JP4569878B2 - Bridge girder construction method - Google Patents
Bridge girder construction method Download PDFInfo
- Publication number
- JP4569878B2 JP4569878B2 JP2006214136A JP2006214136A JP4569878B2 JP 4569878 B2 JP4569878 B2 JP 4569878B2 JP 2006214136 A JP2006214136 A JP 2006214136A JP 2006214136 A JP2006214136 A JP 2006214136A JP 4569878 B2 JP4569878 B2 JP 4569878B2
- Authority
- JP
- Japan
- Prior art keywords
- work
- girder
- work vehicle
- floor
- head
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Description
本発明は橋桁の架設方法に係り、特に高橋脚等の橋桁を張り出し架設工法で施工する際に、架設工に先立つ柱頭部の施工において、その施工合理化を図った橋桁の架設方法に関する。 The present invention relates to a bridge girder construction method, and more particularly to a bridge girder construction method in which the construction of column heads prior to the construction work is streamlined when a bridge girder such as a high pier is overhanged and constructed by the construction method.
図7は、山間部の渓谷51に建設される高橋脚橋梁50の一例を示した全体図である。このような橋梁50の架設工事では、両岸の橋台51と中間支持位置の高橋脚52間に橋桁53を架設する工法である、張り出し架設工法(片持ち式架設工法)が採用されることが多い。図8は、図7に示した橋梁50を、張り出し架設工法によって施工している状況を模式的に示した説明図である。図8に示したように、各高橋脚52の柱頭部52aで組み立てられた複数台の移動作業車60を用いて、各橋脚52位置から桁スパンの中間接合位置あるいは斜面に構築された橋台51まで片持ち梁式に橋桁53を連続施工して延長させて橋桁の架設を行うようになっている。
FIG. 7 is an overall view showing an example of a
この張り出し架設工法では、移動作業車に吊持された型枠を利用して所定のスパンの桁ブロックが連結構築される。この桁ブロックを構築する作業空間には外周足場が組み立てられ、各桁ブロックでの施工の安全性が確保されている。具体的には、移動作業車の下方に位置する、外周足場で囲まれた作業床上の作業空間において、鉄筋組立、PCケーブル用のシースの配管、型枠組立、コンクリート打設の作業を行い、コンクリート養生期間経過後、型枠解体まで一連の作業が行われる。そして移動作業車を隣接ブロックの施工可能位置まで移動させ、次行程の桁ブロックの施工が行われる。このように繰り返される橋桁ブロックの施工工程では、各工程での作業内容がほぼ定まっているため、各工程での工期短縮は難しいとされていた。この問題を解決するために、特許文献1に開示されたコンクリート橋の架設工法及び架設装置が提案されている。 In this overhanging construction method, a girder block having a predetermined span is connected and constructed using a mold suspended from a mobile work vehicle. In the work space for constructing this girder block, an outer periphery scaffold is assembled, and the safety of construction in each girder block is ensured. Specifically, in the work space on the work floor surrounded by the outer periphery scaffold, located below the mobile work vehicle, work of rebar assembly, PC cable sheath piping, formwork assembly, concrete placement, After the concrete curing period, a series of work is performed until the formwork dismantling. Then, the movable work vehicle is moved to the position where the adjacent block can be constructed, and the girder block is constructed in the next process. In the construction process of the bridge girder block that is repeated in this way, the work content in each process is almost fixed, and therefore it is considered difficult to shorten the construction period in each process. In order to solve this problem, the concrete bridge erection method and erection device disclosed in Patent Document 1 have been proposed.
このコンクリート橋の架設方法では、橋脚頂部まで施工完了したら、この橋脚を構築するために組み立てられていた橋脚の回りの作業足場を利用して、そのまま上方に橋脚の柱頭部を構築することにより、工期短縮を図ることが提案されている。 In this concrete bridge erection method, when construction to the pier top is completed, by using the work scaffold around the pier that was assembled to construct this pier, as it is, the pier column head is built up as it is, It has been proposed to shorten the construction period.
しかし、上述した特許文献1に開示された架設装置の特徴は、上述したような張り出し桁架設工程における工程短縮を目的とし、移動作業車の進行方向先端側に外型枠を吊持するとともに、内型枠、鉄筋組立を先行して行える作業足場を設けた点にある。このため、柱頭部の構築、柱頭部施工用の支保工の解体工程、移動作業車の組み立て等の一連の工程における工期短縮を実現することは意図していない。この柱頭部の施工では、通常、在来の型枠工法によって行われるため、柱頭部の施工が完了し、型枠、足場それらを支持していたブラケット等の解体工程の完了後、移動作業車の組み立て工程となる。 However, the feature of the erection device disclosed in Patent Document 1 described above is for the purpose of shortening the process in the overhanging girder erection process as described above, and while suspending the outer formwork on the front end side in the traveling direction of the mobile work vehicle, It is in the point which provided the work scaffold which can carry out an internal formwork and rebar assembly in advance. For this reason, it is not intended to shorten the construction period in a series of processes such as the construction of the pillar head, the dismantling process of the supporting work for the pillar head construction, and the assembly of the mobile work vehicle. Since this column head construction is usually performed by a conventional formwork method, the construction of the column head is completed, and after completion of the dismantling process of the formwork, scaffolding, etc., the mobile work vehicle This is the assembly process.
ところで、従来、柱頭部構築に使用する作業足場と同様の機能を果たす作業床が、桁ブロックの架設工程を通じても移動作業車から吊持する形態で組み込まれ、使用されていた。これらの作業床の共有化を図り、またこの作業床を早期に施工することにより、橋桁施工のための足場組立作業も前倒しに行えようになる。そこで、本発明の目的は上述した従来の技術が有する問題点を解消し、柱頭部の構築工程、移動作業車の組立工程において、仮設作業の資材、機材の共有化、それぞれの組立、解体の時期を調整することで、橋桁架設における工程短縮を図るようにした橋桁の架設方法及び橋桁の架設方法を提供することにある。 By the way, conventionally, a work floor that performs the same function as a work scaffold used for pillar head construction has been incorporated and used in a form of being suspended from a mobile work vehicle even during the construction process of a girder block. By sharing these work floors and constructing the work floors early, scaffold assembly work for bridge girder construction can be carried out ahead of schedule. Therefore, the object of the present invention is to solve the problems of the above-described conventional technology, and in the construction process of the column head and the assembly process of the mobile work vehicle, the materials for temporary work, the sharing of the equipment, the respective assembly, the disassembly of The purpose is to provide a bridge girder erection method and a bridge girder erection method so as to shorten the process in erection of the bridge girder by adjusting the timing.
上記目的を達成するために、本発明は橋脚柱頭部で組み立てられた移動作業車を、張り出し架設して構築した桁ブロック上を進行させて、前記桁ブロックに連続する桁ブロックを連結施工して橋脚スパン間に橋桁を架設するようにした橋桁の架設方法において、前記橋脚の柱頭部を施工する仮設作業床として、前記移動作業車で用いる作業床をあらかじめ敷設して用い、該作業床面上に仮設作業足場を立設して前記柱頭部を構築し、前記柱頭部構築作業に並行して前記作業床上に前記移動作業車による張り出し架設工事の領域を囲む外周足場を立設し、前記柱頭部の完成後に該柱頭部上に前記移動作業車を組み立て、該移動作業車に配備された吊り部材で桁ブロック構築用の型枠と前記外周足場が残置された前記作業床とを吊持し、前記移動作業車を桁方向に進行させて前記柱頭部に連続する橋桁の桁ブロックの張り出し架設作業を開始するようにしたことを特徴とする。 In order to achieve the above-mentioned object, the present invention advances a mobile work vehicle assembled with a bridge pier column head over a girder block constructed by overhanging and connecting and connecting girder blocks continuous to the girder block. In a bridge girder construction method in which bridge girder is constructed between pier spans, a work floor used in the mobile work vehicle is preliminarily used as a temporary work floor for constructing the column head of the pier, and the work floor surface is used. the erected a temporary work scaffolding the capital unit built and configured, upright an outer scaffold surrounding the area of the overhanging erection work by the moving working vehicle to the work floor in parallel with the column capital portion building work, the After completion of the column head, the movable work vehicle is assembled on the column head, and the work frame for constructing the girder block and the work floor on which the outer periphery scaffold is left are suspended by a suspension member provided on the mobile work vehicle. And said move The work vehicle is traveling in the digit direction is characterized in that so as to start the overhanging erection work digits block bridge girder continuous to the stigma section.
橋脚柱頭部で組み立てられた移動作業車を、張り出し架設して構築した桁ブロック上を進行させて、前記桁ブロックに連続する桁ブロックを連結施工して橋脚スパン間に橋桁を架設するようにした橋桁の架設方法において、前記橋脚の柱頭部を施工する仮設作業床として、前記移動作業車で用いる作業床をあらかじめ敷設して用い、該作業床面上に仮設作業足場を立設して前記柱頭部を構築し、前記柱頭部構築作業に並行して前記作業床上に前記移動作業車による張り出し架設工事の領域を囲む外周足場を立設し、前記柱頭部の完成後に該柱頭部上に前記移動作業車を組み立て、該移動作業車に配備された吊り部材の異なる高さに、桁ブロック構築用の型枠と前記外周足場が残置された前記作業床とを、吊持する吊り受け部材をそれぞれ設置し、該吊り受け部材のそれぞれの設置位置で前記型枠と前記作業床とを支持し、前記移動作業車を桁方向に進行させて前記柱頭部に連続する橋桁の桁ブロックの張り出し架設作業を開始するようにしたことを特徴とする。A mobile work vehicle assembled at the head of the pier column is advanced over the girder block constructed by overhanging, and the girder block connected to the girder block is connected and constructed so that the bridge girder is installed between the pier spans. In the construction method of the bridge girder, the work floor used in the mobile work vehicle is laid in advance and used as a temporary work floor for constructing the column head of the pier, and the temporary work scaffold is erected on the work floor surface. In parallel with the pillar head construction work, an outer periphery scaffolding is set up on the work floor to surround an overhanging construction area by the mobile work vehicle, and the movement onto the pillar head is completed after the pillar head is completed. A suspension receiving member for assembling the work vehicle and for suspending the formwork for building the girder block and the work floor on which the outer periphery scaffold is left at different heights of the suspension member provided on the mobile work vehicle. Installation , Supporting the formwork and the work floor at each installation position of the suspension receiving member, and moving the movable work vehicle in the direction of the spar to start the work of overhanging the girder block of the bridge girder continuous with the column head It was made to do.
前記作業床上に、前記桁ブロックの底型枠を載置して前記柱頭部を構築し、前記柱頭部の完成後に、前記移動作業車に配備されて前記底型枠の高さを前記吊り部材に設けられた吊り受け部材の高さを調整し、該底型枠を前記桁ブロックに連続する桁ブロックの底面高さに設置することが好ましい。 The bottom form of the girder block is placed on the work floor to construct the pillar head, and after the completion of the pillar head, the suspension member is arranged on the mobile work vehicle to set the height of the bottom form. It is preferable to adjust the height of the suspension receiving member provided on the bottom of the girder block and to install the bottom mold frame at the bottom surface of the girder block .
本発明によれば、橋脚柱頭部の構築工程と、柱頭部での移動作業車の組立工程とにおいて、移動作業車の資機材を共有し、それらの組立、解体の時期を調整することにより、橋桁の架設工における工程短縮を図ることができるという効果を奏する。 According to the present invention, in the construction process of the pier column head and the assembly process of the mobile work vehicle at the column head, by sharing the materials and equipment of the mobile work vehicle, by adjusting the timing of their assembly and disassembly, There is an effect that it is possible to shorten the process in the construction work of the bridge girder.
以下、本発明の橋桁の架設方法及び橋桁の架設方法の実施するための最良の形態としての実施例について添付図面を参照して説明する。 DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments as the best mode for carrying out a bridge girder erection method and a bridge girder erection method of the present invention will be described below with reference to the accompanying drawings.
図1は、工事対象としての一例としての橋梁(図7)において、公知の型枠工法やスリップフォーム工法で構築された鉄筋コンクリート橋脚2(以下、単に橋脚2と記す。)の頂部(図7中の○印位置)を示した部分拡大図である。この橋脚2の頂部には、橋桁の支点となる柱頭部2a(2点鎖線で表示)が施工される。この橋脚の柱頭部は、橋脚と一体構造をなし、橋桁の連続支点としての役割を果たす。
以下、この柱頭部2aの構築手順について、図2〜図4を参照して説明する。
FIG. 1 shows the top of a reinforced concrete pier 2 (hereinafter simply referred to as a pier 2) constructed by a known formwork method or slip form method in a bridge (FIG. 7) as an example of a construction object. It is the elements on larger scale which showed (circle | circle mark position). A
Hereinafter, the construction procedure of the
柱頭部2aの施工に先立ち、図2に示したように、橋脚2上部のコンクリート側壁面の所定高さにブラケット足場10を取り付ける。このブラケット足場10は、コンクリート側壁面に沿って所定間隔をあけてアンカー(図示せず)固定された立て材11と、各立て材11の上端部から側方に向けて水平配置された受け梁12と、受け梁12を支持する方杖13とから構成されている。
Prior to the construction of the
さらにブラケット足場10上には、後の張り出し架設工法で使用される移動作業車20(図5参照)の作業床21を敷設する(図3)。この作業床21は、格子状に組まれた根太材(図示せず)を介してブラケット足場10上に敷設されており、これにより橋脚2の周囲に平面視してロ字形をなす所定面積の作業スペースが確保される。また作業床21は、後に移動作業車20の吊り部材22で吊持される際の吊り受け部材23を台座としてブラケット足場10上に載置されている。このため、後に移動作業車20に組み込まれる際に、吊り受け部材23を吊り部材22の所定レベル(高さ)の吊り点位置に固定することで、容易に移動作業車20の作業床21として組み直して使用することができる。
Further, a
また、作業床21上には、図3右半図に示したように、桁ブロック5の底型枠25を構成する型枠部材があらかじめ載置されている。この場合にも、作業床21の場合と同様に、吊り部材22で一括して移動作業車20から吊持可能な吊り受け部材24を台座として使用することが好ましい。作業床21、底型枠25の支持点が吊り受け部材23,24のみでは足りない場合には適宜、ブラケット足場10上および作業床21上に支持点(図示せず)を追加することが好ましい。
Further, as shown in the right half of FIG. 3, a mold member constituting the
次いで、図4に示したように、作業床21上で柱頭部2aの構築を行う。作業足場としての作業床21は橋脚2の外周寸法に合わせて組み立てられおり、この作業足場を利用して、まず柱頭部2aの鉄筋組立、型枠組立等を行う。型枠組立完了後、柱頭部2aのコンクリート打設作業までの施工期間に並行して、図4左半図に示したように、張り出し架設用の外周足場26を作業床21上に組み立てる。この外周足場26は、公知の枠組足場を、架設中の桁ブロック5全体が覆える程度の範囲で組み立て、その外周全面に安全ネットを張設したもので、張り出し架設時の桁ブロック5の施工空間全体を覆う安全設備として機能する。また柱頭部2aの構築時の作業員の安全設備としての役割も果たす。
Next, as shown in FIG. 4, the
柱頭部2aのコンクリート養生期間経過後、あるいはコンクリートが所定強度に達した段階で、柱頭部上で移動作業車20の組み立てを行う。移動作業車20は、図5に示したように、走行機構あるいは横引き可能な可動支持体を備えた公知の鉄骨トラス構造フレームからなり、2台が柱頭部2aから両方向の桁方向に向けて橋脚中心線に関して対称形をなして組み立てられる。それぞれの移動作業車20の上弦トラスに直交して組み込まれ、両端が橋桁幅より外方まで延在した吊り桁(図示せず)から複数本の吊り部材22が吊持されている。この吊り部材22によって、上述した作業床21と、桁ブロック5の複数の型枠の全荷重とが、所定の吊り点位置で支持される。作業床21は吊り受け部材23により常に水平保持されて吊持されるが、底型枠25の吊り点としての吊り受け部材24は、桁ブロックの桁高が張り出し架設の進行に伴い低くなるため、その桁ブロックの高さに合わせた底型枠位置に高さ調整され、吊り部材22に固定される。
The
図6に示したように、完成した桁ブロック5上で移動作業車20を走行させ、完成した桁ブロック5の先端位置ま移動させ、次工程の桁ブロック5の施工が行われる。なお、移動作業車20および移動作業車20に吊持された作業足場、外周足場26が橋脚を離れた段階で、橋脚のコンクリート壁にアンカー固定されていたブラケット足場10を撤去することができる。
As shown in FIG. 6, the
その後、公知の張り出し架設工法の手順に基づき、順次桁ブロック5を連続施工し、橋脚間のスパン中間位置で、両側から張り出し架設された桁ブロック5を連結して1スパンの施工を行い、あるいは端部スパンでは橋台位置までの架設工を行う。
After that, based on the procedure of the known overhang construction method, the
このように、移動作業車20の作業床21を柱頭部2aの施工のための作業床21として兼用し、移動作業車20の組み立て時に移動作業車20の一部の設備として転用した点、柱頭部2aの構築時に作業床21上に張り出し架設用の外周足場26を組み立て、その後張り出し架設開始後に橋脚2に取り付けたブラケット足場10を解体、撤去することができる。このように従来、柱頭部2aの施工段階、移動作業車20の組み立て段階で、工程上のクリティカルパスとなっていた上述の作業を、主作業の進行に並行して行えるため、張り出し架設工程が開始できるまでの工程を大幅に短縮できるようになった。
In this way, the
2 橋脚
2a 柱頭部
5 桁ブロック
10 ブラケット足場
20 移動作業車
21 作業床
22 吊り部材
23 吊り受け部材
25 底型枠
26 外周足場
2
Claims (3)
前記橋脚の柱頭部を施工する仮設作業床として、前記移動作業車で用いる作業床をあらかじめ敷設して用い、該作業床面上に仮設作業足場を立設して前記柱頭部を構築し、前記柱頭部構築作業に並行して前記作業床上に前記移動作業車による張り出し架設工事の領域を囲む外周足場を立設し、前記柱頭部の完成後に該柱頭部上に前記移動作業車を組み立て、該移動作業車に配備された吊り部材で桁ブロック構築用の型枠と前記外周足場が残置された前記作業床とを吊持し、前記移動作業車を桁方向に進行させて前記柱頭部に連続する橋桁の桁ブロックの張り出し架設作業を開始するようにしたことを特徴とする橋桁の架設方法。 A mobile work vehicle assembled at the head of the pier column is advanced over the girder block constructed by overhanging, and the girder block connected to the girder block is connected and constructed so that the bridge girder is installed between the pier spans. In the construction method of the bridge girder,
As temporary working floor of applying the capital portion of the pier, using previously laid working floor for use in the mobile work vehicle, the capital portion and built structure erected a temporary work scaffolding on the working floor, In parallel with the pillar head construction work, an outer periphery scaffolding that surrounds an overhang construction area by the mobile work vehicle is erected on the work floor, and the mobile work vehicle is assembled on the pillar head after the completion of the pillar head, A suspension member provided on the mobile work vehicle is used to suspend a formwork for building a girder block and the work floor on which the outer periphery scaffold is left, and the mobile work vehicle is advanced in the direction of the girder to move to the column head. A construction method of a bridge girder characterized by starting overhang construction work of a girder block of continuous bridge girder.
前記橋脚の柱頭部を施工する仮設作業床として、前記移動作業車で用いる作業床をあらかじめ敷設して用い、該作業床面上に仮設作業足場を立設して前記柱頭部を構築し、前記柱頭部構築作業に並行して前記作業床上に前記移動作業車による張り出し架設工事の領域を囲む外周足場を立設し、前記柱頭部の完成後に該柱頭部上に前記移動作業車を組み立て、該移動作業車に配備された吊り部材の異なる高さに、桁ブロック構築用の型枠と前記外周足場が残置された前記作業床とを、吊持する吊り受け部材をそれぞれ設置し、該吊り受け部材のそれぞれの設置位置で前記型枠と前記作業床とを支持し、前記移動作業車を桁方向に進行させて前記柱頭部に連続する橋桁の桁ブロックの張り出し架設作業を開始するようにしたことを特徴とする橋桁の架設方法。As a temporary work floor for constructing the pillar head of the pier, a work floor used in the mobile work vehicle is laid in advance, and a temporary work scaffold is erected on the work floor surface to construct the pillar head, In parallel with the pillar head construction work, an outer periphery scaffolding is provided on the work floor to surround an overhang construction area by the movable work vehicle, and after the completion of the pillar head, the movable work vehicle is assembled on the pillar head, A suspension receiving member for suspending the formwork for constructing the girder block and the work floor on which the outer periphery scaffold is left is installed at different heights of the suspension members provided in the mobile work vehicle. The formwork and the work floor are supported at the respective installation positions of the members, and the mobile work vehicle is advanced in the direction of the spar to start the overhanging work of the girder block of the bridge girder continuous with the column head. Bridge girder characterized by Erection method.
\\ The bottom form of the girder block is placed on the work floor to construct the pillar head, and after the completion of the pillar head, the suspension member is arranged on the mobile work vehicle to set the height of the bottom form. The bridge girder according to claim 2, wherein the height of the suspension receiving member provided on the girder block is adjusted, and the bottom mold is installed at the bottom surface height of the girder block continuous to the girder block . Construction method.
\\
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2006214136A JP4569878B2 (en) | 2006-08-07 | 2006-08-07 | Bridge girder construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2006214136A JP4569878B2 (en) | 2006-08-07 | 2006-08-07 | Bridge girder construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2008038463A JP2008038463A (en) | 2008-02-21 |
JP4569878B2 true JP4569878B2 (en) | 2010-10-27 |
Family
ID=39173813
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2006214136A Active JP4569878B2 (en) | 2006-08-07 | 2006-08-07 | Bridge girder construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4569878B2 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103306206A (en) * | 2013-06-13 | 2013-09-18 | 浙江金筑交通建设有限公司 | Reinforcing steel formwork supporting rack for thin-walled hollow high pier and construction method |
KR101391637B1 (en) * | 2012-03-21 | 2014-05-07 | 원대연 | Constrution methoed for Prestressed Composite Truss girder using steel truss member |
CN103882813A (en) * | 2014-04-10 | 2014-06-25 | 中铁二局股份有限公司 | Corbel bracket platform for bridge pier and transverse straining beam synchronous construction and construction method of corbel bracket platform |
CN108797380A (en) * | 2018-06-05 | 2018-11-13 | 中铁十二局集团有限公司 | Continuous girders by suspension grouting bracket suspends constructing device and construction method in midair |
Families Citing this family (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101761034B (en) * | 2010-03-25 | 2013-05-08 | 中国建筑第六工程局有限公司 | Construction method of side block straight-line segment of cantilever-concreting continuous beam |
CN101831872B (en) * | 2010-05-12 | 2011-07-06 | 重庆城建控股(集团)有限责任公司 | Front and rear fulcrum combined cradle |
CN102535339A (en) * | 2011-12-07 | 2012-07-04 | 中铁十九局集团第七工程有限公司 | Bracket of thin-wall hollow high-pier cantilever pouring continuous beam and construction method thereof |
CN103374885A (en) * | 2012-04-13 | 2013-10-30 | 中铁十局集团第五工程有限公司 | Perforating counter-pull hinge support type bracket |
CN102691266B (en) * | 2012-06-03 | 2014-04-16 | 中交第四公路工程局有限公司 | Construction method for ultrahigh combined support for bridge side span cast-in-situ section |
CN102704409A (en) * | 2012-06-28 | 2012-10-03 | 中铁十三局集团第一工程有限公司 | Shelf bracket |
CN103452049B (en) * | 2013-09-15 | 2015-08-19 | 中铁一局集团有限公司 | Corbel bracket for cast-in-place concrete construction at top of bridge pier |
CN103498425B (en) * | 2013-09-25 | 2015-08-05 | 中铁五局集团第一工程有限责任公司 | One completely knocks down multifunctional assembled bearing bracket structure and construction method thereof |
CN103696373B (en) * | 2013-11-01 | 2015-06-17 | 中铁十七局集团第二工程有限公司 | Construction method for adjustable triangular bracket |
CN103866696A (en) * | 2014-03-26 | 2014-06-18 | 中铁二十四局集团安徽工程有限公司 | Cast-in-situ support of long-cantilever zero segment of short-pylon cable-stayed bridge |
CN103952982B (en) * | 2014-05-13 | 2015-12-02 | 中交二航局第三工程有限公司 | Bridge box and beam Hanging Basket anchorage rod-pulling type jack prepressing device and preloading method |
CN104532758A (en) * | 2014-12-25 | 2015-04-22 | 浙江诚邦园林股份有限公司 | Construction support for pre-stress concrete suspension-poured continuous beam number zero segment |
CN104727231A (en) * | 2015-04-03 | 2015-06-24 | 中铁第五勘察设计院集团有限公司 | Cantilever irrigation method construction continuous beam and continuous rigid frame bridge geometrical parameter structure |
CN104894980B (en) * | 2015-04-09 | 2017-03-08 | 中铁第五勘察设计院集团有限公司 | A kind of assembled tilt adjustable is from fall frame pier-side bracket and its construction method |
CN105951610A (en) * | 2016-05-13 | 2016-09-21 | 中铁十七局集团第二工程有限公司 | Support structure assisting in cantilever beam construction and construction method |
CN106522107B (en) * | 2016-12-23 | 2018-07-20 | 中国水利水电第五工程局有限公司 | A kind of variable arc bridge floor stand device |
CN109098098B (en) * | 2018-10-23 | 2024-04-02 | 中交一公局集团有限公司 | Hanging type tie beam construction device and hanging type tie beam construction method |
CN109356039A (en) * | 2018-12-06 | 2019-02-19 | 广东腾盛模架科技有限公司 | A kind of safe construction assembled bent cap job platform |
CN109610323A (en) * | 2018-12-07 | 2019-04-12 | 江西集银科技有限公司 | A kind of bridge cantilever construction Hanging Basket equipment suspension system |
CN111287095A (en) * | 2020-04-03 | 2020-06-16 | 中国铁建大桥工程局集团有限公司 | Special construction method for main beam of lower-towing super-large bridge |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004218316A (en) * | 2003-01-16 | 2004-08-05 | Ps Mitsubishi Construction Co Ltd | Construction method for capital part and installing work vehicle |
JP2005171521A (en) * | 2003-12-08 | 2005-06-30 | Ps Mitsubishi Construction Co Ltd | Work-execution method for pole head |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0739644B2 (en) * | 1992-04-07 | 1995-05-01 | 川田建設株式会社 | Construction method of superstructure in elevated structure |
JP3831499B2 (en) * | 1997-10-29 | 2006-10-11 | 大成建設株式会社 | Construction method of column head of PC cantilever bridge |
-
2006
- 2006-08-07 JP JP2006214136A patent/JP4569878B2/en active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004218316A (en) * | 2003-01-16 | 2004-08-05 | Ps Mitsubishi Construction Co Ltd | Construction method for capital part and installing work vehicle |
JP2005171521A (en) * | 2003-12-08 | 2005-06-30 | Ps Mitsubishi Construction Co Ltd | Work-execution method for pole head |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101391637B1 (en) * | 2012-03-21 | 2014-05-07 | 원대연 | Constrution methoed for Prestressed Composite Truss girder using steel truss member |
CN103306206A (en) * | 2013-06-13 | 2013-09-18 | 浙江金筑交通建设有限公司 | Reinforcing steel formwork supporting rack for thin-walled hollow high pier and construction method |
CN103306206B (en) * | 2013-06-13 | 2015-09-16 | 浙江金筑交通建设有限公司 | A kind of construction method adopting thin-wall hollow high-pier reinforcement bar support fixing of the forming frame reinforcing bar |
CN103882813A (en) * | 2014-04-10 | 2014-06-25 | 中铁二局股份有限公司 | Corbel bracket platform for bridge pier and transverse straining beam synchronous construction and construction method of corbel bracket platform |
CN103882813B (en) * | 2014-04-10 | 2016-02-03 | 中铁二局工程有限公司 | For calf support platform and the building method thereof of bridge pier and straining beam synchronous construction |
CN108797380A (en) * | 2018-06-05 | 2018-11-13 | 中铁十二局集团有限公司 | Continuous girders by suspension grouting bracket suspends constructing device and construction method in midair |
Also Published As
Publication number | Publication date |
---|---|
JP2008038463A (en) | 2008-02-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4569878B2 (en) | Bridge girder construction method | |
KR100667921B1 (en) | Construction method of pylon using precast concrete beam | |
CN107119574B (en) | A kind of Cantilever Construction Method of arch rib bridge girder | |
CN100503977C (en) | Tower column of stayed-cable bridge and its construction method | |
JP5045214B2 (en) | Column head construction method | |
CN108589535B (en) | Reinforced concrete box type arch bridge construction method | |
KR20070010449A (en) | Construction method for arched bridge | |
KR101889064B1 (en) | Construction method of a long span bridge main tower | |
JPH11181725A (en) | Method for constructing horizontal beam of main tower made of concrete | |
CN107882328A (en) | The construction method of large span steel truss overhung construction | |
JP2019078090A (en) | Overhang erection work vehicle and construction method | |
CN108316150B (en) | Construction system and construction method for main tower and steel anchor beam of cable-stayed bridge | |
JPH0643686B2 (en) | Construction method of arch bridge by precast members | |
JP2639361B2 (en) | Construction method of steel pipe / concrete composite structure pier | |
JP4104910B2 (en) | How to build arch ribs for concrete arch bridges | |
JP3804883B2 (en) | Concrete high structure construction apparatus and concrete oblique column construction method | |
JP6509096B2 (en) | Extension method | |
JP4329535B2 (en) | Mobile work vehicle for overhanging slabs | |
CN110761165B (en) | Steel web box girder installation system and construction method thereof | |
JPH07310304A (en) | Erection method of concrete arch | |
JP5693869B2 (en) | Bridge girder construction method | |
JPH0959932A (en) | Construction method of column head of overhanging erection girder bridge | |
JP6889010B2 (en) | Bridge construction method | |
KR100377868B1 (en) | pier construction method using Pier scaffolding | |
CN211312154U (en) | Steel web box girder installation system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20081119 |
|
A871 | Explanation of circumstances concerning accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A871 Effective date: 20100216 |
|
A975 | Report on accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A971005 Effective date: 20100304 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20100316 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20100514 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20100615 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20100729 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130820 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4569878 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140820 Year of fee payment: 4 |