JPH07310304A - Erection method of concrete arch - Google Patents

Erection method of concrete arch

Info

Publication number
JPH07310304A
JPH07310304A JP10402894A JP10402894A JPH07310304A JP H07310304 A JPH07310304 A JP H07310304A JP 10402894 A JP10402894 A JP 10402894A JP 10402894 A JP10402894 A JP 10402894A JP H07310304 A JPH07310304 A JP H07310304A
Authority
JP
Japan
Prior art keywords
arch
center
frame
concrete
steel frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP10402894A
Other languages
Japanese (ja)
Inventor
Fumio Sato
文雄 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP10402894A priority Critical patent/JPH07310304A/en
Publication of JPH07310304A publication Critical patent/JPH07310304A/en
Withdrawn legal-status Critical Current

Links

Abstract

PURPOSE:To stably and safely erect an arch for supporting bridge floor slabs in a concrete arch bridge without a decrease in the construction efficiency or the safety. CONSTITUTION:A center 3 as a support is constituted of respective centers fabricated in a factory and assembled on a working floor 4 laid on the vertically projected face right below the place where the arch 1 is formed. Forms for defining the arch 1 or prefabricated reinforcements 5 are set on the center 3. Thereafter hanging steel frames 7 erected between abutments 6, between which the arch is formed, are used as reactive bases and the center 3, the forms, and the reinforcements 5 are suspended together right under the position where the arch 1 is formed, while keeping the horizontal posture of the center 3 with a measuring controller. Then concrete is placed in the forms and the reinforcements on the center 3. The hanging steel frames 7 for reaction of the center are utilized as chief members hanging the center 3 on placing concrete. Further, they are buried in the arch 1 to form a SCR-structural arch 1.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、中小規模の支間を有
するコンクリートアーチ橋の架設時に用いる工法であ
り、アーチ橋の橋床版を支持する主要構造として設けら
れるアーチ部の架設工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method used when constructing a concrete arch bridge having small and medium spans, and relates to a construction method of an arch portion provided as a main structure for supporting a bridge deck of an arch bridge. is there.

【0002】[0002]

【従来の技術】従来、この種のコンクリートアーチ橋の
架設時に用いるアーチ部の架設工法としては、(1) 接地
式支保工、(2) セントル工法、(3) 鋼製アーチ先行工法
(合成アーチ工法やメラン工法)、(4) ロアリング工法
という四種類の工法が一般に知られている。
2. Description of the Related Art Conventionally, as the construction method of the arch portion used when constructing a concrete arch bridge of this type, there are (1) ground support method, (2) centle method, (3) steel arch preceding method (synthetic arch method). Four types of construction methods are generally known: construction method and melan method, and (4) lowering method.

【0003】詳述すると、先ず(1) の接地式支保工は、
比較的平坦な地形において、中小規模の支間のコンクリ
ートアーチ橋を施工する時に適用されている工法であ
る。そして、この工法では、先ず、アーチ橋の橋床版を
支持する主要構造として築造するアーチ部(アーチリ
ブ)の直下に、全面支保工を組む。その後、この全面支
保工を足場にして、アーチ部形成用の型枠や鉄筋を組立
てると共に、この型枠内へコンクリートを場所打ちし
て、アーチ部を形成する。
To be more specific, first, the ground-type support work of (1) is
This method is applied when constructing a concrete arch bridge between small and medium-sized spans on relatively flat terrain. Then, in this construction method, first, full support is assembled just below the arch portion (arch rib) to be built as the main structure that supports the bridge deck of the arch bridge. After that, the entire supporting structure is used as a scaffold to assemble a formwork and a reinforcing bar for forming the arch part, and concrete is cast into the formwork to form the arch part.

【0004】次に(2) のセントル工法は、前述した接地
式支保工を適用することが困難な山岳地帯や河川におい
て、中小規模の支間のコンクリートアーチ橋を施工する
時に適用されている工法である。そして、この工法で
は、図12に示すように、先ず、アーチ橋の橋床版を支持
する主要構造として築造するアーチ部(アーチリブ)の
直下に、アーチ形状にした鋼製セントルを組立てる。そ
の後、このセントル上に型枠や鉄筋を組立てセットした
後、この形枠内へコンクリートを場所打ちして、アーチ
部を形成する。
Next, the Centle construction method (2) is a construction method applied when constructing a concrete arch bridge between small and medium-sized spans in a mountain area or a river where it is difficult to apply the above-mentioned ground-type support construction. is there. Then, in this construction method, as shown in FIG. 12, first, an arch-shaped steel centle is assembled immediately below an arch portion (arch rib) to be built as a main structure for supporting a bridge deck of an arch bridge. After that, a mold and a reinforcing bar are assembled and set on the center, and then concrete is cast into the form to form an arch portion.

【0005】なお、セントルは、その反力をアバット上
に置いてピン支承で受けることとした、2ヒンジ形式の
アーチ構造としている。また、形成したアーチ部は、ア
ーチ部コンクリートの閉合後に、セントル材を撤去して
鉛直材や補剛桁の施工を行うため、自立する剛性が必要
である。
The center has a two-hinge type arch structure in which the reaction force is placed on the abutment and received by the pin support. In addition, the formed arch portion needs to have self-standing rigidity because the centle material is removed and a vertical material or a stiffening girder is constructed after the concrete of the arch portion is closed.

【0006】次に(3) の鋼製アーチ先行工法(合成アー
チ工法やメラン工法)は、橋床版支持用の主要構造であ
るアーチ部(アーチリブ)を、コンクリートで直接施工
するのではなく、先行して設けたアーチ芯材(鋼製アー
チ)にコンクリートを巻き立てて形成するものである。
そして、この工法では、図13に示すように、先ず、アー
チ部の施工位置に、コンクリートと比較して重量の軽い
鉄骨や鋼管で、アーチ芯材を完成させる。その後、移動
作業車等を用いて、両アバット(橋台)よりアーチクラ
ウンへ向かい、前記アーチ芯材をコンクリートで巻き立
てて、コンクリートのアーチ部を築造する。
Next, in the steel arch preceding method (3) (synthetic arch method or melanc method), the arch portion (arch rib), which is the main structure for supporting the bridge deck, is not directly constructed with concrete, It is formed by winding concrete on the arch core material (steel arch) provided in advance.
Then, in this construction method, as shown in FIG. 13, first, an arch core material is completed at a construction position of an arch portion with a steel frame or a steel pipe having a lighter weight than concrete. Thereafter, using a mobile work vehicle or the like, the two arch heads (bridge abutments) are moved toward the arch crown, and the arch core material is wound up with concrete to construct a concrete arch portion.

【0007】このような鋼製アーチ先行工法の特長は、
ピロン工法やトラス工法と比較して小さな仮設部材で済
む。また、アーチ芯材(鋼製アーチ)が先行して形成さ
れるので、アーチ部(アーチリブ)のコンクリート打設
時に構造的に安定していると共に、両岸への往来がで
き、施工性がよいことが挙げられる。なお、前述したア
ーチ芯材に、鋼管と中詰めコンクリートとの合成部材を
使用するものを合成アーチ工法(図13参照)といい、鉄
骨部材を使用するものをメラン工法(図14参照)とい
う。
The features of such a steel arch preceding method are as follows:
Compared to the Pilon construction method and truss construction method, a small temporary member is sufficient. Also, since the arch core material (steel arch) is formed in advance, it is structurally stable when concrete is placed in the arch portion (arch rib), and it is possible to move to and from both banks, which is good workability. It can be mentioned. The above-mentioned arch core material that uses a synthetic member of steel pipe and filled concrete is called the synthetic arch method (see Fig. 13), and the one that uses a steel frame member is called the melanin method (see Fig. 14).

【0008】次に(4) のロアリング工法は、橋床版支持
用の主要構造であるアーチ部(アーチリブ)を略二分割
して別個に両アバット(橋台)上で施工し、その後、お
のおのを移動させアーチ状に組立てアーチ部とするもの
てある。そして、この工法では、図15に示すように、先
ず、コンクリートのアーチ部(アーチリブ)を、鉛直方
向へ延びる状態にし、クライミングフォーム等を用いる
ことにより、両アバット(橋台)上で施工する。その
後、このアーチ部の先端部を所定の位置まで降下させ、
アーチクラウン部のコンクリートを打設してアーチ部を
閉合することで、アーチ部を形成するものである。
Next, in the lowering method of (4), the arch portion (arch rib), which is the main structure for supporting the deck slab, is roughly divided into two and separately constructed on both abutments (abutments), and then each is There is an arch part that is moved and assembled into an arch shape. Then, in this construction method, as shown in FIG. 15, first, a concrete arch portion (arch rib) is made to extend in the vertical direction, and a climbing foam or the like is used to perform construction on both abutments (abutments). After that, lower the tip of this arch to a predetermined position,
The arch portion is formed by placing concrete of the arch crown portion and closing the arch portion.

【0009】[0009]

【この発明が解決しようとする課題】コンクリートアー
チ橋が、通常の橋梁と大きく異なる点は、アーチ部(ア
ーチリブ)が必ず傾斜を持っている点である。従って、
アーチ部の施工が場所打ち工法である限り、例えば、従
来の技術の項で述べたような各架設工法の違いにかかわ
らず、傾斜部材の施工を行うという共通の留意すべき点
がある。そのため、従来の各架設工法は、施工の困難さ
からくる施工能率の低下や、傾斜からくる安全性の低下
が問題となる。
A major difference between a concrete arch bridge and an ordinary bridge is that the arch portion (arch rib) always has a slope. Therefore,
As long as the construction of the arch portion is a cast-in-place construction method, there is a common point to be noted in that the inclined member is constructed regardless of the difference in each construction method as described in the section of the conventional technique. Therefore, each conventional erection method poses a problem that the construction efficiency is lowered due to the difficulty of construction and the safety is lowered due to the inclination.

【0010】そこで、前述した従来のアーチ部の各架設
工法における共通する課題を、各工程毎に詳述する。先
ず、支保工について述べると、コンクリート打設時の反
力を支持する接地式支保工は、前述した傾斜のために、
構造的に特別な機能を持たせる必要がある。
Therefore, problems common to the above-described conventional erection construction methods for the arch portion will be described in detail for each step. First of all, regarding the support work, the ground-type support work that supports the reaction force at the time of placing concrete is
It is necessary to have a structurally special function.

【0011】即ち、接地式支保工は、コンクリート打設
時の水平反力に対して構造的に対処する必要上、筋違い
等の補強材を密に配置する必要がある。そのために、複
雑な高所作業の機会が多くなり、それだけ墜落や転落等
の事故が発生する可能性が高くなる。なお、橋梁工事に
おける労災事故の約30%は墜落や転落であるといわれて
いる。従って、高所作業の機会をできるだけ減らすこと
が、墜落や転落事故を減らす根本的な解決方法である。
That is, in the grounding type supporting work, it is necessary to structurally deal with the horizontal reaction force at the time of pouring concrete, and it is necessary to dispose the reinforcing members such as streaks densely. As a result, there are many opportunities for complicated work in high places, and the possibility of accidents such as falls and falls increases accordingly. It is said that about 30% of industrial accidents in bridge construction are crashes or falls. Therefore, reducing the chances of working at height as much as possible is a fundamental solution to reduce crashes and falls.

【0012】次に、型枠およびコンクリート打設につい
て述べると、アーチ部(アーチリブ)の型枠では、スラ
ブ上面の押え型枠が必要となる。従来の施工方法では、
アーチ形状に加工した仮設の鋼材等を設置しこれに押え
型枠を取付けているが、押え型枠の固定に手間がかかる
ので、現場での工程の省力化が望まれている。また、前
述したような安全施工の問題からも、高所作業をできる
だけ減らす方策が必要である。
Next, the formwork and concrete pouring will be described. In the formwork of the arch part (arch rib), a pressing formwork on the upper surface of the slab is required. In the conventional construction method,
Although a temporary steel material processed into an arch shape is installed and a presser form is attached to it, it takes time to fix the presser form, so it is desired to save labor on site. Also, due to the above-mentioned problem of safe construction, it is necessary to take measures to reduce work at high places as much as possible.

【0013】一方、コンクリート打設では、押え型枠部
分は入念なコンクリートの締固めを実施しても、空気や
水のアバタ発生が避けられず、美観あるいは耐久性の難
点となることが多く、余剰水を排出し気泡を透過させる
機構を具備した型枠の使用が望まれている。
On the other hand, in concrete pouring, even if careful pressing of concrete is carried out in the pressing form part, avatars of air and water are unavoidably generated, which often causes problems of aesthetics and durability. It is desired to use a formwork equipped with a mechanism for discharging excess water and allowing air bubbles to pass through.

【0014】次に、鉄筋の組立てについて述べると、こ
の鉄筋の組立て作業も斜面上での施工となるので、スタ
ーラップ等の形状保持が難しく、施工性が低下する工程
である。そのため、鉄筋を予め組立ててプレハブ化した
ものを現地で取付ける等、現場工程の省力化が必要であ
る。
Next, as to the assembling of the reinforcing bar, since the assembling work of the reinforcing bar is also carried out on the slope, it is difficult to maintain the shape of the stirrup or the like and the workability is deteriorated. For this reason, it is necessary to reduce the labor of the on-site process by, for example, assembling the pre-fabricated reinforcing bars in advance and installing them on-site.

【0015】なお、その他にも、アーチ部(アーチリ
ブ)が勾配を持っているため、直接アーチ部上に仮置き
できないので、建設資材(型枠や鉄筋等)の仮置き台を
アーチ部上に設ける必要がある。そのため、アーチ部が
閉合されていない階段では、仮設荷重が増加して不安定
要因となる場合がある。
In addition, since the arch portion (arch rib) has a slope, it cannot be temporarily placed directly on the arch portion. Therefore, a temporary placing table for construction materials (formwork, rebar, etc.) is placed on the arch portion. It is necessary to provide. Therefore, in the stairs where the arch portion is not closed, the temporary load may increase and cause an instability.

【0016】また、アーチ部の施工に伴う計測は、勾配
があり、計測精度や能率の面で劣るため、各施工現場で
その都度工夫している。しかし、計測項目も多く、計測
精度の向上や、なお一層の省力化および迅速化等の情報
化施工が要求されている。
[0016] Further, the measurement involved in the construction of the arch portion has a gradient and is inferior in terms of measurement accuracy and efficiency. Therefore, each construction site is devised each time. However, there are many measurement items, and there is a demand for improvement of measurement accuracy and further computerization work such as labor saving and speedup.

【0017】この発明は前述した事情に鑑みて創案され
たもので、その目的はアーチ橋の橋床版を支持する主要
構造として築造するアーチ部の架設を、施工能率や安全
性が低下することなく、安定した状態で確実に実施でき
ると共に、接地式支保工やセントル工法による施工がで
きる立地条件下であれば適用が可能であるコンクリート
アーチの架設工法を提供することにある。
The present invention was devised in view of the above-mentioned circumstances, and its purpose is to reduce the construction efficiency and safety of the construction of the arch portion to be built as the main structure for supporting the deck slab of the arch bridge. The purpose of the present invention is to provide a concrete arch erection method that can be carried out reliably in a stable state and can be applied under site conditions where grounding type support work and construction by the Centle method can be performed.

【0018】[0018]

【課題を解決するための手段】本発明のコンクリートア
ーチの架設工法は、前述した従来のセントル工法と鋼製
アーチ先行工法におけるメラン工法との利点を併合した
工法として位置づけられる。
The concrete arch erection method of the present invention is positioned as a method that combines the advantages of the above-mentioned conventional Centle method and the melan method of the steel arch preceding method.

【0019】そして、本発明工法での支保工については
セントル構造とし、そのセントルは、工場製作したもの
を、施工現場において、アーチ部(アーチリブ)形成位
置の下方であるアーチ部形成位置の鉛直投影面に設けた
作業床上で組立てる。また、この作業床上で組立てたセ
ントル上に、アーチ部形成用の型枠やアーチ内部に配設
される補強鉄筋をセットする。なお、この補強鉄筋は、
セントルにアーチ部の下型枠取付け後、現地で施工ユニ
ット毎にプレハブ化して組立てる。
The support method according to the present invention has a centr structure, and the centle is a factory-manufactured one, which is vertical projection of the arch portion forming position below the arch portion (arch rib) forming position at the construction site. Assemble on the work floor provided on the surface. In addition, a mold for forming the arch portion and a reinforcing reinforcing bar arranged inside the arch are set on the center assembled on the work floor. In addition, this reinforcing bar is
After attaching the lower formwork of the arch part to the center, prefabricate each construction unit on site and assemble.

【0020】その後、アーチ部形成位置である橋台間に
架設した、曲げ加工してなる吊り鉄骨を反力台とし、吊
り鉄骨に設けたジャッキで、前記セントルおよびセント
ル上にセットした型枠や補強鉄筋を一体に、計測制御装
置でセントルの水平性を保ちながら吊り上げる。このよ
うに、セントルを吊り上げてアーチ部形成位置の直下に
セットすることにより、高所作業の低減を図る。
After that, the bent suspension steel frame erected between the abutments where the arches are formed is used as a reaction force platform, and a jack provided on the suspension steel frame is used to form the centle and the formwork and reinforcement set on the centle. The reinforcing bars are lifted together with the measurement control device while maintaining the horizontality of the center. In this way, by lifting the center and setting it just below the arch portion forming position, work at high places is reduced.

【0021】なお、セントルへの型枠の取付けは、セン
トルを組立てた後、ジャッキで吊り上げる前に作業床で
行う。また、型枠上部の押え型枠は、セントルと補強鉄
筋である下筋とを一緒に吊り上げて上筋を組立てた後、
セントル上に架設した吊り鉄骨からの専用治具によって
取付ける。さらに、型枠の解体は、セントルをジャッキ
ダウンした後に作業床上で行う。
The attachment of the formwork to the center is performed on the work floor after the center is assembled and before it is lifted by the jack. Also, the presser formwork on the upper part of the formwork, after assembling the upper reinforcement by suspending the center and the lower reinforcement which is the reinforcing bar together,
Attach with a special jig from the suspended steel frame erected on the center. Furthermore, the dismantling of the formwork is done on the work floor after the center is jacked down.

【0022】また、セントル反力用の吊り鉄骨は、コン
クリート打設時のセントルを吊り下げる主要部材として
利用する他に、アーチ部(アーチリブ)内に埋め込む。
このことで、SCR構造のアーチ部を形成する。
The hanging steel frame for the reaction force of the centle is used not only as a main member for suspending the centle at the time of placing concrete but also embedded in the arch portion (arch rib).
As a result, the arch portion having the SCR structure is formed.

【0023】このような本発明の架設工法によれば、セ
ントルを作業床上で組立てることと、セントル上にセッ
トした型枠や補強鉄筋を一体に吊り上げることとによ
り、アーチ部(アーチリブ)の形成に際して、傾斜部お
よび高所での作業機会を減らし、建設災害の内の墜落や
転落事故を減少させることができる。
According to the erection method of the present invention as described above, the arch part (arch rib) is formed by assembling the centle on the work floor and by hoisting the formwork and the reinforcing reinforcing bar set on the centle together. It can reduce work opportunities on slopes and high places, and reduce crashes and falls during construction disasters.

【0024】また、型枠用の専用治具や補強鉄筋のプレ
ハブ化により、鉄筋の組立て精度や型枠の組立て精度を
向上させて、耐久性を増すことができる。さらに、吊り
鉄骨を先行架設してアーチ部を形成することにより、ア
ーチ部架設時の応力を確実に橋台へ伝達して、アーチ部
閉合までの安定性を確保する。
Further, by using a prefabricated jig for the formwork and a reinforcing rebar, it is possible to improve the assembling precision of the reinforcing bar and the assembling precision of the formwork and to increase the durability. Further, by suspending the suspended steel frame in advance to form the arch portion, the stress at the time of constructing the arch portion is reliably transmitted to the abutment, and the stability until the arch portion is closed is secured.

【0025】[0025]

【実施例】以下、この発明のコンクリートアーチの架設
工法を、図示する実施例によって説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The concrete arch construction method of the present invention will be described below with reference to the illustrated embodiments.

【0026】中小規模の支間を有するコンクリートアー
チ橋の架設時において、アーチ橋の橋床版2(図1の
(f) 参照)を支持する主要構造として設けられるアーチ
部1の架設工法(図1参照)は、最初に、アーチ部形成
用の型枠やアーチ内部に配設される補強鉄筋を支持すべ
くアーチ部1の直下に設けられるセントル3を、アーチ
部形成位置の下方であるアーチ部形成位置の鉛直投影面
に設けた作業床4において組立てると共に、このセント
ル3上にアーチ部形成用の型枠やプレハブ化した補強鉄
筋5をセットする(図1の(a) 参照)。
At the time of erection of a concrete arch bridge having small and medium spans, the bridge deck 2 of the arch bridge (see FIG. 1).
The construction method of the arch portion 1 (see Fig. 1) provided as a main structure for supporting (f) is to first support the formwork for forming the arch portion and the reinforcing rebars arranged inside the arch. The centle 3 provided directly below the arch portion 1 is assembled on the work floor 4 provided on the vertical projection plane at the arch portion forming position, which is below the arch portion forming position, and the arch portion forming frame is formed on the centle 3. Set the prefabricated reinforcing bar 5 (see (a) in Fig. 1).

【0027】次に、アーチ部1の形成位置である橋台6
間に、アーチ部1と同じ曲率に曲げ加工した吊り鉄骨7
をアーチ部1と同形状に組立てて架設する(図1の(b)
参照)と共に、この吊り鉄骨7に設けたジャッキ8によ
ってセントル3およびセントル上にセットした型枠や補
強鉄筋5を、後述する計測制御装置9(図8参照)でセ
ントル3の水平性を保ちながら吊り上げる(図1の(c)
および(d) 参照)。
Next, the abutment 6 where the arch 1 is formed
In between, the suspended steel frame 7 bent to the same curvature as the arch portion 1
Is assembled and installed in the same shape as the arch part 1 ((b) of FIG. 1)
Together with the jack 8 provided on the hanging steel frame 7, the centre 3 and the formwork and the reinforcing bar 5 set on the centle 3 are maintained by the measurement control device 9 (see FIG. 8) described later while maintaining the levelness of the centle 3. Lift ((c) in Fig. 1)
And (d)).

【0028】次に、セントル3上にセットした型枠や補
強鉄筋5内に、吊り鉄骨7を取込むべくさらに型枠や補
強鉄筋をセットすると共に、セントル3上にセットした
型枠や補強鉄筋5と橋台6の型枠や補強鉄筋とを連結
し、吊り鉄骨7を取込んだ型枠の上部に押え型枠10を吊
り鉄骨7からの専用治具11(図4参照)によって取付け
る。
Next, the formwork and the reinforcing rebars are set in the formwork and the reinforcing bar 5 set on the center 3 so that the hanging steel frame 7 can be taken in. At the same time, the formwork and the reinforcing bar set on the center 3 are set. 5 and the frame of the abutment 6 and the reinforcing steel bars are connected to each other, and the pressing frame 10 is attached to the upper part of the frame in which the hanging steel frame 7 is incorporated by the special jig 11 (see FIG. 4) from the hanging steel frame 7.

【0029】その後、計測制御装置9で計測を行いなが
ら、吊り鉄骨7を取込んだ型枠内にコンクリートを打設
し所定の期間養生する(図1の(e) 参照)と共に、養生
後、セントル3および型枠をジャッキ8により作業床4
まで吊り下げて(図1の(f)参照)セントル3および型
枠を解体することにより、吊り鉄骨7を主要補強部材と
したSRC構造のアーチ部1が形成される。
After that, while performing measurement by the measurement control device 9, concrete is placed in the form frame in which the suspended steel frame 7 is incorporated and cured for a predetermined period (see (e) in FIG. 1), and after curing, Work floor 4 with the center 3 and the formwork jack 8
By hanging down (see (f) of FIG. 1) and disassembling the center 3 and the form, the arch portion 1 of the SRC structure having the suspended steel frame 7 as a main reinforcing member is formed.

【0030】なお、吊り鉄骨7をアーチ部1の形成位置
よりも上方位置に架設して(図示せず)、アーチ部1を
RC構造とすることもできる。この時は、吊り鉄骨7の
撤去工程が追加されることとなる。
The hanging steel frame 7 may be installed above the position where the arch portion 1 is formed (not shown) so that the arch portion 1 has an RC structure. At this time, a process of removing the suspended steel frame 7 will be added.

【0031】そして、この実施例での支保工は、セント
ル構造とし、工場で製作した各部材を施工現場でセント
ル1として組立てる。また、このセントル1上部の橋台
6間に曲げ加工した吊り鉄骨7を架設すると共に、これ
を反力台として吊り鋼材12(図1の(c) 参照)をセント
ル1に取付ける。この吊り鋼材12を介して、プレハブ部
材(型枠や補強鉄筋)5をセットしたセントル3を、ジ
ャッキ8(油圧ジャッキ)で吊り上げてアーチ部1の施
工位置直下にセットすることで、高所作業の低減を図
る。
Then, the supporting work in this embodiment has a center structure, and each member manufactured in the factory is assembled as a center 1 at the construction site. In addition, a bending steel frame 7 is erected between the abutments 6 on the upper part of the center 1, and a steel hanging material 12 (see FIG. 1 (c)) is attached to the center 1 as a reaction base. Through this hanging steel material 12, a prefabricated member (formwork or reinforcing rebar) 5 is set, a centle 3 is lifted by a jack 8 (hydraulic jack) and set just under the construction position of the arch portion 1, thereby performing work at high places. To reduce

【0032】なお、セントル1(図2参照)は、上部の
複数ピン連結してなるセントル梁3aと下部のセントル組
立て桁3bとをセントル支柱3cおよび筋違い3dでトラス状
に連結してなっている。また、図2の(c) に示すよう
に、セントル支柱1cには曲率半径調整装置13が、筋違い
3dには筋違い伸縮装置14がそれぞれ設けられている。
In the center 1 (see FIG. 2), a center beam 3a formed by connecting a plurality of pins at the upper portion and a lower assembly beam 3b at the lower portion are connected in a truss shape by a center column 3c and braces 3d. . In addition, as shown in FIG. 2 (c), the radius of curvature adjusting device 13 is attached to the center strut 1c.
Stranding elastic devices 14 are respectively provided in 3d.

【0033】そして、このセントル3は、複数ピン連結
してなるセントル梁3aと曲率半径調整装置13と筋違い伸
縮装置14とにより、略アーチ状となっているセントル梁
3aの曲率半径を変更できる構造として、他工事への転用
ができるようになっている。
The center 3 has a substantially arcuate shape by means of a center beam 3a formed by connecting a plurality of pins, a radius-of-curvature adjusting device 13 and a striation expansion / contraction device 14.
As a structure that can change the radius of curvature of 3a, it can be diverted to other construction.

【0034】このアーチ部の曲率半径変更に対応できる
構造とし、転活用できるようにしたことにより、建設コ
ストを削減することができる。
The construction cost can be reduced by adopting a structure which can cope with the change of the radius of curvature of the arch portion and can be reused.

【0035】なお、図3の(a) および(b) に、筋違い伸
縮装置14の別態様を示す。この態様では、ネジ鉄筋14a
を一方側のみとし、他方側の端部をリング加工して一方
側のフック14bへ掛けるようにしている。
3 (a) and 3 (b) show another embodiment of the striation expansion / contraction device 14. As shown in FIG. In this mode, the screw rebar 14a
Is only on one side, and the end portion on the other side is subjected to ring processing so as to be hooked on the hook 14b on one side.

【0036】この実施例でのセントル3への型枠の取付
けは、セントル3の組立て後の、ジャッキ8で吊り上げ
る前に、作業床4上で行う。また、押え型枠10は、セン
トル3と型枠および補強鉄筋5とを一緒に吊り上げ、補
強鉄筋5に上筋を組立て後、セントル3上に架設した吊
り鉄骨7からの専用治具11(図4参照)により補強鉄筋
5へ取付ける。さらに、型枠の解体は、ジャッキ8によ
りセントル3と伴に吊り下げて、作業床4上で行う(図
1の(f) 参照)。
The attachment of the formwork to the center 3 in this embodiment is performed on the work floor 4 after the center 3 is assembled and before being lifted by the jack 8. Further, the presser frame 10 is constructed by hoisting the center 3 and the formwork and the reinforcing bar 5 together, and after assembling the upper bar to the reinforcing bar 5, the special jig 11 from the hanging steel frame 7 erected on the center 3 (Fig. (Refer to 4) to attach to the reinforcing bar 5. Further, the dismantling of the formwork is carried out on the work floor 4 by suspending it together with the center 3 by the jack 8 (see (f) in FIG. 1).

【0037】なお、専用治具11は(図4の(a) および
(b) 参照)、吊り鉄骨7間に架設される溝型鋼の型枠固
定桁11aと、この型枠固定桁11aに設けられる、フォー
ムタイ,連結具,両セパ等の型枠固定器具11bとからな
っている。この図4での符号15は角型鋼管で、符号16は
桟木である。
The dedicated jig 11 (see (a) and
(See (b)), a grooved steel form frame fixing girder 11a installed between the suspension steel frames 7, and a form fixing device 11b such as a foam tie, a connecting tool, and both separators provided on the form frame fixing girder 11a. It consists of In FIG. 4, reference numeral 15 is a square steel pipe, and reference numeral 16 is a crosspiece.

【0038】この実施例でのコンクリート打設時におけ
るコンクリート表面のアバタ対策は(図5参照)、排水
孔17aを穿設した中空のプラスチック面木17(図5の
(c) 参照)を、押え型枠10のせき板10aに複数取付ける
(図5の(c) 参照)。この各面木17の配置は橋軸方向へ
延びる状態とし、各面木17の間隔はアーチ部1の耐力低
下を招かない大きさのピッチとする。そして、この各面
木17から、コンクリートの余剰水を排出して、コンクリ
ート表面のアバタを減少させる。
In this embodiment, as a countermeasure for avatars on the concrete surface at the time of placing concrete (see FIG. 5), a hollow plastic board 17 (see FIG. 5) having drain holes 17a is formed.
(see (c)) are attached to the weir plate 10a of the presser mold 10 (see (c) of FIG. 5). The arrangement of the face boards 17 is in a state of extending in the bridge axis direction, and the distance between the face boards 17 is set to a pitch that does not reduce the yield strength of the arch portion 1. Then, the surplus water of concrete is discharged from each of the face boards 17 to reduce avatars on the concrete surface.

【0039】この実施例での補強鉄筋5の組立ては、セ
ントル3にアーチ部1用の下型枠を取付けた後、図6に
示すように、台座上(図6の(a) および(b) 参照)での
現場施工で各ユニット毎(図6の(c) 参照)にブレハブ
化して、クレーン等でセントル3上へ吊り上げて組立て
る。
In order to assemble the reinforcing bar 5 in this embodiment, after attaching the lower formwork for the arch portion 1 to the center 3, as shown in FIG. 6, on the pedestal ((a) and (b in FIG. 6). (See)) for each unit (see (c) in Fig. 6) to make a Brehab, and hang it up on the Centle 3 with a crane to assemble.

【0040】この組立ては、型枠(せき板)上に予めス
ペーサ18(図7参照)を取付けておき、これにプレハブ
化した補強鉄筋5(図6参照)をクレーンでセットし、
スペーサ18を介して補強鉄筋5をセントル3に固定する
ことで行われる。そして、セントル3と型枠および補強
鉄筋5とを一体としてジャッキ8で吊り上げて、所定の
位置にセットする。なお、このスペーサ18は、図7の
(a) および(b) に示すように、所定間隔を設けてフォー
ムタイで固定したPコン18aと、この両Pコン18a間
に、丸鋼を曲げ加工して架設した、スペーサ本体18bと
からなっている。
In this assembly, a spacer 18 (see FIG. 7) is attached in advance on a form (a weir board), and the prefabricated reinforcing bar 5 (see FIG. 6) is set by a crane,
This is performed by fixing the reinforcing reinforcing bar 5 to the center 3 via the spacer 18. Then, the center 3 and the form and reinforcing bar 5 are integrally lifted by a jack 8 and set at a predetermined position. The spacer 18 is shown in FIG.
As shown in (a) and (b), the P-con 18a is fixed with a foam tie at a predetermined interval, and the spacer body 18b is installed by bending round steel between the P-cons 18a. Has become.

【0041】この実施例での計測制御装置9による計測
管理は、セントル3の吊り上げ時の反力となる吊り鉄骨
7の変位や応力、およびセントルの吊り上げ時の水平性
を確保するために、センサー(図示せず)を吊り鉄骨7
とセントル3とに取付け、複数台のジャッキ8の制御を
行うものである。
The measurement control by the measurement control device 9 in this embodiment is performed by a sensor in order to secure the displacement and stress of the hanging steel frame 7 which is a reaction force when the centle 3 is lifted and the levelness when the centle is lifted. Hanging (not shown) steel frame 7
And a plurality of jacks 8 are controlled by attaching the jacks 8 to the center 3.

【0042】なお、セントル3反力用の吊り鉄骨7は、
コンクリート打設時のセントル3を吊り下げる主要部材
として利用する他に、アーチ部1内に埋め込まれてアー
チ部1をSCR構造とするものである。そのため、吊り
鉄骨7の変位や応力の計測を行い、安全性の確認を行い
ながら、アーチ部1形成用のコンクリートを打設する必
要がある。
The hanging steel frame 7 for the reaction force of the center 3 is
In addition to being used as a main member for suspending the center 3 at the time of pouring concrete, it is embedded in the arch portion 1 to have the arch portion 1 as an SCR structure. Therefore, it is necessary to measure the displacement and stress of the suspended steel frame 7 and to check the safety while pouring concrete for forming the arch portion 1.

【0043】ここでの計測制御装置9(図8参照)は、
セントル3とこのセントル吊り下げ用の吊り鉄骨7とに
変位センサー(変位計,歪計)や荷重センサー(荷重
計)等のセンサ部を取付け、このセンサー部からアナロ
グ信号を取出し、A/D変換器を介してコンピュータ
(パソコン)に取り込む。
The measurement control device 9 (see FIG. 8) here is
A sensor unit such as a displacement sensor (displacement meter, strain gauge) or a load sensor (load meter) is attached to the center 3 and the hanging steel frame 7 for hanging the center, and an analog signal is extracted from this sensor unit and A / D converted. It is taken in to the computer (personal computer) through the device.

【0044】そして、セントル3の水平性を保つため
に、変位センサー位置での偏差を計算すると共に、設定
した許容差以内になるように、セントル3を支持してい
る複数台のジャッキ8における電磁弁(図示せず)の開
度を、ソフトウェア(図9,図10および図11参照)によ
り制御操作し、セントル3の吊り上げおよび吊り下げ作
業の安全性を確保する。
Then, in order to maintain the horizontality of the center 3, the deviation at the displacement sensor position is calculated, and the electromagnetic force in the plurality of jacks 8 supporting the center 3 is kept within the set tolerance. The opening degree of the valve (not shown) is controlled by software (see FIGS. 9, 10 and 11) to secure the safety of the lifting and hanging operations of the center 3.

【0045】なお、アーチ部1のコンクリート打設時に
おいても、この計測制御装置9で吊り鉄骨(支保工)7
の変位計測を実施し、理論値との比較を行い、設計の妥
当性を検証する。また、図9,図10および図11の計測,
制御フロー図に示したソフトウェアでは、ジャッキ8に
おける電磁弁の開度を、全開(0%), 半開(50%),
全閉(100%) の三段階で処理する。ここでの図9,図10
のソフトウェアは図9から図10へと流れ、図11のソフト
ウェアは各開度での制御処理を示す。
Even when concrete is poured into the arch portion 1, the suspended steel frame (supporting work) 7 is supported by the measurement control device 9.
Displacement is measured and compared with the theoretical value to verify the validity of the design. In addition, the measurement of FIG. 9, FIG. 10 and FIG.
In the software shown in the control flow chart, the opening of the solenoid valve in the jack 8 can be set to fully open (0%), half open (50%),
It is processed in three stages of fully closed (100%). 9 and 10 here
9 flows from FIG. 9 to FIG. 10, and the software of FIG. 11 shows the control processing at each opening.

【0046】このような本発明の架設工法により、アー
チ橋の橋床版2を支持する主要構造であるアーチ部1の
架設施工を、図面に基づき工程順に説明すると、先ず、
図1の(a) に示すように、架設ヤードの造成やアーチ部
1施工位置の鉛直投影面への作業床4の設置等を行うと
共に、この作業床4上でセントル3組立てる。なお、セ
ントル3は、転活用を考慮した曲率半径対応型とする
(図2参照)。
The construction of the arch portion 1 which is the main structure for supporting the deck slab 2 of the arch bridge by the construction method of the present invention will be described in the order of steps with reference to the drawings.
As shown in FIG. 1 (a), the construction of the construction yard and the installation of the work floor 4 on the vertical projection plane of the arch 1 construction position are performed, and the center 3 is assembled on the work floor 4. In addition, the center 3 is a curvature radius compatible type in consideration of reutilization (see FIG. 2).

【0047】次に、アーチ部1形成用の下型枠をセント
ル上に組立てると共に、スペーサ18をせき板19に固定す
る(図7参照)。そして、このスペーサ18上にプレハブ
化した補強鉄筋5(図6の(c) 参照)をクレーンで搬入
し据え付け、プレハブ鉄筋を連結し固定する。なお、補
強鉄筋5は、最寄りの仮設ヤードで予めプレハブ化を行
っておく(図6参照)。
Next, the lower frame for forming the arch portion 1 is assembled on the center and the spacer 18 is fixed to the dam 19 (see FIG. 7). Then, the prefabricated reinforcing steel bars 5 (see FIG. 6 (c)) are carried onto the spacers 18 by a crane and installed, and the prefabricated steel bars are connected and fixed. The reinforcing bar 5 is prefabricated in advance at the nearest temporary yard (see FIG. 6).

【0048】次に、曲げ加工したセントル吊り上げ用の
吊り鉄骨7をセントル3上に架設する(図1の(b) 参
照)と共に、ジャッキ8をセントル3上の吊り鉄骨7に
セットする(図1の(c) 参照)。また、セントル吊り上
げ用の吊り鋼材12を取付ける((図1の(c) 参照)。
Next, the bent suspension steel frame 7 for lifting the center is erected on the center 3 (see FIG. 1B), and the jack 8 is set on the frame 7 on the center 3 (FIG. 1). (See (c)). Also, attach the hanging steel material 12 for lifting the center (see (c) of Fig. 1).

【0049】次に、計測制御装置9およびジャッキ8に
より、型枠および補強鉄筋5をセットしたセントル3
を、その水平性を保ちながら所定の位置までジャッキア
ップする(図1の(d) 参照)。
Next, the measurement control unit 9 and the jack 8 are used to set the form 3 and the reinforcing bar 5 in the center 3.
Jack up to a predetermined position while maintaining its horizontality (see (d) in Fig. 1).

【0050】次に、型枠および補強鉄筋5の上部にアー
チ部1の上鉄筋を組立てた後(図6の(d) 参照)、この
型枠および補強鉄筋5に橋台6の鉄筋や型枠を連結す
る。また、面木17を取付けた傾斜部の押え型枠10を専用
治具11で取付ける。この際、コンクリート投入窓や点検
窓(図示せず)を数箇所設けておく(図1の(d) および
図5参照)。
Next, after assembling the upper rebar of the arch portion 1 on the upper part of the formwork and the reinforcing bar 5 (see FIG. 6 (d)), the reinforcing bar 5 and the reinforcing bar of the abutment 6 are attached to the formwork and the reinforcing bar 5. To connect. In addition, the presser frame 10 of the inclined portion to which the face plate 17 is attached is attached by the dedicated jig 11. At this time, concrete injection windows and inspection windows (not shown) are provided at several places (see (d) of FIG. 1 and FIG. 5).

【0051】次に、計測制御装置9によって計測を行い
ながらコンクリートを打設し(図1の(e) 参照)、所定
の期間養生する。この時に、吊り鉄骨7はアーチ部1の
中に埋め込まれ、アーチ部1をSRC構造として形成す
る。その後、ジャッキ8を作業床4までダウンして型
枠,セントル3を解体する。このことにより、アーチ橋
の橋床版2を支持する主要構造であるアーチ部1の架設
作業が完了する。
Next, the concrete is poured while the measurement is performed by the measurement control device 9 (see (e) in FIG. 1) and cured for a predetermined period. At this time, the suspended steel frame 7 is embedded in the arch portion 1 to form the arch portion 1 as an SRC structure. After that, the jack 8 is lowered to the work floor 4 and the formwork and the center 3 are disassembled. This completes the work of constructing the arch portion 1 which is the main structure for supporting the bridge deck 2 of the arch bridge.

【0052】なお、吊り鉄骨7は、その架設位置を、ア
ーチ部1の架設位置をかわした上部位置とすることがで
きる。このようにすることにより、アーチ部1架設位置
(高所))でのアーチ部1の上鉄筋組立て作業を割愛す
ることができる。この場合のプレハブ化する補強鉄筋5
は、最初から図6の(d) に示した状態とする。そして、
吊り鉄骨7の撤去工程が追加され、アーチ部1はRC構
造となる。
The suspended steel frame 7 can be installed at a position above the arched position of the arch portion 1. By doing so, it is possible to omit the work of assembling the upper reinforcing bar of the arch portion 1 at the installation position (high place) of the arch portion 1. Prefabricated reinforcing bar 5 in this case
Shows the state shown in FIG. 6 (d) from the beginning. And
A process for removing the suspended steel frame 7 is added, and the arch portion 1 has an RC structure.

【0053】[0053]

【発明の効果】この発明の架設工法によれば、アーチ橋
の橋床版を支持する主要構造であるアーチ部の架設作業
に際して、アーチ部形成用の型枠および補強鉄筋とこの
型枠,補強鉄筋支持用のセントルとの組立てを、アーチ
部形成位置の下方に設置した作業床上で行うので、高所
作業を減少することができ、架設作業における安全性の
向上と工程の短縮とを図ることができる。
According to the erection method of the present invention, during the erection work of the arch portion, which is the main structure for supporting the deck slab of the arch bridge, the form and reinforcing rebar for forming the arch and the form and reinforcement Assembling with the reinforcing bar support center is done on the work floor installed below the arch formation position, which can reduce work in high places, improve safety in erection work and shorten the process. You can

【0054】この高所作業を減少できることは、高所に
おけるアーチ傾斜部の施工機会を減らすことができるこ
ととなり、建設災害の内で発生率の高い墜落や転落事故
を減少させることができる。しかも、計測制御装置を導
入することにより、安全性を確保する等のリアルタイム
な施工管理を可能とすることができる。
Reducing this work at high places can reduce the chances of constructing the sloped portion of the arch at high places, and can reduce the number of crashes and falls that occur frequently among construction disasters. Moreover, the introduction of the measurement control device enables real-time construction management such as ensuring safety.

【0055】また、この発明の架設工法によれば、補強
鉄筋のプレハブ化や、押え型枠などの型枠を取付ける専
用治具の使用等により、補強鉄筋や型枠の組立て精度を
向上させることができ、アーチ部の耐久性を増すことが
できる。
Further, according to the construction method of the present invention, the assembling accuracy of the reinforcing bar and the form can be improved by prefabricating the reinforcing bar and using a dedicated jig for attaching the form such as a pressing form. The durability of the arch portion can be increased.

【0056】さらに、この発明の架設工法によれば、先
行して吊り鉄骨を架設してアーチ部を形成しているの
で、アーチ部架設時の応力は吊り鉄骨によって橋台へ確
実に伝達され、アーチ部閉合までの作業の安定性を増す
ことができる。
Further, according to the erection method of the present invention, since the suspension iron frame is erected in advance to form the arch portion, the stress at the time of erection of the arch portion is surely transmitted to the abutment by the suspension steel frame, It is possible to increase the stability of work until the parts are closed.

【0057】そして、このように安全性の確保と施工効
率の向上とを図ることのできる、本発明の架設工法によ
れば、アーチ部の施工精度とアーチ部形成用のコンクリ
ートの耐久性能を改善することができる。
According to the erection method of the present invention capable of ensuring the safety and improving the construction efficiency as described above, the construction accuracy of the arch portion and the durability performance of the concrete for forming the arch portion are improved. can do.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明のコンクリートアーチの架設工法によ
って実施する、アーチ橋主構造であるアーチ部の架設工
程を示し、(a) は作業床,セントル,型枠および補強鉄
筋の組立て状態を示す概略図で、(b) は吊り鉄骨の組立
て状態を示す概略図で、(c) はジャッキおよび吊り鋼材
でのセントルの吊り上げ状態を示す概略図で、(d) は吊
り上げたセントル上の型枠および補強鉄筋にさらに型枠
および補強鉄筋をセットした状態を示す概略図で、(e)
はセントル上の型枠および補強鉄筋内へのコンクリート
の打設状態を示す概略図で、(f) は完成したアーチ部か
らセントルを吊り下げた状態を示す概略図である。
FIG. 1 shows an erection process of an arch portion which is a main structure of an arch bridge, which is carried out by a concrete arch erection method of the present invention, and (a) is a schematic view showing an assembled state of a work floor, a center, a formwork and a reinforcing bar. In the figure, (b) is a schematic diagram showing the assembled state of the suspended steel frame, (c) is a schematic diagram showing the suspended state of the centle with jacks and suspended steel, and (d) is the formwork on the suspended centle and A schematic view showing a state where the formwork and the reinforcing bar are further set on the reinforcing bar, (e)
[Fig. 3] is a schematic view showing a state where concrete is placed in the formwork and reinforcing bars on the center, and (f) is a schematic view showing a state where the center is suspended from the completed arch portion.

【図2】(a) はこの発明のコンクリートアーチの架設工
法で使用するセントルを示す概略図で、(b) は(a) のG
−G線断面図で、(c) は(a) のA部拡大図で、(d) は
(c) のB−B線矢視図である。
FIG. 2 (a) is a schematic view showing a center used in the concrete arch erection method of the present invention, and (b) is a G of (a).
-G line sectional view, (c) is an enlarged view of part A of (a), (d) is
It is a BB line arrow line view of (c).

【図3】(a) はセントルにおける筋違いでの伸縮装置の
別態様を示す部分破断概略図で、(b) は(a) のC−C線
矢視図である。
FIG. 3 (a) is a partially cutaway schematic view showing another embodiment of a stretching device for bracing in a center, and FIG. 3 (b) is a view taken along line CC of FIG. 3 (a).

【図4】(a) はセントル上に設けた上下型枠を支持する
専用治具を示す概略図で、(b)は(a) のD部拡大図であ
る。
4A is a schematic view showing a dedicated jig for supporting the upper and lower molds provided on the center, and FIG. 4B is an enlarged view of a portion D of FIG. 4A.

【図5】(a) はアバタ対策として設けられるプラスチッ
ク面木の取付け状態を示す概略図で、(b) は(a) のE−
E線断面図で、(c) はプラスチック面木を示す概略斜視
図である。
FIG. 5 (a) is a schematic view showing a mounting state of a plastic face plate provided as a countermeasure for avatars, and FIG. 5 (b) is an E-of FIG.
It is a sectional view taken on the line E, and (c) is a schematic perspective view showing a plastic surface.

【図6】(a) および(b) は補強鉄筋のプレハブ化方法を
示す概略斜視図で、(c) はプレハブ化した補強鉄筋の最
初の配筋状態を示す概略図で、(d) はプレハブ化した補
強鉄筋の最終段階の配筋状態を示す概略図でる。
6 (a) and (b) are schematic perspective views showing a method of prefabricating a reinforcing bar, (c) is a schematic diagram showing a first state of prefabricated reinforcing bar, and (d) is a schematic view. It is a schematic diagram showing the last-stage bar arrangement state of the prefabricated reinforcing bar.

【図7】(a) は型枠内に固定した鉄筋支持用のスペーサ
を示す概略図で、(b) は(a) のF−F線断面図である。
7A is a schematic view showing a spacer for supporting a reinforcing bar fixed in a mold, and FIG. 7B is a sectional view taken along line FF of FIG. 7A.

【図8】計測制御装置を示すブロック図である。FIG. 8 is a block diagram showing a measurement control device.

【図9】計測制御装置における計測,制御のソフトウェ
アのフロー図である。
FIG. 9 is a flowchart of measurement and control software in the measurement control device.

【図10】計測制御装置における計測,制御のソフトウ
ェアのフロー図である。
FIG. 10 is a flow chart of measurement and control software in the measurement control device.

【図11】計測制御装置における制御のソフトウェアの
フロー図である。
FIG. 11 is a flowchart of control software in the measurement control device.

【図12】従来のコンクリートアーチの架設工法を示す
工程図である。
FIG. 12 is a process diagram showing a conventional concrete arch construction method.

【図13】従来のコンクリートアーチの架設工法を示す
工程図である。
FIG. 13 is a process diagram showing a conventional method of constructing a concrete arch.

【図14】従来のコンクリートアーチの架設工法を示す
概略図である。
FIG. 14 is a schematic diagram showing a conventional concrete arch construction method.

【図15】従来のコンクリートアーチの架設工法を示す
工程図である。
FIG. 15 is a process diagram showing a conventional concrete arch construction method.

【符号の説明】[Explanation of symbols]

1…アーチ部、2…橋床版、3…セントル、3a…セント
ル梁、3b…セントル組立て桁、3c…セントル支柱、3d…
筋違い、4…作業床、5…補強鉄筋、6…橋台、7…吊
り鉄骨、8…ジャッキ、9…計測制御装置、10…押え型
枠、10a…せき板、11…専用治具、11a…型枠固定桁、
11b…型枠固定器具、12…吊り鋼材、13…曲率半径調整
装置、14…筋違い伸縮装置、14a…ネジ鉄筋、14b…フ
ック、15…角型鋼管、16…桟木、17…面木、17a…排水
孔、18…スペーサ、18a…Pコン、18b…スペーサ本
体。
1 ... Arch part, 2 ... Bridge deck, 3 ... Centle, 3a ... Centle beam, 3b ... Centle assembly girder, 3c ... Centle column, 3d ...
Streaks 4 ... Work floor, 5 ... Reinforcing bar, 6 ... Abutment, 7 ... Suspended steel frame, 8 ... Jack, 9 ... Measurement control device, 10 ... Pressing form, 10a ... Dam, 11 ... Special jig, 11a ... Formwork fixed girder,
11b ... Form frame fixing device, 12 ... Suspended steel material, 13 ... Curve radius adjusting device, 14 ... Stranding expansion / contraction device, 14a ... Screw rebar, 14b ... Hook, 15 ... Square-shaped steel pipe, 16 ... Pieces, 17 ... Face, 17a … Drainage hole, 18… Spacer, 18a… Pcon, 18b… Spacer body.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 中小規模の支間を有するコンクリートア
ーチ橋の架設時において、前記アーチ橋の橋床版を支持
する主要構造として設けられるアーチ部の架設工法であ
り、 最初に、前記アーチ部形成用の型枠やアーチ内部に配設
される補強鉄筋を支持すべくアーチ部の直下に設けられ
るセントルを、アーチ部形成位置の下方であるアーチ部
形成位置の鉛直投影面に設けた作業床において組立てる
と共に、このセントル上に型枠やプレハブ化した補強鉄
筋をセットし、 次に、前記アーチ部の形成位置である橋台間に、アーチ
部と同じ曲率に曲げ加工した吊り鉄骨をアーチ部と同形
状に組立てて架設すると共に、この吊り鉄骨に設けたジ
ャッキによって前記セントルおよびセントル上にセット
した型枠や補強鉄筋を、計測制御装置でセントルの水平
性を保ちながら吊り上げ、 次に、前記セントル上にセットした型枠や補強鉄筋内
に、前記吊り鉄骨を取込むようにさらに型枠や補強鉄筋
をセットすると共に、セントル上にセットした型枠や補
強鉄筋と前記橋台の型枠や補強鉄筋とを連結し、その
後、吊り鉄骨を取込んだ型枠の上部に押え型枠を吊り鉄
骨からの専用治具によって取付け、 そして、前記計測制御装置で計測を行いながら、前記吊
り鉄骨を取込んだ型枠内にコンクリートを打設し所定の
期間養生すると共に、養生後、前記セントルおよび型枠
をジャッキにより前記作業床まで吊り下げセントルおよ
び型枠を解体することで、前記吊り鉄骨を主要補強部材
としたSRC構造の前記アーチ部が形成されることを特
徴とするコンクリートアーチの架設工法。
1. A method for constructing an arch portion, which is provided as a main structure for supporting a deck slab of the arch bridge when constructing a concrete arch bridge having small and medium-sized spans. Assemble the center that is provided directly below the arch part to support the frame and the reinforcing reinforcing bar provided inside the arch on the work floor provided on the vertical projection surface below the arch part formation position. At the same time, set the formwork and prefabricated reinforcing bars on this center, and then, between the abutments where the arches are formed, the suspended steel frame bent to the same curvature as the arches has the same shape as the arches. Assembled and erected on the suspension steel frame, and the jacks provided on the hanging steel frame are used to measure the centle and the formwork and reinforcing bars set on the centle using the measurement control device. While maintaining the property, then, in the formwork and reinforcing bar set on the Centle, while further setting the formwork and reinforcing bar to take in the hanging steel frame, the formwork set on the Center and Connect the reinforcing bar and the frame of the abutment and the reinforcing bar, and then attach the presser frame to the upper part of the frame incorporating the hanging steel frame with a dedicated jig from the hanging frame, and then use the measurement control device. While performing the measurement, while placing concrete in the form frame in which the suspended steel frame is taken in and curing for a predetermined period, after curing, suspend the centle and the form frame with a jack to the work floor. A method for constructing a concrete arch, wherein the arch portion having an SRC structure using the suspended steel frame as a main reinforcing member is formed by disassembling.
【請求項2】 吊り鉄骨をアーチ部の形成位置よりも上
方位置に架設して、アーチ部をRC構造とすると共に、
前記吊り鉄骨の撤去工程を追加してなることを特徴とす
る請求項1記載のコンクリートアーチの架設工法。
2. A suspension steel frame is installed above a position where an arch portion is formed so that the arch portion has an RC structure.
The method for constructing a concrete arch according to claim 1, wherein a step of removing the suspended steel frame is added.
JP10402894A 1994-05-18 1994-05-18 Erection method of concrete arch Withdrawn JPH07310304A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10402894A JPH07310304A (en) 1994-05-18 1994-05-18 Erection method of concrete arch

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10402894A JPH07310304A (en) 1994-05-18 1994-05-18 Erection method of concrete arch

Publications (1)

Publication Number Publication Date
JPH07310304A true JPH07310304A (en) 1995-11-28

Family

ID=14369800

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10402894A Withdrawn JPH07310304A (en) 1994-05-18 1994-05-18 Erection method of concrete arch

Country Status (1)

Country Link
JP (1) JPH07310304A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008058178A (en) * 2006-08-31 2008-03-13 Penta Ocean Construction Co Ltd Device for measuring optical deformation of long and large structure
JP2012021865A (en) * 2010-07-14 2012-02-02 Tokyo Electric Power Co Inc:The Stress measuring method and device for steel tower members by destressing
CN105350442A (en) * 2015-10-08 2016-02-24 中铁二院工程集团有限责任公司 Arching method for stiff skeleton concrete arch bridge
CN106908587A (en) * 2017-05-05 2017-06-30 山东大学 A kind of soil arching effect model test apparatus and test method
CN107328710A (en) * 2017-08-21 2017-11-07 山东大学 Soil arching effect probes into experimental rig and test method under a kind of Passive deformation pattern
CN109137747A (en) * 2018-10-22 2019-01-04 中铁大桥局集团有限公司 A kind of flexible suspension for long-span arch bridge main girder construction
CN110130200A (en) * 2019-06-04 2019-08-16 中国铁路设计集团有限公司 A kind of CFST Arch Bridge
CN111005318A (en) * 2019-12-03 2020-04-14 中交路桥华南工程有限公司 Prepressing method of curved surface support
CN113062220A (en) * 2021-02-27 2021-07-02 中交第四公路工程局有限公司 Tensioning asymmetric construction method after separation of large-span suspension-spliced arch rib suspension buckle
CN113481884A (en) * 2021-07-18 2021-10-08 陕西省建筑科学研究院有限公司 Formwork erecting method for arched concrete beam

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008058178A (en) * 2006-08-31 2008-03-13 Penta Ocean Construction Co Ltd Device for measuring optical deformation of long and large structure
JP2012021865A (en) * 2010-07-14 2012-02-02 Tokyo Electric Power Co Inc:The Stress measuring method and device for steel tower members by destressing
CN105350442A (en) * 2015-10-08 2016-02-24 中铁二院工程集团有限责任公司 Arching method for stiff skeleton concrete arch bridge
CN106908587A (en) * 2017-05-05 2017-06-30 山东大学 A kind of soil arching effect model test apparatus and test method
CN106908587B (en) * 2017-05-05 2023-07-28 山东大学 Soil arch effect model test device and test method
CN107328710B (en) * 2017-08-21 2023-07-07 山东大学 Soil arch effect exploration test device and test method in passive deformation mode
CN107328710A (en) * 2017-08-21 2017-11-07 山东大学 Soil arching effect probes into experimental rig and test method under a kind of Passive deformation pattern
CN109137747A (en) * 2018-10-22 2019-01-04 中铁大桥局集团有限公司 A kind of flexible suspension for long-span arch bridge main girder construction
CN109137747B (en) * 2018-10-22 2023-09-26 中铁大桥局集团有限公司 Elastic hanging bracket for large-span arch bridge girder construction
CN110130200A (en) * 2019-06-04 2019-08-16 中国铁路设计集团有限公司 A kind of CFST Arch Bridge
CN111005318B (en) * 2019-12-03 2022-02-11 中交路桥华南工程有限公司 Prepressing method of curved surface support
CN111005318A (en) * 2019-12-03 2020-04-14 中交路桥华南工程有限公司 Prepressing method of curved surface support
CN113062220A (en) * 2021-02-27 2021-07-02 中交第四公路工程局有限公司 Tensioning asymmetric construction method after separation of large-span suspension-spliced arch rib suspension buckle
CN113481884A (en) * 2021-07-18 2021-10-08 陕西省建筑科学研究院有限公司 Formwork erecting method for arched concrete beam

Similar Documents

Publication Publication Date Title
CN102493362B (en) Construction method for midspan closure segment of longspan continuous rigid frame bridge
CN108374319B (en) Lower-bearing type tied-arch bridge structural unit, arch bridge structure and construction method thereof
CN106192758A (en) A kind of construction method utilizing the cantilever form large-scale high pier stud of construction
CN109898821B (en) Construction method of high-altitude cantilever formwork support frame body
CN108411790A (en) A kind of adjustable installing bracket of prefabricated assembled segmentation bent cap
CN107806019A (en) Large-span suspension bridge gate Sarasota construction method
JPH07310304A (en) Erection method of concrete arch
KR101889064B1 (en) Construction method of a long span bridge main tower
CN106012849A (en) Construction method for integral binding and hoisting for linear section steel bars of cantilever beam and bridge
KR0141463B1 (en) Method of prefabricating stairway
CN208379444U (en) A kind of adjustable installing bracket of prefabricated assembled segmentation bent cap
KR102477955B1 (en) Bridge pier and the construction method using maintained concrete mold
CN102493363A (en) Quick construction method for segment No.0 of continuous beam
KR100377868B1 (en) pier construction method using Pier scaffolding
CN111005324B (en) Support-free suspension and locking construction method for assembled type segmental box girder
CN113802468A (en) Asymmetric cable-stayed bridge special-shaped concrete tower column construction process
JP2812178B2 (en) Bridge pier construction method by self-elevating formwork method
CN217579798U (en) Prefabricated bent cap high accuracy mounting structure
JP2812177B2 (en) Bridge pier construction method by slip form method
CN219604164U (en) Variable cross-section special-shaped steel tower crown mounting device
CN108797350A (en) Stiff skeleton device and its construction method inside and outside a kind of king-post
CN103321406A (en) Supporting system of high-rise building floor formworks
CN109930497B (en) Workpiece for line crossing construction of formwork suspension casting combined system and construction process
JP3171676B2 (en) Construction method of cast-in-place concrete horizontal member
CN115341472B (en) Construction method for lower cross beam of main tower of highway-railway dual-purpose river-crossing A-type cable-stayed bridge

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20010731