JP2021028764A - 杭工事管理装置、表示方法、及びプログラム - Google Patents
杭工事管理装置、表示方法、及びプログラム Download PDFInfo
- Publication number
- JP2021028764A JP2021028764A JP2019147512A JP2019147512A JP2021028764A JP 2021028764 A JP2021028764 A JP 2021028764A JP 2019147512 A JP2019147512 A JP 2019147512A JP 2019147512 A JP2019147512 A JP 2019147512A JP 2021028764 A JP2021028764 A JP 2021028764A
- Authority
- JP
- Japan
- Prior art keywords
- pile
- construction
- display
- gantry
- piles
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims description 46
- 238000010276 construction Methods 0.000 claims abstract description 79
- 238000009430 construction management Methods 0.000 claims abstract description 59
- 238000013500 data storage Methods 0.000 claims abstract description 34
- 238000009434 installation Methods 0.000 claims description 47
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims description 30
- 238000007726 management method Methods 0.000 abstract 1
- 230000010365 information processing Effects 0.000 description 15
- 238000010586 diagram Methods 0.000 description 14
- 239000004568 cement Substances 0.000 description 12
- 239000008267 milk Substances 0.000 description 12
- 210000004080 milk Anatomy 0.000 description 12
- 235000013336 milk Nutrition 0.000 description 12
- 238000007689 inspection Methods 0.000 description 8
- 238000004891 communication Methods 0.000 description 3
- 230000003247 decreasing effect Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 1
- 230000006870 function Effects 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 238000010248 power generation Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
Images
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
図1は、杭工事管理装置である情報処理装置100の概略的な構成の一例を示す図である。情報処理装置100は、例えば、コンピュータ装置である。図1に示すように、情報処理装置100は、制御部であるCPU10、ROM20、RAM30、表示部40、入力部50、及びHDD60を備えている。
まず、マップ全体について説明する。図2は、マップデータ記憶部62に記憶されるマップデータの全体の一例を示す図である。
マップは、道路R1,R2を挟んで6つのエリア(エリアA1からA6)に分けられている。このような構成されるエリアA1からA6の広さを合計すると、マップ全体でドーム球場の広さ数十個分に相当するほど、広範なエリアとなる場合もある。
図3に示すように、エリアA11は、複数の架台が配置されて構成されている。なお、説明の都合上エリアA11を例に挙げて説明するが、エリアA1の他のエリア、及び他のエリアA2からエリアA6も同様に構成される。
本実施形態では、架台の種類として、長さの異なる3つの架台M1,M2,M3を用いることとする。また、各架台には、架台を特定する架台番号が付されており、エリアA11内に設置される架台には、架台番号A1−001からA1−017の番号がそれぞれ付されている。この架台番号によりマップ内の架台の設置位置を特定することが可能になる。
架台M1は、10個(2×5)の杭で支持されるようになっており、架台M2は、18個(2×9)の杭により支持されるようになっており、架台M3は、36個(2×18)の杭により支持されるようになっている。長手方向の長さは、架台M1がL1、架台M2がL2、架台M3がL3(L1<L2<L3)である。各杭には、杭番号が付されている。架台M1には、杭番号M101からM1110の10個の異なる番号が付されており、架台M2には、杭番号M201からM218の18個の異なる番号が付されており、架台M3には、杭番号M301からM336の36個の異なる番号が付されている。杭番号と、架台番号とを組み合わせることにより、マップ上でどの位置の杭であるかを特定することが可能になる。なお、架台M1,M2,M3には、それぞれ所定数の太陽光パネルモジュールが取り付けられ、工事完成後は、大規模な太陽光発電システムが構成される。なお、架台M1,M2,M3に取り付けられる設置対象物は、太陽光パネルモジュールに限るものはない。
本実施形態では、杭を地面に打ち込む工法として、スクリュ工法と、セメントミルク工法とが用いられる。スクリュ工法は、スクリュ杭を地面に打ち込んで固定し、それを基礎として架台やモジュールを取り付けていく工法である。セメントミルク工法は、掘削したあと杭を挿入し、セメントミルクの根固め液で地盤と一体化する工法である。
工事管理データは、エリア、位置番号、架台の種類、架台設置日、架台検査日、杭位置、杭打込日、工法、および杭検査日が対応付けられている。エリアは、マップ上のエリアであり、本実施形態では、エリアA1からA6のいずれが記憶される。位置番号は、架台が設置される位置、言い換えれば架台番号が記憶される。架台の種類は、M1,M2,M3のいずれかが記憶される。架台設置日は、架台を設置した日が記憶される。架台検査日は、架台を設置後、所定期間経過後に実施される架台の設置状態の検査を行った日が記憶される。杭位置は、架台の種類に応じた杭の位置、言い換えれば杭番号が記憶される。杭打込日は、杭を打ち込んだ日(設置日)が記憶される。工法は、スクリュ(工法)かセメントミルク(工法)かが記憶される。杭検査日は、杭を打ち込んだ後、所定期間経過後に実施される杭の状態の検査を行った日が記憶される。なお、架台と、杭の検査は、1回でなくても所定期間あけて複数回行われてもよい。この場合、検査の回数に応じてフィールドを設けるようにすればよい。
図8は、工事管理状況入力画面41の一例を示す図である。当該画面41は、ユーザが入力部50に対して所定の操作をすることにより表示部40に表示される。工事管理状況入力画面41には、杭設置状況ボタン41a、架台設置状況ボタン41b、表示ボタン41cが設けられている。
図10に示すように、杭又は架台の設置が終了した箇所(ハッチング箇所)と、杭又は架台の設置が終了していな箇所(白抜きの箇所)とが表示されている。当該表示により、ユーザは、エリアA2,エリアA3の工事は完了しており、エリアA1の工事が進行中であることが視認できる。さらに、詳細に説明するため、以下ではエリア1のエリアA11を拡大して説明する。エリアA11の拡大表示は、ユーザが所定の操作を行うことにより可能になっている。例えば、ユーザは、入力部50を用いてエリアA11の範囲を指定し、全画面表示を指定する等の操作を行うことにより、エリアA11の詳細な表示を情報処理装置100にさせることができる。
表示D11は、架台が設置されている箇所を示しており、表示D12は杭(スクリュ工法)が設置されている箇所を示しており、表示D13は杭(セメントミルク工法)が打込まれている箇所を示しており、表示D14は杭も架台も未設置の状態を示している。これにより、ユーザは、エリアA11の工事の進捗状況を正確に把握することができる。
より具体的には、ユーザは、図13に示す表示例により杭の設置状況、図14に示す表示例により架台の設置状況、図11に示す表示例により杭・架台の設置状況を把握することができる。また、ユーザは、図12に示す表示例によりエラーが発生している可能性のある個所を容易に把握することができる。
第2実施形態は、杭の費用を表示するようにした点が第1実施形態と異なっている。このため、以下では当該点について詳細に説明することとする。なお、第1実施形態と同一構成には同一符号を付すこととする。
Claims (9)
- 複数の杭、及び前記複数の杭に支持される架台を設置する工事エリアを規定するマップを記憶するマップデータ記憶部と、
前記複数の杭の工事状況を記憶する工事管理データ記憶部と、
情報を表示する表示部と、
ユーザの入力操作を受付ける入力部と、
前記入力部を介してユーザの第1の入力操作を受付けたときに、前記工事管理データ記憶部に記憶される杭の工事状況を前記マップに反映させて前記表示部に表示する制御部と、
を備える杭工事管理装置。 - 前記工事管理データ記憶部は、前記架台の工事状況を記憶し、
前記制御部は、前記入力部を介してユーザの第2の入力操作を受付けたときに、前記工事管理データ記憶部に記憶される前記架台の工事状況を前記マップに反映させて前記表示部に表示する、
請求項1に記載の杭工事管理装置。 - 前記制御部は、前記入力部を介してユーザの第3の入力操作を受付けたときに、前記杭の工事状況、及び前記架台の工事状況を前記マップに反映させて前記表示部に表示する、
請求項2に記載の杭工事管理装置。 - 前記制御部は、前記杭の表示と、前記架台の表示とが重なる場合、前記架台の表示を優先して表示する、
請求項3に記載の杭工事管理装置。 - 前記制御部は、前記架台の工事状況として前記架台が設置されている旨を表示する場合、当該架台を支持する杭が正しく設置されているか否かを判定し、正しく設置されていないと判定した場合、当該架台の表示態様を正しく設置されていると判定した前記架台から変更する、
請求項3に記載の杭工事管理装置。 - 前記杭は、複数種類あり、
前記工事管理データ記憶部に記憶される杭の工事状況は、設置した杭の種類を含み、
前記制御部は、前記杭を前記表示部に表示するときに、杭の種類に応じて設定された表示態様で前記杭を表示する、
請求項1から請求項5に記載の杭工事管理装置。 - 前記杭は、前記種類に応じて設置費用が異なり、
前記制御部は、前記入力部を介してユーザの第4の入力操作を受付けたときに、設置が予定されている杭の設置費用の予定合計金額と、現在設置した杭の状況を反映させた現在予定金額とを前記表示部に表示する、
請求項5に記載の杭工事管理装置。 - 杭工事管理装置の表示方法は、
入力部を介してユーザの第1の入力操作を受付け、
前記第1の入力操作を受付けると、複数の杭、及び前記複数の杭に支持される架台を設置する工事エリアを規定するマップ、並びに、前記複数の杭の工事状況のデータを含む工事管理データに基づいて、前記杭の工事状況を前記マップに反映させて表示部に表示する、
杭工事管理装置の表示方法。 - コンピュータに、
入力部を介してユーザの第1の入力操作を受付ける処理と、
前記第1の入力操作を受付けると、複数の杭、及び前記複数の杭に支持される架台を設置する工事エリアを規定するマップ、並びに、前記複数の杭の工事状況のデータを含む工事管理データに基づいて、前記杭の工事状況を前記マップに反映させて表示部に表示する処理と、
を実現させるプログラム。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2019147512A JP7370760B2 (ja) | 2019-08-09 | 2019-08-09 | 杭工事管理装置、表示方法、及びプログラム |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2019147512A JP7370760B2 (ja) | 2019-08-09 | 2019-08-09 | 杭工事管理装置、表示方法、及びプログラム |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2021028764A true JP2021028764A (ja) | 2021-02-25 |
JP7370760B2 JP7370760B2 (ja) | 2023-10-30 |
Family
ID=74667069
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2019147512A Active JP7370760B2 (ja) | 2019-08-09 | 2019-08-09 | 杭工事管理装置、表示方法、及びプログラム |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP7370760B2 (ja) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US11788247B1 (en) | 2022-12-21 | 2023-10-17 | Built Robotics Inc. | Basket assembly operation for autonomous pile driving system |
US11822342B1 (en) | 2022-12-21 | 2023-11-21 | Built Robotics Inc. | Obstacle map for autonomous pile driving system |
US20240210946A1 (en) * | 2022-12-21 | 2024-06-27 | Built Robotics Inc. | Autonomous pile driver apparatus and method |
US12129624B2 (en) | 2023-03-08 | 2024-10-29 | Built Robotics Inc. | Pile manipulation tool for autonomous pile driver vehicle |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006283294A (ja) * | 2005-03-31 | 2006-10-19 | Geotop Corp | 杭施工管理方法及び杭施工管理シテテム |
JP2013028923A (ja) * | 2011-07-27 | 2013-02-07 | Daiwa Kiko Kk | 地盤改良機の制御装置 |
JP2014185472A (ja) * | 2013-03-25 | 2014-10-02 | Fudo Tetra Corp | 地盤改良工事及び杭基礎工事における施工管理システム |
JP2015148496A (ja) * | 2014-02-06 | 2015-08-20 | 株式会社日立パワーソリューションズ | 施工調査装置および施工調査方法 |
JP2017045163A (ja) * | 2015-08-25 | 2017-03-02 | 株式会社日立パワーソリューションズ | 土地利用支援システム、及び、土地利用支援方法 |
-
2019
- 2019-08-09 JP JP2019147512A patent/JP7370760B2/ja active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006283294A (ja) * | 2005-03-31 | 2006-10-19 | Geotop Corp | 杭施工管理方法及び杭施工管理シテテム |
JP2013028923A (ja) * | 2011-07-27 | 2013-02-07 | Daiwa Kiko Kk | 地盤改良機の制御装置 |
JP2014185472A (ja) * | 2013-03-25 | 2014-10-02 | Fudo Tetra Corp | 地盤改良工事及び杭基礎工事における施工管理システム |
JP2015148496A (ja) * | 2014-02-06 | 2015-08-20 | 株式会社日立パワーソリューションズ | 施工調査装置および施工調査方法 |
JP2017045163A (ja) * | 2015-08-25 | 2017-03-02 | 株式会社日立パワーソリューションズ | 土地利用支援システム、及び、土地利用支援方法 |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US11788247B1 (en) | 2022-12-21 | 2023-10-17 | Built Robotics Inc. | Basket assembly operation for autonomous pile driving system |
US11822342B1 (en) | 2022-12-21 | 2023-11-21 | Built Robotics Inc. | Obstacle map for autonomous pile driving system |
US20240209584A1 (en) * | 2022-12-21 | 2024-06-27 | Built Robotics Inc. | Basket assembly operation for autonomous pile driving system |
US20240210946A1 (en) * | 2022-12-21 | 2024-06-27 | Built Robotics Inc. | Autonomous pile driver apparatus and method |
US12129624B2 (en) | 2023-03-08 | 2024-10-29 | Built Robotics Inc. | Pile manipulation tool for autonomous pile driver vehicle |
Also Published As
Publication number | Publication date |
---|---|
JP7370760B2 (ja) | 2023-10-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP7370760B2 (ja) | 杭工事管理装置、表示方法、及びプログラム | |
US8041650B2 (en) | Method and system for directed documentation of construction projects | |
JP5769520B2 (ja) | 機器点検支援システム、機器点検支援方法及びプログラム | |
EP2192538A2 (en) | System for sharing video captured at jobsite | |
JP6033115B2 (ja) | 保守作業タイミング判定装置、保守作業タイミング判定システム、保守作業タイミング判定方法およびプログラム | |
WO2020054422A1 (ja) | 端末装置、作業機械システム、情報処理方法、およびサーバ装置 | |
JP4677295B2 (ja) | 現場調査報告作成支援システム | |
JP2009235696A (ja) | 建物の経年変化を調査するためのシステム、方法、及びコンピュータ・プログラム | |
JP2009193407A (ja) | 工事管理システム | |
US20150277413A1 (en) | System construction support apparatus | |
JP5812648B2 (ja) | 進捗表示装置、進捗表示方法および進捗表示プログラム | |
KR102193260B1 (ko) | 시설물 점검용 사진 정리시스템 및 이를 이용한 시설물 점검용 사진의 정리 방법 | |
JP2019028642A (ja) | 点検報告書作成システム | |
JP6796227B2 (ja) | 配管診断履歴表示装置、配管診断履歴表示方法、および配管診断履歴表示プログラム | |
JP6389120B2 (ja) | データ処理装置、データ処理方法、及び、プログラム | |
CN107451174B (zh) | 设施管理装置及设施管理方法 | |
JP6371200B2 (ja) | 情報処理装置、情報管理システム、情報管理方法 | |
JP4592673B2 (ja) | 工事計画システム | |
JP5438417B2 (ja) | 装置試験システム | |
US20190392571A1 (en) | Facility maintenance management system and facility information providing method | |
JP6823898B2 (ja) | 配管診断履歴表示装置、配管診断履歴表示方法、および配管診断履歴表示プログラム | |
JP5086555B2 (ja) | 開発管理システムおよび開発管理プログラム | |
JP2010026993A (ja) | 業務フロー管理システム、業務フロー図作成装置及び業務フロー図作成プログラム | |
JP7406740B2 (ja) | 対象の検査と報告書の作成のためのシステム | |
JP2007226833A5 (ja) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20220719 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20230628 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20230704 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20230831 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20230919 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20231018 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 7370760 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |