁部材を橋軸直角方向に並べて設置し、
前記PC鋼材により前記縦桁部、前記プレキャスト版及び前記横桁部からなる構造体の橋軸直角方向全幅に亘ってポストテンション方式によりプレストレスを導入した後、前記仮支承部材を撤去する請求項4又は5に記載の橋梁の構築方法。
With both ends of the girder support plate material installed on the support member in the direction perpendicular to the bridge axis supported by the substructure cross beam via temporary support members, a plurality of the precast vertical beam members are installed on the girder support plate material in a line perpendicular to the bridge axis;
6. A bridge construction method as described in claim 4 or 5, wherein prestress is introduced by the post-tensioning method using the PC steel material across the entire width perpendicular to the bridge axis of the structure consisting of the vertical beam section, the precast plate and the horizontal beam section, and then the temporary support member is removed.
前記プレキャスト版には橋軸方向に向けたPC鋼材によりプレテンション方式によるプレストレスが導入されている請求項4又は5に記載の橋梁の構築方法。 The bridge construction method according to claim 4 or 5, in which prestress is introduced into the precast slab by pretensioning with PC steel members oriented in the bridge axis direction.
JP2023064963A 2023-04-12 2023-04-12 Bridges and their construction methods Pending JP2024151537A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2023064963A JP2024151537A (en) 2023-04-12 2023-04-12 Bridges and their construction methods

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2023064963A JP2024151537A (en) 2023-04-12 2023-04-12 Bridges and their construction methods

Publications (1)

Publication Number Publication Date
JP2024151537A true JP2024151537A (en) 2024-10-25

Family

ID=93156012

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2023064963A Pending JP2024151537A (en) 2023-04-12 2023-04-12 Bridges and their construction methods

Country Status (1)

Country Link
JP (1) JP2024151537A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN119824821A (en) * 2025-01-16 2025-04-15 浙江交工集团股份有限公司 Prestress cast-in-situ box girder reinforcing method based on steel-concrete combined system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN119824821A (en) * 2025-01-16 2025-04-15 浙江交工集团股份有限公司 Prestress cast-in-situ box girder reinforcing method based on steel-concrete combined system

Similar Documents

Publication Publication Date Title
CN106677049B (en) Assembled steel-concrete combined structure bridge and construction method
US9388561B2 (en) Modular construction mold apparatus and method for constructing concrete buildings and structures
US7461427B2 (en) Bridge construction system and method
CN104929034B (en) A kind of modularization steel reinforced concrete rapid construction small box girder bridge and its construction method
CN108221636B (en) Steel-concrete composite beam bridge constructed by adopting bracket-free scheme for midspan and bridge forming method
JP2004137686A (en) Composite panel structure, panel bridge structure and construction method of continuous composite girder bridge
KR101214602B1 (en) Incremental launching apparatus for constructing rail-type concrete slab of composite bridge using shearing connector rail, and method for the same
CN108316120A (en) It can rapidly-assembled precast bridge and its construction method
KR20130090709A (en) Construction method for corrugated steel plate web-psc composite beam
KR20120053869A (en) Bridge construction method using precast end-block with girder connection member
KR100565384B1 (en) Continuous structure of precast PS beam using beam connecting member and steel beam and bridge construction method
JP2024151537A (en) Bridges and their construction methods
KR20080105588A (en) Prefabricated hollow slab and method of constructing it
KR101118257B1 (en) Deck for concrete slab construction
KR100899713B1 (en) Steel composite girder bridge structure using precast arch-deck and construction method
JP7479547B1 (en) Concrete Structures
CN105019349B (en) Pi-shaped precast beam and preparation method thereof as well as mounting and construction method of precast beam
KR20060022322A (en) Composite bottom plate and its connection structure
KR100631029B1 (en) PC Plate Assembly and PC Plate Installation Method Using the PC Plate Assembly
CN114197307A (en) Prefabricated bridge deck, cable-stayed bridge and construction method of cable-stayed bridge
CN114250688A (en) Steel-concrete composite beam and construction method thereof
JP2010281040A (en) Steel concrete composite floor slab, panel for constructing the steel concrete composite floor slab, and construction method for steel concrete composite floor slab
CN223593219U (en) Hollow slab beam structure and bridge structure
CN113832826B (en) Prestressed concrete slab beam bridge type and construction method thereof
KR101156013B1 (en) Method of constructing bride deck using precast concrete deck and bridge superstructure thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20260220